REKAP AHSP SNI Hal 67

PEKERJAAN PENGECATAN (SNI 2407:2002)


F 001 Mengecat 1 m2 Beton ICI Eksterior 85,630.00
F 002 Mengecat 1 m2 Plafond dan Dinding Interior ICI 91,210.00
F 003 Mengecat 1 m2 Dinding Vinilex (3X) 62,100.00
F 004 Mengecat 1 m2 Dinding Lama Vinilex (2X) 41,400.00
F 005 Mengecat 1 m2 Plafond Vinilex (3X) 62,530.00
F 006 Mengecat 1 m2 Plafond Lama Vinilex (2X) 41,680.00
F 007 Mengecat 1 m2 Dinding Sanlex (3X) 43,390.00
F 008 Mengecat 1 m2 Dinding Lama Sanlex (2X) 28,920.00
F 009 Mengecat 1 m2 Plafond Sanlex (3X) 45,160.00
F 010 Mengecat 1 m2 Plafond Lama Sanlex (2X) 30,100.00
F 011 Mengecat 1 m2 Kayu (3X) Glotex berikut Meni 73,800.00
F 012 Mengecat 1 m2 Kayu Lama (2X) Glotex 49,190.00
F 013 Mengecat 1 m2 Besi (3X) Glotex 73,330.00
F 014 Mengecat 1 m2 Plituran Bangunan (Biasa) 92,160.00
F 015 Mengecat 1 m2 Plituran Meubulair 107,560.00

REKAP AHSP SNI Hal 68


PEKERJAAN PENGECATAN (SNI 2407:2002)
F001 Mengecat 1 m2 Beton ICI Eksterior
Cat tembok ICI 0.2500 lt 85,000.00 21,250.00
Alkali ICI sebelum pengecatan 0.1250 lt 50,000.00 6,250.00
Bahan
Rol cat 0.0100 bh 25,000.00 250.00
Ampelas 0.5000 lbr 5,000.00 2,500.00
Pekerja 0.1600 HO 80,000.00 12,800.00
Tukang cat 0.2800 HO 100,000.00 28,000.00
Tenaga kerja
Kepala tukang 0.0300 HO 120,000.00 3,600.00
Mandor 0.0100 HO 130,000.00 1,300.00
Alat Steger Werk 0.0250 lot 75,950.00 1,898.75
Jumlah 77,848.75
Overhead + Profit 7,784.88
Jumlah 85,633.63
Dibulatkan 85,630.00
F002 Mengecat 1 m2 Plafond dan Dinding Interior ICI
Cat tembok ICI 0.2500 lt 85,000.00 21,250.00
Cat dasar sebelum pengecatan 0.1250 lt 48,000.00 6,000.00
Bahan
Rol cat 0.0100 bh 25,000.00 250.00
Ampelas 0.5000 lbr 5,000.00 2,500.00
Pekerja 0.2000 HO 80,000.00 16,000.00
Tukang cat 0.3000 HO 100,000.00 30,000.00
Tenaga kerja
Kepala tukang 0.0300 HO 120,000.00 3,600.00
Mandor 0.0100 HO 130,000.00 1,300.00
Alat Steger Werk 0.0250 lot 80,900.00 2,022.50
Jumlah 82,922.50
Overhead + Profit 8,292.25
Jumlah 91,214.75
Dibulatkan 91,210.00
F003 Mengecat 1 m2 Dinding Vinilex (3X)
Cat tembok Vinilex 0.1750 kg 20,000.00 3,500.00
Plamir tembok 0.1600 kg 13,000.00 2,080.00
Bahan
Rol cat 0.0100 bh 25,000.00 250.00
Ampelas 0.5000 lbr 5,000.00 2,500.00
Pekerja 0.1600 HO 80,000.00 12,800.00
Tukang cat 0.2800 HO 100,000.00 28,000.00
Tenaga kerja
Kepala tukang 0.0300 HO 120,000.00 3,600.00
Mandor 0.0100 HO 130,000.00 1,300.00
Alat Steger Werk 0.0450 lot 54,030.00 2,431.35
Jumlah 56,461.35
Overhead + Profit 5,646.14
Jumlah 62,107.49
Dibulatkan 62,100.00

