TIME SCEDULE

PPSDM GEOMINERBA
TAHUN 2021
REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN REHABILITASI GEDUNG PENGELOLA
MUSEUM GUNUNG BATUR

JUMLAH HARGA Bobot WAKTU PELAKSANAAN 60 HARI KALENDER


No
URAIAN PEKERJAAN (RP) % BULAN I BULAN II BULAN III Ket
MG 1 MG 2 MG 3 MG 4 MG 5 MG 6 MG 7 MG 8 MG 9
100
PEKERJAAN PERSIAPAN 58,225,460.00 12.32 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37 1.37
- -
2 - PEKERJAAN INTERIOR -
2.1 - RUANG KELAS TIPE 1 173,848,072.14 36.79 9.20 9.20 9.20 9.20
2.2 - RUANG KELAS TIPE 2 149,358,984.89 31.61 7.90 7.90 7.90 7.90 55
2.3 - RUANG KELAS TIPE 3 35,491,826.22 7.51 2.50 2.50 2.50 50
- -
3 - PEKERJAAN MEP -
3.1 - RUANG KELAS TIPE 1 34,953,450.00 7.40 2.47 2.47 2.47 35
3.2 - RUANG KELAS TIPE 2 13,578,575.00 2.87 0.96 0.96 0.96
3.3 - RUANG KELAS TIPE 3 7,111,650.00 1.50 0.50 0.50 0.50
-
JUMLAH RENCANA 472,568,018.24 100.00 1.37 10.57 13.03 20.93 21.89 10.23 13.23 4.37 4.37
OK
KUMULATIF RENCANA - 1.37 11.94 24.97 45.90 67.79 78.02 91.25 95.63 100

MINGGU KE 1 SD 8 TERDIRI DARI 7 HARI KERJA PENUH


MINGGU KE 9 TERDIRI DARI 4 HARI KERJA
TOTAL HARI YANG DIBUTUHKAN 60 HARI