Anda di halaman 1dari 72

ANALISA TINGKAT KERUSAKAN

PADA KOMPONEN/ SUB KOMPONEN BANGUNAN GEDUNG


BANTUAN REHABILITASI GEDUNG SMP NEGERI 1 RONGGUR NIHUTA
TAHUN 2017

Nama Sekolah SMP NEGERI 1 RONGGUR NIHUTA Jenis Bangunan


Alamat Sekolah RONGGUR NIHUTA 1 lantai (√ ) 2 lantai ( ) 3 lantai ( )
Propinsi SUMATERA UTARA Rencana Rehab
Kab/ Kota SAMOSIR 1 lantai ( √ ) 2 lantai ( ) 3 lantai ( )
Tlp/ Fax/ e- mail Bantuan Rehab Gedung
Luas Ruang & Jumlah Direhab Nama Ruang Tahun Dibangun Rehab Ke
Type Bangunan : Permanen

BOBOT %
NO KOMPONEN BANGUNAN SUB KOMPONEN BANGUNAN
Terhadap Seluruh Bangunan Tingkat Kerusakan (%) Nilai Kerusakan (%)

(a) (b) (c) (d) (e) f = (d x e)


1 PONDASI Pondasi 12.00 - -
2 STRUKTUR Kolom dan Balok 19.00 - -
Plesteran 2.00 - -
3 ATAP Kuda- kuda 5.50 - -
Gording + listPlank 2.00 20.00 0.40
Penutup Atap 4.00 100.00 4.00
4 PLAFOND Rangka Plafond 4.00 30.00 1.20
Penutup Plafond 5.00 100.00 5.00
5 DINDING batu bata/ Batako- Dinding 7.00 - -
Plesteran 3.00 - -
Jendela Kaca 2.50 100.00 2.50
Pintu 3.00 100.00 3.00
Kusen 3.00 - -
6 LANTAI Penutup Lantai 10.50 100.00 10.50
7 UTILITAS Instalasi Listrik 4.00 100.00 4.00
Instalasi Air 3.00 - -
Drainase/ Limbah 1.50 - -
8 FINISHING Finishing Struktur 1.00 100.00 1.00
Finishing Plafond 3.00 100.00 3.00
Finishing Dinding 2.50 100.00 2.50
Finishing Kusen/ daun 2.50 100.00 2.50
Jumlah 100.00
Nilai Tingkat Kerusakan (%) (a) 39.60

Kesimpulan Analisa Hasil Pengamatan Lapangan


A. Jenis Perawatan : Sedang Ringan ≤ 30 %
B. Nilai Kerusakan : 39.60 % Sedang 31% - 45%
C. Luas Ruangan di Rehab : 302.12 Berat 46% - 65%
D. Harga satuan Wilayah : 1,500,000.00
E. Perkiraan Biaya Rp. : 179,459,280.00
Terbilang :

Mengetahui/ Menyetujui …………………………………,………………………2017


Kepala Sekolah Tim Teknis

(…………………………………………….) (…………………………………………….)
RENCANA ANGGARAN BIAYA
NAGORI : PARIKSABUNGAN
KECAMATAN : DOLOK PARDAMEAN
KABUPATEN : SIMALUNGUN
PROVINSI : SUMATERA UTARA
NO RAB : 1
JENIS PEKERJAAN : PEMBANGUNAN TAMAN HUTAN SIMARJARUNJUNG
PEKERJAAN : PEMBANGUNAN KIOS
VULUME : 18 X 5 METER
DANA / TAHUN : APBN / 2021

JUMLAH
HARGA HARGA SATUAN HARGA SATUAN JUMAH HARGA TOTAL JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN SATUAN UPAH BAHAN UPAH SATUAN BAHAN HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7 8 9 10

I. PEKERJAAN PENDAHULUAN
1. Bowplank / Pengukuran A. 2.2.1.14 46.00 M' 23,950.00 47,859.00 1,101,700.00 2,201,514.00 3,303,214.00
2. Papan Proyek - 1.00 Ls 200,000.00 200,000.00 200,000.00
JUMLAH I ……………………. 1,101,700.00 2,401,514.00 3,503,214.00
II. PEKERJAAN TANAH
1. Pekerjaan Galian Pondasi A. 2.3.1.1 17.35 M³ 78,250.00 1,357,637.50 - 1,357,637.50
2. Pek. Urugan Pasir di Bawah Lantai A. 2.3.1.11 6.60 M³ 31,300.00 159,120.00 206,580.00 1,050,192.00 1,256,772.00
3. Urugan Kembali Galian Pondasi A. 2.3.1.9 4.18 M³ 56,500.00 235,935.71 - 235,935.71
JUMLAH II ……………………. 1,800,153.21 1,050,192.00 2,850,345.21
III. PEKERJAAN STRUKTUR KIOS
A Pekerjaan Pondasi
1. Pasang Pondasi Batu Kosong A. 3.2.1.9 2.75 M³ 134,940.00 453,859.20 371,085.00 1,248,112.80 1,619,197.80
2. Pasangan Pondasi Batu Belah/Batu Kali 1 ; 4 A. 3.2.1.2 9.63 M³ 259,500.00 677,309.00 2,497,687.50 6,519,099.13 9,016,786.63
B Pekerjaan Beton Bertulang
1. Sloof Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 25 Cm
1.1. Cor Sloof A. 4.1.1.7 2.75 M³ 212,430.00 947,666.00 584,182.50 2,606,081.50 3,190,264.00
1.2. Pembesian A. 4.1.1.17 296.00 kg 1,683.00 13,363.50 498,168.00 3,955,596.00 4,453,764.00
1.3. Bekisting A. 4.1.1.21 27.50 M2 89,960.00 45,795.00 2,473,900.00 1,259,362.50 3,733,262.50
2. Kolom Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 20 Cm
2.1. Cor Kolom Beton A. 4.1.1.7 2.16 M³ 212,430.00 947,666.00 458,423.94 2,045,063.23 2,503,487.17
2.2. Pembesian A. 4.1.1.17 380.00 kg 1,683.00 13,363.50 639,540.00 5,078,130.00 5,717,670.00
2.3. Bekisting A. 4.1.1.22 21.58 M2 114,180.00 88,631.67 2,464,004.40 1,912,671.37 4,376,675.77
3. Ring Balok Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 25
3.1. Cor Ring Balok Beton A. 4.1.1.7 3.25 M³ 212,430.00 947,666.00 690,397.50 3,079,914.50 3,770,312.00
3.2. Pembesian A. 4.1.1.17 389.00 kg 1,683.00 13,363.50 654,687.00 5,198,401.50 5,853,088.50
3.3. Bekisting A. 4.1.1.23 32.50 M2 114,180.00 91,128.67 3,710,850.00 2,961,681.67 6,672,531.67
JUMLAH III ……………………. 15,042,925.84 35,864,114.19 50,907,040.03
IV. PEKERJAAN ARSITEKTUR
A. Pekerjaan Dinding
1. Pasangan Dinding Batu Bata 1/2 Bata 1 : 4 A. 4.4.1.9 112.09 M2 45,250.00 66,310.70 5,072,072.50 7,432,766.36 12,504,838.86
2. Plesteran Dinding Batu Bata 1 : 4 A. 4.4.2.4 224.18 M2 51,900.00 11,244.00 11,634,942.00 2,520,679.92 14,155,621.92
B. Pekerjaan Pintu Kaca dan Jendela Kaca Bingkai Alumunium
1. Pekerjaan Kusen Pintu dan Jendela Alumunium A. 4.2.1.11 76.80 M' 10,292.00 113,390.00 790,425.60 8,708,352.00 9,498,777.60
2. Pekerjaan Bingkai Aluminium A. 4.2.1.13 44.50 M2 20,520.00 332,605.00 913,140.00 14,800,922.50 15,714,062.50
3. Pekerjaan Kaca 10mm A. 4.6.2.17.a 44.50 M2 22,100.00 197,305.00 983,450.00 8,780,072.50 9,763,522.50
4 Handle Pintu Kaca Terpasang 8.00 bh 450,000.00 3,600,000.00 3,600,000.00
5 Kunci Pintu Alumunium dan Kaca Terpasang 3.00 bh 320,000.00 960,000.00 960,000.00
D. Pekerjaan Plafound
1. Pekerjaan Rangka A. 4.6.1.20 140.00 M2 30,600.00 91,850.00 4,284,000.00 12,859,000.00 17,143,000.00
2. Pekerjaan Plafound Triplek 6mm A. 4.5.1.5 140.00 M2 30,600.00 33,924.00 4,284,000.00 4,749,360.00 9,033,360.00
E Pekerjaan Atap, Talang dan Listplank
1. Pekerjaan Rangka Atap A. 2.3.1.1 166.65 M2 28,350.00 84,485.60 4,724,499.15 14,079,440.75 18,803,939.90
2. Pekerjaan Atap A. 2.3.1.14 166.65 M2 23,700.00 46,400.00 3,949,581.30 7,732,513.60 11,682,094.90
3. Pekerjaan Rabung A. 4.5.2.37 29.43 M 46,640.00 34,040.00 1,372,615.20 1,001,797.20 2,374,412.40
4. Pekerjaan Lisplank H. Terpasang 74.96 M - 25,000.00 - 1,874,000.00 1,874,000.00
F Pekerjaan Lantai dan Pelapis
1. Lantai Kerja Beton Cor 1 : 3 : 5 Dibawah Lantai A. A. 4.1.1.5 3.47 M³ 212,430.00 885,864.00 737,981.82 3,077,491.54 3,815,473.36
2. Keramik Lantai Uk. 40 x 40 cm A. 4.4.3.7 340.00 M2 43,380.00 95,288.25 14,749,200.00 32,398,005.00 47,147,205.00
3. Keramik dinding Uk 20 x 40 cm A. 4.4.3.54.1 - M2 116,775.00 122,471.25 - - -
G Pekerjaan Pengecatan
1 Cat Dinding A. 4.7.1.10 224.18 M 2
10,769.00 8,380.00 2,414,194.42 1,878,628.40 4,292,822.82
2 Cat List Plank A. 4.7.1.4 13.49 M2 9,250.00 42,270.00 124,808.40 570,340.66 695,149.06
JUMLAH IV ……………………. 56,034,910.39 127,023,370.43 183,058,280.82
V. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
A. Pekerjaan Instalasi Listrik
Pengadaan Jaringan listrik 1.00 ls 3,500,000.00 - 3,500,000.00 3,500,000.00
1. Instalasi Penerangan dan Stop Kontak( termasuk Pipa) - 25.00 Titik - 95,000.00 - 2,375,000.00 2,375,000.00
2. Kabel NYA - 150.00 M' 4,600.00 - 690,000.00 690,000.00
3. Armature Stop Kontak dan Saklar - - -
3.1. Saklar Tunggal - 5.00 Bh 20,000.00 - 100,000.00 100,000.00
3.2. Saklar Ganda 10.00 Bh 25,000.00 - 250,000.00 250,000.00
3.3. Stop Kontak Ganda - 8.00 Bh 25,000.00 - 200,000.00 200,000.00
4. Armature Lampu Penerangan - - -
4.1 Lampu SL 24 W - 20.00 Set 40,800.00 - 816,000.00 816,000.00
JUMLAH V ……………………. - 7,931,000.00 7,931,000.00
VI. PEKERJAAN SANITASI
2. Pipa PVC dia 3" 5.00 btg 250,000.00 - 1,250,000.00 1,250,000.00
3. Tiang dan Tangki Air Stainles 1000 l - bh 9,000,000.00 - - -
4. Keran Air 1.00 bh 20,000.00 - 20,000.00 20,000.00
5. Pipa PVC dia 1/2" 4.00 btg 45,000.00 - 180,000.00 180,000.00
6. Pipa PVC dia 1" 2.00 btg 70,000.00 - 140,000.00 140,000.00
7. Selang Pipa dia 1" - rol 350,000.00 - - -
-
JUMLAH VI ……………………. - 1,590,000.00 1,590,000.00
VII. BIAYA OPERASIONAL ( BOP )
1. Perencanaan - 1.00 Ls 1,000,000.00 1,000,000.00 - 1,000,000.00
2. Pengawas 3.00 Bulan 800,000.00 2,400,000.00 - 2,400,000.00
3. Administrasi dan dokumentasi Prasasti 1.00 Ls 1,300,000.00 1,300,000.00 - 1,300,000.00
4. Honor TPK (3 Bulan)
Ketua 1.00 org 1,000,000.00 1,000,000.00 - 1,000,000.00
Sekretaris 1.00 org 800,000.00 800,000.00 - 800,000.00
Anggota 2.00 org 800,000.00 1,600,000.00 - 1,600,000.00
5. Pembuatan dokumen akhir 1.00 Ls 600,000.00 600,000.00 - 600,000.00
- -
JUMLAH VII ……………………. 8,700,000.00 - 8,700,000.00
TOTAL I + II + III + IV + V + VI + VII ………….…………. 82,679,689.44 175,860,190.62 258,539,880.05

DIKETAHUI OLEH: DISETUJUI OLEH Nagori Pariksabungan,…………………… 2021


PANGULU NAGORI PARIKSABUNGAN KEPALA DPMPN KAB. SIMALUNGUN DIBUAT OLEH:

PERIKSON PURBA, S.pd SARIMUDA A.D PURBA ,S,Sos,M.Si ERICK JOHNSON RUMAHORBO
PEMBINA TK.I TENAGA TEKNIK
NIP : 1974020519944021002
REKAPITULASI
RENCANA ANGGARAN BIAYA
NAGORI : PARIKSABUNGAN
KECAMATAN : DOLOK PARDAMEAN
KABUPATEN : SIMALUNGUN
PROVINSI : SUMATERA UTARA
NO RAB : 1
JENIS PEKERJAAN : PEMBANGUNAN TAMAN HUTAN SIMARJARUNJUNG
PEKERJAAN : PEMBANGUNAN KIOS
VULUME : 18 X 5 METER
DANA / TAHUN : APBN / 2021

SUB JUMLAH HARGA JUMLAH HARGA


NO URAIAN PEKERJAAN
( Rp ) ( Rp )
A. BAHAN
I. PEKERJAAN PENDAHULUAN 2,401,514.00 2,401,514.00
II. PEKERJAAN TANAH 1,050,192.00 1,050,192.00
III. PEKERJAAN STRUKTUR KIOS 35,864,114.19 35,864,114.19
IV. PEKERJAAN ARSITEKTUR 127,023,370.43 127,023,370.43
V. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL 7,931,000.00 7,931,000.00
VI. PEKERJAAN SANITASI 1,590,000.00 1,590,000.00
JUMLAH A 175,860,190.62
PPN & PPH 11.5% 20,223,921.92
TOTAL A 196,084,112.54
B. BOP DAN UPAH
VII BIAYA OPERASIONAL ( BOP ) 8,700,000.00 8,700,000.00
VIII UPAH 73,979,689.44 73,979,689.44
TOTAL B 82,679,689.44
TOTAL = TOTAL A + TOTAL B 278,763,801.97
Dibulatkan.....……………………………..………………………………………………………………………………………………….. 278,763,000.00
Terbilang : Dua Ratus Dua Puluh Lima Juta Enam Ratus Enam Puluh Sembilan Ribu Rupiah

Nagori Pariksabungan,…………………… 2021


DIKETAHUI OLEH: DIBUAT OLEH:
PANGULU NAGORI PARIKSABUNGAN

PERIKSON PURBA, S.pd ERICK JOHNSON RUMAHORBO


DISETUJUI OLEH TENAGA TEKNIK
KEPALA DPMPN KAB. SIMALUNGUN

SARIMUDA A.D PURBA ,S,Sos,M.Si


PEMBINA TK.I
NIP : 1974020519944021002
BACK UP DATA
(TAKE OF SHEET)
NO. URAIAN PEKERJAAN ANALISA DATA HITUNG VOLUME VOLUME TOTAL

I. PEKERJAAN PENDAHULUAN

Papan Proyek
1 1.00 LS

2. Bowplank / Pengukuran A. 2.2.1.14 Bouplank


A. Panjang 21.4 m
46.00 m'
II. PEKERJAAN TANAH
1. Pekerjaan Galian Pondasi A. 2.3.1.1 1. Pondasi
A. Lebar Pondasi 0.5 m
B. Panjang Pondasi 55 m
C. Dalam Galian 0.5 m
V= (A*B*C) 13.75 m3

2. Septik Tank
A. Lebar 1.5 m
B. Panjang 2m
C. Dalam Galian 1.2 m
V= (A*B*C) 3.6 m3
17.35 m3
1 unit 17.35 m3
2. Pek. Urugan Pasir di Bawah Lantai A. 2.3.1.11 R1 A. Panjang 55
B. Lebar 0.5
C. Tebal 0.1
V= (A*B*C) 2.75 m3

