PATIARASE PROPERTINDO
DEVELOPER • REAL ESTATE • CONTRACTOR • SUPPLIER
GRAND AROEPALA Blok A No. 7 Telp. (0411) 497111 / 5611956
BILL OF QUANTITY
BILL OF QUANTITY
I. PEKERJAAN PERSIAPAN
1. Pekerjaan Pembongkaran
1 m3 Bongkaran Dinding Tembok Bata Merah/Beton Bertulang
6.667 Oh Pekerja @ Rp. 30,000.00 = Rp. 200,010.00
0.033 Oh Mandor @ Rp. - = Rp. -
3. Pemasangan Bouwplank
1 m' Pengukuran dan Pemasangan Bouwplank
0.012 m3 Kayu Kelas III (balok) @ Rp. 1,200,000.00 = Rp. 14,400.00
0.02 kg Paku Biasa @ Rp. 15,000.00 = Rp. 300.00
0.007 m3 Kayu Kelas III (papan) @ Rp. 1,200,000.00 = Rp. 8,400.00
0.1 Oh Tukang Kayu @ Rp. 45,000.00 = Rp. 4,500.00
0.1 Oh Pekerja @ Rp. 30,000.00 = Rp. 3,000.00
0.01 Oh Kepala Tukang @ Rp. 50,000.00 = Rp. 500.00
0.005 Oh Mandor @ Rp. 75,000.00 = Rp. 375.00
1 m3 Pemadatan Tanah
0.5 Oh Pekerja @ Rp. 50,000.00 = Rp. 25,000.00
0.05 Oh Mandor @ Rp. 75,000.00 = Rp. 3,750.00
Jadi Untuk 1 Kg Pembesian dengan Besi Polos atau Besi Ulir = Rp. 10,107.50
1 m3 Beton Tumbuk 1 : 3 : 5
218 kg Semen Portland @ Rp. 1,075.00 = Rp. 234,350.00
0.52 m3 Pasir Beton @ Rp. 45,000.00 = Rp. 23,400.00
0.87 m3 Kerikil Pecah Tersaring @ Rp. 250,000.00 = Rp. 217,500.00
0.9 kg Semen Warna @ Rp. 2,000.00 = Rp. 1,800.00
1.65 Oh Pekerja @ Rp. 50,000.00 = Rp. 82,500.00
0.25 Oh Tukang Batu @ Rp. 75,000.00 = Rp. 18,750.00
0.025 Oh Kepala Tukang @ Rp. 75,000.00 = Rp. 1,875.00
0.08 Oh Mandor @ Rp. 75,000.00 = Rp. 6,000.00
V. PEKERJAAN DINDING
1. Pasangan Batu Bata Trassram 1 : 2
1 m2 Pasangan Bata Merah Tebal 1/2 Bata 1 Pc : 2 Ps
110 bh Batu Merah 5x11x22 @ Rp. 350.00 = Rp. 38,500.00
18.95 Kg Semen Portland @ Rp. 1,075.00 = Rp. 20,371.25
0.038 m³ Pasir Pasangan @ Rp. 115,000.00 = Rp. 4,370.00
0.1 Oh Tukang Batu @ Rp. 75,000.00 = Rp. 7,500.00
0.01 Oh Kepala Tukang @ Rp. 75,000.00 = Rp. 750.00
0.32 Oh Pekerja @ Rp. 50,000.00 = Rp. 16,000.00
0.015 Oh Mandor @ Rp. 75,000.00 = Rp. 1,125.00
Jadi Untuk 1 m2 Pasangan Bata Merah Tebal 1/2 Bata 1 Pc : 2 Ps = Rp. 88,616.25
2. Pasangan Batu Bata Biasa 1 : 4
1 m2 Pasangan Bata Merah Tebal 1/2 Bata 1 Pc : 4 Ps
106 bh Batu Merah 5x11x22 @ Rp. 350.00 = Rp. 37,100.00
9.7 Kg Semen Portland @ Rp. 1,075.00 = Rp. 10,406.00
0.045 m³ Pasir Pasangan @ Rp. 115,000.00 = Rp. 5,175.00
0.1 Oh Tukang Batu @ Rp. 75,000.00 = Rp. 7,500.00
0.01 Oh Kepala Tukang @ Rp. 75,000.00 = Rp. 750.00
0.30 Oh Pekerja @ Rp. 50,000.00 = Rp. 15,000.00
0.015 Oh Mandor @ Rp. 75,000.00 = Rp. 1,125.00
Jadi Untuk 1 m2 Pasangan Bata Merah Tebal 1/2 Bata 1 Pc : 4 Ps = Rp. 77,056.00
75,181.00
3. Pekerjaan Plesteran Trassram 1 : 2
1 m2 Plesteran 1 Pc : 2 Ps Tebal 15 mm
