Anda di halaman 1dari 34

REKAPITULASI

SATUAN KERJA : DINAS PENDIDIKAN


KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAN : REHABILITASI RUANG TATA USAHA SMP NEGERI 3 KUMERSOT
LOKASI : KELURAHAN KUMERSOT
TAHUN ANGGARAN : 2021

NO. URAIAN PEKERJAAN JUMLAH (Rp)

A PEKERJAAN PERSIAPAN 21,524,641.83


B RUANG TATA USAHA
I PEKERJAAN ATAP 44,114,388.65
II PEKERJAAN PLAFOND 41,357,909.25
III PEKERJAAN LANTAI KERAMIK 87,293,847.97
IV PEKERJAAN CAT 12,481,001.88
V PEKERJAAN PINTU DAN JENDELA KAYU 45,150,614.76
VI PEKERJAAN KUNCI DAN PENGGANTUNG 1,009,900.00
VII PEKERJAAN ELEKTRIKAL 3,419,200.00
VIII PEKERJAAN TOILET 12,698,049.96
IX PEKERJAAN SEPTICTANK 14,434,594.80
C PEKERJAAN LAIN-LAIN
I PEKERJAAN AKHIR 1,900,000.00

JUMLAH 285,384,149.10
PPN 10% 28,538,414.91
TOTAL 313,922,564.01
PEMBULATAN 313,922,000.00
Terbilang :

Err:511

Bitung, April 2021


Konsultan Perencana
Pejabat Pembuat Komitmen (PPK)

MAXI Z. RUMUAT, MP
NIP. 1966 0305 198803 1 014 Direktur
HARGA
NO. URAIAN JENIS PEKERJAAN SAT VOLUME SATUAN
(Rp.)

A. REHAB PAGAR SMP 2 NEGERI BITUNG

I. PEKERJAAN PERSIAPAN
1 Pembongkaran Dinding m2 16.20 #REF!
2 Bongkaran beton bertulang m3 #REF! #REF!
4 Pembongkaran Pondasi m3 21.54 #REF!
5 Pas. Bouwplank dan pengukuran m' 10.60 #REF!

II. PEKERJAAN PASIR DAN BUANGAN SISA MATERIAL


1 Pembuangan Material sisa bongkaran m3 12.10 #REF!
2 Urugan pasir dibawah pondasi m3 0.34 #REF!
3 Pas. Batu Kosong 1.01 #REF!

III. PEKERJAAN PONDASI, BETON DAN PLESTERAN


1 Pas. Batu Pondasi 1 : 5 m3 4.56 #REF!
2 Sloof 15 X 20 cm m3 0.27 #REF!
3 Kolom Beton 30 X 30 cm m3 0.59 #REF!
4 Pas. Batu Bata 1 : 5 m2 32.83 #REF!
5 Cor dinding beton m3 2.31 #REF!
6 Bekisting cor dinding beton m2 14.33 #REF!
7 Plesteran Dinding 1 : 5 m2 #REF!
Acian m2 #REF!
IV. PEKERJAAN PAGAR BESI HOLLOW
Pas. Pagar Hollow m1 50.45 550,000.00
Pintu Pagar Type 1 Ls 1.00 2,500,000.00
Pintu Pagar Type 2 Ls 1.00 3,300,000.00
Pintu Pagar Type Ls 1.00 3,000,000.00

V PEKERJAAN CAT
1 Cat dinding m2 - #REF!
2 Cat Pagar m2 100.00 #REF!
3
4
5
6
PEKERJAAN PAGAR BESI
1
2
JUMLAH
(Rp.)

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

27,747,500.00
2,500,000.00
3,300,000.00
3,000,000.00
-
#REF!
#REF!
#REF!

#REF!
ENGINERING ESTIMATE (EE)
SATUAN KERJA : DINAS PENDIDIKAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAN : REHABILITASI RUANG TATA USAHA SMP NEGERI 3 KUMERSOT
LOKASI : KELURAHAN KUMERSOT
TAHUN ANGGARAN 2021

HARGA SATUAN JUMLAH


NO. URAIAN JENIS PEKERJAAN SAT VOLUME
(Rp.) (Rp.)
a b c d e f=(d x e)
A PEKERJAAN PERSIAPAN
1 Pembersihan Awal Ls 1.00 2,000,000.00 2,000,000.00
2 Pembongkaran atap Ls 1.00 2,500,000.00 2,500,000.00
3 Pembongkaran Dinding bata m2 4.80 58,300.00 279,840.00
4 Pembongkaran kuda-kuda + gording m2 190.12 30,325.00 5,765,493.83
5 Pembongkaran rangka+penutup plafond m2 103.80 17,630.00 1,829,994.00
6 Pembongkaran lantai Keramik m2 102.60 80,890.00 8,299,314.00
7 Papan proyek Ls 1.00 350,000.00 350,000.00
8 Listrik dan Air kerja Ls 1.00 500,000.00 500,000.00
sub jumlah 21,524,641.83
B RUANG TATA USAHA
I PEKERJAAN ATAP
1 Pasang Kuda kuda Konvensional kayu Kls II m3 2.19 8,065,500.00 17,663,445.00
2 Pasang gording 5 X 10 Kayu Kls II m3 1.12 7,713,050.00 8,638,616.00
3 Penutup atap bjls 30 m2 190.12 64,700.00 12,300,987.65
4 Lisplank papan 30 cm m1 50.00 96,350.00 4,817,500.00
5 Bumbungan atap m1 14.00 49,560.00 693,840.00
sub jumlah 44,114,388.65
II PEKERJAAN PLAFOND
1 Pasang Rangka plafond kayu Kls II m2 106.05 152,100.00 16,130,205.00
2 Pasang penutup plafond Sundha + lis m2 106.05 237,885.00 25,227,704.25
sub jumlah 41,357,909.25
III PEKERJAAN LANTAI KERAMIK
1 Pasang keramik lantai Granito 40 x 40 cm m2 102.60 453,601.90 46,539,554.94
2 Pasang keramik lantai 20 x 20 cm m2 2.25 224,324.00 504,729.00
3 Keramik Dinding WC 40 x 40 Biasa m2 16.64 220,619.40 3,671,106.82
3 Keramik Dinding Granito 40 x 40 m2 80.64 453,601.90 36,578,457.22
sub jumlah 87,293,847.97
IV PEKERJAAN PARTISI
1 Pek.Dinding Partisi PVC m2 20.51 448,225.00 9,193,094.75
sub jumlah 9,193,094.75
V PEKERJAAN CAT
1 Cat dinding m2 302.35 26,460.00 8,000,181.00
2 Cat kosen pintu, jendela dan jalusi m2 20.57 42,985.00 884,351.90
3 Cat daun pintu dan daun jendela m2 20.75 42,985.00 891,852.78
4 Cat Lisplank m1 52.00 42,985.00 2,235,220.00
5 Cat Teralis m2 10.92 42,985.00 469,396.20
sub jumlah 12,481,001.88
VI PEKERJAAN PINTU DAN JENDELA KAYU
1 Kusen pintu dan jendela kayu Kls II m3 0.89 9,383,500.00 8,307,118.72
2 Daun pintu panel Kayu Kls II m2 4.83 770,250.00 3,720,307.50
3 Daun jendela kayu + kaca 5 mm Kayu Kls II m2 11.09 678,050.00 7,518,218.40
4 Pasang Jalusi Papan kayu Kls II m2 14.25 712,500.00 10,153,125.00
5 Kusen Aluminium m 4.94 65,851.00 325,303.94
6 Pintu Kaca Riben 6 mm Frame aluminium m2 1.60 1,601,600.00 2,562,560.00
7 Door Closer bh 1.00 425,200.00 425,200.00
9 Pasang Teralis 20mm x 40 mm m2 10.92 1,111,610.00 12,138,781.20
sub jumlah 45,150,614.76
VII PEKERJAAN KUNCI DAN PENGGANTUNG
1 Pemasangan kunci tanam Besar bh 1.00 451,775.00 451,775.00
2 Pemasangan kunci tanam Kecil bh 1.00 226,775.00 226,775.00
3 Pemasangan engsel pintu Ps 2.00 62,172.50 124,345.00
4 Pemasangan engsel jendela Ps 2.00 44,115.00 88,230.00
5 Pemasangan Tarikan jendela Bh 2.00 22,115.00 44,230.00
6 Pemasangan Hak angin Bh 2.00 37,272.50 74,545.00
sub jumlah 1,009,900.00
VIII PEKERJAAN ELEKTRIKAL
1 Pasang Instalasi listrik Titik 8.00 359,900.00 2,879,200.00
2 Pas. Mata Lampu SL 11 Watt + Fitting set 3.00 71,550.00 214,650.00
3 Saklar ganda Bh 1.00 58,050.00 58,050.00
4 Saklar Tunggal Bh 3.00 44,550.00 133,650.00
5 Stop kontak bh 3.00 44,550.00 133,650.00
sub jumlah 3,419,200.00
HARGA SATUAN JUMLAH
NO. URAIAN JENIS PEKERJAAN SAT VOLUME
(Rp.) (Rp.)
a b c d e f=(d x e)
VIII PEKERJAAN TOILET
1 Pek. Galian Tanah m3 1.13 74,500.00 83,812.50
2 Pek.Aanstamping m3 0.14 410,460.00 55,412.10
3 Pek.Pondasi batu camp.1;5 m3 1.01 742,140.00 751,416.75
4 Pek.Beton Tumbuk camp.1;3;5 m3 0.23 916,937.38 206,310.91
5 Pek.Kolom Praktis 15 x 20 m 0.19 90,570.00 17,389.44
6 Pek.Ring Balok 15 x 20 m3 0.14 5,805,105.00 783,689.18
7 Pek. Sloof 15 x 20 m3 0.14 4,253,305.00 574,196.18
8 Pekerjaan Dinding Bata Camp 1;5 m2 14.40 122,646.80 1,766,113.92
9 Pek.Plesteran m2 28.80 62,751.84 1,807,252.99
10 Pek.Acian m2 28.80 39,495.00 1,137,456.00
11 Roster bh 3.00 50,000.00 150,000.00
12 Closet Jongkok +accessories bh 1.00 3,500,000.00 3,500,000.00
13 Floor Drain bh 1.00 45,000.00 45,000.00
14 Wastafel bh 1.00 550,000.00 550,000.00
15 Kran Air bh 1.00 70,000.00 70,000.00
16 Pipa PVC 1/2 inc Ls 1.00 300,000.00 300,000.00
17 Pintu PVC Toilet Unit 1.00 900,000.00 900,000.00
sub jumlah 12,698,049.96
IX PEKERJAAN SEPTICTANK
1 Pek.Galian Tanah m3 5.40 74,500.00 402,300.00
2 Lantai kerja m3 0.18 916,937.38 165,048.73
3 Pek.dinding Beton Bertulang m3 1.67 7,007,355.00 11,667,246.08
4 Pek.Pipa 4 " inc Ls 1.00 1,500,000.00 1,500,000.00
5 Pek.Penutup Plat WC Ls 1.00 700,000.00 700,000.00
sub jumlah 14,434,594.80
C PEKERJAAN LAIN-LAIN
I PEKERJAAN AKHIR Ls 1.00 1,900,000.00 1,900,000.00
1 Pembersihan Akhir
sub jumlah 1,900,000.00

MAXI Z. RUMUAT, MP
Nip. 1966 0305 198803 1 014 Direktur
DAFTAR HARGA SATUAN JADI
SATUAN KERJA : DINAS PENDIDIKAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAN : REHABILITASI RUANG TATA USAHA SMP NEGERI 3 KUMERSOT
LOKASI : KELURAHAN KUMERSOT
TAHUN ANGGARAN 2021

