IV PEKERJAAN ATAP -
PAJAK 10 % 48,666,802.18
DIBULATKAN 535,334,000.00
TERBILANG : ###
ROSTA MANULLANG
Direktur
RENCANA ANGGARAN BIAYA (RAB)
SATU HARGA
No. URAIAN VOLUME JUMLAH
AN SATUAN
I PEKERJAAN PERSIAPAN
1 Papan nama proyek unit 1.00 311,459.00 311,459.00
2 Pembuatan Direksi Keet m2 12.00 400,032.00 4,800,384.00
3 Air dan Listrik Kerja bln 5.00 -
4 Pagar Pengaman Proyek m1 112.02 -
5 Mobilisasi dan demobilisasi ls 1.00 -
6 Biaya administrasi Proyek ls 1.00 -
Subtotal 5,111,843.00
II PEKERJAAN PONDASI DAN STRUKTUR BAWAH
1 Sloof Beton (SL2) m3 1.98 5,071,346.00 10,041,265.08
Subtotal 10,041,265.08
III PEKERJAAN STRUKTUR
1 Kolom Beton (K2) m3 0.90 4,870,398.00 4,383,358.20
2 Pas. Angkur bh 48.00 11,800.00 566,400.00
3 Base Plate Kolom Baja kg 220.00 -
4 Kolom Baja IWF (KB1) kg 2,774.52 29,666.00 82,308,910.32
5 Kolom Praktis (10/10) m3 1.76 4,145,054.00 7,295,295.04
6 Ring Balok Beton 1 (RB1) m3 1.50 5,376,936.00 8,065,404.00
7 Ring Balok Beton 2 (RB2) m3 2.53 5,568,569.00 14,088,479.57
8 Dak Talang Beton m3 3.90 4,363,366.00 17,017,127.40
9 Lisplank Beton m3 2.48 4,060,256.00 10,069,434.88
Subtotal 143,794,409.41
IV PEKERJAAN ATAP
1 Rangka Atap Kuda-Kuda Utama (T1) kg 2,686.40 -
2 Rangka Atap Kuda-Kuda Depan (T2) kg 554.67 -
3 Rangka Atap Kuda-Kuda Canopy (T3) kg 512.00 -
4 Rangka Lisplank (T4) kg 300.00 -
5 Rangka Penghubung Kuda-Kuda Utama (CR 1 & 2) kg 1,500.00 -
6 Pelat Sambung Rangka Atap + Dudukan Gording kg 150.00 -
7 Mur Baut HTB (High Tension Bolt) Sambungan Kuda-Ku bh 336.00 -
8 Gording Canal Atap kg 4,346.08 -
9 Trekstang dan Ikat Angin (Diagonal Bracing) Lengkap dg kg 20.00 -
10 Pas. Atap Zincalume t=0,4mm Color Coated (t=0,45mm T m2 733.90 -
11 Pas. Nok atap Zincalume t=0,4mm Color Coated (t=0,45 m1 28.00 -
12 Pas. Insulasi Atap Alumunium Foil, Glasswool dan roofme m2 733.90 -
Subtotal -
V PEKERJAAN DINDING DAN PLAFOND
1 Pas. Dinding Batu Bata, t= 1/2 Bata ad. 1 : 5 m2 323.52 90,979.00 29,433,526.08
2 Pek. Plasteran dan Acian ad. 1 : 5 m2 647.04 55,212.00 35,724,372.48
3 Pek. Pipa BIP Jaring Pengaman, 3" t= 3,25mm dan 2" t kg 2,080.00 -
4 Pek. Pelat Dudukan Pipa (Base Plate) kg 87.00 -
5 Pas. Angkur Pipa bh 40.00 -
6 Kawat Harmonika Galvanis BWG mesh 55x55 mm t= 3,2 m2 368.00 -
7 Besi polos dia. 10 penjepit kawat harmonika kg 234.03 8,700.00 2,036,061.00
8 Pas. Dinding Zincalume t=0,4mm Color Coated (t=0,45 m2 117.00 84,100.00 9,839,700.00
9 Pas. Dinding Polycarbonate Gelombang m2 30.00 -
10 Gording Canal Dinding kg 550.00 -
11 Trekstang Dinding bh 57.00 -
12 Pelat Dudukan Gording kg 55.00 -
13 Pas. Plafond GRC Rangka Hollow m2 207.00 -
Subtotal 77,033,659.56
VI PEKERJAAN LANTAI BETON ARENA
1 Urugan Pasir Bawah Pelat lantai m3 69.05 294,922.00 20,364,364.10
2 Beton Lantai K-225 wiremesh M6-150 Finish Trowel m3 138.08 1,445,662.00 199,617,008.96
3 Gawang Futsal dan Jaring Standar unit 2.00 -
Subtotal 219,981,373.06
VII PEKERJAAN LANTAI KERAMIK DAN RABAT
1 Rabat Beton t = 7 cm m2 6.93 61,637.00 427,144.41
2 Lantai Kerja bawah Rabat dan Pas. Keramik t = 5 cm m3 5.95 971,423.00 5,779,966.85
3 Urugan Pasir Bawah lantai t = 5 cm m3 5.95 294,922.00 1,754,785.90
4 Pas. Keramik Lantai Uk. 40 x 40 m2 156.00 124,426.00 19,410,456.00
5 Pas. Keramik Lantai Uk. 20 x 20 Anti Slip m2 22.50 124,951.00 2,811,397.50
6 Pas. Keramik Dinding Uk. 20 x 25 m2 87.75 -
7 Pas. Plint Keramik Standar m1 9.00 57,969.00 521,721.00
Subtotal 30,705,471.66
VIII PEKERJAAN PINTU DAN JENDELA
1 Pas. Pintu Double Alumunium (P1) bh 2.00 -
2 Pas. Pintu Alumunium (P2) bh 2.00 -
3 Pas. Pintu Geser Pipa Galvanis 2" Jaring Kawat Harmoni bh 2.00 -
4 Pekerjaan Pintu PVC bh 6.00 -
5 Pas. Jendela Alumunium (J1) bh 2.00 -
6 Pas. Jendela Alumunium (J2) bh 4.00 -
Subtotal -
IX PEKERJAAN PENGECATAN DAN WATERPROOFING
1 Pek. Cat Besi Struktur Baja dan Besi Pipa m2 129.35 -
2 Pek. Cat Dinding Exterior Weathershield m2 293.52 -
3 Pek. Cat Dinding Interior m2 472.12 -
4 Pek. Cat Plafond m2 207.00 -
5 Pek. Cat Lapangan dan Garis Lapangan m2 513.00 -
6 Pek. Waterproofing Talang Beton m2 19.00 -
Subtotal -
X PEKERJAAN PLUMBING & SANITAIR
1 Closet Jongkok unit 4.00 -
2 Floor Drain bh 6.00 -
3 Roof Drain Cast Iron 4" Talang Beton bh 6.00 -
4 Kran Air Ø 1/2" bh 8.00 -
5 Shower Air Tempel Standar bh 2.00 -
6 Instalasi Air Kotor / Bekas Pipa PVC AW 4" m1 24.00 -
7 Instalasi Air Bersih Pipa PVC AW 1/2" dan 1" m1 28.00 -
8 Instalasi Pipa Buangan Air Hujan Pipa PVC AW 3" m1 16.00 -
9 Pompa Air Jet Pump unit 1.00 -
10 Tanki Air Kapasitas 1000 Ltr unit 1.00 -
11 Septictank FRP Sistem Biotech cap. 3 m3 + Pondasi + R unit 2.00 -
12 Water Tower Rangka Besi Siku L 50,50,5 unit 1.00 -
Subtotal -
XII PEKERJAAN ELEKTRIKAL
1 Instalasi Titik Lampu Kabel NYM 3 x 2,5 mm titik 24.00 -
2 Instalasi Stop Kontak Kabel NYM 3 x 2,5 mm titik 10.00 -
3 Pasangan Saklar Double titik 6.00 -
4 Pasangan Skalar Tunggal titik 3.00 -
5 Pasangan Stop Kontak titik 5.00 -
6 Lampu SL 25 Watt (Inbouw), Termasuk Bahan. Komplit titik 9.00 -
