PERHITUNGAN VOLUME PENAN

PAKET : PEMEL. BERKAL


No. Item Uraian Pekerjaan

1.2 MOBILISASI

3.2.(2) TIMBUNAN PILIHAN

5.1(1) LAPIS PONDASI AGGREGAT KELAS A

5.1(2) LAPIS PONDASI AGGREGAT KELAS B

5.1(3) LAPIS PONDASI AGGREGAT KELAS S

5.6.(1.a) SEMEN UNTUK CTRB

5.6.(1.b) CEMENT TREATED RECYCLING BASE (CTRB)

6.1(1)a LAPIS RESAP PENGIKAT ( PRIME COAT )-ASPAL CAIR

6.1(2)a LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR (OVERLAY)

LAPIS PEREKAT ( TACK COAT ) (UNTUK LEVELING)-ASPAL CAIR

6.3(3)a HRS - WC 3,0Cm (GRADASI SENJANG/SEMI SENJANG )

6.3(4)a HRS - BASE (GRADASI SENJANG/SEMI SENJANG )

6.3(4)b HRS - BASE LEVELING (GRADASI SENJANG/SEMI SENJANG)

6.3(8) ASPAL

ASPAL UNTUK HRS-WC

ASPAL UNTUK HRS-BASE

ASPAL UNTUK HRS-BASE LEVELLING

6.3 (10) Bahan Pengisi (Filer) Tambahan (Semen)

6.4.6 Bahan Anti Pengelupasan (Anti Striping Agent)

7.1(7) BETON MUTU SEDANG DENGAN fc'=20 Mpa ( K-250 )

7.1(8) BETON MUTU RENDAH DENGAB fc'=15 Mpa ( K-125 )

7.3(1) BAJA TULANGAN BJ 24 POLOS

8.1(1) LAPIS PONDASI AGG. KELAS A UTK PEK. MINOR


JUMLAH

PPN 10 %

JUMLAH

JUMLAH DIBULATKAN

PERHITUNGAN VOLUME PENAN


PAKET : PEMEL. BERKAL
No. Item Uraian Pekerjaan

1.2 MOBILISASI

3.2.(2) TIMBUNAN PILIHAN

5.1(1) LAPIS PONDASI AGGREGAT KELAS A

5.1(2) LAPIS PONDASI AGGREGAT KELAS B

5.1(3) LAPIS PONDASI AGGREGAT KELAS S

5.6.(1.a) SEMEN UNTUK CTRB

5.6.(1.b) CEMENT TREATED RECYCLING BASE (CTRB)

6.1(1)a LAPIS RESAP PENGIKAT ( PRIME COAT )-ASPAL CAIR

6.1(2)a LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR (OVERLAY)

LAPIS PEREKAT ( TACK COAT ) (UNTUK LEVELING)-ASPAL CAIR

6.3(3)a HRS - WC 3,0Cm (GRADASI SENJANG/SEMI SENJANG )

6.3(4)a HRS - BASE (GRADASI SENJANG/SEMI SENJANG )

6.3(4)b HRS - BASE LEVELING (GRADASI SENJANG/SEMI SENJANG)

6.3(8) ASPAL

ASPAL UNTUK HRS-WC

ASPAL UNTUK HRS-BASE

ASPAL UNTUK HRS-BASE LEVELLING


7.1(7) BETON MUTU SEDANG DENGAN fc'=20 Mpa ( K-250 )

7.1(8) BETON MUTU RENDAH DENGAB fc'=15 Mpa ( K-125 )

7.3(1) BAJA TULANGAN BJ 24 POLOS

8.1(1) LAPIS PONDASI AGG. KELAS A UTK PEK. MINOR

JUMLAH
PPN 10 %
JUMLAH
JUMLAH DIBULATKAN
PERHITUNGAN VOLUME PENANGANAN TAHUN AN
PAKET : PEMEL. BERKALA JALAN BTS. KOTA SAMPIT
Uraian Pekerjaan Tebal Lebar

MOBILISASI

TIMBUNAN PILIHAN 1.50 M X 1.00

LAPIS PONDASI AGGREGAT KELAS A 0.15 M X 8.00

LAPIS PONDASI AGGREGAT KELAS B 0.25 M X 8.00

LAPIS PONDASI AGGREGAT KELAS S 0.15 M X 1.50

SEMEN UNTUK CTRB VOLUME CTRB X 6,5%

CEMENT TREATED RECYCLING BASE (CTRB) 0.30 M X 5.00

LAPIS RESAP PENGIKAT ( PRIME COAT )-ASPAL CAIR 0.85 Ltr X 3.50

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR (OVERLAY) 0.15 Ltr X 4.50

LAPIS PEREKAT ( TACK COAT ) (UNTUK LEVELING)-ASPAL CAIR 0.15 Ltr X 4.50

HRS - WC 3,0Cm (GRADASI SENJANG/SEMI SENJANG ) 0.03 M X 4.50

HRS - BASE (GRADASI SENJANG/SEMI SENJANG ) 0.04 M X 3.50

HRS - BASE LEVELING (GRADASI SENJANG/SEMI SENJANG) 0.04 M X 4.50

ASPAL UNTUK HRS-WC VOLUME HRS - WC X 7%

ASPAL UNTUK HRS-BASE VOLUME HRS - BASE X 6%

ASPAL UNTUK HRS-BASE LEVELLING VOLUME HRS - BASE LEVELLING X 6%

Bahan Pengisi (Filer) Tambahan (Semen) VOLUME HRS-WC DAN BASE X 1%

Bahan Anti Pengelupasan (Anti Striping Agent)