NO. URAIAN PEKERJAAN SATUAN HARGA SATUAN KETERANGAN

1 Pembersihan Awal Ls 2,000,000.00


2 Pembongkaran atap Ls 2,500,000.00
3 Pembongkaran Dinding bata m2 58,300.00
4 Pembongkaran kuda-kuda + gording m2 30,325.00
5 Pembongkaran rangka+penutup plafond m2 17,630.00
6 Pembongkaran lantai Keramik m2 80,890.00
7 Papan proyek Ls 350,000.00
8 Listrik dan Air kerja Ls 500,000.00
9 Pasang Kuda kuda Konvensional kayu Kls II m3 8,065,500.00
10 Pasang gording 5 X 10 Kayu Kls II m3 7,713,050.00
11 Penutup atap bjls 30 m2 64,700.00
12 Lisplank papan 30 cm m1 96,350.00
13 Bumbungan atap m1 49,560.00
14 Pasang Rangka plafond kayu Kls II m2 152,100.00
15 Pasang penutup plafond Sundha + lis m2 237,885.00
16 Pasang keramik lantai Granito 40 x 40 cm m2 453,601.90
17 Pasang keramik lantai 20 x 20 cm m2 224,324.00
18 Keramik Dinding WC 40 x 40 Biasa m2 220,619.40
19 Keramik Dinding Granito 40 x 40 m2 453,601.90
20 Pek.Dinding Partisi PVC m2 448,225.00
21 Cat dinding m2 26,460.00
22 Cat kosen pintu, jendela dan jalusi m2 42,985.00
23 Cat daun pintu dan daun jendela m2 42,985.00
24 Cat Lisplank m1 42,985.00
25 Cat Teralis m2 42,985.00
26 Kusen pintu dan jendela kayu Kls II m3 9,383,500.00
27 Daun pintu panel Kayu Kls II m2 770,250.00
28 Daun jendela kayu + kaca 5 mm Kayu Kls II m2 678,050.00
29 Pasang Jalusi Papan kayu Kls II m2 712,500.00
30 Kusen Aluminium m 65,851.00
31 Pintu Kaca Riben 6 mm Frame aluminium m2 1,601,600.00
32 Door Closer bh 425,200.00
33 Pasang Teralis 20mm x 40 mm m2 1,111,610.00
34 Pemasangan kunci tanam Besar bh 451,775.00
35 Pemasangan kunci tanam Kecil Ls 1,900,000.00
36 Pemasangan engsel pintu Ps 62,172.50
37 Pemasangan engsel jendela Ps 44,115.00
38 Pemasangan Tarikan jendela Bh 22,115.00
39 Pemasangan Hak angin Bh 37,272.50
40 Pasang Instalasi listrik Titik 359,900.00
41 Pas. Mata Lampu SL 11 Watt + Fitting set 71,550.00
42 Saklar ganda Bh 58,050.00
43 Saklar Tunggal Bh 44,550.00
44 Stop kontak bh 44,550.00
45 Pek.Aanstamping m3 410,460.00
46 Pek.Pondasi batu camp.1;5 m3 742,140.00
47 Pek.Beton Tumbuk camp.1;3;5 m3 916,937.38
48 Pek.Kolom Praktis 15 x 20 m 90,570.00
49 Pek.Ring Balok 15 x 20 m3 5,805,105.00
50 Pek. Sloof 15 x 20 m3 4,253,305.00
51 Pekerjaan Dinding Bata Camp 1;5 m2 122,646.80
52 Pek.Plesteran m2 62,751.84
53 Pek.Acian m2 39,495.00
54 Roster bh 50,000.00
55 Closet Jongkok +accessories bh 3,500,000.00
56 Floor Drain bh 45,000.00
57 Wastafel bh 550,000.00
58 Kran Air bh 70,000.00
59 Pipa PVC 1/2 inc Ls 300,000.00
60 Pintu PVC Toilet Unit 900,000.00
61 Pek.Galian Tanah m3 74,500.00
62 Pek.dinding Beton Bertulang m3 7,007,355.00
63 Pek.Pipa 4 " inc Ls 1,500,000.00
64 Pek.Penutup Plat WC Ls 700,000.00
65 Pembersihan Akhir Ls 1,900,000.00
Bitung, April 2021
Konsultan Perencana
Pejabat Pembuat Komitmen (PPK)

MAXI Z. RUMUAT, MP
NIP. 1966 0305 198803 1 014 Direktur
DAFTAR HARGA UPAH
SATUAN KERJA : DINAS PENDIDIKAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAN : REHABILITASI RUANG TATA USAHA SMP NEGERI 3 KUMERSOT
LOKASI : KELURAHAN KUMERSOT
TAHUN ANGGARAN : 2021

NO URAIAN SATUAN HARGA DASAR KET.

UPAH
1 Kepala Tukang OH Rp 160,000
2 Tukang OH Rp 135,000
3 Tukang Kayu OH Rp 135,000
4 Tukang batu OH Rp 135,000
5 Tukang listrik OH Rp 135,000
6 Tukang besi OH Rp 135,000
7 Tukang cat OH Rp 135,000
8 Pekerja OH Rp 95,000
9 Mandor OH Rp 130,000

Bitung, April 2021


Konsultan Perencana
Pejabat Pembuat Komitmen (PPK)

MAXI Z. RUMUAT, MP
Nip. 1966 0305 198803 1 014 Direktur
DAFTAR HARGA BAHAN
SATUAN KERJA : DINAS PENDIDIKAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAN : REHABILITASI RUANG TATA USAHA SMP NEGERI 3 KUMERSOT
LOKASI : KELURAHAN KUMERSOT
TAHUN ANGGARAN : 2021

NO URAIAN SATUAN HARGA DASAR KET.

1 Air Ltr Rp 100


2 Ampelas Lbr Rp 2,500
3 Balok kayu kelas II M3 Rp 5,000,000
4 Bata merah 5 x 11 x 22 Buah Rp 850
5 Batako Bh Rp 1,500
6 Batu belah 15/20 cm M3 Rp 200,000
7 Baut 12 mm bh Rp 12,000
8 Besi Beton Kg Rp 12,500
9 Besi beton polos Kg Rp 12,500
10 Besi hollow 2 x 4x 1mm ujung Rp 115,000
11 Besi strip tebal 5 mm Kg Rp 12,500
12 Cat dasar Kg Rp 30,000
13 Cat dasar Kayu Kg Rp 30,000
14 Cat dasar Tembok Kg Rp 30,000
15 Cat menie Kg Rp 45,000
16 Cat Penutup Kayu Kg Rp 60,000
17 Cat Penutup Tembok Kg Rp 30,000
18 Cat tembok penutup 2 x Kg Rp 75,000
19 Dolken kayu galam/Bambu P = 4 m Btg Rp 10,000
20 Dolken kayu Ø 8-10/400 cm Batang Rp 10,000
21 Door Closer Bh Rp 395,000
22 Engsel jendela Bh Rp 28,000
23 Engsel pintu Bh Rp 38,000
24 Grendel jendela Bh Rp 5,000
25 Grendel pintu Bh Rp 10,000
26 Gypsum board 9 mm Lbr Rp 95,000
27 Hak angin Bh Rp 7,500
28 Handle Pintu Bh Rp 65,000
29 Hollow 2x4 Ujung Rp 28,000
30 Hollow 4x4 Ujung Rp 38,000
31 Kabel NGA 3 x 2,5 mm m1 Rp 12,500
32 Kaca 5 mm m2 Rp 165,000
33 Kaca bening 3 mm M2 Rp 135,000
34 Kaca bening 5 mm M2 Rp 165,000
35 Kanal C Ujung Rp 110,000
36 Kawat beton Kg Rp 22,000
37 Kayu 5/7 M³ Rp 3,500,000
38 Kayu Kaso 4/6 M3 Rp 5,000,000
39 Kayu Kaso 4/6 Kelas III M3 Rp 3,500,000
40 Kayu Kelas II M3 Rp 5,000,000
41 Kayu Kelas II (cempaka) M3 Rp 5,000,000
42 Kayu Kelas III M3 Rp 3,500,000
43 Kayu Papan 3/20 M³ Rp 3,500,000
44 Kayu Profil SP 4 M1 Rp 25,000
45 Keramik 20 x 20 cm Dos Rp 65,000
46 Keramik 30 x 30 cm Dos Rp 75,000
47 Keramik 40 x 40 cm Dos Rp 75,000
48 Keramik 40 x 40 cm Antislip Dos Rp 85,000
49 Kerikil M3 Rp 320,000
50 Klam pipa Bh Rp 400
51 Kuas Bh Rp 12,000
52 Kunci Tanam Bh Rp 150,000
53 Kunci Tanam besar Bh Rp 375,000
NO URAIAN SATUAN HARGA DASAR KET.

54 Las Doof Bh Rp 850


55 List Sundha Plafond m Rp 85,000
56 Lem Kayu Kg Rp 31,500
57 Mata Lampu SL 11 Watt + Fitting Bh Rp 45,000
58 MCB 10 amper Bh Rp 185,000
59 Minyak bekisting Lt Rp 30,000
60 Paku 10 cm Kg Rp 20,000
61 Paku 5 - 12 cm kg Rp 20,000
62 Paku biasa 1/2" x 1" Kg Rp 22,000
63 Paku biasa 12 cm Kg Rp 20,000
64 Paku biasa 2" - 5" Kg Rp 20,000
65 Paku 5 - 10 cm Kg Rp 20,000
66 Paku biasa 5 dan 7 cm Kg Rp 20,000
67 Paku biasa 7 - 10 cm Kg Rp 20,000
68 Paku gypsum Bh Rp 1,000
69 Paku seng Kg Rp 22,000
70 Paku tripleks Kg Rp 24,000
71 Pasir M3 Rp 160,000
72 Pasir beton M3 Rp 120,000
73 Pasir pasang M3 Rp 120,000
74 Pasir plester M3 Rp 120,000
75 Pasir urug M3 Rp 75,000
76 Pengencer Kg Rp 25,000
77 Pipa PVC 5/8" m1 Rp 2,500
78 Pintu aluminium m Rp 105,000
79 Plamir Kg Rp 18,000
80 Plamuur Kg Rp 18,000
81 Plywood 9 mm Lembar Rp 135,000
82 Profil alluminium m Rp 35,000
83 Profil Kaca m2 Rp 235,000
84 Portland cement Kg Rp 1,260
85 Saklar ganda Bh Rp 35,000
86 Saklar tunggal Bh Rp 25,000
87 Skrup Fixer bh Rp 1,500
88 Sealant Tube Rp 225,000
89 Sekrup Bh Rp 300
90 Semen Warna Kg Rp 12,000
91 Seng gelombang bjls 30 Lbr Rp 55,000
92 Seng plat 3" x 6 " bjls 28 Lbr Rp 50,000
93 Shunda Plafond Lbr Rp 140,000
94 Stop Kontak Bh Rp 15,000
95 T Dos PVC Bh Rp 75,000
96 Tarikan jendela Bh Rp 6,000
97 Tripleks, tebal 4 mm Lbr Rp 75,000
98 Ubin Granito Bh Rp 56,500

Bitung, April 2021


Konsultan Perencana
Pejabat Pembuat Komitmen (PPK)

MAXI Z. RUMUAT, MP
NIP. 1966 0305 198803 1 014 Direktur
DAFTAR HARGA SATUAN ALAT

HARGA
PERALATAN
NO JENIS PERALATAN SAT KETERANGAN
(Rp.)