R2 A. Panjang 0
B. Lebar 0
C. Tebal 0
V= (A*B*C) 0 m3

Selasar Depan
A. Panjang 55
B. Lebar 1
C. Tebal 0.07
V= (A*B*C) 3.85 m3
6.60 m3
1 unit 6.60 m3
3. Urugan Kembali Galian Pondasi A. 2.3.1.9 4.18 m3
1 unit 4.18 m3
III. PEKERJAAN STRUKTUR KIOS
A Pekerjaan Pondasi
1. Pasang Pondasi Batu Kosong A. 3.2.1.9 1. Pondasi
A. Lebar Pondasi 0.5 m
B. Panjang Pondasi 55 m
C. Dalam Galian 0.1 m
V= (A*B*C) 2.75 m3
2.75 m3
1 unit 2.75 m3
2. Pasangan Pondasi Batu Belah/Batu Kali 1 ; 4 A. 3.2.1.2 A.Alas 0.5
B.Bubung 0.2
C. Tinggi 0.5
D. Panjang 55
V=(((A+B)/2)*C)*D 9.625 m3
9.63 m3
NO. URAIAN PEKERJAAN ANALISA DATA HITUNG VOLUME VOLUME TOTAL

1 unit 9.63 m3
B Pekerjaan Beton Bertulang
1. Sloof Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 25 Cm
1.1. Cor Sloof A. 4.1.1.7 A.Panjang 55 m
B. Lebar 0.2 m
C. Tinggi 0.25 m
V=A*B*C 2.75 m3
2.75 m3
1 unit 2.75 m3
1.3. Bekisting A. 4.1.1.21 A.Panjang 55 m
B. Lebar 0.2 m
C. Tinggi 0.25 m
V=(A*C)*2 27.5 m2
27.50 m2
1 unit 27.50 m2
2. Kolom Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 20 Cm
2.1. Cor Kolom Beton A. 4.1.1.7 A.Panjang 0.2 m
B. Lebar 0.2 m
C. Tinggi 4.15 m
D. Jlh 13 Bh
V=A*B*C*D 2.158 m3
2.16 m3
1 unit 2.16 m2
2.3. Bekisting A. 4.1.1.22 A.Panjang 0.2 m
B. Lebar 0.2 m
C. Tinggi 4.15 m
D. Jlh 13 Bh
V=((A*C)*2)*D 21.58 m2
21.58 m2
1 unit 21.58 m2

3. Ring Balok Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 25


3.1. Cor Ring Balok Beton A. 4.1.1.7 A.Panjang 65 m
B. Lebar 0.2 m
C. Tinggi 0.25 m
V=A*B*C 3.25 m3
3.25 m3
1 unit 3.25 m2

3.3. Bekisting A. 4.1.1.23

A.Panjang 65 m
B. Lebar 0.2 m
C. Tinggi 0.25 m
V=(A*C)*2 32.5 m2
32.50 m2
1 unit 32.50 m2
IV. PEKERJAAN ARSITEKTUR
7.2. Pasangan Dinding Batu Bata Tebal 1/2 batu camp. 1pc:4ps A. 4.4.1.9 Kios
Panjang 34 m
Tinggi 4.15 m
141.1 m2

Teras
Panjang 17 m
Tinggi 0.6 m
Jlh 1 bh
NO. URAIAN PEKERJAAN ANALISA DATA HITUNG VOLUME VOLUME TOTAL

10.2 m2
151.30 m2

Pengurangan Lubang jendela dan Pintu


Pintu Buka 2
Lebar 1.5 m
Tinggi 2.5 m
Jlh 1 bh
3.75 m2

Pintu Buka 1
Lebar 0.9 m
Tinggi 2.5 m
Jlh 2 bh
4.5 m2

Pentilasi
Lebar 0.6 m
Tinggi 0.4 m
Jlh 4 bh
0.96 m2

Jendela Kaca
Lebar 2m
Tinggi 2.5 m
Jlh 3 bh
15 m2

Jendela Kaca
Lebar 3m
Tinggi 2.5 m
Jlh 2 bh
15 m2
39.21 m2

112.09 m2
1 unit 112.09 m2

7.4. Plesteran Camp. 1 : 4 tebal 15 mm A. 4.4.2.4 Vol. Pas batu 1:4 *2 224.18 m2 224.18 m2
1 unit 224.18 m2

VIII. PEKERJAAN PINTU DAN JENDELA


8.1. Pekerjaan Kosen, Pintu dan Jendela
8.1.1. Aluminium A. 4.2.1.13 P2
Panjang 6.5 M'
P1
Panjang 11.8 M'
J1
Panjang 30 M'

J2
Panjang 28.5 M'

76.80 m'
1 unit 76.80 M'
NO. URAIAN PEKERJAAN ANALISA DATA HITUNG VOLUME VOLUME TOTAL

8.1.2. Memasang 1 M2 Bingkai Pintu / Jendela Kaca Rangka Alumunium A. 4.2.1.13 P2 Tinggi 2.5
Lebar 1.5
Jlh 1 3.75 M2

P1 Tinggi 2.5
Lebar 0.9
Jlh 2 4.5 M2

J1 Tinggi 2.5
Lebar 2.5
Jlh 3 18.75 M2

J2 Tinggi 2.5
Lebar 3.5
Jlh 2 17.5 M2

44.5 m2 44.50 m2
1 unit 44.50 m2

8.1.2. 1 M2 Pasang Kaca Cermin 10mm 1 unit 44.50 m2

E Pekerjaan Atap, Talang dan Listplank


1. Pekerjaan Rangka Atap Terpasang Luasan 166.649 m2
166.65 m2
1 unit 166.65 m2
Pekerjaan Atap A. 2.3.1.14 Luasan 166.649 m2
166.65 m2
1 unit 166.65 m2
Pekerjaan Rabung A. 4.5.2.37 Panjang 29.43 m
29.43 m
1 unit 29.43 m2
Pekerjaan Lisplank Terpasang Panjang 74.96 m
74.96 m
1 unit 74.96 m2
F Pekerjaan Lantai dan Pelapis
1. Lantai Kerja Beton Cor 1 : 3 : 5 Dibawah Lantai A. A. 4.1.1.5 Ruang Kios
A. Panjang 8
B. Lebar 5
V= (A*B) 40 m2

Selasar Depan
A. Panjang 19.48
B. Lebar 1
V= (A*B) 19.48 m2

Selasar Samping
A. Panjang 10
B. Lebar 1
V= (A*B) 10 m2

69.48 m2
Tinggi 0.05 m
3.47 m3
NO. URAIAN PEKERJAAN ANALISA DATA HITUNG VOLUME VOLUME TOTAL

2. Keramik Lantai Uk. 40 x 40 cm A. 4.4.3.7


R1 A. Panjang 8
B. Lebar 5
V= (A*B) 40 m2
jumlah 5 200 m2
R2 A. Panjang 10
B. Lebar 5
V= (A*B) 50 m2
jumlah 1 50 m2
340.00 m2
1 unit 340.00 m2
3. Keramik dinding Uk 20 x 40 cm A. 4.4.3.54.1 R1 A. Panjang 0
B. Lebar 0
V= (A*B) 0 m2
jlh 4
0.00 m2
1 unit 0.00 m2
ANALISA HARGA SATUAN

PEKERJAAN : PEMBANGUNAN KIOS

KABUPATEN : SIMALUNGUN

Pengukuran dan pemasangan 1m' bouplank Kode Analisa A. 2.2.1.14


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.1000 Oh Pekerja Rp 100,000.00 Rp 10,000.00
2 0.1000 oh Tukang kayu Rp 120,000.00 Rp 12,000.00
3 0.0100 oh Kepala tukang Rp 130,000.00 Rp 1,300.00
4 0.0050 Oh Mandor Rp 130,000.00 Rp 650.00
JUMLAH TENAGA KERJA Rp 23,950.00
B BAHAN
1 0.0120 m3 Balok Kayu Sembarang Rp 2,497,000.00 Rp 29,964.00
2 0.0200 Kg Paku Biasa Rp 20,800.00 Rp 416.00
3 0.0070 m3 Kayu Sembarang Rp 2,497,000.00 Rp 17,479.00
JUMLAH BAHAN Rp 47,859.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 71,809.00

1 M3 Galian Tanah Biasa Kode Analisa A. 2.3.1.1


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.7500 Oh Pekerja Rp 100,000.00 Rp 75,000.00
2 0.0250 Oh Mandor Rp 130,000.00 Rp 3,250.00
JUMLAH TENAGA KERJA Rp 78,250.00
B BAHAN

JUMLAH BAHAN Rp -
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 78,250.00

1 M3 Urugan Tanah Kembali Kode Analisa A. 2.3.1.9


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.5000 Oh Pekerja Rp 100,000.00 Rp 50,000.00
2 0.0500 Oh Mandor Rp 130,000.00 Rp 6,500.00
JUMLAH TENAGA KERJA Rp 56,500.00
B BAHAN

JUMLAH BAHAN Rp -
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 56,500.00

1 M3 Urugan Pasir Kode Analisa A. 2.3.1.11


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.3000 Oh Pekerja Rp 100,000.00 Rp 30,000.00
2 0.0100 Oh Mandor Rp 130,000.00 Rp 1,300.00
JUMLAH TENAGA KERJA Rp 31,300.00
B BAHAN
1 1.2000 m3 Pasir Urug Rp 132,600.00 Rp 159,120.00

JUMLAH BAHAN Rp 159,120.00


C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 190,420.00

1 M3 Pasangan Batu Kosong Kode Analisa A. 3.2.1.9


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.7800 Oh Pekerja Rp 100,000.00 Rp 78,000.00
2 0.3900 Oh Tukang Batu Rp 120,000.00 Rp 46,800.00
3 0.0390 Oh Kepala Tukang Rp 130,000.00 Rp 5,070.00
4 0.0390 Oh Mandor Rp 130,000.00 Rp 5,070.00
JUMLAH TENAGA KERJA Rp 134,940.00
B BAHAN
1 1.2000 m3 Batu belah Rp 330,480.00 Rp 396,576.00
2 0.4320 m3 Pasir urug Rp 132,600.00 Rp 57,283.20
JUMLAH BAHAN Rp 453,859.20
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 588,799.20

1 M3 Pasangan Batu Belah 1:4 Kode Analisa A. 3.2.1.2


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 1.5000 Oh Pekerja Rp 100,000.00 Rp 150,000.00
2 0.7500 Oh Tukang Batu Rp 120,000.00 Rp 90,000.00
3 0.0750 Oh Kepala Tukang Rp 130,000.00 Rp 9,750.00
4 0.0750 Oh Mandor Rp 130,000.00 Rp 9,750.00
JUMLAH TENAGA KERJA Rp 259,500.00
B BAHAN
1 1.2000 m3 Batu belah Rp 330,480.00 Rp 396,576.00
2 0.5200 m3 Pasir Pasang Rp 121,400.00 Rp 63,128.00
3 163.0000 kg Portland Cement Rp 1,335.00 Rp 217,605.00
JUMLAH BAHAN Rp 677,309.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 936,809.00

Memasang 1 m2 rangka atap Kode Analisa A. 2.3.1.1


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.1200 Oh Pekerja Rp 100,000.00 Rp 12,000.00
2 0.1200 Oh Tukang Kayu Rp 120,000.00 Rp 14,400.00
3 0.0100 Oh Kepala Tukang Rp 130,000.00 Rp 1,300.00
4 0.0050 Oh Mandor Rp 130,000.00 Rp 650.00
JUMLAH TENAGA KERJA Rp 28,350.00
B BAHAN
1 0.0140 m3 Kayu Kls II Rp 5,950,000.00 Rp 83,300.00
2 0.0570 kg Paku Biasa Rp 20,800.00 Rp 1,185.60
JUMLAH BAHAN Rp 84,485.60
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 112,835.60

Memasang 1 m2 rangka langit-langit (60 x 120) cm, kayu kelas II Kode Analisa A. 4.6.1.20
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.1000 Oh Pekerja Rp 100,000.00 Rp 10,000.00
2 0.1500 Oh Tukang Kayu Rp 120,000.00 Rp 18,000.00
3 0.0150 Oh Kepala Tukang Rp 130,000.00 Rp 1,950.00
4 0.0050 Oh Mandor Rp 130,000.00 Rp 650.00
JUMLAH TENAGA KERJA Rp 30,600.00
B BAHAN
1 0.0150 M3 Kaso-kaso (5 x 5) cm Rp 5,950,000.00 Rp 89,250.00
2 0.1250 kg Paku Rp 20,800.00 Rp 2,600.00
JUMLAH BAHAN Rp 91,850.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 122,450.00

Memasang 1 m2 langit-langit (120 x 240) cm, Tebal 6mm Kode Analisa A. 4.5.1.5
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.1000 Oh Pekerja Rp 100,000.00 Rp 10,000.00
2 0.1500 Oh Tukang Kayu Rp 120,000.00 Rp 18,000.00
3 0.0150 Oh Kepala Tukang Rp 130,000.00 Rp 1,950.00
4 0.0050 Oh Mandor Rp 130,000.00 Rp 650.00
JUMLAH TENAGA KERJA Rp 30,600.00
B BAHAN
1 0.3750 Lbr Triplek 6mm Rp 88,800.00 Rp 33,300.00
2 0.0300 kg Paku Rp 20,800.00 Rp 624.00
JUMLAH BAHAN Rp 33,924.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 64,524.00

Memasang 1 m2 atap Kode Analisa A. 2.3.1.14


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.1400 Oh Pekerja Rp 100,000.00 Rp 14,000.00
2 0.0700 Oh Tukang Kayu Rp 120,000.00 Rp 8,400.00
3 0.0070 Oh Kepala Tukang Rp 130,000.00 Rp 910.00
4 0.0030 Oh Mandor Rp 130,000.00 Rp 390.00
JUMLAH TENAGA KERJA Rp 23,700.00
B BAHAN
1 0.8000 M Seng Gelombang Rp 51,000.00 Rp 40,800.00
2 0.1600 kg Paku Seng Rp 35,000.00 Rp 5,600.00
JUMLAH BAHAN Rp 46,400.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 70,100.00

1 M2 Pasangan Dinding Batu Bata Tebal 1/2 batu, Camp. 1 : 4 Kode Analisa A. 4.4.1.9
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.3000 Oh Pekerja Rp 100,000.00 Rp 30,000.00
2 0.1000 Oh Tukang Batu Rp 120,000.00 Rp 12,000.00
3 0.0100 Oh Kepala Tukang Rp 130,000.00 Rp 1,300.00
4 0.0150 Oh Mandor Rp 130,000.00 Rp 1,950.00
JUMLAH TENAGA KERJA Rp 45,250.00
B BAHAN
1 70.0000 Bh Batu Bata Rp 653.40 Rp 45,738.00
2 0.0430 m3 Pasir Pasang Rp 121,400.00 Rp 5,220.20
3 11.5000 kg Portland Cement Rp 1,335.00 Rp 15,352.50
JUMLAH BAHAN Rp 66,310.70
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 111,560.70

1 M2 Plesteran Camp. 1 : 4 tebal 15 mm Kode Analisa A. 4.4.2.4


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.3000 Oh Pekerja Rp 100,000.00 Rp 30,000.00
2 0.1500 Oh Tukang Batu Rp 120,000.00 Rp 18,000.00
3 0.0150 Oh Kepala Tukang Rp 130,000.00 Rp 1,950.00
4 0.0150 Oh Mandor Rp 130,000.00 Rp 1,950.00
JUMLAH TENAGA KERJA Rp 51,900.00
B BAHAN
1 0.0240 m3 Pasir Pasang Rp 121,400.00 Rp 2,913.60
2 6.2400 kg Portland Cement Rp 1,335.00 Rp 8,330.40
JUMLAH BAHAN Rp 11,244.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 63,144.00

1 M3 Beton 1 : 2,3 : 3,4 setara K175 Kode Analisa A. A. 4.1.1.5


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 1.6500 Oh Pekerja Rp 100,000.00 Rp 165,000.00
2 0.2750 Oh Tukang Batu Rp 120,000.00 Rp 33,000.00
3 0.0280 Oh Kepala Tukang Rp 130,000.00 Rp 3,640.00
4 0.0830 Oh Mandor Rp 130,000.00 Rp 10,790.00
JUMLAH TENAGA KERJA Rp 212,430.00
B BAHAN
1 326.0000 kg Semen @ 40 Kg Rp 1,335.00 Rp 435,210.00
2 0.5430 m3 Pasir Pasang Rp 121,400.00 Rp 65,920.20
3 0.7620 m3 Kerikil/ Batu Pecah Rp 504,900.00 Rp 384,733.80
4 215.0000 Ltr Air Rp - Rp -
JUMLAH BAHAN Rp 885,864.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 1,098,294.00

