RENCANA ANGGARAN BIAYA
NAGORI : PARIKSABUNGAN
KECAMATAN : DOLOK PARDAMEAN
KABUPATEN : SIMALUNGUN
PROVINSI : SUMATERA UTARA
NO RAB : 1
JENIS PEKERJAAN : PEMBANGUNAN TAMAN HUTAN SIMARJARUNJUNG
PEKERJAAN : PEMBANGUNAN KIOS
VULUME : 18 X 5 METER
DANA / TAHUN : APBN / 2021
JUMLAH
HARGA HARGA SATUAN HARGA SATUAN JUMAH HARGA TOTAL JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN SATUAN UPAH BAHAN UPAH SATUAN BAHAN HARGA
( Rp ) ( Rp ) ( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7 8 9 10
I. PEKERJAAN PENDAHULUAN
1. Bowplank / Pengukuran A. 2.2.1.14 46.00 M' 23,950.00 47,859.00 1,101,700.00 2,201,514.00 3,303,214.00
2. Papan Proyek - 1.00 Ls 200,000.00 200,000.00 200,000.00
JUMLAH I ……………………. 1,101,700.00 2,401,514.00 3,503,214.00
II. PEKERJAAN TANAH
1. Pekerjaan Galian Pondasi A. 2.3.1.1 17.35 M³ 78,250.00 1,357,637.50 - 1,357,637.50
2. Pek. Urugan Pasir di Bawah Lantai A. 2.3.1.11 6.60 M³ 31,300.00 159,120.00 206,580.00 1,050,192.00 1,256,772.00
3. Urugan Kembali Galian Pondasi A. 2.3.1.9 4.18 M³ 56,500.00 235,935.71 - 235,935.71
JUMLAH II ……………………. 1,800,153.21 1,050,192.00 2,850,345.21
III. PEKERJAAN STRUKTUR KIOS
A Pekerjaan Pondasi
1. Pasang Pondasi Batu Kosong A. 3.2.1.9 2.75 M³ 134,940.00 453,859.20 371,085.00 1,248,112.80 1,619,197.80
2. Pasangan Pondasi Batu Belah/Batu Kali 1 ; 4 A. 3.2.1.2 9.63 M³ 259,500.00 677,309.00 2,497,687.50 6,519,099.13 9,016,786.63
B Pekerjaan Beton Bertulang
1. Sloof Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 25 Cm
1.1. Cor Sloof A. 4.1.1.7 2.75 M³ 212,430.00 947,666.00 584,182.50 2,606,081.50 3,190,264.00
1.2. Pembesian A. 4.1.1.17 296.00 kg 1,683.00 13,363.50 498,168.00 3,955,596.00 4,453,764.00
1.3. Bekisting A. 4.1.1.21 27.50 M2 89,960.00 45,795.00 2,473,900.00 1,259,362.50 3,733,262.50
2. Kolom Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 20 Cm
2.1. Cor Kolom Beton A. 4.1.1.7 2.16 M³ 212,430.00 947,666.00 458,423.94 2,045,063.23 2,503,487.17
2.2. Pembesian A. 4.1.1.17 380.00 kg 1,683.00 13,363.50 639,540.00 5,078,130.00 5,717,670.00
2.3. Bekisting A. 4.1.1.22 21.58 M2 114,180.00 88,631.67 2,464,004.40 1,912,671.37 4,376,675.77
3. Ring Balok Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 25
3.1. Cor Ring Balok Beton A. 4.1.1.7 3.25 M³ 212,430.00 947,666.00 690,397.50 3,079,914.50 3,770,312.00
3.2. Pembesian A. 4.1.1.17 389.00 kg 1,683.00 13,363.50 654,687.00 5,198,401.50 5,853,088.50
3.3. Bekisting A. 4.1.1.23 32.50 M2 114,180.00 91,128.67 3,710,850.00 2,961,681.67 6,672,531.67
JUMLAH III ……………………. 15,042,925.84 35,864,114.19 50,907,040.03
IV. PEKERJAAN ARSITEKTUR
A. Pekerjaan Dinding
1. Pasangan Dinding Batu Bata 1/2 Bata 1 : 4 A. 4.4.1.9 112.09 M2 45,250.00 66,310.70 5,072,072.50 7,432,766.36 12,504,838.86
2. Plesteran Dinding Batu Bata 1 : 4 A. 4.4.2.4 224.18 M2 51,900.00 11,244.00 11,634,942.00 2,520,679.92 14,155,621.92
B. Pekerjaan Pintu Kaca dan Jendela Kaca Bingkai Alumunium
1. Pekerjaan Kusen Pintu dan Jendela Alumunium A. 4.2.1.11 76.80 M' 10,292.00 113,390.00 790,425.60 8,708,352.00 9,498,777.60
2. Pekerjaan Bingkai Aluminium A. 4.2.1.13 44.50 M2 20,520.00 332,605.00 913,140.00 14,800,922.50 15,714,062.50
3. Pekerjaan Kaca 10mm A. 4.6.2.17.a 44.50 M2 22,100.00 197,305.00 983,450.00 8,780,072.50 9,763,522.50
4 Handle Pintu Kaca Terpasang 8.00 bh 450,000.00 3,600,000.00 3,600,000.00
5 Kunci Pintu Alumunium dan Kaca Terpasang 3.00 bh 320,000.00 960,000.00 960,000.00
D. Pekerjaan Plafound
1. Pekerjaan Rangka A. 4.6.1.20 140.00 M2 30,600.00 91,850.00 4,284,000.00 12,859,000.00 17,143,000.00
2. Pekerjaan Plafound Triplek 6mm A. 4.5.1.5 140.00 M2 30,600.00 33,924.00 4,284,000.00 4,749,360.00 9,033,360.00
E Pekerjaan Atap, Talang dan Listplank
1. Pekerjaan Rangka Atap A. 2.3.1.1 166.65 M2 28,350.00 84,485.60 4,724,499.15 14,079,440.75 18,803,939.90
2. Pekerjaan Atap A. 2.3.1.14 166.65 M2 23,700.00 46,400.00 3,949,581.30 7,732,513.60 11,682,094.90
3. Pekerjaan Rabung A. 4.5.2.37 29.43 M 46,640.00 34,040.00 1,372,615.20 1,001,797.20 2,374,412.40
4. Pekerjaan Lisplank H. Terpasang 74.96 M - 25,000.00 - 1,874,000.00 1,874,000.00
F Pekerjaan Lantai dan Pelapis
1. Lantai Kerja Beton Cor 1 : 3 : 5 Dibawah Lantai A. A. 4.1.1.5 3.47 M³ 212,430.00 885,864.00 737,981.82 3,077,491.54 3,815,473.36
2. Keramik Lantai Uk. 40 x 40 cm A. 4.4.3.7 340.00 M2 43,380.00 95,288.25 14,749,200.00 32,398,005.00 47,147,205.00