1 Dump Truck 3 - 4 m3 Jam 210,000.00


2
3
4
5
6

Bitung, April 2021


Konsultan Perencana
Pejabat Pembuat Komitmen (PPK)

MAXI Z. RUMUAT, MP
NIP. 1966 0305 198803 1 014 Direktur
DAFTAR ANALISA HARGA SATUAN PEKERJAAN

SATUAN KERJA : DINAS PENDIDIKAN


KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAN : REHABILITASI RUANG TATA USAHA SMP NEGERI 3 KUMERSOT
LOKASI : KELURAHAN KUMERSOT
TAHUN ANGGARAN 2021

1 1 M² Bongkaran atap
Tenaga
- Tukang 0.05000 Oh Rp. 135,000.00 6,750.00
- Kepala tukang - Oh Rp. 160,000.00 -
- Pekerja 0.01000 Oh Rp. 95,000.00 950.00
- Mandor - Oh Rp. 130,000.00 -
Jumlah Rp. 7,700.00

2 1 M2 Membersihkan Lapangan / Lokasi


Tenaga
- Tukang Oh Rp. 135,000.00 -
- Kepala tukang Oh Rp. 160,000.00 -
- Pekerja 0.2010 Oh Rp. 95,000.00 19,095.00
- Mandor 0.0800 Oh Rp. 130,000.00 10,400.00
Rp. 29,495.00

3 1 M3 Bongkaran Keramik
Tenaga
- Pekerja 0.4500 Oh Rp. 95,000.00 42,750.00
- Tukang 0.2300 Oh Rp. 135,000.00 31,050.00
- Kepala Tukang 0.0240 Oh Rp. 160,000.00 3,840.00
- Mandor 0.0250 Oh Rp. 130,000.00 3,250.00
Rp. 80,890.00

3 1 M3 Angkut dn Buang Hasil Bongkaran


Alat
- Dump Truck 3 - 4 m3 0.2000 Jam Rp. 210,000.00 42,000.00

Tenaga
- Pekerja 0.3200 Oh Rp. 95,000.00 30,400.00
- Tukang - Oh Rp. 135,000.00 -
- Kepala Tukang - Oh Rp. 160,000.00 -
- Mandor 0.0070 Oh Rp. 130,000.00 910.00
Rp. 73,310.00
4 1 M2 Bongkar gording + Kuda kuda
Tenaga
- Tukang 0.20000 Oh Rp. 135,000.00 27,000.00
- Kepala tukang - Oh Rp. 160,000.00 -
- Pekerja 0.03500 Oh Rp. 95,000.00 3,325.00
- Mandor - Oh Rp. 130,000.00 -
Jumlah Rp. 30,325.00

5 1 M² Bongkaran Plafond + Rangka


Tenaga
- Tukang - Oh Rp. 135,000.00 -
- Kepala tukang - Oh Rp. 160,000.00 -
- Pekerja 0.15000 Oh Rp. 95,000.00 14,250.00
- Mandor 0.02600 Oh Rp. 130,000.00 3,380.00
Jumlah Rp. 17,630.00

6 1 M² Bongkaran lantai
Tenaga
- Tukang - Oh Rp. 135,000.00 -
- Kepala tukang - Oh Rp. 160,000.00 -
- Pekerja 0.18000 Oh Rp. 95,000.00 17,100.00
- Mandor 0.04000 Oh Rp. 130,000.00 5,200.00
Jumlah Rp. 22,300.00

7 1 M² Bongkaran dinding bata


Tenaga
- Pekerja 0.6000 Oh Rp. 95,000.00 57,000.00
- Mandor 0.0100 Oh Rp. 130,000.00 1,300.00
Jumlah Rp. 58,300.00

8 1 M3 Bongkaran beton bertulang


Tenaga
- Tukang 13.3340 Oh Rp. 135,000.00 1,800,090.00
- Kepala Tukang - Oh Rp. 160,000.00 -
- Pekerja 0.6660 Oh Rp. 95,000.00 63,270.00
- Mandor - Oh Rp. 130,000.00 -
Jumlah Rp. 1,863,360.00

9 1 M' Pengukuran dan pemasangan Bouwplank


Bahan
- Kayu 5/7 0.0120 M³ Rp. 3,500,000.00 = Rp. 42,000.00
- Paku biasa 2" - 5" 0.0200 Kg Rp. 20,000.00 = Rp. 400.00
- Kayu Papan 3/20 0.0070 M³ Rp. 3,500,000.00 = Rp. 24,500.00

Tenaga
- Pekerja 0.1000 Oh Rp. 95,000.00 = Rp. 9,500.00
- Tukang Kayu 0.1000 Oh Rp. 135,000.00 = Rp. 13,500.00
- Kepala Tukang 0.0100 Oh Rp. 160,000.00 = Rp. 1,600.00
- Mandor 0.0050 Oh Rp. 130,000.00 = Rp. 650.00
Jumlah Rp. 92,150.00
Analisa Harga Satuan Pekerjaan Tanah
10 Menggali 1 m3 tanah biasa sedalam 1 meter
Tenaga
- Pekerja 0.7500 Oh Rp. 95,000.00 = Rp. 71,250.00
- Mandor 0.0250 Oh Rp. 130,000.00 = Rp. 3,250.00
Jumlah Rp. 74,500.00

11 Menggali 1 m3 tanah biasa sedalam 2 meter


Tenaga
- Pekerja 0.9000 Oh Rp. 95,000.00 = Rp. 85,500.00
- Mandor 0.0450 Oh Rp. 130,000.00 = Rp. 5,850.00
Jumlah Rp. 91,350.00

12 Menggali 1 m3 tanah keras sedalam 1 meter


Tenaga
- Pekerja 1.0000 Oh Rp. 95,000.00 = Rp. 95,000.00
- Mandor 0.0320 Oh Rp. 130,000.00 = Rp. 4,160.00
Jumlah Rp. 99,160.00

13 Mengurug kembali 1 m 3 galian


Mengurug kembali 1 m3 galian dihitung sari 1/3 kali indeks pekerjaan galian
Tenaga
- Pekerja 0.2500 Oh Rp. 95,000.00 = Rp. 23,750.00
- Mandor 0.0083 Oh Rp. 130,000.00 = Rp. 1,083.33
Jumlah Rp. 24,833.33

14 Memadatkan 1 m3 tanah (per 20 cm)


Tenaga
- Pekerja 0.5000 Oh Rp. 95,000.00 = Rp. 47,500.00
- Mandor 0.0500 Oh Rp. 130,000.00 = Rp. 6,500.00
Jumlah Rp. 54,000.00

15 Mengurug 1 m3 Pasir urug


Bahan
- Pasir urug 1.2000 M3 Rp. 75,000.00 = Rp. 90,000.00

Tenaga
- Pekerja 0.3000 Oh Rp. 95,000.00 = Rp. 28,500.00
- Mandor 0.0100 Oh Rp. 130,000.00 = Rp. 1,300.00
Jumlah Rp. 119,800.00

Analisa Harga Satuan Pekerjaan Pondasi


16 Memasang 1 m3 pondasi batu belah, campuran 1 Pc : 5 Pp
Bahan
- Batu belah 15/20 cm 1.2000 M3 Rp. 200,000.00 = Rp. 240,000.00
- Portland cement 136.000 Kg Rp. 1,260.00 = Rp. 171,360.00
- Pasir pasang 0.5440 M3 Rp. 120,000.00 = Rp. 65,280.00

Tenaga
- Pekerja 1.5000 Oh Rp. 95,000.00 = Rp. 142,500.00
- Tukang batu 0.7500 Oh Rp. 135,000.00 = Rp. 101,250.00
- Kepala tukang 0.0750 Oh Rp. 160,000.00 = Rp. 12,000.00
- Mandor 0.0750 Oh Rp. 130,000.00 = Rp. 9,750.00
Jumlah Rp. 742,140.00
17 Memasang 1 m3 batu kosong (aanstamping)
Bahan
- Batu belah 15/20 cm 1.2000 M3 Rp. 200,000.00 = Rp. 240,000.00
- Pasir urug 0.4320 M3 Rp. 75,000.00 = Rp. 32,400.00

Tenaga
- Pekerja 0.7800 Oh Rp. 95,000.00 = Rp. 74,100.00
- Tukang batu 0.3900 Oh Rp. 135,000.00 = Rp. 52,650.00
- Kepala tukang 0.0390 Oh Rp. 160,000.00 = Rp. 6,240.00
- Mandor 0.0390 Oh Rp. 130,000.00 = Rp. 5,070.00
Jumlah Rp. 410,460.00

Analisa Harga Satuan Pekerjaan Beton


18 Membuat 1 m 3 beton mutu f'c = 7,4 Mpa (K 100), slump (12 ± 2) cm, w/c = 0,87
Bahan
- Portland cement 247.0000 Kg Rp. 1,260.00 =Rp. 311,220.00
- Pasir beton 0.6207 M3 Rp. 120,000.00 =Rp. 74,485.71
- Kerikil 0.7400 M3 Rp. 320,000.00 =Rp. 236,800.00
- Air 215.0000 Ltr Rp. 100.00 =Rp. 21,500.00

Tenaga
- Pekerja 1.6500 Oh Rp. 95,000.00 =Rp. 156,750.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 =Rp. 37,125.00
- Kepala tukang 0.0280 Oh Rp. 160,000.00 =Rp. 4,480.00
- Mandor 0.0830 Oh Rp. 130,000.00 =Rp. 10,790.00
Jumlah Rp. 853,150.71

19 Membuat 1 m 3 beton mutu f'c = 12,2 Mpa (K 150), slump (12 ± 2) cm, w/c = 0,72
Bahan
- Portland cement 299.0000 Kg Rp. 1,260.00 =Rp. 376,740.00
- Pasir beton 0.5707 M3 Rp. 120,000.00 =Rp. 68,485.71
- Kerikil 0.7533 M3 Rp. 320,000.00 =Rp. 241,066.67
- Air 215.0000 Ltr Rp. 100.00 =Rp. 21,500.00

Tenaga
- Pekerja 1.6500 Oh Rp. 95,000.00 =Rp. 156,750.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 =Rp. 37,125.00
- Kepala tukang 0.0280 Oh Rp. 160,000.00 =Rp. 4,480.00
- Mandor 0.0830 Oh Rp. 130,000.00 =Rp. 10,790.00
Jumlah Rp. 916,937.38

20 Membuat 1 m 3 beton mutu f'c = 14,5 Mpa (K 175), slump (12 ± 2) cm, w/c = 0,66
Bahan
- Portland cement 326.0000 Kg Rp. 1,260.00 =Rp. 410,760.00
- Pasir beton 0.5429 M3 Rp. 120,000.00 =Rp. 65,142.86
- Kerikil 0.7622 M3 Rp. 320,000.00 =Rp. 243,911.11
- Air 215.0000 Ltr Rp. 100.00 =Rp. 21,500.00

Tenaga
- Pekerja 1.6500 Oh Rp. 95,000.00 =Rp. 156,750.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 =Rp. 37,125.00
- Kepala tukang 0.0280 Oh Rp. 160,000.00 =Rp. 4,480.00
- Mandor 0.0830 Oh Rp. 130,000.00 =Rp. 10,790.00
Jumlah Rp. 950,458.97

21 Membuat 1 m 3 beton mutu f'c = 16,9 Mpa (K 200), slump (12 ± 2) cm, w/c = 0,61
Bahan
- Portland cement 352.0000 Kg Rp. 1,260.00 =Rp. 443,520.00
- Pasir beton 0.5221 M3 Rp. 120,000.00 =Rp. 62,657.14
- Kerikil 0.7637 M3 Rp. 320,000.00 =Rp. 244,385.19
- Air 215.0000 Ltr Rp. 100.00 =Rp. 21,500.00

Tenaga
- Pekerja 1.6500 Oh Rp. 95,000.00 =Rp. 156,750.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 =Rp. 37,125.00
- Kepala tukang 0.0280 Oh Rp. 160,000.00 =Rp. 4,480.00
- Mandor 0.0830 Oh Rp. 130,000.00 =Rp. 10,790.00
Jumlah Rp. 981,207.33

22 1 m3 Membuat sloop beton bertulang (110 kg besi + bekisting)


Bahan
- Kayu Kelas III 0.2700 M3 Rp. 3,500,000.00 = Rp. 945,000.00
- Paku 5 - 10 cm 2.0000 Kg Rp. 20,000.00 = Rp. 40,000.00
- Minyak bekisting 0.6000 Lt Rp. 30,000.00 = Rp. 18,000.00
- Besi beton polos 110.0000 Kg Rp. 12,500.00 = Rp. 1,375,000.00
- Kawat beton 3.0000 Kg Rp. 22,000.00 = Rp. 66,000.00
- Portland cement 336.0000 Kg Rp. 1,260.00 = Rp. 423,360.00
- Pasir beton 0.5400 M3 Rp. 120,000.00 = Rp. 64,800.00
- Kerikil 0.8100 M3 Rp. 320,000.00 = Rp. 259,200.00

