Anda di halaman 1dari 4

RE

INSTALASI PEN

NO. ZONE IPA TRI WULAN I

SODA KAPORIT PAC


1 2 3 4 5

1 KAMPUNG BUGIS 3,850 4,050 14,300

2 IPA PERSEMAIAN 6,925 4,515 10,700

3 KAMPUNG SATU 6,250 3,990 15,675

4 JUATA LAUT 6,000 645 6,150

TOTAL 23,025 13,200 46,825

Sumber Data : Bidang Produksi PDAM Tirta Alam Kota Tarakan 2019
REALISASI PEMAKAIAN BAHAN KIMIA SODA
INSTALASI PENGOLAHAN AIR PDAM KOTA TARAKAN
TAHUN 2019

ZONA IPA
NO BULAN
KAMPUNG BUGIS IPA PERSEMAIAN KAMPUNG SATU JUATA LAUT

1 JANUARI 2,250 2,450 2,300 1,900

2 PEBRUARI 1,300 2,075 1,900 2,175

3 MARET 300 2,400 2,050 1,925

TOTAL TRI WULAN I 3,850 6,925 6,250 6,000

RATA-RATA / BULAN 1,283 2,308 2,083 2,000

4 APRIL 1,550 2,300 1,950 2,425

5 MEI 1,775 2,625 2,850 2,500

6 JUNI 1,625 2,275 3,600 2,275

TOTAL TRI WULAN II 4,950 7,200 8,400 7,200

RATA-RATA / BULAN 1,650 2,400 2,800 2,400

TOTAL SEMESTER I 8,800 14,125 14,650 13,200

RATA-RATA / BULAN 1,467 2,354 2,442 2,200

7 JULI 1,375 2,350 3,700 2,575

8 AGUSTUS 1,625 2,275 3,600 2,275

9 SEPTEMBER - 2,600 3,700 1,850

TOTAL TRI WULAN III 3,000 7,225 11,000 6,700

RATA-RATA / BULAN 1,000 2,408 3,667 2,233

10 OKTOBER 625 2,625 4,150 2,100

11 NOPEMBER 1,875 2,650 4,100 1,975

12 DESEMBER 2,200 3,400 4,600 2,575

TOTAL TRI WULAN IV 4,700 8,675 12,850 6,650

RATA-RATA / BULAN 1,567 2,892 4,283 2,217

TOTAL SEMESTER II 7,700 15,900 23,850 13,350

RATA-RATA / BULAN 1,283 2,650 3,975 2,225


REALISASI PEMAKAIAN BAHAN KIMIA KAPORIT
INSTALASI PENGOLAHAN AIR PDAM KOTA TARAKAN
TAHUN 2019

ZONA IPA
NO BULAN
KAMPUNG BUGIS IPA PERSEMAIAN KAMPUNG SATU JUATA LAUT

1 JANUARI 1,395 1,395 1,410 210

2 PEBRUARI 1,260 1,260 1,260 225

3 MARET 1,395 1,860 1,320 210

TOTAL TRI WULAN I 4,050 4,515 3,990 645

RATA-RATA / BULAN 1,350 1,505 1,330 215

4 APRIL 1,350 1,800 1,380 240

5 MEI 1,395 1,860 1,455 285

6 JUNI 1,230 1,740 1,215 255

TOTAL TRI WULAN II 3,975 5,400 4,050 780

RATA-RATA / BULAN 1,325 1,800 1,350 260

TOTAL SEMESTER I 8,025 9,915 8,040 1,425

RATA-RATA / BULAN 1,338 1,653 1,340 238

7 JULI 1,445 1,445 1,330 420

8 AGUSTUS 1,230 1,740 1,215 255

9 SEPTEMBER 1,500 1,500 1,500 350

TOTAL TRI WULAN III 4,175 4,685 4,045 1,025

RATA-RATA / BULAN 1,392 1,562 1,348 342

10 OKTOBER 1,550 1,550 1,550 300

11 NOPEMBER 1,500 1,500 1,500 350

12 DESEMBER 1,550 1,550 1,500 450

TOTAL TRI WULAN IV 4,600 4,600 4,550 1,100

RATA-RATA / BULAN 1,533 1,533 1,517 367

TOTAL SEMESTER II 8,775 9,285 8,595 2,125

RATA-RATA / BULAN 1,463 1,548 1,433 354


REALISASI PEMAKAIAN BAHAN KIMIA PAC
INSTALASI PENGOLAHAN AIR PDAM KOTA TARAKAN
TAHUN 2019

ZONA IPA
NO BULAN
KAMPUNG BUGIS IPA PERSEMAIAN KAMPUNG SATU JUATA LAUT

1 JANUARI 5,775 3,325 5,925 2,025

2 PEBRUARI 4,250 3,225 4,575 2,075

3 MARET 4,275 4,150 5,175 2,050

TOTAL TRI WULAN I 14,300 10,700 15,675 6,150

RATA-RATA / BULAN 4,767 3,567 5,225 2,050

4 APRIL 4,500 4,250 5,700 2,600

5 MEI 4,250 4,725 5,625 3,000

6 JUNI 4,200 4,075 5,200 2,725

TOTAL TRI WULAN II 12,950 13,050 16,525 8,325

RATA-RATA / BULAN 4,317 4,350 5,508 2,775

TOTAL SEMESTER I 27,250 23,750 32,200 14,475

RATA-RATA / BULAN 4,542 3,958 5,367 2,413

7 JULI 4,600 3,900 6,450 2,725

8 AGUSTUS 4,200 4,075 5,200 2,725

9 SEPTEMBER 2,925 3,950 4,500 1,775

TOTAL TRI WULAN III 11,725 11,925 16,150 7,225

RATA-RATA / BULAN 3,908 3,975 5,383 2,408

10 OKTOBER 4,575 4,050 5,850 2,250

11 NOPEMBER 5,200 4,425 5,626 2,575

12 DESEMBER 4,975 7,450 6,425 2,325

TOTAL TRI WULAN IV 14,750 15,925 17,901 7,150

RATA-RATA / BULAN 4,917 5,308 5,967 2,383

TOTAL SEMESTER II 26,475 27,850 34,051 14,375

RATA-RATA / BULAN 4,413 4,642 5,675 2,396

Anda mungkin juga menyukai