BETON MUTU SEDANG DENGAN fc'=20 Mpa ( K-250 ) 2 BUAH BOX CULVERT

BETON MUTU RENDAH DENGAB fc'=15 Mpa ( K-125 ) 2 BUAH BOX CULVERT

BAJA TULANGAN BJ 24 POLOS 2 BUAH BOX CULVERT

LAPIS PONDASI AGG. KELAS A UTK PEK. MINOR 0.15 M X 3.50


PPN 10 %

JUMLAH DIBULATKAN

PERHITUNGAN VOLUME PENANGANAN TAHUN ANG


PAKET : PEMEL. BERKALA JALAN BTS. KOTA SAMPIT
Uraian Pekerjaan Tebal Lebar

MOBILISASI

TIMBUNAN PILIHAN 1.50 M X 1.00

LAPIS PONDASI AGGREGAT KELAS A 0.15 M X 8.00

LAPIS PONDASI AGGREGAT KELAS B 0.25 M X 8.00

LAPIS PONDASI AGGREGAT KELAS S 0.15 M X 2.00

SEMEN UNTUK CTRB VOLUME CTRB X 6,5%

CEMENT TREATED RECYCLING BASE (CTRB) 0.30 M X 5.00

LAPIS RESAP PENGIKAT ( PRIME COAT )-ASPAL CAIR 0.85 Ltr X 3.50

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR (OVERLAY) 0.15 Ltr X 4.50

LAPIS PEREKAT ( TACK COAT ) (UNTUK LEVELING)-ASPAL CAIR 0.15 Ltr X 4.50

HRS - WC 3,0Cm (GRADASI SENJANG/SEMI SENJANG ) 0.03 M X 4.50

HRS - BASE (GRADASI SENJANG/SEMI SENJANG ) 0.04 M X 3.50

HRS - BASE LEVELING (GRADASI SENJANG/SEMI SENJANG) 0.04 M X 4.50

ASPAL UNTUK HRS-WC VOLUME HRS - WC X 7%

ASPAL UNTUK HRS-BASE VOLUME HRS - BASE X 6%

ASPAL UNTUK HRS-BASE LEVELLING VOLUME HRS - BASE LEVELLING X 6%


BETON MUTU SEDANG DENGAN fc'=20 Mpa ( K-250 ) 2 BUAH BOX CULVERT

BETON MUTU RENDAH DENGAB fc'=15 Mpa ( K-125 ) 2 BUAH BOX CULVERT

BAJA TULANGAN BJ 24 POLOS 2 BUAH BOX CULVERT

LAPIS PONDASI AGG. KELAS A UTK PEK. MINOR 0.15 M X 3.50

PPN 10 %

JUMLAH DIBULATKAN
AN TAHUN ANGGARAN 2011 (KONTRAK ASAL)
N BTS. KOTA SAMPIT - PALANTARAN / KM.65
Lebar Panjang Volume Satuan Harga Satuan

1.00 Ls 80,231,097.14

M X 12.00 M = x2 36.00 M3 241,270.00

M X 20.00 M = 24.00 M3 602,330.00

M X 20.00 M = 40.00 M3 571,090.00

M X 5,350.00 M = x2 2,407.00 M3 438,340.00

65.52 TON 1,658,780.00

M X 300.00 M = 450.00 M3 222,850.00

M X 2,515.00 M = 14,964.00 Liter 12,145.00

5,636.00 Liter 12,940.00

M X 5,350.00 M = 3,611.00 Liter

M X 3,000.00 M = 2,025.00 Liter

M X 5,000.00 M = x 2,25 1,519.00 Ton 414,180.00

M X 2,515.00 M = x 2,25 792.00 Ton 415,730.00

M X 3,000.00 M = x 2,25 1,215.00 Ton 415,730.00

226.75 Ton 11,850,000.00

106.33 Ton

BASE X 6% 47.52 Ton

BASE LEVELLING X 6% 72.90 Ton

WC DAN BASE X 1% 15.19 Ton 1,658,780.00

265.83 Kg 100,000.00

51.97 M3 1,092,650.00

6.58 M3 845,450.00

6,484.00 KG 17,730.00

M X 2,515.00 M = 1,320.00 M3 601,650.00


AN TAHUN ANGGARAN 2011 (TAMBAHAN 10%)
N BTS. KOTA SAMPIT - PALANTARAN / KM.65
Lebar Panjang Volume Satuan Harga Satuan

1.00 Ls 80,231,097.14

M X 12.00 M = xx 22 36.00 M3 241,270.00

M X 20.00 M = 24.00 M3 602,330.00

M X 20.00 M = 40.00 M3 571,090.00

M X 5,910.00 M = x2 3,546.00 M3 438,340.00


x 2,25 29.25 TON 1,658,780.00

M X 300.00 M = x 2,32 450.00 M3 222,850.00


x 2,25
M X 2,590.00 M = 15,411.00 Liter 12,145.00

6,082.00 Liter 12,940.00

M X 5,910.00 M = 3,989.00 Liter

M X 3,100.00 M = 2,093.00 Liter

M X 5,910.00 M = x 2,25 1,795.00 Ton 414,180.00

M X 2,590.00 M = x 2,25 816.00 Ton 415,730.00

M X 3,100.00 M = x 2,25 1,256.00 Ton 415,730.00

249.97 Ton 11,850,000.00

125.65 Ton

BASE X 6% 48.96 Ton

BASE LEVELLING X 6% 75.36 Ton


51.97 M3 1,092,650.00

6.58 M3 845,450.00

6,484.00 KG 17,730.00

M X 2,590.00 M = 1,360.00 M3 601,650.00


L)

