REKAPITULASI BIAYA

PEKERJAAN STRUKTUR TOWER 1


PROYEK : TOWER 1 DIBUAT : Hari
LOKASI : SERANG - BANTEN DIPERIKSA : Agus
PEMILIK : TGL : 15/04/2022
SUBJECT : REKAPITULASI REVISI : 1

No. URAIAN PEKERJAAN HARGA TOTAL HARGA

I PEKERJAAN PERSIAPAN Rp. 592.853.040.00


II PEKERJAAN SUB STRUKTUR Rp. 207.159.195.11
III PEKERJAAN PONDASI Rp. 845.370.900.29
IV PEKERJAAN STRUKTUR LT. 1 Rp. 483.221.955.32
Struktur Elv. -0.700 s/d Elv. +3.550
V PEKERJAAN STRUKTUR LT. 2 Rp. 995.558.312.40
Struktur Elv. +3.550 s/d Elv. +6.950
VI PEKERJAAN STRUKTUR LT. 3 Rp. 967.545.732.50
Struktur Elv. +6.950 s/d +11.350
VII PEKERJAAN STRUKTUR LT. 4 Rp. 955.080.498.04
Struktur Elv. +11.350 s/d +13.750
VIII PEKERJAAN STRUKTUR LT. 5 Rp. 935.939.902.81
Struktur Elv. +13.750 s/d +17.150
VIII PEKERJAAN STRUKTUR LT. DAK ATAP Rp. 921.492.217.51
Struktur Elv. +17.150 s/d +19.650
IX PEKERJAAN STRUKTUR LT. DAK ATAP TANGGA Rp. 207.512.931.09
TOTAL Rp. 7.111.734.685.07
PPN 11 % Rp 782.290.815.36
GRAND TOTAL Rp 7.894.025.500.42
RENCANA ANGGARAN BIAYA
PEKERJAAN STRUKTUR TOWER 1
PROYEK : TOWER 1 DIBUAT : Hari
LOKASI : SERANG - BANTEN DIPERIKSA : Agus
PEMILIK : 0 TGL : 15/04/2022
SUBJECT : RENCANA ANGGARAN BIAYA REVISI : 1

HARGA
No. URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME TOTAL HARGA KETERANGAN
SATUAN

I PEKERJAAN PERSIAPAN Rp 592.853.040.00

I-01 Pekerjaan Pembersihan Lokasi m2 832.00 17.415.00 14.489.280.00


I-02 Pekerjaan Gambar Kerja Ls 1.00 29.025.000.00 29.025.000.00
I-03 Pekerjaan Gambar As built Ls 1.00 29.025.000.00 29.025.000.00
I-04 Pekerjaan Pengukuran m2 832.00 17.415.00 14.489.280.00
I-05 Pekerjaan Bowplank m' 116.00 208.980.00 24.241.680.00
I-06 Mobilisasi & Demobilisasi Ls 1.00 29.025.000.00 29.025.000.00
I-07 Buang Puing Keluar Area Ls 1.00 11.610.000.00 11.610.000.00
I-08 Keamanan Ls 7.00 5.805.000.00 40.635.000.00
I-09 Pekerjaan bedeng & los kerja Ls 36.00 2.089.800.00 75.232.800.00
I-10 Management Lapangan Ls 7.00 46.440.000.00 325.080.000.00

II PEKERJAAN SUB STRUKTUR Rp 207.159.195.11

II.01 Pekerjaan Galian Pondasi beton PC1 m3 73.22 127.710.00 9.350.415.36


II.02 Pekerjaan Galian Pondasi beton PC2 m3 121.68 127.710.00 15.539.752.80
II.03 Pekerjaan Galian Pondasi beton PC3 m3 11.23 127.710.00 1.434.438.72
II.04 Pekerjaan Galian Pondasi beton PL m3 25.92 127.710.00 3.310.243.20
II.05 Pekerjaan Galian Pondasi sloof 25x40 m3 22.32 127.710.00 2.850.487.20
II.06 Pekerjaan Galian Pondasi sloof 20x40 m3 5.69 127.710.00 727.231.82
II.07 Pekerjaan Lt. kerja bawah pondasi beton PC1 m3 6.60 1.277.100.00 8.428.860.00
II.08 Pekerjaan Lt. kerja bawah pondasi beton PC2 m3 9.00 1.277.100.00 11.493.900.00
II.09 Pekerjaan Lt. kerja bawah pondasi beton PC3 m3 0.90 1.277.100.00 1.149.390.00
II.10 Pekerjaan Lt. kerja bawah pondasi beton PL m3 0.45 1.277.100.00 574.695.00
II.11 Pekerjaan Lt. kerja bawah Sloof beton 25x40 m3 3.98 1.277.100.00 5.078.388.15
II.12 Pekerjaan Lt. kerja bawah Sloof beton 20x40 m3 0.99 1.277.100.00 1.260.255.05
II.13 Pekerjaan Lt. kerja bawah Slab beton S1 m3 10.19 1.277.100.00 13.016.841.75
II.14 Pekerjaan Lt. kerja bawah Slab beton S2 m3 22.61 1.277.100.00 28.880.569.28
II.15 Pekerjaan Pasir bawah pondasi beton PC1 m3 1.10 371.520.00 408.672.00
II.16 Pekerjaan Pasir bawah pondasi beton PC2 m3 1.50 371.520.00 557.280.00
II.17 Pekerjaan Pasir bawah pondasi beton PC3 m3 0.15 371.520.00 55.728.00
II.18 Pekerjaan Pasir bawah pondasi beton PL m3 0.45 371.520.00 167.184.00
II.19 Pekerjaan Pasir bawah Sloof beton 25x40 m3 3.98 371.520.00 1.477.349.28
II.20 Pekerjaan Pasir bawah Sloof beton 20x40 m3 0.99 371.520.00 366.619.65
II.21 Pekerjaan Pasir bawah Slab beton S1 m3 10.19 371.520.00 3.786.717.60
II.22 Pekerjaan Sirtu bawah Slab beton S2 m3 22.61 371.520.00 8.401.620.15
II.23 Pekerjaan Urugan Kembali m3 177.46 89.397.00 15.864.026.88
II.24 Pekerjaan Buangan Tanah m3 82.61 60.372.00 4.987.118.41
II.25 Pekerjaan dinding bata penahan peninggian level m' 71.60 183.438.00 13.134.160.80
II.26 Pekerjaan urugan tanah peninggian level m3 315.00 174.150.00 54.857.250.00

