ADDENDUM

PROGRAM : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)


KEGIATAN : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
SUB KEGIATAN : PERENCANAAN PENYEDIAAN PSU PERMUKIMAN
PEKERJAAN :
PERENCANAAN PEMBANGUNAN MCK JORONG LOMPATAN KABUPATEN TANAH DATAR
LOKASI : KAB. TANAH DATAR
NO. KONTRAK : 126/SPK.KPA/FISIK.PSU/KP-PERKIMTAN/X-2021
TANGGAL KONTRAK : 4 OKTOBER 2021
NO. KONTRAK ADD : 126.ADD-01/SPK.KPA/FISIK.PSU/KP-PERKIMTAN/X-2021
TANGGAL KONTRAK ADD : 7 OKTOBER 2021

MC-0 PEKERJAAN KURANG PEKERJAAN TAMBAH ADDENDUM


HARGA
NO. URAIAN PEKERJAAN STN JUMLAH HARGA Bobot JUMLAH JUMLAH JUMLAH Bobot KETERANGAN
VOLUME SATUAN VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
A PEKERJAAN PENDAHULUAN & PERSIAPAN
I Plank Nama Proyek Ls 1.00 200,000 200,000 0.00 - - - - 1.00 200,000 0.00
II Perlengkapan K3 - - - - - - - - -
1 Safety helmet Bh 200000.00 40,000 8,000,000,000 0.02 - - - - 200,000.00 8,000,000,000 0.02
2 Sarung tangan Bh 50000.00 10,000 500,000,000 0.00 - - - - 50,000.00 500,000,000 0.00
3 Rompi Bh 375000.00 75,000 28,125,000,000 0.07 - - - - 375,000.00 28,125,000,000 0.07
4 Rambu Peringatan Bh 100000.00 100,000 10,000,000,000 0.03 - - - - 100,000.00 10,000,000,000 0.03
5 sepatu Boot Bh 70000.00 70,000 4,900,000,000 0.01 - - - - 70,000.00 4,900,000,000 0.01
6 Prokest Covid Ls 300000.00 300,000 90,000,000,000 0.23 - - - - 300,000.00 90,000,000,000 0.23
III Managemen Mutu Ls 1900000.00 1,900,000 3,610,000,000,000 9.16 - - - - ### ### 9.16
0.00 - - - - - - - - - -
B PEKERJAAN PEMBONGKARAN DAN PEMBERSIHAN 0.00 - - - - - - - - - -
I Pekerjaan Pembongkaran Keramik Lama - - - - - - - - - -
1 Pembongkaran Keramik Lantai M2 232080.00 8,000 1,856,640,000 0.00 - - - - 232,080.00 1,856,640,000 0.00
2 Pembongkaran Keramik Dinding M2 453050.00 8,500 3,850,925,000 0.01 - - - - 453,050.00 3,850,925,000 0.01
II Pekerjaan Pembongkaran Dinding Bata dan Pipa - - - - - - - - - -
1 Pembongkaran Dinding Bata Pemisah Urinor T.Wudhu Wanita m3 1910182.89 834,141 1,593,361,866,047 4.04 - - - - ### ### 4.04
2 Pembongkaran Pipa-Pipa Air Bersih Lama Ls 300000.00 300,000 90,000,000,000 0.23 - - - - 300,000.00 90,000,000,000 0.23
3 Pembongkaran Pintu Toilet Lama Ls 100000.00 100,000 10,000,000,000 0.03 - - - - 100,000.00 10,000,000,000 0.03
4 Pembongkaran Kozen Ventilasi Ls 100000.00 100,000 10,000,000,000 0.03 - - - - 100,000.00 10,000,000,000 0.03
5 Pembuangan Sisa-Sisa Bongkaran Ke Tempat Pembuangan Ls 800000.00 800,000 640,000,000,000 1.62 - - - - 800,000.00 640,000,000,000 1.62
( Termasuk Sewa Mobil L300, Upah Muat dan Pembuangan ) - - - - - - - - - -
6 Pembongkaran Toilet Lama Ls 300000.00 300,000 90,000,000,000 0.23 - - - - 300,000.00 90,000,000,000 0.23
III M2 2181481.50 19,388 42,293,472,581 0.11 - - - - ### 42,293,472,581 0.11
Pengikisan/pengerokan dan Pembersihan permukaan cat lama Bagian Dalam
- - - - - - - - - -
C PEKERJAAN PASANGAN DINDING DAN KERAMIK - - - - - - - - - -
