SUB TOTAL
NO PEKERJAAN VOL. SAT. BAHAN ALAT UPAH Jumlah
Dana 2 Dana 1 Dana 2 Dana 1 Dana 2 Dana 1
6 Pasangan Tegel K.Mandi 20 x 20 cm 0.95 M
2
Upah :
0.4000 Pekerja HOK 0.378
0.2000 Tukang batu HOK 0.189
0.0100 Mandor HOK 0.009
Bahan :
1.0000 Tegel 20 x 20 cm dos 0.945
0.1300 Semen @ 50 kg Zak 0.123
0.0230 Pasir pasang M³ 0.022