III PEKERJAAN PONDASI Rp 845.370.900.29

III.01 Pekerjan Tiang Borepile


- Mob Demob alat borepile Ls 1.00 25.000.000.00 25.000.000.00
- Pekerjaan Pengeboran 0 m' 385.00 210.000.00 80.850.000.00
- beton tiang borepile K-500 m3 75.56 1.451.000.00 109.632.118.75
- Pekerjaan pembesian borepile kg 7.330.29 17.531.10 128.507.977.60
- Pekerjaan pecah kepala tiang pancang unit 55.00 290.250.00 15.963.750.00
III.02 Pekerjan beton pondasi PC1
- Adukan Beton K-300 m3 17.60 1.684.611.00 29.649.153.60
- Bekisting papan m2 37.20 243.810.00 9.069.732.00
- Pembesian U-24 + U-39 U-42 kg 1.573.93 17.531.10 27.592.712.97
III.03 Pekerjan beton pondasi PC2
- Adukan Beton K-300 m3 24.00 1.684.611.00 40.430.664.00
RENCANA ANGGARAN BIAYA
PEKERJAAN STRUKTUR TOWER 1
PROYEK : TOWER 1 DIBUAT : Hari
LOKASI : SERANG - BANTEN DIPERIKSA : Agus
PEMILIK : 0 TGL : 15/04/2022
SUBJECT : RENCANA ANGGARAN BIAYA REVISI : 1

HARGA
No. URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME TOTAL HARGA KETERANGAN
SATUAN
- Bekisting papan m2 50.00 243.810.00 12.190.500.00
- Pembesian U-24 + U-39 U-42 kg 2.146.27 17.531.10 37.626.426.78
RENCANA ANGGARAN BIAYA
PEKERJAAN STRUKTUR TOWER 1
PROYEK : TOWER 1 DIBUAT : Hari
LOKASI : SERANG - BANTEN DIPERIKSA : Agus
PEMILIK : 0 TGL : 15/04/2022
SUBJECT : RENCANA ANGGARAN BIAYA REVISI : 1

HARGA
No. URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME TOTAL HARGA KETERANGAN
SATUAN

III.04 Pekerjan beton pondasi PC3


- Adukan Beton K-300 m3 2.40 1.684.611.00 4.043.066.40
- Bekisting papan m2 6.80 243.810.00 1.657.908.00
- Pembesian U-24 + U-39 U-42 kg 214.63 17.531.10 3.762.642.68
III.05 Pekerjan beton pondasi PL
- Adukan Beton (pondasi) K-300 m3 1.30 1.684.611.00 2.189.994.30
- Adukan Beton (dinding pit) K-300 m3 5.20 1.684.611.00 8.759.977.20
- Bekisting papan (pondasi) m2 6.04 243.810.00 1.472.612.40
- Bekisting papan (dinding pit) m2 52.00 243.810.00 12.678.120.00
- Pembesian u-42 (pondasi) U-42 kg 199.56 17.531.10 3.498.452.82
- Pembesian u-42 (dinding pit) U-42 kg 798.23 17.531.10 13.993.811.27
III.06 Pekerjaan Sloof beton 25x40
- Adukan Beton K-300 m3 31.81 1.684.611.00 53.590.845.13
- Bekisting papan m2 254.50 243.810.00 62.048.669.76
- Pembesian u-42 (Utama+sengkang) U-42 kg 5.571.34 17.531.10 97.671.746.72
III.07 Pekerjaan Sloof beton 20x40
- Adukan Beton K-300 m3 7.89 1.684.611.00 13.299.127.85
- Bekisting papan m2 78.94 243.810.00 19.247.531.69
- Pembesian u-42 (Utama+sengkang) U-42 kg 1.288.12 17.531.10 22.582.090.17
III.08 Pekerjaan Pondasi tangga
- Adukan Beton K-300 m3 1.86 1.684.611.00 3.133.881.84
- Bekisting papan m2 11.34 243.810.00 2.764.073.97
- Pembesian D10 U-42 kg 85.06 17.531.10 1.491.265.49
- Pembesian D12 U-42 kg 55.45 17.531.10 972.046.90

IV PEKERJAAN STRUKTUR LT. 1 Rp 483.221.955.32


Struktur Elv. -0.700 s/d Elv. +3.550

IV.01 Pekerjaan kolom beton K1 (450X450)