7 Lampu TL 2x36 watt (Inbouw), Termasuk Bahan. Komplit titik 3.00 -
8 Lampu HPIT 250 W Tipe Tango Lengkap titik 12.00 -
9 Lampu Sorot SL 36 watt + reflector PAR 368 titik 2.00 -
10 Box Panel uk. 70x50x40 bh 1.00 -
11 MCB Pembagi 6 A bh 25.00 -
12 Lampu Taman SL 25 watt Tiang Pipa GIP t= 2m + Pondas bh 15.00 -
13 Penangkal Petir + Grounding set 3.00 -
14 Installasi Listrik PLN + KWH Meter watt 7,700.00 -
Subtotal -
XIII PEKERJAAN SARANA LUAR
1 Saluran Buis Beton 1/2 Ø 30 cm m1 315.48 -
2 Sumur Resapan dia. 1m unit 4.00 -
3 Pek. Pemasangan Paving Block t = 6 cm K250 m2 710.00 -
4 Sirtu Bawah Paving block t=20cm + Pemadatan m3 142.00 -
5 Pek. Pasangan Kansteen K250 uk. 40.20.10 m1 316.90 -
6 Huruf Stainless Steel tinggi 30 cm tebal 7 cm bh 15.00 -
7 Huruf Stainless Steel tinggi 25 cm tebal 7 cm bh 26.00 -
8 Pasang Logo Kota Tangerang Stainless Steel bh 1.00 -
9 Penanaman Pohon Pucuk Merah t = 1 m bh 20.00 -
10 Penanaman Pohon Trembesi t = 4 - 5 m phn 15.00 -
11 Penanaman Rumput Gajah Mini m2 135.05 -
Subtotal -
ANALISA TEKNIS
HARGA SATUAN PEKERJAAN
PEKERJAAN PERSIAPAN
PEKERJAAN TANAH
PEKERJAAN PONDASI
PEKERJAAN BETON
DIBULATKAN 12,216.00
BT13 1 m2 - Bekisting dengan papan + bongkaran dan penyiraman
Kayu Papan terentang 2/20-400 cm 0.0240 m3 2,420,000.00 58,080.00
Kayu Kaso terentang 5/7-400 cm 0.0280 m3 3,205,700.00 89,759.60
Paku 0.2500 kg 16,000.00 4,000.00
Pekerja 0.1650 hr 78,700.00 12,985.50
Tukang kayu 0.3940 hr 94,500.00 37,233.00
Mandor 0.0270 hr 131,200.00 3,542.40
JUMLAH 205,600.50
DIBULATKAN 205,600.00
BT14 1 m2 - Bekisting dengan triplex 9 mm + bongkaran dan penyiraman
Kayu Kaso terentang 5/7-400 cm 0.0280 m3 3,205,700.00 89,759.60
Multiplex 9 mm 0.3500 lbr 143,400.00 50,190.00
Paku 0.2500 kg 16,000.00 4,000.00
Pekerja 0.1650 bh 78,700.00 12,985.50
Tukang kayu 0.3940 hr 94,500.00 37,233.00
Mandor 0.0270 hr 131,200.00 3,542.40
JUMLAH 197,710.50
DIBULATKAN 197,710.00
BT14a 1 m3 - Bekisting sloof beton struktur
Kayu Kaso terentang 5/7-400 cm 0.1247 m3 3,205,700.00 399,750.79
Multiplex 9 mm 1.5667 lbr 143,400.00 224,664.78
Paku 1.1120 kg 16,000.00 17,792.00
Pekerja 0.7340 hr 78,700.00 57,765.80
Tukang kayu 1.7507 hr 94,500.00 165,441.15
Mandor 0.1200 hr 131,200.00 15,744.00
JUMLAH 881,158.52
DIBULATKAN 881,158.00
BT15 1 m3 - Bekisting kolom beton struktur
Kayu Kaso terentang 5/7-400 cm 0.2520 m3 3,205,700.00 807,836.40
Multiplex 9 mm 3.1500 lbr 143,400.00 451,710.00
Paku 2.2500 kg 16,000.00 36,000.00
Pekerja 1.4850 hr 78,700.00 116,869.50
Tukang kayu 3.5440 hr 94,500.00 334,908.00
Mandor 0.2430 hr 131,200.00 31,881.60
JUMLAH 1,779,205.50
DIBULATKAN 1,779,205.00
BT16 1 m3 - Bekisting balok beton struktur
Kayu Kaso terentang 5/7-400 cm 0.1870 m3 3,205,700.00 599,465.90
Multiplex 9 mm 2.3500 lbr 143,400.00 336,990.00
Paku 1.6680 kg 16,000.00 26,688.00
Pekerja 1.1010 hr 78,700.00 86,648.70
Tukang kayu 2.6260 hr 94,500.00 248,157.00
Mandor 0.1800 hr 131,200.00 23,616.00
JUMLAH 1,321,565.60
DIBULATKAN 1,321,565.00
BT17 1 m3 - Bekisting lantai beton
Kayu Kaso terentang 5/7-400 cm 0.2320 m3 3,205,700.00 743,722.40
Multiplex 9 mm 2.9050 lbr 143,400.00 416,577.00
Paku 2.0750 kg 16,000.00 33,200.00
Pekerja 1.3700 hr 78,700.00 107,819.00
Tukang kayu 3.2685 hr 94,500.00 308,873.25
Mandor 0.2245 hr 131,200.00 29,454.40
JUMLAH 1,639,646.05
DIBULATKAN 1,639,646.00
BT18 1 m2 - Perancah kayu / stoot werk - tinggi s/d 2 m
Kayu Kaso terentang 5/7-400 cm 0.0608 m3 3,205,700.00 194,906.56
Paku 0.3000 kg 16,000.00 4,800.00
Pekerja 0.6000 hr 78,700.00 47,220.00
Tukang kayu 0.4200 hr 94,500.00 39,690.00
Mandor 0.0300 hr 131,200.00 3,936.00
JUMLAH 290,552.56
DIBULATKAN 290,552.00
BT19 1 m2 - Perancah kayu / stoot werk - tinggi s/d 3 m
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
DIBULATKAN 4,984,477.00
BT29 1 m3 - Sloof beton 15/20 K.225
Adukan beton K.225 ( konvensional ) 1.0000 m3 1,464,032.00 1,464,032.00
Pembesian besi polos 187.1111 kg 12,216.00 2,285,749.33
Bekisting balok struktur 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 5,071,346.33
DIBULATKAN 5,071,346.00
BT30 1 m3 - Kolom beton 30/30 K-225
Adukan beton K-225 (ready-mix) 1.0000 m3 977,825.00 977,825.00
Pembesian 213.0000 kg 12,216.00 2,602,008.00
Bekisting Kolom 1.0000 m3 1,779,205.00 1,779,205.00
JUMLAH 5,359,038.00
DIBULATKAN 5,359,038.00
BT31 1 m3 - Kolom beton 25/35 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian besi polos 179.0000 kg 12,216.00 2,186,664.00
Bekisting kolom 1.0000 m3 1,779,205.00 1,779,205.00
JUMLAH 4,943,694.00
DIBULATKAN 4,943,694.00
BT32 1 m3 - Kolom beton 25/25 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian besi polos 155.0000 kg 12,216.00 1,893,480.00
Bekisting kolom 1.0000 m3 1,779,205.00 1,779,205.00
JUMLAH 4,650,510.00
DIBULATKAN 4,650,510.00
BT33 1 m3 - Kolom beton 25/25 K.250
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian besi ulir 260.0000 kg 12,216.00 3,176,160.00
Bekisting kolom 1.0000 m3 1,779,205.00 1,779,205.00