I PASANGAN DINDING 1/2 BATA SP 14 - - - - - - - - - -
1 Dinding Pembatas Urinor Untuk T. Wudhu Wanita M2 133,902 - - - - - - - - -
1 Dinding Pembatas T.Wudhu M2 899819.29 133,902 120,487,314,574 0.31 - - - - 899,819.29 120,487,314,574 0.31
II PEKERJAAN PASANGAN KERAMIK 0.00 - - - - - - - - - -
1 Pasangan Keramik Lantai 25x25 ( IKAD ) Kasar M2 9617934.41 296,667 2,853,320,863,418 7.24 - - - - ### ### 7.24
2 Pasangan Dinding Keramik 25x40 Polished ( IKAD ) Type 1 m2 28427728.48 361,170 10,267,256,340,720 26.06 - - - - ### ### 26.06
3 Pasangan Dinding Keramik 25x40 Polisher ( IKAD ) Type 2 M2 361,170 - - - - - - - - -
3 Pasangan Bon-Bon Keramik m 3927207.47 69,214 271,818,091,042 0.69 - - - - ### 271,818,091,042 0.69
- - - - - - - - - -
D PEKERJAAN KUZEN, DAUN PINTU DAN VENTILASI - - - - - - - - - -
I Pekerjaan Kuzen Aluminium - - - - - - - - - -
1 Kuzen Kayu Untuk Pinti P3 m3 8,111,917 - - - - - - - - -
1 Kuzen Aluminium Untuk Pintu P2 m 1519872.20 165,204 251,088,206,993 0.64 - - - - ### 251,088,206,993 0.64
II Pekerjaan Daun Pintu Alumunium P2 - - - - - - - - - -
II Pasangan Daun Pintu - - - - - - - - - -
1 Daun Pintu Panil Kayu Kelas II Untuk P1 M2 816,625 - - - - - - - - -
2 Daun Pintu Panil Kayu Kelas II Untuk P3 M2 816,625 - - - - - - - - -
3 Daun Pintu Fiber untuk P2 ( 0,7*1.95) Bh 550,000 - - - - - - - - -
4 Pasangan Kaca tbl. 5 mm untuk Ventilasi M2 159,346 - - - - - - - - -
5 Pasangan Kunci Tanam Pintu Antik Bh 419,678 - - - - - - - - -
6 Pasangan Engsel Pintu 4 Bh 54,384 - - - - - - - - -
7 Pasangan Grendel Pintu Bh 102,410 - - - - - - - - -
1 Pekerjaan Daun Pintu Alumunium P2 M2 1486108.09 558,687 830,269,639,211 2.11 - - - - ### 830,269,639,211 2.11
2 Pekerjaan Kuzen Ventilasi M2 594571.07 8,111,917 4,823,111,157,722 12.24 - - - - 594,571.07 ### 12.24
3 Pas. Kaca tbl.5 mm untuk ventilasi Bh 446965.53 159,346 71,222,169,343 0.18 - - - - 446,965.53 71,222,169,343 0.18
- - - - - - - - - -
E PEKERJAAN PENGECATAN - - - - - - - - - -
I Pekerjaan Pengecatan Dinding - - - - - - - - - -
1 Pengecatan Dinding Dalam dengan Jotun Interior( 1 lapis Alkali, 2 Lapis Cat Penutup ) M2 2513585.25 23,034 57,897,922,649 0.15 - - - - ### 57,897,922,649 0.15
2 Pengecatan Dinding Luar dengan Jotun Exterior ( 1 lapis Alkali, 2 Lapis Cat Penutup ) M2 251583.75 35,310 8,883,422,213 0.02 - - - - 251,583.75 8,883,422,213 0.02
3 Pengecatan Dinding Masjid dan Dinding Luar MCK dengan Jotun Exterior ( 1 lapis Alkali, 2 Lapis Cat Penutup ) M2 4915954.42 35,310 173,582,350,561 0.44 ### 173,582,350,561 0.44
II Pekerjaan Pengecatan Kayu - - - - - - - - - -
1 Pengecatan Kuzen Kayu (1lapis plamuur, 1 lapis cat dasar,2 lapis cat penutup) M2 66011.63 49,820 3,288,706,132 0.01 - - - - 66,011.63 3,288,706,132 0.01
2 Pengecatan Daun Pintu Kayu (1lapis plamuur, 1 lapis cat dasar,2 lapis cat penutup) M2 49,820 - - - - - - - - -
- - - - - - - - - -
III Pekerjaan Pengecatan Besi - - - - - - - - - -