Jumlah Harga Keterangan

80,231,097.14

8,685,720.00

14,455,920.00

22,843,600.00

1,055,084,380.00

108,683,265.60

100,282,500.00

181,737,780.00

72,929,840.00

629,139,420.00 1519

329,258,160.00 106.33

505,111,950.00 1625.33

2,686,987,500.00 5350.8806584

106.33

25,196,868.20 Item Baru

26,582,500.00 Item Baru

56,785,020.50

5,563,061.00

114,961,320.00

794,178,000.00
6,818,697,902.44

681,869,790.24

7,500,567,692.68 7,987,795,000

7,660,000,000.00 487,227,307.32

750,056,769.27
%) 8,410,056,769.27

Jumlah Harga

80,231,097.14

8,685,720.00

14,455,920.00

22,843,600.00

1,554,353,640.00

48,519,315.00

100,282,500.00

187,166,595.00

78,701,080.00

743,453,100.00

339,235,680.00

522,156,880.00

2,962,144,500.00
56,785,020.50

5,563,061.00

114,961,320.00

818,244,000.00

7,657,783,028.64
765,778,302.86
8,423,561,331.50
8,423,000,000.00
PERHITUNGAN VOLUME PENAN
PAKET : PEMEL. BERKAL
No. Item Uraian Pekerjaan

1.2 MOBILISASI

3.2.(2) TIMBUNAN PILIHAN

5.1(1) LAPIS PONDASI AGGREGAT KELAS A

5.1(2) LAPIS PONDASI AGGREGAT KELAS B

5.1(3) LAPIS PONDASI AGGREGAT KELAS S

5.6.(1.a) SEMEN UNTUK CTRB

5.6.(1.b) CEMENT TREATED RECYCLING BASE (CTRB)

6.1(1)a LAPIS RESAP PENGIKAT ( PRIME COAT )-ASPAL CAIR

6.1(2)a LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR (OVERLAY)

LAPIS PEREKAT ( TACK COAT ) (UNTUK LEVELING)-ASPAL CAIR

6.3(3)a HRS - WC 3,0Cm (GRADASI SENJANG/SEMI SENJANG )

6.3(4)a HRS - BASE (GRADASI SENJANG/SEMI SENJANG )

6.3(4)b HRS - BASE LEVELING (GRADASI SENJANG/SEMI SENJANG)

6.3(8) ASPAL

ASPAL UNTUK HRS-WC

ASPAL UNTUK HRS-BASE

ASPAL UNTUK HRS-BASE LEVELLING

6.31 BAHAN PENGISI (FILER) TAMBAHAN (SEMEN)

7.1(7) BETON MUTU SEDANG DENGAN fc'=20 Mpa ( K-250 )

7.1(8) BETON MUTU RENDAH DENGAB fc'=15 Mpa ( K-125 )

7.3(1) BAJA TULANGAN BJ 24 POLOS

8.1(1) LAPIS PONDASI AGG. KELAS A UTK PEK. MINOR


JUMLAH

PPN 10 %

JUMLAH

JUMLAH DIBULATKAN

PERHITUNGAN VOLUME PENAN


PAKET : PEMEL. BERKAL
No. Item Uraian Pekerjaan

1.2 MOBILISASI

3.2.(2) TIMBUNAN PILIHAN

5.1(1) LAPIS PONDASI AGGREGAT KELAS A

5.1(2) LAPIS PONDASI AGGREGAT KELAS B

5.1(3) LAPIS PONDASI AGGREGAT KELAS S

5.6.(1.a) SEMEN UNTUK CTRB

5.6.(1.b) CEMENT TREATED RECYCLING BASE (CTRB)

6.1(1)a LAPIS RESAP PENGIKAT ( PRIME COAT )-ASPAL CAIR

6.1(2)a LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR (OVERLAY)

LAPIS PEREKAT ( TACK COAT ) (UNTUK LEVELING)-ASPAL CAIR

6.3(3)a HRS - WC 3,0Cm (GRADASI SENJANG/SEMI SENJANG )

6.3(4)a HRS - BASE (GRADASI SENJANG/SEMI SENJANG )

6.3(4)b HRS - BASE LEVELING (GRADASI SENJANG/SEMI SENJANG)

6.3(8) ASPAL

ASPAL UNTUK HRS-WC

ASPAL UNTUK HRS-BASE

ASPAL UNTUK HRS-BASE LEVELLING

7.1(7) BETON MUTU SEDANG DENGAN fc'=20 Mpa ( K-250 )


7.1(8) BETON MUTU RENDAH DENGAB fc'=15 Mpa ( K-125 )

7.3(1) BAJA TULANGAN BJ 24 POLOS

8.1(1) LAPIS PONDASI AGG. KELAS A UTK PEK. MINOR

JUMLAH
PPN 10 %
JUMLAH
JUMLAH DIBULATKAN
PERHITUNGAN VOLUME PENANGANAN TAHUN AN
PAKET : PEMEL. BERKALA JALAN BTS. KOTA SAMPIT
Uraian Pekerjaan Tebal Lebar