JUMLAH 5,933,190.00
DIBULATKAN 5,933,190.00
BT34 1 m3 - Kolom beton 20/20 K.225 ( K3)
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian besi ulir 170.0000 kg 12,216.00 2,076,720.00
Bekisting kolom 1.0000 m3 1,779,205.00 1,779,205.00
JUMLAH 4,833,750.00
DIBULATKAN 4,833,750.00
BT35 1 m3 - Kolom beton 15/30 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian besi polos 173.0000 kg 12,216.00 2,113,368.00
Bekisting kolom 1.0000 m3 1,779,205.00 1,779,205.00
JUMLAH 4,870,398.00
DIBULATKAN 4,870,398.00
BT36 1 m3 - Kolom beton 15/20 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian besi polos 187.1111 kg 12,216.00 2,285,749.20
Bekisting kolom 1.0000 m3 1,779,205.00 1,779,205.00
JUMLAH 5,042,779.20
DIBULATKAN 5,042,779.00
BT37 1 m3 - Kolom beton 15/40 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian besi ulir 180.0000 kg 12,216.00 2,198,880.00
Bekisting kolom 1.0000 m3 1,779,205.00 1,779,205.00
JUMLAH 4,955,910.00
DIBULATKAN 4,955,910.00
BT38 1 m3 - Kolom beton 12/30 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian besi ulir 170.0000 kg 12,216.00 2,076,720.00
Bekisting kolom 1.0000 m3 1,779,205.00 1,779,205.00
JUMLAH 4,833,750.00
DIBULATKAN 4,833,750.00
BT39 1 m3 - Kolom beton 12/30 K.250
Adukan beton K-225 (ready-mixl) 1.0000 m3 977,825.00 977,825.00
Pembesian besi ulir 170.0000 kg 12,216.00 2,076,720.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
JUMLAH 6,346,815.81
DIBULATKAN 6,346,815.00
BT49 1 m3 - Balok beton 25/60 K.250
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian besi ulir 150.0000 kg 12,216.00 1,832,400.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6675 m2 522,866.00 871,879.05
Bekisting balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 5,003,669.06
DIBULATKAN 5,003,669.00
BT50 1 m3 - Balok beton 25/65 K.250
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian besi ulir 230.0000 kg 12,216.00 2,809,680.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6675 m2 522,866.00 871,879.05
Bekisting balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 5,980,949.06
DIBULATKAN 5,980,949.00
BT51 1 m3 - Balok beton 20/50 K-225
Adukan beton K-225 (ready-mix) 1.0000 m3 977,825.00 977,825.00
Pembesian 175.1652 kg 12,216.00 2,139,818.08
Perancah kayu / stoot werk - tinggi s/d 4 m 1.6675 m2 522,866.00 871,879.05
Bekisting balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 5,311,087.14
DIBULATKAN 5,311,087.00
BT52 1 m3 - Balok beton 20/40 K-225
Adukan beton K-225 (ready-mix) 1.0000 m3 977,825.00 977,825.00
Pembesian 205.6215 kg 12,216.00 2,511,872.24
Perancah kayu / stoot werk - tinggi s/d 4 m 1.6675 m2 522,866.00 871,879.05
Bekisting balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 5,683,141.30
DIBULATKAN 5,683,141.00
BT53 1 m3 - Balok beton 20/35 K-225
Adukan beton K-225 (ready-mix) 1.0000 m3 977,825.00 977,825.00
Pembesian 180.0000 kg 12,216.00 2,198,880.00
Perancah kayu / stoot werk - tinggi s/d 4 m 1.6675 m2 522,866.00 871,879.05
Bekisting Balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 5,370,149.06
DIBULATKAN 5,370,149.00
BT54 1 m3 - Balok beton 20/30 K-225
Adukan beton K-225 (ready-mix) 1.0000 m3 977,825.00 977,825.00
Pembesian 180.2920 kg 12,216.00 2,202,447.07
Perancah kayu / stoot werk - tinggi s/d 4 m 1.6675 m2 522,866.00 871,879.05
Bekisting Balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 5,373,716.13
DIBULATKAN 5,373,716.00
BT55 1 m3 - Balok beton 15/25 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian 180.5556 kg 12,216.00 2,205,667.21
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6675 m2 522,866.00 871,879.05
Bekisting balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 5,376,936.26
DIBULATKAN 5,376,936.00
BT56 1 m3 - Balok beton 15/30 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian 196.2427 kg 12,216.00 2,397,300.42
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6675 m2 522,866.00 871,879.05
Bekisting balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 5,568,569.47
DIBULATKAN 5,568,569.00
BT57 1 m3 - Balok beton 15/60 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian 120.0000 kg 12,216.00 1,465,920.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6665 m2 522,866.00 871,356.19
Bekisting balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 4,636,666.19
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
DIBULATKAN 4,636,666.00
BT58 1 m3 - Balok beton 12/60 K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian 120.0000 kg 12,216.00 1,465,920.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6665 m2 522,866.00 871,356.19
Bekisting balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 4,636,666.19
DIBULATKAN 4,636,666.00
BT59 1 m3 - Balok beton 12/60 K.250
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian 120.0000 kg 12,216.00 1,465,920.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.6665 m2 522,866.00 871,356.19