Tenaga
- Pekerja 5.6500 Oh Rp. 95,000.00 = Rp. 536,750.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 = Rp. 37,125.00
- Tukang kayu 1.5600 Oh Rp. 135,000.00 = Rp. 210,600.00
- Tukang besi 1.4000 Oh Rp. 135,000.00 = Rp. 189,000.00
- Kepala tukang 0.3230 Oh Rp. 160,000.00 = Rp. 51,680.00
- Mandor 0.2830 Oh Rp. 130,000.00 = Rp. 36,790.00
Jumlah Rp. 4,253,305.00

23 1 m3 Membuat sloop beton bertulang (150 kg besi + bekisting)


Bahan
- Kayu Kelas III 0.2700 M3 Rp. 3,500,000.00 = Rp. 945,000.00
- Paku 5 - 10 cm 2.0000 Kg Rp. 20,000.00 = Rp. 40,000.00
- Minyak bekisting 0.6000 Lt Rp. 30,000.00 = Rp. 18,000.00
- Besi beton polos 150.0000 Kg Rp. 12,500.00 = Rp. 1,875,000.00
- Kawat beton 3.0000 Kg Rp. 22,000.00 = Rp. 66,000.00
- Portland cement 336.0000 Kg Rp. 1,260.00 = Rp. 423,360.00
- Pasir beton 0.5400 M3 Rp. 120,000.00 = Rp. 64,800.00
- Kerikil 0.8100 M 3
Rp. 320,000.00 = Rp. 259,200.00

Tenaga
- Pekerja 5.6500 Oh Rp. 95,000.00 = Rp. 536,750.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 = Rp. 37,125.00
- Tukang kayu 1.5600 Oh Rp. 135,000.00 = Rp. 210,600.00
- Tukang besi 1.4000 Oh Rp. 135,000.00 = Rp. 189,000.00
- Kepala tukang 0.3230 Oh Rp. 160,000.00 = Rp. 51,680.00
- Mandor 0.2830 Oh Rp. 130,000.00 = Rp. 36,790.00
Jumlah Rp. 4,753,305.00
24 1 m3 Membuat kolom beton bertulang (110 kg besi + bekisting)
Bahan
- Kayu Kelas III 0.4000 M3 Rp. 3,500,000.00 = Rp. 1,400,000.00
- Paku 5 - 10 cm 4.0000 Kg Rp. 20,000.00 = Rp. 80,000.00
- Minyak bekisting 2.0000 Lt Rp. 30,000.00 = Rp. 60,000.00
- Besi beton polos 110.0000 Kg Rp. 12,500.00 = Rp. 1,375,000.00
- Kawat beton 4.5000 Kg Rp. 22,000.00 = Rp. 99,000.00
- Portland cement 336.0000 Kg Rp. 1,260.00 = Rp. 423,360.00
- Pasir beton 0.5400 M3 Rp. 120,000.00 = Rp. 64,800.00
- Kerikil 0.8100 M3 Rp. 320,000.00 = Rp. 259,200.00
- Balok kayu kelas II 0.1500 M3 Rp. 5,000,000.00 = Rp. 750,000.00
- Plywood 9 mm 3.5000 Lembar Rp. 135,000.00 = Rp. 472,500.00
- Dolken kayu galam/Bambu P = 4 m 20.0000 Btg Rp. 10,000.00 = Rp. 200,000.00

Tenaga
- Pekerja 7.0500 Oh Rp. 95,000.00 = Rp. 669,750.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 = Rp. 37,125.00
- Tukang kayu 1.6500 Oh Rp. 135,000.00 = Rp. 222,750.00
- Tukang besi 2.1000 Oh Rp. 135,000.00 = Rp. 283,500.00
- Kepala tukang 0.4030 Oh Rp. 160,000.00 = Rp. 64,480.00
- Mandor 0.3530 Oh Rp. 130,000.00 = Rp. 45,890.00
Jumlah Rp. 6,507,355.00

25 1 m3 Membuat Plat beton bertulang (150 kg besi + bekisting)


Bahan
- Kayu Kelas III 0.4000 M3 Rp. 3,500,000.00 = Rp. 1,400,000.00
- Paku 5 - 10 cm 4.0000 Kg Rp. 20,000.00 = Rp. 80,000.00
- Minyak bekisting 2.0000 Lt Rp. 30,000.00 = Rp. 60,000.00
- Besi beton polos 150.0000 Kg Rp. 12,500.00 = Rp. 1,875,000.00
- Kawat beton 4.5000 Kg Rp. 22,000.00 = Rp. 99,000.00
- Portland cement 336.0000 Kg Rp. 1,260.00 = Rp. 423,360.00
- Pasir beton 0.5400 M3 Rp. 120,000.00 = Rp. 64,800.00
- Kerikil 0.8100 M3 Rp. 320,000.00 = Rp. 259,200.00
- Balok kayu kelas II 0.1500 M 3
Rp. 5,000,000.00 = Rp. 750,000.00
- Plywood 9 mm 3.5000 Lembar Rp. 135,000.00 = Rp. 472,500.00
- Dolken kayu galam/Bambu P = 4 m 20.0000 Btg Rp. 10,000.00 = Rp. 200,000.00

Tenaga
- Pekerja 7.0500 Oh Rp. 95,000.00 = Rp. 669,750.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 = Rp. 37,125.00
- Tukang kayu 1.6500 Oh Rp. 135,000.00 = Rp. 222,750.00
- Tukang besi 2.1000 Oh Rp. 135,000.00 = Rp. 283,500.00
- Kepala tukang 0.4030 Oh Rp. 160,000.00 = Rp. 64,480.00
- Mandor 0.3530 Oh Rp. 130,000.00 = Rp. 45,890.00
Jumlah Rp. 7,007,355.00
26 1 m3 Membuat kolom beton bertulang (200 kg besi + bekisting)
Bahan
- Kayu Kelas III 0.4000 M3 Rp. 3,500,000.00 = Rp. 1,400,000.00
- Paku 5 - 10 cm 4.0000 Kg Rp. 20,000.00 = Rp. 80,000.00
- Minyak bekisting 2.0000 Lt Rp. 30,000.00 = Rp. 60,000.00
- Besi beton polos 200.0000 Kg Rp. 12,500.00 = Rp. 2,500,000.00
- Kawat beton 4.5000 Kg Rp. 22,000.00 = Rp. 99,000.00
- Portland cement 336.0000 Kg Rp. 1,260.00 = Rp. 423,360.00
- Pasir beton 0.5400 M3 Rp. 120,000.00 = Rp. 64,800.00
- Kerikil 0.8100 M3 Rp. 320,000.00 = Rp. 259,200.00
- Balok kayu kelas II 0.1500 M3 Rp. 5,000,000.00 = Rp. 750,000.00
- Plywood 9 mm 3.5000 Lembar Rp. 135,000.00 = Rp. 472,500.00
- Dolken kayu galam/Bambu P = 4 m 20.0000 Btg Rp. 10,000.00 = Rp. 200,000.00

Tenaga
- Pekerja 7.0500 Oh Rp. 95,000.00 = Rp. 669,750.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 = Rp. 37,125.00
- Tukang kayu 1.6500 Oh Rp. 135,000.00 = Rp. 222,750.00
- Tukang besi 2.1000 Oh Rp. 135,000.00 = Rp. 283,500.00
- Kepala tukang 0.4030 Oh Rp. 160,000.00 = Rp. 64,480.00
- Mandor 0.3530 Oh Rp. 130,000.00 = Rp. 45,890.00
Jumlah Rp. 7,632,355.00

27 1 m3 Membuat balok beton bertulang (110 kg besi + bekisting)


Bahan
- Kayu Kelas III 0.3200 M3 Rp. 3,500,000.00 = Rp. 1,120,000.00
- Paku 5 - 10 cm 3.2000 Kg Rp. 20,000.00 = Rp. 64,000.00
- Minyak bekisting 1.6000 Lt Rp. 30,000.00 = Rp. 48,000.00
- Besi beton polos 110.0000 Kg Rp. 12,500.00 = Rp. 1,375,000.00
- Kawat beton 3.0000 Kg Rp. 22,000.00 = Rp. 66,000.00
- Portland cement 336.0000 Kg Rp. 1,260.00 = Rp. 423,360.00
- Pasir beton 0.5400 M3 Rp. 120,000.00 = Rp. 64,800.00
- Kerikil 0.8100 M3 Rp. 320,000.00 = Rp. 259,200.00
- Balok kayu kelas II 0.1400 M3 Rp. 5,000,000.00 = Rp. 700,000.00
- Plywood 9 mm 2.8000 Lembar Rp. 135,000.00 = Rp. 378,000.00
- Dolken kayu galam/Bambu P = 4 m 16.0000 Btg Rp. 10,000.00 = Rp. 160,000.00

Tenaga
- Pekerja 6.3500 Oh Rp. 95,000.00 = Rp. 603,250.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 = Rp. 37,125.00
- Tukang kayu 1.6500 Oh Rp. 135,000.00 = Rp. 222,750.00
- Tukang besi 1.4000 Oh Rp. 135,000.00 = Rp. 189,000.00
- Kepala tukang 0.3330 Oh Rp. 160,000.00 = Rp. 53,280.00
- Mandor 0.3180 Oh Rp. 130,000.00 = Rp. 41,340.00
Jumlah Rp. 5,805,105.00
28 1 m3 Membuat balok beton bertulang (150 kg besi + bekisting)
Bahan
- Kayu Kelas III 0.3200 M3 Rp. 3,500,000.00 = Rp. 1,120,000.00
- Paku 5 - 10 cm 3.2000 Kg Rp. 20,000.00 = Rp. 64,000.00
- Minyak bekisting 1.6000 Lt Rp. 30,000.00 = Rp. 48,000.00
- Besi beton polos 150.0000 Kg Rp. 12,500.00 = Rp. 1,875,000.00
- Kawat beton 3.0000 Kg Rp. 22,000.00 = Rp. 66,000.00
- Portland cement 336.0000 Kg Rp. 1,260.00 = Rp. 423,360.00
- Pasir beton 0.5400 M3 Rp. 120,000.00 = Rp. 64,800.00
- Kerikil 0.8100 M3 Rp. 320,000.00 = Rp. 259,200.00
- Balok kayu kelas II 0.1400 M3 Rp. 5,000,000.00 = Rp. 700,000.00
- Plywood 9 mm 2.8000 Lembar Rp. 135,000.00 = Rp. 378,000.00
- Dolken kayu galam/Bambu P = 4 m 16.0000 Btg Rp. 10,000.00 = Rp. 160,000.00

Tenaga
- Pekerja 6.3500 Oh Rp. 95,000.00 = Rp. 603,250.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 = Rp. 37,125.00
- Tukang kayu 1.6500 Oh Rp. 135,000.00 = Rp. 222,750.00
- Tukang besi 1.4000 Oh Rp. 135,000.00 = Rp. 189,000.00
- Kepala tukang 0.3330 Oh Rp. 160,000.00 = Rp. 53,280.00
- Mandor 0.3180 Oh Rp. 130,000.00 = Rp. 41,340.00
Jumlah Rp. 6,305,105.00

29 1 m3 Membuat balok beton bertulang (200 kg besi + bekisting)


Bahan
- Kayu Kelas III 0.3200 M3 Rp. 3,500,000.00 = Rp. 1,120,000.00
- Paku 5 - 10 cm 3.2000 Kg Rp. 20,000.00 = Rp. 64,000.00
- Minyak bekisting 1.6000 Lt Rp. 30,000.00 = Rp. 48,000.00
- Besi beton polos 200.0000 Kg Rp. 12,500.00 = Rp. 2,500,000.00
- Kawat beton 3.0000 Kg Rp. 22,000.00 = Rp. 66,000.00
- Portland cement 336.0000 Kg Rp. 1,260.00 = Rp. 423,360.00
- Pasir beton 0.5400 M3 Rp. 120,000.00 = Rp. 64,800.00
- Kerikil 0.8100 M 3
Rp. 320,000.00 = Rp. 259,200.00
- Balok kayu kelas II 0.1400 M3 Rp. 5,000,000.00 = Rp. 700,000.00
- Plywood 9 mm 2.8000 Lembar Rp. 135,000.00 = Rp. 378,000.00
- Dolken kayu galam/Bambu P = 4 m 16.0000 Btg Rp. 10,000.00 = Rp. 160,000.00