3. Keramik dinding Uk 20 x 40 cm A. 4.4.3.54.1 - M2 116,775.00 122,471.25 - - -
G Pekerjaan Pengecatan
1 Cat Dinding A. 4.7.1.10 224.18 M 2
10,769.00 8,380.00 2,414,194.42 1,878,628.40 4,292,822.82
2 Cat List Plank A. 4.7.1.4 13.49 M2 9,250.00 42,270.00 124,808.40 570,340.66 695,149.06
JUMLAH IV ……………………. 56,034,910.39 127,023,370.43 183,058,280.82
V. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
A. Pekerjaan Instalasi Listrik
Pengadaan Jaringan listrik 1.00 ls 3,500,000.00 - 3,500,000.00 3,500,000.00
1. Instalasi Penerangan dan Stop Kontak( termasuk Pipa) - 25.00 Titik - 95,000.00 - 2,375,000.00 2,375,000.00
2. Kabel NYA - 150.00 M' 4,600.00 - 690,000.00 690,000.00
3. Armature Stop Kontak dan Saklar - - -
3.1. Saklar Tunggal - 5.00 Bh 20,000.00 - 100,000.00 100,000.00
3.2. Saklar Ganda 10.00 Bh 25,000.00 - 250,000.00 250,000.00
3.3. Stop Kontak Ganda - 8.00 Bh 25,000.00 - 200,000.00 200,000.00
4. Armature Lampu Penerangan - - -
4.1 Lampu SL 24 W - 20.00 Set 40,800.00 - 816,000.00 816,000.00
JUMLAH V ……………………. - 7,931,000.00 7,931,000.00
VI. PEKERJAAN SANITASI
2. Pipa PVC dia 3" 5.00 btg 250,000.00 - 1,250,000.00 1,250,000.00
3. Tiang dan Tangki Air Stainles 1000 l - bh 9,000,000.00 - - -
4. Keran Air 1.00 bh 20,000.00 - 20,000.00 20,000.00
5. Pipa PVC dia 1/2" 4.00 btg 45,000.00 - 180,000.00 180,000.00
6. Pipa PVC dia 1" 2.00 btg 70,000.00 - 140,000.00 140,000.00
7. Selang Pipa dia 1" - rol 350,000.00 - - -
-
JUMLAH VI ……………………. - 1,590,000.00 1,590,000.00
VII. BIAYA OPERASIONAL ( BOP )
1. Perencanaan - 1.00 Ls 1,000,000.00 1,000,000.00 - 1,000,000.00
2. Pengawas 3.00 Bulan 800,000.00 2,400,000.00 - 2,400,000.00
3. Administrasi dan dokumentasi Prasasti 1.00 Ls 1,300,000.00 1,300,000.00 - 1,300,000.00
4. Honor TPK (3 Bulan)
Ketua 1.00 org 1,000,000.00 1,000,000.00 - 1,000,000.00
Sekretaris 1.00 org 800,000.00 800,000.00 - 800,000.00
Anggota 2.00 org 800,000.00 1,600,000.00 - 1,600,000.00
5. Pembuatan dokumen akhir 1.00 Ls 600,000.00 600,000.00 - 600,000.00
- -
JUMLAH VII ……………………. 8,700,000.00 - 8,700,000.00
TOTAL I + II + III + IV + V + VI + VII ………….…………. 82,679,689.44 175,860,190.62 258,539,880.05
PERIKSON PURBA, S.pd SARIMUDA A.D PURBA ,S,Sos,M.Si ERICK JOHNSON RUMAHORBO
PEMBINA TK.I TENAGA TEKNIK
NIP : 1974020519944021002
REKAPITULASI
RENCANA ANGGARAN BIAYA
NAGORI : PARIKSABUNGAN
KECAMATAN : DOLOK PARDAMEAN
KABUPATEN : SIMALUNGUN
PROVINSI : SUMATERA UTARA
NO RAB : 1
JENIS PEKERJAAN : PEMBANGUNAN TAMAN HUTAN SIMARJARUNJUNG
PEKERJAAN : PEMBANGUNAN KIOS
VULUME : 18 X 5 METER
DANA / TAHUN : APBN / 2021
I. PEKERJAAN PENDAHULUAN
Papan Proyek
1 1.00 LS
2. Septik Tank
A. Lebar 1.5 m
B. Panjang 2m
C. Dalam Galian 1.2 m
V= (A*B*C) 3.6 m3
17.35 m3
1 unit 17.35 m3
2. Pek. Urugan Pasir di Bawah Lantai A. 2.3.1.11 R1 A. Panjang 55
B. Lebar 0.5
C. Tebal 0.1
V= (A*B*C) 2.75 m3
R2 A. Panjang 0
B. Lebar 0
C. Tebal 0
V= (A*B*C) 0 m3
Selasar Depan
A. Panjang 55
B. Lebar 1
C. Tebal 0.07
V= (A*B*C) 3.85 m3
6.60 m3
1 unit 6.60 m3
3. Urugan Kembali Galian Pondasi A. 2.3.1.9 4.18 m3
1 unit 4.18 m3
III. PEKERJAAN STRUKTUR KIOS
A Pekerjaan Pondasi
1. Pasang Pondasi Batu Kosong A. 3.2.1.9 1. Pondasi
A. Lebar Pondasi 0.5 m
B. Panjang Pondasi 55 m
C. Dalam Galian 0.1 m
V= (A*B*C) 2.75 m3
2.75 m3
1 unit 2.75 m3
2. Pasangan Pondasi Batu Belah/Batu Kali 1 ; 4 A. 3.2.1.2 A.Alas 0.5
B.Bubung 0.2
C. Tinggi 0.5
D. Panjang 55
V=(((A+B)/2)*C)*D 9.625 m3
9.63 m3
NO. URAIAN PEKERJAAN ANALISA DATA HITUNG VOLUME VOLUME TOTAL
1 unit 9.63 m3
B Pekerjaan Beton Bertulang
1. Sloof Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 25 Cm
1.1. Cor Sloof A. 4.1.1.7 A.Panjang 55 m
B. Lebar 0.2 m
C. Tinggi 0.25 m
V=A*B*C 2.75 m3
2.75 m3
1 unit 2.75 m3
1.3. Bekisting A. 4.1.1.21 A.Panjang 55 m
B. Lebar 0.2 m
C. Tinggi 0.25 m
V=(A*C)*2 27.5 m2
27.50 m2
1 unit 27.50 m2
2. Kolom Beton Bertulang Campuran 1 : 2 : 3 Uk. 20 x 20 Cm
2.1. Cor Kolom Beton A. 4.1.1.7 A.Panjang 0.2 m
B. Lebar 0.2 m
C. Tinggi 4.15 m
D. Jlh 13 Bh
V=A*B*C*D 2.158 m3
2.16 m3
1 unit 2.16 m2
2.3. Bekisting A. 4.1.1.22 A.Panjang 0.2 m
B. Lebar 0.2 m
C. Tinggi 4.15 m
D. Jlh 13 Bh
V=((A*C)*2)*D 21.58 m2
21.58 m2
1 unit 21.58 m2
A.Panjang 65 m
B. Lebar 0.2 m
C. Tinggi 0.25 m
V=(A*C)*2 32.5 m2
32.50 m2
1 unit 32.50 m2
IV. PEKERJAAN ARSITEKTUR
7.2. Pasangan Dinding Batu Bata Tebal 1/2 batu camp. 1pc:4ps A. 4.4.1.9 Kios
Panjang 34 m
Tinggi 4.15 m
141.1 m2
Teras
Panjang 17 m
Tinggi 0.6 m
Jlh 1 bh
