ANALISA HARGA SATUAN PEKERJAAN

1 m3 Galian Tanah Biasa sedalam lebih kecil sama dengan 1 m


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 OH 0.7500 90,000.000 67,500.000
2 Mandor L.15 OH 0.0250 110,000.000 2,750.000
JUMLAH HARGA TENAGA KERJA 70,250.000
B Peralatan
1 alat bantu Set 1.0000 4,215.000 4,215.000
JUMLAH HARGA PERALATAN 4,215.000
Jumlah 74,465.000
B PEMBULATAN 74,460.000

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 OH 0.5000 90,000.000 45,000.000
2 Mandor L.15 OH 0.0500 110,000.000 5,500.000
JUMLAH HARGA TENAGA KERJA 50,500.000
B Peralatan
-
JUMLAH HARGA PERALATAN -
Jumlah 50,500.000
B PEMBULATAN 50,500.000

Biaya K3
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Kebutuhan
1 Rambu Rambu Set 1.0000 200,000.000 200,000.000
2 Peralatan P3K Set 1.0000 150,000.000 150,000.000
3 Helm bh 10.0000 30,000.000 300,000.000
4 Sepatu boot bh 10.0000 80,000.000 800,000.000
5 Rompi bh 10.0000 10,000.000 100,000.000
6 Masker bh 10.0000 5,000.000 50,000.000
7 Sarung Tangan bh 10.0000 7,000.000 70,000.000
8 Bak Cuci Tangan bh 1.0000 100,000.000 100,000.000
JUMLAH HARGA TENAGA KERJA 1,770,000.000
Jumlah 1,770,000.000
B PEMBULATAN 1,770,000.000

1 m³ Urugan Pedel Dipadatkan


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 jam 1.0258 12,857.143 13,188.857
2 Mandor L.15 jam 0.1465 15,714.286 2,302.143
JUMLAH HARGA TENAGA KERJA 15,491.000
B Bahan
Pudel M3 1.1100 133,375.000 148,046.250
JUMLAH HARGA BAHAN 148,046.250
C Peralatan
1 Stamper jam 0.1070 86,633.000 9,269.731
JUMLAH HARGA PERALATAN 9,269.731

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 172,806.981

E PEMBULATAN 172,800.000
1 m³ Urugan Pasir Urug Dipadatkan
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.02 jam 1.0258 12,857.143 13,188.857
2 Mandor L.15 jam 0.1465 15,714.286 2,302.143
JUMLAH HARGA TENAGA KERJA 15,491.000
B Bahan
Pasir Urug / Timbun M3 1.1100 212,500.000 235,875.000
JUMLAH HARGA BAHAN 235,875.000
C Peralatan
1 Stamper jam 0.1070 - -
JUMLAH HARGA PERALATAN -

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 251,366.000

E PEMBULATAN 251,360.000

1 m³ Beton mutu, f'c = 14,5 Mpa (K175), slump (12±2) cm, w/c = 0,66
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 1.6500 90,000.000 148,500.000
2 Tukang L.04 OH 0.2750 100,000.000 27,500.000
3 Kepala tukang L.03 OH 0.0280 105,000.000 2,940.000
4 Mandor L.15 OH 0.0830 110,000.000 9,130.000
JUMLAH HARGA TENAGA KERJA 188,070.000
B Bahan
1 Semen ( PC ) M.18 Kg 326.0000 1,300.000 423,800.000
2 Pasir beton M.09 Kg 760.0000 238.125 180,975.000
3 Batu Pecah 2-3cm - Kg 1,029.0000 269.259 277,067.511
4 Air tawar M.01 Ltr 215.0000 100.000 21,500.000
JUMLAH HARGA BAHAN 903,342.511
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 1,091,412.511

Jumlah 1,091,412.511
F PEMBULATAN 1,091,410.000

1 m3 Lantai kerja beton mutu fc'=7,4 Mpa (K100) slump (3-6) cm, w/c = 0,87
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga Molen
1 Pekerja L.01 OH 1.2000 90,000.000 108,000.000
2 Tukang L.04 OH 0.2000 100,000.000 20,000.000
3 Kepala tukang L.03 OH 0.0200 105,000.000 2,100.000
4 Mandor L.15 OH 0.0600 110,000.000 6,600.000
JUMLAH HARGA TENAGA KERJA 136,700.000
B Bahan
1 Semen ( PC ) M.18 Kg 230.0000 1,300.000 299,000.000
2 Pasir beton M.09 M3 893.0000 238.125 212,645.625
3 Batu Pecah 2-3cm - M3 1,027.0000 269.259 276,528.993
4 Air tawar M.01 Ltr 200.0000 100.000 20,000.000
JUMLAH HARGA BAHAN 808,174.618