Tenaga
- Pekerja 6.3500 Oh Rp. 95,000.00 = Rp. 603,250.00
- Tukang batu 0.2750 Oh Rp. 135,000.00 = Rp. 37,125.00
- Tukang kayu 1.6500 Oh Rp. 135,000.00 = Rp. 222,750.00
- Tukang besi 1.4000 Oh Rp. 135,000.00 = Rp. 189,000.00
- Kepala tukang 0.3330 Oh Rp. 160,000.00 = Rp. 53,280.00
- Mandor 0.3180 Oh Rp. 130,000.00 = Rp. 41,340.00
Jumlah Rp. 6,930,105.00
30 1 m1 Membuat kolom praktis beton bertulang (11 x 15) cm
Bahan
- Kayu Kelas III 0.0020 M3 Rp. 3,500,000.00 = Rp. 7,000.00
- Paku 5 - 10 cm 0.0100 Kg Rp. 20,000.00 = Rp. 200.00
- Besi beton polos 3.0000 Kg Rp. 12,500.00 = Rp. 37,500.00
- Kawat beton 0.4500 Kg Rp. 22,000.00 = Rp. 9,900.00
- Portland cement 4.0000 Kg Rp. 1,260.00 = Rp. 5,040.00
- Pasir beton 0.0060 M3 Rp. 120,000.00 = Rp. 720.00
- Kerikil 0.0090 M3 Rp. 320,000.00 = Rp. 2,880.00

Tenaga
- Pekerja 0.1800 Oh Rp. 95,000.00 = Rp. 17,100.00
- Tukang batu 0.0200 Oh Rp. 135,000.00 = Rp. 2,700.00
- Tukang kayu 0.0200 Oh Rp. 135,000.00 = Rp. 2,700.00
- Tukang besi 0.0200 Oh Rp. 135,000.00 = Rp. 2,700.00
- Kepala tukang 0.0060 Oh Rp. 160,000.00 = Rp. 960.00
- Mandor 0.0090 Oh Rp. 130,000.00 = Rp. 1,170.00
Jumlah Rp. 90,570.00

31 1 m1 Membuat ring balok beton bertulang (10 x 15) cm


Bahan
- Kayu Kelas III 0.0030 M3 Rp. 3,500,000.00 = Rp. 10,500.00
- Paku 5 - 10 cm 0.0200 Kg Rp. 20,000.00 = Rp. 400.00
- Besi beton polos 3.6000 Kg Rp. 12,500.00 = Rp. 45,000.00
- Kawat beton 0.0500 Kg Rp. 22,000.00 = Rp. 1,100.00
- Portland cement 5.5000 Kg Rp. 1,260.00 = Rp. 6,930.00
- Pasir beton 0.0090 M3 Rp. 120,000.00 = Rp. 1,080.00
- Kerikil 0.0150 M3 Rp. 320,000.00 = Rp. 4,800.00

Tenaga
- Pekerja 0.2970 Oh Rp. 95,000.00 = Rp. 28,215.00
- Tukang batu 0.0330 Oh Rp. 135,000.00 = Rp. 4,455.00
- Tukang kayu 0.0330 Oh Rp. 135,000.00 = Rp. 4,455.00
- Tukang besi 0.0330 Oh Rp. 135,000.00 = Rp. 4,455.00
- Kepala tukang 0.0100 Oh Rp. 160,000.00 = Rp. 1,600.00
- Mandor 0.1500 Oh Rp. 130,000.00 = Rp. 19,500.00
` Jumlah Rp. 132,490.00

32 Pemasangan 1 m2 bekisting untuk pondasi


Bahan
- Kayu kelas III 0.0400 m3 Rp. 3,500,000.00 = Rp. 140,000.00
- Paku 5 - 10 cm 0.3000 kg Rp. 20,000.00 = Rp. 6,000.00
- Minyak bekisting 0.1000 Liter Rp. 30,000.00 = Rp. 3,000.00

Tenaga
- Pekerja 0.5200 Oh Rp. 95,000.00 = Rp. 49,400.00
- Tukang Kayu 0.2600 Oh Rp. 135,000.00 = Rp. 35,100.00
- Kepala Tukang 0.0260 Oh Rp. 160,000.00 = Rp. 4,160.00
- Mandor 0.0260 Oh Rp. 130,000.00 = Rp. 3,380.00
Jumlah Rp. 241,040.00

33 Pemasangan 1 m2 bekisting untuk sloof


Bahan
- Kayu kelas III 0.0450 m3 Rp. 3,500,000.00 = Rp. 157,500.00
- Paku 5 - 10 cm 0.3000 kg Rp. 20,000.00 = Rp. 6,000.00
- Minyak bekisting 0.1000 Liter Rp. 30,000.00 = Rp. 3,000.00

Tenaga
- Pekerja 0.5200 Oh Rp. 95,000.00 = Rp. 49,400.00
- Tukang Kayu 0.2600 Oh Rp. 135,000.00 = Rp. 35,100.00
- Kepala Tukang 0.0260 Oh Rp. 160,000.00 = Rp. 4,160.00
- Mandor 0.0260 Oh Rp. 130,000.00 = Rp. 3,380.00
Jumlah Rp. 258,540.00

34 Pemasangan 1 m2 bekisting untuk kolom


Bahan
- Kayu kelas III 0.0400 m3 Rp. 3,500,000.00 = Rp. 140,000.00
- Paku 5 - 12 cm 0.4000 kg Rp. 20,000.00 = Rp. 8,000.00
- Minyak bekisting 0.2000 Liter Rp. 30,000.00 = Rp. 6,000.00
- Balok kayu kelas II 0.0150 m3 Rp. 5,000,000.00 = Rp. 75,000.00
- Plywood 9 mm 0.3500 Lbr Rp. 135,000.00 = Rp. 47,250.00
- Dolken kayu Ø 8-10/400 cm 2.0000 Batang Rp. 10,000.00 = Rp. 20,000.00

Tenaga
- Pekerja 0.6600 Oh Rp. 95,000.00 = Rp. 62,700.00
- Tukang Kayu 0.3300 Oh Rp. 135,000.00 = Rp. 44,550.00
- Kepala Tukang 0.0330 Oh Rp. 160,000.00 = Rp. 5,280.00
- Mandor 0.0330 Oh Rp. 130,000.00 = Rp. 4,290.00
Jumlah Rp. 413,070.00

35 Pemasangan 1 m2 bekisting untuk balok


Bahan
- Kayu kelas III 0.0400 m3 Rp. 3,500,000.00 = Rp. 140,000.00
- Paku 5 - 12 cm 0.4000 kg Rp. 20,000.00 = Rp. 8,000.00
- Minyak bekisting 0.2000 Ltr Rp. 30,000.00 = Rp. 6,000.00
- Balok kayu kelas II 0.0180 m3 Rp. 5,000,000.00 = Rp. 90,000.00
- Plywood 9 mm 0.3500 Lbr Rp. 135,000.00 = Rp. 47,250.00
- Dolken kayu Ø 8-10/400 cm 2.0000 Btg Rp. 10,000.00 = Rp. 20,000.00

Tenaga
- Pekerja 0.6600 Oh Rp. 95,000.00 = Rp. 62,700.00
- Tukang Kayu 0.3300 Oh Rp. 135,000.00 = Rp. 44,550.00
- Kepala Tukang 0.0330 Oh Rp. 160,000.00 = Rp. 5,280.00
- Mandor 0.0330 Oh Rp. 130,000.00 = Rp. 4,290.00
Jumlah Rp. 428,070.00

36 Pemasangan 1 m2 bekisting untuk lantai


Bahan
- Kayu kelas III 0.0400 m3 Rp. 3,500,000.00 = Rp. 140,000.00
- Paku 5 - 12 cm 0.4000 kg Rp. 20,000.00 = Rp. 8,000.00
- Minyak bekisting 0.2000 Ltr Rp. 30,000.00 = Rp. 6,000.00
- Balok kayu kelas II 0.0150 m3 Rp. 5,000,000.00 = Rp. 75,000.00
- Plywood 9 mm 0.3500 Lbr Rp. 135,000.00 = Rp. 47,250.00
- Dolken kayu Ø 8-10/400 cm 6.0000 Btg Rp. 10,000.00 = Rp. 60,000.00

Tenaga
- Pekerja 0.6600 Oh Rp. 95,000.00 = Rp. 62,700.00
- Tukang Kayu 0.3300 Oh Rp. 135,000.00 = Rp. 44,550.00
- Kepala Tukang 0.0330 Oh Rp. 160,000.00 = Rp. 5,280.00
- Mandor 0.0330 Oh Rp. 130,000.00 = Rp. 4,290.00
Jumlah Rp. 453,070.00

37 10 Kg Memotong / Pasang Besi


Bahan
- Besi Beton 10.5000 Kg Rp. 12,500.00 =Rp. 131,250.00
- Kawat Beton 0.1500 Kg Rp. 22,000.00 =Rp. 3,300.00
Tenaga
- Pekerja 0.0700 Oh Rp. 95,000.00 =Rp. 6,650.00
- Tukang Besi 0.0700 Oh Rp. 135,000.00 =Rp. 9,450.00
- Kepala tukang 0.0070 Oh Rp. 160,000.00 =Rp. 1,120.00
Mandor 0.0040 Oh Rp. 130,000.00 =Rp. 520.00
Jumlah / 10 kg Rp. 152,290.00
Analisa biaya konstruksi pekerjaan pasangan dinding
38 1 m2 Pasangan bata merah tebal 1/2 bata , 1 Pc : 4 Ps
Bahan
- Bata merah 5 x 11 x 22 70.0000 Buah Rp. 850.00 = Rp. 59,500.00
- Portland cement 11.5000 Kg Rp. 1,260.00 = Rp. 14,490.00
- Pasir pasang 0.0430 M3 Rp. 120,000.00 = Rp. 5,160.00

Tenaga
- Pekerja 0.3000 Oh Rp. 95,000.00 = Rp. 28,500.00
- Tukang batu 0.1000 Oh Rp. 135,000.00 = Rp. 13,500.00
- Kepala tukang 0.0100 Oh Rp. 160,000.00 = Rp. 1,600.00
- Mandor 0.0150 Oh Rp. 130,000.00 = Rp. 1,950.00
Jumlah Rp. 124,700.00

39 1 m2 Pasangan bata merah tebal 1/2 bata , 1 Pc : 5 Ps


Bahan
- Bata merah 5 x 11 x 22 70.0000 Buah Rp. 850.00 = Rp. 59,500.00
- Portland cement 9.6800 Kg Rp. 1,260.00 = Rp. 12,196.80
- Pasir pasang 0.0450 M3 Rp. 120,000.00 = Rp. 5,400.00

Tenaga
- Pekerja 0.3000 Oh Rp. 95,000.00 = Rp. 28,500.00
- Tukang batu 0.1000 Oh Rp. 135,000.00 = Rp. 13,500.00
- Kepala tukang 0.0100 Oh Rp. 160,000.00 = Rp. 1,600.00
- Mandor 0.0150 Oh Rp. 130,000.00 = Rp. 1,950.00
Jumlah Rp. 122,646.80

40 1 m2 Pasangan Batako Sp. 1:4 Pasangan 1/2 Bt


Bahan
- Batako 34.0000 Bh Rp. 1,500.00 = Rp. 51,000.00
- Portland cement 6.1500 Kg Rp. 1,260.00 = Rp. 7,749.00
- Pasir 0.0120 M3 Rp. 160,000.00 = Rp. 1,920.00

Tenaga
- Pekerja 0.0680 Oh Rp. 95,000.00 = Rp. 6,460.00
- Tukang batu 0.0060 Oh Rp. 135,000.00 = Rp. 810.00
- Kepala tukang 0.0010 Oh Rp. 160,000.00 = Rp. 160.00
- Mandor 0.0030 Oh Rp. 130,000.00 = Rp. 390.00
Jumlah Rp. 68,489.00

41 1 m2 Plesteran 1 Pc : 4 Ps, tebal 15 mm


Bahan
- Portland cement 6.2400 Kg Rp. 1,260.00 = Rp. 7,862.40
- Pasir plester 0.0240 M3 Rp. 120,000.00 = Rp. 2,880.00

