Harga Set
No Rincian Bahan-Bahan Material Jumlah Set Besar ( Rp)
(Rp)
1 Drum ( Tempat Air ) 2.0 buah 250,000 500,000
2 Selang Air 3/4 in 5/8 in 25.0 m 10,000 250,000
3 Pacul "Jago" + Doran 5.0 buah 60,000 300,000
4 Sekop 3.0 buah 55,000 165,000
5 Ember Kecil 30.0 buah 8,000 240,000
6 Ember Besar 15.0 buah 12,000 180,000
7 Benang Jagung 5.0 pak 25,000 125,000
8 Kawat Ayakan Hijau 1 Cm 5.0 m 25,000 125,000
9 Setang Gergaji Besi 2.0 buah 40,000 80,000
10 Mata Gergaji Besi ( Sanflex ) 4.0 buah 15,000 60,000
11 PAKU
a. Paku 3/4 in ( Triplex ) 2.0 Kg 20,000 40,000
b. Paku 2 in ( Reng Kayu ) 50.0 Kg 15,000 750,000
c. Paku 3 in ( Plafon ) 40.0 Kg 15,000 600,000
d. Paku 4 in ( Usuk ) 30.0 Kg 15,000 450,000
e. Paku 5 in ( Dludur 12 cm ) 25.0 Kg 15,000 375,000
f. Paku Payung 2 in + Karet Perpak 1.0 pak 25,000 25,000
12 Kayu Kaso 4/6 Kalimantan Panjang 4 m 25.0 pak 250,000 6,250,000
13 Kawat Bendrat 50.0 Kg 20,000 1,000,000
14 Bambu Ø 6 cm - 10 cm, panjang 9 m 600.0 batang 25,000 15,000,000
15 Papan Pinus 2/20 x 200 cm 400.0 lembar 35,000 14,000,000
16 Triplex 4 mm Tikwool ( 1,2 x 2,4 m ) Untuk Pekerjaan Ac 15.0 lembar 110,000 1,650,000
17 Triplex 2 mm Tikwool ( 1,2 x 2,4 m ) Untuk Dak 50.0 lembar 60,000 3,000,000
18 a. Pasir Pasang ( cirebon ) ± 8.5 m3 15.0 Truk 1,500,000 22,500,000
19 b. Pasir Cor / Plesteran (kali gung) ±3.5 m3 20.0 Truk 600,000 12,000,000
20 Split 1-2 cm 10.0 Truk 1,500,000 15,000,000
21 Semen Tiga Roda Portland 500.0 Sak 90,000 45,000,000
22 Batu Bata 20,000.0 bh 1,200 24,000,000
23 Genteng 5,000.0 bh 2,500 12,500,000
24 Tenaga Kerja Pelaksana Bangunan 2.0 Ls 39,000,000 78,000,000
JUMLAH TOTAL 254,165,000