1 Pengecatan Pintu Besi M2 136913.92 37,400 5,120,580,608 0.01 - - - - 136,913.92 5,120,580,608 0.01
- - - - - - - - - -
F PEKERJAAN PLAFOUND - - - - - - - - - -
I Pekerjaan Pasangan Plafound Pvc ( JAVAPOND ) + Rangka Hollow Zinclaume4x4cm - - - - - - - - - -
1 Plafound Area Wanita M2 207,478 - - - - - - - - -
2 Plafound Area Pria M2 207,478 - - - - - - - - -
II Pekerjaan Pasangan Lest Pvc ( JAVAPOND ) Cutting L - - - - - - - - - -
1 Plafound Area Wanita M 16,528 - - - - - - - - -
2 Plafound Area Pria M 16,528 - - - - - - - - -
- - - - - - - - - -
G PEKERJAAN INSTALASI LISTRIK DAN LAMPU - - - - - - - - - -
1 Pemasangan Titik Lampu ( Downligh LED 18 Watt ) Putih ( Philips ) Ttk 1420000.00 355,000 504,100,000,000 1.28 - - - - ### 504,100,000,000 1.28
2 Pemasangan Titik Lampu ( Downligh LED 8 Watt ) Kuning ( Philips ) Ttk 1960000.00 245,000 480,200,000,000 1.22 - - - - ### 480,200,000,000 1.22
3 Pemasangan Titik Lampu ( Downligh LED 8 Watt ) Putih ( Philips ) Ttk 980000.00 245,000 240,100,000,000 0.61 - - - - 980,000.00 240,100,000,000 0.61
4 Pasangan Saklar Seri bh 80000.00 40,000 3,200,000,000 0.01 - - - - 80,000.00 3,200,000,000 0.01
5 Pasangan Saklar Tunggal bh 140000.00 35,000 4,900,000,000 0.01 - - - - 140,000.00 4,900,000,000 0.01
- - - - - - - - - -
H PEKERJAAN SANITASI - - - - - - - - - -
1 Pas. Kloset jongkok Bh 1384033.20 692,017 957,773,949,351 2.43 - - - - ### 957,773,949,351 2.43
2 Pas. Pipa PVC Ø 3/4" Saluran kran wudhu, urinor,toilet m' 665441.92 31,992 21,289,084,081 0.05 - - - - 665,441.92 21,289,084,081 0.05
3 Pas. Pipa PVC Ø 3/4" untuk Kran m' 108774.16 31,992 3,479,946,436 0.01 - - - - 108,774.16 3,479,946,436 0.01
4 Pas. Kran Air Ø 3/4 Bh 3900000.00 195,000 760,500,000,000 1.93 - - - - ### 760,500,000,000 1.93
5 Pas. Stop Kran Air Ø 3/4" Bh 75000.00 25,000 1,875,000,000 0.00 - - - - 75,000.00 1,875,000,000 0.00
6 Pas. Pipa PVC Ø 4" m' 1061222.80 132,653 140,774,228,905 0.36 - - - - ### 140,774,228,905 0.36
7 Pas. Mesin pompa Air BH 850000.00 850,000 722,500,000,000 1.83 - - - - 850,000.00 722,500,000,000 1.83
8 Pas. Septiktank 0.00 - - - - - - - - - -
a Galian Tanah Septiktank (Lingkaran) m3 287113.75 91,438 26,252,963,516 0.07 - - - - 287,113.75 26,252,963,516 0.07
b Pembesian Penutup Septiktank Kg 80334.69 14,727 1,183,072,972 0.00 - - - - 80,334.69 1,183,072,972 0.00
c Plat Lantai Beton t. 15 cm (Penutup Septiktank) m3 244946.39 924,675 226,495,784,363 0.57 - - - - 244,946.39 226,495,784,363 0.57
d Pipa Beton Bertulan D100 Bh 1980784.80 1,980,785 3,923,508,423,911 9.96 - - - - ### ### 9.96
- - - - - - - - - -
1 Pasangan Pipa 1 x1/2 untuk Saluran Kran berwudhu, urinor dan Bak Toilet M 51,000 - - - - - - - - -
2 Pasangan Pipa 3/2 untuk Kran M 32,000 - - - - - - - - -
- - - - - - - - - -
I PEKERJAAN PENAMBAHAN TEMPAT WUDHU BARU DISAMPING MASJID - - - - - - - - - -
I Pekerjaan Galian Tanah - - - - - - - - - -
1 Galian Tanah Untuk Penempatan Sloof m3 86,625 - - - - - - - - -