AHSP SNI Hal 15


F004 Mengecat 1 m2 Dinding Lama Vinilex (2X)
Mengecat 1 m2 Dinding Vinilex (3X) 2/3 X 62,100.00 41,400.00
Dibulatkan 41,400.00
F005 Mengecat 1 m2 Plafond Vinilex (3X)
Cat tembok Vinilex 0.2000 kg 20,000.00 4,000.00
Plamir tembok 0.1600 kg 13,000.00 2,080.00
Bahan
Rol cat 0.0100 bh 25,000.00 250.00
Ampelas 0.5000 lbr 5,000.00 2,500.00
Pekerja 0.1600 HO 80,000.00 12,800.00
Tukang cat 0.2800 HO 100,000.00 28,000.00
Tenaga kerja
Kepala tukang 0.0300 HO 120,000.00 3,600.00
Mandor 0.0100 HO 130,000.00 1,300.00
Alat Steger Werk 0.0425 lot 54,530.00 2,317.53
Jumlah 56,847.53
Overhead + Profit 5,684.75
Jumlah 62,532.28
Dibulatkan 62,530.00
F006 Mengecat 1 m2 Plafond Lama Vinilex (2X)
Mengecat 1 m2 Plafond Vinilex (3X) 2/3 X 62,530.00 41,686.67
Dibulatkan 41,680.00
F007 Mengecat 1 m2 Dinding Sanlex (3X)
Cat tembok Sanlex 0.1750 kg 15,800.00 2,765.00
Plamir tembok 0.1600 kg 13,000.00 2,080.00
Bahan
Rol cat 0.0100 bh 25,000.00 250.00
Ampelas 0.5000 lbr 5,000.00 2,500.00
Pekerja 0.1040 HO 80,000.00 8,320.00
Tukang cat 0.1820 HO 100,000.00 18,200.00
Tenaga kerja
Kepala tukang 0.0195 HO 120,000.00 2,340.00
Mandor 0.0100 HO 130,000.00 1,300.00
Alat Steger Werk 0.0450 lot 37,755.00 1,698.98
Jumlah 39,453.98
Overhead + Profit 3,945.40
Jumlah 43,399.37
Dibulatkan 43,390.00
F008 Mengecat 1 m2 Dinding Lama Sanlex (2X)
Mengecat 1 m2 Dinding Sanlex (3X) 2/3 X 43,390.00 28,926.67
Dibulatkan 28,920.00
F009 Mengecat 1 m2 Plafond Sanlex (3X)
Cat tembok Sanlex 0.2000 kg 15,800.00 3,160.00
Plamir tembok 0.1600 kg 13,000.00 2,080.00
Bahan
Rol cat 0.0100 bh 25,000.00 250.00
Ampelas 0.5000 lbr 5,000.00 2,500.00
Pekerja 0.1040 HO 80,000.00 8,320.00
Tukang cat 0.1820 HO 100,000.00 18,200.00
Tenaga kerja
Kepala tukang 0.0195 HO 120,000.00 2,340.00
Mandor 0.0195 HO 130,000.00 2,535.00
Alat Steger Werk 0.0425 lot 39,385.00 1,673.86
Jumlah 41,058.86
Overhead + Profit 4,105.89
Jumlah 45,164.75
Dibulatkan 45,160.00
F010 Mengecat 1 m2 Plafond Lama Sanlex (2X)
Mengecat 1 m2 Plafond Sanlex (3X) 2/3 X 45,160.00 30,106.67
Dibulatkan 30,100.00
F011 Mengecat 1 m2 Kayu (3X) Glotex berikut Meni
Meni kayu 0.1670 kg 16,000.00 2,672.00
Plamir kayu 0.0830 kg 25,000.00 2,075.00
Cat kayu merk GLOTEK 0.2000 kg 40,000.00 8,000.00
Bahan
Amplas kayu 0.4000 lbr 5,000.00 2,000.00
Minyak cat terpentin 0.1500 ltr 6,000.00 900.00
Kwas 3" 0.0500 bh 11,000.00 550.00
Pekerja 0.2000 HO 80,000.00 16,000.00
Tukang cat 0.3000 HO 100,000.00 30,000.00
Tenaga kerja
Kepala tukang 0.0300 HO 120,000.00 3,600.00
Mandor 0.0100 HO 130,000.00 1,300.00
Jumlah 67,097.00
Overhead + Profit 6,709.70
Jumlah 73,806.70
Dibulatkan 73,800.00
F012 Mengecat 1 m2 Kayu Lama (2X) Glotex
Mengecat 1 m2 Kayu (3X) Glotex berikut Meni 2/3 X 73,800.00 49,200.00
Dibulatkan 49,190.00

