Anda di halaman 1dari 10

RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBUATAN TALUD PENAHAN TANAH LONGSOR PEMUKIMAN


LOKASI : DUSUN CIJERUK DESA SURUSUNDA KECAMATAN KARANGPUCUNG
TAHUN ANGGARAN : 2022

KODE HARGA JUMLAH


NO URAIAN PEKERJAAN VOLUME SAT ANALISA SATUAN HARGA
(Rp) (Rp)
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 1.00 Unit Taksir 400,000.00 400,000.00
2 Pengukuran / bouwplank 1.00 Unit Taksir 340,000.00 340,000.00
JUMLAH I 740,000.00
II PEKERJAAN TALUD
1 Galian Tanah 53.71 m3 A.2.3.1.1 60,425.75 3,245,587.88
2 urugan Tanah Kembali 13.43 m3 A.2.3.1.9 43,851.50 588,837.94
3 urugan Tanah Setempat 14.14 m3 A.2.3.1.11.b 116,570.30 1,648,770.32
4 Urugan Pasir Bawah Pondasi 3.20 m3 A.2.3.1.11. 153,530.30 491,296.96
5 Pasangan Turap Batu Kali 1 : 6 88.00 m3 A.3.2.1.4 770,623.59 67,814,875.92
6 Plesteran 1 : 4 16.00 m2 A,4,4,2.4 52,379.91 838,078.56
7 Acian 16.00 m2 A,4,4,2.27 31,247.70 499,963.20
8 Siar-an 1 :2 76.80 m2 A,4,4,2.26 50,658.63 3,890,582.78
9 Pasang Pipa Kapiler PVC 2" - 1 m 64.00 bh Dihitung 1 44,562.87 2,852,023.68
10 Cerucuk Bambu 96.00 bh Dihitung 2 23,856.47 2,290,221.12
JUMLAH II 84,160,238.37
JUMLAH I - II 84,900,238.37
PPN 10 % 8,490,023.84
TOTAL 93,390,262.21
DIBULATKAN 93,390,000.00

Terbilang : Sembilan puluh tiga juta lima ratus ribu rupiah

Cilacap, April 2022


Kepala Pelaksana
Badan Penanggulangan Bencana Daerah

Drs. WIJONARDI, MM,


NIP. 19630415 198503 1 022
1.00 1.00
1.00 1.00
-
32.00
53.71 53.71 28.80 24.91 - -
13.43 13.43
14.14 14.14 14.14 -
3.20 3.20 3.20 -
88.00 88.00 25.60 62.40 - -
16.00 16.00 16.00 -
16.00 16.00
76.80 76.80 76.80 -
64.00 64.00 64.00 -
96.00 96.00 96.00 -

85,263,690.91
- 363,452.54

93,790,060.00
400,060.00

93,500,000.00
- 110,000.00
ANALISA HARGA SATUAN PEKERJAAN

PEKERJAAN PEMBUATAN TALUD PENAHAN TANAH LONGSOR PEMUKIMAN


LOKASI DUSUN CIJERUK DESA SURUSUNDA KECAMATAN KARANGPUCUNG
TAHUN ANGGARAN 2022

1 A.2.3.1.1 1 m3 Menggali Tanah Biasa Sedalam 1 m


A TENAGA 54,932.50
L.01 0.75 OH Pekerja 70,000.00 52,500.00
L.04 0.025 OH Mandor 97,300.00 2,432.50
B BAHAN
C PERALATAN
D Jumlah A + B + C 54,932.50
E Overhead & Profit 10% 5,493.25
F Harga Satuan Pekerjaan (D+E) 60,425.75

2 A.2.3.1.9 1 m3 Pengurugan Kembali


Pengurugan Kembali di hitung
dari 1/3 kali koefisien Pekerjaan
galian
A TENAGA 39,865.00
0 0.50 OH Pekerja 70,000.00 35,000.00
L.01 0.050 OH Mandor 97,300.00 4,865.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 39,865.00
E Jumlah A + B + C 10% 3,986.50
F Harga Satuan Pekerjaan (D+E) 43,851.50