NO. URAIAN PEKERJAAN ANALISA DATA HITUNG VOLUME VOLUME TOTAL
10.2 m2
151.30 m2
Pintu Buka 1
Lebar 0.9 m
Tinggi 2.5 m
Jlh 2 bh
4.5 m2
Pentilasi
Lebar 0.6 m
Tinggi 0.4 m
Jlh 4 bh
0.96 m2
Jendela Kaca
Lebar 2m
Tinggi 2.5 m
Jlh 3 bh
15 m2
Jendela Kaca
Lebar 3m
Tinggi 2.5 m
Jlh 2 bh
15 m2
39.21 m2
112.09 m2
1 unit 112.09 m2
7.4. Plesteran Camp. 1 : 4 tebal 15 mm A. 4.4.2.4 Vol. Pas batu 1:4 *2 224.18 m2 224.18 m2
1 unit 224.18 m2
J2
Panjang 28.5 M'
76.80 m'
1 unit 76.80 M'
NO. URAIAN PEKERJAAN ANALISA DATA HITUNG VOLUME VOLUME TOTAL
8.1.2. Memasang 1 M2 Bingkai Pintu / Jendela Kaca Rangka Alumunium A. 4.2.1.13 P2 Tinggi 2.5
Lebar 1.5
Jlh 1 3.75 M2
P1 Tinggi 2.5
Lebar 0.9
Jlh 2 4.5 M2
J1 Tinggi 2.5
Lebar 2.5
Jlh 3 18.75 M2
J2 Tinggi 2.5
Lebar 3.5
Jlh 2 17.5 M2
44.5 m2 44.50 m2
1 unit 44.50 m2
Selasar Depan
A. Panjang 19.48
B. Lebar 1
V= (A*B) 19.48 m2
Selasar Samping
A. Panjang 10
B. Lebar 1
V= (A*B) 10 m2
69.48 m2
Tinggi 0.05 m
3.47 m3
NO. URAIAN PEKERJAAN ANALISA DATA HITUNG VOLUME VOLUME TOTAL
KABUPATEN : SIMALUNGUN
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 71,809.00
JUMLAH BAHAN Rp -
C PERALATAN
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 78,250.00
JUMLAH BAHAN Rp -
C PERALATAN
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 56,500.00
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 190,420.00
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 588,799.20
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 936,809.00
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 112,835.60
Memasang 1 m2 rangka langit-langit (60 x 120) cm, kayu kelas II Kode Analisa A. 4.6.1.20
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.1000 Oh Pekerja Rp 100,000.00 Rp 10,000.00
2 0.1500 Oh Tukang Kayu Rp 120,000.00 Rp 18,000.00
3 0.0150 Oh Kepala Tukang Rp 130,000.00 Rp 1,950.00
4 0.0050 Oh Mandor Rp 130,000.00 Rp 650.00
JUMLAH TENAGA KERJA Rp 30,600.00
B BAHAN
1 0.0150 M3 Kaso-kaso (5 x 5) cm Rp 5,950,000.00 Rp 89,250.00
2 0.1250 kg Paku Rp 20,800.00 Rp 2,600.00
JUMLAH BAHAN Rp 91,850.00
C PERALATAN
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 122,450.00
Memasang 1 m2 langit-langit (120 x 240) cm, Tebal 6mm Kode Analisa A. 4.5.1.5
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.1000 Oh Pekerja Rp 100,000.00 Rp 10,000.00
2 0.1500 Oh Tukang Kayu Rp 120,000.00 Rp 18,000.00
3 0.0150 Oh Kepala Tukang Rp 130,000.00 Rp 1,950.00
4 0.0050 Oh Mandor Rp 130,000.00 Rp 650.00
JUMLAH TENAGA KERJA Rp 30,600.00
B BAHAN
1 0.3750 Lbr Triplek 6mm Rp 88,800.00 Rp 33,300.00
2 0.0300 kg Paku Rp 20,800.00 Rp 624.00
JUMLAH BAHAN Rp 33,924.00
C PERALATAN
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 64,524.00
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 70,100.00
1 M2 Pasangan Dinding Batu Bata Tebal 1/2 batu, Camp. 1 : 4 Kode Analisa A. 4.4.1.9
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.3000 Oh Pekerja Rp 100,000.00 Rp 30,000.00
2 0.1000 Oh Tukang Batu Rp 120,000.00 Rp 12,000.00
3 0.0100 Oh Kepala Tukang Rp 130,000.00 Rp 1,300.00
4 0.0150 Oh Mandor Rp 130,000.00 Rp 1,950.00
JUMLAH TENAGA KERJA Rp 45,250.00
B BAHAN
1 70.0000 Bh Batu Bata Rp 653.40 Rp 45,738.00
2 0.0430 m3 Pasir Pasang Rp 121,400.00 Rp 5,220.20
3 11.5000 kg Portland Cement Rp 1,335.00 Rp 15,352.50
JUMLAH BAHAN Rp 66,310.70
C PERALATAN
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 111,560.70
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 63,144.00
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 1,098,294.00
1 M3 Beton Campuran 1 : 1,88 : 2,82 fc 19,3 Mpa setara K225 Kode Analisa A. 4.1.1.7
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 1.6500 Oh Pekerja Rp 100,000.00 Rp 165,000.00
2 0.2750 Oh Tukang Batu Rp 120,000.00 Rp 33,000.00
3 0.0280 Oh Kepala Tukang Rp 130,000.00 Rp 3,640.00
4 0.0830 Oh Mandor Rp 130,000.00 Rp 10,790.00
JUMLAH TENAGA KERJA Rp 212,430.00
B BAHAN
1 371.0000 kg Semen @ 40 Kg Rp 1,335.00 Rp 495,285.00
2 0.4990 m3 Pasir Pasang Rp 121,400.00 Rp 60,578.60
3 0.7760 m3 Kerikil/ Batu Pecah Rp 504,900.00 Rp 391,802.40
4 215.0000 Ltr Air Rp - Rp -
JUMLAH BAHAN Rp 947,666.00
C PERALATAN
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 1,160,096.00
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 15,046.50
HARGA SATUAN PEMBESIAN 1 KG Rp 15,046.50
1 m2 bekisting untuk Sloof (Asumsi 3 kali Pemakaian Bahan) Kode Analisa A. 4.1.1.21