1 Galian Tanah Untuk Tempat Wudhu Baru m3 111698.22 91,438 10,213,406,106 0.03 - - - - 111,698.22 10,213,406,106 0.03
II Pekerjaan Pemasangan Sloof 15/20 cm 0.00 - - - - - - - - - -
1 Beton Camp 123 setara K175 m3 952,272 - - - - - - - - -
2 Pembesian Kg 16,000 - - - - - - - - -
3 Bekisting Sloof m2 178,090 - - - - - - - - -
III Pekerjaan Pasangan Dinding - - - - - - - - - -
1 Pasangan 1/2 Bata Sp 14 m2 272489.92 133,902 36,486,857,910 0.09 - - - - 272,489.92 36,486,857,910 0.09
2 Plesteran Sp 14 m2 78,349 - - - - - - - - -
3 Acian m2 47,883 - - - - - - - - -
IV Pekerjaan Lantai dan Keramik - - - - - - - - - -
1 Pas. Beton K-175 t. 15 cm m3 1571248.82 952,272 1,496,256,268,699 3.80 - - - - ### ### 3.80
2 Pasangan Keramik Lantai Ukuran 25*25 ( Ikad ) Kasar m2 2276916.92 296,667 675,485,429,572 1.71 - - - - ### 675,485,429,572 1.71
3 Pasangan Dinding Keramik 25x40 ( Ikad ) Polished Type 1 m2 6200935.97 361,170 2,239,595,021,139 5.68 - - - - ### ### 5.68
4 Pas. Bon-Bon Keramik m' 2385809.68 69,214 165,131,646,074 0.42 - - - - ### 165,131,646,074 0.42
V Pekerjaan Pengecatan - - - - - - - - - -
1 Pengecatan Dinding Dalam dengan Jotun Interior( 1 lapis Alkali, 2 Lapis Cat Penutup ) m2 23,034 - - - - - - - - -
VI Pekerjaan Sanitasi - - - - - - - - - -
1 Pasangan Pipa 1 x1/2 untuk Saluran Kran berwudhu dari Tangki air ke lokasi M 51,000 - - - - - - - - -
2 Pasangan Pipa 3/2 untuk Kran M 32,000 - - - - - - - - -
1 Pas. Pipa PVC Ø 3/4" untuk saluran Kran berwudhu dari Tangki air ke lokasi M 1471650.40 31,992 47,081,628,257 0.12 - - - - ### 47,081,628,257 0.12
2 Pas. Pipa PVC Ø 3/4" untuk Kran M 22394.68 31,992 716,459,560 0.00 - - - - 22,394.68 716,459,560 0.00
3 Pasangan Kran Stainlesee Bh 1365000.00 195,000 266,175,000,000 0.68 - - - - ### 266,175,000,000 0.68
VII Pekerjaan Instalasi Titik Lampu - - - - - - - - - -
1 Pemasangan Titik Lampu ( Downligh LED 8 Watt ) Putih ( Philips ) bh 245,000 - - - - - - - - -
2 Pasangan Saklar Tunggal bh 35,000 - - - - - - - - -
VIII Pekerjaan Plat Deker - - - - - - - - - -
1 Beton Camp 123 setara K175 m3 952,272 - - - - - - - - -
2 Pembesian Kg 16,000 - - - - - - - - -
3 Bekisting Lantai m2 388,824 - - - - - - - - -
- - - - - - - - - -
IX PEKERJAAN PAGAR BESI - - - - - - - - - -
1 Besi Holoow 20 x 40 x 1,2 mm Kg 5736169.65 48,923 280,627,759,604 0.71 - - - - ### 280,627,759,604 0.71
2 Besi Holoow 40 x 40 x 1,2 mm Kg 1746647.40 48,923 85,450,357,549 0.22 - - - - ### 85,450,357,549 0.22
Pengecatan Besi Holoow 20 x 40 x 1,2 mm M2 580388.16 37,400 21,706,517,184 0.06 - - - - 580,388.16 21,706,517,184 0.06
Pengecatan Besi Holoow 40 x 40 x 1,2 mm M2 773850.88 37,400 28,942,022,912 0.07 - - - - 773,850.88 28,942,022,912 0.07
- - - - - - - - - -
J PEKERJAAN AKHIR - - - - - - - - - -
1 Pek. Pembersihan Akhir Ls 230000.00 230,000 52,900,000,000 0.13 - - - - 230,000.00 52,900,000,000 0.13
JUMLAH 39,395,135,696,915 100 - - ### 100
PPN 10% 3,939,513,569,691 - - ###
TOTAL 43,334,649,266,606 - - ###

