Lama Pekerjaan
Nilai Proyek Nomor Nama Pekerjaan Tanggal Mulai Pekerjaan
(hari)
2019
Oktober - Masa Pelaksanaan Proyek Wednesday, January 1, 2020 822
November - Rp 182,188,010,000 1 Jembatan Suwan Wednesday, January 1, 2020 234
Desember - 2 Jembatan Kati Monday, June 1, 2020 234
- 3 Jembatan Pani 1 Wednesday, January 1, 2020 180
4 Jembatan Pani 2 Sunday, March 1, 2020 180
2020 5 Jembatan Mahne Tuesday, December 1, 2020 234
Januari 4,783,796,694 6 Jembatan Ikang Thursday, October 1, 2020 429
Februari 3,902,380,579
Maret 18,503,247,941
April 8,686,559,983
Mei 10,529,231,610 Masa Pelaksanaan Proyek 822
Juni 10,506,480,097
Juli 19,305,772,938
Agustus 9,945,851,479 Jembatan Suwan 234
September 3,143,191,688
Oktober 17,600,135,793
November 7,451,485,664
Jembatan Kati 234
Desember 13,495,144,248
127,853,278,716
234
429
DIVISI 1. UMUM
Mobilisasi Tuesday, October 1, 2019 31 Thursday, October 31, 2019 196,333,055 196,333,055 196,333,055 196,333,055
Lain-lain Tuesday, October 8, 2019 808 Thursday, December 23, 2021 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561 23,338,561
Demobilisasi Wednesday, December 1, 2021 30 Thursday, December 30, 2021 196,333,055 196,333,055 196,333,055 196,333,055
JEMBATAN SUWAN Friday, November 1, 2019 234 Sunday, June 21, 2020
DIVISI 2. DRAINASE
Pasangan Batu dengan Mortar Saturday, May 23, 2020 21 Friday, June 12, 2020 294,409,907 294,409,907 294,409,907
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
Galian Batu Lunak Friday, November 1, 2019 14 Thursday, November 14, 2019
Galian Struktur dengan Kedalaman 0 - 2 M Friday, November 1, 2019 14 Thursday, November 14, 2019 14,174,213 14,174,213
Galian Struktur dengan Kedalaman 2 - 4 M Friday, November 1, 2019 7 Thursday, November 7, 2019
Galian Struktur dengan Kedalaman 4 - 6 M Friday, November 1, 2019 14 Thursday, November 14, 2019
Timbunan Pilihan dari Sumber Galian Wednesday, November 27, 2019 7 Tuesday, December 3, 2019 2,520,826,426
Penyiapan Badan Jalan Wednesday, November 27, 2019 30 Thursday, December 26, 2019 764,107 764,107 764,107 764,107
DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
Lapis Fondasi Agregat Kelas A Wednesday, November 27, 2019 21 Tuesday, December 17, 2019 244,314,143 244,314,143 244,314,143
Lapis Fondasi Agregat Kelas B Wednesday, November 27, 2019 21 Tuesday, December 17, 2019 349,872,723 349,872,723 349,872,723
DIVISI 7. STRUKTUR 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585 217,850,585
Dinding Sumuran Friday, November 1, 2019 8 Friday, November 8, 2019
Isian Sumuran Fc' 30 Saturday, November 9, 2019 6 Thursday, November 14, 2019
Isian Sumuran (Beton Siklop) Friday, November 15, 2019 12 Tuesday, November 26, 2019
Penulangan + Bekisting + Pengecoran Abutmen 1 Wednesday, November 27, 2019 25 Saturday, December 21, 2019
Penulangan + Bekisting + Pengecoran Abutmen 2 Wednesday, November 27, 2019 25 Saturday, December 21, 2019
Penulangan + Bekisting + Pengecoran Pilar 1 Sunday, December 22, 2019 30 Monday, January 20, 2020
Penulangan + Bekisting + Pengecoran Pilar 2 Sunday, December 22, 2019 30 Monday, January 20, 2020
Masa Umur Beton Tuesday, January 21, 2020 14 Monday, February 3, 2020
Pemasangan Girder 1 + Bekisting + Penulangan + Pengecoran Lantai Tuesday, February 4, 2020 18 Friday, February 21, 2020
Masa Umur Beton Saturday, February 22, 2020 14 Friday, March 6, 2020