Bekisting balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 4,636,666.19
DIBULATKAN 4,636,666.00
BT60 1 m3 - Ring balok beton 13/20 - K. 175 (site mix)
Adukan beton K-225 (site-mix) 1.0000 m3 1,464,032.00 1,464,032.00
Pembesian 157.4200 kg 12,216.00 1,923,042.72
Bekisting Balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 4,708,639.72
DIBULATKAN 4,708,639.00
BT61 1 m3 - Ring balok beton 13/13 K-175 (site mix)
Adukan beton K-175 (site-mix) 1.0000 m3 1,284,654.00 1,284,654.00
Pembesian besi ulir 155.0000 kg 12,216.00 1,893,480.00
Bekisting Balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 4,499,699.00
DIBULATKAN 4,499,699.00
BT62 1 m3 - Ring balok beton 15/25 K-175 (site mix)
Adukan beton K-175 (site-mix) 1.0000 m3 1,284,654.00 1,284,654.00
Pembesian besi ulir 160.0000 kg 12,216.00 1,954,560.00
Bekisting Balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 4,560,779.00
DIBULATKAN 4,560,779.00
BT63 1 m3 - Ring balok beton 25/35 K-225 (ready mix)
Adukan beton K-225 (ready-mix) 1.0000 m3 977,825.00 977,825.00
Pembesian besi ulir 160.0000 kg 12,216.00 1,954,560.00
Perancah kayu / stoot werk - tinggi s / d 4 m 2.8575 m2 522,866.00 1,494,089.60
Bekisting Balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 5,748,039.60
DIBULATKAN 5,748,039.00
BT64 1 m3 - Plat lantai & tangga beton K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian 198.4100 kg 12,216.00 2,423,776.56
Perancah kayu / stoot werk - tinggi s / d 4 m 8.3333 m2 522,866.00 4,357,199.24
Bekisting plat lantai 1.0000 m3 1,639,646.00 1,639,646.00
JUMLAH 9,398,446.80
DIBULATKAN 9,398,446.00
BT65 1 m3 - Plat lantai & tangga beton K.250
Adukan beton K.250 ( ready - mix ) 1.0000 m3 994,225.00 994,225.00
Pembesian 198.4100 kg 12,216.00 2,423,776.56
Perancah kayu / stoot werk - tinggi s / d 4 m 8.3333 m2 522,866.00 4,357,199.24
Bekisting plat lantai 1.0000 m3 1,639,646.00 1,639,646.00
JUMLAH 9,414,846.80
DIBULATKAN 9,414,846.00
BT66 1 m3 - Plat listplank beton K.225
Adukan beton K.225 ( ready - mix ) 1.0000 m3 977,825.00 977,825.00
Pembesian 100.0000 kg 12,216.00 1,221,600.00
Perancah kayu / stoot werk - tinggi s / d 4 m 1.0000 m2 522,866.00 522,866.00
Bekisting balok 1.0000 m3 1,321,565.00 1,321,565.00
JUMLAH 4,043,856.00
DIBULATKAN 4,043,856.00
BT67 1 m3 - Plat listplank beton K.250
Adukan beton K.250 ( ready - mix ) 1.0000 m3 994,225.00 994,225.00
Pembesian 100.0000 kg 12,216.00 1,221,600.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
JUMLAH 29,771.40
DIBULATKAN 29,771.00
PA17 1 m2 - Alumunium foil + Roofmesh
Alumunium foil 1.0500 m2 19,900.00 20,895.00
Roofmesh 1.0500 m2 29,600.00 31,080.00
Pekerja 0.0330 hr 78,700.00 2,597.10
Tukang kayu 0.0330 hr 94,500.00 3,118.50
Mandor 0.0050 hr 131,200.00 656.00
JUMLAH 58,346.60
DIBULATKAN 58,346.00
PA18 1 m1 - Talang datar
Papan kayu meranti Oven 0.0096 m3 2,420,000.00 23,232.00
Plat seng 0.5000 m1 55,300.00 27,650.00
Paku 0.0150 kg 16,000.00 240.00
Pekerja 0.0500 hr 78,700.00 3,935.00
Tukang kayu 0.1200 hr 94,500.00 11,340.00
Mandor 0.0120 hr 131,200.00 1,574.40
JUMLAH 67,971.40
DIBULATKAN 67,971.00
PA19 1 m2 - Pasangan Atap Zincalume + Alumunium Foil + Roofmesh
Atap Zincalume 1.0000 m2 84,100.00 84,100.00
Alumunium Foil 1.0500 m2 19,900.00 20,895.00
Roofmesh 1.0500 m2 29,600.00 31,080.00
Paku Pengikat Atap metal/zincalume 0.1750 kg 16,000.00 2,800.00
Sealent 0.0650 tube 17,200.00 1,118.00
Pekerja 0.0695 hr 78,700.00 5,469.65
Tukang kayu 0.1225 hr 94,500.00 11,576.25
Mandor 0.0067 hr 131,200.00 879.04
JUMLAH 157,917.94
DIBULATKAN 157,917.00
PA20 1 m2 - Pasangan Atap Metal berpasir cutting + Alumunium Foil + Roofmesh
Atap Metal berpasir tebal 0,3 mm cutting 1.3000 lbr 126,600.00 164,580.00
Alumunium Foil 1.0500 m2 19,900.00 20,895.00
Roofmesh 1.0500 m2 29,600.00 31,080.00
Paku Pengikat Atap metal/zincalume 0.1200 kg 16,000.00 1,920.00
Pekerja 0.1400 hr 78,700.00 11,018.00
Tukang kayu 0.1000 hr 94,500.00 9,450.00
Kepala Tukang kayu 0.0080 hr 105,000.00 840.00
Mandor 0.0080 hr 131,200.00 1,049.60
JUMLAH 240,832.60
DIBULATKAN 240,832.00
PA21 1 m2 - Pasangan Atap Metal berpasir cutting
Atap Metal berpasir tebal 0,3 mm cutting 1.3000 lbr 45,100.00 58,630.00
Paku Pengikat Atap metal/zincalume 0.1200 kg 16,000.00 1,920.00
Pekerja 0.1400 hr 78,700.00 11,018.00
Tukang kayu 0.1000 hr 94,500.00 9,450.00
Kepala Tukang kayu 0.0080 hr 105,000.00 840.00
Mandor 0.0080 hr 131,200.00 1,049.60
JUMLAH 82,907.60
DIBULATKAN 82,907.00
PA23 1 m1 - Pasangan Nok Zincalume
Nok Zincalume 1.1000 lbr 45,100.00 49,610.00
Paku Pengikat Atap metal/zincalume 0.1200 kg 16,000.00 1,920.00
Pekerja 0.1400 hr 78,700.00 11,018.00
Tukang kayu 0.1000 hr 94,500.00 9,450.00
Kepala Tukang kayu 0.0080 hr 105,000.00 840.00
Mandor 0.0080 hr 131,200.00 1,049.60
JUMLAH 73,887.60
DIBULATKAN 73,887.00
PEKERJAAN KAYU
KY01 1 m3 - Kusen kayu kamper samarinda oven
Kayu balok kamper samarinda Oven 1.1000 m3 9,597,500.00 10,557,250.00
Paku 3.0000 kg 16,000.00 48,000.00