MOBILISASI

TIMBUNAN PILIHAN 1.50 M X 1.00

LAPIS PONDASI AGGREGAT KELAS A 0.15 M X 8.00

LAPIS PONDASI AGGREGAT KELAS B 0.25 M X 8.00

LAPIS PONDASI AGGREGAT KELAS S 0.15 M X 2.00

SEMEN UNTUK CTRB VOLUME CTRB X 6,5%

CEMENT TREATED RECYCLING BASE (CTRB) 0.30 M X 5.00

LAPIS RESAP PENGIKAT ( PRIME COAT )-ASPAL CAIR 0.85 Ltr X 3.50

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR (OVERLAY) 0.15 Ltr X 4.50

LAPIS PEREKAT ( TACK COAT ) (UNTUK LEVELING)-ASPAL CAIR 0.15 Ltr X 4.50

HRS - WC 3,0Cm (GRADASI SENJANG/SEMI SENJANG ) 0.03 M X 4.50

HRS - BASE (GRADASI SENJANG/SEMI SENJANG ) 0.04 M X 3.50

HRS - BASE LEVELING (GRADASI SENJANG/SEMI SENJANG) 0.04 M X 4.50

ASPAL UNTUK HRS-WC VOLUME HRS - WC X 7%

ASPAL UNTUK HRS-BASE VOLUME HRS - BASE X 6%

ASPAL UNTUK HRS-BASE LEVELLING VOLUME HRS - BASE LEVELLING X 6%

BAHAN PENGISI (FILER) TAMBAHAN (SEMEN) VOLUME HRS-WC DAN BASE X 1%

BETON MUTU SEDANG DENGAN fc'=20 Mpa ( K-250 ) 2 BUAH BOX CULVERT

BETON MUTU RENDAH DENGAB fc'=15 Mpa ( K-125 ) 2 BUAH BOX CULVERT

BAJA TULANGAN BJ 24 POLOS 2 BUAH BOX CULVERT

LAPIS PONDASI AGG. KELAS A UTK PEK. MINOR 0.15 M X 3.50


PPN 10 %

JUMLAH DIBULATKAN

PERHITUNGAN VOLUME PENANGANAN TAHUN ANG


PAKET : PEMEL. BERKALA JALAN BTS. KOTA SAMPIT
Uraian Pekerjaan Tebal Lebar

MOBILISASI

TIMBUNAN PILIHAN 1.50 M X 1.00

LAPIS PONDASI AGGREGAT KELAS A 0.15 M X 8.00

LAPIS PONDASI AGGREGAT KELAS B 0.25 M X 8.00

LAPIS PONDASI AGGREGAT KELAS S 0.15 M X 2.00

SEMEN UNTUK CTRB VOLUME CTRB X 6,5%

CEMENT TREATED RECYCLING BASE (CTRB) 0.30 M X 5.00

LAPIS RESAP PENGIKAT ( PRIME COAT )-ASPAL CAIR 0.85 Ltr X 3.50

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR

LAPIS PEREKAT ( TACK COAT )-ASPAL CAIR (OVERLAY) 0.15 Ltr X 4.50

LAPIS PEREKAT ( TACK COAT ) (UNTUK LEVELING)-ASPAL CAIR 0.15 Ltr X 4.50

HRS - WC 3,0Cm (GRADASI SENJANG/SEMI SENJANG ) 0.03 M X 4.50

HRS - BASE (GRADASI SENJANG/SEMI SENJANG ) 0.04 M X 3.50

HRS - BASE LEVELING (GRADASI SENJANG/SEMI SENJANG) 0.04 M X 4.50

ASPAL UNTUK HRS-WC VOLUME HRS - WC X 7%

ASPAL UNTUK HRS-BASE VOLUME HRS - BASE X 6%

ASPAL UNTUK HRS-BASE LEVELLING VOLUME HRS - BASE LEVELLING X 6%

BETON MUTU SEDANG DENGAN fc'=20 Mpa ( K-250 ) 2 BUAH BOX CULVERT
BETON MUTU RENDAH DENGAB fc'=15 Mpa ( K-125 ) 2 BUAH BOX CULVERT

BAJA TULANGAN BJ 24 POLOS 2 BUAH BOX CULVERT

LAPIS PONDASI AGG. KELAS A UTK PEK. MINOR 0.15 M X 3.50

PPN 10 %

JUMLAH DIBULATKAN
AN TAHUN ANGGARAN 2011 (KONTRAK ASAL)
N BTS. KOTA SAMPIT - PALANTARAN / KM.65
Lebar Panjang Volume Satuan Harga Satuan

1.00 Ls 80,231,097.14

M X 12.00 M = x2 36.00 M3 241,270.00

M X 20.00 M = 24.00 M3 602,330.00

M X 20.00 M = 40.00 M3 571,090.00

M X 5,000.00 M = x2 3,000.00 M3 438,340.00

29.25 TON 1,658,780.00

M X 300.00 M = 450.00 M3 222,850.00

M X 2,515.00 M = 14,964.00 Liter 12,145.00

5,400.00 Liter 12,940.00

M X 5,000.00 M = 3,375.00 Liter

M X 3,000.00 M = 2,025.00 Liter

M X 5,000.00 M = x 2,25 1,519.00 Ton 414,180.00

M X 2,515.00 M = x 2,25 792.00 Ton 415,730.00

M X 3,000.00 M = x 2,25 1,215.00 Ton 415,730.00

226.75 Ton 11,850,000.00

106.33 Ton

BASE X 6% 47.52 Ton

BASE LEVELLING X 6% 72.90 Ton

WC DAN BASE X 1%

51.97 M3 1,092,650.00

6.58 M3 845,450.00

6,484.00 KG 17,730.00

M X 2,515.00 M = 1,320.00 M3 601,650.00


AN TAHUN ANGGARAN 2011 (TAMBAHAN 10%)
N BTS. KOTA SAMPIT - PALANTARAN / KM.65
Lebar Panjang Volume Satuan Harga Satuan