Tenaga
- Pekerja 0.3000 Oh Rp. 95,000.00 = Rp. 28,500.00
- Tukang batu 0.1500 Oh Rp. 135,000.00 = Rp. 20,250.00
- Kepala tukang 0.0150 Oh Rp. 160,000.00 = Rp. 2,400.00
- Mandor 0.0150 Oh Rp. 130,000.00 = Rp. 1,950.00
Jumlah Rp. 63,842.40

42 1 m2 Plesteran 1 Pc : 5 Ps, tebal 15 mm


Bahan
- Portland cement 5.1840 Kg Rp. 1,260.00 = Rp. 6,531.84
- Pasir plester 0.0260 M3 Rp. 120,000.00 = Rp. 3,120.00

Tenaga
- Pekerja 0.3000 Oh Rp. 95,000.00 = Rp. 28,500.00
- Tukang batu 0.1500 Oh Rp. 135,000.00 = Rp. 20,250.00
- Kepala tukang 0.0150 Oh Rp. 160,000.00 = Rp. 2,400.00
- Mandor 0.0150 Oh Rp. 130,000.00 = Rp. 1,950.00
Jumlah Rp. 62,751.84

43 1 m2 Acian
Bahan
- Portland cement 3.2500 Kg Rp. 1,260.00 = Rp. 4,095.00

Tenaga
- Pekerja 0.2000 Oh Rp. 95,000.00 = Rp. 19,000.00
- Tukang batu 0.1000 Oh Rp. 135,000.00 = Rp. 13,500.00
- Kepala tukang 0.0100 Oh Rp. 160,000.00 = Rp. 1,600.00
- Mandor 0.0100 Oh Rp. 130,000.00 = Rp. 1,300.00
Jumlah Rp. 39,495.00

Analisa Biaya Konstruksi Pekerjaan Kayu


44 Membuat dan memasang 1 m 3 kusen pintu dan kusen jendela Kayu, Kayu II
Bahan
- Kayu Kelas II 1.2000 M3 Rp. 5,000,000.00 = Rp. 6,000,000.00
- Paku 10 cm 1.2500 Kg Rp. 20,000.00 = Rp. 25,000.00
- Lem Kayu 1.0000 Kg Rp. 31,500.00 = Rp. 31,500.00

Tenaga
- Pekerja 6.0000 Oh Rp. 95,000.00 = Rp. 570,000.00
- Tukang kayu 18.0000 Oh Rp. 135,000.00 = Rp. 2,430,000.00
- Kepala tukang 1.8000 Oh Rp. 160,000.00 = Rp. 288,000.00
- Mandor 0.3000 Oh Rp. 130,000.00 = Rp. 39,000.00
Jumlah Rp. 9,383,500.00

45 Membuat dan memasang 1 m 2 Daun pintu panel, Kayu kelas II


Bahan
- Kayu Kelas II 0.0400 M3 Rp. 5,000,000.00 = Rp. 200,000.00
- Lem Kayu 0.5000 Kg Rp. 31,500.00 = Rp. 15,750.00

Tenaga
- Pekerja 1.0000 Oh Rp. 95,000.00 = Rp. 95,000.00
- Tukang kayu 3.0000 Oh Rp. 135,000.00 = Rp. 405,000.00
- Kepala tukang 0.3000 Oh Rp. 160,000.00 = Rp. 48,000.00
- Mandor 0.0500 Oh Rp. 130,000.00 = Rp. 6,500.00
Jumlah Rp. 770,250.00

46 Membuat dan memasang1 m 2 pintu dan jendela kaca 5 mm, Kayu Kelas II
Bahan
- Kayu Kelas II 0.0120 M3 Rp. 5,000,000.00 = Rp. 60,000.00
- Lem Kayu 0.3000 Kg Rp. 31,500.00 = Rp. 9,450.00
- Kaca 5 mm 1.0000 M2 Rp. 165,000.00 = Rp. 165,000.00

Tenaga
- Pekerja 0.8000 Oh Rp. 95,000.00 = Rp. 76,000.00
- Tukang kayu 2.4000 Oh Rp. 135,000.00 = Rp. 324,000.00
- Kepala tukang 0.2400 Oh Rp. 160,000.00 = Rp. 38,400.00
- Mandor 0.0400 Oh Rp. 130,000.00 = Rp. 5,200.00
Jumlah Rp. 678,050.00

47 Membuat dan memasang1 m 2 jendela dan ventilasi kaca mati 5 mm


Bahan
- Kaca 5 mm 1.0000 M2 Rp. 165,000.00 = Rp. 165,000.00

Tenaga
- Pekerja 0.0150 Oh Rp. 95,000.00 = Rp. 1,425.00
- Tukang kayu 0.1500 Oh Rp. 135,000.00 = Rp. 20,250.00
- Kepala tukang 0.0150 Oh Rp. 160,000.00 = Rp. 2,400.00
- Mandor 0.0008 Oh Rp. 130,000.00 = Rp. 97.50
Jumlah Rp. 189,172.50

48 1 m2 Pasang jalusi kusen, Kayu kelas II


Bahan
- Kayu Kelas II 0.0600 M3 Rp. 5,000,000.00 = Rp. 300,000.00
- Paku biasa 1/2" x 1" 0.1500 Kg Rp. 22,000.00 = Rp. 3,300.00

Tenaga
- Pekerja 0.6700 Oh Rp. 95,000.00 = Rp. 63,650.00
- Tukang kayu 2.0000 Oh Rp. 135,000.00 = Rp. 270,000.00
- Kepala tukang 0.2000 Oh Rp. 160,000.00 = Rp. 32,000.00
- Mandor 0.3350 Oh Rp. 130,000.00 = Rp. 43,550.00
Jumlah Rp. 712,500.00

49 Membuat dan memasang Kusen Aluminium


Bahan
Profil alluminium 1.1000 m Rp. 35,000.00 = Rp. 38,500.00
Skrup Fixer 2.0000 buah Rp. 1,500.00 = Rp. 3,000.00
Sealant 0.0600 tube Rp. 225,000.00 = Rp. 13,500.00

Tenaga
Pekerja 0.0430 Oh Rp. 95,000.00 = Rp. 4,085.00
Tukang besi 0.0430 Oh Rp. 135,000.00 = Rp. 5,805.00
Kepala tukang 0.0043 Oh Rp. 160,000.00 = Rp. 688.00
Mandor 0.0021 Oh Rp. 130,000.00 = Rp. 273.00
Jumlah Rp. 65,851.00

50 Membuat dan memasang Pintu Kaca Aluminium


Bahan
Pintu aluminium 4.4000 m Rp. 105,000.00 = Rp. 462,000.00
Profil Kaca 4.5000 m2 Rp. 235,000.00 = Rp. 1,057,500.00
Sealant 0.2700 tube Rp. 225,000.00 = Rp. 60,750.00

Tenaga
Pekerja 0.0850 Oh Rp. 95,000.00 = Rp. 8,075.00
Tukang besi 0.0850 Oh Rp. 135,000.00 = Rp. 11,475.00
Kepala tukang 0.0080 Oh Rp. 160,000.00 = Rp. 1,280.00
Mandor 0.0040 Oh Rp. 130,000.00 = Rp. 520.00
Jumlah Rp. 1,601,600.00

51 Memasang 1 m3 konstruksi kuda-kuda konvensional, Kayu Kelas II


Bahan
- Kayu Kelas II (cempaka) 1.1000 M3 Rp. 5,000,000.00 = Rp. 5,500,000.00
- Besi strip tebal 5 mm 15.0000 Kg Rp. 12,500.00 = Rp. 187,500.00
- Baut 12 mm 4.0000 bh Rp. 12,000.00 = Rp. 48,000.00
- Paku biasa 12 cm 5.6000 Kg Rp. 20,000.00 = Rp. 112,000.00

Tenaga
- Pekerja 4.0000 Oh Rp. 95,000.00 = Rp. 380,000.00
- Tukang kayu 12.0000 Oh Rp. 135,000.00 = Rp. 1,620,000.00
- Kepala tukang 1.2000 Oh Rp. 160,000.00 = Rp. 192,000.00
- Mandor 0.2000 Oh Rp. 130,000.00 = Rp. 26,000.00
Jumlah Rp. 8,065,500.00

52 Memasang 1 m3 konstruksi gordeng, Kayu Kelas II


Bahan
- Kayu Kelas II 1.1000 M3 Rp. 5,000,000.00 = Rp. 5,500,000.00
- Paku biasa 12 cm 3.0000 Kg Rp. 20,000.00 = Rp. 60,000.00

Tenaga
- Pekerja 4.0000 Oh Rp. 95,000.00 = Rp. 380,000.00
- Tukang kayu 10.0000 Oh Rp. 135,000.00 = Rp. 1,350,000.00
- Kepala tukang 1.2000 Oh Rp. 160,000.00 = Rp. 192,000.00
- Mandor 0.3350 Oh Rp. 130,000.00 = Rp. 43,550.00
Jumlah Rp. 7,713,050.00

53 Memasang 1 m3 konstruksi gordeng, Kayu Kelas III


Bahan
- Kayu Kelas III 1.1000 M3 Rp. 3,500,000.00 = Rp. 3,850,000.00
- Paku biasa 12 cm 3.0000 Kg Rp. 20,000.00 = Rp. 60,000.00

Tenaga
- Pekerja 4.0000 Oh Rp. 95,000.00 = Rp. 380,000.00
- Tukang kayu 10.0000 Oh Rp. 135,000.00 = Rp. 1,350,000.00
- Kepala tukang 1.2000 Oh Rp. 160,000.00 = Rp. 192,000.00
- Mandor 0.3350 Oh Rp. 130,000.00 = Rp. 43,550.00
Jumlah Rp. 5,875,550.00

54 Memasang 1 m1 lisplank ukuran (3 x 0,3) cm, Kayu kelas II


Bahan
- Kayu kelas II 0.0108 M3 Rp. 5,000,000.00 = Rp. 54,000.00
- Paku biasa 5 dan 7 cm 0.1000 Kg Rp. 20,000.00 = Rp. 2,000.00

Tenaga
- Pekerja 0.1000 Oh Rp. 95,000.00 = Rp. 9,500.00
- Tukang kayu 0.2000 Oh Rp. 135,000.00 = Rp. 27,000.00
- Kepala tukang 0.0200 Oh Rp. 160,000.00 = Rp. 3,200.00
- Mandor 0.0050 Oh Rp. 130,000.00 = Rp. 650.00
Jumlah Rp. 96,350.00

Analisa Biaya Konstruksi Pekerjaan Penutup Lantai dan Dinding


55 Memasang 1 m2 lantai keramik ukuran (40 x 40) cm
Bahan
- Keramik 40 x 40 cm 1.0000 Dos Rp. 75,000.00 = Rp. 75,000.00
- Portland cement 8.1900 Kg Rp. 1,260.00 = Rp. 10,319.40
- Pasir pasang 0.0450 M3 Rp. 120,000.00 = Rp. 5,400.00
- Semen Warna 0.5000 Kg Rp. 12,000.00 = Rp. 6,000.00
Tenaga
- Pekerja 0.7000 Oh Rp. 95,000.00 = Rp. 66,500.00
- Tukang batu 0.3500 Oh Rp. 135,000.00 = Rp. 47,250.00
- Kepala tukang 0.0350 Oh Rp. 160,000.00 = Rp. 5,600.00
- Mandor 0.0350 Oh Rp. 130,000.00 = Rp. 4,550.00
Jumlah Rp. 220,619.40

56 Memasang 1 m2 lantai keramik Granito ukuran (40 x 40) cm


Bahan
- Ubin Granito 6.9000 Bh Rp. 56,500.00 = Rp. 389,850.00
- Portland cement 8.1900 Kg Rp. 1,260.00 = Rp. 10,319.40
- Pasir pasang 0.0450 M3 Rp. 120,000.00 = Rp. 5,400.00
- Semen Warna 0.5000 Kg Rp. 12,000.00 = Rp. 6,000.00