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.5200 Oh Pekerja Rp 100,000.00 Rp 52,000.00
2 0.2600 Oh Tukang Kayu Rp 120,000.00 Rp 31,200.00
3 0.0260 Oh Kepala Tukang Rp 130,000.00 Rp 3,380.00
4 0.0260 Oh Mandor Rp 130,000.00 Rp 3,380.00
JUMLAH TENAGA KERJA Rp 89,960.00
B BAHAN
1 0.0150 m3 Kayu Sembarang Rp 2,497,000.00 Rp 37,455.00
2 0.3000 kg Paku Biasa Rp 20,800.00 Rp 6,240.00
3 0.1000 Ltr Minyak Bekisting Rp 21,000.00 Rp 2,100.00
JUMLAH BAHAN Rp 45,795.00
C PERALATAN
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 135,755.00
JUMLAH PERALATAN Rp -
N PEKERJAAN (A + B + C) Rp 123,682.00
Memasang 1 M2 Bingkai Pintu / Jendela Kaca Rangka Alumunium Kode Analisa A. 4.2.1.13
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.0850 Oh Pekerja Rp 100,000.00 Rp 8,500.00
2 0.0850 Oh Tukang Batu Rp 120,000.00 Rp 10,200.00
3 0.0090 Oh Kepala Tukang Rp 130,000.00 Rp 1,170.00
4 0.0050 Oh Mandor Rp 130,000.00 Rp 650.00
JUMLAH TENAGA KERJA Rp 20,520.00
B BAHAN
1 4.4000 m' Bingkai Alumunium Rp 62,000.00 Rp 272,800.00
2 4.5000 bh Profi Kaca Rp 12,300.00 Rp 55,350.00
3 0.2700 tube Sealant Rp 16,500.00 Rp 4,455.00
JUMLAH BAHAN Rp 332,605.00
C PERALATAN
JUMLAH PERALATAN Rp -
N PEKERJAAN (A + B + C) Rp 353,125.00
JUMLAH PERALATAN Rp -
N PEKERJAAN (A + B + C) Rp 219,405.00
1 m2 bekisting untuk Kolom (Asumsi 3 kali Pemakaian Bahan) Kode Analisa A. 4.1.1.22
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.6600 Oh Pekerja Rp 100,000.00 Rp 66,000.00
2 0.3300 Oh Tukang Kayu Rp 120,000.00 Rp 39,600.00
3 0.0330 Oh Kepala Tukang Rp 130,000.00 Rp 4,290.00
4 0.0330 Oh Mandor Rp 130,000.00 Rp 4,290.00
JUMLAH TENAGA KERJA Rp 114,180.00
B BAHAN
1 0.0133 m3 Kayu Sembarang Rp 2,497,000.00 Rp 33,293.33
2 0.4000 kg Paku Biasa Rp 20,800.00 Rp 8,320.00
3 0.2000 Ltr Minyak Bekisting Rp 21,000.00 Rp 4,200.00
4 0.0050 m3 Balok Kayu Sembarang Rp 2,497,000.00 Rp 12,485.00
5 0.1167 Lbr Plywood tebal 9 mm Rp 144,000.00 Rp 16,800.00
6 0.6667 Btg Dolken Kayu dia 8 - 10 cm- pjg 4 m Rp 20,300.00 Rp 13,533.33
JUMLAH BAHAN Rp 88,631.67
C PERALATAN
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 202,811.67
1 m2 bekisting untuk balok (Asumsi 3 kali Pemakaian Bahan) Kode Analisa A. 4.1.1.23
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.6600 Oh Pekerja Rp 100,000.00 Rp 66,000.00
2 0.3300 Oh Tukang Kayu Rp 120,000.00 Rp 39,600.00
3 0.0330 Oh Kepala Tukang Rp 130,000.00 Rp 4,290.00
4 0.0330 Oh Mandor Rp 130,000.00 Rp 4,290.00
JUMLAH TENAGA KERJA Rp 114,180.00
B BAHAN
1 0.0133 m3 Kayu Sembarang Rp 2,497,000.00 Rp 33,293.33
2 0.4000 kg Paku Biasa Rp 20,800.00 Rp 8,320.00
3 0.2000 Ltr Minyak Bekisting Rp 21,000.00 Rp 4,200.00
4 0.0060 m3 Balok Kayu Sembarang Rp 2,497,000.00 Rp 14,982.00
5 0.1167 Lbr Plywood tebal 9 mm Rp 144,000.00 Rp 16,800.00
6 0.6667 Btg Dolken Kayu dia 8 - 10 cm- pjg 4 m Rp 20,300.00 Rp 13,533.33
JUMLAH BAHAN Rp 91,128.67
C PERALATAN
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 205,308.67
1 m2 Lantai Keramik 40 x 40 cm Kode Analisa A. 4.4.3.7
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.2500 Oh Pekerja Rp 100,000.00 Rp 25,000.00
2 0.1250 Oh Tukang Batu Rp 120,000.00 Rp 15,000.00
3 0.0130 Oh Kepala Tukang Rp 130,000.00 Rp 1,690.00
4 0.0130 Oh Mandor Rp 130,000.00 Rp 1,690.00
JUMLAH TENAGA KERJA Rp 43,380.00
B BAHAN
1 6.6300 Bh Keramik 40 x 40 cm Rp 10,900.00 Rp 72,267.00
2 9.8000 kg Semen PC Rp 1,335.00 Rp 13,083.00
3 0.0450 M3 Pasir Pasang Rp 121,400.00 Rp 5,463.00
4 1.3000 kg Semen Warna Rp 3,442.50 Rp 4,475.25
JUMLAH BAHAN Rp 95,288.25
C PERALATAN
JUMLAH PERALATAN Rp -
1 m2 Dinding Keramik 20 x 40 cm Kode Analisa A. 4.4.3.54.1
No. Volume Satuan Uraian Harga Satuan Biaya Harga Satuan
( Rp. ) ( Rp. ) ( Rp. )
A TENAGA KERJA
1 0.6750 Oh Pekerja Rp 100,000.00 Rp 67,500.00
2 0.3375 Oh Tukang Batu Rp 120,000.00 Rp 40,500.00
3 0.0338 Oh Kepala Tukang Rp 130,000.00 Rp 4,387.50
4 0.0338 Oh Mandor Rp 130,000.00 Rp 4,387.50
JUMLAH TENAGA KERJA Rp 116,775.00
B BAHAN
1 6.6300 Bh Keramik 20 x 40 cm Rp 15,000.00 Rp 99,450.00
2 9.8000 kg Semen PC Rp 1,335.00 Rp 13,083.00
3 0.0450 M3 Pasir Pasang Rp 121,400.00 Rp 5,463.00
4 1.3000 kg Semen Warna Rp 3,442.50 Rp 4,475.25
JUMLAH BAHAN Rp 122,471.25
C PERALATAN
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 239,246.25
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 80,680.00
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 253,150.00