3 A.2.3.1.11 1 m3 Urugan Pasir


A TENAGA 21,973.00
0 0.30 OH Pekerja 70,000.00 21,000.00
L.01 0.01 OH Mandor 97,300.00 973.00
B BAHAN 117,600.00
1.2 m3 Pasir Urug 98,000.00 117,600.00
C PERALATAN
D Jumlah A + B + C 139,573.00
E Jumlah A + B + C 10% 13,957.30
F Harga Satuan Pekerjaan (D+E) 153,530.30

4 A.2.3.1.11.b 1 m3 Urugan Tanah


A TENAGA 21,973.00
L.01 0.30 OH Pekerja 70,000.00 21,000.00
0 0.01 OH Mandor 97,300.00 973.00
B BAHAN 84,000.00
1.2 m3 Tanah Urug 70,000.00 84,000.00
C PERALATAN
D Jumlah A + B + C 105,973.00
E Jumlah A + B + C 10% 10,597.30
F Harga Satuan Pekerjaan (D+E) 116,570.30

5 A.3.2.1.4 1 m3 Pekerjaan Pondasi Batu Belah 1SP : 6 PP


A TENAGA 183,802.50
0 1.5 OH Pekerja 70,000.00 105,000.00
0 0.750 OH Tukang Batu 86,100.00 64,575.00
0 0.075 OH Kepala Tukang 92,400.00 6,930.00
0 0.075 OH Mandor 97,300.00 7,297.50
B BAHAN 516,764.40
1.2 m3 Batu Belah 15/20 248,000.00 297,600.00
117 Kg Portland Sement 1,200.00 140,400.00
0.561 m3 Pasir Pasang 140,400.00 78,764.40
C PERALATAN
D Jumlah A + B + C 700,566.90
E Jumlah A + B + C 10% 70,056.69
F Harga Satuan Pekerjaan (D+E) 770,623.59

6 A,4,4,2.4 1 m2 Pekerjaan Plesteran 1 Pc : 4 Pp Tebal 15 mm


A TENAGA 36,760.50
0 0.3 OH Pekerja 70,000.00 21,000.00
0 0.15 OH Tukang batu 86,100.00 12,915.00
0 0.015 OH Kepala Tukang 92,400.00 1,386.00
0 0.015 OH Mandor 97,300.00 1,459.50
B BAHAN 10,857.60
6.240 Kg Portland Sement 1,200.00 7,488.00
0.024 m3 Pasir Pasang 140,400.00 3,369.60
C PERALATAN
D Jumlah A + B + C 47,618.10
E Jumlah A + B + C 10% 4,761.81
F Harga Satuan Pekerjaan (D+E) 52,379.91

7 A,4,4,2.26 1 m2 Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp


A TENAGA 36,760.50
0 0.3 OH Pekerja 70,000.00 21,000.00
0 0.15 OH Tukang batu 86,100.00 12,915.00
0 0.015 OH Kepala Tukang 92,400.00 1,386.00
0 0.015 OH Mandor 97,300.00 1,459.50
B BAHAN 9,292.80
6.34 Kg Portland Sement 1,200.00 7,608.00
0.012 m3 Pasir Pasang 140,400.00 1,684.80
C PERALATAN
D Jumlah A + B + C 46,053.30
E Overhead & Profit 10% 4,605.33
F Harga Satuan Pekerjaan (D+E) 50,658.63

8 A,4,4,2.27 1 m2 Pekerjaan Acian


A TENAGA 24,507.00
0 0.20 OH Pekerja 70,000.00 14,000.00
0 0.10 OH Tukang batu 86,100.00 8,610.00
0 0.010 OH Kepala Tukang 92,400.00 924.00
0 0.010 OH Mandor 97,300.00 973.00
B BAHAN 3,900.00
3.25 Kg Portland Sement 1,200.00 3,900.00
C PERALATAN
D Jumlah A + B + C 28,407.00
E Overhead & Profit 10% 2,840.70
F Harga Satuan Pekerjaan (D+E) 31,247.70

