JADWAL PELAKSANAAN KERJA (KURVA S)

PEMBUATAN JALAN LINGKAR TAHAP 2 RSUPN DR. CIPTO MANGUNKUSUMO


WAKTU PELAKSANAAN (45 HARI)
NO URAIAN PEKERJAAN TOTAL BOBOT KET
M1 M2 M3 M4 M5 M6 M7

100
A PEKERJAAN PERSIAPAN 16.585.200,00 1,497 1,497
B PEKERJAAN BONGKARAN 23.921.640,65 2,159 1,079 1,079
C PEKERJAAN RELOKASI & PERBAIKAN 11.641.672,20 1,050 0,525 0,525 90
D PEKERJAAN GROUND WATER TANK
1 Modifikasi Ground Water Tank 1 12.987.526,47 1,172 1,172
2 Modifikasi Ground Water Tank 2 68.135.784,09 6,148 3,074 3,074 80

E PEKERJAAN SALURAN
1 Saluran box culvert 50x50x100 cm 143.213.689,14 12,923 4,308 4,308 4,308
70
2 Saluran box culvert 60x60x100 cm 206.230.652,71 18,609 6,203 6,203 6,203
3 Bak kontrol 84x84 cm 115.226.065,91 10,397 5,199 5,199
4 Bak kontrol 70x70 cm 65.598.671,12 5,919 2,960 2,960 60
F PEKERJAAN PEDESTRIAN & KANSTIN
1 Pekerjaan pedestrian Utilitas 13.688.247,74 1,235 1,235
2 Pekerjaan pedestrian Parkir 62.275.314,85 5,619 2,810 2,810 50

3 Pekerjaan pedestrian Putaran Jembatan 44.351.277,08 4,002 1,334 1,334 1,334


4 Pekerjaan pedestrian Rumah Singgah 15.269.852,61 1,378 1,378
40
5 Pekerjaan pedestrian Gerbang Keluar 12.550.272,04 1,132 1,132
6 Pekerjaan pedestrian Kirana 14.906.144,84 1,345 1,345
7 Pekerjaan Kanstin 55.695.558,48 5,026 5,026 30
G PEKERJAAN JALAN
1 Pekerjaan jalan beton 32.330.741,41 2,917 1,459 1,459
2 Pengaspalan tempat parkir dan jalan rusak 60.266.997,79 5,438 1,813 1,813 1,813 20

3 Pengecatan Marka Jalan Thermoplastic Yellow tebal 3 mm 37.095.237,56 3,347 1,674 1,674
4 Pengecatan Marka Parkir Thermoplastic Yellow tebal 3 mm 32.677.053,19 2,949 1,474 1,474
10
5 Pasang lampu PJU
Area Parkir depan CMU 2 49.348.106,87 4,453 2,226 2,226
Area Boiler/KIrana 14.234.461,00 1,284 1,284 0
JUMLAH 1.108.230.167,74 100,00
BOBOT RENCANA PER MINGGU 2,576 10,158 24,687 32,161 18,261 8,646 3,511
KOMULATIF BOBOT RENCANA PER MINGGU 2,576 12,734 37,421 69,582 87,843 96,489 100,000

KURVA S 1 of 1