Anda di halaman 1dari 1

CV.

SURYASAPUTRA

PENAWARAN HARGA BORONGAN


INSTALASI PENGOLAHAN AIR LIMBA

HARGA
NO JENIS PEKERJAAN VOLUME SATUAN JUMLAH BIAYA
SATUAN

Bak Vesel
1 Pembongkaran Paving 52.50 m2 22,500 Rp 1,181,250.00
2 Galian 150.81 m3 127,800 Rp 19,273,518.00
3 Langsir Galian 150.81 m3 72,000 Rp 10,858,320.00
4 Lantai Kerja PC 1:2:3 2.95 m3 607,500 Rp 1,792,125.00
5 Pek. Pembesian 941.98 kg 20,250 Rp 19,075,095.00
6 Pek. Bekisting 150.90 m2 126,000 Rp 19,013,400.00
7 Pek. Pengecoran K-200 11.90 m3 1,410,000 Rp 16,779,000.00
8 Plester Aci 72.68 m2 54,000 Rp 3,924,720.00
9 Cat Weatherproof 72.68 m2 42,750 Rp 3,107,070.00
Rp -
10 Penutup Bak Vesel Rp -
11 Pek. Pembesian 241.50 kg 20,250 Rp 4,890,375.00
12 Pek. Bekisting 28.05 m2 126,000 Rp 3,534,300.00
13 Pek. Pengecoran K-200 2.47 m3 1,410,000 Rp 3,482,700.00
14 Plester Aci 26.93 m2 54,000 Rp 1,454,220.00
15 Cat Weatherproof 26.93 m2 42,750 Rp 1,151,257.50
16 Pintu Besi manhole 5.00 bh 1,665,000 Rp 8,325,000.00
17 Bak Penampungan 2 m3 3.00 bh 3,519,000 Rp 10,557,000.00
18 Bak Penampungan 5 m3 2.00 bh 8,109,000 Rp 16,218,000.00
19 Bak Penampungan 10 m3 1.00 bh 11,430,000 Rp 11,430,000.00
20 Instalasi Pipa IpaI 3' 157.00 m1 31,950 Rp 5,016,150.00
21 Galian untuk instalasi pipa t =40 cm I = 30 cm 18.84 m3 127,800 Rp 2,407,752.00
22 Lantai kerja Pipa K-100t=5 cm 7.85 m3 607,500 Rp 4,768,875.00
23 Pemasangan pompa 4.00 bh 337,500 Rp 1,350,000.00
24 Pemasangan blower 2.00 bh 225,000 Rp 450,000.00

JUMLAH Rp 170,040,127.50
JUMLAH TOTAL Rp 170,040,127.50
DIBULATKAN Rp 170,040,000.00
SERATUS TUJUH PULUH JUTA EMPAT PULUH RIBU
Terbilang : RUPIAH
Jangka waktu pelaksanaan 90 hari setelah uang muka
Sistim pembayaran : Sidoarjo 12 Januari 2022
Dp 40 %
Termin I Progres 50% dibayar 30%
Termin II Progres 100% dibayar 30%
masa pemeliharaan 30 hari setelah BAST Agoes Alexander