AHSP SNI Hal 16


F013 Mengecat 1 m2 Besi (3X) Glotex
Meni besi 0.1670 kg 16,000.00 2,672.00
Cat besi merk Glotek 0.2000 kg 40,000.00 8,000.00
Bahan Amplas besi 0.4000 lbr 5,000.00 2,000.00
Minyak cat thiner B 0.1500 ltr 17,000.00 2,550.00
Kwas 3" 0.0500 bh 11,000.00 550.00
Pekerja 0.2000 HO 80,000.00 16,000.00
Tukang cat 0.3000 HO 100,000.00 30,000.00
Tenaga kerja
Kepala tukang 0.0300 HO 120,000.00 3,600.00
Mandor 0.0100 HO 130,000.00 1,300.00
Jumlah 66,672.00
Overhead + Profit 6,667.20
Jumlah 73,339.20
Dibulatkan 73,330.00
F014 Mengecat 1 m2 Plituran Bangunan (Biasa)
Dempul plitur (dempul kasar) 0.0300 kg 27,000.00 810.00
Wood Filer (INFRA) 0.2000 kg 29,000.00 5,800.00
Oker putih 0.0200 kg 21,000.00 420.00
Oker warna 0.0100 kg 21,000.00 210.00
Bahan Batu Apung (gosok) 0.1000 kg 16,000.00 1,600.00
Sirlak ex India 0.2000 kg 87,200.00 17,440.00
Kwas 3" 0.0100 bh 11,000.00 110.00
Spirtus 0.2000 ltr 6,000.00 1,200.00
Ampelas kayu 0.1000 lbr 3,000.00 300.00
Pekerja 0.2500 HO 80,000.00 20,000.00
Tukang cat 0.2850 HO 100,000.00 28,500.00
Tenaga kerja
Kepala tukang 0.0400 HO 120,000.00 4,800.00
Mandor 0.0200 HO 130,000.00 2,600.00
Jumlah 83,790.00
Overhead + Profit 8,379.00
Jumlah 92,169.00
Dibulatkan 92,160.00
F015 Mengecat 1 m2 Plituran Meubulair
Dempul plitur (dempul kasar) 0.0300 kg 27,000.00 810.00
Wood Filer (INFRA) 0.2000 kg 29,000.00 5,800.00
Melamik 0.3500 kg 40,000.00 14,000.00
Oker putih 0.0200 kg 21,000.00 420.00
Oker warna 0.0100 kg 21,000.00 210.00
Bahan
Batu Apung (gosok) 0.1000 kg 16,000.00 1,600.00
Sirlak ex India 0.2000 kg 87,200.00 17,440.00
Kwas 3" 0.0100 bh 11,000.00 110.00
Spirtus 0.2000 ltr 6,000.00 1,200.00
Ampelas kayu 0.1000 lbr 3,000.00 300.00
Pekerja 0.2500 HO 80,000.00 20,000.00
Tukang cat 0.2850 HO 100,000.00 28,500.00
Tenaga kerja
Kepala tukang 0.0400 HO 120,000.00 4,800.00
Mandor 0.0200 HO 130,000.00 2,600.00
Jumlah 97,790.00
Overhead + Profit 9,779.00
Jumlah 107,569.00
Dibulatkan 107,560.00

AHSP SNI Hal 17