- Adukan Beton K-300 m3 6.97 1.684.611.00 11.735.000.23
- Bekisting papan m2 61.92 243.810.00 15.096.715.20
- Pembesian u-42 (Utama) U-42 kg 1.841.09 17.531.10 32.276.297.84
- Pembesian u-42 (sengkang) U-42 kg 244.53 17.531.10 4.286.844.82
IV.02 Pekerjaan kolom beton K2 (450X450)
- Adukan Beton K-300 m3 10.45 1.684.611.00 17.602.500.34
- Bekisting papan m2 92.88 243.810.00 22.645.072.80
- Pembesian u-42 (Utama) U-42 kg 2.301.36 17.531.10 40.345.372.30
- Pembesian u-42 (sengkang) U-42 kg 366.79 17.531.10 6.430.267.23
IV.03 Pekerjaan kolom beton K3 (400X400)
- Adukan Beton K-300 m3 11.01 1.684.611.00 18.544.197.89
- Bekisting papan m2 110.08 243.810.00 26.838.604.80
- Pembesian u-42 (Utama) U-42 kg 2.454.78 17.531.10 43.035.063.78
- Pembesian u-42 (sengkang) U-42 kg 431.52 17.531.10 7.565.020.27
IV.04 Pekerjaan kolom beton KL (200X400X2)
- Adukan Beton K-300 m3 1.84 1.684.611.00 3.092.945.80
- Bekisting papan m2 24.48 243.810.00 5.968.468.80
- Pembesian u-42 (Utama) U-42 kg 409.43 17.531.10 7.177.723.21
- Pembesian u-42 (sengkang) U-42 kg 278.26 17.531.10 4.878.133.76
IV.05 Pekerjaan beton Slab on ground S1
- Adukan Beton K-300 m3 30.58 1.684.611.00 51.511.192.85
- Bekisting papan m2 18.72 243.810.00 4.563.391.77
- Pembesian M8@150 (2 lapis) U-42 kg 2.221.97 17.531.10 38.953.490.61
IV.06 Pekerjaan beton Slab on ground S2
- Adukan Beton K-300 m3 45.23 1.684.611.00 76.192.192.77
- Bekisting papan m2 5.21 243.810.00 1.270.250.10
- Pembesian M8@150 (1 lapis) U-42 kg 2.464.95 17.531.10 43.213.208.16
RENCANA ANGGARAN BIAYA
PEKERJAAN STRUKTUR TOWER 1
PROYEK : TOWER 1 DIBUAT : Hari
LOKASI : SERANG - BANTEN DIPERIKSA : Agus
PEMILIK : 0 TGL : 15/04/2022
SUBJECT : RENCANA ANGGARAN BIAYA REVISI : 1

HARGA
No. URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME TOTAL HARGA KETERANGAN
SATUAN

V PEKERJAAN STRUKTUR LT. 2 Rp 995.558.312.40


Struktur Elv. +3.550 s/d Elv. +6.950

V.01 Pekerjaan kolom beton K1 (450X450)


- Adukan Beton K-300 m3 5.51 1.684.611.00 9.278.837.39
- Bekisting papan m2 48.96 243.810.00 11.936.937.60
- Pembesian u-42 (Utama) U-42 kg 1.213.12 17.531.10 21.267.328.03
- Pembesian u-42 (sengkang) U-42 kg 193.94 17.531.10 3.399.911.41
V.02 Pekerjaan kolom beton K2 (450X450)
- Adukan Beton K-300 m3 8.26 1.684.611.00 13.918.256.08
- Bekisting papan m2 73.44 243.810.00 17.905.406.40
- Pembesian u-42 (Utama) U-42 kg 1.455.74 17.531.10 25.520.793.64
- Pembesian u-42 (sengkang) U-42 kg 290.90 17.531.10 5.099.867.11
V.03 Pekerjaan kolom beton K3 (400X400)
- Adukan Beton K-300 m3 8.70 1.684.611.00 14.662.854.14
- Bekisting papan m2 87.04 243.810.00 21.221.222.40
- Pembesian u-42 (Utama) U-42 kg 1.940.99 17.531.10 34.027.724.85
- Pembesian u-42 (sengkang) U-42 kg 342.24 17.531.10 5.999.843.66
V.04 Pekerjaan kolom beton KL (200X400X2)
- Adukan Beton K-300 m3 1.22 1.684.611.00 2.061.963.86
- Bekisting papan m2 16.32 243.810.00 3.978.979.20
- Pembesian u-42 (Utama) U-42 kg 272.95 17.531.10 4.785.148.81
- Pembesian u-42 (sengkang) U-42 kg 188.23 17.531.10 3.299.914.02
V.05 Pekerjaan Balok 180X250
- Adukan Beton K-300 m3 2.84 1.684.611.00 4.788.190.90
- Bekisting papan m2 54.32 243.810.00 13.243.698.25
- Pembesian u-42 (Utama) U-42 kg 399.19 17.531.10 6.998.187.22
- Pembesian u-42 (sengkang) U-42 kg 118.67 17.531.10 2.080.352.53
V.06 Pekerjaan Balok 180X300
- Adukan Beton K-300 m3 9.79 1.684.611.00 16.485.855.94
- Bekisting papan m2 173.98 243.810.00 42.417.088.56
- Pembesian u-42 (Utama) U-42 kg 1.145.34 17.531.10 20.079.105.14
- Pembesian u-42 (sengkang) U-42 kg 384.70 17.531.10 6.744.280.79
V.07 Pekerjaan Balok 200X350
- Adukan Beton K-300 m3 3.26 1.684.611.00 5.483.408.81
- Bekisting papan m2 51.15 243.810.00 12.470.881.50
- Pembesian u-42 (Utama) U-42 kg 829.56 17.531.10 14.543.099.32
- Pembesian u-42 (sengkang) U-42 kg 192.20 17.531.10 3.369.477.42
V.08 Pekerjaan Balok 200X400
- Adukan Beton K-300 m3 0.52 1.684.611.00 877.682.33
- Bekisting papan m2 7.82 243.810.00 1.905.375.15
- Pembesian u-42 (Utama) U-42 kg 82.32 17.531.10 1.443.125.09
- Pembesian u-42 (sengkang) U-42 kg 30.01 17.531.10 526.073.25
V.09 Pekerjaan Balok 200X450
- Adukan Beton K-300 m3 5.59 1.684.611.00 9.415.290.88
- Bekisting papan m2 80.73 243.810.00 19.682.781.30
- Pembesian u-42 (Utama) U-42 kg 1.107.86 17.531.10 19.422.074.57
- Pembesian u-42 (sengkang) U-42 kg 308.02 17.531.10 5.399.859.30
V.10 Pekerjaan Balok 250X400
- Adukan Beton K-300 m3 2.83 1.684.611.00 4.765.343.37
- Bekisting papan m2 36.77 243.810.00 8.965.807.99
- Pembesian u-42 (Utama) U-42 kg 504.65 17.531.10 8.847.052.08
- Pembesian u-42 (sengkang) U-42 kg 140.62 17.531.10 2.465.153.16
V.11 Pekerjaan Balok 250X500
- Adukan Beton K-300 m3 28.70 1.684.611.00 48.342.439.56
- Bekisting papan m2 414.51 243.810.00 101.060.464.05
RENCANA ANGGARAN BIAYA
PEKERJAAN STRUKTUR TOWER 1
PROYEK : TOWER 1 DIBUAT : Hari
LOKASI : SERANG - BANTEN DIPERIKSA : Agus
PEMILIK : 0 TGL : 15/04/2022
SUBJECT : RENCANA ANGGARAN BIAYA REVISI : 1