1 M3 Beton Campuran 1 : 1,88 : 2,82 fc 19,3 Mpa setara K225 Kode Analisa A. 4.1.1.7
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 1.6500 Oh Pekerja Rp 100,000.00 Rp 165,000.00
2 0.2750 Oh Tukang Batu Rp 120,000.00 Rp 33,000.00
3 0.0280 Oh Kepala Tukang Rp 130,000.00 Rp 3,640.00
4 0.0830 Oh Mandor Rp 130,000.00 Rp 10,790.00
JUMLAH TENAGA KERJA Rp 212,430.00
B BAHAN
1 371.0000 kg Semen @ 40 Kg Rp 1,335.00 Rp 495,285.00
2 0.4990 m3 Pasir Pasang Rp 121,400.00 Rp 60,578.60
3 0.7760 m3 Kerikil/ Batu Pecah Rp 504,900.00 Rp 391,802.40
4 215.0000 Ltr Air Rp - Rp -
JUMLAH BAHAN Rp 947,666.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 1,160,096.00

Pembesian 10 kg dengan Besi Polos atau Ulir Kode Analisa A. 4.1.1.17


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.0700 Oh Pekerja Rp 100,000.00 Rp 7,000.00
2 0.0700 Oh Tukang Batu Rp 120,000.00 Rp 8,400.00
3 0.0070 Oh Kepala Tukang Rp 130,000.00 Rp 910.00
4 0.0040 Oh Mandor Rp 130,000.00 Rp 520.00
JUMLAH TENAGA KERJA Rp 1,683.00
B BAHAN
1 10.5000 kg Besi Beton Rp 12,500.00 Rp 131,250.00
2 0.1500 m3 Kawat Beton Rp 15,900.00 Rp 2,385.00
JUMLAH BAHAN Rp 13,363.50
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 15,046.50
HARGA SATUAN PEMBESIAN 1 KG Rp 15,046.50
1 m2 bekisting untuk Sloof (Asumsi 3 kali Pemakaian Bahan) Kode Analisa A. 4.1.1.21
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.5200 Oh Pekerja Rp 100,000.00 Rp 52,000.00
2 0.2600 Oh Tukang Kayu Rp 120,000.00 Rp 31,200.00
3 0.0260 Oh Kepala Tukang Rp 130,000.00 Rp 3,380.00
4 0.0260 Oh Mandor Rp 130,000.00 Rp 3,380.00
JUMLAH TENAGA KERJA Rp 89,960.00
B BAHAN
1 0.0150 m3 Kayu Sembarang Rp 2,497,000.00 Rp 37,455.00
2 0.3000 kg Paku Biasa Rp 20,800.00 Rp 6,240.00
3 0.1000 Ltr Minyak Bekisting Rp 21,000.00 Rp 2,100.00
JUMLAH BAHAN Rp 45,795.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 135,755.00

Memasang 1 m' Kusen Pintu Alumunium Kode Analisa A. 4.2.1.11


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.0430 Oh Pekerja Rp 100,000.00 Rp 4,300.00
2 0.0430 Oh Tukang Batu Rp 120,000.00 Rp 5,160.00
3 0.0043 Oh Kepala Tukang Rp 130,000.00 Rp 559.00
4 0.0021 Oh Mandor Rp 130,000.00 Rp 273.00
JUMLAH TENAGA KERJA Rp 10,292.00
B BAHAN
1 1.1000 m' Profil Alumunium Rp 80,000.00 Rp 88,000.00
2 2.0000 bh Skrup Fiser Rp 12,200.00 Rp 24,400.00
3 0.0600 tube Sealant Rp 16,500.00 Rp 990.00
JUMLAH BAHAN Rp 113,390.00
C PERALATAN

JUMLAH PERALATAN Rp -
N PEKERJAAN (A + B + C) Rp 123,682.00

Memasang 1 M2 Bingkai Pintu / Jendela Kaca Rangka Alumunium Kode Analisa A. 4.2.1.13
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.0850 Oh Pekerja Rp 100,000.00 Rp 8,500.00
2 0.0850 Oh Tukang Batu Rp 120,000.00 Rp 10,200.00
3 0.0090 Oh Kepala Tukang Rp 130,000.00 Rp 1,170.00
4 0.0050 Oh Mandor Rp 130,000.00 Rp 650.00
JUMLAH TENAGA KERJA Rp 20,520.00
B BAHAN
1 4.4000 m' Bingkai Alumunium Rp 62,000.00 Rp 272,800.00
2 4.5000 bh Profi Kaca Rp 12,300.00 Rp 55,350.00
3 0.2700 tube Sealant Rp 16,500.00 Rp 4,455.00
JUMLAH BAHAN Rp 332,605.00
C PERALATAN

JUMLAH PERALATAN Rp -
N PEKERJAAN (A + B + C) Rp 353,125.00

1 M2 Pasang Kaca Cermin 10mm Kode Analisa A. 4.6.2.17.a


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.0150 Oh Pekerja Rp 100,000.00 Rp 1,500.00
2 0.1500 Oh Tukang Batu Rp 120,000.00 Rp 18,000.00
3 0.0150 Oh Kepala Tukang Rp 130,000.00 Rp 1,950.00
4 0.0050 Oh Mandor Rp 130,000.00 Rp 650.00
JUMLAH TENAGA KERJA Rp 22,100.00
B BAHAN
1 1.1000 M2 Kaca Cermin 10mm Rp 125,000.00 Rp 137,500.00
2 4.5000 bh Profi Kaca Rp 12,300.00 Rp 55,350.00
3 0.2700 tube Sealant Rp 16,500.00 Rp 4,455.00
JUMLAH BAHAN Rp 197,305.00
C PERALATAN

JUMLAH PERALATAN Rp -
N PEKERJAAN (A + B + C) Rp 219,405.00

1 m2 bekisting untuk Kolom (Asumsi 3 kali Pemakaian Bahan) Kode Analisa A. 4.1.1.22
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.6600 Oh Pekerja Rp 100,000.00 Rp 66,000.00
2 0.3300 Oh Tukang Kayu Rp 120,000.00 Rp 39,600.00
3 0.0330 Oh Kepala Tukang Rp 130,000.00 Rp 4,290.00
4 0.0330 Oh Mandor Rp 130,000.00 Rp 4,290.00
JUMLAH TENAGA KERJA Rp 114,180.00
B BAHAN
1 0.0133 m3 Kayu Sembarang Rp 2,497,000.00 Rp 33,293.33
2 0.4000 kg Paku Biasa Rp 20,800.00 Rp 8,320.00
3 0.2000 Ltr Minyak Bekisting Rp 21,000.00 Rp 4,200.00
4 0.0050 m3 Balok Kayu Sembarang Rp 2,497,000.00 Rp 12,485.00
5 0.1167 Lbr Plywood tebal 9 mm Rp 144,000.00 Rp 16,800.00
6 0.6667 Btg Dolken Kayu dia 8 - 10 cm- pjg 4 m Rp 20,300.00 Rp 13,533.33
JUMLAH BAHAN Rp 88,631.67
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 202,811.67

1 m2 bekisting untuk balok (Asumsi 3 kali Pemakaian Bahan) Kode Analisa A. 4.1.1.23
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.6600 Oh Pekerja Rp 100,000.00 Rp 66,000.00
2 0.3300 Oh Tukang Kayu Rp 120,000.00 Rp 39,600.00
3 0.0330 Oh Kepala Tukang Rp 130,000.00 Rp 4,290.00
4 0.0330 Oh Mandor Rp 130,000.00 Rp 4,290.00
JUMLAH TENAGA KERJA Rp 114,180.00
B BAHAN
1 0.0133 m3 Kayu Sembarang Rp 2,497,000.00 Rp 33,293.33
2 0.4000 kg Paku Biasa Rp 20,800.00 Rp 8,320.00
3 0.2000 Ltr Minyak Bekisting Rp 21,000.00 Rp 4,200.00
4 0.0060 m3 Balok Kayu Sembarang Rp 2,497,000.00 Rp 14,982.00
5 0.1167 Lbr Plywood tebal 9 mm Rp 144,000.00 Rp 16,800.00
6 0.6667 Btg Dolken Kayu dia 8 - 10 cm- pjg 4 m Rp 20,300.00 Rp 13,533.33
JUMLAH BAHAN Rp 91,128.67
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 205,308.67
1 m2 Lantai Keramik 40 x 40 cm Kode Analisa A. 4.4.3.7
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.2500 Oh Pekerja Rp 100,000.00 Rp 25,000.00
2 0.1250 Oh Tukang Batu Rp 120,000.00 Rp 15,000.00
3 0.0130 Oh Kepala Tukang Rp 130,000.00 Rp 1,690.00
4 0.0130 Oh Mandor Rp 130,000.00 Rp 1,690.00
JUMLAH TENAGA KERJA Rp 43,380.00
B BAHAN
1 6.6300 Bh Keramik 40 x 40 cm Rp 10,900.00 Rp 72,267.00
2 9.8000 kg Semen PC Rp 1,335.00 Rp 13,083.00
3 0.0450 M3 Pasir Pasang Rp 121,400.00 Rp 5,463.00
4 1.3000 kg Semen Warna Rp 3,442.50 Rp 4,475.25
JUMLAH BAHAN Rp 95,288.25
C PERALATAN

JUMLAH PERALATAN Rp -
1 m2 Dinding Keramik 20 x 40 cm Kode Analisa A. 4.4.3.54.1
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.6750 Oh Pekerja Rp 100,000.00 Rp 67,500.00
2 0.3375 Oh Tukang Batu Rp 120,000.00 Rp 40,500.00
3 0.0338 Oh Kepala Tukang Rp 130,000.00 Rp 4,387.50
4 0.0338 Oh Mandor Rp 130,000.00 Rp 4,387.50
JUMLAH TENAGA KERJA Rp 116,775.00
B BAHAN
1 6.6300 Bh Keramik 20 x 40 cm Rp 15,000.00 Rp 99,450.00
2 9.8000 kg Semen PC Rp 1,335.00 Rp 13,083.00
3 0.0450 M3 Pasir Pasang Rp 121,400.00 Rp 5,463.00
4 1.3000 kg Semen Warna Rp 3,442.50 Rp 4,475.25
JUMLAH BAHAN Rp 122,471.25
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 239,246.25

1 m' Nok Spandek Kode Analisa A. 4.5.2.37


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.2500 Oh Pekerja Rp 100,000.00 Rp 25,000.00
2 0.1500 Oh Tukang Kayu Rp 120,000.00 Rp 18,000.00
3 0.0150 Oh Kepala Tukang Rp 130,000.00 Rp 1,950.00
4 0.0130 Oh Mandor Rp 130,000.00 Rp 1,690.00
JUMLAH TENAGA KERJA Rp 46,640.00
B BAHAN
1 1.1000 Bh Nok Spandek 30 Rp 30,000.00 Rp 33,000.00
2 0.0500 kg Paku Biasa Rp 20,800.00 Rp 1,040.00
JUMLAH BAHAN Rp 34,040.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 80,680.00

Pemasangan 1 buah kunci tanam biasa Kode Analisa A. 4.6.2.2


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.0100 Oh Pekerja Rp 100,000.00 Rp 1,000.00
2 0.5000 Oh Tukang Kayu Rp 120,000.00 Rp 60,000.00
3 0.0500 Oh Kepala Tukang Rp 130,000.00 Rp 6,500.00
4 0.0050 Oh Mandor Rp 130,000.00 Rp 650.00
JUMLAH TENAGA KERJA Rp 68,150.00
B BAHAN
1 1.0000 Bh Kunci Tanam Biasa Rp 185,000.00 Rp 185,000.00
JUMLAH BAHAN Rp 185,000.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 253,150.00

Pemasangan 1 buah engsel pintu Kode Analisa A. 4.6.2.5


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.0150 Oh Pekerja Rp 100,000.00 Rp 1,500.00
2 0.1500 Oh Tukang Kayu Rp 120,000.00 Rp 18,000.00
3 0.0150 Oh Kepala Tukang Rp 130,000.00 Rp 1,950.00
4 0.0008 Oh Mandor Rp 130,000.00 Rp 104.00
JUMLAH TENAGA KERJA Rp 21,554.00
B BAHAN
1 1.0000 Bh Engsel Pintu Rp 25,400.00 Rp 25,400.00
JUMLAH BAHAN Rp 25,400.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 46,954.00

1 m2 Pengecatan bidang kayu baru


(1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) Kode Analisa A. 4.7.1.4
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.0700 Oh Pekerja Rp 100,000.00 Rp 7,000.00
2 0.0090 Oh Tukang Cat Rp 120,000.00 Rp 1,080.00
3 0.0060 Oh Kepala Tukang Rp 130,000.00 Rp 780.00
4 0.0030 Oh Mandor Rp 130,000.00 Rp 390.00
JUMLAH TENAGA KERJA Rp 9,250.00
B BAHAN
1 0.2000 Kg Cat Manie Rp 51,200.00 Rp 10,240.00
2 0.1500 Kg Plamuur Rp 19,000.00 Rp 2,850.00
3 0.1700 Kg Cat Dasar Rp 65,000.00 Rp 11,050.00
4 0.2600 Kg Cat Penutup Rp 65,000.00 Rp 16,900.00
5 0.0100 Bh Kuas Rp 13,700.00 Rp 137.00
6 0.0300 Kg Pengencer Rp 23,100.00 Rp 693.00
7 0.2000 Lbr Ampelas Rp 2,000.00 Rp 400.00
JUMLAH BAHAN Rp 42,270.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 51,520.00

1 m2 Pengecatan tembok baru


(1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) Kode Analisa A. 4.7.1.10
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.0200 Oh Pekerja Rp 100,000.00 Rp 2,000.00
2 0.0630 Oh Tukang Cat Rp 120,000.00 Rp 7,560.00
3 0.0063 Oh Kepala Tukang Rp 130,000.00 Rp 819.00
4 0.0030 Oh Mandor Rp 130,000.00 Rp 390.00
JUMLAH TENAGA KERJA Rp 10,769.00
B BAHAN
2 0.1000 Kg Plamuur Rp 19,000.00 Rp 1,900.00
3 0.1000 Kg Cat Dasar Rp 18,000.00 Rp 1,800.00
4 0.2600 Kg Cat Penutup Rp 18,000.00 Rp 4,680.00
JUMLAH BAHAN Rp 8,380.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 19,149.00

Pemasangan 1 buah Kloset duduk Kode Analisa A. 5.1.1.1


No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 3.3000 Oh Pekerja Rp 100,000.00 Rp 330,000.00
2 1.1000 Oh Tukang Batu Rp 120,000.00 Rp 132,000.00
3 0.0100 Oh Kepala Tukang Rp 130,000.00 Rp 1,300.00
4 0.1600 Oh Mandor Rp 130,000.00 Rp 20,800.00
JUMLAH TENAGA KERJA Rp 484,100.00
B BAHAN
1 1.0000 Unit Kloset duduk Rp 2,090,000.00 Rp 2,090,000.00
2 Ls Perlengkapan (6% x kloset duduk) Rp 125,400.00 Rp 125,400.00
JUMLAH BAHAN Rp 2,215,400.00
C PERALATAN

JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 2,699,500.00
DAFTAR HARGA UPAH

PEKERJAAN : PEMBANGUNAN KIOS


KABUPATEN : SIMALUNGUN

HARGA DASAR UPAH HARGA BAHAN UPAH


No. URIAN DILOKASI PEKERJAAN SATUAN KETERANGAN
(Rp.) (Rp)

UPAH
1 Pekerja 100,000.00 100,000.00 Hr/Org
2 Mandor 130,000.00 130,000.00 Hr/Org
3 Tukang 120,000.00 120,000.00 Hr/Org
4 Kepala Tukang 130,000.00 130,000.00 Hr/Org
DAFTAR HARGA DASAR BAHAN
PEKERJAAN : PEMBANGUNAN KIOS
KABUPATEN : SIMALUNGUN

HARGA DASAR BAHAN HARGA BAHAN


No. URIAN DILOKASI PEKERJAAN SATUAN KETERANGAN
(Rp.) (Rp)

A. TIMBUNAN / GALIAN
1 Tanah Timbun/Merah 97,920.00 97,920.00 M³
2 Pasir Timbun / Urug 132,600.00 132,600.00 M³
3 Pasir Pasang 121,400.00 121,400.00 M³
4 Sirtu 357,000.00 357,000.00 M³

B. BAHAN PEREKAT
1 Portland Cement 40 kg 1,335.00 1,335.00 Kg
2 Cement Putih 2,754.00 2,754.00 Kg
3 Cement Warna 3,442.50 3,442.50 Kg
4 Kapur 108,000.00 108,000.00 Kg

C. BATU / BATU CETAKAN


1 Batu Kerikil Bersih (batu kerikil A Cor) 504,900.00 504,900.00 M³
2 Batu Belah/Kali 330,480.00 330,480.00 M³
3 Batu Bata 653.40 653.40 Bh
4 Batu Terawang - - Bh
5 Batu Kacang/jagung 0,5 - 1 cm 585,000.00 585,000.00 M³