Pemasangan Rangka + Bekisting + Penulangan + Pengecoran Lantai Saturday, March 7, 2020 45 Monday, April 20, 2020
Masa Umur Beton Tuesday, April 21, 2020 14 Monday, May 4, 2020
Pemasangan Girder 2 + Bekisting + Penulangan + Pengecoran Lantai Tuesday, May 5, 2020 18 Friday, May 22, 2020
Finishing Saturday, May 23, 2020 30 Sunday, June 21, 2020
Beton struktur, fc '30 MPa
Beton struktur bervolume besar, fc '30 MPa
Beton struktur, fc '20 Mpa
Beton Siklop, fc '15 MPa
Beton, fc '10 Mpa
Baja Tulangan Polos-BjTP 280
Baja Tulangan Sirip BjTS 420A
Penyediaan Baja Struktur Grade 250 (Kuat Leleh 250 Mpa)
Pemasangan Baja Struktur
Penyediaan Struktur Jembatan Rangka Baja Standar panjang 60 m
Pemasangan Jembatan Rangka Baja Standar panjang 60 m
Pengangkutan Bahan Jembatan yang disediakan Pengguna Jasa
Fondasi Cerucuk, Penyediaan dan Pemancangan
Dinding Sumuran Silinder terpasang, Diameter 3,5 m
Dinding Sumuran Silinder terpasang, Diameter 3 m
Pasangan Batu
Sambungan Siar Muai Tipe Asphaltic Plug, Fixed
Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran 200 mm x 250 mm x 40 mm
Sandaran (Railing)
Papan Nama Jembatan
Pipa Drainase Baja diameter 100 mm
DIVISI 9. PEKERJAAN HARIAN DAN PEKERJAAN LAIN-LAIN 11,917,832 11,917,832 11,917,832 11,917,832
Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade
Patok Pengarah
Kereb Pracetak Jenis 1 (Peninggi/Mountable)
JEMBATAN KATI Monday, June 1, 2020 234 Wednesday, January 20, 2021
DIVISI 2. DRAINASE
Pasangan Batu dengan Mortar Tuesday, December 22, 2020 21 Monday, January 11, 2021 294,409,907 294,409,907 294,409,907
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
Galian Batu Lunak Monday, June 1, 2020 14 Sunday, June 14, 2020
Galian Struktur dengan Kedalaman 0 - 2 M Monday, June 1, 2020 14 Sunday, June 14, 2020 15,841,598 15,841,598
Galian Struktur dengan Kedalaman 2 - 4 M Monday, June 1, 2020 7 Sunday, June 7, 2020
Galian Struktur dengan Kedalaman 4 - 6 M Monday, June 1, 2020 14 Sunday, June 14, 2020
Timbunan Pilihan dari Sumber Galian Saturday, June 27, 2020 7 Friday, July 3, 2020 5,471,293,122
Penyiapan Badan Jalan Saturday, June 27, 2020 30 Sunday, July 26, 2020 764,107 764,107 764,107 764,107
DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
Lapis Fondasi Agregat Kelas A Saturday, June 27, 2020 21 Friday, July 17, 2020 244,314,143 244,314,143 244,314,143
Lapis Fondasi Agregat Kelas B Saturday, June 27, 2020 21 Friday, July 17, 2020 349,872,723 349,872,723 349,872,723
DIVISI 7. STRUKTUR 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879 507,751,879
Dinding Sumuran Monday, June 1, 2020 8 Monday, June 8, 2020
Isian Sumuran Fc' 30 Tuesday, June 9, 2020 6 Sunday, June 14, 2020
Isian Sumuran (Beton Siklop) Monday, June 15, 2020 12 Friday, June 26, 2020
Penulangan + Bekisting + Pengecoran Abutmen 1 Saturday, June 27, 2020 25 Tuesday, July 21, 2020
Penulangan + Bekisting + Pengecoran Abutmen 2 Saturday, June 27, 2020 25 Tuesday, July 21, 2020
Penulangan + Bekisting + Pengecoran Pilar 1 Wednesday, July 22, 2020 30 Thursday, August 20, 2020
Penulangan + Bekisting + Pengecoran Pilar 2 Wednesday, July 22, 2020 30 Thursday, August 20, 2020
Masa Umur Beton Friday, August 21, 2020 14 Thursday, September 3, 2020
Pemasangan Girder 1 + Bekisting + Penulangan + Pengecoran Lantai Friday, September 4, 2020 18 Monday, September 21, 2020
Masa Umur Beton Tuesday, September 22, 2020 14 Monday, October 5, 2020