1.00 Ls 80,231,097.14

M X 12.00 M = xx 22 36.00 M3 241,270.00

M X 20.00 M = 24.00 M3 602,330.00

M X 20.00 M = 40.00 M3 571,090.00

M X 5,910.00 M = x2 3,546.00 M3 438,340.00


x 2,25 29.25 TON 1,658,780.00

M X 300.00 M = x 2,32 450.00 M3 222,850.00


x 2,25
M X 2,590.00 M = 15,411.00 Liter 12,145.00

6,082.00 Liter 12,940.00

M X 5,910.00 M = 3,989.00 Liter

M X 3,100.00 M = 2,093.00 Liter

M X 5,910.00 M = x 2,25 1,795.00 Ton 414,180.00

M X 2,590.00 M = x 2,25 816.00 Ton 415,730.00

M X 3,100.00 M = x 2,25 1,256.00 Ton 415,730.00

249.97 Ton 11,850,000.00

125.65 Ton

BASE X 6% 48.96 Ton

BASE LEVELLING X 6% 75.36 Ton

51.97 M3 1,092,650.00
6.58 M3 845,450.00

6,484.00 KG 17,730.00

M X 2,590.00 M = 1,360.00 M3 601,650.00


L)

Jumlah Harga

80,231,097.14

8,685,720.00

14,455,920.00

22,843,600.00

1,315,020,000.00

48,519,315.00

100,282,500.00

181,737,780.00

69,876,000.00

629,139,420.00 1518.75

329,258,160.00

505,111,950.00

2,686,987,500.00

393

56,785,020.50

5,563,061.00

114,961,320.00

794,178,000.00
6,963,636,363.64

696,363,636.36

7,660,000,000.00 7,987,795,000

7,660,000,000.00 327,795,000.00

766,000,000.00
%) 8,426,000,000.00

Jumlah Harga

80,231,097.14

8,685,720.00

14,455,920.00

22,843,600.00

1,554,353,640.00

48,519,315.00

100,282,500.00

187,166,595.00

78,701,080.00

743,453,100.00

339,235,680.00

522,156,880.00

2,962,144,500.00

56,785,020.50
5,563,061.00

114,961,320.00

818,244,000.00

7,657,783,028.64
765,778,302.86
8,423,561,331.50
8,423,000,000.00
Baglak Kegiatan : Asam Baru - Km. 65 (Sp. Bangkal) - Bts. Kota Sampit Nomor Kontrak : HK. 02.03/SNVT-WIL.I.PPK.05/17

Nama Paket : Pemeliharaan Berkala Jalan Km. 65 (Sp. Bangkal) - Bts. Kota Sampit Tanggal Kontrak : 10 Juni 2011
Nilai Kontrak : Rp. 7.660.000.000,00 Waktu Pelaksanaan : 180 (Seratus Delapan Puluh) Hari Kalender

Kontraktor : PT. TRI DHARMA MULIA Rencana PHO : 11 Desember 2011

Konsultan : PT. RANCANGTAMA BANGUNMANDIRI INDRACITRA Rencana FHO : 08 Juni 2012

Tahun Anggaran : 2011

KONTRAK ASAL ADDENDUM KONTRAK - 01 PENAMBAHAN DANA 10% USUL


No. Item Uraian Satuan Harga Satuan (Rp) Total KONTRAK TAMBAH Ket.
Volume Total Harga (Rp) Bobot (%) Volume Total Harga (Rp) Bobot (%) Volume Total Volume
Harga DANA
DIVISI - 1 UMUM
1.2 Mobilisasi Ls 80,231,097.14 1.00 80,231,097.14 1.152 1.00 80,231,097.14 1.048 - - 1.00 80,231,097.14 TETAP

DIVISI - 3 PEKERJAAN TANAH


3.2(2) Timbunan Pilihan M3 241,270.00 36.00 8,685,720.00 0.125 36.00 8,685,720.00 0.113 - - 36.00 8,685,720.00 TETAP

DIVISI - 5 PERKERASAN BERBUTIR


5.1(1) Lapis Pondasi Aggregat Klas A M3 602,330.00 24.00 14,455,920.00 0.208 24.00 14,455,920.00 0.189 - - 24.00 14,455,920.00 TETAP
5.1(2) Lapis Pondasi Aggregat Klas B M3 571,090.00 40.00 22,843,600.00 0.328 40.00 22,843,600.00 0.298 - - 40.00 22,843,600.00 TETAP
5.1(3) Lapis Pondasi Aggregat Klas S M3 438,340.00 3,000.00 1,315,020,000.00 18.884 3,546.00 1,554,353,640.00 20.298 546.00 239,333,640.000 3,546.00 1,554,353,640.00 BERTAMBAH
Skh 5.6(1a) Semen untuk CTRB Ton 1,658,780.00 29.25 48,519,315.00 0.697 29.25 48,519,315.00 0.634 - - 29.25 48,519,315.00 TETAP
Skh 5.6(1b) Lapis Cement Trated Recycler Base (CTRB) M3 222,850.00 450.00 100,282,500.00 1.440 450.00 100,282,500.00 1.310 - - 450.00 100,282,500.00 TETAP