D. KAYU / LANGIT-LANGIT
1 Kayu Keras Setempat/Kayu Sampinur (Balok Kls II) 5,950,000.00 5,950,000.00 M³
2 Kayu Keras Setempat/Kayu Sampinur (Papan Kls II) 6,270,000.00 6,270,000.00 M³
3 Kayu Kls III 4,500,000.00 4,500,000.00 M³
4 Kayu Sembarang/Bekisting 2,497,000.00 2,497,000.00 M³
5 Kayu Dolken / bulat Ø 7,5 - 10 / 400 cm 20,300.00 20,300.00 Btg
6 Tripleks 120 x 240 tbl. 4 mm 78,900.00 78,900.00 Lbr
7 Tripleks 120 x 240 tbl. 6 mm 88,800.00 88,800.00 Lbr
8 Tripleks 120 x 240 tbl. 9 mm 144,000.00 144,000.00 Lbr
9 Tripleks 120 x 240 tbl. 12 mm 148,500.00 148,500.00 Lbr
10 Multiflex 12 mm 150,000.00 148,500.00 Lbr
11 Multiflex 18 mm 300,000.00 300,000.00 Lbr
12 Profil Gypsum 3" 35,000.00 35,000.00 M'
13 Gypsum Board 120 x 240 tbl. 9 mm 98,000.00 98,000.00 Lbr

E. BESI / ALLUMINIUM
1 Besi Beton Polos 12,500.00 12,500.00 Kg
2 Kawat Besi Beton 15,900.00 15,900.00 Kg
3 Paku Biasa 20,800.00 20,800.00 Kg
4 Paku Sekrup 90,000.00 90,000.00 Kg
5 Rangka Baja Ringan 86,700.00 86,700.00 M2
6 Rangka Furing Flafon 80,000.00 80,000.00 M2
7 Profil Alumunium 80,000.00 80,000.00 M'
Skrup Fiser 12,200.00 12,200.00 Bh
Sealant 16,500.00 16,500.00 Tube
Bingkai Alumunium 62,000.00 62,000.00 M'
Profi Kaca 12,300.00 12,300.00 Bh
Kaca Cermin 10mm 125,000.00 125,000.00 M2
Handle Pintu Kaca 450,000.00 450,000.00 Bh
Kunci Pintu Alumunium dan Kaca 320,000.00 320,000.00 bh

F. PENUTUP ATAP
1 Atap Spandeck 0,3 mm 46,900.00 46,900.00 M
2 Rabung Spandek 30,000.00 30,000.00 Bh
3 Paku Seng + Ring karet 500.00 500.00 Bh
4 Furing Channel 20,300.00 20,300.00 M
5 Bout Ramset / Dina Bolt 500.00 500.00 Bh
6 Seng Gelombang BJLS- 30 51,000.00 51,000.00 Lbr
7. Listplank GRC 25,000.00 25,000.00 M

G. PENUTUP LANTAI DAN DINDING


1 Keramik 40 x 40 cm setara Roman 10,900.00 10,900.00 Bh
2 Keramik 40 x 40 cm setara Granito 44,000.00 44,000.00 Bh
3 Keramik 20 x 40 cm 15,000.00 15,000.00 Bh
4 Plint Keramik 10 x 40 cm setara Roman 2,500.00 2,500.00 Bh
5 Plint Keramik 10 x 40 cm setara Ganito 15,000.00 15,000.00 Bh
H. KUNCI DAN KACA
1 Kunci tanam biasa 185,000.00 185,000.00 Bh
2 Engsel pintu 4" 25,400.00 25,400.00 Bh
3 Engsel jendela 3" 18,200.00 18,200.00 Bh
4 Engsel angin 15,000.00 15,000.00 Bh
5 Grendel Pintu 23,100.00 23,100.00 Bh
6 Grendel Jendela 19,200.00 19,200.00 Bh
7 Hak angin 35,000.00 35,000.00 Bh
8 Handle Jendela 10,000.00 10,000.00 Bh
9 Kaca Polos tbl. 5 mm 240,000.00 240,000.00 M2

I. CAT / MINYAK
1 Cat Tembok 18,000.00 18,000.00 Kg
2 Cat Minyak untuk Kayu 65,000.00 65,000.00 Kg
3 Cat Menie Kayu 51,200.00 51,200.00 Kg
4 Cat Menie Besi 39,000.00 39,000.00 Kg
5 Plamuur 19,000.00 19,000.00 Kg
6 Dempul Kayu 11,000.00 11,000.00 Kg
7 Tinner 23,100.00 23,100.00 Ltr
8 Lem Kayu 12,100.00 12,100.00 Kg
9 Kuas 13,700.00 13,700.00 Bh
10 Ampelas 2,000.00 2,000.00 Lbr
11 Waterfroof 60,000.00 60,000.00 Kg
12 Coating AM-52 30,000.00 30,000.00 Ltr
13 Minyak Bekisting 21,000.00 21,000.00 Ltr
14 Minyak Pelumas 35,000.00 35,000.00 Ltr
15 Minyak solar 5,100.00 5,100.00 Ltr
16 Minyak Pertalite 7,800.00 7,800.00 Ltr

J. LISTRIK / ACSESORIES
1 Lampu TL 40 W Lengkap kotak 86,400.00 86,400.00 Set
2 Lampu XL 18 Watt 27,500.00 27,500.00 Set
3 Lampu XL 24 Watt 40,800.00 40,800.00 Set
4 Stop Kontak Ganda 17,000.00 17,000.00 Bh
5 Saklar Ganda 18,700.00 18,700.00 Bh
6 Saklar Triple 22,000.00 22,000.00 Bh
7 Saklar Tunggal 16,500.00 16,500.00 Bh
8 Panel Kontrol 1,500,000.00 1,500,000.00 Unit
9 Instalasi listrik titik api / Lampu Nyala 120,000.00 120,000.00 Ttk
10 Kabel NYA 4,600.00 4,600.00 M

Nagori Pariksabungan,…………………… 2021


DIKETAHUI OLEH: DIBUAT OLEH:
PANGULU NAGORI PARIKSABUNGAN

PERIKSON PURBA, S.pd ERICK JOHNSON RUMAHORBO


TENAGA TEKNIK
RENCANA ANGGARAN BIAYA (RAB)

PEMBANGUNAN KIOS

SUMBER DANA APBN

TAHUN ANGGARAN
2021
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan BULLDOZER 100-150 HP E04
2. Tenaga Pw 155.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 915,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 91,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 108,618.61 Rupiah
W

b. Asuransi, dll = 0.002 x B F 915.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 109,533.61 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 94,860.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 135,625.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 40,031


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 57,187.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 25,000.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,428.57 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 367,132.32 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 476,665.93 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3 E06
2. Tenaga Pw 20.0 HP
3. Kapasitas Cp 500.0 Liter
4. Alat Baru : a. Umur Ekonomis A 2.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 80,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 8,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.57619 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 27,657.14 Rupiah
W

b. Asuransi, dll = 0.002 x B F 106.67 Rupiah


W

Biaya Pasti per Jam = (E+F) G 27,763.81 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 15,300.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 21,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 4,667 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 9,333.33 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 25,000.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,428.57 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 89,728.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 117,492.38 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3.5 TON E08
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 3.5 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 240,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 24,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 28,490.13 Rupiah
W

b. Asuransi, dll = 0.002 x B F 240.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 28,730.13 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 61,200.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 87,500.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 10,500


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 15,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 18,571.43 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12,000.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 204,771.43 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 233,501.56 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 18,571.43 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 12,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 10 TON E09
2. Tenaga Pw 190.0 HP
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 320,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 32,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 37,986.84 Rupiah
W

b. Asuransi, dll = 0.002 x B F 320.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 38,306.84 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 116,280.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 166,250.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 14,000 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 20,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 18,571.43 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 12,000.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 347,101.43 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 385,408.27 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 18,571.43 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 12,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 80-140 HP E10
2. Tenaga Pw 133.0 HP
3. Kapasitas Cp 0.93 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 2,000,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 200,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 237,417.73 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2,000.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 239,417.73 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 81,396.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 116,375.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 87,500 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 125,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 25,000.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,428.57 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 449,699.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 689,117.30 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan MOTOR GRADER >100 HP E13
2. Tenaga Pw 135.0 HP
3. Kapasitas Cp 10,800.0 -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 800,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 80,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 94,967.09 Rupiah
W

b. Asuransi, dll = 0.002 x B F 800.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 95,767.09 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 82,620.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 118,125.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 35,000 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 50,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 25,000.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,428.57 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 325,173.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 420,940.66 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE VIBRATOR E20
2. Tenaga Pw 5.5 HP
3. Kapasitas Cp 25.0 -
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 10,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 1,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.31547 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 2,839.24 Rupiah
W

b. Asuransi, dll = 0.002 x B F 20.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 2,859.24 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 4,207.50 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 5,775.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 625 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 1,750.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 25,000.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,428.57 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 51,786.07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 54,645.31 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WATER PUMP 70-100 mm E22
2. Tenaga Pw 6.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 3.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 9,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 900,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.40211 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 1,628.56 Rupiah
W

b. Asuransi, dll = 0.002 x B F 9.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 1,637.56 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 3,672.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 5,250.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 394 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 562.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 25,000.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,428.57 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 49,306.82 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 50,944.39 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
JADWAL PELAKSANAAN KEGIATAN

Nama Kegiatan : Err:509


Desa : PARIKSABUNGAN
Kecamatan : Err:509
Kabupaten : Err:509

Jumlah Harga Bobot Jadwal Pelaksanaan (Tahun 2021)


No. Uraian Pekerjaan Satuan Volume
(Rp) (%) BLN 1 BLN 2 BLN 3 BLN 4
I. PEKERJAAN PENDAHULUAN
100
Bowplank / Pengukuran M' 46.00 3,303,214.00 Err:509 Err:509
Papan Proyek Ls 1.00 200,000.00 Err:509 Err:509
II. PEKERJAAN TANAH
Pekerjaan Galian Pondasi M³ 17.35 1,357,637.50 Err:509 Err:509
Pek. Urugan Pasir di Bawah Lantai M³ 6.60 1,256,772.00 Err:509 Err:509 90

Err:509 M³ 4.18 235,935.71 Err:509 Err:509


III. PEKERJAAN STRUKTUR KIOS
Pasang Pondasi Batu Kosong M³ 2.75 1,619,197.80 Err:509 Err:509
Pasangan Pondasi Batu Belah/Batu Kali 1 ; 4 M³ 9.63 9,016,786.63 Err:509 Err:509
Sloof Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 25 Cm - Err:509 Err:509 80

Kolom Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 20 Cm - Err:509 Err:509


Ring Balok Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 25 - Err:509 Err:509
SEPTIK TANK - Err:509 Err:509
IV. PEKERJAAN ARSITEKTUR
70
Pasangan Dinding Batu Bata 1/2 Bata 1 : 4 M2 112.09 12,504,838.86 Err:509 Err:509
Plesteran Dinding Batu Bata 1 : 4 Err:509 224.18 14,155,621.92 Err:509 Err:509
Pekerjaan Kusen Pintu dan Jendela Alumunium M' - 9,498,777.60 Err:509 Err:509
Pekerjaan Bingkai Aluminium M2 44.50 15,714,062.50 Err:509 Err:509
Pekerjaan Kaca 10mm M2 44.50 9,763,522.50 Err:509 Err:509 60
Kunci Tanam Biasa Bh - - Err:509 Err:509
Engsel Pintu Bh - - Err:509 Err:509
Err:509 Bh Err:509 Err:509 Err:509 Err:509
Pekerjaan Rangka Atap M2 166.65 18,803,939.90 Err:509 Err:509
Pekerjaan Atap M2 166.65 11,682,094.90 Err:509 Err:509 50

Pekerjaan Rabung M 29.43 2,374,412.40 Err:509 Err:509


Pekerjaan Lisplank M 74.96 1,874,000.00 Err:509 Err:509
Keramik Lantai Uk. 40 x 40 cm M2 340.00 47,147,205.00 Err:509 Err:509
Cat Minyak Kozen, Pintu M2 - - Err:509 Err:509
40
Cat Dinding M2 224.18 4,292,822.82 Err:509 Err:509 Err:509
Cat List Plank Err:509 13.49 695,149.06 Err:509 Err:509
V. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
Pengadaan Jaringan listrik ls 1.00 3,500,000.00 Err:509 Err:509
Instalasi Penerangan dan Stop Kontak( termasuk Pipa) Titik 25.00 2,375,000.00 Err:509 Err:509
30
Kabel NYA M' 150.00 690,000.00 Err:509 Err:509
Saklar Tunggal Bh 5.00 100,000.00 Err:509 Err:509
Saklar Ganda Bh 10.00 250,000.00 Err:509 Err:509
Stop Kontak Ganda Bh 8.00 200,000.00 Err:509 Err:509
Lampu SL 24 W Set 20.00 816,000.00 Err:509 Err:509 20

VI. PEKERJAAN SANITASI


1 Pipa PVC dia 3" btg 5.00 1,250,000.00 Err:509
2 Tiang dan Tangki Air Stainles 1000 l bh - - Err:509 Err:509
3 Keran Air bh 1.00 20,000.00 Err:509 Err:509
10
4 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
5 Pipa PVC dia 1/2" btg 4.00 180,000.00 Err:509 Err:509
6 Pipa PVC dia 1" btg 2.00 140,000.00 Err:509 Err:509
7 Selang Pipa dia 1" rol - - Err:509 Err:509
Jumlah Err:509 Err:509
0
Rencana fisik per bulan Err:509 Err:509 Err:509 Err:509
Rencana fisik kumulatif Err:509 Err:509 Err:509 Err:509

Partukkonaginjang, 2021

Dibuat Oleh,
DATA PEMBESIAN

SKET GAMBAR URAIAN PERHITUNGAN

1. Beton Cor Bertulang Sloof 0.20 x 0.25


Panjang (P) = 55.00 m'
Lebar (L) = 0.20 m'
Tinggi (T) = 0.25 m'
Jumlah (J) = 1.00 bh
Volume (V) = P x L x T x J
(V) = 55.00 x 0.20 x 0.25 x 1.00
(V) = 2.75 m3

Pembesian
Tulangan Pokok
Diamater (Ø) = 12.00 mm
Berat (Bj) = 0.888 Kg / m'
Panjang (P) = 55.05 m'
Jumlah (J) = 4.00 btg
Volume (V) = Bj x P x J
= 0.888 x 55.05 x 4.00
(V1) = 195.54 Kg
Sengkang
Diamater (Ø) = 8.00 mm
Berat (Bj) = 0.395 Kg / m'
Panjang (P) = 0.93 m'
Jumlah (J) = 276.00 bh
Volume (V) = Bj x P x J
= 0.395 x 0.93 x 276.00
(V2) = 100.84 Kg

Total Volume (V) = V1 + V2


(V) = 195.54 + 100.84
(V) = 296.00 Kg

2.a Kolom Struktur Bertulang 20 X 20


Panjang (P) = 0.20 m'
Lebar (L) = 0.40 m'
Tinggi (T) = 4.15 m'
Jumlah (J) = 13.00 bh
Volume (V) = P x L x T x J
(V) = 0.20 x 0.40 x 4.15 x 13.00
(V) = 4.32 m3

Pembesian Kolom
Tulangan Pokok
Diamater (Ø) = 12.00 mm
Berat (Bj) = 0.888 Kg / m'
Panjang (P) = 4.20 m'
Jumlah btg (Jb) = 4.00 btg
Jumlah (J) = 13.00 bh
Volume (V) = Bj x P x J
= 0.888 x 4.20 x 4.00 x 13.00
(V1) = 193.94 Kg
Sengkang
Diamater (Ø) = 8.00 mm
Berat (Bj) = 0.395 Kg / m'
Panjang (P) = 1.25 m'
Jumlah btg (Jb) = 29.00 btg
Jumlah (J) = 13.00 bh
Volume (V) = Bj x P x J
= 0.395 x 1.25 x 29.00 x 13.00
(V2) = 186.14 Kg
Total Volume (V) = V1 + V2
(V) = 193.94 + 186.14
(V) = 380.00 Kg

(V) = 380.00 Kg

2.b Kolom Struktur Bertulang 15 X 15


Panjang (P) = 0.15 m'
Lebar (L) = 0.15 m'
Tinggi (T) = 0.00 m'
Jumlah (J) = 4.00 bh
Volume (V) = P x L x T x J
(V) = 0.15 x 0.15 x 0.00 x 4.00
(V) = 0.00 m3

Pembesian Kolom
Tulangan Pokok
Diamater (Ø) = 0.00 mm
Berat (Bj) = 0 Kg / m'
Panjang (P) = 0.05 m'
Jumlah btg (Jb) = 4.00 btg
Jumlah (J) = 4.00 bh
Volume (V) = Bj x P x J
= 0 x 0.05 x 4.00 x 4.00
(V1) = 0.00 Kg
Sengkang
Diamater (Ø) = 0.00 mm
Berat (Bj) = 0 Kg / m'
Panjang (P) = 0.65 m'
Jumlah btg (Jb) = 1.00 btg
Jumlah (J) = 4.00 bh
Volume (V) = Bj x P x J
= 0 x 0.65 x 1.00 x 4.00
(V2) = 0.00 Kg