Pemasangan Rangka + Bekisting + Penulangan + Pengecoran Lantai Tuesday, October 6, 2020 45 Thursday, November 19, 2020
Masa Umur Beton Friday, November 20, 2020 14 Thursday, December 3, 2020
Pemasangan Girder 2 + Bekisting + Penulangan + Pengecoran Lantai Friday, December 4, 2020 18 Monday, December 21, 2020
Finishing Tuesday, December 22, 2020 30 Wednesday, January 20, 2021
Beton struktur, fc '30 MPa
Beton struktur bervolume besar, fc '30 MPa
Beton struktur, fc '20 Mpa
Beton Siklop, fc '15 MPa
Beton, fc '10 Mpa
Baja Tulangan Polos-BjTP 280
Baja Tulangan Sirip BjTS 420A
Penyediaan Baja Struktur Grade 250 (Kuat Leleh 250 Mpa)
Pemasangan Baja Struktur
Penyediaan Struktur Jembatan Rangka Baja Standar panjang 60 m
Pemasangan Jembatan Rangka Baja Standar panjang 60 m
Pengangkutan Bahan Jembatan yang disediakan Pengguna Jasa
Fondasi Cerucuk, Penyediaan dan Pemancangan
Dinding Sumuran Silinder terpasang, Diameter 3,5 m
Dinding Sumuran Silinder terpasang, Diameter 3 m
Pasangan Batu
Sambungan Siar Muai Tipe Asphaltic Plug, Fixed
Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran 200 mm x 250 mm x 40 mm
Sandaran (Railing)
Papan Nama Jembatan
Pipa Drainase Baja diameter 100 mm
DIVISI 9. PEKERJAAN HARIAN DAN PEKERJAAN LAIN-LAIN 14,441,700 14,441,700 14,441,700 14,441,700
Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade
Patok Pengarah
Kereb Pracetak Jenis 1 (Peninggi/Mountable)
JEMBATAN PANI 1 Sunday, December 1, 2019 180 Thursday, May 28, 2020
DIVISI 2. DRAINASE
Pasangan Batu dengan Mortar Wednesday, April 29, 2020 21 Tuesday, May 19, 2020 294,409,907 294,409,907 294,409,907
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
Galian Batu Lunak Sunday, December 1, 2019 14 Saturday, December 14, 2019 2,093,867,644 2,093,867,644
Galian Struktur dengan Kedalaman 0 - 2 M Sunday, December 1, 2019 14 Saturday, December 14, 2019 11,131,710 11,131,710
Galian Struktur dengan Kedalaman 2 - 4 M Sunday, December 1, 2019 7 Saturday, December 7, 2019
Galian Struktur dengan Kedalaman 4 - 6 M Sunday, December 1, 2019 14 Saturday, December 14, 2019
Timbunan Pilihan dari Sumber Galian Wednesday, December 18, 2019 7 Tuesday, December 24, 2019 1,822,815,668
Penyiapan Badan Jalan Wednesday, December 18, 2019 30 Thursday, January 16, 2020 764,107 764,107 764,107 764,107
DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
Lapis Fondasi Agregat Kelas A Wednesday, December 18, 2019 21 Tuesday, January 7, 2020 244,314,143 244,314,143 244,314,143
Lapis Fondasi Agregat Kelas B Wednesday, December 18, 2019 21 Tuesday, January 7, 2020 349,872,723 349,872,723 349,872,723
DIVISI 7. STRUKTUR 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412 311,259,412
Dinding Sumuran Sunday, December 1, 2019 5 Thursday, December 5, 2019
Isian Sumuran Fc' 30 Friday, December 6, 2019 4 Monday, December 9, 2019
Isian Sumuran (Beton Siklop) Tuesday, December 10, 2019 8 Tuesday, December 17, 2019
Penulangan + Bekisting + Pengecoran Abutmen 1 Wednesday, December 18, 2019 17 Friday, January 3, 2020
Penulangan + Bekisting + Pengecoran Abutmen 2 Wednesday, December 18, 2019 17 Friday, January 3, 2020
Penulangan + Bekisting + Pengecoran Pilar 1 Saturday, January 4, 2020 20 Thursday, January 23, 2020
Penulangan + Bekisting + Pengecoran Pilar 2 Saturday, January 4, 2020 20 Thursday, January 23, 2020