C Jumlah Harga Tenaga, Bahan dan Peralatan (A + B ) 944,874.618


E PEMBULATAN 944,870.000
1 kg Pembesian dengan besi polos atau ulir
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.0700 90,000.000 6,300.000
2 Tukang besi L.04 OH 0.0700 100,000.000 7,000.000
3 Kepala tukang L.03 OH 0.0070 105,000.000 735.000
4 Mandor L.15 OH 0.0040 110,000.000 440.000
JUMLAH HARGA TENAGA KERJA 14,475.000
B Bahan
1 Besi beton Kg 10.5000 11,000.000 115,500.000
2 Kawat beton M.75 Kg 0.1500 19,000.000 2,850.000
JUMLAH HARGA BAHAN 118,350.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 132,825.000

Harga Satuan Pekejaan /kg 13,282.500


Jumlah 13,282.500
E PEMBULATAN 13,280.000

1 m² Begisting untuk Dinding


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 OH 0.6600 90,000.000 59,400.000
2 Tukang kayu L.04 OH 0.3300 100,000.000 33,000.000
3 Kepala tukang L.03 OH 0.0330 105,000.000 3,465.000
4 Mandor L.15 OH 0.0330 110,000.000 3,630.000
JUMLAH HARGA TENAGA KERJA 99,495.000
B Bahan
1 Multiplek 8 mm 120 x 240 cm M.61/M.17 Lbr 0.3500 105,000.000 36,750.000
2 Kayu bekisting M.54 m³ 0.0300 3,500,000.000 105,000.000
3 Paku M.77 Kg 0.4000 20,000.000 8,000.000
JUMLAH HARGA BAHAN 149,750.000
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 249,245.000

Asumsi dipakai 3 kali 0.3333 X D 83,073.359


Jumlah 83,073.359
PEMBULATAN 83,070.000
1 BH Pengadaan dan Pemasangan BC 80 x 80 120 T 12 cm Mesh 10 K-350
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja jam 2.6496 12,857.143 34,066.286
2 Tukang jam 1.0598 14,285.714 15,140.000
3 Mandor jam 0.5299 15,714.286 8,327.000
JUMLAH HARGA TENAGA KERJA 57,533.286
B Bahan
1 BC 80 x 80 120 T 12 cm Mesh 10 K-350 BH 1.0000 2,931,500.000 2,931,500.000
JUMLAH HARGA BAHAN 2,931,500.000
C Peralatan
1 Sewa Alat / Crane jam 0.5857 712.457 417.286
2 Alat bantu Set 1.0000 3,451.997 3,451.997
JUMLAH HARGA PERALATAN 3,869.283

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 2,992,902.569


PEMBULATAN 2,992,900.000

1 BH Pengadaan dan Pemasangan U-DICTH 40.50.120 t 6 cm mesh 6 K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja jam 0.6550 12,857.143 8,421.429
2 Tukang jam 0.2620 14,285.714 3,742.857
3 Mandor jam 0.1310 15,714.286 2,058.571
JUMLAH HARGA TENAGA KERJA 14,222.857
B Bahan
1 U-DICTH 40.50.120 t 6 cm mesh 6 K. 350 BH 1.0000 496,000.000 496,000.000
JUMLAH HARGA BAHAN 496,000.000
C Peralatan
1 Sewa Alat / Crane jam 0.1339 580,902.000 77,782.778
2 Alat bantu Set 1.0000 853.371 853.371
JUMLAH HARGA PERALATAN 78,636.149

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 588,859.006


PEMBULATAN 588,850.000

1 BH Pengadaan dan Pemasangan COVER-DICTH 40.120 t 12 cm mesh 8 K. 350


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja jam 0.4464 12,857.143 5,739.429
2 Tukang jam 0.1786 14,285.714 2,551.429
3 Mandor jam 0.0893 15,714.286 1,403.286
JUMLAH HARGA TENAGA KERJA 9,694.144
B Bahan
1 COVER-DICTH 40.120 t 12 cm mesh 8 K. 350 BH 1.0000 302,000.000 302,000.000
JUMLAH HARGA BAHAN 302,000.000
C Peralatan
1 Sewa Alat / Crane jam 0.0602 580,902.000 34,970.300
2 Alat bantu Set 1.0000 581.649 581.649
JUMLAH HARGA PERALATAN 35,551.949

