Anda di halaman 1dari 4

REKAPITULASI RENCANA ANGGARAN BIAYA

PROGRAM : PENYEDIAAN DAN PENGEMBANGAN PRASARANA PERTANIAN


KEGIATAN : PEMBANGUNAN PRASARANA PERTANIAN
SUB KEGIATAN : PEMBANGUNAN, REHABILITASI DAN PEMELIHARAAN PRASARANA PERTANIAN LANINNYA
PEKERJAAN : PEMBANGUNAN KOMPARTEMEN DI DESA GERO
LOKASI : KEC. BOAWAE - KAB. NAGEKEO
T.A. : 2021

NO
JUMLAH HARGA
MATA URAIAN PEKERJAAN
(Rp)
ANGAARAN
1 2 3
BAB I PEKERJAAN UMUM DAN PERSIAPAN RP. 3,800,000.00
BAB II PEKERJAAN TANAH DAN PONDASI RP. 12,439,458.69
BAB III PEKERJAAN STRUKTUR RP. 13,652,983.51
BAB IV PEKERJAAN DINDIDNG RP. 10,496,191.71
BAB V PEKERJAAN LANTAI RP. 3,179,281.88
BAB VI PEKERJAAN PINTU BESI DAN MENHOLE RP. 14,000,000.00
BAB VII PEKERJAAN FINISHING DAN PENGECATAN RP. 1,396,387.22
BAB VIII PEKERJAAN RANGKA ATAP, PENUTUP ATAP DAN LISPLANK RP. 9,970,158.09
BAB IX PEKERJAAN PENGADAAN RP. 3,700,000.00

A JUMLAH RP. 72,634,461.10


B PPN (10 % X A) RP. 7,263,446.11
C JUMLAH (A + B) RP. 79,897,907.21
D DIBULATKAN RP. 79,897,907.00
TERBILANG : TUJUH PULUH SEMBILAN JUTA DELAPAN RATUS SEMBILAN PULUH TUJUH RIBU SEMBILAN
RATUS TUJUH RUPIAH
DAFTAR RENCANA ANGGARAN BIAYA
PROGRAM : PENYEDIAAN DAN PENGEMBANGAN PRASARANA PERTANIAN
KEGIATAN : PEMBANGUNAN PRASARANA PERTANIAN
SUB KEGIATAN : PEMBANGUNAN, REHABILITASI DAN PEMELIHARAAN PRASARANA PERTANIAN LANINNYA
PEKERJAAN PEMBANGUNAN KOMPARTEMEN DI DESA GERO
LOKASI : KEC. BOAWAE - KAB. NAGEKEO
T.A. : 2021

NO. HARGA SATUAN SUB TOTAL


MATA URAIAN PEKERJAAN SAT. VOL. PEKERJAAN
ANGG. (RP.) (RP.)
1 2 3 4 5 6
BAB I PEKERJAAN UMUM DAN PERSIAPAN
1 Penyediaan Air Kerja ls 1.00 1,000,000.00 1,000,000.00
2 Pek. Pengukuran, Pemasangan Bouplank dan Patok ls 1.00 500,000.00 500,000.00
3 Papan Nama Proyek ls 1.00 300,000.00 300,000.00
4 Pek. Direksi Keet ls 1.00 1,000,000.00 1,000,000.00
5 Administrasi dan Dokumentasi ls 1.00 1,000,000.00 1,000,000.00

JUMLAH I 3,800,000.00
BAB II PEKERJAAN TANAH DAN PONDASI
1 Galian Pondasi Tanah Biasa m3 27.5200 51,425.00 1,415,216.00
2 Urugan Pasir Dasar Pondasi m3 1.3100 178,970.00 234,450.70
3 Urugan Kembali Tanah Pada Galian Pondasi m3 5.4700 17,141.67 93,764.92
4 Urugan Tanah di bawah Lantai m3 3.4500 130,570.00 450,466.50
5 Urugan Pasir di bawah Lantai m3 1.5300 178,970.00 273,824.10
6 Aanstamping Batu kali m3 4.0700 431,145.00 1,754,760.15
7 Pas. Pondasi Batu Kali 1 PC 5 Psr m3 10.5200 781,081.40 8,216,976.33