(V) = V1 + V2
(V) = 0.00 + 0.00
(V) = 0.00 Kg

(V) = 0.00 Kg

Total Pembesihan Kolom Struktur 15x15 (V) = 380.00 Kg

RING BALOK
3. Balok Struktur Bertulang 0.20 0.25

Panjang tot (P) = 65.00 m'


Lebar (L) = 0.20 m'
Tinggi (T) = 0.25 m'
Jumlah (J) = 1.00 bh
Volume (V) = PxLxTxJ
(V) = 65.00 x 0.20 x 0.25 x 1.00
(V) = 3.25 m3

Total Cor Beton Balok Struktur (V) = 3.25 m3

Pembesihan 0.20 0.25


Tulangan Pokok
Diamater (Ø) = 12.00 mm
Berat (Bj) = 0.888 Kg / m'
Panjang (P) = 65.05 m'
Jumlah (J) = 4.00 bh
Volume (V) = Bj x P x J
= 0.888 x 65.05 x 4.00
(V1) = 231.06 Kg
Sengkang
Diamater (Ø) = 8.00 mm
Berat (Bj) = 0.395 Kg / m'
Panjang (P) = 0.93 m'
Jumlah (J) = 434.00 bh
Volume (V) = Bj x P x J
= 0.395 x 0.93 x 434.00
(V2) = 158.57 Kg

(V) = V1 + V2
(V) = 231.06 + 158.57
(V) = 389.00 Kg

Total Pembesihan Balok Struktur (V) = 389.00 Kg


ANALISA HARGA DASAR SATUAN BAHAN

Jenis : S i r t u
Lokasi : Quarry
Tujuan : Lokasi Pekerjaan

HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi Base Camp L 5.00 Km
4 Harga satuan Sirtu di Quarry RpM16 1.00 M3 357,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 0.00
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 0.00
7 Berat volume sirtu Bil 1.51 ton/m3

II. URUTAN KERJA


1 Sirtu digali dengan Excavator
2 Excavator sekaligus memuat sirtu hasil
galian ke dalam Dump Truck
3 Dump Truck mengangkut sirtu ke lokasi
Base Camp

III. PERHITUNGAN

EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.6826 M3 / Jam
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 0.00 Rupiah

DUMP TRUCK (E09)


Kapasitas bak V 3.00 m3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts2
- Muat = (V x 60)/(Q1 x Bil) T1 2.86 menit
- Waktu tempuh isi = (L/v1) x 60 T2 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T3 5.00 menit
- Lain-lain T4 1.00 menit
Ts2 16.36 menit

Bersambung
ANALISA HARGA DASAR SATUAN BAHAN

Jenis : S i r t u
Lokasi : Quarry
Tujuan : Lokasi Pekerjaan

Lanjutan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)

Kapasitas Produksi / Jam =


V x Fa x 60 Q2 6.05 M3 / Jam
Ts2 x Bil

Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 0.00 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga Satuan Dasar Sirtu =

( RpM16 + Rp1 + Rp2 ) M16 357,000.00 Rupiah

Dibulatkan : M16 357,000.00 Rupiah


ANALISA HARGA DASAR SATUAN BAHAN

Jenis : Pasir Timbun / Urug


Lokasi : Quarry
Tujuan : Lokasi Pekerjaan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi pekerjaan L 5.00 Km
4 Harga satuan pasir urug di Quarry RpM44 1.00 M3 132,600.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 0.00
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 0.00
7 Berat volume pasir urug Bil 1.42 ton/m3

II. URUTAN KERJA


1 pasir urug digali dengan Excavator
2 Excavator sekaligus memuat pasir urug
hasil galian ke dalam Dump Truck
3 Dump Truck mengangkut pasir urug
ke lokasi pekerjaan

III. PERHITUNGAN

EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.6826 M3 / Jam
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 0.00 Rupiah

DUMP TRUCK (E09)


Kapasitas bak V 3.00 m3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts2
- Muat = (V x 60)/(Q1 x Bil) T1 3.04 menit
- Waktu tempuh isi = (L/v1) x 60 T2 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T3 5.00 menit
- Lain-lain T4 1.00 menit
Ts2 16.54 menit

Bersambung
ANALISA HARGA DASAR SATUAN BAHAN

Jenis : Pasir Timbun / Urug


Lokasi : Quarry
Tujuan : Lokasi Pekerjaan

Lanjutan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)

Kapasitas Produksi / Jam =


V x Fa x 60 Q2 6.36 M3 / Jam
Ts2 x Bil

Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 0.00 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga Satuan Dasar pasir urug =

( RpM44 + Rp1 + Rp2 ) M44 132,600.00 Rupiah

Dibulatkan : M44 132,600.00 Rupiah


MOBILISASI

KAPASITAS HARGA JUMLAH


No. JENIS ALAT ALAT SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)

A PERALATAN
1 Dump Truck 3,5 M3 Unit 1 - -
2 CONCRETE MIXER 0.3-0.6 M3 125 Ltr Unit 1 - -
JUMLAH -

B DEMOBILISASI LS 1 - -
JUMLAH -

C LAIN-LAIN

JUMLAH -
JUMLAH -

Total Biaya Mobilisasi -


DIREKTORAT JENDRAL BINA MARGA
ANALISA HARGA SATUAN KODE
DIREKTORAT BINA PROGRAM JALAN ACUAN UNTUK BETON STRUKTUR
SUBDIT PERENCANAAN Menggunakan Buruh K.710
JALAN LOKAL
DAN KABUPATEN

Propinsi Kode Kabupaten Kode Disiapkan oleh : Tanggal :

SUMATERA UTARA 03 SAMOSIR 0 CV. BETHALINK INTERNUSA PERSADA

PROSES : ANGGAPAN :
1 Pengadaan bahan oleh Leveransir 1. Kelompok tukang kayu memasang 20m2 dalam satu hari kerja
2 Kelompok tukang kayu memotong 2. 1/3 material dapat dipakai kembali
dan membuat acuan 3. Pengadaan bahan oleh pemasok
3 Kelompok tukang kayu membongkar 4. Untuk 1m3 beton dipakai 20 lbr plywood (120 cm x 240 cm x 1,75cm )
acuan setelah beton cukup kuat 5. Kelompok tukang kayu membongkar acuan
4 Kelompok Tukang Kayu membersihkan
acuan untuk dipakai kembali.

JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Kepala Tukang 1.00 1.00 L073 1.00 #REF! #REF!
Tukang 4.00 1.00 L079 4.00 #REF! #REF!
P E K E R J A

Buruh tak terampil 7.00 1.00 L101 7.00 #REF! #REF!


Buruh terampil 3.00 1.00 L106 3.00 #REF! #REF!

PEKERJA Rp. #REF!


TOTAL HARGA BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME (Rp / Unit ) (Rp. ) (Rp.)

Paku Biasa Kg M166 4.00 #REF! #REF!


M A T E R I A L

Kayu Acuan M3 M180 0.60 #REF! #REF!


Alat bantu kerja ( 3 set ) Set M170 0.56 #REF! #REF!

MATERIAL Rp. #REF!


HARI JUMLAH HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KERJA KODE JAM (Rp./Jam) (Rp. ) (Rp.)
KERJA
P E R A L A T A N

PERALATAN Rp. -
TOTAL Rp. #REF!

Volume 20 Satuan M2 Harga Satuan Rp. #REF! / M2


DIREKTORAT JENDRAL BINA MARGA
ANALISA HARGA SATUAN KODE
DIREKTORAT BINA PROGRAM JALAN MEMOTONG, MEMBENGKOK DAN MEMASANG TULANGAN BESI BETON
SUBDIT PERENCANAAN Menggunakan Buruh K.715
JALAN LOKAL
DAN KABUPATEN

Propinsi Kode Kabupaten Kode Disiapkan oleh : Tanggal :

SUMATERA UTARA 03 SAMOSIR 0 CV. BETHALINK INTERNUSA PERSADA

PROSES : ANGGAPAN :
1 Batang besi beton dipotong sesuai 1. 200 Kg tulangan jadi disiapkan dalam 1 hari
ukuran panjang yang diperlukan. 2. Besi untuk tulangan dikirim ke tempat pekerjaan oleh Pemasok
2 Batang dan beugel besi beton 3. Penyusutan akibat pemotongan 10% dan pakai kawat baja dll dianggap 1%
dibengkok sesuai yang diperlukan. 4. Membengkok dan memasang batang besi beton dilaksanakan dengan tangan.
3 Perakitan tulangan besi beton 5. Panjang dan diameter besi tulangan yang biasa dipakai gorong-gorong dll.
dan diikat dengan kawat baja. 6. 0,8 orang -hari memotong 200kg batang besi beton.
7. 1,0 orang hari membengkok 200kg batang besi beton.
8. 1,2 orang-hari memasang dan mengikat 200kg tulangan besi beton.
9. Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat

JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Kepala Tukang 1.00 1.00 L073 1.00 #REF! #REF!
P E K E R J A

Buruh tak terampil 3.00 1.00 L101 3.00 #REF! #REF!


Buruh terampil 1.00 1.00 L106 1.00 #REF! #REF!

PEKERJA Rp. #REF!


TOTAL HARGA BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME (Rp / Unit ) (Rp. ) (Rp.)

Besi Beton Kg M167 225.00 #REF! #REF!


M A T E R I A L

Alat bantu kerja ( 3 set ) Set M170 0.12 #REF! #REF!

MATERIAL Rp. #REF!


HARI JUMLAH HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KERJA KODE JAM (Rp./Jam) (Rp. ) (Rp.)
KERJA
P E R A L A T A N

PERALATAN Rp. -
TOTAL Rp. #REF!

Volume 200 Satuan Kg Harga Satuan Rp. #REF! / Kg


DIREKTORAT JENDRAL BINA MARGA
ANALISA HARGA SATUAN KODE
DIREKTORAT BINA PROGRAM JALAN MEMBUAT PARIT
SUBDIT PERENCANAAN Menggunakan Buruh K.110
JALAN LOKAL
DAN KABUPATEN

Propinsi Kode Kabupaten Kode Disiapkan oleh : Tanggal :

SUMATERA UTARA 03 SAMOSIR 0 #REF!

PROSES : ANGGAPAN :
1 Gali parit dengan tenaga manusia 1. Menggunakan tenaga manusia ( 100 m / hari )
2 Membuang sisa galian menggunakan 2. Dimensi parit : Lebar bawah = 0,5 m
truk bak terbuka Lebar atas = 1,3 m
Kedalaman = 0,6 m ( Vol = 0,54 m3/m )
3. 25 % hasil galian dibuang setempat
4. sisa galian dibuang sejauh 2 km
5. Menggali dan membuang dihitung 1,5 m3/orang-hari
6. Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat

JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Buruh tak terampil 36.00 1.00 L101 36.00 #REF! #REF!
P E K E R J A

PEKERJA Rp. #REF!


TOTAL HARGA BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME (Rp / Unit ) (Rp. ) (Rp.)

Alat bantu kerja ( 3 set ) Set M170 1.44 #REF! #REF!


M A T E R I A L

MATERIAL Rp. #REF!


HARI JUMLAH HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KERJA KODE JAM (Rp./Jam) (Rp. ) (Rp.)
KERJA
P E R A L A T A N

PERALATAN Rp. -
TOTAL Rp. #REF!

Volume 54 Satuan M3 Harga Satuan Rp. #REF! / M3


DIREKTORAT JENDRAL BINA MARGA
ANALISA HARGA SATUAN KODE
DIREKTORAT BINA PROGRAM JALAN Pengupasan dan Pembersihan Semak Pada DAMIJA
SUBDIT PERENCANAAN Menggunakan Buruh K.210
JALAN LOKAL
DAN KABUPATEN

Propinsi Kode Kabupaten Kode Disiapkan oleh : Tanggal :

SUMATERA UTARA 03 SAMOSIR 0 #REF!

PROSES : ANGGAPAN :
1 Mengupas dan membuang semak 1. Menggunakan tenaga manusia ( 1200 m2 / hari )
dengan tenaga manusia pada 2. Tidak ada pohon besar pada DAMIJA ( hanya semak )
DAMIJA (Daerah Milik Jalan) 3. DAMIJA 12 m
2 Lebar Pengupasan dan pembersihan 4. Pembersihan DAMIJA 100 m / hari
= DAMIJA minus Lebar Badan Jalan 5. Bakar sampah di lokasi pekerjaan
6. Hasil kerja 25 m2 / orang - hari
7. Umur alat bantu rata-rata 1 bulan / orang / set @ 3 alat

JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Buruh tak terampil 48.00 1.00 L101 48.00 #REF! #REF!
P E K E R J A

PEKERJA Rp. #REF!


TOTAL HARGA BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME (Rp / Unit ) (Rp. ) (Rp.)

Alat bantu kerja ( 3 set ) Set M170 1.92 #REF! #REF!


M A T E R I A L

MATERIAL Rp. #REF!


HARI JUMLAH HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KERJA KODE JAM (Rp./Jam) (Rp. ) (Rp.)
KERJA
P E R A L A T A N

PERALATAN Rp. -
TOTAL Rp. #REF!

Volume 1,200 Satuan M2 Harga Satuan Rp. #REF! / M2


DIREKTORAT JENDRAL BINA MARGA
ANALISA HARGA SATUAN KODE
DIREKTORAT BINA PROGRAM JALAN GALIAN TANAH UNTUK KONSTRUKSI
SUBDIT
PERENCANAAN JALAN LOKAL Menggunakan Buruh K.224
DAN
KABUPATEN
Propinsi Kode Kabupaten Kode Disiapkan oleh : Tanggal :

SUMATERA UTARA 03 SAMOSIR 0 #REF!

PROSES : ANGGAPAN :
1 Digali dengan tenaga manusia 1. Menggunakan tenaga manusia ( 40 m3 / hari )
2 Membuang tanah galian sejauh 2. Kepastian kerja per orang 1,3 m3 / hari
30 m dari lobang galian 3. Kedalaman rata-rata galian s/d 3 m
4. Umur alat bantu rata-rata 1 bulan / orang / set @ 3 alat

JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH (Rp./org
PEKERJA HARI KODE (Rp. ) (Rp.)
ORANG
ORANG /hari)
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Buruh tak terampil 30.00 1.00 L101 30.00 #REF! #REF!
P E K E R J A

PEKERJA Rp. #REF!


TOTAL HARGA BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME (Rp / Unit ) (Rp. ) (Rp.)

Alat bantu kerja ( 3 set ) Set M170 1.20 #REF! #REF!


M A T E R I A L

MATERIAL Rp. #REF!


HARI JUMLAH HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KERJA KODE JAM (Rp./Jam) (Rp. ) (Rp.)
KERJA
P E R A L A T A N

PERALATAN Rp. -
TOTAL Rp. #REF!

Volume 40 Satuan M3 Harga Satuan Rp. #REF! / M3


DIREKTORAT JENDRAL BINA MARGA
ANALISA HARGA SATUAN KODE
DIREKTORAT BINA PROGRAM JALAN GALIAN TANAH DAN PEMBUANGAN
SUBDIT PERENCANAAN Menggunakan Buruh K.320
JALAN LOKAL
DAN KABUPATEN

Propinsi Kode Kabupaten Kode Disiapkan oleh : Tanggal :

SUMATERA UTARA 03 SAMOSIR 0 #REF!

PROSES : ANGGAPAN :
1 Digali dengan tenaga manusia 1. Menggunakan tenaga manusia ( 32 m3 / hari )
2 Permukaan tanah dibentuk dan 2. 20 % dibuang di lokasi tanpa diangkut dengan truk
diratakan dengan tenaga manusia 3. 80 % dibuang dan diangkut dengan truk
3 Dimuat ke truk dengan tenaga 4. Jarak 1 rit pp < 2 Km
manusia 5. 1,6 rit pp / jam / truk
4 Membuang tanah menggunakan truk 6. Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat
3,5 ton

JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Supir Terampil 2.00 1.00 L091 2.00 #REF! #REF!
P E K E R J A

Pembantu Supir 2.00 1.00 L099 2.00 #REF! #REF!


Buruh tak terampil 36.00 1.00 L101 36.00 #REF! #REF!

PEKERJA Rp. #REF!


TOTAL HARGA BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME (Rp / Unit ) (Rp. ) (Rp.)

Alat bantu kerja ( 3 set ) Set M170 1.44 #REF! #REF!


M A T E R I A L

MATERIAL Rp. #REF!


HARI JUMLAH HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KERJA KODE JAM (Rp./Jam) (Rp. ) (Rp.)
KERJA
#REF! 2.00 1.00 E211 10.00 #REF! #REF!
P E R A L A T A N

PERALATAN Rp. #REF!


