CIVIL ARSITEKTUR
A. TEMPAT WUDHU PRIA
Pemasangan lantao area wudhu
1
Granite tile abu-abu 60 x 60 cm ex. Wisma sehati/elora rockstone black
Pengadaan Dinding granite area wudhu
2
Granite tile putih 60 x 60 cm ex Wisma sehati/verona cararra white
Pemasangan dinding area keran uk. 60 x 5 x 100 cm
3 Granite tile hitam 30 x 60 cm ex Wisma sehati/ sehati galaxy black
imdirect lamp + cup warm white
Pengadaan tempat wudhu duduk Uk. 40 x 30 x 40 cm
4
Granite tile wood texture alliya atlas natural mate 20 x 120 ex wisma sehati + cat hitam
Pekerjaan cat dinding
5
ex. Jotun
Pengadaam & pemasangam Ambelan penyimpanan barang
6 Hollow 2/2 + Pervorated Fin. Powder Coating
Foamboard 15mm, fin.HPL, Indirect Lamp + cup warm white
HARGA SATUAN TOTAL HARGA
JUMLAH CATATAN
(RP) (RP)
1 ls
6,500,000 Rp6,500,000
Rp 19.750.000
64,000 Rp662,400
978,500 Rp10,763,500
735,000 Rp8,820,000
2,500,000 2,500,000
2,000,000 Rp2,000,000
475,000 Rp304,000
220,000 Rp2,200,000
TOTAL Rp62,397,555
2,000,000 Rp942,000
2,200,000 Rp1,425,600
120,000 Rp1,656,000
85,500 Rp3,283,200
65,000 Rp2,496,000
2,500,000 Rp1,177,500
475,000 Rp6,384,000
57,500 Rp6,166,300
425,000 Rp26,171,500
435,000 Rp1,740,000
NO KODE
11
12
13
14
15
16
17
18
19
20
21
22
23
C. TOILET PRIA
4
JUMLAH
ITEM PEKERJAAN
Pemasangan lantai area wudhu 28,38 m2
Granite tile abu-abu 60x60 cm ex. Wisma sehati/ elora rockstone black
Pengadaan tempat wudhu duduk Uk. 40 x 30 x 40 cm 4,00 m2
Granite tile wood texture alliya atlad natural mate 20 x 120 ec. wisma sehati + cat hitam
Pengadaan & pemasangan Ambalan penyimpanan barang 7,34 m2
Hallow 2/2 + pervorated fin. powder coating
Foamboard 15mm, fin.HPL, indirect lamp + cup warm white
Pekerjaan plafond 20,05 m2
Gypsum ec. Jayaboard 9 mm + coumpond
Hollow Galvanize 2×4, 4x4
Pengecatan Celling 30,48 m2
cat ex. Dulux pentalite
Pekerjaan & pemasangan lampi downlight + instalasi 8 m2
Pengadaan & pembuatan Grill Pembangunan air 7,34 m'
Stainless
Pengadaan & pemasangan pintu kamar mandi UPVC 2,00 unit
Pengadaan keran wudhu 9,00 unit
ex. Toto
Pengadaan Keran air taman 2,00 unit
ex. Onda
Pengadaan & pemasangan pintu kobol 2,00 unit
Foamboard uk. 1,7 × 1
Pembaharuan Instalasi Air bersih 1,00 ls
Pembaharuam Instalasi Air kotor 1,00 ls
PRIA
Pemasangan lantai area wudhu 15,09 m2
Granite tile putih 60 x 60 cm ec Wisma sehati/ elora rockstone black
Pengadaan Dinding granite area wudhu 34,72 m3
Granite tile putih 60 x 60 cm ex Wisma sehati / verona cararra white
Pekerjaan penebalan dinding ketinggian 1,5M 4,05 unit
Bata hevel tebal 100 mm
Mortar semen pasang hebel ex. MU 380/setara
Pekerjaan pengecatan dinding 31,44 m2
ex. Jotun
HARGA SATUAN TOTAL HARGA
CATATAN
(RP) (RP)
425,000 Rp12,061,500
655,000 Rp2,620,000
225,000 Rp1,651,500
185,000 Rp3,709,250
65,000 Rp1,981,200
250,000 Rp2,000,000
1,068,363 Rp7,841,784
1,435,000 Rp2,870,000
588,000 Rp5,292,000
420,000 Rp840,000
1,700,000 Rp3,400,000
2,500,000 Rp2,500,000
2,000,000 Rp2,000,000
TOTAL Rp100,209,000
425,000 Rp6,413,000
425,000 Rp14,756,000
120,000 Rp486,000
71,875 Rp2,259,750
NO KODE ITEM PEKERJAAN
5 Pengadaan & pemasangan cover Pompa + Storage
Multiplek 9mm fin.hpl
6 Pengadaan & pemasangan closet jongkok
Ex. Toto
7 Pengadaan & pemasangan closet duduk
Ex. Toto
8 Pengadaan & pemasamgan partisi Pvc
Ex Phonelic termasuk Asesoris
9 Pekerjaan Plafond
Gypsum ex. jayaboard 9 mm + coumpond
Hollow Galvanize 2x4, 4x4
10 Pekerjaan Cat Plafon
ex. Dulux pentalite
11 Pekerjaan & pemasangam lampu downlight + instalasi
12 Pengadaan & pembuatan Grill apembuangan air
Stainless
13 Pekerjaan pembuatan bak cuci kaki
Batu andesit
14 Pengadaan sensor gerak
Sensor geram dan pompa
15 Pengadaan Instalasi air bersih
16 Pengadaan Instalasi Air kotor
1 2,250,000 Ro 2.250.000
TOTAL Rp88,807,000
8
9
10
11
12
2
3
4
7
8
10
11
2
ITEM PEKERJAAN JUMLAH
HALAT OUTDOOR
Penggantian Lantai 282,01 m3
vinyl tv-014 natural beach uk.150 x 90, ex taco (termasuk step nosing)
Pemasangan list lantai untuk batas 23,47 m2
HARGA SATUAN
TOTAL HARGA (RP) CATATAN
(RP)
1,068,363 Rp5,021,306
125,000 Rp236,250
57,500 Rp1,345,500
445,000 Rp2,670,000
2,500,000 Rp2,500,000
2,000,000 Rp2,000,000
TOTAL Rp31,395,750
100,000 Rp1,266,000
65,000 Rp1,645,800
55,000 Rp1,392,600
1,575,000 Rp14,175,000
325,000 Rp3,402,750
1,068,363 Rp7,692,214
125,000 Rp708,750
57,500 Rp1,455,900
445,000 Rp4,005,000
2,500,000 Rp2,500,000
2,000,000 Rp2,000,000
TOTAL Rp40,244,014
300,000 Rp84,603,000
300,000 Rp70,410,000
NO KODE ITEM PEKERJAAN JUMLAH
REKAPITULASI
I SUB TOTAL PEKERJAAN PERSIAPAN & PEMBONGKARAN
A TEMPAT WUDHU PRIA
B TEMPAT WUDHU DAN TOILET WANITA
C TOILET PRIA
D TEMPAT WUDHU PRIA BARU
E TEMPAT WUDHU TAMBAHAN 3 TITIK
F AREA SHALAT OUTDOR
G AREA KOLAM
GRAND TOTAL
HARGA SATUAN (RP) TOTAL HARGA (RP) CATATAN
Rp19,750,000
Rp62,397,000
Rp100,209,000
Rp88,807,000
Rp31,395,000
Rp40,244,000
Rp256,000,000
Rp14,000,000
GRAND TOTAL Rp612,802,000