HARGA
No. URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME TOTAL HARGA KETERANGAN
SATUAN
- Pembesian u-42 (Utama) U-42 kg 6.399.32 17.531.10 112.187.110.09
- Pembesian u-42 (sengkang) U-42 kg 1.581.74 17.531.10 27.729.712.24
V.12 Pekerjaan pelat beton lantai t:12cm
- Adukan Beton K-300 m3 77.26 1.684.611.00 130.159.730.40
- Bekisting papan m2 15.60 243.810.00 3.804.021.14
- Pembesian M8@150 (2 lapis) U-42 kg 7.246.72 17.531.10 127.042.916.19
V.13 Pekerjaan Tangga beton
- Adukan Beton K-300 m3 3.11 1.684.611.00 5.237.657.75
- Bekisting papan m2 16.87 243.810.00 4.113.952.42
- Pembesian D8 U-42 kg 87.77 17.531.10 1.538.664.33
- Pembesian D12 U-42 kg 202.92 17.531.10 3.557.410.81

VI PEKERJAAN STRUKTUR LT. 3 Rp 967.545.732.50


Struktur Elv. +6.950 s/d +11.350

VI.01 Pekerjaan kolom beton K1 (400X400)


- Adukan Beton K-300 m3 4.35 1.684.611.00 7.331.427.07
- Bekisting papan m2 43.52 243.810.00 10.610.611.20
- Pembesian u-42 (Utama) U-42 kg 970.50 17.531.10 17.013.862.43
- Pembesian u-42 (sengkang) U-42 kg 193.94 17.531.10 3.399.911.41
VI.02 Pekerjaan kolom beton K2 (400X400)
- Adukan Beton K-300 m3 6.53 1.684.611.00 10.997.140.61
- Bekisting papan m2 65.28 243.810.00 15.915.916.80
- Pembesian u-42 (Utama) U-42 kg 1.091.81 17.531.10 19.140.595.23
- Pembesian u-42 (sengkang) U-42 kg 290.90 17.531.10 5.099.867.11
VI.03 Pekerjaan kolom beton K3 (400X400)
- Adukan Beton K-300 m3 8.70 1.684.611.00 14.662.854.14
- Bekisting papan m2 87.04 243.810.00 21.221.222.40
- Pembesian u-42 (Utama) U-42 kg 1.455.74 17.531.10 25.520.793.64
- Pembesian u-42 (sengkang) U-42 kg 387.87 17.531.10 6.799.822.82
VI.04 Pekerjaan kolom beton KL (200X400X2)
- Adukan Beton K-300 m3 1.63 1.684.611.00 2.749.285.15
- Bekisting papan m2 16.32 243.810.00 3.978.979.20
- Pembesian u-42 (Utama) U-42 kg 272.95 17.531.10 4.785.148.81
- Pembesian u-42 (sengkang) U-42 kg 64.17 17.531.10 1.124.970.69
VI.05 Pekerjaan Balok 180X250
- Adukan Beton K-300 m3 2.84 1.684.611.00 4.788.190.90
- Bekisting papan m2 54.32 243.810.00 13.243.698.25
- Pembesian u-42 (Utama) U-42 kg 399.19 17.531.10 6.998.187.22
- Pembesian u-42 (sengkang) U-42 kg 118.67 17.531.10 2.080.352.53
VI.06 Pekerjaan Balok 180X300
- Adukan Beton K-300 m3 9.79 1.684.611.00 16.485.855.94
- Bekisting papan m2 173.98 243.810.00 42.417.088.56
- Pembesian u-42 (Utama) U-42 kg 1.145.34 17.531.10 20.079.105.14
- Pembesian u-42 (sengkang) U-42 kg 384.70 17.531.10 6.744.280.79
VI.07 Pekerjaan Balok 200X350
- Adukan Beton K-300 m3 3.26 1.684.611.00 5.483.408.81
- Bekisting papan m2 51.15 243.810.00 12.470.881.50
- Pembesian u-42 (Utama) U-42 kg 829.56 17.531.10 14.543.099.32
- Pembesian u-42 (sengkang) U-42 kg 192.20 17.531.10 3.369.477.42
VI.08 Pekerjaan Balok 200X400
- Adukan Beton K-300 m3 0.52 1.684.611.00 877.682.33
- Bekisting papan m2 7.82 243.810.00 1.905.375.15
- Pembesian u-42 (Utama) U-42 kg 82.32 17.531.10 1.443.125.09
- Pembesian u-42 (sengkang) U-42 kg 30.01 17.531.10 526.073.25
VI.09 Pekerjaan Balok 200X450
- Adukan Beton K-300 m3 5.59 1.684.611.00 9.415.290.88
RENCANA ANGGARAN BIAYA
PEKERJAAN STRUKTUR TOWER 1
PROYEK : TOWER 1 DIBUAT : Hari
LOKASI : SERANG - BANTEN DIPERIKSA : Agus
PEMILIK : 0 TGL : 15/04/2022
SUBJECT : RENCANA ANGGARAN BIAYA REVISI : 1

