RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN SARANA & PRASARANA SALURAN KELURAHAN GIRIAN ATAS


LOKASI : KELURAHAN GIRIAN ATAS, LING. V RT. 18
SUMBER DANA : APBD - DAU
TAHUN ANGGARAN : 2023

Harga Satuan Jumlah


No Jenis Pekerjaan Sat VOL
(Rp) (Rp)
I PEKERJAAN PERSIAPAN 7,895,895.00
1 Papan Nama Proyek Ls 1.00 400,000.00 400,000.00
2 Biaya K3 Ls 1.00 500,000.00 500,000.00
3 Pengukuran Kembali (Uitzet Trase Saluran) Ls 1.00 700,000.00 700,000.00
4 Pembersihan Lokasi Ls 1.00 2,000,000.00 2,000,000.00
5 Mobilisasi dan Demobilisasi Peralatan Ls 1.00 400,000.00 400,000.00
6 Pembongkaran Rabat Beton/jalan m3 2.84 981,000.00 2,781,135.00
7 Pembongkaran Beton Bertulang m3 0.47 1,308,000.00 614,760.00
8 Pengadaan Air Kerja Ls 1.00 500,000.00 500,000.00

II PEKERJAAN SALURAN DRAINASE 69,879,697.46


1 Galian Tanah Biasa m3 81.65 56,400.00 4,605,060.00
2 Pasang Bekisting m2 117.04 190,250.00 22,266,860.00
3 Pasang Dinding Batu Kali/Pecah (1 PC : 4 Ps) m3 24.38 927,990.00 22,624,396.20
4 Cor Lantai beton (1 PC : 2 Ps : 3 krk) m3 5.75 981,610.00 5,644,257.50
5 Plesteran (1 PC : 3 Ps, tebal 15 mm) m2 146.2 82,118.60 12,005,739.32
6 Acian m2 146.2 18,696.20 2,733,384.44

III PEKERJAAN WHOLE BAK 4,663,922.29


1 Galian Tanah Biasa m3 3.84 56,400.00 216,576.00
2 Pasang Bekisting m2 5.61 190,250.00 1,067,302.50
3 Pasang Dinding Batu Kali/Pecah (1 PC : 4 Ps) m3 1.14 927,990.00 1,057,908.60
4 Cor Lantai beton (1 PC : 2 Ps : 3 krk) m3 0.24 981,610.00 235,586.40
5 Plesteran (1 PC : 3 Ps, tebal 15 mm) m2 6.81 82,118.60 559,227.67
6 Acian m2 6.81 18,696.20 127,321.12
7 Manhole (Rangka Besi) set 2.00 700,000.00 1,400,000.00

IV PEKERJAAN PLAT DUIKER 4,740,690.00


1 Pasang Bekisting Plat m2 9.30 153,560.00 1,428,108.00
2 Pembesian kg 131.00 18,543.00 2,429,133.00
3 Cor beton (1 PC : 2 Ps : 3 krk) m3 0.90 981,610.00 883,449.00

V PEKERJAAN LAIN-LAIN 2,800,000.00


1 Pembersihan Sedimen Badan Jalan Ls 1.00 400,000.00 400,000.00
2 Pembersihan Akhir Ls 1.00 600,000.00 600,000.00
3 Laporan Kegiatan dan As Built Drawing set 1.00 1,500,000.00 1,500,000.00
4 Laporan Dokumentasi set 1.00 300,000.00 300,000.00

BITUNG, MEI 2023


CV. MAJU BERSAMA ABADI

HENCE ADRIAN MAILANGKAY


DIREKTUR