DIVISI - 6 PERKERASAN ASPAL


6.1(1) (a) Lapis Resap Pengikat - Aspal Cair Ltr 12,145.00 14,964.00 181,737,780.00 2.610 15,411.00 187,166,595.00 2.444 447.00 5,428,815.000 15,411.00 187,166,595.00 BERTAMBAH
6.1(2) (a) Lapis Perekat - Aspal Cair Ltr 12,940.00 5,400.00 69,876,000.00 1.003 6,082.00 78,701,080.00 1.028 682.00 8,825,080.000 6,082.00 78,701,080.00 BERTAMBAH
6.3 (3a) Lataston Lapis Aus(HRS-WC) Gradasi senjang/semi senjang) Ton 414,180.00 1,519.00 629,139,420.00 9.035 1,795.00 743,453,100.00 9.708 276.00 114,313,680.000 1,795.00 743,453,100.00 BERTAMBAH
6.3 (4a) Lataston Lapis Pondasi(HRS-Base) Gradasi senjang/semi senjang) Ton 415,730.00 792.00 329,258,160.00 4.728 816.00 339,235,680.00 4.430 24.00 9,977,520.000 816.00 339,235,680.00 BERTAMBAH
6.3 (4b) Lataston LapPon Perata(HRS-Base) Gradasi senjang/semi senjang) Ton 415,730.00 1,215.00 505,111,950.00 7.254 1,256.00 522,156,880.00 6.819 41.00 17,044,930.000 1,256.00 522,156,880.00 BERTAMBAH
6.3.8 Aspal Ton 11,850,000.00 226.75 2,686,987,500.00 38.586 249.97 2,962,144,500.00 38.681 23.22 275,157,000.000 249.97 2,962,144,500.00 BERTAMBAH

DIVISI - 7 STRUKTUR
7.1(7) Beton Mutu Sedang Dengan Fc=20 Mpa (K-250) M3 1,092,650.00 51.97 56,785,020.50 0.815 51.97 56,785,020.50 0.742 - - 51.97 56,785,020.50 TETAP
7.1(10) Beton Mutu Rendah Dengan Fc=10 Mpa (K-125) M3 845,450.00 6.58 5,563,061.00 0.080 6.58 5,563,061.00 0.073 - - 6.58 5,563,061.00 TETAP
7.3(1) Baja Tulangan Bj-24 Polos Kg 17,730.00 6,484.00 114,961,320.00 1.651 6,484.00 114,961,320.00 1.501 - - 6,484.00 114,961,320.00 TETAP

DIVISI - 8 PENGEMBALIAN KODISI DAN PEKERJAAN MINOR


8.1(1) Lapis Pondasi Aggregat Klas A untuk pekerjaan minor M3 601,650.00 1,320.00 794,178,000.00 11.405 1,360.00 818,244,000.00 10.685 40.00 24,066,000.000 1,360.00 818,244,000.00 BERTAMBAH

A Jumlah Harga Pekerjaan (termasuk biaya umum dan keuntungan) 6,963,636,363.64 100.00 7,657,783,028.64 100.00 694,146,665.00 7,657,783,028.64
B Pajak Pertambahan Nilai (PPN) = 10% x (A) 696,363,636.36 765,778,302.86 69,414,666.50 765,778,302.86
C Jumlah Total Pekerjaan = (A + B) 7,660,000,000.00 8,423,561,331.50 763,561,331.50 8,423,561,331.50
D DIBULATKAN 7,660,000,000.00 8,423,000,000.00 8,423,000,000.00

10,094,848,000.00
(1,671,286,668.50)
9,177,134,900.00 290,267.39
8,342,849,909.09
DAFTAR KUANTITAS DAN HARGA
TABEL. 7. BALANCE BUDGET
: PPK - 05 Batas Kota Sampit + Jalan Dalam Kota - palantaran/Km. 6 Nomor Kontrak : HK. 02.03/SNVT-WIL.I.PPK.05/17

: Pemeliharaan Berkala Jalan Batas Kota Sampit - Pelantaran/Km 65 Tanggal Kontrak : 10 Juni 2011
: Rp. 7.660.000.000,00 Waktu Pelaksanaan : 180 (Seratus Delapan Puluh) Hari Kalender

: PT. TRI DHARMA MULIA Rencana PHO : 11 Desember 2011

: PT. RANCANGTAMA BANGUNMANDIRI INDRACITRA Rencana FHO : 08 Juni 2012

Tahun Anggaran : 2011

Harga KONTRAK AWAL PERUBAHAN VOLUME ADDENDUM ( CC0 1 )


Uraian Satuan Satuan (Rp) TAMBAH KURANG Ket.
Volume Total Harga (Rp) Bobot (%) Jumlah Harga Jumlah Harga Volume Total Harga (Rp) Bobot (%)
Volume Volume
(Rp) (Rp)
DIVISI - 1 UMUM
Mobilisasi Ls 80,231,097.14 1.00 80,231,097.14 1.152 1.00 80,231,097.14 1.152 TETAP

DIVISI - 3 PEKERJAAN TANAH


Timbunan Pilihan M3 241,270.00 36.00 8,685,720.00 0.125 104.25 25,152,397.50 140.25 33,838,117.50 0.486 BERTAMBAH