Angkur 10.5600 kg 12,500.00 132,000.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
PEKERJAAN PARTISI
JUMLAH 2,394,527.00
DIBULATKAN 2,394,527.00
ST04 1 bh - Wastafel
Wastafel + Accesoris 1.0000 bh 1,500,000.00 1,500,000.00
Pekerja 0.3000 hr 78,700.00 23,610.00
Tukang batu 0.2500 hr 94,500.00 23,625.00
Mandor 0.1800 hr 131,200.00 23,616.00
JUMLAH 1,570,851.00
DIBULATKAN 1,570,851.00
ST05 1 bh - Kitchen Zink
Kitchen Zink 1.0000 bh 250,000.00 250,000.00
Pekerja 0.3000 hr 78,700.00 23,610.00
Tukang batu 0.2500 hr 94,500.00 23,625.00
Mandor 0.1800 hr 131,200.00 23,616.00
JUMLAH 320,851.00
DIBULATKAN 320,851.00
ST07 1 bh - Floor drain
Floor drain stainless 1.0000 bh 174,000.00 174,000.00
Pekerja 0.0100 hr 78,700.00 787.00
Tukang batu 0.1000 hr 94,500.00 9,450.00
Mandor 0.0050 hr 131,200.00 656.00
JUMLAH 184,893.00
DIBULATKAN 184,893.00
ST08 1 bh - Shower
Shower 1.0000 bh 303,000.00 303,000.00
Pekerja 0.0100 hr 78,700.00 787.00
Tukang batu 0.1000 hr 94,500.00 9,450.00
Mandor 0.0050 hr 131,200.00 656.00
JUMLAH 313,893.00
DIBULATKAN 313,893.00
ST09 1 bh - Kran leher angsa 1/2"
Kran air leher angsa 1/2 1.0000 bh 288,200.00 288,200.00
Seal tape 0.0250 roll 2,600.00 65.00
Lem pipa PVC 0.1250 tube 14,300.00 1,787.50
Pekerja 0.0100 hr 78,700.00 787.00
Tukang batu 0.1000 hr 94,500.00 9,450.00
Mandor 0.0050 hr 131,200.00 656.00
JUMLAH 300,945.50
DIBULATKAN 300,945.00
ST10 1 bh - Kran air 1/2"
Kran air 1/2 1.0000 bh 25,000.00 25,000.00
Seal tape 0.0250 roll 2,600.00 65.00
Lem pipa PVC 0.1250 tube 14,300.00 1,787.50
Pekerja 0.0100 hr 78,700.00 787.00
Tukang batu 0.1000 hr 94,500.00 9,450.00
Mandor 0.0050 hr 131,200.00 656.00
JUMLAH 37,745.50
DIBULATKAN 37,745.00
ST11 1 unit - Pompa air jet pump + Instalasi dan pengeboran
Pompa air jet pump 1.0000 bh 1,991,200.00 1,991,200.00
Pipa PVC 1 " 40.0000 m1 9,200.00 368,000.00
Pipa PVC 4 " 16.0000 m1 10,312.00 164,992.00
Bocht LL-D 1" (lokal) 6.0000 bh 25,100.00 150,600.00
Water moer 2.0000 bh 60,500.00 121,000.00
Ongkos pengeboran 1.0000 ls 1,300,000.00 1,300,000.00
JUMLAH 4,095,792.00
DIBULATKAN 4,095,792.00
ST11 1 unit - Pompa air jet pump tanpa pengeboran
Pompa air jet pump 1.0000 bh 1,991,200.00 1,991,200.00
Ongkos pasang 1.0000 ls 75,000.00 75,000.00
JUMLAH 2,066,200.00
DIBULATKAN 2,066,200.00
ST12 1 unit - Water tower rangka besi siku
Konstruksi besi siku 210.0000 kg 14,300.00 3,003,000.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
JUMLAH 37,593.00
DIBULATKAN 37,593.00
AS03 1 bh - Pasang hak angin
Hak angin 1.0000 bh 14,100.00 14,100.00
Pekerja 0.0100 hr 78,700.00 787.00
Tukang kayu 0.1000 hr 94,500.00 9,450.00
Mandor 0.0050 hr 131,200.00 656.00
JUMLAH 24,993.00
DIBULATKAN 24,993.00
AS04 1 bh - Pasang slot jendela
Slot jendela 1.0000 bh 91,600.00 91,600.00
Pekerja 0.0100 hr 78,700.00 787.00
Tukang kayu 0.1000 hr 94,500.00 9,450.00
Mandor 0.0050 hr 131,200.00 656.00
JUMLAH 102,493.00
DIBULATKAN 102,493.00
AS05 1 bh - Pasang kunci double slaag (SOLID)
Kunci double slaag (SOLID) 1.0000 bh 292,700.00 292,700.00
Pekerja 0.0500 hr 78,700.00 3,935.00
Tukang kayu 0.2500 hr 94,500.00 23,625.00
Mandor 0.0100 hr 131,200.00 1,312.00
JUMLAH 321,572.00
DIBULATKAN 321,572.00
AS06 1 bh - Pasang Grendel pintu
Grendel Pintu 1.0000 bh 40,800.00 40,800.00
Pekerja 0.0100 hr 78,700.00 787.00
Tukang kayu 0.1000 hr 94,500.00 9,450.00
Mandor 0.0050 hr 131,200.00 656.00
JUMLAH 51,693.00
DIBULATKAN 51,693.00
PEKERJAAN SARANA LUAR
SL01 1 m1 - Saluran buis beton 1/2 dia. 20 cm tanpa tulangan
Buis beton 1/2 dia. 20 cm 1.0250 m1 65,300.00 66,932.50
Pasir urug 0.1200 m3 225,000.00 27,000.00
Pasir pasang 0.0540 m3 279,800.00 15,109.20
Semen PC ( 50 kg ) 0.0270 zak 79,000.00 2,133.00
Pekerja 0.0750 hr 78,700.00 5,902.50
Tukang batu 0.0500 hr 94,500.00 4,725.00
Mandor 0.0125 hr 131,200.00 1,640.00
JUMLAH 123,442.20
DIBULATKAN 123,442.00
SL02 1 m1 - Saluran tertutup buis beton dia. 30 cm tanpa tulangan
Buis beton dia. 30 cm 1.0250 m1 125,400.00 128,535.00
Pasir urug 0.1200 m3 225,000.00 27,000.00
Pasir pasang 0.0540 m3 279,800.00 15,109.20
Semen PC ( 50 kg ) 0.0270 zak 79,000.00 2,133.00
Pekerja 0.0750 hr 78,700.00 5,902.50
Tukang batu 0.0500 hr 94,500.00 4,725.00
Mandor 0.0125 hr 131,200.00 1,640.00
JUMLAH 185,044.70
DIBULATKAN 185,044.00
SL03 1 m2 - Paving block t = 6 cm
Paving block t = 6 cm K.250 1.0250 m2 81,400.00 83,435.00
Abu batu 0.0250 m3 279,800.00 6,995.00
Pekerja 0.1500 hr 78,700.00 11,805.00
Tukang batu 0.0500 hr 94,500.00 4,725.00
Mandor 0.0030 hr 131,200.00 393.60
JUMLAH 107,353.60
DIBULATKAN 107,353.00
SL04 1 m2 - Paving block t = 8 cm
Paving block t = 8 cm K.250 1.0250 m2 103,900.00 106,497.50
Abu batu 0.0250 m3 279,800.00 6,995.00
Pekerja 0.1500 hr 78,700.00 11,805.00
Tukang batu 0.0500 hr 94,500.00 4,725.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
DIBULATKAN 1,428,903.00
PJ13 1 unit - Jendela J1 (Kelurahan)
Kusen Alumunium warna ukuran 4" x 1 3/4" 4.4000 m1 106,900.00 470,360.00
Frame Daun jendela 4.0000 m1 176,000.00 704,000.00