Masa Umur Beton Friday, January 24, 2020 14 Thursday, February 6, 2020
Pemasangan Girder 1 + Bekisting + Penulangan + Pengecoran Lantai Friday, February 7, 2020 12 Tuesday, February 18, 2020
Masa Umur Beton Wednesday, February 19, 2020 14 Tuesday, March 3, 2020
Pemasangan Rangka + Bekisting + Penulangan + Pengecoran Lantai Wednesday, March 4, 2020 30 Thursday, April 2, 2020
Masa Umur Beton Friday, April 3, 2020 14 Thursday, April 16, 2020
Pemasangan Girder 2 + Bekisting + Penulangan + Pengecoran Lantai Friday, April 17, 2020 12 Tuesday, April 28, 2020
Finishing Wednesday, April 29, 2020 30 Thursday, May 28, 2020
Beton struktur, fc '30 MPa
Beton struktur bervolume besar, fc '30 MPa
Beton struktur, fc '20 Mpa
Beton Siklop, fc '15 MPa
Beton, fc '10 Mpa
Baja Tulangan Polos-BjTP 280
Baja Tulangan Sirip BjTS 420A
Penyediaan Baja Struktur Grade 250 (Kuat Leleh 250 Mpa)
Pemasangan Baja Struktur
Penyediaan Struktur Jembatan Rangka Baja Standar panjang 60 m
Pemasangan Jembatan Rangka Baja Standar panjang 60 m
Pengangkutan Bahan Jembatan yang disediakan Pengguna Jasa
Fondasi Cerucuk, Penyediaan dan Pemancangan
Dinding Sumuran Silinder terpasang, Diameter 3,5 m
Dinding Sumuran Silinder terpasang, Diameter 3 m
Pasangan Batu
Sambungan Siar Muai Tipe Asphaltic Plug, Fixed
Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran 200 mm x 250 mm x 40 mm
Sandaran (Railing)
Papan Nama Jembatan
Pipa Drainase Baja diameter 100 mm
DIVISI 9. PEKERJAAN HARIAN DAN PEKERJAAN LAIN-LAIN 12,548,799 12,548,799 12,548,799 12,548,799
Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade
Patok Pengarah
Kereb Pracetak Jenis 1 (Peninggi/Mountable)
JEMBATAN PANI 2 Sunday, March 1, 2020 180 Thursday, August 27, 2020
DIVISI 2. DRAINASE
Pasangan Batu dengan Mortar Wednesday, July 29, 2020 21 Tuesday, August 18, 2020 294,409,907 294,409,907 294,409,907
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
Galian Batu Lunak Sunday, March 1, 2020 14 Saturday, March 14, 2020 2,093,867,644 2,093,867,644
Galian Struktur dengan Kedalaman 0 - 2 M Sunday, March 1, 2020 14 Saturday, March 14, 2020 14,991,049 14,991,049
Galian Struktur dengan Kedalaman 2 - 4 M Sunday, March 1, 2020 7 Saturday, March 7, 2020
Galian Struktur dengan Kedalaman 4 - 6 M Sunday, March 1, 2020 14 Saturday, March 14, 2020
Timbunan Pilihan dari Sumber Galian Wednesday, March 18, 2020 7 Tuesday, March 24, 2020 1,822,815,668
Penyiapan Badan Jalan Wednesday, March 18, 2020 30 Thursday, April 16, 2020 764,107 764,107 764,107 764,107
DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
Lapis Fondasi Agregat Kelas A Wednesday, March 18, 2020 21 Tuesday, April 7, 2020 244,314,143 244,314,143 244,314,143
Lapis Fondasi Agregat Kelas B Wednesday, March 18, 2020 21 Tuesday, April 7, 2020 349,872,723 349,872,723 349,872,723
DIVISI 7. STRUKTUR 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897 252,739,897
Dinding Sumuran Sunday, March 1, 2020 5 Thursday, March 5, 2020
Isian Sumuran Fc' 30 Friday, March 6, 2020 4 Monday, March 9, 2020
Isian Sumuran (Beton Siklop) Tuesday, March 10, 2020 8 Tuesday, March 17, 2020
Penulangan + Bekisting + Pengecoran Abutmen 1 Wednesday, March 18, 2020 17 Friday, April 3, 2020
Penulangan + Bekisting + Pengecoran Abutmen 2 Wednesday, March 18, 2020 17 Friday, April 3, 2020
Penulangan + Bekisting + Pengecoran Pilar 1 Saturday, April 4, 2020 20 Thursday, April 23, 2020
