REKAPITULASI ANGGARAN DAN BIAYA SUB - KONTRAKTOR (DENGAN BESI) - SECTION 4

PEKERJAAN PEMBANGUNAN SUTT 150 kV GI KASONGAN - KUALA KURUN (T. 302 -T.377)

1) No. Tower T. 302


2) Tipe Tower AA 0
3) Tipe Pondasi AA
4) Class Pondasi II
5) Jarak Langsir Medan Datar 600 m
6) Jarak Langsir Medan Berbukit 0 m
7) Total Jarak Langsiran 600 m
8) Panjang Bored Pile 112 m
9) Berat Tower 0 kg
10) Pekerjaan Demolishing 0 m3
Detail Tagihan :
I Pek. Pondasi 84,830,608
→ Langsir Medan Datar 17,869,500
→ Langsir Medan Berbukit -
II Pek. Bored Pile 49,088,279
→ Langsir Medan Datar 9,289,061
→ Langsir Medan Berbukit -
III Pek. Erection -
Pek. Langsir Erection -
IV Pek.Demolisihing -
Total Tagihan Subkon = Rp 161,077,448

HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME JUMLAH HARGA
SATUAN
1 2 3 4 5 6
I PEKERJAAN PONDASI TOWER
A TOWER TYPE AA2
2 TIPE PONDASI II Set 28.00 115,103,001 3,222,884,040
1 Pekerjaan pembersihan lokasi tower 1.00 3,540,887 3,540,887
2 Mobilisasi & Demobilisasi Pekerja & Alat Bantu Kerja 1.00 2,500,000 2,500,000
3 Pengukuran & bouwplank (termasuk stub setting & modifikasi stub) + Grounding Tower 1.00 2,092,757 2,092,757
4 Jalan masuk ketitik tower 1.00 2,520,000 2,520,000
5 Galian tanah biasa 34.97 80,319 2,808,906
6 Urugan pasir dibawah pondasi 4.66 253,424 1,179,941
7 Urugan tanah kembali dan pemadatan 2.91 60,372 175,561
8 Beton lantai kerja B-O 2.33 1,073,573 2,499,278
9 Beton K.225 27.08 1,456,317 39,429,784
10 Besi Beton U-24 / U-32 2,595.46 1,000 2,595,460
11 Bekisting 56.26 395,006 22,223,017
12 Dewatering/ pengeringan 1.00 971,286 971,286
13 Tes beton di Lab (umur kubus 7, 14 dan 28 hari) 3.00 550,000 1,650,000
14 Patok batas tanah beton 10/10-80 4.00 160,933 643,733
JUMLAH 84,830,608

E PEKERJAAN BOREPILE DIAMETER 40 cm / m m 112 438,288 49,088,279


Include :
- Galian Lubang Bored Pile
- Casing (Jika dibutuhkan)
- Pembesian kg 17.53
- Pengecoran kg 0.1257

F.1 MEDAN DATAR


Beton K.225
0 - 499 m m3 1 330,000 330,000
500 m - 999 m m3 1 660,000 660,000
>= 1000 m m3 1 990,000 990,000

Kalkulator Langsir Beton K-225


Langsir Material Beton K-225 seberat 1 m3 sejauh 600 m dengan perhitungan sebagai berikut : Berat 27 Jarak 600
Lansir Beton K-225 27 660,000 17,869,500
Total Langsir Material Beton K-225 Medan Datar sebesar 27.075 m3 sejauh 600 m 17,869,500

F.2 MEDAN BERBUKIT


Beton K.225
0 - 499 m m3 1 605,000 605,000
500 m - 999 m m3 1 1,210,000 1,210,000
1000 m- 1499m m3 1 1,410,000 1,410,000
1500 - 1999 m m3 1 1,815,000 1,815,000
2000 > m3 1 2,100,000 2,100,000

Kalkulator Langsir Beton K-225


Langsir Material Beton K-225 seberat 1 m3 sejauh 0 m dengan perhitungan sebagai berikut : Berat 27 Jarak -
Lansir Beton K-225 m3 27.08 - -
Total Langsir Material Beton K-225 Medan Berbukit sebesar 27.075 m3 sejauh 0 m -