7.78 Kg Semen Portland @ Rp. 1,075.00 = Rp. 8,359.20
0.23 m3 Pasir Pasangan @ Rp. 115,000.00 = Rp. 26,450.00
0.15 Oh Tukang Batu @ Rp. 75,000.00 = Rp. 11,250.00
0.015 Oh Kepala Tukang @ Rp. 75,000.00 = Rp. 1,125.00
0.2 Oh Pekerja @ Rp. 50,000.00 = Rp. 10,000.00
0.01 Oh Mandor @ Rp. 75,000.00 = Rp. 750.00
4. Pekerjaan Plesteran
1 m2 Plesteran 1 Pc : 4 Ps Tebal 15 mm
5.2 Kg Semen Portland @ Rp. 1,075.00 = Rp. 5,572.80
0.026 m3 Pasir Pasangan @ Rp. 115,000.00 = Rp. 2,990.00
0.15 Oh Tukang Batu @ Rp. 75,000.00 = Rp. 11,250.00
0.015 Oh Kepala Tukang @ Rp. 75,000.00 = Rp. 1,125.00
0.3 Oh Pekerja @ Rp. 50,000.00 = Rp. 15,000.00
0.01 Oh Mandor @ Rp. 75,000.00 = Rp. 750.00
Jadi Untuk 1 m2 Pasang Jalusi Mati Kusen Kayu Kelas I = Rp. 464,125.00
Jadi Untuk 1 m2 Pasang Kaso + Reng Genteng Kayu Kelas I = Rp. 48,075.00
Jadi Untuk 1 m' Pasang Listplang ukuran (3 x 20) cm Kelas I = Rp. 55,025.00
X. PEKERJAAN M & E
1 Titik Mengerjakan Lampu Pijar
1.000 bh fitting @ Rp. 12,000.00 = Rp. 12,000.00
1.000 bh Bohlam Pijar 40 Watt @ Rp. 3,000.00 = Rp. 3,000.00
0.600 roll Kabel NYM 3 x 2,5 mm @ Rp. 450,000.00 = Rp. 270,000.00
0.250 dos Sadel Plastik @ Rp. 6,000.00 = Rp. 1,500.00
0.075 Oh Pekerja @ Rp. 50,000.00 = Rp. 3,750.00
0.850 Oh Tukang Listrik @ Rp. 35,000.00 = Rp. 29,750.00
Jadi Untuk 1 Titik Mengerjakan Stop Kontak dan Saklar = Rp. 15,105.00
XI. PEKERJAAN PENGECATAN
1 m2 Pengecatan Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) dengan Cat Mutu Baik
0.1 Kg Plamur @ Rp. 4,000.00 = Rp. 400.00
0.1 Kg Cat Dasar @ Rp. 15,000.00 = Rp. 1,500.00
0.26 Kg Cat Penutup @ Rp. 16,000.00 = Rp. 4,160.00
0.02 Oh Pekerja @ Rp. 50,000.00 = Rp. 1,000.00
0.063 Oh Tukang Cat @ Rp. 45,000.00 = Rp. 2,835.00
0.0063 Oh Kepala Tukang @ Rp. 75,000.00 = Rp. 472.50
0.0025 Oh Mandor @ Rp. 75,000.00 = Rp. 187.50
1 m2 Pengecatan Bidang Kayu Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) dengan Cat Mutu Baik
0.2 Kg Cat Meni @ Rp. 15,000.00 = Rp. 3,000.00
0.15 Kg Plamur @ Rp. 4,000.00 = Rp. 600.00
0.17 Kg Meni @ Rp. 15,000.00 = Rp. 2,550.00
0.26 Kg Cat Penutup @ Rp. 60,000.00 = Rp. 15,600.00
0.07 Oh Pekerja @ Rp. 50,000.00 = Rp. 3,500.00
0.009 Oh Tukang Cat @ Rp. 45,000.00 = Rp. 405.00
0.006 Oh Kepala Tukang @ Rp. 75,000.00 = Rp. 450.00
0.0025 Oh Mandor @ Rp. 75,000.00 = Rp. 187.50
Jadi Untuk 1 m' Memasang Instalasi Air Kotor 2" = Rp. 61,877.50
Jadi Untuk 1 m' Memasang Instalasi Air Kotor 3" = Rp. 88,945.00
Jadi Untuk 1 m' Memasang Instalasi Air Hujan 2" = Rp. 61,877.50
TERBILANG :
MENGETAHUI :
TERBILANG :
MENGETAHUI :
TERBILANG :
MENGETAHUI :
TERBILANG :