TOTAL Rp. #REF!

Volume 32 Satuan M3 Harga Satuan Rp. #REF! / M3


DIREKTORAT JENDRAL BINA MARGA
ANALISA HARGA SATUAN KODE
DIREKTORAT BINA PROGRAM JALAN GALIAN TANAH DAN PEMBUANGAN
SUBDIT
PERENCANAAN JALAN LOKAL Menggunakan Alat K.321
DAN
KABUPATEN
Propinsi Kode Kabupaten Kode Disiapkan oleh : Tanggal :

SUMATERA UTARA 03 SAMOSIR 0 #REF!

PROSES : ANGGAPAN :
1 Digali dengan buldozer 1. Menggunakanperalatan berat ( 200 m3 / hari )
2 Permukaan tanah dibentuk dan 2. 20 % dibuang di lokasi tanpa diangkut dengan truk
diratakan dengan grader 3. 80 % diangkut dan dibuang dengan 1 truk
3 Dimuat ke truk dengan loader 4. Jarak 1 rit pp , 2 Km
dirapihkan dengan grader 5. 2,5 rit pp / jam / truk
4 Membuang tanah menggunakan
truck

JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH (Rp./org
PEKERJA HARI KODE (Rp. ) (Rp.)
ORANG
ORANG /hari)
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Operator Terampil 3.00 1.00 L081 3.00 #REF! #REF!
Pembantu Operator 3.00 1.00 L089 3.00 #REF! #REF!
P E K E R J A

Supir Terampil 4.00 1.00 L091 4.00 #REF! #REF!


Pembantu Supir 4.00 1.00 L099 4.00 #REF! #REF!
Buruh tak terampil 6.00 1.00 L101 6.00 #REF! #REF!

PEKERJA Rp. #REF!


TOTAL HARGA BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME (Rp / Unit ) (Rp. ) (Rp.)

Alat bantu kerja ( 3 set ) Set M170 0.24 #REF! #REF!


M A T E R I A L

MATERIAL Rp. #REF!


HARI JUMLAH HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KERJA KODE JAM (Rp./Jam) (Rp. ) (Rp.)
KERJA
Buldozer 110 hp 1.00 1.00 E001 5.00 #REF! #REF!
Grader 110 HP E010
P E R A L A T A N

1.00 1.00 5.00 #REF! #REF!


Wheel Loader 80 HP 1.00 1.00 E052 5.00 #REF! #REF!
Dump truk (5 T) - 68 HP 4.00 1.00 E221 20.00 #REF! #REF!

PERALATAN Rp. #REF!


TOTAL Rp. #REF!

Volume 200 Satuan M3 Harga Satuan Rp. #REF! / M3


DIREKTORAT JENDRAL BINA MARGA
ANALISA HARGA SATUAN KODE
DIREKTORAT BINA PROGRAM JALAN PENYIAPAN TANAH DASAR
SUBDIT PERENCANAAN Menggunakan Alat K.342
JALAN LOKAL
DAN KABUPATEN

Propinsi Kode Kabupaten Kode Disiapkan oleh : Tanggal :

SUMATERA UTARA 03 SAMOSIR 0 #REF!

PROSES : ANGGAPAN :
1. Pembentukan tanah dasr dengan 1. Menggunakan alat berat ( 8 m x 500 m/hari )
Grader 2. DAMIJA dibersihkan dari semak dan lain-lain
2. Dipadatkan dengan mesin gilas roda baja 3. Lebar dasar jalan 8 m
sampai 100 % MDD ( AASHTO 199 ) 4. Hasil kerja menyiapkan dasar jalan 500 m/hari

JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Operator Terampil 2.00 1.00 L081 2.00 #REF! #REF!
P E K E R J A

Pembantu Operator 2.00 1.00 L089 2.00 #REF! #REF!


Buruh tak terampil 80.00 1.00 L101 80.00 #REF! #REF!

PEKERJA Rp. #REF!


TOTAL HARGA BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME (Rp / Unit ) (Rp. ) (Rp.)

Alat bantu kerja ( 3 set ) Set M170 0.16 #REF! #REF!


M A T E R I A L

MATERIAL Rp. #REF!


HARI JUMLAH HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KERJA KODE JAM (Rp./Jam) (Rp. ) (Rp.)
KERJA
MOTOR GRADER >100 HP 1.00 1.00 E13 6.00 #REF! #REF!
THREE WHEEL ROLLER 6-8 T 1.00 1.00 E16 6.00 #REF! #REF!
P E R A L A T A N

PERALATAN Rp. #REF!


TOTAL Rp. #REF!

Volume 4,000 Satuan M2 Harga Satuan Rp. #REF! / M2


DIREKTORAT JENDRAL BINA MARGA
ANALISA HARGA SATUAN KODE
DIREKTORAT BINA PROGRAM JALAN PEMBERSIHAN SEMAK DLL PADA BAHU JALAN
SUBDIT PERENCANAAN Menggunakan Buruh K.422
JALAN LOKAL
DAN KABUPATEN

Propinsi Kode Kabupaten Kode Disiapkan oleh : Tanggal :

SUMATERA UTARA 03 SAMOSIR 0 #REF!

PROSES : ANGGAPAN :
1 Potong semak belukar yang tumbuh 1. Menggunakan tenaga manusia ( 2 x 1,5 x 500 m/hari )
pada bahu jalan 2. Dengan lebar 1,5 m dari tepi jalan, rata-rata luas yang dibersihkan
2 Bersihkan rumput/semak dari 1.500 m2/km satu sisi
bahu dan aspalan 3. Hasil Kerja 60 m2/hari - orang
4. Sampah / reruntuhan dibuang sejauh 1,0 Km
5. Penggunaan alat bantu 1 bulan/orang/set @ 3 alat

JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Buruh tak terampil 25.00 1.00 L101 25.00 #REF! #REF!
P E K E R J A

PEKERJA Rp. #REF!


TOTAL HARGA BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME (Rp / Unit ) (Rp. ) (Rp.)

Alat bantu kerja ( 3 set ) Set M170 1.00 #REF! #REF!


M A T E R I A L

MATERIAL Rp. #REF!


HARI JUMLAH HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KERJA KODE JAM (Rp./Jam) (Rp. ) (Rp.)
KERJA
P E R A L A T A N

PERALATAN Rp. -
TOTAL Rp. #REF!

Volume 1,500 Satuan M2 Harga Satuan Rp. #REF! / M2


DIREKTORAT JENDRAL BINA MARGA
ANALISA HARGA SATUAN KODE
DIREKTORAT BINA PROGRAM JALAN PEMBERSIHAN PARIT
SUBDIT PERENCANAAN Menggunakan Buruh K.424
JALAN LOKAL
DAN KABUPATEN

Propinsi Kode Kabupaten Kode Disiapkan oleh : Tanggal :

SUMATERA UTARA 03 SAMOSIR 0 #REF!

PROSES : ANGGAPAN :
1 Membersihkan dan membentuk ulang 1. Menggunakan tenaga manusia (500 m/hari)
parit dan menimbun tumpukan puing 2. Membersihkan sampah, kotoran yang menyumbat, tumbuh-tumbuhan dari parit dan gorong-gorong.
disepanjang jalan dengan tenaga orang
3. Pembuangan puing sejauh 1 km (10 m3/100 m)
4. Kapasitas 1,6 rit pp/jam/truk
2 Membuang puing dengan truk bak 5. Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat
terbuka, dimuat atau dibongkar dengan
tenaga orang

JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Supir Terampil 2.00 1.00 L091 2.00 #REF! #REF!
P E K E R J A

Pembantu Supir 2.00 1.00 L099 2.00 #REF! #REF!


Buruh tak terampil 36.00 1.00 L101 36.00 #REF! #REF!

PEKERJA Rp. #REF!


TOTAL HARGA BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME (Rp / Unit ) (Rp. ) (Rp.)

Alat bantu kerja ( 3 set ) Set M170 1.44 #REF! #REF!


M A T E R I A L

MATERIAL Rp. #REF!


HARI JUMLAH HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KERJA KODE JAM (Rp./Jam) (Rp. ) (Rp.)
KERJA
#REF! 2.00 1.00 E211 10.00 #REF! #REF!
P E R A L A T A N

PERALATAN Rp. #REF!


TOTAL Rp. #REF!

Volume 500 Satuan M' Harga Satuan Rp. #REF! / M'


DIREKTORAT JENDRAL BINA MARGA
ANALISA HARGA SATUAN KODE
DIREKTORAT BINA PROGRAM JALAN PLESTERAN CAMP. 1 : 2
SUBDIT PERENCANAAN Menggunakan Buruh G.50h
JALAN LOKAL
DAN KABUPATEN

Propinsi Kode Kabupaten Kode Disiapkan oleh : Tanggal :

SUMATERA UTARA 03 SAMOSIR 0 CV. MANDIRI TEKNIK KONSULTAN

PROSES : ANGGAPAN :

JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Kepala Tukang 0.0150 1.00 L073 0.0150 #REF! #REF!
Tukang 0.1500 1.00 L079 0.1500 #REF! #REF!
P E K E R J A

Buruh tak terampil 0.4000 1.00 L101 0.4000 #REF! #REF!


Mandor 0.0200 1.00 L061 0.0200 #REF! #REF!

PEKERJA Rp. #REF!


TOTAL HARGA BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME (Rp / Unit ) (Rp. ) (Rp.)

Pasir Pasang M3 M041 0.0084 #REF! #REF!


Semen Portland @ 40 Kg Zak M080 0.1430 #REF! #REF!
M A T E R I A L

MATERIAL Rp. #REF!


HARI JUMLAH HARGA BIAYA SUB TOTAL
PERALATAN JUMLAH KERJA KODE JAM (Rp./Jam) (Rp. ) (Rp.)
KERJA
P E R A L A T A N

PERALATAN Rp. -
TOTAL Rp. #REF!

Volume 1 Satuan M2 Harga Satuan Rp. #REF! / M2


ANALISA HARGA BAHAN SAMPAI DILOKASI PEKERJAAN

KODE JENIS MATERIAL LOKASI PENGAMBILAN TUJUAN JARAK ( KM )


Portland Cement 40 kg QUARRY PROYEK 5.00
SATUAN
No. URAIAN KODE KOEF. SATUAN
(Rp.)
I. ASUMSI
1 Manual ( Tenaga manusia )
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi pekerjaan L 5.00 Km
- Dump truck L1 5.00 Km
- Pikul L2 0.00 Meter
4 Harga satuan Semen Portland @ 40 kg RpM004 1.00 Zak 53,400.00
5 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam 0.00
8 Berat Jenis Semen BJ 3.15 T/m3

II. URUTAN KERJA


1 Muat - Bongkar Material dilakukan oleh Pemasok
2 Dump Truck mengangkut material ke
lokasi Pekerjaan
III. PERHITUNGAN
1 DUMP TRUCK (E08)
Kapasitas bak V 3.50 Ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 5.00 menit
- Waktu lain - lain T3 1.00 menit
- Waktu muat T4 45.00 menit
- Waktu bongkar T5 15.00 menit
Ts 73.50 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q1 18.82 Zak/ Jam
Ts x BJ

Biaya Dump Truck / m3 = (1 : Q1) x RpE08 Rp1 0.00 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga satuan Semen Portland @ 40 kg =

( RpM080+ Rp1 + Rp2 + Rp3 + Rp 4 ) 53,400.00 Rp/zak

Dibulatkan : 53,400.00 Rp/zak


ANALISA HARGA BAHAN SAMPAI DILOKASI PEKERJAAN

KODE JENIS MATERIAL LOKASI PENGAMBILAN TUJUAN JARAK ( KM )


Besi Beton Polos QUARRY PROYEK 5.00
SATUAN
No. URAIAN KODE KOEF. SATUAN
(Rp.)
I. ASUMSI
1 Manual ( Tenaga manusia )
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi pekerjaan L 5.00 Km
- Dump truck L1 5.00 Km
- Pikul L2 0.00 Meter
4 Harga satuan RpM006 1.00 kg 12,500.00
5 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam 0.00
8 Berat Janis Besi Beton BJ 7.85 T/m3

II. URUTAN KERJA


1 Muat - Bongkar Material dilakukan oleh Pemasok
2 Dump Truck mengangkut material ke
lokasi Pekerjaan
III. PERHITUNGAN
1 DUMP TRUCK (E08)
Kapasitas bak V 3.50 Ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 5.00 menit
- Waktu lain - lain T3 1.00 menit
- Waktu muat T4 45.00 menit
- Waktu bongkar T5 15.00 menit
Ts 73.50 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q1 302.09 Ton/ Jam
Ts x Bj

Biaya Dump Truck / m3 = (1 : Q1) x RpE08 Rp1 0.00 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga satuan Besi beton =

( RpM167+ Rp1 + Rp2 + Rp3 + Rp 4 ) 12,500.00 Rp/kg

Dibulatkan : 12,500.00 Rp/kg


ANALISA HARGA BAHAN SAMPAI DILOKASI PEKERJAAN

KODE JENIS MATERIAL LOKASI PENGAMBILAN TUJUAN JARAK ( KM )


Tripleks 120 x 240 tbl. 4 mm QUARRY PROYEK 5.00
SATUAN
No. URAIAN KODE KOEF. SATUAN
(Rp.)
I. ASUMSI
1 Manual ( Tenaga manusia )
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi pekerjaan L 5.00 Km
- Dump truck L1 5.00 Km
- Pikul L2 0.00 Meter
4 Harga satuan RpM009 1.00 Lbr 78,900.00
5 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam 0.00

II. URUTAN KERJA


1 Muat - Bongkar Material dilakukan oleh Pemasok
2 Dump Truck mengangkut material ke
lokasi Pekerjaan
III. PERHITUNGAN
1 DUMP TRUCK (E08)
Kapasitas bak V 4.00 m3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 5.00 menit
- Waktu lain - lain T3 1.00 menit
- Waktu muat T4 45.00 menit
- Waktu bongkar T5 15.00 menit
Ts 73.50 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q1 235.26 Lbr/ Jam
Ts

Biaya Dump Truck / m3 = (1 : Q1) x RpE08 Rp1 0 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga satuan Tripleks 120 x 240 tbl. 4 mm =

( RpM180+ Rp1 + Rp2 + Rp3 + Rp 4 ) 78,900.00 Rp/m3

Dibulatkan : 78,900.00 Rp/m3


ANALISA HARGA BAHAN SAMPAI DILOKASI PEKERJAAN

KODE JENIS MATERIAL LOKASI PENGAMBILAN TUJUAN JARAK ( KM )


Tripleks 120 x 240 tbl. 12 mm QUARRY PROYEK 5.00
SATUAN
No. URAIAN KODE KOEF. SATUAN
(Rp.)
I. ASUMSI
1 Manual ( Tenaga manusia )
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi pekerjaan L 5.00 Km
- Dump truck L1 5.00 Km
- Pikul L2 0.00 Meter
4 Harga satuan RpM009 1.00 Lbr 148,500.00
5 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam 0.00

II. URUTAN KERJA


1 Muat - Bongkar Material dilakukan oleh Pemasok
2 Dump Truck mengangkut material ke
lokasi Pekerjaan
III. PERHITUNGAN
1 DUMP TRUCK (E08)
Kapasitas bak V 4.00 m3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 5.00 menit
- Waktu lain - lain T3 1.00 menit
- Waktu muat T4 45.00 menit
- Waktu bongkar T5 15.00 menit
Ts 73.50 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q1 784.20 Lbr/ Jam
Ts

Biaya Dump Truck / m3 = (1 : Q1) x RpE08 Rp1 0 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga satuan Tripleks 120 x 240 tbl. 12 mm =

( RpM180+ Rp1 + Rp2 + Rp3 + Rp 4 ) 148,500.00 Rp/m3

Dibulatkan : 148,500.00 Rp/m3


ANALISA HARGA BAHAN SAMPAI DILOKASI PEKERJAAN

KODE JENIS MATERIAL LOKASI PENGAMBILAN TUJUAN JARAK ( KM )


Seng Gelombang BJLS- 30 QUARRY PROYEK 5.00
SATUAN
No. URAIAN KODE KOEF. SATUAN
(Rp.)
I. ASUMSI
1 Manual ( Tenaga manusia )
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi pekerjaan L 5.00 Km
- Dump truck L1 5.00 Km
- Pikul L2 0.00 Meter
4 Harga satuan RpM004 1.00 Lbr 51,000.00
5 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam 0.00
8 Berat Jenis Seng Gelombang BJ 1.00 T/m3

II. URUTAN KERJA


1 Muat - Bongkar Material dilakukan oleh Pemasok
2 Dump Truck mengangkut material ke
lokasi Pekerjaan
III. PERHITUNGAN
1 DUMP TRUCK (E08)
Kapasitas bak V 3.50 Ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 5.00 menit
- Waktu lain - lain T3 1.00 menit
- Waktu muat T4 45.00 menit
- Waktu bongkar T5 15.00 menit
Ts 73.50 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q1 2,371.43 Ton/ Jam
Ts x BJ