Pasangan kaca polos, t= 5 mm 0.6500 m2 112,700.00 73,255.00
Engsel jendela casemen 16" 1.0000 set 100,100.00 100,100.00
Karet dan sealent 4.0000 m1 5,500.00 22,000.00
Fisher 4.0000 bh 1,200.00 4,800.00
ramp buncis 1.0000 bh 27,700.00 27,700.00
Upah potong kaca 0.6500 m2 52,200.00 33,930.00
Upah pasang + aksesories 1.0000 unit 166,200.00 166,200.00
JUMLAH 1,602,345.00
DIBULATKAN 1,602,345.00
PJ16 1 unit - Jendela J4 (Kelurahan)
Kusen Alumunium warna ukuran 4" x 1 3/4" 2.2000 m1 106,900.00 235,180.00
Kaca Es 5mm 0.3000 m2 112,700.00 33,810.00
Upah potong kaca 0.3000 m2 52,200.00 15,660.00
Upah pasang + aksesories 1.0000 unit 166,200.00 166,200.00
JUMLAH 450,850.00
DIBULATKAN 450,850.00
PJ17 1 unit - Jendela J4a (Kelurahan)
Kusen Alumunium warna ukuran 4" x 1 3/4" 2.0000 m1 106,900.00 213,800.00
Kaca Es 5mm 0.2600 m2 112,700.00 29,302.00
Upah potong kaca 0.2600 m2 52,200.00 13,572.00
Upah pasang + aksesories 1.0000 unit 166,200.00 166,200.00
JUMLAH 422,874.00
DIBULATKAN 422,874.00
PJ18 1 unit - Jendela J2 (UPTD)
Kusen Alumunium warna ukuran 4" x 1 3/4" 32.3000 m1 106,900.00 3,452,870.00
Frame Daun jendela 22.5000 m1 176,000.00 3,960,000.00
Engsel jendela casemen 16" 5.0000 set 100,100.00 500,500.00
Karet dan sealent 20.0000 m1 5,500.00 110,000.00
Kaca Reflektif 8.8900 m2 522,800.00 4,647,692.00
Fisher 10.0000 bh 1,200.00 12,000.00
ramp buncis 5.0000 bh 27,700.00 138,500.00
Upah potong kaca 8.8900 m2 52,200.00 464,058.00
Upah pasang + aksesories 1.0000 unit 166,200.00 166,200.00
JUMLAH 13,451,820.00
DIBULATKAN 13,451,820.00
PJ18 1 unit - Jendela J2a (UPTD)
Kusen Alumunium warna ukuran 4" x 1 3/4" 41.2000 m1 106,900.00 4,404,280.00
Frame Daun jendela 27.0000 m1 176,000.00 4,752,000.00
Engsel jendela casemen 16" 6.0000 set 100,100.00 600,600.00
Karet dan sealent 20.0000 m1 5,500.00 110,000.00
Kaca Reflektif 11.6600 m2 522,800.00 6,095,848.00
Fisher 10.0000 bh 1,200.00 12,000.00
ramp buncis 6.0000 bh 27,700.00 166,200.00
Upah potong kaca 11.6600 m2 52,200.00 608,652.00
Upah pasang + aksesories 1.0000 unit 166,200.00 166,200.00
JUMLAH 16,915,780.00
DIBULATKAN 16,915,780.00
PJ19 1 unit - Jendela J3 (UPTD)
Kusen Alumunium warna ukuran 4" x 1 3/4" 15.6000 m1 106,900.00 1,667,640.00
Pasangan kaca reflektif, t= 8 mm 6.3600 m2 522,800.00 3,325,008.00
Karet dan sealent 10.2000 m1 5,500.00 56,100.00
Fisher 6.0000 bh 1,200.00 7,200.00
Upah potong kaca 6.3600 m2 52,200.00 331,992.00
Upah pasang + aksesories 1.0000 unit 166,200.00 166,200.00
JUMLAH 5,554,140.00
DIBULATKAN 5,554,140.00
1 Unit - Jalusi Alumunium
Kusen Alumunium warna ukuran 4" x 1 3/4" 5.60 m' 106,900.00 598,640.00
kisi-kisi aluminium 16.77 m' 55,000.00 922,350.00
Karet dan silent 5.60 m' 5,500.00 30,800.00
Fisher 8.00 bh 1,200.00 9,600.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
#REF!
#REF!
#REF!
###
###
###
###
###
###
#REF! ###
#REF!
DAFTAR HARGA
UPAH DAN BAHAN / MATERIAL
1 2 3 4
I PASIR DAN BATU
Abu Batu/Screening 5 mm 264,300.00 m3
Batu Belah Pondasi 265,800.00 m3
Batu Pecah/Split ukr. 2 - 3 cm 278,300.00 m3
Batu Pecah/Split ukr. 3 - 4 cm 278,300.00 m3
Macadam/Steel Slag ukr. 5 - 7 cm 242,000.00 m3
Batu Tempel Hitam 148,500.00 m2
Koral Beton 247,900.00 m3
Pasir Beton 301,000.00 m3
Pasir pasang 279,800.00 m3
Pasir urug darat 225,000.00 m3
Sirtu 250,200.00 m3
Tanah Merah 145,000.00 m3
-
II PAVING BLOCK
Kastin Abu-abu ukr. 10.20.40 K 250 30,700.00 m1
Paving Block K 250 Tebal 6 Abu-abu 81,400.00 m2
Paving Block K 250 Tebal 8 Abu-abu 103,900.00 m2
Paving Block K 350 Tebal 6 Abu-abu 95,700.00 m2
Paving Block K 350 Tebal 8 Abu-abu 110,100.00 m2
Grass Blok tebal 6 (spek) 118,000.00 m2
-
III PAGAR PRECAST
pagar panel uk, 5x40x240, mutu beton K225 125,000.00 bh
Tiang pagar uk, 16x18x275, mutu beton K225 270,000.00 bh
Tiang pagar uk, 16x18x340, mutu beton K225 326,000.00 bh
-
IV SEMEN DAN KAPUR
Bata merah 400.00 bh
Bata Ringan / Hebel 9,200.00 bh
Rooster Beton 20 x 20 x 7 cm 8,300.00 bh
Glass block 23,300.00 bh
Semen Tiga Roda 50 kg 79,000.00 zak
Semen Warna 20,900.00 kg
Semen Instan (mortar) 116,400.00 zak
Compound Jaya (20 Kg) 70,200.00 zak
-
V KAYU & PLAFOND
Kaso kayu Meranti Jambi/Palembang - 400 cm 3,205,700.00 m3
Balok Kayu Meranti Jambi/palembang - 400 cm 3,787,900.00 m3
Papan Kayu Terentang - 400 cm 2,420,000.00 m3
Dolken Ø 8 - 10 cm ukr. 350 - 400 cm 27,700.00 btg
List Gypsum 7 cm 19,200.00 m1
List Gypsum 10 cm 23,200.00 m1
List profil kamper 5 Cm 60,500.00 m1
Balok Kayu Kamper Samarinda Oven : 6x15x400 cm 9,597,500.00 m3
Papan Kayu Kamper Samarinda Oven : 3x30x400 cm 10,532,500.00 m3
Daun Pintu Kayu Kamper Samarinda (Bukan Oven) 1,900,000.00 Unit
Daun Pintu Kayu Kamper Samarinda Kualitas Export (Oven) 2,430,000.00 Unit
Bahan plafond hardplex 5 mm 120x240 79,000.00 lbr
Formika ukr. 122 x 244 x 3 mm 121,600.00 lbr
Kusen dan Daun Pintu PVC ukuran standar 237,800.00 Unit
Multiplek ukr. 122 x 244 x 9 mm 143,400.00 lbr
Teakwood ukr. 122 x 244 x 4 mm 102,800.00 lbr
NO. NAMA BAHAN/MATERIAL HARGA SATUAN SATUAN