DELAPAN PULUH EMPAT JUTA LIMA RATUS TUJUH BELAS RIBU RUPIAH
MENGETAHUI :
TERBILANG :
SERATUS SEPULUH JUTA DELAPAN RATUS EMPAT PULUH TUJUH RIBU RUPIAH
MENGETAHUI :
TERBILANG :
SERATUS TIGA PULUH TUJUH JUTA SERATUS TUJUH PULUH ENAM RIBU RUPIAH
MENGETAHUI :
I. UPAH
1 Pekerja Oh Rp 50,000
2 Tukang batu Oh Rp 75,000
3 Tukang kayu Oh Rp 75,000
4 Tukang besi Oh Rp 75,000
5 Tukang cat Oh Rp 75,000
6 Tukang pipa Oh Rp 75,000
7 Kepala tukang Oh Rp 75,000
64
II BAHAN
Material Kayu
1 Balok ( Kayu Kelas III ) M³ Rp 1,200,000
2 Papan ( Kayu Kelas III ) M³ Rp 1,200,000
3 Multipleks 9 mm Lbr Rp 105,000
4 Bambu Btg Rp 18,000
Material Batu
5 Batu Kali Reet Rp 345,000
6 Batu Merah Biji Rp 350
7 Batu Kerikil ( Chipping ) Reet Rp 750,000
Material Pasir
8 Pasir Urug Reet Rp 335,000
9 Pasir Pasangan Reet Rp 345,000
10 Pasir Beton Reet Rp 350,000
Material Semen
11 Semen Bosowa Sak Rp 42,000
12 Semen Tiga Roda Sak Rp 42,000
13 Semen Tonasa Sak Rp 43,000
14 Plamur Amplus Zak Rp 100,000
15 Semen Nat Putih Bks Rp 12,000
Material Besi
16 Besi 10 ( ø 9.2 - ø 9.6 ) Btg Rp 52,000
17 Besi 8 ( ø 7.2 - ø 7.6 ) Btg Rp 45,000
18 Besi 6 ( ø 4.2 - ø 4.6 ) Btg Rp 22,000
19 Besi Hollow 2x4 Btg Rp 20,000
20 Besi Canal C Btg Rp 150,000
Material Keramik
21 Keramik WC ( 20 x 25 ) Syney Brown_Impresso Dos Rp 51,500
22 Keramik WC ( 20 x 20 ) Regatta Ivory_Picasso Dos Rp 47,000
23 Keramik ( 40 x 40 ) Victoria Grey_Impresso Dos Rp 48,500
24 Keramik ( 30 x 30 ) Rocky Blanco Impresso Dos Rp 52,000
Material Atap + Plafon
25 Atap Spandek 0.35 Gel. Besar M² Rp 51,500
26 Gypsum Jaya Board 9 mm Lbr Rp 52,500
27 Calsiboard Jaya Board 4 mm Lbr Rp 53,000
28 List Profil Gypsum Btg Rp 18,500
29 List Profil Kayu Btg Rp 12,500
30 Sekrup Gypsum Dos Rp 55,000
31 Plaster Gypsum Roll Rp 15,000
Material Pintu & Jendela
32 Daun Pintu HDF ( Excellent Door ) Kg Rp 500,000
33 Kusen Pintu + Ventilasi Roll Rp 700,000
34 Pintu Vinyl WC Dos Rp 175,000
35 Jendela Alminium + Engsel + Grendel Type 38 Rp 3,315,000
36 Jendela Alminium + Engsel + Grendel Type 52 Set Rp 4,525,000
37 Jendela Alminium + Engsel + Grendel Type 64 Set Rp 5,000,000
38 Handle Pintu ( Kunci Pintu + Body_Muller ) Set Rp 175,000
39 Engsel Pintu ( MAB ) Psg Rp 35,000
40 Kunci Tanam ( MAB ) Set Rp 350,000
Material Cat
41 Vinilex ( Putih Bersih ) Gln Rp 105,000
42 Avian S.W Klg Rp 45,000
43 Dempul Autolux 1,4 KG Klg Rp 38,000
44 Dempul Autolux 4 Kg Pail Rp 90,000
45 Dempul Yoko Klg Rp 18,000
46 Cat Mowilex ( Putih Bersih ) Gln Rp 120,000
47 Dulux Ws Brilliant White Gln Rp 270,000
48 Nippe 2000 Sw Klg Rp 60,000
49 No Drop Gln Rp 150,000