DIVISI - 5 PERKERASAN BERBUTIR


Lapis Pondasi Aggregat Klas A M3 602,330.00 24.00 14,455,920.00 0.208 970.00 584,260,100.00 994.00 598,716,020.00 8.598 BERTAMBAH

Lapis Pondasi Aggregat Klas B M3 571,090.00 40.00 22,843,600.00 0.328 40.00 22,843,600.00 0.328 TETAP

Lapis Pondasi Aggregat Klas S M3 438,340.00 3,000.00 1,315,020,000.00 18.884 122.33 53,621,873.45 2,877.67 1,261,398,126.55 18.114 BERKURANG

Semen untuk CTRB Ton 1,658,780.00 29.25 48,519,315.00 0.697 36.27 60,163,950.60 65.52 108,683,265.60 1.561 BERTAMBAH

Lapis Cement Trated Recycler Base (CTRB) M3 222,850.00 450.00 100,282,500.00 1.440 450.00 100,282,500.00 1.440 TETAP

DIVISI - 6 PERKERASAN ASPAL


Lapis Resap Pengikat - Aspal Cair Ltr 12,145.00 14,964.00 181,737,780.00 2.610 5,839.55 70,921,334.75 9,124.45 110,816,445.25 1.591 BERKURANG

Lapis Perekat - Aspal Cair Ltr 12,940.00 5,400.00 69,876,000.00 1.003 382.71 4,952,267.40 5,017.29 64,923,732.60 0.932 BERKURANG

Lataston Lapis Aus(HRS-WC) Gradasi senjang/semi senjang) Ton 414,180.00 1,519.00 629,139,420.00 9.035 1,519.00 629,139,420.00 9.035 TETAP

Lataston Lapis Pondasi(HRS-Base) Gradasi senjang/semi senjang) Ton 415,730.00 792.00 329,258,160.00 4.728 792.00 329,258,160.00 4.728 TETAP

Lataston LapPon Perata(HRS-Base) Gradasi senjang/semi senjang) Ton 415,730.00 1,215.00 505,111,950.00 7.254 1,215.00 505,111,950.00 7.254 TETAP

Aspal Ton 11,850,000.00 226.75 2,686,987,500.00 38.586 226.75 2,686,987,500.00 38.586 TETAP

Bahan Pengisi (Filer) Tambahan (Semen) Ton 1,658,780.00 15.19 25,196,868.20 15.19 25,196,868.20 0.362 ITEM BARU

Bahan Anti Pengelupasan (Anti Striping Agent) Kg 150,000.00 265.83 39,873,750.00 265.83 39,873,750.00 0.573 ITEM BARU

DIVISI - 7 STRUKTUR
Beton Mutu Sedang Dengan Fc=20 Mpa (K-250) M3 1,092,650.00 51.97 56,785,020.50 0.815 12.79 13,979,364.10 39.18 42,805,656.40 0.615 BERKURANG

Beton Mutu Rendah Dengan Fc=10 Mpa (K-125) M3 845,450.00 6.58 5,563,061.00 0.080 0.15 125,126.60 6.43 5,437,934.40 0.078 BERKURANG

Baja Tulangan Bj-24 Polos Kg 17,730.00 6,484.00 114,961,320.00 1.651 420.00 7,446,600.00 6,064.00 107,514,720.00 1.544 BERKURANG

DIVISI - 8 PENGEMBALIAN KODISI DAN PEKERJAAN MINOR


Lapis Pondasi Aggregat Klas A untuk pekerjaan minor M3 601,650.00 1,320.00 794,178,000.00 11.405 970.00 583,600,500.00 350.00 210,577,500.00 3.024 BERKURANG

Jumlah Harga Pekerjaan (termasuk biaya umum dan keuntungan) 6,963,636,363.64 100.00 734,647,066.30 734,647,066.30 6,963,636,363.64 100.00
Pajak Pertambahan Nilai (PPN) = 10% x (A) 696,363,636.36 696,363,636.36
Jumlah Total Pekerjaan = (A + B) 7,660,000,000.00 7,660,000,000.00
DIBULATKAN 7,660,000,000.00 7,660,000,000.00

Sampit, Juli 2011


Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :
PPK-05 Batas Kota Sampit + Konsultan Supervisi Kontrktor
Jalan Dalam Kota - Palantaran/Km. 65 PT. Rancangtama Bangunmandiri Indracitra. PT. Tri Dharma Mulia

EDY SUTANTO, ST Ir. SARTONO IRWAN WIRIADI


NIP : 110059391 Site Engineering Direktur utama
Baglak Kegiatan : Asam Baru - Km. 65 (Sp. Bangkal) - Bts. Kota Sampit Nomor Kontrak : HK. 02.03/SNVT-WIL.I.PPK.05/17

Nama Paket : Pemeliharaan Berkala Jalan Km. 65 (Sp. Bangkal) - Bts. Kota Sampit Tanggal Kontrak : 10 Juni 2011
Nilai Kontrak : Rp. 7.660.000.000,00 Waktu Pelaksanaan : 180 (Seratus Delapan Puluh) Hari Kalender

Kontraktor : PT. TRI DHARMA MULIA Rencana PHO : 11 Desember 2011

Konsultan : PT. RANCANGTAMA BANGUNMANDIRI INDRACITRA Rencana FHO : 08 Juni 2012

Tahun Anggaran : 2011

ADDENDUM KONTRAK - 01 ADDENDUM KONTRAK - 02 PENAMBAHAN DANA 10% USUL


No. Item Uraian Satuan Harga Satuan (Rp) Total KONTRAK TAMBAH Ket.
Volume Total Harga (Rp) Bobot (%) Volume Total Harga (Rp) Bobot (%) Volume Total Volume
Harga DANA
DIVISI - 1 UMUM
1.2 Mobilisasi Ls 80,231,097.14 1.00 80,231,097.14 1.163 1.00 80,231,097.14 1.076 - - 1.00 80,231,097.14 TETAP