Tenaga
- Pekerja 0.2500 Oh Rp. 95,000.00 = Rp. 23,750.00
- Tukang batu 0.1200 Oh Rp. 135,000.00 = Rp. 16,200.00
- Kepala tukang 0.0120 Oh Rp. 160,000.00 = Rp. 1,920.00
- Mandor 0.0013 Oh Rp. 130,000.00 = Rp. 162.50
Jumlah Rp. 453,601.90

57 Memasang 1 m2 lantai keramik ukuran 40 x 40 cm (anti slip)


Bahan
- Keramik 40 x 40 cm Antislip 1.0000 Dos Rp. 85,000.00 = Rp. 85,000.00
- Portland cement 8.1900 Kg Rp. 1,260.00 = Rp. 10,319.40
- Pasir pasang 0.0450 M3 Rp. 120,000.00 = Rp. 5,400.00
- Semen Warna 1.6200 Kg Rp. 12,000.00 = Rp. 19,440.00

Tenaga
- Pekerja 0.7000 Oh Rp. 95,000.00 = Rp. 66,500.00
- Tukang batu 0.3500 Oh Rp. 135,000.00 = Rp. 47,250.00
- Kepala tukang 0.0350 Oh Rp. 160,000.00 = Rp. 5,600.00
- Mandor 0.0350 Oh Rp. 130,000.00 = Rp. 4,550.00
Jumlah Rp. 244,059.40

58 1 m2 Pasang dinding keramik 30 x 30


Bahan
- Keramik 30 x 30 cm 1.0000 Dos Rp. 75,000.00 = Rp. 75,000.00
- Portland cement 8.1900 Kg Rp. 1,260.00 = Rp. 10,319.40
- Pasir pasang 0.0450 M3 Rp. 120,000.00 = Rp. 5,400.00
- Semen warna 1.6200 Kg Rp. 12,000.00 = Rp. 19,440.00

Tenaga
- Pekerja 0.7000 Oh Rp. 95,000.00 = Rp. 66,500.00
- Tukang batu 0.3500 Oh Rp. 135,000.00 = Rp. 47,250.00
- Kepala tukang 0.0350 Oh Rp. 160,000.00 = Rp. 5,600.00
- Mandor 0.0350 Oh Rp. 130,000.00 = Rp. 4,550.00
Jumlah Rp. 234,059.40

59 1 m2 Pasang dinding keramik 20 x 20


Bahan
Keramik 20 x 20 cm 1.0000 Dos Rp. 65,000.00 = Rp. 65,000.00
Portland cement 8.4000 Kg Rp. 1,260.00 = Rp. 10,584.00
Pasir pasang 0.0450 M3 Rp. 120,000.00 = Rp. 5,400.00
Semen warna 1.6200 Kg Rp. 12,000.00 = Rp. 19,440.00

Tenaga
Pekerja 0.7000 Oh Rp. 95,000.00 = Rp. 66,500.00
Tukang batu 0.3500 Oh Rp. 135,000.00 = Rp. 47,250.00
Kepala tukang 0.0350 Oh Rp. 160,000.00 = Rp. 5,600.00
Mandor 0.0350 Oh Rp. 130,000.00 = Rp. 4,550.00
Jumlah Rp. 224,324.00

60 Memasang 1 m2 rangka langit-langit (60 X 60) cm, Kayu kelas II


Bahan
- Kayu Kaso 4/6 0.0163 M3 Rp. 5,000,000.00 = Rp. 81,500.00
- Paku biasa 7 - 10 cm 0.2500 Kg Rp. 20,000.00 = Rp. 5,000.00

Tenaga
- Pekerja 0.2000 Oh Rp. 95,000.00 = Rp. 19,000.00
- Tukang kayu 0.3000 Oh Rp. 135,000.00 = Rp. 40,500.00
- Kepala tukang 0.0300 Oh Rp. 160,000.00 = Rp. 4,800.00
- Mandor 0.0100 Oh Rp. 130,000.00 = Rp. 1,300.00
Jumlah Rp. 152,100.00

61 Memasang 1 m2 Partisi PVC rangla Kanal C 2 sisi


Bahan
- Kanal C 1.2000 m Rp. 110,000.00 = Rp. 132,000.00
Shunda Plafond 2.0000 M2 140,000.00 = Rp. 280,000.00
- Sekrup 10.0000 Kg Rp. 300.00 = Rp. 3,000.00

Tenaga
- Pekerja 0.2500 Oh Rp. 95,000.00 = Rp. 23,750.00
- Tukang besi 0.0250 Oh Rp. 135,000.00 = Rp. 3,375.00
- Kepala tukang 0.0300 Oh Rp. 160,000.00 = Rp. 4,800.00
- Mandor 0.0100 Oh Rp. 130,000.00 = Rp. 1,300.00
Jumlah Rp. 448,225.00

62 Memasang 1 bh Door Closer


Bahan
Door closer 1.0000 m Rp. 395,000.00 = Rp. 395,000.00

Tenaga
Tukang Kayu 0.2000 Oh Rp. 135,000.00 = Rp. 27,000.00
Kepala Tukang 0.0200 Oh Rp. 160,000.00 = Rp. 3,200.00
Jumlah Rp. 425,200.00

63 Memasang 1 m2 rangka langit-langit (60 X 60) cm, Kayu kelas III


Bahan
- Kayu Kaso 4/6 kelas III 0.0163 M3 Rp. 3,500,000.00 = Rp. 57,050.00
- Paku biasa 7 - 10 cm 0.2500 Kg Rp. 20,000.00 = Rp. 5,000.00

Tenaga
- Pekerja 0.2000 Oh Rp. 95,000.00 = Rp. 19,000.00
- Tukang kayu 0.3000 Oh Rp. 135,000.00 = Rp. 40,500.00
- Kepala tukang 0.0300 Oh Rp. 160,000.00 = Rp. 4,800.00
- Mandor 0.0100 Oh Rp. 130,000.00 = Rp. 1,300.00
Jumlah Rp. 127,650.00

64 Memasang 1 m2 langit-langit tripleks ukuran (120 x 240) cm, tebal 4 mm


Bahan
- Tripleks, tebal 4 mm 0.3750 Lbr Rp. 75,000.00 = Rp. 28,125.00
- Paku tripleks 0.0300 Kg Rp. 24,000.00 = Rp. 720.00
Tenaga
- Pekerja 0.1000 Oh Rp. 95,000.00 = Rp. 9,500.00
- Tukang kayu 0.1000 Oh Rp. 135,000.00 = Rp. 13,500.00
- Kepala tukang 0.0100 Oh Rp. 160,000.00 = Rp. 1,600.00
- Mandor 0.0050 Oh Rp. 130,000.00 = Rp. 650.00
Jumlah Rp. 54,095.00

65 1 M2 Pemasangan Plafond Shunda PVC


Bahan
- Shunda Plafond 0.4750 Lbr Rp. 140,000.00 = Rp. 66,500.00
- Sekrup 10.0000 bh Rp. 300.00 = Rp. 3,000.00
List Sundha Plafond 1.5000 m Rp. 85,000.00 = Rp. 127,500.00
Tenaga
- Pekerja 0.1500 Oh Rp. 95,000.00 = Rp. 14,250.00
- Tukang kayu 0.1650 Oh Rp. 135,000.00 = Rp. 22,275.00
- Kepala tukang 0.0175 Oh Rp. 160,000.00 = Rp. 2,800.00
- Mandor 0.0120 Oh Rp. 130,000.00 = Rp. 1,560.00
Jumlah Rp. 237,885.00

66 1 m1 Pasang list plafond - kayu profil SP 4


Bahan
- Kayu Profil SP 4 1.0500 M1 Rp. 25,000.00 = Rp. 26,250.00

Tenaga
- Pekerja 0.0500 Oh Rp. 95,000.00 = Rp. 4,750.00
- Tukang kayu 0.0500 Oh Rp. 135,000.00 = Rp. 6,750.00
- Kepala tukang 0.0050 Oh Rp. 160,000.00 = Rp. 800.00
- Mandor 0.0030 Oh Rp. 130,000.00 = Rp. 390.00
Jumlah Rp. 38,940.00

Analisa biaya konstruksi pekerjaan penutup atap


67 1 m2 Pasang atap seng gelombang bjls 30
Bahan
- Seng gelombang bjls 30 0.7000 Lbr Rp. 55,000.00 = Rp. 38,500.00
- Paku seng 0.0200 Kg Rp. 22,000.00 = Rp. 440.00

Tenaga
- Pekerja 0.1500 Oh Rp. 95,000.00 = Rp. 14,250.00
- Tukang kayu 0.0700 Oh Rp. 135,000.00 = Rp. 9,450.00
- Kepala tukang 0.0080 Oh Rp. 160,000.00 = Rp. 1,280.00
- Mandor 0.0060 Oh Rp. 130,000.00 = Rp. 780.00
Jumlah Rp. 64,700.00

68 1 m2 Pasang atap nok seng


Bahan
- Seng plat 3" x 6 " bjls 28 0.3000 Lbr Rp. 50,000.00 = Rp. 15,000.00
- Paku biasa 1/2" x 1" 0.4000 Kg Rp. 22,000.00 = Rp. 8,800.00
Tenaga
- Pekerja 0.1500 Oh Rp. 95,000.00 = Rp. 14,250.00
- Tukang kayu 0.0700 Oh Rp. 135,000.00 = Rp. 9,450.00
- Kepala tukang 0.0080 Oh Rp. 160,000.00 = Rp. 1,280.00
- Mandor 0.0060 Oh Rp. 130,000.00 = Rp. 780.00
Jumlah Rp. 49,560.00

Analisa Biaya Konstruksi Pekerjaan Kunci dan Kaca

69 1 buah pasang kunci tanam pintu kebaya


Bahan
- Kunci Tanam besar 1.0000 Bh Rp. 375,000.00 = Rp. 375,000.00

Tenaga
- Pekerja 0.0100 Oh Rp. 95,000.00 = Rp. 950.00
- Tukang kayu 0.5000 Oh Rp. 135,000.00 = Rp. 67,500.00
- Kepala tukang 0.0500 Oh Rp. 160,000.00 = Rp. 8,000.00
- Mandor 0.0025 Oh Rp. 130,000.00 = Rp. 325.00
Jumlah Rp. 451,775.00

70 1 buah pasang kunci tanam


Bahan
- Kunci Tanam 1.0000 Bh Rp. 150,000.00 = Rp. 150,000.00

Tenaga
- Pekerja 0.0100 Oh Rp. 95,000.00 = Rp. 950.00
- Tukang kayu 0.5000 Oh Rp. 135,000.00 = Rp. 67,500.00
- Kepala tukang 0.0500 Oh Rp. 160,000.00 = Rp. 8,000.00
- Mandor 0.0025 Oh Rp. 130,000.00 = Rp. 325.00
Jumlah Rp. 226,775.00

71 1 Bh Pemasangan Handle Kunci


Bahan :
Handle Pintu 0.7500 Bh Rp. 65,000.00 = Rp. 48,750.00
Tenaga
Pekerja 0.0300 Oh Rp. 95,000.00 = Rp. 2,850.00
Tukang kayu 0.5200 Oh Rp. 135,000.00 = Rp. 70,200.00
Kepala tukang 0.0640 Oh Rp. 160,000.00 = Rp. 10,240.00
Mandor 0.0620 Oh Rp. 130,000.00 = Rp. 8,060.00
Jumlah Rp. 140,100.00

72 1 buah pasang engsel pintu


Bahan
- Engsel pintu 1.0000 Bh Rp. 38,000.00 = Rp. 38,000.00

Tenaga
- Pekerja 0.0150 Oh Rp. 95,000.00 = Rp. 1,425.00
- Tukang kayu 0.1500 Oh Rp. 135,000.00 = Rp. 20,250.00
- Kepala tukang 0.0150 Oh Rp. 160,000.00 = Rp. 2,400.00
- Mandor 0.0008 Oh Rp. 130,000.00 = Rp. 97.50
Jumlah Rp. 62,172.50

73 1 buah pasang engsel jendela


Bahan
- Engsel jendela 1.0000 Bh Rp. 28,000.00 = Rp. 28,000.00

Tenaga
- Pekerja 0.0100 Oh Rp. 95,000.00 = Rp. 950.00
- Tukang kayu 0.1000 Oh Rp. 135,000.00 = Rp. 13,500.00
- Kepala tukang 0.0100 Oh Rp. 160,000.00 = Rp. 1,600.00
- Mandor 0.0005 Oh Rp. 130,000.00 = Rp. 65.00
Jumlah Rp. 44,115.00

