RENCANA 

ANGGARAN  BIAYA (RAB)


MASJID " AL IKHLAS " DSN KRAJAN RT 001 RW 004 DS TEGALHARJO
KECAMATAN GLENMORE

Bidang :
Kegiatan :

Waktu pelaksanaan :

Rincian pendanaan

NO. URAIAN PEKERJAAN VOLUME

1 2 3
l BAHAN
1 Pasir kali 1
2 Pasir cor 1
3 Batu split 2/3 1
4 Batu bata 5000
5 Semen gresik ( 50 kg ) 84
6 besi diameter 10 mm 12m 165
7 besi diameter 6 mm 12m 120
8 Bendrat 10
9 Kayu Kruing 8x12x4m 10
10 Kayu Kruing 6x12x4m 20
11 Kayu Kruing usuk 5x7x4m 20
12 Kayu Kruing reng 2x3x4m 50
13 Kayu Begisting 48
14 Genteng Karang Pilang 1940
15 Genteng Wuwung 48
16 Batu Alam Andesit 10
17 Keramik Dinding 10
18 Keramik Lantai 36
19 Keramik Lantai Kamar Mandi 10
20 Closet 1
21 Paku Dur Beton 5
22 Paku Usuk 5
23 Paku Reng 5
24 Pintu Kamar Mandi 1
25 Resplang 10
26 Cat 25kg Vinilex 2
27 Pintu Kayu + Kusen 1
28 Kunci Pintu 1
29 Kusen dan Daun Jendela 3
30 Grendel dan penyangga Jendela 3
31 KalsiBoard Ling 4,5 mm (1.220 x 2.440 mm) 25
32 Gypsum Plafon 48
33 Instalasi Listrik + Lampu 1
34 Bambu 40
35 Ongkos Kerja 1

Jumlah Total :

Page 1
YA (RAB)
RW 004 DS TEGALHARJO
RE

Pelaksanaan Pembangunan Masjid Al Ikhlas


Pembangunan Kantor Sekretariat
Masjid Al Ikhlas Jl RS Bhakti Husada Krikilan
Akhir Tahun 2022

HARGA
UNIT JUMLAH (Rp)
SATUAN  (Rp)
4 5 6

truk 800,000 800,000


truk 1,400,000 1,400,000
truk 1,300,000 1,300,000
biji 800 4,000,000
sak 56,000 4,704,000
lonjor 77,750 12,828,750
lonjor 28,750 3,450,000
kg 26,500 265,000
btg 211,500 2,115,000
btg 69,000 1,380,000
btg 39,500 790,000
btg 11,000 550,000
btg 14,750 708,000
biji 7,500 14,550,000
biji 7,000 336,000
m2 125,000 1,250,000
dus 69,900 699,000
dus 69,900 2,516,400
m2 69,000 690,000
biji 598,800 598,800
kg 35,900 179,500
kg 9,650 48,250
kg 5,000 25,000
biji 675,000 675,000
lb 75,000 750,000
galon 635,000 1,270,000
set 3,000,000 3,000,000
set 160,000 160,000
set 560,000 1,680,000
set 48,000 144,000
lembar 86,550 2,163,750
m 48,000 2,304,000
set 1,000,000 1,000,000
batang 18,000 720,000
kontrak 17,262,613 17,262,613

86,313,063

Page 2
RENCANA  ANGGARAN  BIAYA (RAB)
MASJID " AL IKHLAS " DSN KRAJAN RT 001 RW 004 DS TEGALHAR
KECAMATAN GLENMORE

Bidang :
Kegiatan :

Waktu pelaksanaan :

Rincian pendanaan

NO. URAIAN PEKERJAAN VOLUME

1 2 3
l PEKERJAAN PERSIAPAN
1 Bowplank 1
2 Pek pembersihan lahan 1
II BAHAN
1 Semen Gersik 90
2 batu kali 1
3 Pasir Beton 25
4 Pasir Urug 5
5 Batu 2/3 cm (split) 10
6 Besi beton diameter 12mm - 12m 175
7 Kawat Beton (Bendrat) 10
8 besi beton diameter 6mm - 12m 130
9 Besi Ulir 10
10 Kayu bagisting 50
11 Bambu penyanggah cor 48
12 Paku Campur 10
13 Plastik untuk Alas Cor Beton 34
14 Batu bata 7,680
15 Batu Alam Andesit 20x40 cm 18
16 Cat Dasar 2
17 Cat Kilat Dinding 2
18 Amplas 3
19 Alat Bantu (Kuas) 2
20 Plafon KalsiBoard Ling 4,5 mm (1.220 x 2.440 mm) 30
21 Cat 25kg Vinilex 2
22 Keramik Dinding 10
23 Keramik Lantai 40
24 Gypsum Plafon 48
25 Instalasi Listrik + Lampu 1
26 Ongkos Kerja 1