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 347,246.093


PEMBULATAN 347,240.000
1 m2 Plesteran tebal 15mm Campuran 1:5
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja OH 0.3000 90,000.000 27,000.000
2 Tukang OH 0.1500 100,000.000 15,000.000
3 Kepala tukang OH 0.0150 105,000.000 1,575.000
4 Mandor OH 0.0300 110,000.000 3,300.000
JUMLAH HARGA TENAGA KERJA 46,875.000
B Bahan
1 Pasir Pasang m3 0.0160 305,000.000 4,880.000
2 Semen ( PC ) kg 5.1840 1,300.000 1,300.000
JUMLAH HARGA BAHAN 6,180.000
C Peralatan
JUMLAH HARGA PERALATAN -

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 53,055.000

E Jumlah 53,055.000
PEMBULATAN 53,050.000

1 m3 Pembongkaran beton (Mekanis)/Jack Hammer


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja jam 13.3340 12,857.143 171,437.145
2 Mandor jam 0.6660 15,714.286 10,465.714
JUMLAH HARGA TENAGA KERJA 181,902.859
B Peralatan
1 Jack Hammrer jam 1.2048 50,479.000 60,817.099
JUMLAH HARGA PERALATAN 60,817.099

C Jumlah Harga Tenaga dan Peralatan (A + B + C) 242,719.958


PEMBULATAN 242,710.000

1 m2 Pembongkaran paving block


HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga
1 Pekerja L.01 Jam 0.5500 12,857.140 7,071.427
2 Tukang L.04 Jam 0.2000 14,285.710 2,857.142
3 Mandor L.15 Jam 0.0500 15,714.290 785.715
JUMLAH HARGA TENAGA KERJA 10,714.284
B Bahan
-
JUMLAH HARGA BAHAN -
C Peralatan

JUMLAH HARGA PERALATAN

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 10,714.284

Jumlah 10,714.284
F PEMBULATAN 10,710.000
1 m3 Pengangkutan Material Bekas Bongkaran
HARGA JUMLAH
NO. URAIAN KODE SATUAN KOEFISIEN
SATUAN (Rp) HARGA (Rp)
A Tenaga

JUMLAH HARGA TENAGA KERJA -


B Bahan

JUMLAH HARGA BAHAN -


C Peralatan
Dump Truck jam 0.2114 244,000.000 51,581.600
JUMLAH HARGA PERALATAN 51,581.600

D Jumlah Harga Tenaga, Bahan dan Peralatan (A + B + C) 51,581.600

Jumlah 51,581.600
F PEMBULATAN 51,580.000
DAFTAR HARGA SATUAN UPAH DAN BAHAN
TAHUN ANGGARAN 2021
PROPINSI : JAWA TIMUR KABUPATEN : BOJONEGORO
HARGA UPAH / BAHAN SESUAI
NO URAIAN SATUAN KET.
NEGOSIASI PPK
1 2 4 5 6

I UPAH
- Mandor Orang/Hari Rp. 110,000.000
- Kepala Tukang Orang/Hari Rp. 105,000.000
- Tukang Orang/Hari Rp. 100,000.000
- Pekerja Orang/Hari Rp. 90,000.000
- Operator Terlatih Orang/Hari Rp. 175,000.000
- Pembantu Operator Orang/Hari Rp. 125,000.000

II BAHAN
- U-DICTH 40.50.120 t 6 cm mesh 6 K. 350 bh Rp. 496,000.000
- COVER-DICTH 40.120 t 12 cm mesh 8 K. 350 bh Rp. 302,000.000
- BC 80 x 80 120 T 12 cm Mesh 10 K-350 bh Rp. 2,931,500.000
- Pasir Urug / Timbun m3 Rp. 212,500.000
- Semen ( PC ) kg Rp. 1,300.000
- Pasir Pasang m3 Rp. 305,000.000
- Paku Kg Rp. 20,000.000
- Pasir beton m3 Rp. 333,375.000
- Batu Pecah 2-3cm m3 Rp. 363,500.000
- Pudel m3 Rp. 133,375.000
- Besi beton Kg Rp. 11,000.000
- Kawat beton Kg Rp. 19,000.000
- Air tawar Liter Rp. 100.000
- Multiplek 8 mm 120 x 240 cm Lbr Rp. 105,000.000

III SEWA ALAT

- Stamper jam 86,633.000


- Jack Hammer jam 50,479.000
- Exavator jam 431,951.000
- Truck Crane 5 ton jam 580,902.000
- Dump Truck jam 244,000.000
- Chainsaw jam 57,100.000
- Tandem Roller jam 439,876.030
- Three Wheel Roller jam 200,000.000
- Asphalt Distributor jam 404,733.932
- Three Wheel Roller jam 244,378.349
- Kompresor jam 161,027.817
- Pompa Air Set 50,000.000