DIVISI - 3 PEKERJAAN TANAH


3.2(2) Timbunan Pilihan M3 241,270.00 140.25 33,838,117.50 0.491 140.25 33,838,117.50 0.454 - - 140.25 33,838,117.50 TETAP

DIVISI - 5 PERKERASAN BERBUTIR


5.1(1) Lapis Pondasi Aggregat Klas A M3 602,330.00 994.00 598,716,020.00 8.679 994.00 598,716,020.00 8.031 - - 994.00 598,716,020.00 TETAP
5.1(2) Lapis Pondasi Aggregat Klas B M3 571,090.00 40.00 22,843,600.00 0.331 40.00 22,843,600.00 0.306 - - 40.00 22,843,600.00 TETAP
5.1(3) Lapis Pondasi Aggregat Klas S M3 438,340.00 2,877.67 1,261,398,126.55 18.285 2,877.67 1,261,398,126.55 16.919 - - 2,877.67 1,261,398,126.55 BERTAMBAH
Skh 5.6(1a) Semen untuk CTRB Ton 1,658,780.00 65.52 108,683,265.60 1.575 65.52 108,683,265.60 1.458 - - 65.52 108,683,265.60 TETAP
Skh 5.6(1b) Lapis Cement Trated Recycler Base (CTRB) M3 222,850.00 450.00 100,282,500.00 1.454 450.00 100,282,500.00 1.345 - - 450.00 100,282,500.00 TETAP

DIVISI - 6 PERKERASAN ASPAL


6.1(1) (a) Lapis Resap Pengikat - Aspal Cair Ltr 12,145.00 9,124.45 110,816,445.25 1.606 15,411.00 187,166,595.00 2.510 6,286.55 76,350,149.750 15,411.00 187,166,595.00 BERTAMBAH
6.1(2) (a) Lapis Perekat - Aspal Cair Ltr 12,940.00 5,017.29 64,923,732.60 0.941 6,082.00 78,701,080.00 1.056 1,064.71 13,777,347.400 6,082.00 78,701,080.00 BERTAMBAH
6.3 (3a) Lataston Lapis Aus(HRS-WC) Gradasi senjang/semi senjang) Ton 414,180.00 1,519.00 629,139,420.00 9.120 1,795.00 743,453,100.00 9.972 276.00 114,313,680.000 1,795.00 743,453,100.00 BERTAMBAH
6.3 (4a) Lataston Lapis Pondasi(HRS-Base) Gradasi senjang/semi senjang) Ton 415,730.00 792.00 329,258,160.00 4.773 816.00 339,235,680.00 4.550 24.00 9,977,520.000 816.00 339,235,680.00 BERTAMBAH
6.3 (4b) Lataston LapPon Perata(HRS-Base) Gradasi senjang/semi senjang) Ton 415,730.00 1,215.00 505,111,950.00 7.322 1,256.00 522,156,880.00 7.004 41.00 17,044,930.000 1,256.00 522,156,880.00 BERTAMBAH
6.3.8 Aspal Ton 11,850,000.00 226.75 2,686,987,500.00 38.950 249.97 2,962,144,500.00 39.732 23.22 275,157,000.000 249.97 2,962,144,500.00 BERTAMBAH

DIVISI - 7 STRUKTUR
7.1(7) Beton Mutu Sedang Dengan Fc=20 Mpa (K-250) M3 1,092,650.00 39.18 42,805,656.40 0.621 51.97 56,785,020.50 0.762 12.79 13,979,364.100 51.97 56,785,020.50 TETAP
7.1(10) Beton Mutu Rendah Dengan Fc=10 Mpa (K-125) M3 845,450.00 6.43 5,437,934.40 0.079 6.58 5,563,061.00 0.075 0.15 125,126.600 6.58 5,563,061.00 TETAP
7.3(1) Baja Tulangan Bj-24 Polos Kg 17,730.00 6,064.00 107,514,720.00 1.559 6,064.00 107,514,720.00 1.442 - - 6,064.00 107,514,720.00 TETAP

DIVISI - 8 PENGEMBALIAN KODISI DAN PEKERJAAN MINOR


8.1(1) Lapis Pondasi Aggregat Klas A untuk pekerjaan minor M3 601,650.00 350.00 210,577,500.00 3.052 410.00 246,676,500.00 3.309 60.00 36,099,000.000 410.00 246,676,500.00 BERTAMBAH

A Jumlah Harga Pekerjaan (termasuk biaya umum dan keuntungan) 6,898,565,745.44 100.00 7,455,389,863.29 100.00 556,824,117.85 7,455,389,863.29
B Pajak Pertambahan Nilai (PPN) = 10% x (A) 689,856,574.54 745,538,986.33 55,682,411.79 745,538,986.33
C Jumlah Total Pekerjaan = (A + B) 7,588,422,319.98 8,200,928,849.62 612,506,529.64 8,200,928,849.62
D DIBULATKAN 7,588,422,319.98 8,423,000,000.00 8,423,000,000.00

10,094,848,000.00
(1,893,919,150.38)
9,177,134,900.00 290,267.39
8,342,849,909.09