Diperiksa dan Disetujui oleh,


KONSULTAN PENGAWAS -
CV, GESTALT ARCHITECTURE -
-
0

Oddy Satrio Nugroho, ST


Inspector 0
0
DAFTAR HARGA DASAR SATUAN UPAH

HARGA HARGA
No. URAIAN KODE KETERANGAN SATUAN PERJAM SATUAN PERHARI
( Rp.) ( Rp.)

1 Pekerja L01 Rp 15,000.00 105,000.00


2 Tukang L02 Rp 21,428.57 150,000.00
3 Kepala Tukang L03 Rp 25,000.00 175,000.00
4 Mandor L04 Rp 25,000.00 175,000.00
5 Juru ukur L05 Rp 25,714.29 180,000.00
6 Pembantu juru ukur L06 Rp 15,000.00 105,000.00
7 Ahli muda L07
Upah dihitung
8 Ahli madya L08
dengan jumlah
9 Ahli Utama L09 hari kerja di
7 Sopir / Driver L10 asumsikan 25 hari Rp 15,000.00 105,000.00
8 Pembantu Sopir / Driver L11 dalam sebulan. Rp 15,000.00 105,000.00
9 Operator L12 Jam kerja efektif Rp 25,714.29 180,000.00
diasumsikan 7 jam
10 Pembantu Operator L13 sehari. Rp 15,000.00 105,000.00
11 Mekanik L14 Rp 25,714.29 180,000.00
12 Pembantu Mekanik L15 Rp 15,000.00 105,000.00
13 Desain engineer L16 Rp 25,714.29 180,000.00
5 Operator komputer/printer/ploter L17 Rp 17,142.86 120,000.00
6 Drafter Cad / Estimator L18 Rp 25,714.29 180,000.00
16 Penjaga malam L19 Rp 20,571.43 144,000.00
17 Juru Ukur/Drafter Cad/Estimator (D3) Rp 25,714.29 180,000.00

Harga Dasar Upah dan Bahan 4 dari 205


DAFTAR HARGA DASAR SATUAN BAHAN

HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)