1 2 3 4
Triplek ukr. 122 x 244 x 4 mm 70,900.00 lbr
Gypsum Jaya 9 mm (122 mm x 244 mm) 74,900.00 lbr
GRC Board t = 4 mm 87,000.00 lbr
Kassa Gypsum / Textille 5,500.00 rol
Plafon Gyptile terpasang 123,200.00 m2
Bambu Ø 8 - 10 Cm Panjang = 5 - 6 M 20,000.00 btg
Galpanis 4x4 tbl = 1,6 mm 160,000.00 btg
Galpanis 5x5 tbl = 1,6 mm 190,000.00 btg
Besi galpanis Ø 2 inch 75,000.00 m1
Besi tempa 16 mm 150,000.00 btg
Zincromate 1,000.00 m2
-
VI READYMIX
Readymix beton K-225 tanpa pompa 891,000.00 m3
Readymix beton K-250 tanpa pompa 907,400.00 m3
Readymix beton K-300 tanpa pompa 952,800.00 m3
VII BETON
Buis Beton -
Buis Beton Ukuran .Ø 20 cm tanpa tulangan panjang 1,00 m Lokal 114,500.00 m1
Buis Beton Ukuran .Ø 30 cm tanpa tulangan panjang 1,00 m lokal 125,400.00 m1
Buis Beton Ukuran .1/2 Ø 20 cm tanpa tulangan panjang 1,00 m lokal 65,300.00 btg
Buis Beton Ukuran .1/2 Ø 30 cm tanpa tulangan panjang 1,00 m lokal 75,400.00 btg
-
VIII CAT
Amplas Kayu 3,400.00 lbr
Ampelas Besi 5,000.00 lbr
Cat minyak setara F Talit 59,100.00 kg
Cat tembok Dulux/ICI interior 45,900.00 kg
Cat tembok Dulux/ICI exterior 73,600.00 kg
Cat dasar setara Dulux/ICI 51,500.00 kg
Lem Putih 15,100.00 Kg
Dempul plitur 43,000.00 kg
Ijuk 7,600.00 ikat
Kwas 3" 13,700.00 bh
Melamik 59,800.00 kg
Meni setara Nippon 41,800.00 kg
Minyak Cat/Tinner 23,200.00 ltr
Pelamir Tembok 26,700.00 kg
Pelitur 52,900.00 kg
Rool cat tembok 25,900.00 bh
Vernis Bee Brand 66 (kayu/besi) 40,000.00 ltr
Aquaproof 49,600.00 kg
-
IX LANTAI
Ubin Keramik Ukr. 20x20 Standar KW 1 72,700.00 m2
Ubin Keramik Ukr. 20x25 Standar KW1 72,100.00 m2
Ubin Keramik Ukr. 30x30 Standar KW 1 61,200.00 m2
Ubin Keramik Ukr. 40x40 Standar KW 1 72,200.00 m2
Step noising Keramik 10 x 30 23,400.00 bh
-
X ALAT PENGUNCI
Engsel Pintu Nilon ukuran 3" 26,700.00 ps
Engsel Pintu Nilon ukuran 4" 40,100.00 ps
Engsel Jendela Casemen 16 " 100,100.00 set
Dyna Bolt 1,500.00 bh
Kunci KM / WC 35,000.00 bh
Kait Angin 29,200.00 bh
NO. NAMA BAHAN/MATERIAL HARGA SATUAN SATUAN
1 2 3 4
Hak Angin 14,100.00 bh
Grendel tanam pintu 91,600.00 bh
Kunci pintu setara Solid 292,700.00 bh
Kunci Gembok 50,000.00 bh
Grendel Ukuran 4" setara Solid 40,800.00 bh
Handel pintu 135,000.00 set
-
XI SANITASI AIR
Closet Duduk 2,595,700.00 bh
Closet Jongkok setara TOTO 236,400.00 bh
Urinoir 2,326,300.00 bh
Shower 303,000.00 bh
Kitchen zinck 265,400.00 bh
Kran leher angsa 288,200.00 bh
Kran Air TOTO 1/2" 219,200.00 bh
Floor Drain Stainless 174,000.00 bh
Roofdrain 117,700.00 bh
Sealtape 2,600.00 bh
Lem Pipa PVC 14,300.00 tube
Pompa jetpump 1,991,200.00 unit
Bocht LL-D 1" (lokal) 25,100.00 bh
Water moer 60,500.00 bh
Ongkos pengeboran 1,300,000.00 ls
Konstruksi besi siku 14,300.00 kg
Besi siku L.40.40.4 16,100.00 kg
Tangki air kapasitas 1 m3 1,727,700.00 bh
Pipa Galv Medium dia 1/2 inch ; P : 6 m (SNI ) 172,500.00 btg
Pipa Galv Medium dia 1/2 inch (SNI ) 28,700.00 m'
Pipa Galv Medium dia 3/4 inch ; P : 6 m (SNI/SII ) 191,000.00 btg
Pipa Galv Medium dia 3/4 inch (SNI/SII ) 31,800.00 m'
Pipa Galv Medium dia 1 inch P : 6 m (2,95 mm) (SNI) 302,300.00 btg
Pipa Galv Medium dia 1 inch (2,95 mm) (SNI) 50,300.00 m'
Pipa Galv Medium dia 1-1/4 inch P : 6 m (3,65 mm) (SNI) 384,800.00 btg
Pipa Galv Medium dia 1-1/4 inch (3,65 mm) (SNI) 64,100.00 m'
Pipa Galv Medium dia 1-1/2 inch P : 6 m (3 mm) (SNI) 412,300.00 btg
Pipa Galv Medium dia 1-1/2 inch (3 mm) (SNI) 68,700.00 m'
Pipa Galv Medium dia 2 inch P : 6 m (3,2 mm) (SNI) 498,800.00 btg
Pipa Galv Medium dia 2 inch (3,2 mm) (SNI) 83,100.00 m'
-
PIPA PVC Wavin Standard -
Pipa PVC dia. 1/2 inch type AW, tebal 22 mm, panjang 4 m 20,200.00 btg
Pipa PVC dia. 1/2 inch type AW, tebal 22 mm 5,000.00 m'
Pipa PVC dia. 3/4 inch type AW, tebal 26 mm, panjang 4 m 27,400.00 btg
Pipa PVC dia. 3/4 inch type AW, tebal 26 mm 6,800.00 m'
Pipa PVC dia. 1 inch type AW, panjang 4 m 37,100.00 btg
Pipa PVC dia. 1 inch type AW 9,200.00 m'
Pipa PVC dia. 2 inch type AW, panjang 4 m 76,700.00 btg
Pipa PVC dia. 2 inch type AW 19,100.00 m'
Pipa PVC dia. 3 inch type AW, panjang 4 m 148,500.00 btg
Pipa PVC dia. 3 inch type AW 37,100.00 m'
Pipa PVC dia. 4 inch type D, panjang 4 m 140,300.00 btg
Pipa PVC dia. 4 inch type D 35,000.00 m'
Knee 1/2" 2,400.00 Bh
Knee 3/4" 3,200.00 Bh
Knee 1" 6,800.00 Bh
Knee 2" 10,800.00 Bh
Knee 3" 15,200.00 Bh
Knee 4" 22,000.00 Bh
-
NO. NAMA BAHAN/MATERIAL HARGA SATUAN SATUAN
1 2 3 4
XII ATAP
Alumunium Foil 19,900.00 m2
Glasswool 23,800.00 roll
Roofmesh 29,600.00 m2
-
Fiber / Asbes semen gelombang 180x108x0,5 cm 60,900.00 lbr
Zinc Alume (Bahan) Gelombang Besar 84,100.00 m2
-
Genteng Metal Setara rainbow 126,600.00 Lembar
Nok 45,100.00 m1
-
Kusen Alumunium Natural Ukuran 3" x 1 1/2" 101,200.00 m1
Kusen Alumunium Natural Ukuran 4" x 1 3/4" 106,900.00 m1
Jalusi Alumunium Warna 55,000.00 m1
Frame daun Jendela Alumunium 176,000.00 m1
-
Seng gelombang 180 x 90 x 0,20 55,300.00 lbr
Sealent 17,200.00 tube
Karet List 5,500.00 m1
-