JUMLAH II 12,439,458.69
BAB III PEKERJAAN STRUKTUR
1 Beton Bertulang Sloof uk. 15 x 20 cm 1PC 2Psr 3Krl m3 0.91 1,272,961.25 1,158,394.74
Pembesihan Polos Kg 150.90 16,330.67 2,464,297.60
Begesting Slof m2 3.00 212,115.75 636,347.25
2 Beton Kolom Praktis uk. 15 x 15 cm 1PC 2Psr 3Krl m3 0.53 1,272,961.25 674,669.46
Pembesihan Polos Kg 106.50 16,330.67 1,739,216.00
Begesting Kolom m2 2.64 212,115.75 559,985.58
3 Beton Ring Balk uk. 12 x 20 cm 1PC 2Psr 3Krl m3 0.32 1,272,961.25 407,347.60
Pembesihan Polos Kg 51.80 16,330.67 845,928.53
Begesting Balok m2 2.30 304,551.13 700,467.61
4 Beton Kolom Gewel uk. 15 x 15 cm 1PC 2Psr 3Krl m3 0.02 1,272,961.25 25,459.23
Pembesihan Polos Kg 12.72 16,330.67 207,726.08
Begesting Kolom Gewel m2 2.00 304,551.13 609,102.27
5 Beton Balok Gewel uk. 12 x 20 cm 1PC 2Psr 3Krl m3 0.25 1,272,961.25 318,240.31
Pembesihan Polos Kg 20.12 16,330.67 328,573.01
Begesting Balok m2 2.00 304,551.13 609,102.27
6 Beton plat penutup Septitank uk. 1.50 cm x 2.50 cm x 0.12 cm 1PC 2Psr 3Krl m3 0.45 1,272,961.25 572,832.56
Pembesihan Polos Kg 40.00 16,330.67 653,226.67
Begesting plat penutup m2 3.75 304,551.13 1,142,066.75

JUMLAH IV 13,652,983.51
BAB IV PEKERJAAN DINDIDNG
1 Pemasangan 1m2 dinding batu batako pada dinding kandang, saluran dan Septitank (10x20x m2 37.95 116,140.96 4,407,549.29
2 Plesteran Biasa Tbl. 25 mm 1PC 5Psr m2 75.91 52,251.51 3,966,412.31
3 Acian Tembok dan Kolom dengan Semen Mortar m2 75.91 27,957.19 2,122,230.10

JUMLAH V 10,496,191.71
NO. HARGA SATUAN SUB TOTAL
MATA URAIAN PEKERJAAN SAT. VOL. PEKERJAAN
ANGG. (RP.) (RP.)
1 2 3 4 5 6
BAB V PEKERJAAN LANTAI
1 Rabat Beton Lantai 1 PC 3 Psr 5 Krl m3 3.05 1,042,387.50 3,179,281.88
JUMLAH VI 3,179,281.88
BAB VI PEKERJAAN PINTU BESI DAN MENHOLE
1 Pemasangan Pintu Besi Komplit Bh 8.00 1,500,000.00 12,000,000.00
2 Pemasangan Menhole Beton Ukuran 50 x 50 cm Bh 2.00 1,000,000.00 2,000,000.00

JUMLAH VII 14,000,000.00


BAB VII PEKERJAAN FINISHING DAN PENGECATAN
1 Cat Dinding Tembok m2 75.91 18,395.30 1,396,387.22

JUMLAH VIII 1,396,387.22


BAB VIII PEKERJAAN RANGKA ATAP, PENUTUP ATAP DAN LISPLANK
1 Kuda - Kuda Kayu Balok Kls. II uk. 6/12 cm m3 0.16 6,894,734.00 1,103,157.44
2 Gording Kayu Balok Kls. II uk. 6/8 cm m3 0.40 6,306,355.00 2,522,542.00
3 Beugel U Bulat bh 2.00 50,650.00 101,300.00
4 Beugel U Plat bh 1.00 37,650.00 37,650.00
5 Plat Strep bh 2.00 40,650.00 81,300.00
6 Mur Baut Kuda - Kuda bh 4.00 15,650.00 62,600.00
7 Lisplank Papan Kayu Kls. II diprofil Tengah dan Pinggir m1 28.00 79,852.85 2,235,879.80
8 Atap Seng Galvalum BJLS 0,25 mm Warna Biru uk. 80 x 180 cm m2 50.52 69,781.80 3,525,376.54
9 Bubungan Seng Plat BJLS 0,20 mm m1 6.57 45,715.73 300,352.31

JUMLAH X 9,970,158.09
BAB IX PEKERJAAN PENGADAAN
1 Mesin Cuci Kendaraan/ Car Washer Unit 1.00 1,500,000 1,500,000.00
2 Penyemprot Tangan / Hand Spayer Unit 1.00 750,000 750,000.00
3 Papan Whiteboard Ukuran 120 x 240 cm Bh 1.00 750,000 750,000.00
4 Dram Plastik 200 Liter Bh 2.00 350,000 700,000.00
JUMLAH XIV 3,700,000.00
JUMLAH ( I s/d XII ) 72,634,461.10

Anda mungkin juga menyukai