Penulangan + Bekisting + Pengecoran Pilar 2 Saturday, April 4, 2020 20 Thursday, April 23, 2020
Masa Umur Beton Friday, April 24, 2020 14 Thursday, May 7, 2020
Pemasangan Girder 1 + Bekisting + Penulangan + Pengecoran Lantai Friday, May 8, 2020 12 Tuesday, May 19, 2020
Masa Umur Beton Wednesday, May 20, 2020 14 Tuesday, June 2, 2020
Pemasangan Rangka + Bekisting + Penulangan + Pengecoran Lantai Wednesday, June 3, 2020 30 Thursday, July 2, 2020
Masa Umur Beton Friday, July 3, 2020 14 Thursday, July 16, 2020
Pemasangan Girder 2 + Bekisting + Penulangan + Pengecoran Lantai Friday, July 17, 2020 12 Tuesday, July 28, 2020
Finishing Wednesday, July 29, 2020 30 Thursday, August 27, 2020
Beton struktur, fc '30 MPa
Beton struktur bervolume besar, fc '30 MPa
Beton struktur, fc '20 Mpa
Beton Siklop, fc '15 MPa
Beton, fc '10 Mpa
Baja Tulangan Polos-BjTP 280
Baja Tulangan Sirip BjTS 420A
Penyediaan Baja Struktur Grade 250 (Kuat Leleh 250 Mpa)
Pemasangan Baja Struktur
Penyediaan Struktur Jembatan Rangka Baja Standar panjang 60 m
Pemasangan Jembatan Rangka Baja Standar panjang 60 m
Pengangkutan Bahan Jembatan yang disediakan Pengguna Jasa
Fondasi Cerucuk, Penyediaan dan Pemancangan
Dinding Sumuran Silinder terpasang, Diameter 3,5 m
Dinding Sumuran Silinder terpasang, Diameter 3 m
Pasangan Batu
Sambungan Siar Muai Tipe Asphaltic Plug, Fixed
Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran 200 mm x 250 mm x 40 mm
Sandaran (Railing)
Papan Nama Jembatan
Pipa Drainase Baja diameter 100 mm
DIVISI 9. PEKERJAAN HARIAN DAN PEKERJAAN LAIN-LAIN 11,917,832 11,917,832 11,917,832 11,917,832
Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade
Patok Pengarah
Kereb Pracetak Jenis 1 (Peninggi/Mountable)
JEMBATAN MAHNE Tuesday, December 1, 2020 234 Thursday, July 22, 2021
DIVISI 2. DRAINASE
Pasangan Batu dengan Mortar Wednesday, June 23, 2021 21 Tuesday, July 13, 2021
DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
Galian Batu Lunak Tuesday, December 1, 2020 14 Monday, December 14, 2020 720,175,440 720,175,440
Galian Struktur dengan Kedalaman 0 - 2 M Tuesday, December 1, 2020 14 Monday, December 14, 2020 12,302,299 12,302,299
Galian Struktur dengan Kedalaman 2 - 4 M Tuesday, December 1, 2020 7 Monday, December 7, 2020
Galian Struktur dengan Kedalaman 4 - 6 M Tuesday, December 1, 2020 14 Monday, December 14, 2020
w Timbunan Pilihan dari Sumber Galian Sunday, December 27, 2020 7 Saturday, January 2, 2021 885,702,668
Penyiapan Badan Jalan Sunday, December 27, 2020 30 Monday, January 25, 2021
DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
Lapis Fondasi Agregat Kelas A Sunday, December 27, 2020 21 Saturday, January 16, 2021
Lapis Fondasi Agregat Kelas B Sunday, December 27, 2020 21 Saturday, January 16, 2021
DIVISI 7. STRUKTUR 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595 207,362,595
Dinding Sumuran Tuesday, December 1, 2020 8 Tuesday, December 8, 2020
Isian Sumuran Fc' 30 Wednesday, December 9, 2020 6 Monday, December 14, 2020
Isian Sumuran (Beton Siklop) Tuesday, December 15, 2020 12 Saturday, December 26, 2020
Penulangan + Bekisting + Pengecoran Abutmen 1 Sunday, December 27, 2020 25 Wednesday, January 20, 2021
Penulangan + Bekisting + Pengecoran Abutmen 2 Sunday, December 27, 2020 25 Wednesday, January 20, 2021
Penulangan + Bekisting + Pengecoran Pilar 1 Thursday, January 21, 2021 30 Friday, February 19, 2021