Biaya Dump Truck / m3 = (1 : Q1) x RpE08 Rp1 0.00 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga satuan Seng Gelombang BJLS- 30 =

( RpM080+ Rp1 + Rp2 + Rp3 + Rp 4 ) 51,000.00 Rp/Lbr

Dibulatkan : 51,000.00 Rp/Lbr


ANALISA HARGA BAHAN SAMPAI DILOKASI PEKERJAAN

KODE JENIS MATERIAL LOKASI PENGAMBILAN TUJUAN JARAK ( KM )


Keramik 40 x 40 cm setara Roman QUARRY PROYEK 5.00
SATUAN
No. URAIAN KODE KOEF. SATUAN
(Rp.)
I. ASUMSI
1 Manual ( Tenaga manusia )
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi pekerjaan L 5.00 Km
- Dump truck L1 5.00 Km
- Pikul L2 0.00 Meter
4 Harga satuan RpM004 1.00 bh 10,900.00
5 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam 0.00
8 Berat Jenis Keramik BJ 2.40 T/m3

II. URUTAN KERJA


1 Muat - Bongkar Material dilakukan oleh Pemasok
2 Dump Truck mengangkut material ke
lokasi Pekerjaan
III. PERHITUNGAN
1 DUMP TRUCK (E08)
Kapasitas bak V 3.50 Ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 5.00 menit
- Waktu lain - lain T3 1.00 menit
- Waktu muat T4 45.00 menit
- Waktu bongkar T5 15.00 menit
Ts 73.50 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q1 988.10 Ton/ Jam
Ts x BJ

Biaya Dump Truck / m3 = (1 : Q1) x RpE08 Rp1 0.00 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga satuan Keramik 40 x 40 cm setara Roman =

( RpM080+ Rp1 + Rp2 + Rp3 + Rp 4 ) 10,900.00 Rp/bh

Dibulatkan : 10,900.00 Rp/bh


ANALISA HARGA BAHAN SAMPAI DILOKASI PEKERJAAN

KODE JENIS MATERIAL LOKASI PENGAMBILAN TUJUAN JARAK ( KM )


Keramik 40 x 40 cm setara Granito QUARRY PROYEK 5.00
SATUAN
No. URAIAN KODE KOEF. SATUAN
(Rp.)
I. ASUMSI
1 Manual ( Tenaga manusia )
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi pekerjaan L 5.00 Km
- Dump truck L1 5.00 Km
- Pikul L2 0.00 Meter
4 Harga satuan RpM004 1.00 bh 44,000.00
5 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam 0.00
8 Berat Jenis Keramik BJ 2.40 T/m3

II. URUTAN KERJA


1 Muat - Bongkar Material dilakukan oleh Pemasok
2 Dump Truck mengangkut material ke
lokasi Pekerjaan
III. PERHITUNGAN
1 DUMP TRUCK (E08)
Kapasitas bak V 3.50 Ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 5.00 menit
- Waktu lain - lain T3 1.00 menit
- Waktu muat T4 45.00 menit
- Waktu bongkar T5 15.00 menit
Ts 73.50 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q1 988.10 Ton/ Jam
Ts x BJ

Biaya Dump Truck / m3 = (1 : Q1) x RpE08 Rp1 0.00 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga satuan Keramik 40 x 40 cm Tekstur Batu Kacang

( RpM080+ Rp1 + Rp2 + Rp3 + Rp 4 ) 44,000.00 Rp/bh

Dibulatkan : 44,000.00 Rp/bh


ANALISA HARGA BAHAN SAMPAI DILOKASI PEKERJAAN

KODE JENIS MATERIAL LOKASI PENGAMBILAN TUJUAN JARAK ( KM )


Keramik 20 x 40 cm QUARRY PROYEK 5.00
SATUAN
No. URAIAN KODE KOEF. SATUAN
(Rp.)
I. ASUMSI
1 Manual ( Tenaga manusia )
2 Kondisi Jalan : sedang / baik
3 Jarak Quarry ke lokasi pekerjaan L 5.00 Km
- Dump truck L1 5.00 Km
- Pikul L2 0.00 Meter
4 Harga satuan RpM004 1.00 bh 15,000.00
5 Harga Satuan Dasar Dump Truck RpE08 1.00 Jam 0.00
8 Berat Jenis Keramik BJ 2.40 T/m3

II. URUTAN KERJA


1 Muat - Bongkar Material dilakukan oleh Pemasok
2 Dump Truck mengangkut material ke
lokasi Pekerjaan
III. PERHITUNGAN
1 DUMP TRUCK (E08)
Kapasitas bak V 3.50 Ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts
- Waktu tempuh isi = (L/v1) x 60 T1 7.50 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 5.00 menit
- Waktu lain - lain T3 1.00 menit
- Waktu muat T4 45.00 menit
- Waktu bongkar T5 15.00 menit
Ts 73.50 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q1 988.10 Ton/ Jam
Ts x BJ

Biaya Dump Truck / m3 = (1 : Q1) x RpE08 Rp1 0.00 Rupiah

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga satuan Keramik 20 x 20 cm setara Roman

( RpM080+ Rp1 + Rp2 + Rp3 + Rp 4 ) 15,000.00 Rp/bh

Dibulatkan : 15,000.00 Rp/bh


Suplemen - 1
### 1 Unit Septictank dan Peresapan
Rangkuman Pekerjaan
4.9058 M3 Galian tanah A. 2.3.1.1 @ Rp 78,250.00 = Rp 383,878.85
0.2599 M3 Beton cor 1:3:5 A. A. 4.1.1.5 @ Rp 1,098,294.00 = Rp 285,446.61
0.7950 M3 Dinding Bata 1:2 A. 4.4.1.7 @ Rp 120,899.45 = Rp 96,115.06
9.2200 M2 Plesteran dinding 1:2 A. 4.4.2.2 @ Rp 67,977.04 = Rp 626,748.31
0.3713 M3 Beton Bertulang 1:2:3 A. 4.1.1.7 @ Rp 1,160,096.00 = Rp 430,743.64
21.0000 Kg Pembesian A. 4.1.1.17 @ Rp 15,046.50 = Rp 315,976.50
2.4750 M2 Bekisting A. 4.1.1.24 @ Rp 436,235.00 = Rp 1,079,681.63
0.3649 M3 Urugan Pasir A. 2.3.1.11 @ Rp 190,420.00 = Rp 69,484.26
0.5100 M3 Batu Kosong A. 3.2.1.9 @ Rp 588,799.20 = Rp 300,287.59
4.0000 M' Pipa PVC Class AW Ø 4" A. 5.1.1.32 @ Rp 77,725.00 = Rp 310,900.00
1.0000 Bh Pipa hawa Ø 2" @ Rp 27,500.00 = Rp 27,500.00
20.0000 Ikat Ijuk peresapan @ Rp 5,000.00 = Rp 100,000.00
Jumlah = Rp 4,026,762.45
Dibulatkan = Rp 4,026,762.00
ANALISA MEUBELAIR

Anl -1 Pekerjaan Satu Unit Meja Siswa Tunggal


No Pekerjaan / Bahan Sat Koefisien Harga Sat Jumlah Harga
1 Kayu Kls II M3 0.0070 Rp 5,950,000 Rp 41,458
2 Multipleks 18 mm Lbr 0.4635 Rp 300,000 Rp 139,063
3 Paku Kg 0.3000 Rp 20,800 Rp 6,240
4 Cat Menie kayu Kg 0.2500 Rp 51,200 Rp 12,800
5 Cat Minyak Kg 0.2000 Rp 65,000 Rp 13,000
6 Tinner Ltr 0.2194 Rp 23,100 Rp 5,068
7 Amplas Lbr 3.0000 Rp 2,000 Rp 6,000
8 Pekerja Org 0.6000 Rp 100,000 Rp 60,000
9 Tukang Org 0.5000 Rp 120,000 Rp 60,000
Jumlah Rp 343,629
Dibulatkan Rp 343,000

Anl -2 Pekerjaan Satu Unit Kursi Siswa


No Pekerjaan / Bahan Sat Koefisien Harga Sat Jumlah Harga
1 Kayu Kls II M3 0.0054 Rp 5,950,000 Rp 32,237
2 Papan Kayu Kls II M3 0.0035 Rp 6,270,000 Rp 21,714
2 Paku Kg 0.2000 Rp 20,800 Rp 4,160
3 Cat Minyak Kg 0.1500 Rp 65,000 Rp 9,750
4 Tinner Ltr 0.1500 Rp 23,100 Rp 3,465
5 Amplas Lbr 2.0000 Rp 2,000 Rp 4,000
6 Pekerja Org 0.6000 Rp 100,000 Rp 60,000
7 Tukang Org 0.5000 Rp 120,000 Rp 60,000
Jumlah Rp 195,326
Dibulatkan Rp 195,000
Anl -5 Pekerjaan Satu Unit Lemari Simpan
No Pekerjaan / Bahan Sat Koefisien Harga Sat Jumlah Harga
1 Kayu Kls II m3 0.0362 Rp 5,950,000 Rp 215,481
2 Triplek 9 mm lbr 2.5645 Rp 144,000 Rp 369,290
3 Dempul Kayu kg 0.5000 Rp 11,000 Rp 5,500
4 Cat Minyak Kg 0.1800 Rp 65,000 Rp 11,700
5 Vernis kg 1.0000 Rp 42,000 Rp 42,000
6 Tinner Ltr 0.5000 Rp 23,100 Rp 11,550
7 Amplas lbr 5.0000 Rp 2,000 Rp 10,000
8 Paku kg 1.0000 Rp 20,800 Rp 20,800
9 Kunci bh 3.0000 Rp 10,500 Rp 31,500
10 Engsel bh 8.0000 Rp 18,200 Rp 145,600
11 Handle bh 2.0000 Rp 10,000 Rp 20,000
12 Pekerja org 1.0000 Rp 100,000 Rp 100,000
13 Tukang kayu org 1.0000 Rp 120,000 Rp 120,000
Jumlah Rp 1,103,421
Dibulatkan Rp 1,103,000
PERHITUNGAN BANGUNAN A

II. PEKERJAAN TANAH

1 Pekerjaan Galian Pondasi

1.1. Pekerjaan Galian Pondasi Menerus


a. Panjang pondasi Menerus = 57.00 m
Luasan = ((0,8+1,23)/2)*0,85
= 0.86275 m2
Volume = 0.86275 x 57.00
= 49.18 m3

Total Galian Pondasi Menerus = 49.18


= 49.18 m3

2. Pek. Urugan Pasir di Bawah Pondasi

2.1. Pek. Urugan Pasir di Bawah Pondasi


a. Panjang pondasi Menerus = 57.00 m
Luasan = (0,05*0,8)
= 0.04 m2
Volume = 0.04 x 57.00
= 2.28 m3

Total Urugan Pasir di Bawah Pondasi = 2.28


= 2.28 m3

3. Pek. Urugan Pasir di Bawah Lantai


Tebal = 0.05 m
Luasan I = 8.87 x 6.87
= 60.9369 m2
II = 8.87 x 6.87
= 60.9369 m2
III = 1.9 x 18
= 34.2 m2

Luasan = 60.9369 + 60.9369 + 34.2


= 156.0738 m2

Luasan Total = 156.0738


= 156.0738 m2

Total Volume Urugan Pasir = 0.05 x 156.0738


= 7.80 m3

4. Pek. Urugan Peil Lantai


Tebal = 0.10 m
Luasan I = 8.87 x 6.87
= 60.9369 m2
II = 8.87 x 6.87
= 60.9369 m2
III = 1.9 x 18
= 34.2 m2

Luasan Total = 60.9369 + 60.9369 + 34.2


= 156.0738 m2

Luasan Total = 156.0738


= 156.0738 m2

Total Volume Urugan Tanah = 0.10 x 156.0738


= 15.61 m3
IV. Urugan Kembali Galian Pondasi
Total Urugan Tanah Kembali = 0.25 x Total Galian Pondasi Menerus
= 0.25 x 49.18
= 12.29 m3

B. PEKERJAAN STRUKTUR

I. Pekerjaan Pondasi
1. Pasang Pondasi Batu Kosong
Panjang pondasi Menerus = 57.00 m
Luasan = (0,1*0,8)
= 0.08 m2
Volume = 0.08 x 57.00
= 4.56 m3

2. Pasangan Pondasi Batu Belah/Batu Kali 1 ; 4


Panjang pondasi Menerus = 57.00 m
Luasan = ((0,6+0,25)/2)*0,7
= 0.2975 m2
Volume = 0.2975 x 57.00
= 16.96 m3
II. Pekerjaan Beton Bertulang

1. Kolom Beton Bertulang Campuran 1 : 2 : 3 Uk. 13 x 20 Cm (kolom Praktis)


Tinggi = 3.55 m
Jumlah = 11.00 bh
Dimensi = 0.13 x 0.2
= 0.026 m3
= 0.026 x 3.55 x 11.00
= 1.0153 m3

Volume Keseluruhan = 1.02


= 1.02 m3 s
Volume Total Kolom = Volume Kolom - Volume besi
= 1.0153 - 0.024395
= 0.99090536512 m3

Pembesian dia 12 Panjang = 3.55 m


Jumlah = 4.00 bh
Panjang 1 ttk = 3.55 x 4.00
= 14.2 m
Panjang keseluruhan = 11.00 x 14.20
= 156.2 m
Berat = 12.00 x 12.00 x 0.006165 x 156.20
= 138.6681 kg
dia 8 Panjang = 0.51 m
Jumlah = 23.67 bh
= 24.00 bh
Panjang 1 ttk = 0.51 x 24.00
= 12.192 m
Panjang keseluruhan = 11.00 x 12.19
= 134.112 m
Berat = 8.00 x 8.00 x 0.006165 x 134.11
= 52.91523 kg

Total Berat Besi Kolom = 138.6681 + 52.9152307 +

= 191.5833 kg

Volume Besi dia 12 = 3.14 x 0.006 x 0.006 x 156.2


= 0.017657 m3

dia 8 = 3.14 x 0.004 x 0.004 x 134.112


= 0.006738 m3

Volume Total Besi = 0.017657 + 0.00673779

= 0.024395 m3

Bekisting
Sisi = 2
Luasan = 0.13 x 3.55 x 2
= 0.923 m2

Sisi = 2
Luasan = 0.2 x 3.55 x 2
= 1.42 m2

Luasan I = (0,923+1,42) x 11
= 25.77 m2

Luasan Total Bekisting Kolom = 25.77


= 25.77 m2

2. Kolom Beton Bertulang Campuran 1 : 2 : 3 Uk. 15 x 20 Cm (kolom Induk)


Tinggi = 3.55 m
Jumlah = 6.00 bh
Dimensi = 0.15 x 0.2
= 0.03 m3
= 0.03 x 3.55 x 6.00
= 0.639 m3

Volume Keseluruhan = 0.64


= 0.64 m3 s
Volume Total Kolom = Volume Kolom - Volume besi
= 0.639 - 0.013596
= 0.62540445312 m3

Pembesian dia 12 Panjang = 3.55 m


Jumlah = 4.00 bh
Panjang 1 ttk = 3.55 x 4.00
= 14.2 m
Panjang keseluruhan = 6.00 x 14.20
= 85.2 m
Berat = 12.00 x 12.00 x 0.006165 x 85.20
= 75.63715 kg

dia 8 Panjang = 0.55 m


Jumlah = 23.67 bh
= 24.00 bh
Panjang 1 ttk = 0.55 x 24.00
= 13.152 m
Panjang keseluruhan = 6.00 x 13.15
= 78.912 m
Berat = 8.00 x 8.00 x 0.006165 x 78.91
= 31.13552 kg

Total Berat Besi Kolom = 75.63715 + 31.1355187 +

= 106.7727 kg

Volume Besi dia 12 = 3.14 x 0.006 x 0.006 x 85.2


= 0.009631 m3

dia 8 = 3.14 x 0.004 x 0.004 x 78.912


= 0.003965 m3

Volume Total Besi = 0.009631 + 0.00396454

= 0.013596 m3

Bekisting
Sisi = 2
Luasan = 0.15 x 3.55 x 2
= 1.065 m2
Sisi = 2
Luasan = 0.2 x 3.55 x 2
= 1.42 m2

Luasan I = (1,065+1,42) x 6
= 14.91 m2

Luasan Total Bekisting Kolom = 14.91


= 14.91 m2

2. Kolom Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 20 Cm (kolom Selasar)


Tinggi = 2.97 m
Jumlah = 7.00 bh
Dimensi = 0.2 x 0.2
= 0.04 m3
= 0.04 x 2.97 x 7.00
= 0.8316 m3