74 1 buah Grendel Jendela


Bahan
- Grendel jendela 1.0000 Bh Rp. 5,000.00 = Rp. 5,000.00

Tenaga
- Pekerja 0.0100 Oh Rp. 95,000.00 = Rp. 950.00
- Tukang kayu 0.1000 Oh Rp. 135,000.00 = Rp. 13,500.00
- Kepala tukang 0.0100 Oh Rp. 160,000.00 = Rp. 1,600.00
- Mandor 0.0005 Oh Rp. 130,000.00 = Rp. 65.00
Jumlah Rp. 21,115.00

75 1 buah Grendel pintu


Bahan
- Grendel pintu 1.0000 Bh Rp. 10,000.00 = Rp. 10,000.00

Tenaga
- Pekerja 0.0100 Oh Rp. 95,000.00 = Rp. 950.00
- Tukang kayu 0.1000 Oh Rp. 135,000.00 = Rp. 13,500.00
- Kepala tukang 0.0100 Oh Rp. 160,000.00 = Rp. 1,600.00
- Mandor 0.0005 Oh Rp. 130,000.00 = Rp. 65.00
Jumlah Rp. 26,115.00

76 1 buah Tarikan Jendela


Bahan
- Tarikan jendela 1.0000 Bh Rp. 6,000.00 = Rp. 6,000.00

Tenaga
- Pekerja 0.0100 Oh Rp. 95,000.00 = Rp. 950.00
- Tukang kayu 0.1000 Oh Rp. 135,000.00 = Rp. 13,500.00
- Kepala tukang 0.0100 Oh Rp. 160,000.00 = Rp. 1,600.00
- Mandor 0.0005 Oh Rp. 130,000.00 = Rp. 65.00
Jumlah Rp. 22,115.00

77 1 buah pasang hak angin


Bahan
- Hak angin 1.0000 Bh Rp. 7,500.00 = Rp. 7,500.00

Tenaga
- Pekerja 0.0150 Oh Rp. 95,000.00 = Rp. 1,425.00
- Tukang kayu 0.1500 Oh Rp. 135,000.00 = Rp. 20,250.00
- Kepala tukang 0.0500 Oh Rp. 160,000.00 = Rp. 8,000.00
- Mandor 0.0008 Oh Rp. 130,000.00 = Rp. 97.50
Jumlah Rp. 37,272.50
78 1 m2 pasang kaca bening 3 mm
Bahan
- Kaca bening 3 mm 1.1000 M2 Rp. 135,000.00 = Rp. 148,500.00

Tenaga
- Pekerja 0.0150 Oh Rp. 95,000.00 = Rp. 1,425.00
- Tukang kayu 0.1500 Oh Rp. 135,000.00 = Rp. 20,250.00
- Kepala tukang 0.0150 Oh Rp. 160,000.00 = Rp. 2,400.00
- Mandor 0.0008 Oh Rp. 130,000.00 = Rp. 97.50
Jumlah Rp. 172,672.50

79 1 m2 pasang kaca bening 5 mm


Bahan
- Kaca bening 5 mm 1.1000 M2 Rp. 165,000.00 = Rp. 181,500.00

Tenaga
- Pekerja 0.0150 Oh Rp. 95,000.00 = Rp. 1,425.00
- Tukang kayu 0.1500 Oh Rp. 135,000.00 = Rp. 20,250.00
- Kepala tukang 0.0150 Oh Rp. 160,000.00 = Rp. 2,400.00
- Mandor 0.0008 Oh Rp. 130,000.00 = Rp. 97.50
Jumlah Rp. 205,672.50
Analisa Biaya Konstruksi Pekerjaan Pengecatan
80 Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup)
BAHAN
Cat dasar Tembok 0.1200 Kg Rp. 30,000.00 = Rp. 3,600.00
Cat Penutup Tembok 0.1800 Kg Rp. 30,000.00 = Rp. 5,400.00

TENAGA
Pekerja 0.0280 OH Rp. 95,000.00 = Rp. 2,660.00
Tukang cat 0.0420 OH Rp. 135,000.00 = Rp. 5,670.00
Kepala tukang 0.0042 OH Rp. 160,000.00 = Rp. 672.00
Mandor 0.0030 OH Rp. 130,000.00 = Rp. 390.00
Jumlah Rp. 18,392.00

81 1 m2 pengecatan tembok baru ( 1 lapis plamir ), 1 lapis cat dasar, 2 lapis cat penutup
Bahan
- Plamir 0.1000 Kg Rp. 18,000.00 = Rp. 1,800.00
- Cat dasar 0.1000 Kg Rp. 30,000.00 = Rp. 3,000.00
- Cat tembok penutup 2 x 0.2600 Kg Rp. 75,000.00 = Rp. 19,500.00

Tenaga
- Pekerja 0.0200 Oh Rp. 95,000.00 = Rp. 1,900.00
- Tukang cat 0.0630 Oh Rp. 135,000.00 = Rp. 8,505.00
- Kepala tukang 0.0063 Oh Rp. 160,000.00 = Rp. 1,008.00
- Mandor 0.0025 Oh Rp. 130,000.00 = Rp. 325.00
Jumlah Rp. 36,038.00

82 1 m2 pengecatan tembok lama ( 1 lapis cat dasar ), 2 lapis cat cat penutup
Bahan
- Cat dasar 0.1200 Kg Rp. 30,000.00 = Rp. 3,600.00
- Cat tembok penutup 2 x 0.1800 Kg Rp. 75,000.00 = Rp. 13,500.00

Tenaga
- Pekerja 0.0280 Oh Rp. 95,000.00 = Rp. 2,660.00
- Tukang cat 0.0420 Oh Rp. 135,000.00 = Rp. 5,670.00
- Kepala tukang 0.0040 Oh Rp. 160,000.00 = Rp. 640.00
- Mandor 0.0030 Oh Rp. 130,000.00 = Rp. 390.00
Jumlah Rp. 26,460.00

83 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
BAHAN
- Cat menie 0.2000 Kg Rp. 45,000.00 = Rp. 9,000.00
- Plamuur 0.1500 Kg Rp. 18,000.00 = Rp. 2,700.00
- Cat dasar Kayu 0.1700 Kg Rp. 30,000.00 = Rp. 5,100.00
- Cat Penutup Kayu 0.2600 Kg Rp. 60,000.00 = Rp. 15,600.00
- Kuas 0.0100 Bh Rp. 12,000.00 = Rp. 120.00
- Pengencer 0.0300 Kg Rp. 25,000.00 = Rp. 750.00
- Ampelas 0.2000 Lbr Rp. 2,500.00 = Rp. 500.00

TENAGA
- Pekerja 0.0700 Oh Rp. 95,000.00 = Rp. 6,650.00
- Tukang cat 0.0090 Oh Rp. 135,000.00 = Rp. 1,215.00
- Kepala tukang 0.0060 Oh Rp. 160,000.00 = Rp. 960.00
- Mandor 0.0030 Oh Rp. 130,000.00 = Rp. 390.00
Jumlah Rp. 42,985.00

84 1 m2 Pekerjaan Teralis Hollow 2 x 4 cm


BAHAN
- Besi hollow 2 x 4x 1mm 6.0000 Ujung Rp. 115,000.00 = Rp. 690,000.00

TENAGA
- Pekerja 1.6700 Oh Rp. 95,000.00 = Rp. 158,650.00
- Tukang besi 1.6700 Oh Rp. 135,000.00 = Rp. 225,450.00
- Kepala tukang 0.1670 Oh Rp. 160,000.00 = Rp. 26,720.00
- Mandor 0.0830 Oh Rp. 130,000.00 = Rp. 10,790.00
Jumlah Rp. 1,111,610.00

85 1 m2 Pengecatan bidang kayu lama


BAHAN
- Cat Penutup Kayu 0.2600 Kg Rp. 60,000.00 = Rp. 15,600.00
- Kuas 0.0100 Bh Rp. 12,000.00 = Rp. 120.00
- Pengencer 0.0300 Kg Rp. 25,000.00 = Rp. 750.00
- Ampelas 0.2000 Lbr Rp. 2,500.00 = Rp. 500.00

TENAGA
- Pekerja 0.0700 Oh Rp. 95,000.00 = Rp. 6,650.00
- Tukang cat 0.0090 Oh Rp. 135,000.00 = Rp. 1,215.00
- Kepala tukang 0.0060 Oh Rp. 160,000.00 = Rp. 960.00
- Mandor 0.0030 Oh Rp. 130,000.00 = Rp. 390.00
Jumlah Rp. 26,185.00

86 1 Titik Pasang Instalasi Listrik


Bahan
- Kabel NGA 3 x 2,5 mm 10.000 m1 Rp. 12,500.00 = Rp. 125,000.00
- Pipa PVC 5/8" 4.000 m1 Rp. 2,500.00 = Rp. 10,000.00
- Las Doof 4.000 Bh Rp. 850.00 = Rp. 3,400.00
- Klam pipa 10.000 Bh 400.00 = Rp. 4,000.00
- T Dos PVC 2.000 Bh Rp. 75,000.00 = Rp. 150,000.00

Upah
- Tukang 0.5000 OH Rp. 135,000.00 = Rp. 67,500.00
Jumlah Rp. 359,900.00

87 Memasang 1 Bh Stop Kontak


Bahan
- Stop Kontak 1.0 Bh Rp. 15,000.00 = Rp. 15,000.00
- Perlengkapan 35% Hrg Rp. 15,000.00 = Rp. 5,250.00

Tenaga
- Tukang listrik 0.054 Oh Rp. 135,000.00 = Rp. 7,290.00
- Mandor 0.027 Oh Rp. 130,000.00 = Rp. 3,510.00
Jumlah Rp. 31,050.00

88 Memasang 1 Bh Saklar tunggal


Bahan
- Saklar tunggal 1.0 Bh Rp. 25,000.00 = Rp. 25,000.00
- Perlengkapan 35% Hrg Rp. 25,000.00 = Rp. 8,750.00

Tenaga
- Tukang listrik 0.054 Oh Rp. 135,000.00 = Rp. 7,290.00
- Mandor 0.027 Oh Rp. 130,000.00 = Rp. 3,510.00
Jumlah Rp. 44,550.00

89 Memasang 1 Bh Saklar ganda


Bahan
- Saklar ganda 1.0 Bh Rp. 35,000.00 = Rp. 35,000.00
- Perlengkapan 35% Hrg Rp. 35,000.00 = Rp. 12,250.00

Tenaga
- Tukang listrik 0.054 Oh Rp. 135,000.00 = Rp. 7,290.00
- Mandor 0.027 Oh Rp. 130,000.00 = Rp. 3,510.00
Jumlah Rp. 58,050.00

90 Memasang 1 Bh Mata lampu + Fitting tempel


Bahan
- Mata Lampu SL 11 Watt + Fitting 1.0 Bh Rp. 45,000.00 = Rp. 45,000.00
- Perlengkapan 35% Hrg Rp. 45,000.00 = Rp. 15,750.00

Tenaga
- Tukang listrik 0.054 Oh Rp. 135,000.00 = Rp. 7,290.00
- Mandor 0.027 Oh Rp. 130,000.00 = Rp. 3,510.00
Jumlah Rp. 71,550.00

91 Memasang 1 Bh MCB 10 Amper


Bahan
- MCB 10 amper 1.0 Bh Rp. 185,000.00 = Rp. 185,000.00
- Perlengkapan 35% Hrg Rp. 185,000.00 = Rp. 64,750.00
Tenaga
- Tukang listrik 0.054 Oh Rp. 135,000.00 = Rp. 7,290.00
- Mandor 0.027 Oh Rp. 130,000.00 = Rp. 3,510.00
Jumlah Rp. 260,550.00

Bitung, April 2021


Konsultan Perencana
Pejabat Pembuat Komitmen (PPK)

MAXI Z. RUMUAT, MP
NIP. 1966 0305 198803 1 014 Direktur

Anda mungkin juga menyukai