HARGA
No. URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME TOTAL HARGA KETERANGAN
SATUAN
- Bekisting papan m2 80.73 243.810.00 19.682.781.30
- Pembesian u-42 (Utama) U-42 kg 1.107.86 17.531.10 19.422.074.57
- Pembesian u-42 (sengkang) U-42 kg 308.02 17.531.10 5.399.859.30
VI.10 Pekerjaan Balok 250X400
- Adukan Beton K-300 m3 2.83 1.684.611.00 4.765.343.37
- Bekisting papan m2 36.77 243.810.00 8.965.807.99
- Pembesian u-42 (Utama) U-42 kg 504.65 17.531.10 8.847.052.08
- Pembesian u-42 (sengkang) U-42 kg 140.62 17.531.10 2.465.153.16
VI.11 Pekerjaan Balok 250X500
- Adukan Beton K-300 m3 28.70 1.684.611.00 48.342.439.56
- Bekisting papan m2 414.51 243.810.00 101.060.464.05
- Pembesian u-42 (Utama) U-42 kg 6.399.32 17.531.10 112.187.110.09
- Pembesian u-42 (sengkang) U-42 kg 1.581.74 17.531.10 27.729.712.24
VI.12 Pekerjaan pelat beton lantai t:12cm
- Adukan Beton K-300 m3 77.26 1.684.611.00 130.159.730.40
- Bekisting papan m2 15.60 243.810.00 3.804.021.14
- Pembesian M8@150 (2 lapis) U-42 kg 7.246.72 17.531.10 127.042.916.19
VI.13 Pekerjaan Tangga beton
- Adukan Beton K-300 m3 3.11 1.684.611.00 5.237.657.75
- Bekisting papan m2 16.87 243.810.00 4.113.952.42
- Pembesian D8 U-42 kg 87.77 17.531.10 1.538.664.33
- Pembesian D12 U-42 kg 202.92 17.531.10 3.557.410.81

VII PEKERJAAN STRUKTUR LT. 4 Rp 955.080.498.04


Struktur Elv. +11.350 s/d +13.750

VII.01 Pekerjaan kolom beton K1 (400X400)


- Adukan Beton K-300 m3 4.35 1.684.611.00 7.331.427.07
- Bekisting papan m2 43.52 243.810.00 10.610.611.20
- Pembesian u-42 (Utama) U-42 kg 970.50 17.531.10 17.013.862.43
- Pembesian u-42 (sengkang) U-42 kg 193.94 17.531.10 3.399.911.41
VII.02 Pekerjaan kolom beton K2 (400X400)
- Adukan Beton K-300 m3 6.53 1.684.611.00 10.997.140.61
- Bekisting papan m2 65.28 243.810.00 15.915.916.80
- Pembesian u-42 (Utama) U-42 kg 1.091.81 17.531.10 19.140.595.23
- Pembesian u-42 (sengkang) U-42 kg 290.90 17.531.10 5.099.867.11
VII.03 Pekerjaan kolom beton K3 (400X400)
- Adukan Beton K-300 m3 8.70 1.684.611.00 14.662.854.14
- Bekisting papan m2 87.04 243.810.00 21.221.222.40
- Pembesian u-42 (Utama) U-42 kg 1.455.74 17.531.10 25.520.793.64
- Pembesian u-42 (sengkang) U-42 kg 387.87 17.531.10 6.799.822.82
VII.04 Pekerjaan kolom beton KL (200X400X2)
- Adukan Beton K-300 m3 1.63 1.684.611.00 2.749.285.15
- Bekisting papan m2 16.32 243.810.00 3.978.979.20
- Pembesian u-42 (Utama) U-42 kg 272.95 17.531.10 4.785.148.81
- Pembesian u-42 (sengkang) U-42 kg 64.17 17.531.10 1.124.970.69
VII.05 Pekerjaan Balok 180X250
- Adukan Beton K-300 m3 2.84 1.684.611.00 4.788.190.90
- Bekisting papan m2 54.32 243.810.00 13.243.698.25
- Pembesian u-42 (Utama) U-42 kg 399.19 17.531.10 6.998.187.22
- Pembesian u-42 (sengkang) U-42 kg 118.67 17.531.10 2.080.352.53
VII.06 Pekerjaan Balok 180X300
- Adukan Beton K-300 m3 9.79 1.684.611.00 16.485.855.94
- Bekisting papan m2 173.98 243.810.00 42.417.088.56
- Pembesian u-42 (Utama) U-42 kg 1.145.34 17.531.10 20.079.105.14
- Pembesian u-42 (sengkang) U-42 kg 384.70 17.531.10 6.744.280.79
VII.07 Pekerjaan Balok 200X350
RENCANA ANGGARAN BIAYA
PEKERJAAN STRUKTUR TOWER 1
PROYEK : TOWER 1 DIBUAT : Hari
LOKASI : SERANG - BANTEN DIPERIKSA : Agus
PEMILIK : 0 TGL : 15/04/2022
SUBJECT : RENCANA ANGGARAN BIAYA REVISI : 1

HARGA
No. URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME TOTAL HARGA KETERANGAN
SATUAN
- Adukan Beton K-300 m3 3.26 1.684.611.00 5.483.408.81
- Bekisting papan m2 51.15 243.810.00 12.470.881.50
- Pembesian u-42 (Utama) U-42 kg 829.56 17.531.10 14.543.099.32
- Pembesian u-42 (sengkang) U-42 kg 192.20 17.531.10 3.369.477.42
VII.08 Pekerjaan Balok 200X400
- Adukan Beton K-300 m3 0.52 1.684.611.00 877.682.33
- Bekisting papan m2 7.82 243.810.00 1.905.375.15
- Pembesian u-42 (Utama) U-42 kg 82.32 17.531.10 1.443.125.09
- Pembesian u-42 (sengkang) U-42 kg 30.01 17.531.10 526.073.25
VII.09 Pekerjaan Balok 200X450
- Adukan Beton K-300 m3 5.59 1.684.611.00 9.415.290.88
- Bekisting papan m2 80.73 243.810.00 19.682.781.30
- Pembesian u-42 (Utama) U-42 kg 1.107.86 17.531.10 19.422.074.57
- Pembesian u-42 (sengkang) U-42 kg 308.02 17.531.10 5.399.859.30
VII.10 Pekerjaan Balok 250X400
- Adukan Beton K-300 m3 2.83 1.684.611.00 4.765.343.37
- Bekisting papan m2 36.77 243.810.00 8.965.807.99
- Pembesian u-42 (Utama) U-42 kg 504.65 17.531.10 8.847.052.08
- Pembesian u-42 (sengkang) U-42 kg 140.62 17.531.10 2.465.153.16
VII.11 Pekerjaan Balok 250X500
- Adukan Beton K-300 m3 28.70 1.684.611.00 48.342.439.56
- Bekisting papan m2 414.51 243.810.00 101.060.464.05
- Pembesian u-42 (Utama) U-42 kg 5.688.28 17.531.10 99.721.875.63
- Pembesian u-42 (sengkang) U-42 kg 1.581.74 17.531.10 27.729.712.24
VII.12 Pekerjaan pelat beton lantai t:12cm
- Adukan Beton K-300 m3 77.26 1.684.611.00 130.159.730.40
- Bekisting papan m2 15.60 243.810.00 3.804.021.14
- Pembesian M8@150 (2 lapis) U-42 kg 7.246.72 17.531.10 127.042.916.19
VII.13 Pekerjaan Tangga beton
- Adukan Beton K-300 m3 3.11 1.684.611.00 5.237.657.75
- Bekisting papan m2 16.87 243.810.00 4.113.952.42
- Pembesian D8 U-42 kg 87.77 17.531.10 1.538.664.33
- Pembesian D12 U-42 kg 202.92 17.531.10 3.557.410.81