Volume Keseluruhan = 0.83


= 0.83 m3 s
Volume Total Kolom = Volume Kolom - Volume besi
= 0.8316 - 0.013958
= 0.8176418208 m3

Pembesian dia 12 Panjang = 2.97 m


Jumlah = 4.00 bh
Panjang 1 ttk = 2.97 x 4.00
= 11.88 m
Panjang keseluruhan = 7.00 x 11.88
= 83.16 m
Berat = 12.00 x 12.00 x 0.006165 x 83.16
= 73.82612 kg

dia 8 Panjang = 0.65 m


Jumlah = 19.80 bh
= 20.00 bh
Panjang 1 ttk = 0.65 x 20.00
= 12.96 m
Panjang keseluruhan = 7.00 x 12.96
= 90.72 m
Berat = 8.00 x 8.00 x 0.006165 x 90.72
= 35.79448 kg

Total Berat Besi Kolom = 73.82612 + 35.7944832 +

= 109.6206 kg

Volume Besi dia 12 = 3.14 x 0.006 x 0.006 x 83.16


= 0.0094 m3

dia 8 = 3.14 x 0.004 x 0.004 x 90.72


= 0.004558 m3

Volume Total Besi = 0.0094 + 0.00455777

= 0.013958 m3

Bekisting
Sisi = 2
Luasan = 0.2 x 2.97 x 2
= 1.188 m2

Sisi = 2
Luasan = 0.2 x 2.97 x 2
= 1.188 m2

Luasan I = (1,188+1,188) x 7
= 16.63 m2

Luasan Total Bekisting Kolom = 16.63


= 16.63 m2
4. Sloof Beton Bertulang Campuran 1 : 2 : 3 Uk. 15 x 20 Cm
Panjang = 75.00 m
Dimensi = 0.15 x 0.2
= 0.03 m2
Volume = 0.03 x 75.00
= 2.25 m3
Volume Total = Volume Sloof - Volume besi
= 2.25 - 0.048884
= 2.20111648 m3

Pembesian dia 12 Panjang = 75.00 m


Jumlah = 4.00 bh
Panjang = 75.00 x 4.00
= 300 m
Berat = 12.00 x 12.00 x 0.006165 x 300.00
= 266.328 kg

dia 8 Panjang = 0.60 m


Jumlah = 500.00 bh
= 500.00 bh
Panjang = 0.60 x 500.00
= 298 m
Berat = 8.00 x 8.00 x 0.006165 x 298.00
= 117.5789 kg

Total Berat Besi Sloof = 266.328 + 117.57888


= 383.9069 kg

Volume Besi dia 12 = 3.14 x 0.006 x 0.006 x 300


= 0.033912 m3

dia 8 = 3.14 x 0.004 x 0.004 x 298


= 0.014972 m3

Volume Total Besi = 0.033912 + 0.01497152


= 0.048884 m3

Bekisting
Sisi = 2
Luasan I = 0.2 x 75.00
= 15 m2
Luasan Total Bekisting = 15 x 2
= 30.00 m2
5. Ring Balok Beton Bertulang Campuran 1 : 2 : 3 Uk. 15 x 20
Panjang = 75.00 m
Dimensi = 0.15 x 0.2
= 0.03 m2
Volume = 0.03 x 75.00
= 2.25 m3
Volume Total Balok = Volume Balok - Volume besi
= 2.25 - 0.038522
= 2.21147848 m3

Pembesian
Tul. Induk (dia 12) Panjang = 75.00 m
Jumlah = 4.00 bh
Panjang = 75.00 x 4.00
= 300 m
Berat = 12.00 x 12.00 x 0.006165 x 300.00
= 266.328 kg

dia 8 (sengkang) Panjang = 0.60 m


Jumlah = 500.00 bh
= 500.00 bh
Panjang = 0.60 x 500.00
= 298 m
Berat = 8.00 x 8.00 x 0.006165 x 298.00
= 117.5789 kg
Total Berat Besi = 266.328 + 117.57888
= 383.9069 kg

Volume Besi dia 10 = 3.14 x 0.005 x 0.005 x 300


= 0.02355 m3

dia 8 = 3.14 x 0.004 x 0.004 x 298


= 0.014972 m3

Volume Total Besi = 0.02355 + 0.01497152


= 0.038522 m3

Bekisting
Sisi = 2
Luasan I = 0.2 x 75.00 x 2
= 30.00 m2
Luasan Total Bekisting Ring Balok = 30.00
= 30.00 m2

5. LateiBalok Beton Bertulang Campuran 1 : 2 : 3 Uk. 13 x 15


Panjang = 36.00 m
Dimensi = 0.13 x 0.15
= 0.0195 m2
Volume = 0.0195 x 36.00
= 0.70 m3
Volume Total Balok = Volume Balok - Volume besi
= 0.702 - 0.016802
= 0.6851977344 m3

Pembesian
Tul. Induk (dia 12) Panjang = 36.00 m
Jumlah = 4.00 bh
Panjang = 36.00 x 4.00
= 144 m
Berat = 12.00 x 12.00 x 0.006165 x 144.00
= 127.8374 kg

dia 8 (sengkang) Panjang = 0.46 m


Jumlah = 240.00 bh
= 240.00 bh
Panjang = 0.46 x 240.00
= 109.44 m
Berat = 8.00 x 8.00 x 0.006165 x 109.44
= 43.18065 kg

Total Berat Besi = 127.8374 + 43.1806464


= 171.0181 kg

Volume Besi dia 10 = 3.14 x 0.005 x 0.005 x 144


= 0.011304 m3

dia 8 = 3.14 x 0.004 x 0.004 x 109.44


= 0.005498 m3

Volume Total Besi = 0.011304 + 0.00549827


= 0.016802 m3

Bekisting
Sisi = 2
Luasan I = 0.15 x 36.00 x 2
= 10.80 m2
Luasan Total Bekisting Ring Balok = 10.80
= 10.80 m2

II. PEKERJAAN ARSITEKTUR

3. Pekerjaan Kosen, Pintu dan Jendela

3.1. Pekerjaan Kusen Kayu


a. Kusen Pintu PJ1
Jumlah 2 bh
Sisi Tegak
a = 2.6 x 0.05 x 0.13
= 0.0169 m3
Jlh = 2 bh
Vol sisi Tegak = 0.0169 x 2
= 0.0338

b = 1.05 x 0.05 x 0.13


= 0.006825 m3
Jlh = 2 bh
Vol sisi Tegak = 0.006825 x 2
= 0.01365

Sisi Atas
a = 1.2 x 0.05 x 0.13
= 0.0078 m3
Jlh = 2 bh
Vol sisi Tegak = 0.0078 x 2
= 0.0156
b = 0.58 x 0.05 x 0.13
= 0.00377 m3
Jlh = 6 bh
Vol sisi Tegak = 0.00377 x 6
= 0.02262

Jlh Total Volume Kusen P1 = 0.0338 + 0.01365 + 0.0156 + 0.02262 x 2


= 0.17134 m3

b. Kusen Jendela J1
Jumlah 10 bh
Sisi Tegak = 1.3 x 0.05 x 0.13
= 0.00845 m3
Jlh = 3 bh
Vol sisi Tegak = 0.00845 x 3
= 0.02535

Sisi Atas = 0.58 x 0.05 x 0.13


= 0.00377 m3
Jlh = 9 bh
Vol sisi Tegak = 0.00377 x 9
= 0.03393

Jlh Total Volume Kusen J1 = 0.02535 + 0.03393 x 10


= 0.5928 m3

Total Volume Kusen = 0.17134 + 0.5928


= 0.76414 m3
3.3. Pekerjaan Daun Pintu Panel
Pintu P1 = 1.2 x 2.1
= 2.52 m2
Jumlah 2 bh
Daun Pintu 1 = 2.52 x 2
= 5.04 m2

Total Daun Pintu = 5.04


= 5.04 m2

3.4. Pekerjaan Daun Jendela Kaca


a. PJ1
Panjang = 4.64
Lebar = 0.07
Luasan = 4.64 x 0.07
= 0.3248 m2
Jumlah 2 bh
Luasan PJ1 = 0.3248 x 2
= 0.6496 m2

J1
Panjang = 8.16
Lebar = 0.07
Luasan = 8.16 x 0.07
= 0.5712 m2
Jumlah 10 bh
Luasan J1 = 0.5712 x 10
= 5.712 m2

Luasan Total Daun Jendela Kaca = 0.6496 + 5.712


= 6.3616 m2

3.5. Pekerjaan Jendela Kaca


a. PJ1
Panjang = 0.58
Lebar = 0.58
Luasan = 0.58 x 0.58 x 2
= 0.6728 m2

Jumlah 2 bh
Luasan PJ1 = 0.6728 x 2
= 2.6728

J1
Panjang = 0.58
Lebar = 0.78
Luasan = 0.58 x 0.78 x 3
= 1.3572 m2

Jumlah 10 bh
Luasan J1 = 1.3572 x 10
= 11.3572

Luas Total J1 2.6728 + 11.3572


= 14.03 m2
Luasan Total Jendela Kaca = 14.03
= 14.03 m2

4. Pekerjaan Dinding
4.1. Pasangan Dinding Batu Bata 1/2 Bata 1 : 2
Panjang = 57.00
Tinggi = 0.3
Luasan = 17.1 m2

PJ1 = (0,3*1,2)
= 0.36
Jlh = 2 bh
Luasn = 0.72 m2

Luasan Bata 1:2 = 17.1 - 0.72


= 16.38 m2

Luasan Total Bata 1:2 = 16.38


= 16.38 m2

4.2. Pasangan Dinding Batu Bata 1/2 Bata 1 : 4

I. Panjang = 57.00
Tinggi = 3.25
Luasan I = 185.25 m2

Luasan Total = 185.25


= 185.25 m2
PJ1 = (2,3*1,2)+(1,36*1,15)
= 4.324
Jlh = 2 bh
Luasn = 8.648 m2

J1 = 2.7
= 2.7
Jlh = 10 bh
Luasn = 27 m2

Luasan Bata 1:4 = 185.25 - (8,648+27)


= 149.602 m2

Luasan Total Bata 1:4 = 149.602


= 149.602 m2

4.3. Plesteran Dinding Batu Bata1 : 2


= 16.38 x 2
= 32.76 m2

4.5. Plesteran Dinding Batu Bata1 : 4


= 149.602 x 2
= 299.204 m2
5. Pekerjaan Lantai dan Pelapis

Luasan I = 8.87 x 6.87


= 60.9369 m2
II = 8.87 x 6.87
= 60.9369 m2
III = 1.9 x 18
= 34.2 m2

Luasan Total = 60.9369 + 60.9369 + 34.2


= 156.0738 m2

Luasan Total = 156.0738


= 156.0738 m2

5.1 Lantai Kerja Beton Cor 1 : 3 : 5 Dibawah Lantai/K-125


Luasn = 156.0738 m2
Tebal = 0.02 m
Volume = 156.0738 x 0.02
= 3.121476 m3
5.2 Cat Minyak Kozen, Pintu

pJ1 = 1.3 x 2.1 x 2


= 5.46

= 2.5 x 0.13 x 2
= 0.65

= 1.1 x 0.05 x 6
= 0.33

= 1.1 x 0.13 x 4
= 0.572

PJ1 = 5.46 + 0.65 + 0.33 + 0.572


= 7.012

Jumlah = 2

Total PJ1 = 7.012 x 2


= 14.024

J1 = 1.4 x 0.05 x 8
= 0.56

= 1.4 x 0.13 x 6
= 1.092

= 0.6 x 0.05 x 18
= 0.54

= 0.6 x 0.13 x 12
= 0.936

J1 = 0.56 + 1.092 + 0.54 + 0.936


= 3.128

Jumlah = 10

Total J1 = 3.128 x 10
= 31.28

Total Pengecatan Kusen = 14.024 + 31.28


= 45.304 m2

Pekerjaan Plafond

Plafond Dalam
Luasan I = 8.87 x 8
= 70.96 m2
Jlh = 2
Total Luas I = 141.92

Plafond Luar
Luasan I = 1x 6.87 x 2
= 13.74 m2

Luasan II = 2.4 x 18
= 43.2 m2

Luasan I + II + III = 13.74 + 43.2 + 141.92


= 198.86 m2

Frofil Kayu 2"


Panjang = 112.18 m
REKAPITULASI KEBUTUHAN BAHAN DAN UPAH

NO BAHAN SATUAN VOLUME HARGA SATUAN JUMLAH


1 Portlan semen @ 40 kg zak 293.70 53,600.00 15,742,233.17
2 Semen Warna kg 442.00 3,442.50 1,521,585.00
3 Pasir m3 36.46 121,400.00 4,426,537.06
4 Batu Belah m3 14.85 330,480.00 4,907,628.00
5 Batu Bata bh 7,846.30 653.40 5,126,772.42
6 Kerikil/ Batu Pecah m3 8.98 504,900.00 4,532,889.20
7 Pasir uruk m3 9.11 132,600.00 1,207,720.80
8 Keramik uk 40 x 40 cm Bh 2,254.20 10,900.00 24,570,780.00
9 Keramik uk 20 x 40 cm Bh - 8,000.00 -
10 Seng Gelombang M 133.32 51,000.00 6,799,279.20
11 Nok Spandek 30 M 32.37 30,000.00 971,190.00
12 Paku Biasa kg 63.47 20,800.00 1,320,227.85
13 Paku Seng kg 26.66 35,000.00 933,234.40
14 Kayu Kls II m3 4.43 5,950,000.00 26,376,861.70
15 Balok Kayu Sembarang m3 0.55 2,497,000.00 1,378,344.00
16 Kayu sembarang m3 1.46 2,497,000.00 3,634,549.97
17 Tripleks 120 x 240 tbl. 6 mm lbr 52.50 88,800.00 4,662,000.00
18 Tripleks 120 x 240 tbl. 9 mm lbr 6.31 144,000.00 908,544.00
19 Dolken btg 36.05 20,300.00 731,882.67
20 Minyak bekisting ltr 13.57 21,000.00 284,886.00
21 Besi Beton Kg 1,118.25 12,500.00 13,978,125.00
22 Kawat beton kg 15.98 15,900.00 254,002.50
23 Pipa PVC dia 3" btg 5.00 250,000.00 1,250,000.00
24 Keran Air bh 1.00 20,000.00 20,000.00
25 Pipa PVC dia 1/2" bh 4.00 45,000.00 180,000.00
26 Pipa PVC dia 1" bh 2.00 70,000.00 140,000.00
27 Selang Pipa dia 1" Rol - 350,000.00 -
28 Profil Alumunium M' 84.48 80,000.00 6,758,400.00
29 Skrup Fiser Bh 153.60 12,200.00 1,873,920.00
30 Sealant Tube 28.64 16,500.00 472,527.00
31 Bingkai Alumunium M' 195.80 62,000.00 12,139,600.00
32 Profi Kaca Bh 400.50 12,300.00 4,926,150.00
33 Kaca Cermin 10mm M2 48.95 125,000.00 6,118,750.00
34 Handle Pintu Kaca Bh 8.00 450,000.00 3,600,000.00
35 Kunci Pintu Alumunium dan Kaca bh 3.00 320,000.00 960,000.00
36 Saklar Tunggal bh 5.00 20,000.00 100,000.00
37 Saklar Ganda bh 10.00 25,000.00 250,000.00
38 Stop Kontak Ganda bh 8.00 25,000.00 200,000.00
39 Lampu SL 24 W bh 20.00 40,800.00 816,000.00
40 Cat Minyak kg 2.70 51,200.00 138,166.27
41 Cat dasar kg 2.29 65,000.00 149,095.44
42 Cat penutup Kg 3.51 65,000.00 228,028.32
43 Plamur kg 24.44 19,000.00 464,396.48
44 Kuas Bh 1.00 13,700.00 13,700.00
45 Pengencer kg 0.40 23,100.00 9,350.51
46 Ampelas Lbr 2.70 2,000.00 5,397.12
47 Cat Dasar Kg 22.42 18,000.00 403,524.00
48 Cat Penutup Kg 58.29 18,000.00 1,049,162.40
49 Jaringan Listrik ls 1.00 3,500,000.00 3,500,000.00
50 Instalasi Penerangan( termasuk Pipa) Titik 25.00 95,000.00 2,375,000.00
51 Papan Proyek Ls 1.00 200,000.00 200,000.00
52 Lisplank m1 74.96 25,000.00 1,874,000.00
53 Kabel NYA m1 150.00 4,600.00 690,000.00
JUMLAH BAHAN......................................................................................... 175,174,440.48

UPAH SATUAN VOLUME HARGA SATUAN JUMLAH


1 Pekerja oh 392.65 100,000.00 39,265,126.26
2 Tukang oh 241.96 120,000.00 29,035,192.22
3 Kepala Tukang oh 24.13 130,000.00 3,136,844.72
4 Mandor oh 19.56 130,000.00 2,542,526.23
73,979,689.44