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 46,954.00
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 51,520.00
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 19,149.00
JUMLAH PERALATAN Rp -
HARGA SATUAN PEKERJAAN (A + B + C) Rp 2,699,500.00
DAFTAR HARGA UPAH
UPAH
1 Pekerja 100,000.00 100,000.00 Hr/Org
2 Mandor 130,000.00 130,000.00 Hr/Org
3 Tukang 120,000.00 120,000.00 Hr/Org
4 Kepala Tukang 130,000.00 130,000.00 Hr/Org
DAFTAR HARGA DASAR BAHAN
PEKERJAAN : PEMBANGUNAN KIOS
KABUPATEN : SIMALUNGUN
A. TIMBUNAN / GALIAN
1 Tanah Timbun/Merah 97,920.00 97,920.00 M³
2 Pasir Timbun / Urug 132,600.00 132,600.00 M³
3 Pasir Pasang 121,400.00 121,400.00 M³
4 Sirtu 357,000.00 357,000.00 M³
B. BAHAN PEREKAT
1 Portland Cement 40 kg 1,335.00 1,335.00 Kg
2 Cement Putih 2,754.00 2,754.00 Kg
3 Cement Warna 3,442.50 3,442.50 Kg
4 Kapur 108,000.00 108,000.00 Kg
D. KAYU / LANGIT-LANGIT
1 Kayu Keras Setempat/Kayu Sampinur (Balok Kls II) 5,950,000.00 5,950,000.00 M³
2 Kayu Keras Setempat/Kayu Sampinur (Papan Kls II) 6,270,000.00 6,270,000.00 M³
3 Kayu Kls III 4,500,000.00 4,500,000.00 M³
4 Kayu Sembarang/Bekisting 2,497,000.00 2,497,000.00 M³
5 Kayu Dolken / bulat Ø 7,5 - 10 / 400 cm 20,300.00 20,300.00 Btg
6 Tripleks 120 x 240 tbl. 4 mm 78,900.00 78,900.00 Lbr
7 Tripleks 120 x 240 tbl. 6 mm 88,800.00 88,800.00 Lbr
8 Tripleks 120 x 240 tbl. 9 mm 144,000.00 144,000.00 Lbr
9 Tripleks 120 x 240 tbl. 12 mm 148,500.00 148,500.00 Lbr
10 Multiflex 12 mm 150,000.00 148,500.00 Lbr
11 Multiflex 18 mm 300,000.00 300,000.00 Lbr
12 Profil Gypsum 3" 35,000.00 35,000.00 M'
13 Gypsum Board 120 x 240 tbl. 9 mm 98,000.00 98,000.00 Lbr
E. BESI / ALLUMINIUM
1 Besi Beton Polos 12,500.00 12,500.00 Kg
2 Kawat Besi Beton 15,900.00 15,900.00 Kg
3 Paku Biasa 20,800.00 20,800.00 Kg
4 Paku Sekrup 90,000.00 90,000.00 Kg
5 Rangka Baja Ringan 86,700.00 86,700.00 M2
6 Rangka Furing Flafon 80,000.00 80,000.00 M2
7 Profil Alumunium 80,000.00 80,000.00 M'
Skrup Fiser 12,200.00 12,200.00 Bh
Sealant 16,500.00 16,500.00 Tube
Bingkai Alumunium 62,000.00 62,000.00 M'
Profi Kaca 12,300.00 12,300.00 Bh
Kaca Cermin 10mm 125,000.00 125,000.00 M2
Handle Pintu Kaca 450,000.00 450,000.00 Bh
Kunci Pintu Alumunium dan Kaca 320,000.00 320,000.00 bh
F. PENUTUP ATAP
1 Atap Spandeck 0,3 mm 46,900.00 46,900.00 M
2 Rabung Spandek 30,000.00 30,000.00 Bh
3 Paku Seng + Ring karet 500.00 500.00 Bh
4 Furing Channel 20,300.00 20,300.00 M
5 Bout Ramset / Dina Bolt 500.00 500.00 Bh
6 Seng Gelombang BJLS- 30 51,000.00 51,000.00 Lbr
7. Listplank GRC 25,000.00 25,000.00 M
I. CAT / MINYAK
1 Cat Tembok 18,000.00 18,000.00 Kg
2 Cat Minyak untuk Kayu 65,000.00 65,000.00 Kg
3 Cat Menie Kayu 51,200.00 51,200.00 Kg
4 Cat Menie Besi 39,000.00 39,000.00 Kg
5 Plamuur 19,000.00 19,000.00 Kg
6 Dempul Kayu 11,000.00 11,000.00 Kg
7 Tinner 23,100.00 23,100.00 Ltr
8 Lem Kayu 12,100.00 12,100.00 Kg
9 Kuas 13,700.00 13,700.00 Bh
10 Ampelas 2,000.00 2,000.00 Lbr
11 Waterfroof 60,000.00 60,000.00 Kg
12 Coating AM-52 30,000.00 30,000.00 Ltr
13 Minyak Bekisting 21,000.00 21,000.00 Ltr
14 Minyak Pelumas 35,000.00 35,000.00 Ltr
15 Minyak solar 5,100.00 5,100.00 Ltr
16 Minyak Pertalite 7,800.00 7,800.00 Ltr
J. LISTRIK / ACSESORIES
1 Lampu TL 40 W Lengkap kotak 86,400.00 86,400.00 Set
2 Lampu XL 18 Watt 27,500.00 27,500.00 Set
3 Lampu XL 24 Watt 40,800.00 40,800.00 Set
4 Stop Kontak Ganda 17,000.00 17,000.00 Bh
5 Saklar Ganda 18,700.00 18,700.00 Bh
6 Saklar Triple 22,000.00 22,000.00 Bh
7 Saklar Tunggal 16,500.00 16,500.00 Bh
8 Panel Kontrol 1,500,000.00 1,500,000.00 Unit
9 Instalasi listrik titik api / Lampu Nyala 120,000.00 120,000.00 Ttk
10 Kabel NYA 4,600.00 4,600.00 M
PEMBANGUNAN KIOS
TAHUN ANGGARAN
2021
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan BULLDOZER 100-150 HP E04
2. Tenaga Pw 155.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 915,000,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3 E06
2. Tenaga Pw 20.0 HP
3. Kapasitas Cp 500.0 Liter
4. Alat Baru : a. Umur Ekonomis A 2.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 80,000,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3.5 TON E08
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 3.5 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 240,000,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 18,571.43 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 12,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 10 TON E09