VIII PEKERJAAN STRUKTUR LT. 5 Rp 935.939.902.81


Struktur Elv. +13.750 s/d +17.150

VIII.01 Pekerjaan kolom beton K1 (400X400)


- Adukan Beton K-300 m3 4.35 1.684.611.00 7.331.427.07
- Bekisting papan m2 43.52 243.810.00 10.610.611.20
- Pembesian u-42 (Utama) U-42 kg 727.87 17.531.10 12.760.396.82
- Pembesian u-42 (sengkang) U-42 kg 193.94 17.531.10 3.399.911.41
VIII.02 Pekerjaan kolom beton K2 (400X400)
- Adukan Beton K-300 m3 6.53 1.684.611.00 10.997.140.61
- Bekisting papan m2 65.28 243.810.00 15.915.916.80
- Pembesian u-42 (Utama) U-42 kg 727.87 17.531.10 12.760.396.82
- Pembesian u-42 (sengkang) U-42 kg 290.90 17.531.10 5.099.867.11
VIII.03 Pekerjaan kolom beton K3 (400X400)
- Adukan Beton K-300 m3 8.70 1.684.611.00 14.662.854.14
- Bekisting papan m2 87.04 243.810.00 21.221.222.40
- Pembesian u-42 (Utama) U-42 kg 970.50 17.531.10 17.013.862.43
- Pembesian u-42 (sengkang) U-42 kg 387.87 17.531.10 6.799.822.82
VIII.04 Pekerjaan kolom beton KL (200X400X2)
- Adukan Beton K-300 m3 1.63 1.684.611.00 2.749.285.15
- Bekisting papan m2 16.32 243.810.00 3.978.979.20
- Pembesian u-42 (Utama) U-42 kg 272.95 17.531.10 4.785.148.81
- Pembesian u-42 (sengkang) U-42 kg 64.17 17.531.10 1.124.970.69
RENCANA ANGGARAN BIAYA
PEKERJAAN STRUKTUR TOWER 1
PROYEK : TOWER 1 DIBUAT : Hari
LOKASI : SERANG - BANTEN DIPERIKSA : Agus
PEMILIK : 0 TGL : 15/04/2022
SUBJECT : RENCANA ANGGARAN BIAYA REVISI : 1

HARGA
No. URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME TOTAL HARGA KETERANGAN
SATUAN

VII.05 Pekerjaan Balok 180X250


- Adukan Beton K-300 m3 2.84 1.684.611.00 4.788.190.90
- Bekisting papan m2 54.32 243.810.00 13.243.698.25
- Pembesian u-42 (Utama) U-42 kg 399.19 17.531.10 6.998.187.22
- Pembesian u-42 (sengkang) U-42 kg 118.67 17.531.10 2.080.352.53
VII.06 Pekerjaan Balok 180X300
- Adukan Beton K-300 m3 9.79 1.684.611.00 16.485.855.94
- Bekisting papan m2 173.98 243.810.00 42.417.088.56
- Pembesian u-42 (Utama) U-42 kg 1.145.34 17.531.10 20.079.105.14
- Pembesian u-42 (sengkang) U-42 kg 384.70 17.531.10 6.744.280.79
VII.07 Pekerjaan Balok 200X350
- Adukan Beton K-300 m3 3.26 1.684.611.00 5.483.408.81
- Bekisting papan m2 51.15 243.810.00 12.470.881.50
- Pembesian u-42 (Utama) U-42 kg 829.56 17.531.10 14.543.099.32
- Pembesian u-42 (sengkang) U-42 kg 192.20 17.531.10 3.369.477.42
VII.08 Pekerjaan Balok 200X400
- Adukan Beton K-300 m3 0.52 1.684.611.00 877.682.33
- Bekisting papan m2 7.82 243.810.00 1.905.375.15
- Pembesian u-42 (Utama) U-42 kg 82.32 17.531.10 1.443.125.09
- Pembesian u-42 (sengkang) U-42 kg 30.01 17.531.10 526.073.25
VII.09 Pekerjaan Balok 200X450
- Adukan Beton K-300 m3 5.59 1.684.611.00 9.415.290.88
- Bekisting papan m2 80.73 243.810.00 19.682.781.30
- Pembesian u-42 (Utama) U-42 kg 1.107.86 17.531.10 19.422.074.57
- Pembesian u-42 (sengkang) U-42 kg 308.02 17.531.10 5.399.859.30
VII.10 Pekerjaan Balok 250X400
- Adukan Beton K-300 m3 2.83 1.684.611.00 4.765.343.37
- Bekisting papan m2 36.77 243.810.00 8.965.807.99
- Pembesian u-42 (Utama) U-42 kg 504.65 17.531.10 8.847.052.08
- Pembesian u-42 (sengkang) U-42 kg 140.62 17.531.10 2.465.153.16
VII.11 Pekerjaan Balok 250X500
- Adukan Beton K-300 m3 28.70 1.684.611.00 48.342.439.56
- Bekisting papan m2 414.51 243.810.00 101.060.464.05
- Pembesian u-42 (Utama) U-42 kg 5.688.28 17.531.10 99.721.875.63
- Pembesian u-42 (sengkang) U-42 kg 1.581.74 17.531.10 27.729.712.24
VII.12 Pekerjaan pelat beton lantai t:12cm
- Adukan Beton K-300 m3 77.26 1.684.611.00 130.159.730.40
- Bekisting papan m2 15.60 243.810.00 3.804.021.14
- Pembesian M8@150 (2 lapis) U-42 kg 7.246.72 17.531.10 127.042.916.19
VII.13 Pekerjaan Tangga beton
- Adukan Beton K-300 m3 3.11 1.684.611.00 5.237.657.75
- Bekisting papan m2 16.87 243.810.00 4.113.952.42
- Pembesian D8 U-42 kg 87.77 17.531.10 1.538.664.33
- Pembesian D12 U-42 kg 202.92 17.531.10 3.557.410.81