Perangkat Penangkal Petir - titik
Splitzer uk.2 49,500.00 bh
Kabel BC 75 mm2 24,500.00 m
Klem Kabel 3,000.00 bh
Pentanahan 918,800.00 ls
Bak kontrol 600 x 600 x 400 118,000.00 bh
Box Test 434,400.00 bh
-
RANGKA ATAP BAJA RINGAN -
Rangka atap baja ringan setara SMART TRUSS (terpasang) 173,900.00 m2
-
PLAFON -
Plafon Gyptile 60 x 60 (Material + Rangka Main Tee + Cross Tee + Terpasang) 123,200.00 m2
Plafon Acoustic Armstrong 60x60 (tebal 15 mm) + Rangka Main Tee + Cross Tee 196,400.00 m2
-
LIST PLANK -
List Plank GRC Uk.15 x 240 cm ; tebal 12 mm 35,000.00 m
List Plank GRC Uk.30 x 240 cm ; tebal 12 mm 37,500.00 m
-
XIII BAJA TULANGAN / PROFIL
Besi beton polos 8,700.00 kg
Besi beton ulir 8,700.00 kg
Baja IWF ex.DN SII 13,500.00 kg
Baja Canal C 29,500.00 kg
Besi Siku/Profil 40 x 40 x 4 15,600.00 kg
Besi Hollow 2 x 4 cm, rangka plafond 20,200.00 Batang
Besi Hollow 4 x 4 cm, rangka plafond 27,300.00 Batang
Besi Hollow 4 x 4 cm, rangka pagar 136,300.00 Batang
Besi Hollow 2 x 4 cm, rangka pagar 67,200.00 Batang
Besi Plat Strip 2 x 30 mm, (6 m) 11,200.00 kg
Besi Plat Strip 5 x 30 mm, (6 m) 13,600.00 kg
Sekrup Gypsum Merk Zolo 2 x 6" (isi 1.000 pieces) 81,600.00 dus
Besi Pipa stainless dia. 2" 80,600.00 m
Besi Pipa stainless dia. 1" 58,000.00 m
Alumunium composite 117,300.00 m2
Braket galvanis ACP 16,000.00 bh
Rangka alumunium composite (Almn. 4 0 x 40 x 2 mm ) 19,200.00 m
Skrup almunium 15,900.00 kg
-
NO. NAMA BAHAN/MATERIAL HARGA SATUAN SATUAN
1 2 3 4
XIV KAWAT
Kawat beton 18,200.00 kg
Paku segala ukuran (rata-rata) 16,000.00 kg
Wiremesh DM 8,dia.8x8,spasi 150x150mm,uk.5,4x2,1 m 636,600.00 lbr
Pagar BRC t = 1,20 m Ø 8 194,300.00 m1
Bondek 126,500.00 m2
-
XV KACA
Kaca bening 5 mm 112,700.00 m2
Kaca Es 5 mm 163,900.00 m2
Kaca Rayben 5 mm 143,700.00 m2
Kaca revlektif 522,800.00 m2
-
XVI LISTRIK
Kabel NYM 3x2.5 mm 12,900.00 m
Kabel NYY 4x35mm2 264,000.00 meter
Kabel NYY 4x16mm2 126,500.00 meter
Kabel NYY 4x10mm2 66,000.00 meter
Klem kabel 6,700.00 dus
Saklar tunggal 14,600.00 bh
Saklar double 20,200.00 bh
Saklar tukar 20,200.00 bh
Stop Kontak 15,500.00 bh
Lampu TL 2 x 18 watt, armatur, komplit philips 102,300.00 bh
Lampu SL 18 watt, komplit philips 32,600.00 bh
Lampu Halogen 50 Watt Merk : Philips/osram 500,000.00 buah
Lampu pagar 185,900.00 bh
Lampu Down Light + Isi SL 25 watt 92,000.00 bh
Fitting Keramik 16,100.00 bh
Panel PP-LP01, 40X60 cm2 750,000.00 bh
Panel PP-LP01, 60X80 cm2 950,000.00 unit
Penyambungan daya Listrik 1,500.00 watt
Lampu PLC 13 watt 65,000.00 bh
Lampu sorot LED 50 watt 550,000.00 bh
MCB 10 A 94,200.00 bh
Box MCB 4 group 27,500.00 bh
1 2 3 4
Huruf Stainles 20 cm 209,000.00 hrf
Huruf Stainles 15 cm 156,700.00 hrf
Tiang pancang 25x25 kelas C K-500 335,400.00 m'
Sambung TP kotak 25x25 kelas C 1,304,100.00 joint
Tiang pancang 25x25 214,200.00 m'
Tiang pancang 20x20 161,900.00 m'
Alat Pancang Hidraulic 80,700.00 m
Pengelasan/Penyambungan/Cutting Beton 76,000.00 ttk
roster beton 26,100.00 m3
Kusen pintu aluminium lengkap 1,306,200.00 unit
Pipa listrik panjang 4 m 9,900.00 btg
Stop kontak telpon 57,400.00 bh
Exhausfan 522,500.00 bh
Kitchen zinc 470,200.00 bh
Frameless tempered 12 mm 992,700.00 m2
Floor hings ex dexon 2,351,200.00 bh
Fitch fitting ex dexon 2,560,200.00 bh
Hendel stainless 470,200.00 bh
Pasang U aluminium 73,100.00 m1
RUMPUT -
Rumput Gajah Mini 20,900.00 m2
Rumput Manila ( Gebalan ) 15,600.00 m2
Eucaliptus Ø 4 - 7 cm, t = 1 - 3 m 99,200.00 phn
Tanaman Pucuk Merah 1 104,500.00 phn
Tanaman Krokol Three Colour 7,800.00 plbg
Tanaman Three Colour 7,800.00 plbg
Tanaman Sansivera 7,800.00 plbg
Tanaman Soka Jepang 26,100.00 plbg
Kiara Payung 133,000.00 phn
Pohon Glodogan Tiang T = 1.5m 190,000.00 phn
Papan kayu 3X10 cm 23,700.00 m1
List profil kayu 2X4 cm 11,400.00 m1
Plint kayu 1,5/10 21,300.00 m1
Besi Hollow 60 x 60 x 1,8 133,500.00 btg
Grendel besi + Kunci 128,200.00 set
Roda Besi 14,200.00 bh
Plat besi 6 mm untuk dudukan roda 11,000.00 kg
Besi Siku 40 x 40 x 4 untuk rel 15,200.00 kg
Pengelasan & Pengecatan hollow pagar 80,700.00 ls
Ongkos pasang Pagar Besi 166,200.00 ls
WLC elektrode 389,500.00 bh
Angkur 11,800.00 bh
Fisher 1,200.00 bh
ramp buncis 27,700.00 bh
Upah potong kaca 52,200.00 m2
Upah pasang + aksesories Jendela 166,200.00 unit
Pengelasan dengan argon 3,400.00 cm
Tangga Besi 1,900,000.00 bh
Meja Counter 1,757,500.00 bh
Angkur bout dia 19mm 130,600.00 bh
Baseplate tebal 10 mm 13,000.00 kg
XVIII UPAH
Pekerja / knek 78,700.00 hari
Tukang gali 89,200.00 hari
Kepala Tukang Batu 105,000.00 hari
Tukang Batu 94,500.00 hari
Kepala Tukang Kayu 105,000.00 hari
Tukang Kayu 94,500.00 hari
Kepala Tukang Besi 99,700.00 hari
NO. NAMA BAHAN/MATERIAL HARGA SATUAN SATUAN
1 2 3 4
Tukang Besi 89,200.00 hari
Kepala Tukang Cat 110,200.00 hari
Tukang Cat 94,500.00 hari
Mandor / pengawas 131,200.00 hari
Instalator / Tukang Listrik 105,000.00 hari
Pembantu Instalator 84,000.00 hari
Operator Alat Berat 110,200.00 hari
Pembantu Operator Alat Berat 84,000.00 hari