Jumlah Total:

Page 3
YA (RAB)
RW 004 DS TEGALHARJO
RE

Pelaksanaan Pembangunan Masjid Al Ikhlas


Pembangunan TERAS
Masjid Al Ikhlas Jl RS Bhakti Husada Krikilan
Akhir Tahun 2022

HARGA SATUAN 
UNIT JUMLAH (Rp)
(Rp)
4 5 6

kerja 500,000 500,000


kerja 1,000,000 1,000,000

sak 60,500 5,445,000


rit 800,000 800,000
M3 125,000 3,125,000
M3 110,000 550,000
M3 500,000 5,000,000
Btg 113,450 19,853,750
Kg 25,000 250,000
btg 28,600 3,718,000
lonjor 162,000 1,620,000
Btg 17,000 850,000
Btg 18,000 864,000
Kg 35,000 350,000
M2 5,000 170,000
Bh 800 6,144,000
M2 100,000 1,800,000
Liter 50,000 100,000
Liter 65,000 130,000
Lbr 5,000 15,000
Bh 20,000 40,000
lbr 86,550 2,596,500
galon 635,000 1,270,000
dus 69,900 699,000
dus 69,900 2,796,000
m 48,000 2,304,000
set 1,000,000 1,000,000
kontrak 15,747,563 15,747,563

78,737,813

Page 4
RENCANA  ANGGARAN  BIAYA (RAB)
MASJID " AL IKHLAS " DSN KRAJAN RT 001 RW 004 DS TEGALHARJO
KECAMATAN GLENMORE

Bidang  :
Kegiatan  :

Waktu Pelaksanaan  :

Rincian Pendanaan
NO. URAIAN PEKERJAAN VOLUME
1 2 3
I PEKERJAAN PERSIAPAN
1 bowplank 1
2 pembersihan lapangan 1
3 pebuatan nama proyek 1
4 galian tanah 15
5 urukan tanah kembali 1
II BAHAN
1 Semen (1 zak=50 kg) 100
2 Pasir Beton 6
3 Pasir Urug 5
4 batu kali 2
5 Batu 2/3 cm (kerikil) 5
6 batu merah 3000
7 Besi beton polos dia 12 mm - 12m 36
8 Kawat Beton (Bendrat) 3
9 Papan Mal uk 2/18 cm - 4m 8
10 Kayu Usuk 5x7x4m 10
11 Kayu cerucuk untuk perancah 10
12 Kayu 7 x 15 - 6m 8
13 keramik dinding motif batu alam ukuran 50 cm 10
14 Stenles pagar panjang 9mx2(kanan kiri) 2
15 pintu stenles gapura panjang sliding 6 m 1
16 Kubah Gapura 1
17 Kabel Engkel 1
18 Lampu Led Taman 6
19 Paku Campur 10
20 Batu Alam Andesit 20x40 cm 18
21 Cat Dasar 2
22 Cat Kilat Dinding 2
23 Amplas 3
24 Alat Bantu (Kuas) 2
Ongkos Kerja 1
Jumlah Total :

NO RINCIAN PENDANAAN GLOBAL


I PEMBANGUNAN TERAS
II PEMBANGUNAN KANTOR SEKRETARIAT
III PEMBANGUNAN GAPURA
TOTAL RINCIAN PENDANAAN

Page 5
RAB)
004 DS TEGALHARJO

Pelaksanaan Pembangunan Masjid Al Ikhlas


Pembangunan GAPURA
Masjid Al Ikhlas Jl RS Bhakti Husada Krikilan
Tahun 2023

HARGA SATUAN 
UNIT JUMLAH (Rp)
(Rp)
4 5 6

kerja 500,000 500,000


kerja 1,500,000 1,500,000
set 200,000 200,000
m2 45,000 675,000
500,000 500,000

sak 65,000 6,500,000


M3 125,000 750,000
M3 110,000 550,000
rit 850,000 1,700,000
M3 500,000 2,500,000
biji 800 2,400,000
Btg 113,450 4,084,200
Kg 25,000 75,000
Kpg 40,000 320,000
Btg 40,000 400,000
Btg 7,000 70,000
Btg 200,000 1,600,000
m 125,000 1,250,000
set 7,500,000 15,000,000
set 7,500,000 7,500,000
buah 2,000,000 2,000,000
roll 375,000 375,000
buah 250,000 1,500,000
Kg 35,000 350,000
M2 100,000 1,800,000
Liter 50,000 100,000
Liter 65,000 130,000
Lbr 5,000 15,000
Bh 20,000 40,000
Kontrak 13,596,050 13,596,050
67,980,250

JUMLAH (Rp)
78,737,813
86,313,063
67,980,250
233,031,125