Anda di halaman 1dari 1

JADWAL PELAKSANAAN PEKERJAAN

( TIME SCHEDULE )
PEKERJAAN : PERENCANAAN TEKNIS REVITALISASI GUDANG FARMASI DAN APOTIK (DAK – PERIORITAS DAERAH)
SUMBER DANA : (DAK – PERIORITAS DAERAH)
TAHUN ANGGARAN : 2018

Bulan I Bulan II
JUMLAH VOLUME HARGA SATUAN BOBOT
NO URAIAN KEGIATAN JUMLAH HARGA (Rp) KETERANGAN
(Orang) (Bulan) (Rp) (%)
1 2 3 4 5 6
1 2 3 4 5 6 7

I BIAYA LANGSUNG PERSONIL


A TENAGA AHLI
1 Team Leader 1,00 1,50 Rp 7.850.000,00 Rp 11.775.000,00 16,90% 5,63% 5,63% 5,63% 100
2 Tenaga Ahli Manajemen Mutu 1,00 1,50 Rp 6.900.000,00 Rp 10.350.000,00 14,85% 2,48% 2,48% 2,48% 2,48% 2,48% 2,48%
B TENAGA PENDUKUNG
1 Surveyor 1,00 1,50 Rp 5.350.000,00 Rp 8.025.000,00 11,52% 1,92% 1,92% 1,92% 1,92% 1,92% 1,92% 80
2 Draftman 1,00 1,50 Rp 5.750.000,00 Rp 8.625.000,00 12,38% 2,06% 2,06% 2,06% 2,06% 2,06% 2,06%
3 Quantity & Estimate Engineering 1,00 1,50 Rp 5.750.000,00 Rp 8.625.000,00 12,38% 2,06% 2,06% 2,06% 2,06% 2,06% 2,06%
4 Administrasi/Operator Komputer 1,00 1,50 Rp 4.750.000,00 Rp 7.125.000,00 10,23% 1,70% 1,70% 1,70% 1,70% 1,70% 1,70%
60
II BIAYA LANGSUNG NON PERSONIL
A Biaya Peralatan
- Komputer, Printer & Alat-alat Ukur Teknik 1,00 1,50 Rp 3.800.000,00 Rp 5.700.000,00 8,18% 1,36% 1,36% 1,36% 1,36% 1,36% 1,36%
B Kendaraan Kerja 40
- Sewa Kenderaan Roda 2 + BBM 1,00 1,50 Rp 1.500.000,00 Rp 2.250.000,00 3,23% 0,54% 0,54% 0,54% 0,54% 0,54% 0,54%
2,3 Biaya Laporan
1 Laporan Pendahuluan 1,00 5,00 Rp 420.000,00 Rp 2.100.000,00 3,01% 1,51% 1,51% 20
2 Laporan Antara 1,00 5,00 Rp 420.000,00 Rp 2.100.000,00 3,01% 1,51% 1,51%
3 Laporan Akhir (CD Master) Gambar A3 + RAB 1,00 5,00 Rp 500.000,00 Rp 2.500.000,00 3,59% 1,79% 1,79%
4 Dokumentasi 1,00 1,00 Rp 500.000,00 Rp 500.000,00 0,72% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12%
0
TOTAL Rp 69.675.000,00 19,39% 13,75% 19,39% 13,75% 19,67% 14,04%
PPn 10 % Rp 6.967.500,00 100,00% 19,39% 33,14% 52,53% 66,28% 85,96% 100,00%
TOTAL Rp 76.642.500,00 Kumulatif Bobot Rencana

Catatan :
Jangka Waktu Penyelesaian Pekerjaan 45 (Empat Puluh Lima) Hari Kalender
1 Bulan = 30 (Tiga Puluh) Hari Kerja
1 Hari = 8 (delapan) Jam Kerja