VIII PEKERJAAN STRUKTUR LT. DAK ATAP Rp 921.492.217.51


Struktur Elv. +17.150 s/d +19.650

VIII.01 Pekerjaan kolom beton K1 (400X400)


- Adukan Beton K-300 m3 4.35 1.684.611.00 7.331.427.07
- Bekisting papan m2 43.52 243.810.00 10.610.611.20
- Pembesian u-42 (Utama) U-42 kg 727.87 17.531.10 12.760.396.82
- Pembesian u-42 (sengkang) U-42 kg 193.94 17.531.10 3.399.911.41
VIII.02 Pekerjaan kolom beton K2 (400X400)
- Adukan Beton K-300 m3 6.53 1.684.611.00 10.997.140.61
- Bekisting papan m2 65.28 243.810.00 15.915.916.80
- Pembesian u-42 (Utama) U-42 kg 727.87 17.531.10 12.760.396.82
RENCANA ANGGARAN BIAYA
PEKERJAAN STRUKTUR TOWER 1
PROYEK : TOWER 1 DIBUAT : Hari
LOKASI : SERANG - BANTEN DIPERIKSA : Agus
PEMILIK : 0 TGL : 15/04/2022
SUBJECT : RENCANA ANGGARAN BIAYA REVISI : 1

HARGA
No. URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME TOTAL HARGA KETERANGAN
SATUAN
- Pembesian u-42 (sengkang) U-42 kg 290.90 17.531.10 5.099.867.11
VIII.03 Pekerjaan kolom beton K3 (400X400)
- Adukan Beton K-300 m3 8.70 1.684.611.00 14.662.854.14
- Bekisting papan m2 87.04 243.810.00 21.221.222.40
- Pembesian u-42 (Utama) U-42 kg 970.50 17.531.10 17.013.862.43
- Pembesian u-42 (sengkang) U-42 kg 387.87 17.531.10 6.799.822.82
VIII.04 Pekerjaan kolom beton KL (200X400X2)
- Adukan Beton K-300 m3 1.63 1.684.611.00 2.749.285.15
- Bekisting papan m2 16.32 243.810.00 3.978.979.20
- Pembesian u-42 (Utama) U-42 kg 272.95 17.531.10 4.785.148.81
- Pembesian u-42 (sengkang) U-42 kg 64.17 17.531.10 1.124.970.69
VIII.05 Pekerjaan Balok 180X250
- Adukan Beton K-300 m3 2.84 1.684.611.00 4.788.190.90
- Bekisting papan m2 54.32 243.810.00 13.243.698.25
- Pembesian u-42 (Utama) U-42 kg 399.19 17.531.10 6.998.187.22
- Pembesian u-42 (sengkang) U-42 kg 118.67 17.531.10 2.080.352.53
VIII.06 Pekerjaan Balok 180X300
- Adukan Beton K-300 m3 9.79 1.684.611.00 16.485.855.94
- Bekisting papan m2 173.98 243.810.00 42.417.088.56
- Pembesian u-42 (Utama) U-42 kg 1.145.34 17.531.10 20.079.105.14
- Pembesian u-42 (sengkang) U-42 kg 384.70 17.531.10 6.744.280.79
VIII.07 Pekerjaan Balok 200X350
- Adukan Beton K-300 m3 3.26 1.684.611.00 5.483.408.81
- Bekisting papan m2 51.15 243.810.00 12.470.881.50
- Pembesian u-42 (Utama) U-42 kg 829.56 17.531.10 14.543.099.32
- Pembesian u-42 (sengkang) U-42 kg 192.20 17.531.10 3.369.477.42
VIII.08 Pekerjaan Balok 200X400
- Adukan Beton K-300 m3 0.52 1.684.611.00 877.682.33
- Bekisting papan m2 7.82 243.810.00 1.905.375.15
- Pembesian u-42 (Utama) U-42 kg 82.32 17.531.10 1.443.125.09
- Pembesian u-42 (sengkang) U-42 kg 30.01 17.531.10 526.073.25
VIII.09 Pekerjaan Balok 200X450
- Adukan Beton K-300 m3 5.59 1.684.611.00 9.415.290.88
- Bekisting papan m2 80.73 243.810.00 19.682.781.30
- Pembesian u-42 (Utama) U-42 kg 1.107.86 17.531.10 19.422.074.57
- Pembesian u-42 (sengkang) U-42 kg 308.02 17.531.10 5.399.859.30
VIII.10 Pekerjaan Balok 250X400
- Adukan Beton K-300 m3 2.83 1.684.611.00 4.765.343.37
- Bekisting papan m2 36.77 243.810.00 8.965.807.99
- Pembesian u-42 (Utama) U-42 kg 504.65 17.531.10 8.847.052.08
- Pembesian u-42 (sengkang) U-42 kg 140.62 17.531.10 2.465.153.16
VIII.11 Pekerjaan Balok 250X500
- Adukan Beton K-300 m3 28.70 1.684.611.00 48.342.439.56
- Bekisting papan m2 414.51 243.810.00 101.060.464.05
- Pembesian u-42 (Utama) U-42 kg 5.688.28 17.531.10 99.721.875.63
- Pembesian u-42 (sengkang) U-42 kg 1.581.74 17.531.10 27.729.712.24
VIII.12 Pekerjaan pelat beton lantai t:12cm
- Adukan Beton K-300 m3 77.26 1.684.611.00 130.159.730.40
- Bekisting papan m2 15.60 243.810.00 3.804.021.14
- Pembesian M8@150 (2 lapis) U-42 kg 7.246.72 17.531.10 127.042.916.19