50 Thinner Super Ltr Rp 13,000
Material Instalasi Listrik
51 Saklar Seri Panasonic Buah Rp 16,700
52 Saklar Tunggal Panasonic Buah Rp 10,500
53 Stop Arde Panasonic Buah Rp 10,500
54 Stop Tlp Panasonic Buah Rp 36,200
55 Stop Tv Panasonic Buah Rp 38,750
56 Downlight 5" Silver Bh Rp 21,000
57 Box Panel 25x25 Sw Bh Rp 112,000
58 Conector Bh Rp 6,500
59 Dorabos 5/8 Bh Rp 15,000
60 Hyo 2x2,5 Mm Mtr Rp 5,000
61 Isolasi Htm 5.1500 Roll Rp 8,000
62 Mcb 6a ( Merlin Gerlin/Scheider ) Bh Rp 37,500
63 Servis Clamp Bh Rp 2,500
64 Spiral 20w Eclat Bh Rp 28,000
65 Kabel Eternik Mtr Rp 4,000
Material Instalasi Air
66 Closet Duduk Orin Set Rp 1,050,000
67 Westafle Set Rp 500,000
68 Kitchen Zink Set Rp 175,000
69 Shower Set ( Onda_SW 12 ) Set Rp 150,000
70 Jet Washer Putih ( Onda ) Set Rp 90,000
71 Kran Air Westafle ( F34PJ_Onda ) Buah Rp 130,000
72 Kran Air Leher Angsa ( H88 PJ_Onda ) Buah Rp 100,000
73 Mesin Shimizu Ps 130 Bh Rp 480,000
74 Knee 3" Buah Rp 7,500
75 Knee 3/4 Bh Rp 2,500
76 Kran Air Biasa 0,5 Bh Rp 10,000
77 Kuas 4" Eterna Bh Rp 36,000
78 Lem Fox Bks Rp 14,000
79 Lem Pipa Klg Rp 35,000
80 Pipa 3/4 Lucky Btg Rp 20,000
81 Pipa3" Lucky Bh Rp 52,000
82 Sambungan Pipa 3/4 T Bh Rp 3,000
83 Sambungan T 3/4 Bh Rp 2,500
84 Sok Drag Dalam 1-3/4" Bh Rp 8,000
85 L 1/2 " Biji Rp 2,000
86 L 3" Buah Rp 7,000
87 L 3/4" Buah Rp 2,000
88 Ldd Kuningan 3/4 Buah Rp 7,500
89 Kran Air Tembok ( Onda_F800Y ) Buah Rp 35,000
90 Floor Drain Buah Rp 17,000
Material Pelengkap
91 List Tali Air 0.08 Btg Rp 15,000
92 Adhi Bond ( Perekat Beton ) Ltr Rp 20,000
93 Sekrup 6x1 Dos Rp 50,000
94 Pemotong Tehel Euro Buah Rp 60,000
95 Serat Fiber Buah Rp 10,000
96 Skopan Buah Rp 50,000
97 Tangki Premier 1 M3 Buah Rp 1,000,000
98 Amplas 240 Mtr Rp 8,000
99 Kuas Roll Buah Rp 22,000
100 Cornice Zak Rp 65,000
101 Cup Bh Rp 5,000
102 K.D.D Roll Rp 7,000
103 Kawat Beton Kg Rp 15,000
104 Kawat Beton 20 Kg Roll Rp 300,000
105 Paku 10" Dos Rp 240,000
106 Paku 5 Cm Kg Rp 15,000
107 Paku 5" Dos Rp 240,000
108 Paku 7 Cm Kg Rp 15,000
109 Paku Beton 5 Cm Dos Rp 12,000
110 Plester Dico Roll Rp 7,000
111 Kuas 3" Buah Rp 10,000
112 Kuas 4" Bh Rp 13,000
113 Metal Stut Buah Rp 41,000
114 Uranner Buah Rp 25,000
115 Alkali Vinilex Gln Rp 130,000
116 Amplas 120 Roll Rp 300,000
117 Amplas 120 M Rp 8,000
118 Gerobak Arco Merah Buah Rp 360,000
119 Gurinda Maktek Buah Rp 300,000
PT. PATIARASE PROPERTINDO
DEVELOPER • REAL ESTATE • CONTRACTOR • SUPPLIER
GRAND AROEPALA Blok A No. 7 Telp. (0411) 497111 / 5611956
TOTAL COST
COST / M2
DIBULATKAN / M2
OPERTINDO
RACTOR • SUPPLIER
11) 497111 / 5611956
OS
HARGA (Rp.)
