WAKTU
PROYEK
Gentisya Tri Mardiani
MANAJEMEN PROYEK
PERANGKAT LUNAK
Latihan
ID Description Preceding Activity
B Membuat ERD A
C Membuat SKPL A
D Membuat DFD A
F Prototyping B,C,D
G Development F
H Testing E, G
AON Network
B E
ERD Lap
Pendahuluan
Testing
A C F G
Analisa SKPL Prototyping Development
BP
D
DFD
ES ID EF
SL Deskripsi
LS Dur LF
AON Project Duration Example
ID Description Preceding Estimated
Activity Duration
A Analisis Proses Bisnis None 5
B Membuat ERD A 5
C Analisis kebutuhan A 11
fungsional
D Analisis kebutuhan non- A 6
fungsional
E Membuat dokumentasi B, C 6
laporan awal (SKPL)
F Prototyping B,C,D 20
G Development F 10
H Testing E, G 2
AON Network
B E
ERD SKPL
Testing
A C F G
Analisis A.Keb. Prototyping Development
BP Fungsio
nal
D
A.Keb.
Non-
fungsional
ES ID EF
SL Deskripsi
LS d LF
AON Network (tidak ada slack)
5 B 10 16 E 22
ERD SKPL
5 6
46 H 48
Testing
0 A 5 5 C 16 16 F 36 36 G 46 2
5 D 11
A.Keb.
Non-
fungsional
ES ID EF
6
SL Deskripsi
LS d LF
SLACK / FLOAT
• Total Slack (TS)
– Jumlah waktu yang diperkenankan untuk suatu kegiatan boleh ditunda atau
terlambat, tanpa mempengaruhi jadwal pelaksanaan proyek secara
keseluruhan
– Kegiatan-kegiatan yang memiliki nilai slack total tertentu (tidak sama
dengan nol), maka pelaksanaan kegiatan tersebut dalam jalur yang
bersangkutan dapat ditunda atau diperpanjang sampai batas nilai slack
– Kegiatan-kegiatan yang mempunyai nilai float total sama dengan nol,
berarti kegiatan tersebut dalam pelaksanaanya tidak boleh ditunda atau
terlambat sama sekali.
5 6
46 H 48
Testing
0 A 5 5 C 16 16 F 36 36 G 46 2
5 D 11
A.Keb.
Non-
fungsional
ES ID EF
6
SL Deskripsi
LS d LF
AON Network (ada slack)
5 B 10 16 E 22
2 ERD Lap
24 Pendahuluan
7 5 12
40 6 46
46 H 48
Testing
0 A 5 5 C 16 16 F 36 36 G 46 46 2 48
5 D 16
0 A.Keb.
Non-
fungsional
ES ID EF
5 6 11
SL Deskripsi
LS Dur LF
Latihan