Penulangan + Bekisting + Pengecoran Pilar 2 Thursday, January 21, 2021 30 Friday, February 19, 2021
Masa Umur Beton Saturday, February 20, 2021 14 Friday, March 5, 2021
Pemasangan Girder 1 + Bekisting + Penulangan + Pengecoran Lantai Saturday, March 6, 2021 18 Tuesday, March 23, 2021
Masa Umur Beton Wednesday, March 24, 2021 14 Tuesday, April 6, 2021
Pemasangan Rangka + Bekisting + Penulangan + Pengecoran Lantai Wednesday, April 7, 2021 45 Friday, May 21, 2021
Masa Umur Beton Saturday, May 22, 2021 14 Friday, June 4, 2021
Pemasangan Girder 2 + Bekisting + Penulangan + Pengecoran Lantai Saturday, June 5, 2021 18 Tuesday, June 22, 2021
Finishing Wednesday, June 23, 2021 30 Thursday, July 22, 2021
Beton struktur, fc '30 MPa
Beton struktur bervolume besar, fc '30 MPa
Beton struktur, fc '20 Mpa
Beton Siklop, fc '15 MPa
Beton, fc '10 Mpa
Baja Tulangan Polos-BjTP 280
Baja Tulangan Sirip BjTS 420A
Penyediaan Baja Struktur Grade 250 (Kuat Leleh 250 Mpa)
Pemasangan Baja Struktur
Penyediaan Struktur Jembatan Rangka Baja Standar panjang 60 m
Pemasangan Jembatan Rangka Baja Standar panjang 60 m
Pengangkutan Bahan Jembatan yang disediakan Pengguna Jasa
Fondasi Cerucuk, Penyediaan dan Pemancangan
Dinding Sumuran Silinder terpasang, Diameter 3,5 m
Dinding Sumuran Silinder terpasang, Diameter 3 m
Pasangan Batu
Sambungan Siar Muai Tipe Asphaltic Plug, Fixed
Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran 200 mm x 250 mm x 40 mm
Sandaran (Railing)
Papan Nama Jembatan
Pipa Drainase Baja diameter 100 mm
DIVISI 9. PEKERJAAN HARIAN DAN PEKERJAAN LAIN-LAIN 11,330,450 11,330,450 11,330,450 11,330,450
Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade
Patok Pengarah
Kereb Pracetak Jenis 1 (Peninggi/Mountable)
TOTAL PER MINGGU 196,333,055 219,671,616 219,671,616 219,671,616 255,363,360 255,363,360 241,189,146 3,356,966,545 3,252,398,885 3,252,398,885 2,970,979,306 1,147,399,531 1,147,399,531 553,212,665 552,448,558 552,448,558 552,448,558 552,448,558 552,448,558 552,448,558 2,914,047,148 2,914,047,148 3,222,955,096 1,400,139,429 1,400,139,429 805,952,563 805,188,455 805,188,455 1,112,147,162 1,112,147,162 1,112,147,162 1,124,064,993 1,323,850,259 1,323,850,259 1,013,598,754 783,830,337 6,850,074,433 1,378,781,310 1,378,781,310 784,594,445 1,090,158,076 1,090,158,076 1,090,158,076 795,748,169 531,090,440 531,090,440 531,090,440 531,090,440 2,492,594,780 2,053,370,540 1,110,305,036 6,238,981,080 1,110,305,036 1,110,305,036 1,110,305,036 1,705,256,009 2,645,096,344 2,645,096,344 1,318,431,739 2,512,221,907 1,626,519,238 1,626,519,238 1,332,109,331 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 809,915,753 821,246,202 821,246,202 821,246,202 821,246,202 602,553,158 602,553,158 602,553,158 602,553,158 602,553,158 602,553,158 602,553,158 602,553,158 602,553,158 602,553,158 602,553,158 602,553,158 602,553,158 915,583,255 915,583,255 915,583,255 621,173,347 817,506,402 219,671,616 219,671,616 196,333,055
TOTAL PER BULAN 855,347,904 4,108,882,410 10,623,176,608 2,805,509,312 2,209,794,232 10,451,188,821 3,816,468,902 4,460,506,478 4,445,129,610 10,392,231,498 4,066,222,399 2,124,361,760 11,895,251,436 5,036,171,118 9,120,846,333 5,395,063,561 3,239,663,011 3,239,663,011 3,239,663,011 3,239,663,011 3,250,993,461 3,066,291,765 2,410,212,630 2,410,212,630 2,410,212,630 3,367,923,112 1,453,182,690