9 Dihitung 1 1 m2 Pekerjaan Pasang pipa kapiler 2" /m1


A Tenaga 18,207.70
0.19 OH Tukang Batu 86,100.00 16,359.00
0.019 OH Mandor 97,300.00 1,848.70
B Bahan 22,304.00
0.25 btg PVC 2" 65,600.00 16,400.00
30% Perlengkapan 19,680.00 5,904.00

D Jumlah A + B + C 40,511.70
E Overhead & Profit 10% 4,051.17
F Harga Satuan Pekerjaan (D+E) 44,562.87

10 Dihitung 2 1 m2 Pekerjaan Crucuk Bambu /m1


A Tenaga 18,207.70
0.19 OH Tukang Batu 86,100.00 16,359.00
0.019 OH Mandor 97,300.00 1,848.70
B Bahan 3,480.00
0.2 btg Bambu 12,000.00 2,400.00
30% Perlengkapan 3,600.00 1,080.00

D Jumlah A + B + C 21,687.70
E Overhead & Profit 10% 2,168.77
F Harga Satuan Pekerjaan (D+E) 23,856.47

Cilacap, April 2022


Kepala Pelaksana
Badan Penanggulangan Bencana Daerah

Drs. WIJONARDI, MM,


NIP. 19630415 198503 1 022
DAFTAR HARGA SATUAN PEKERJAAN

PEKERJAAN : PEMBUATAN TALUD PENAHAN TANAH LONGSOR PEMUKIMAN


LOKASI : DUSUN CIJERUK DESA SURUSUNDA KECAMATAN KARANGPUCUNG
TAHUN ANGGARAN : 2022

NO. KODE URAIAN PEKERJAAN SAT

1 A.2.3.1.1 Galian Tanah m3

2 A.2.3.1.9 urugan Tanah Kembali m3

3 A.2.3.1.11.b urugan Tanah Setempat m3

4 A.2.3.1.11. Urugan Pasir Bawah Pondasi m3

5 A.3.2.1.4 Pasangan Turap Batu Kali 1 : 6 m3

6 A,4,4,2.4 Plesteran 1 : 4 m2

7 A,4,4,2.27 Acian m2

8 A,4,4,2.26 Siar-an 1 :2 m2

9 Dihitung Pasang Pipa Kapiler PVC 2" - 1 m bh

10 Dihitung Cerucuk Bambu bh

Cilacap, April 2022


Kepala Pelaksana
Badan Penanggulangan Bencana Daerah

Drs. WIJONARDI, MM,


NIP. 19630415 198503 1 022
N

R PEMUKIMAN
AN KARANGPUCUNG

HARGA
SATUAN PEKERJAAN
(Rp)

60,425.75

43,851.50

116,570.30

153,530.30

770,623.59

52,379.91

31,247.70

50,658.63

44,562.87

23,856.47

p, April 2022
la Pelaksana
langan Bencana Daerah

JONARDI, MM,
415 198503 1 022
DAFTAR HARGA BAHAN / MATERIAL

PEKERJAAN : PEMBUATAN TALUD PENAHAN TANAH LONGSOR PEMUKIMAN


LOKASI : DUSUN CIJERUK DESA SURUSUNDA KECAMATAN KARANGPUCUNG
TAHUN ANGGARAN : 2022

HARGA SATUAN
NO. JENIS BAHAN SATUAN
(Rp)

I BAHAN / MATERIAL

1 Pasir Urug m3 98,000.00


2 Tanah Urug m3 70,000.00
3 Batu Belah m3 248,000.00
4 Pasir Pasang m3 140,400.00
5 Portland Sement kg 1,200.00
6 Bambu bh 12,000.00
7 Pipa 2" bh 65,600.00

II TENAGA KERJA

1 Pekerja OH 70,000.00
2 Tukang batu OH 86,100.00
3 Kepala Tukang OH 92,400.00
4 Mandor OH 97,300.00

Cilacap, April 2022


Kepala Pelaksana
Badan Penanggulangan Bencana Daerah

Drs. WIJONARDI, MM,


NIP. 19630415 198503 1 022