Rencana Usaha Pembibitan

Lokasi PN Jalan Sungai Rupat Bengkulu


Luas 30x40 = 1200 m2 84000 pb

Lokasi MN Rawa Makmur Bengkulu


Luas 25000 m2 37500 pb

Kebutuhan Biaya Bahan


Pre-Nursery
Land Clearing 1200 m2
1
HK 15 100,000 1,500,000
Pemagaran
Pancang 2 m 25 2,000 50,000
2
Waring 100 m/gulung 1 300,000 300,000
HK 3 100,000 300,000
Media Tanam
Tanah Top Soil (truk) 2 150,000 300,000
3
Tanah Kompos/Sekam (pickup) 2 300,000 600,000
Pasir laut (truk) 1 900,000 900,000
Benih/Kecambah
4
Pembayaran 40% x 40,000 butir) 40,000 3,600 144,000,000
Polybag Kecil lay flat (14x22 cm)
5
42000 helai >> 220 helai/kg = 200 kg 200 20,000 4,000,000
Paranet 75%
6
400x3 m >> 4 gulung 4 900,000 3,600,000
Naungan tempat Paranet
7
Pancang 3 m >> 50 bh 50 5,000 250,000
Kawat Licin/Jemuran
8 11x40 m>> 500m
/35m per gulung >> 15 gulung 15 25,000 375,000
9 Tirex 10 cm >> 500 bh >> 5 bks 5 15,000 75,000
10 Paku Campur 2" & 3" (kg) 3 20,000 60,000
11 Mesin Pompa 125W 1 700,000 700,000
12 Pipa PVC 3/4" >> Rp. 300.000 1 300,000 300,000
13 Selang 1/2" 1 gulung (50m) 1 350,000 350,000
14 Upah Aduk Tanah Media (HK) 10 100,000 1,000,000
Upah isi Polybag kecil (HK)
15
40000 + 5% = 42000 42,000 175 7,350,000
16 Susun Polybag 42,000 25 1,050,000
17 Bahan Bedengan + Upah 1 1,000,000 1,000,000
Upah Pemeliharaan + Penyiraman
18
3 bulan >> 1 HK x 30 hari x 3 bulan 90 100,000 9,000,000
Biaya Lain-lain 1 5,940,000 5,940,000
Tangki semprot 1 350,000 350,000
19 Pupuk NPK 15.15.6.4 10 6,000 60,000
Honor Jaga malam selama 3 bulan 3 1,000,000 3,000,000
Insektisida dan Fungisida 1 100,000 100,000
186,510,000
MAIN NURSERY ektif 2.5 Ha)

No Uraian Jumlah Harga Satuan Total


1 Persiapan Lahan
a Pagar Keliling (asumsi 270 x 100 = 740 m)
Kawat Duri 4 tingkat (740 x 4 = 2960 m >> 3000 m) 30 245,000 7,350,000
b Pagar Pelapis (ganti waring) 740/15 = 49 >> 50 gulung 50 50,000 2,500,000
c Tiang Pagar 740/3 = 247 >> 250 batang 250 5,000 1,250,000
d Paku Campur >>10 kg 10 20,000 200,000
e Upah Kerja >>25 HK 25 100,000 2,500,000
f Sewa lahan +/- Rp. 3000000/thn selama 5 thn 5 3,000,000 15,000,000
g Pembangunan Rumah Jaga >> 4 m x 4 m 16 2,000,000 32,000,000
h Instalasi Listrik untuk Penerangan dan Jaga 1

2 Pembersihan Lahan
a Racun Rumput 2,5 Ha x 5L = 12.5 L 12.5 50,000 625,000
b Upah Kerja 5 HK x 2.5 Ha = 12.5 12.5 100,000 1,250,000
c Drainase 5HK x 2.5 Ha = 12.5 12.5 100,000 1,250,000

3 Pengisian Polybag/Large Polybag (40x50 cm)


a Polybag 42000 -10% = 37800 polybag ~~ 18 helai/kg = 2100 kg 2,100 28,000 58,800,000
b Media 37800 pb x 25 kg = 945000 kg >> 1000000 kg
- Tanah Top Soil 60% x 1000000 = 600000 kg
1 truk = 6000 kg = 100 truk 100 150,000 15,000,000
- Pasir 20% x 1000000 = 200000 kg >> 33 truk 33 900,000 29,700,000
- Sekam/Bahan Organik 20% >> 33 truk 33 1,000,000 33,000,000
c Isi Polybag + Susun Rp 750/pb 37,800 750 28,350,000
d Pemindahan bibit PN ke MN 37,800 1,500 56,700,000
e Angkutan PN ke MN taksasi 1000 pb/pick up 40 150,000 6,000,000

4 Instalasi Penyiraman
a mesin Pompa air modifikasi 2"->2" 450 W input 900W 1 3,000,000 3,000,000
b pipa-pipa berbagai ukuran + sambungan, Elbow, lem dll 1 5,000,000 5,000,000
c Selang Drip 33 gulung/Ha x 2.5 Ha = 82.5 gulung >> 83 gulung 83 440,000 36,520,000
d Biaya Listrik/BBM Pompa +/- Rp. 2000000/bln 9 2,000,000 18,000,000

5 Pemeliharaan
a Penyiangan di dalam dan di luar polybag 15 HK/Bln selama 9 bln 135 100,000 13,500,000
b Memupuk bibit 20 HK/Bln selama 9 bulan 180 100,000 18,000,000
Pupuk NPK dan Kieserite
- umur 4-6 bln NPK 15.15.6.4 : 25 gram/bibit 945 6,000 5,670,000
- umur 7-12 bln NPK 12.12.17.2 : 230 grm/bibit 8,694 6,500 56,511,000
- Pupuk Kieserite umur 8-12 bln 8/31/2021 55 grm/bibit 2,079 4,500 9,355,500
c Tenaga Penyiram 1 HK selama 9 bulan 270 100,000 27,000,000
d Pengendalian Hama dan Penyakit
- Insektisida 10 100,000 1,000,000
- Fungisida 10 100,000 1,000,000
- Upah kerja 10 HK/Bulan selama 9 bulan 90 100,000 9,000,000

6 Operasional
a Gaji Pengawas/Mandor 1 HK selama 9 bulan 270 125,000 33,750,000
b Penjaga malam selama 9 bulan 270 100,000 27,000,000

7 Operasional Penjualan
a Bongkar dan muat bibit ke truk +/- Rp.2000/bibit 34,020 1,500 51,030,000

8 Biaya biaya lain


a Sertifikasi dari kecambah s/d bibit siap tanan 40,000 200 8,000,000
Total Biaya MN 614,811,500
Total Biaya PN 186,510,000
Pelunasan 60% benih 40,000 5,400 216,000,000
TOTAL 1,017,321,500
Penjualan (37.800 - 10%) bibit 34,020
34,020 35,000 1,190,700,000
Harga Jual
34,020 40,000 1,360,800,000