IX PEKERJAAN STRUKTUR LT. DAK ATAP TANGGA 207.512.931.09


IX.01 Pekerjaan Balok 200X450
- Adukan Beton K-300 m3 0.96 1.684.611.00 1.617.226.56
- Bekisting papan m2 14.40 243.810.00 3.510.864.00
- Pembesian u-42 (Utama) U-42 kg 160.56 17.531.10 2.814.793.42
- Pembesian u-42 (sengkang) U-42 kg 71.42 17.531.10 1.252.141.29
IX.02 Pekerjaan Balok 200X400
RENCANA ANGGARAN BIAYA
PEKERJAAN STRUKTUR TOWER 1
PROYEK : TOWER 1 DIBUAT : Hari
LOKASI : SERANG - BANTEN DIPERIKSA : Agus
PEMILIK : 0 TGL : 15/04/2022
SUBJECT : RENCANA ANGGARAN BIAYA REVISI : 1

HARGA
No. URAIAN PEKERJAAN SPESIFIKASI SAT. VOLUME TOTAL HARGA KETERANGAN
SATUAN
- Adukan Beton K-300 m3 0.47 1.684.611.00 788.397.95
- Bekisting papan m2 6.24 243.810.00 1.521.374.40
- Pembesian u-42 (Utama) U-42 kg 69.58 17.531.10 1.219.743.81
- Pembesian u-42 (sengkang) U-42 kg 38.69 17.531.10 678.243.20
IX.03 Pekerjaan Balok 200X300
- Adukan Beton K-300 m3 1.27 1.684.611.00 2.145.857.49
- Bekisting papan m2 21.23 243.810.00 5.176.086.30
- Pembesian u-42 (Utama) U-42 kg 189.37 17.531.10 3.319.892.46
- Pembesian u-42 (sengkang) U-42 kg 105.65 17.531.10 1.852.125.65
IX.04 Pekerjaan pelat beton lantai t:12cm
- Adukan Beton K-300 m3 2.16 1.684.611.00 3.638.759.76
- Bekisting papan m2 18.00 243.810.00 4.388.580.00
- Pembesian M8@150 (2 lapis) U-42 kg 196.20 17.531.10 3.439.601.82
IX.05 Pekerjaan pelat beton lantai t:12cm
- Adukan Beton K-300 m3 1.89 1.684.611.00 3.178.492.03
- Bekisting papan m2 15.72 243.810.00 3.833.467.30
- Pembesian M8@150 (2 lapis) U-42 kg 171.38 17.531.10 3.004.525.63
IX.06 Pekerjaan kolom beton KLA (200X400X2)
- Adukan Beton U-42 m3 1.20 1.684.611.00 2.021.533.20
- Bekisting papan m2 24.00 243.810.00 5.851.440.00
- Pembesian u-42 (Utama) 0 kg 267.60 17.531.10 4.691.322.36
- Pembesian u-42 (sengkang) K-300 kg 63.24 17.531.10 1.108.666.76
IX.07 Pekerjaan kolom beton KLB (200X400)
- Adukan Beton U-42 m3 1.20 1.684.611.00 2.021.533.20
- Bekisting papan m2 24.00 243.810.00 5.851.440.00
- Pembesian u-42 (Utama) U-42 kg 267.60 17.531.10 4.691.322.36
- Pembesian u-42 (sengkang) 0 kg 94.86 17.531.10 1.663.000.15
IX.07 Pekerjaan Water Profing membrane m2 587.70 225.000.00 132.232.500.00
Pekerjan Tiang Borepile 55 titik
BJ BESI POLOS
1 Pekerjaan Sloof beton 25x40 318.12 m' DIAMETER PANJANG BERAT BERAT
No.
2 Pekerjaan Sloof beton 20x40 98.681 m' mm m kg/btg kg/m'
1. 6 12 2.66 0.22
2. 8 12 4.47 0.37
lantai 1-2 3. 9 12 6 0.50
1 Pekerjaan kolom beton K1 (450X450) 8 titik 4. 10 12 7.4 0.62
2 Pekerjaan kolom beton K2 (450X450) 12 titik 5. 12 12 10.66 0.89
3 Pekerjaan kolom beton K3 (400X400) 16 titik 6. 13 12 12.48 1.04
4 Pekerjaan kolom beton KL (200X400X2) 3 titik 7. 16 12 18.96 1.58
8. 19 12 26.76 2.23
lantai 3-5 9. 22 12 35.76 2.98
1 Pekerjaan kolom beton K1 (400X400) 8 titik 10. 25 12 46.2 3.85
2 Pekerjaan kolom beton K2 (400X400) 12 titik 11. 28 12 57.96 4.83
3 Pekerjaan kolom beton K3 (400X400) 16 titik 12. 32 12 75.72 6.31
4 Pekerjaan kolom beton KL (200X400X2) 3 titik 13. 36 12 95.88 7.99

1.25
1 Pekerjaan Balok 180X250 63.1625 BJ BESI ULIR/DEFORM
2 Pekerjaan Balok 180X300 181.225 m' DIAMETER PANJANG BERAT BERAT
No.
3 Pekerjaan Balok 200X350 46.5 m' mm m kg/btg kg/m'
4 Pekerjaan Balok 200X400 6.5125 m' 1. 10 12 7.4 0.62
5 Pekerjaan Balok 200X450 62.1 m' 2. 13 12 12.48 1.04
6 Pekerjaan Balok 250X400 28.2875 m' 3. 16 12 18.96 1.58
7 Pekerjaan Balok 250X500 318.85 m' 4. 19 12 26.76 2.23
706.6375 m' 5. 22 12 35.76 2.98
6. 25 12 46.2 3.85
7. 29 12 62.28 5.19
8. 32 12 75.72 6.31