No Itemized Costs qty/vol Unit Unit Price Amount Keterangan


A. Item Persiapan Lahan
I Pekerjaan Persiapan
1 Pembersihan Lahan 42.0 m2 14,000.00 Rp 588,000
2 Pasangan Bowplank & Pengukuran 42.0 m' 50,000.00 Rp 2,100,000
3 Listrik & Air Kerja 1.0 Ls 1,500,000.00 Rp 1,500,000
Sub-total A Rp 4,188,000

B. PEKERJAAN STRUKTUR DAN TANAH

I Pekerjaan Tanah
1 Galian Pondasi batu Kali (t=100cm L = 60cm) 20.4 m3 105,000.00 Rp 2,142,000
2 Galian Pond. footplat (t=150cm L= 80cm) 7.7 m3 105,000.00 Rp 806,400
3 Urugan pasir t=5 cm dibawah Pondasi 1.0 m3 450,000.00 Rp 459,000
Sub. Total B I Rp 3,407,400
II Pekerjaan Pondasi
1 Pondasi Batu Kali 17.0 m3 750,000.00 Rp 12,750,000

Sub. Total B II Rp 12,750,000


III Pekerjaan Beton
1 Sloof Beton (25 x 15 cm x 340cm) 2.0 m3 6,250,000.00 Rp 12,656,250
2 Kolom Praktis (15 x25 cm) 1.9 m3 6,608,840.00 Rp 12,292,442
3 Kolom Praktis (10 x 12 cm) 0.5 m4 6,608,840.00 Rp 2,981,909
3 Ring Balok (15 x 20 cm) 0.32 m3 5,707,800.00 Rp 1,797,957
4 Dak beton t =15 cm ᴓ 8 cm 6.2 m3 6,707,210.50 Rp 41,249,345
5 Waterproofing dak beton 41.0 m2 115,200.00 Rp 4,723,200
Sub. Total B III Rp 75,701,103
SUB. TOTAL B (PEKERJAAN STRUKTUR & TANAH) Rp 91,858,503
C. PEKERJAAN ARSITEKTUR
I Pekerjaan Dinding
1 Pasangan Dinding Hbel tbl 10 126.0 m2 161,000.00 Rp 20,286,000
2 Plesteran + Acian 287.0 m2 61,610.00 Rp 17,682,070
3 Pasangan ornamen 27.6 m2 850,000.00 Rp 23,460,000
4 Cat dinding Vinylex/setara 288.0 m2 47,500.00 Rp 13,680,000
5 Cat dinding Vinylex/setara exterior 40.3 m2 87,400.00 Rp 3,522,220
Sub. Total C I Rp 78,630,290
II Pekerjaan Pintu dan Jendela accsesoris
1 Pintu Aluminium(100 x 260 cm 1.0 Ls 1,750,000.00 Rp 1,750,000

2 Jendela Kaca Ruang Security 2.0 ls 825,000.00 Rp 1,650,000


Sub. Total C II Rp 3,400,000
III Pekerjaan Lantai Keramik & Accesoris

1 Peninggian Lantai dgn urugan tanah 30 cm*


2 urugan pasir 10 cm 2.8 m3 427,400.00 Rp 1,196,720
3 lantai kerja 5cm 1.5 m3 1,124,500.00 Rp 1,686,750
4 Keramik Lantai KM 40x40 6.0 m2 251,000.00 Rp 1,506,000
Sub. Total C III Rp 4,389,470
SUB. TOTAL C (ARSITEKTUR) Rp 86,419,760
Sub. Total D I Rp -
III Pekerjaan ME
1 Lampu TL 18 W ex. Philip/ setara 2.0 ttk 113,000.00 Rp 226,000
2 Lampu LED Outbow 4.0 ttk 145,000.00 Rp 580,000
3 Lampu LED strip 1.0 ttk 220,000.00 Rp 220,000
4 Dudukan Lampu TL 2.0 ttk 160,000.00 Rp 320,000
5 Sakelar Ganda (ex. Panasonic) 1.0 ttk 182,000.00 Rp 182,000
6 Sakelar Tunggal (ex. Panasonic) 1.0 ttk 155,000.00 Rp 155,000
7 Stop Kontak 1.0 ttk 155,000.00 Rp 155,000
8 Jaringan Kabel Listik 12.0 ttk 67,000.00 Rp 804,000
9 MCB 1.0 ttk 345,000.00 Rp 345,000
10 Jaringan antene TV 1.0 ttk 155,000.00 Rp 155,000
Sub. Total D III Rp 3,142,000
SUB. TOTAL D ( ME) Rp 3,142,000
Total Rp 185,608,263
TOTAL AKHIR Rp 185,608,263
Luas Bangunan
Rate per meter

Keterangan : Penawaran ini bukan tanda pembayaran. Ukuran berdasarkan hasil pengukuran awal, masih dapat berubah
secara minor. Sebelum adanya tanda jadi harga masih dapat berubah sewaktu-waktu. Hubungi kami lebih lanjut untuk
informasi lebih jelas & detail. Terimakasih
Jakarta, 3 Mei 2022
Hormat Kami

Andri Oktifan
15 18 33

3200
230,000,000
Discount 10%
TOTAL AKHIR
Luas Bangunan

Rate per meter

Keterangan : Penawaran ini bukan tanda pembayaran. Ukuran berdasarkan hasil pengukuran awal, masih dapat berubah secara minor. Sebelum adanya ta
dapat berubah sewaktu-waktu. Hubungi kami lebih lanjut untuk informasi lebih jelas & detail. Terimakasih.

Bandung, 15 Februari 2022


Direktur
Afif Abdulbasith, M.Si
-Rp24.730.296
Rp222.572.663
73

Rp3.069.121

wal, masih dapat berubah secara minor. Sebelum adanya tanda jadi harga masih
erimakasih.

andung, 15 Februari 2022


irektur
Afif Abdulbasith, M.Si
4 6.0025
10.0025