BOBOT (%)
JUMLAH
Rp 100,000 4.662
Rp 200,000 9.324
Rp 300,000 13.985
Rp 600,000 27.971
Rp 87,339 4.072
Rp 15,868 0.740 Rp 468,536
Rp 103,207 4.811
Rp 294,481 13.728
Rp 294,481 13.728
Rp 1,147,426 53.490
Rp 1,147,426 53.490 0.20 0.20 Rp 2,341,685
Rp 2,145,113
Rp 306,445 100 %
Rp 307,000
Rp 468,337 21.833
PT. PATIARASE PROPERTINDO
DEVELOPER • REAL ESTATE • CONTRACTOR • SUPPLIER
GRAND AROEPALA Blok A No. 7 Telp. (0411) 497111 / 5611956
BIAYA BOBOT JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER JANUARI FEBRUARI MARET APRIL MEI JUNI
NO URAIAN PEKERJAAN SATUAN VOLUME JUMLAH KET
KONSTRUKSI (%) III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II
I PEKERJAAN KONSTRUKSI RUMAH % 100
1. Cluster Latinoz, Type 38/90 Unit 2 Rp 87,400,000.00 Rp 174,800,000.00 2.270 0.142 0.142 0.142 0.142 0.142 0.142 0.142 0.142 0.142 0.142 0.142 0.142 0.142 0.142 0.142 0.142
1. Cluster Latinoz, Type 52/105 Unit 18 Rp 119,600,000.00 Rp 2,152,800,000.00 27.954 1.553 1.553 1.553 1.553 1.553 1.553 1.553 1.553 1.553 1.553 1.553 1.553 1.553 1.553 1.553 1.553 1.553 1.553 90%
SUB TOTAL Rp 2,327,600,000.00
II PEKERJAAN PONDASI KOMPLEKS
1. Pondasi Batu Kali mˈ 164.64 Rp 388,000.00 Rp 63,880,320.00 0.829 0.104 0.104 0.104 0.104 0.104 0.104 0.104 0.104 80 %
2. Pondasi Batu Kali Setengah mˈ 9.30 Rp 168,666.67 Rp 1,568,600.00 0.020 0.01 0.01
3. Pondasi Semi Poer m³ 33.00 Rp 1,024,000.00 Rp 33,792,000.00 0.439 0.11 0.11 0.11 0.11
70 %
SUB TOTAL Rp 99,240,920.00
III PEKERJAAN TIMBUNAN
60 %
1. Penimbunan Lokasi Reet 18000.00 Rp 180,000.00 Rp 3,240,000,000.00 42.071 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315 1.315
SUB TOTAL Rp 3,240,000,000.00
IV PEKERJAAN JALAN 50 %
1. Hamparan Sirtu 15 cm m³ 3175.97 Rp 265,000.00 Rp 841,632,315.00 10.929
2. Hamparan Pasir 10 cm m³ 688.08 Rp 458,399.00 Rp 315,415,183.92 4.096
3. Pemasangan Paving Blok m² 9.60 Rp 2,927,331.00 Rp 28,102,377.60 0.365 40 %
4. Pemasangan Cainstein mˈ 1.00 Rp 75,000,000.00 Rp 75,000,000.00 0.974
5. Pekerjaan Jembatan m³ 249.20 Rp 468,536.00 Rp 116,758,234.13 1.516 % 30
SUB TOTAL Rp 1,376,908,110.65
V PEKERJAAN DRAINASE
1. Galian Drainase mˈ 1.00 Rp 127,500,000.00 Rp 127,500,000.00 1.656 % 20
2. Pasangan Batu Kali mˈ 1.00 Rp 272,500,000.00 Rp 272,500,000.00 3.538
3. Plesteran m² 51.00 Rp 2,500,000.00 Rp 127,500,000.00 1.656 % 10
4. Pekerjaan Plat Deukker m³ 52.00 Rp 2,500,001.00 Rp 130,000,052.00 1.688
SUB TOTAL Rp 657,500,052.00 %0
TOTAL Rp 7,701,249,082.65 100 %
KEMAJUAN PEKERJAAN DALAM MINGGUAN % 2.971 2.971 2.971 2.971 2.971 2.971 2.971 2.971 2.878 2.878 2.977 2.977 2.977 2.977 2.868 2.868 2.868 2.868 1.457 1.457 1.457 1.457 1.457 1.457 1.457 1.457 1.457 1.457 1.457 1.457 1.457 1.457 0.142 0.142 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
KEMAJUAN PEKERJAAN DALAM BULANAN % 5.943 17.828 29.527 41.437 52.908 58.734 64.560 70.387 73.583 73.583 73.583 73.583 73.583