Rab-Sdm 9 BJM
Rab-Sdm 9 BJM
226,424,665.00
134,516,720.00
47,987,500.00
RENCANA ANGGARAN BIAYA
1 Kunci pintu utama kipas ex. Solid lt.1 bh 8.00 750,000.00 6,000,000.00
2 Kunci pintu km/wc ex. Solid lt.2 bh 2.00 750,000.00 1,500,000.00
3 Engsel pintu 5 " ex.solid/gradino lt.1,2,3 bh 11.00 125,000.00 1,375,000.00
4 Engsel jendela 3 " ex. Solid lt.2 bh 33.00 95,000.00 3,135,000.00
5 Grendel jendela ex. solid/gradino lt.1,2,3 bh 66.00 35,000.00 2,310,000.00
6 Kait angin jendela ex. solid/gradino lt.2 bh 33.00 35,000.00 1,155,000.00
7 Pegangan jendela ex. solid/gradino lt.1,2,3 bh 33.00 35,000.00 1,155,000.00
16,630,000.00
16,525,000.00
RENCANA ANGGARAN BIAYA
X. PEK. SANITASI
22,463,260.00
1 Cat Dinding Dalam dan kolom lt.1 Profan m² 208.00 54,635.00 11,364,080.00
2 Cat Dinding Dalam lt.2 profan m² 318.00 66,270.00 21,073,860.00
4 Cat Dinding Luar lt.2 jotun m² 284.75 70,270.00 20,009,382.50
7 Cat Plafond dak dana brite lt.1 m² 126.00 37,270.00 4,696,020.00
8 Cat Plafond luar dana brite lt.2,3 m² 212.00 37,270.00 7,901,240.00
10 Deco kusen pintu lt.1,2,3 m' 45.50 56,000.00 2,548,000.00
12 Deco kusen jendela lt.1,2,3 m' 217.00 56,000.00 12,152,000.00
13 Deco pintu lt.1,2,3 bh 10.00 800,000.00 8,000,000.00
14 Deco jendela lt.1,2,3 bh 33.00 850,000.00 28,050,000.00
15 Cat lisplank m' 64.00 70,270.00 4,497,280.00
120,291,862.50
1 Railling Tangga dan Pagar Balkon besi tempa clasik m1 18.00 850,000.00 15,300,000.00
2 Tandon plastik 1100 L ex. bh 1.00 3,500,000.00 3,500,000.00
3 Tangga naik ke atas tandon m2 1.00 1,250,000.00 1,250,000.00
20,050,000.00
Jumlah 875,982,143.75
Pembulatan 1,750,000,000.00
RENCANA ANGGARAN BIAYA
X PEK. CAT-CATAN
1 Cat Dinding Dalam dan kolom lt.1 Nifon m²
2 Cat Dinding Luar lt.1 Nifon m²
4 Cat Plafond Nifon brite lt.1 m²
7 Cat Plafond luar Nifon lt.1 m²
8 Cat kusen pintu lt.1 m'
10 Cat kusen jendela lt.1 m'
12 Cat pintu lt.1 bh
13 Cat jendela lt.1 bh
1 Pembersihan galian tanah dan sisa bongkaran exsisting ls 1.00 8,200,000.00 8,200,000.00 Terealisasi
2 Bowplank m2 150.00 25,000.00 3,750,000.00 Terealisasi
3 Jembatan darurat pintu masuk ls 1.00 4,300,000.00 4,300,000.00 Dana Sekolah
4 Gudang Seng 3 x5 ls 1.00 7,600,000.00 7,600,000.00 Belum Terealisasi
5 Pemancangan galam panjang 9m btg 532.00 95,000.00 50,540,000.00 Baru beli Bahan
6 Pemancangan galam panjang 7m btg 1,968.00 75,000.00 147,600,000.00 Bahan Full dan sudah 650 yang terpancang
Total dana yang terpakai 170.430.000