2. Tenaga Pw 190.0 HP
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 320,000,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 18,571.43 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 12,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 80-140 HP E10
2. Tenaga Pw 133.0 HP
3. Kapasitas Cp 0.93 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 2,000,000,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan MOTOR GRADER >100 HP E13
2. Tenaga Pw 135.0 HP
3. Kapasitas Cp 10,800.0 -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 800,000,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE VIBRATOR E20
2. Tenaga Pw 5.5 HP
3. Kapasitas Cp 25.0 -
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 10,000,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan WATER PUMP 70-100 mm E22
2. Tenaga Pw 6.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 3.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 9,000,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 25,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,428.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,800.00 Liter
5. Bahan Bakar Solar Ms 5,100.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
JADWAL PELAKSANAAN KEGIATAN
Partukkonaginjang, 2021
Dibuat Oleh,
DATA PEMBESIAN
Pembesian
Tulangan Pokok
Diamater (Ø) = 12.00 mm
Berat (Bj) = 0.888 Kg / m'
Panjang (P) = 55.05 m'
Jumlah (J) = 4.00 btg
Volume (V) = Bj x P x J
= 0.888 x 55.05 x 4.00
(V1) = 195.54 Kg
Sengkang
Diamater (Ø) = 8.00 mm
Berat (Bj) = 0.395 Kg / m'
Panjang (P) = 0.93 m'
Jumlah (J) = 276.00 bh
Volume (V) = Bj x P x J
= 0.395 x 0.93 x 276.00
(V2) = 100.84 Kg
Pembesian Kolom
Tulangan Pokok
Diamater (Ø) = 12.00 mm
Berat (Bj) = 0.888 Kg / m'
Panjang (P) = 4.20 m'
Jumlah btg (Jb) = 4.00 btg
Jumlah (J) = 13.00 bh
Volume (V) = Bj x P x J
= 0.888 x 4.20 x 4.00 x 13.00
(V1) = 193.94 Kg
Sengkang
Diamater (Ø) = 8.00 mm
Berat (Bj) = 0.395 Kg / m'
Panjang (P) = 1.25 m'
Jumlah btg (Jb) = 29.00 btg
Jumlah (J) = 13.00 bh
Volume (V) = Bj x P x J
= 0.395 x 1.25 x 29.00 x 13.00
(V2) = 186.14 Kg
Total Volume (V) = V1 + V2
(V) = 193.94 + 186.14
(V) = 380.00 Kg
(V) = 380.00 Kg
Pembesian Kolom
Tulangan Pokok
Diamater (Ø) = 0.00 mm
Berat (Bj) = 0 Kg / m'
Panjang (P) = 0.05 m'
Jumlah btg (Jb) = 4.00 btg
Jumlah (J) = 4.00 bh
Volume (V) = Bj x P x J
= 0 x 0.05 x 4.00 x 4.00
(V1) = 0.00 Kg
Sengkang
Diamater (Ø) = 0.00 mm
Berat (Bj) = 0 Kg / m'
Panjang (P) = 0.65 m'
Jumlah btg (Jb) = 1.00 btg
Jumlah (J) = 4.00 bh
Volume (V) = Bj x P x J
= 0 x 0.65 x 1.00 x 4.00
(V2) = 0.00 Kg
(V) = V1 + V2
(V) = 0.00 + 0.00
(V) = 0.00 Kg
(V) = 0.00 Kg
RING BALOK
3. Balok Struktur Bertulang 0.20 0.25
(V) = V1 + V2
(V) = 231.06 + 158.57
(V) = 389.00 Kg
Jenis : S i r t u
Lokasi : Quarry
Tujuan : Lokasi Pekerjaan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi Base Camp L 5.00 Km
4 Harga satuan Sirtu di Quarry RpM16 1.00 M3 357,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 0.00
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 0.00
7 Berat volume sirtu Bil 1.51 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.6826 M3 / Jam
Ts1
Bersambung
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : S i r t u
Lokasi : Quarry
Tujuan : Lokasi Pekerjaan
Lanjutan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi pekerjaan L 5.00 Km
4 Harga satuan pasir urug di Quarry RpM44 1.00 M3 132,600.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 0.00
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 0.00
7 Berat volume pasir urug Bil 1.42 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.6826 M3 / Jam
Ts1
Bersambung
ANALISA HARGA DASAR SATUAN BAHAN
Lanjutan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
A PERALATAN
1 Dump Truck 3,5 M3 Unit 1 - -
2 CONCRETE MIXER 0.3-0.6 M3 125 Ltr Unit 1 - -
JUMLAH -
B DEMOBILISASI LS 1 - -
JUMLAH -
C LAIN-LAIN
JUMLAH -
JUMLAH -
PROSES : ANGGAPAN :
1 Pengadaan bahan oleh Leveransir 1. Kelompok tukang kayu memasang 20m2 dalam satu hari kerja
2 Kelompok tukang kayu memotong 2. 1/3 material dapat dipakai kembali
dan membuat acuan 3. Pengadaan bahan oleh pemasok
3 Kelompok tukang kayu membongkar 4. Untuk 1m3 beton dipakai 20 lbr plywood (120 cm x 240 cm x 1,75cm )
acuan setelah beton cukup kuat 5. Kelompok tukang kayu membongkar acuan
4 Kelompok Tukang Kayu membersihkan
acuan untuk dipakai kembali.
JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Kepala Tukang 1.00 1.00 L073 1.00 #REF! #REF!
Tukang 4.00 1.00 L079 4.00 #REF! #REF!
P E K E R J A
PERALATAN Rp. -
TOTAL Rp. #REF!
PROSES : ANGGAPAN :
1 Batang besi beton dipotong sesuai 1. 200 Kg tulangan jadi disiapkan dalam 1 hari
ukuran panjang yang diperlukan. 2. Besi untuk tulangan dikirim ke tempat pekerjaan oleh Pemasok
2 Batang dan beugel besi beton 3. Penyusutan akibat pemotongan 10% dan pakai kawat baja dll dianggap 1%
dibengkok sesuai yang diperlukan. 4. Membengkok dan memasang batang besi beton dilaksanakan dengan tangan.
3 Perakitan tulangan besi beton 5. Panjang dan diameter besi tulangan yang biasa dipakai gorong-gorong dll.
dan diikat dengan kawat baja. 6. 0,8 orang -hari memotong 200kg batang besi beton.
7. 1,0 orang hari membengkok 200kg batang besi beton.
8. 1,2 orang-hari memasang dan mengikat 200kg tulangan besi beton.
9. Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat
JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Kepala Tukang 1.00 1.00 L073 1.00 #REF! #REF!
P E K E R J A
PERALATAN Rp. -
TOTAL Rp. #REF!
PROSES : ANGGAPAN :
1 Gali parit dengan tenaga manusia 1. Menggunakan tenaga manusia ( 100 m / hari )
2 Membuang sisa galian menggunakan 2. Dimensi parit : Lebar bawah = 0,5 m
truk bak terbuka Lebar atas = 1,3 m
Kedalaman = 0,6 m ( Vol = 0,54 m3/m )
3. 25 % hasil galian dibuang setempat
4. sisa galian dibuang sejauh 2 km
5. Menggali dan membuang dihitung 1,5 m3/orang-hari
6. Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat
JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Buruh tak terampil 36.00 1.00 L101 36.00 #REF! #REF!
P E K E R J A
PERALATAN Rp. -
TOTAL Rp. #REF!
PROSES : ANGGAPAN :
1 Mengupas dan membuang semak 1. Menggunakan tenaga manusia ( 1200 m2 / hari )
dengan tenaga manusia pada 2. Tidak ada pohon besar pada DAMIJA ( hanya semak )
DAMIJA (Daerah Milik Jalan) 3. DAMIJA 12 m
2 Lebar Pengupasan dan pembersihan 4. Pembersihan DAMIJA 100 m / hari
= DAMIJA minus Lebar Badan Jalan 5. Bakar sampah di lokasi pekerjaan
6. Hasil kerja 25 m2 / orang - hari
7. Umur alat bantu rata-rata 1 bulan / orang / set @ 3 alat
JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Buruh tak terampil 48.00 1.00 L101 48.00 #REF! #REF!
P E K E R J A
PERALATAN Rp. -
TOTAL Rp. #REF!
PROSES : ANGGAPAN :
1 Digali dengan tenaga manusia 1. Menggunakan tenaga manusia ( 40 m3 / hari )
2 Membuang tanah galian sejauh 2. Kepastian kerja per orang 1,3 m3 / hari
30 m dari lobang galian 3. Kedalaman rata-rata galian s/d 3 m
4. Umur alat bantu rata-rata 1 bulan / orang / set @ 3 alat
JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH (Rp./org
PEKERJA HARI KODE (Rp. ) (Rp.)
ORANG
ORANG /hari)
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Buruh tak terampil 30.00 1.00 L101 30.00 #REF! #REF!
P E K E R J A
PERALATAN Rp. -
TOTAL Rp. #REF!
PROSES : ANGGAPAN :
1 Digali dengan tenaga manusia 1. Menggunakan tenaga manusia ( 32 m3 / hari )
2 Permukaan tanah dibentuk dan 2. 20 % dibuang di lokasi tanpa diangkut dengan truk
diratakan dengan tenaga manusia 3. 80 % dibuang dan diangkut dengan truk
3 Dimuat ke truk dengan tenaga 4. Jarak 1 rit pp < 2 Km
manusia 5. 1,6 rit pp / jam / truk
4 Membuang tanah menggunakan truk 6. Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat
3,5 ton
JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Supir Terampil 2.00 1.00 L091 2.00 #REF! #REF!
P E K E R J A
PROSES : ANGGAPAN :
1 Digali dengan buldozer 1. Menggunakanperalatan berat ( 200 m3 / hari )
2 Permukaan tanah dibentuk dan 2. 20 % dibuang di lokasi tanpa diangkut dengan truk
diratakan dengan grader 3. 80 % diangkut dan dibuang dengan 1 truk
3 Dimuat ke truk dengan loader 4. Jarak 1 rit pp , 2 Km
dirapihkan dengan grader 5. 2,5 rit pp / jam / truk
4 Membuang tanah menggunakan
truck
JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH (Rp./org
PEKERJA HARI KODE (Rp. ) (Rp.)
ORANG
ORANG /hari)
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Operator Terampil 3.00 1.00 L081 3.00 #REF! #REF!
Pembantu Operator 3.00 1.00 L089 3.00 #REF! #REF!
P E K E R J A
PROSES : ANGGAPAN :
1. Pembentukan tanah dasr dengan 1. Menggunakan alat berat ( 8 m x 500 m/hari )
Grader 2. DAMIJA dibersihkan dari semak dan lain-lain
2. Dipadatkan dengan mesin gilas roda baja 3. Lebar dasar jalan 8 m
sampai 100 % MDD ( AASHTO 199 ) 4. Hasil kerja menyiapkan dasar jalan 500 m/hari
JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Operator Terampil 2.00 1.00 L081 2.00 #REF! #REF!
P E K E R J A
PROSES : ANGGAPAN :
1 Potong semak belukar yang tumbuh 1. Menggunakan tenaga manusia ( 2 x 1,5 x 500 m/hari )
pada bahu jalan 2. Dengan lebar 1,5 m dari tepi jalan, rata-rata luas yang dibersihkan
2 Bersihkan rumput/semak dari 1.500 m2/km satu sisi
bahu dan aspalan 3. Hasil Kerja 60 m2/hari - orang
4. Sampah / reruntuhan dibuang sejauh 1,0 Km
5. Penggunaan alat bantu 1 bulan/orang/set @ 3 alat
JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Buruh tak terampil 25.00 1.00 L101 25.00 #REF! #REF!
P E K E R J A
PERALATAN Rp. -
TOTAL Rp. #REF!
PROSES : ANGGAPAN :
1 Membersihkan dan membentuk ulang 1. Menggunakan tenaga manusia (500 m/hari)
parit dan menimbun tumpukan puing 2. Membersihkan sampah, kotoran yang menyumbat, tumbuh-tumbuhan dari parit dan gorong-gorong.
disepanjang jalan dengan tenaga orang
3. Pembuangan puing sejauh 1 km (10 m3/100 m)
4. Kapasitas 1,6 rit pp/jam/truk
2 Membuang puing dengan truk bak 5. Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat
terbuka, dimuat atau dibongkar dengan
tenaga orang
JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Mandor 1.00 1.00 L061 1.00 #REF! #REF!
Supir Terampil 2.00 1.00 L091 2.00 #REF! #REF!
P E K E R J A
PROSES : ANGGAPAN :
JUMLAH
HARI/ UPAH BIAYA SUB TOTAL
JUMLAH
PEKERJA HARI KODE (Rp./org/hari) (Rp. ) (Rp.)
ORANG
ORANG
Kepala Tukang 0.0150 1.00 L073 0.0150 #REF! #REF!
Tukang 0.1500 1.00 L079 0.1500 #REF! #REF!
P E K E R J A
PERALATAN Rp. -
TOTAL Rp. #REF!
B. PEKERJAAN STRUKTUR
I. Pekerjaan Pondasi
1. Pasang Pondasi Batu Kosong
Panjang pondasi Menerus = 57.00 m
Luasan = (0,1*0,8)
= 0.08 m2
Volume = 0.08 x 57.00
= 4.56 m3
= 191.5833 kg
= 0.024395 m3
Bekisting
Sisi = 2
Luasan = 0.13 x 3.55 x 2
= 0.923 m2
Sisi = 2
Luasan = 0.2 x 3.55 x 2
= 1.42 m2
Luasan I = (0,923+1,42) x 11
= 25.77 m2
= 106.7727 kg
= 0.013596 m3
Bekisting
Sisi = 2
Luasan = 0.15 x 3.55 x 2
= 1.065 m2
Sisi = 2
Luasan = 0.2 x 3.55 x 2
= 1.42 m2
Luasan I = (1,065+1,42) x 6
= 14.91 m2
= 109.6206 kg
= 0.013958 m3
Bekisting
Sisi = 2
Luasan = 0.2 x 2.97 x 2
= 1.188 m2
Sisi = 2
Luasan = 0.2 x 2.97 x 2
= 1.188 m2
Luasan I = (1,188+1,188) x 7
= 16.63 m2
Bekisting
Sisi = 2
Luasan I = 0.2 x 75.00
= 15 m2
Luasan Total Bekisting = 15 x 2
= 30.00 m2
5. Ring Balok Beton Bertulang Campuran 1 : 2 : 3 Uk. 15 x 20
Panjang = 75.00 m
Dimensi = 0.15 x 0.2
= 0.03 m2
Volume = 0.03 x 75.00
= 2.25 m3
Volume Total Balok = Volume Balok - Volume besi
= 2.25 - 0.038522
= 2.21147848 m3
Pembesian
Tul. Induk (dia 12) Panjang = 75.00 m
Jumlah = 4.00 bh
Panjang = 75.00 x 4.00
= 300 m
Berat = 12.00 x 12.00 x 0.006165 x 300.00
= 266.328 kg
Bekisting
Sisi = 2
Luasan I = 0.2 x 75.00 x 2
= 30.00 m2
Luasan Total Bekisting Ring Balok = 30.00
= 30.00 m2
Pembesian
Tul. Induk (dia 12) Panjang = 36.00 m
Jumlah = 4.00 bh
Panjang = 36.00 x 4.00
= 144 m
Berat = 12.00 x 12.00 x 0.006165 x 144.00
= 127.8374 kg
Bekisting
Sisi = 2
Luasan I = 0.15 x 36.00 x 2
= 10.80 m2
Luasan Total Bekisting Ring Balok = 10.80
= 10.80 m2
Sisi Atas
a = 1.2 x 0.05 x 0.13
= 0.0078 m3
Jlh = 2 bh
Vol sisi Tegak = 0.0078 x 2
= 0.0156
b = 0.58 x 0.05 x 0.13
= 0.00377 m3
Jlh = 6 bh
Vol sisi Tegak = 0.00377 x 6
= 0.02262
b. Kusen Jendela J1
Jumlah 10 bh
Sisi Tegak = 1.3 x 0.05 x 0.13
= 0.00845 m3
Jlh = 3 bh
Vol sisi Tegak = 0.00845 x 3
= 0.02535
J1
Panjang = 8.16
Lebar = 0.07
Luasan = 8.16 x 0.07
= 0.5712 m2
Jumlah 10 bh
Luasan J1 = 0.5712 x 10
= 5.712 m2
Jumlah 2 bh
Luasan PJ1 = 0.6728 x 2
= 2.6728
J1
Panjang = 0.58
Lebar = 0.78
Luasan = 0.58 x 0.78 x 3
= 1.3572 m2
Jumlah 10 bh
Luasan J1 = 1.3572 x 10
= 11.3572
4. Pekerjaan Dinding
4.1. Pasangan Dinding Batu Bata 1/2 Bata 1 : 2
Panjang = 57.00
Tinggi = 0.3
Luasan = 17.1 m2
PJ1 = (0,3*1,2)
= 0.36
Jlh = 2 bh
Luasn = 0.72 m2
I. Panjang = 57.00
Tinggi = 3.25
Luasan I = 185.25 m2
J1 = 2.7
= 2.7
Jlh = 10 bh
Luasn = 27 m2
= 2.5 x 0.13 x 2
= 0.65
= 1.1 x 0.05 x 6
= 0.33
= 1.1 x 0.13 x 4
= 0.572
Jumlah = 2
J1 = 1.4 x 0.05 x 8
= 0.56
= 1.4 x 0.13 x 6
= 1.092
= 0.6 x 0.05 x 18
= 0.54
= 0.6 x 0.13 x 12
= 0.936
Jumlah = 10
Total J1 = 3.128 x 10
= 31.28
Pekerjaan Plafond
Plafond Dalam
Luasan I = 8.87 x 8
= 70.96 m2
Jlh = 2
Total Luas I = 141.92
Plafond Luar
Luasan I = 1x 6.87 x 2
= 13.74 m2
Luasan II = 2.4 x 18
= 43.2 m2