A. KELOMPOK AIR,TANAH,BATU DAN SEMEN


1 Air M.02 M3 Rp 18,100.00
2 Pasir Pasang (Sedang) M01b M3 Rp 176,600.00 Base Camp
3 Pasir Beton (Kasar) M01a M3 Rp 176,500.00 Base Camp
4 Pasir Halus (untuk HRS) M01c M3 Rp 176,700.00 Base Camp
5 Pasir Urug M44 M3 Rp 115,800.00 Base Camp
6 Batu Kali M02 M3 Rp 192,600.00 Lokasi Pekerjaan
7 Agregat Pecah Mesin 20-30 mm (agregat kasar) M93 M3 Rp 245,400.00 Base Camp
8 Agregat Pecah Mesin 5-10 & 10-20 mm (agregat sedang) M92 M3 Rp 235,900.00 Base Camp
9 Agregat Pecah Mesin 0-5 mm (agregat halus) M91 M3 Rp 261,100.00 Base Camp
10 Bahan Agr.Base Kelas A M26 M3 Rp 300,850.00 Base Camp
11 Bahan Agr.Base Kelas B M27 M3 Rp 267,300.00 Base Camp
12 Bahan Agr.Base Kelas C M28 M3 Rp 252,450.00 Base Camp
13 Batu Pecah 5/10 M3 Rp 283,600.00
14 Batu Pecah 5/7 M3 Rp 279,500.00
15 Batu Pecah 3/4 M3 Rp 328,300.00
16 Batu Pecah 2/3 M3 Rp 334,800.00
17 Batu Pecah 1/2 M3 Rp 343,400.00
18 Split 0..5 - 1 cm M3 Rp 338,000.00
19 Filler M05 Kg Rp 2,000.00 Proses/Base Camp
20 Batu Belah M06 M3 Rp 172,400.00 Lokasi Pekerjaan
21 Gravel M07 M3 Rp 133,900.00 Base Camp
22 Bahan Tanah Timbunan M08 M3 Rp 125,000.00 Borrow Pit/quarry
23 Bahan Pilihan M09 M3 Rp 137,900.00 Quarry
24 Abu Batu / Pasir saring M.01 M3 Rp 271,200.00
25 Sirtu M16 M3 Rp 171,400.00 Lokasi Pekerjaan
26 Kerikil/agregat Beton M.06 M3 Rp 174,300.00
27 Tanah liat M.17a M3 Rp 110,500.00
28 Batu brojol (untuk bronjong) M02a M3 Rp 170,400.00
29 Bahan Aditif (Caldbon, Strorox, dll) M.03 Ltr Rp 50,400.00
30 Batu bata / merah bakar kelas I M.04.a Bh Rp 900.00
31 Batu bata / merah bakar biasa M.04.b Bh Rp 700.00
32 Batu bata / merah bakar kelas II M.04.c Bh Rp 800.00
33 Batu candi M.05 M2 Rp -
34 Batu muka M.06 M2 Rp -
35 Kapur Sirih M.11a kg Rp -
36 Semen / PC (50kg) M12 Zak Rp 62,000.00 Base Camp
37 Semen / PC (kg) M12 Kg Rp 1,240.00 Base Camp
38 Semen Putih M12a kg Rp 4,800.00
39 Semen Merah kg Rp 13,800.00
40 Lem Rakol tube Rp 18,600.00
41 Semen Warna (Tepung Affa) M.15b Kg Rp 15,400.00
42 Additive M67a Ltr Rp 75,000.00
43 Curing Compound M98 Ltr Rp 46,200.00
44 Elastomer M62 Bh Rp 642,500.00
45 Arbocell M45 Kg. Rp 93,700.00 Base Camp
46 Chipping M41 M3 Rp 259,000.00 Base Camp
47 Chipping (kg) M41kg Kg Rp - Base Camp
48 Geotextile M30 M2 Rp - Lokasi Pekerjaan
49 Plastik Filter M23 M2 Rp 53,800.00
50 Polytene 125 mikron M97 Kg Rp 23,100.00
51 Plastik cor (Hitam) M23a M2 Rp 7,300.00
52 Lempengan rumput / Gebalan Rumput M32 M2 Rp 25,000.00 Lokasi Pekerjaan
53 Kapur M40 M3 Rp 860,000.00 Hasil Proses
54 Bata Ringan 20 x 60 x 10 cm Bh Rp 14,800.00 Kunango Jantan
55 Bata Ringan 20 x 60 x 7.5 cm Bh Rp 13,800.00 Kunango Jantan

B. KELOMPOK BAHAN BETON PABRIKASI


1 Beton ready mixed K-125 M.09a m3 Rp 922,900.00
2 Beton ready mixed K-150 M.09b m3 Rp 926,600.00
3 Beton ready mixed K-175 M.09c m3 Rp 999,800.00
4 Beton ready mixed K-200 M.09d m3 Rp 979,100.00
5 Beton ready mixed K-225 M.09e m3 Rp 1,036,900.00
6 Beton ready mixed K-250 M.09f m3 Rp 1,083,100.00
7 Beton ready mixed K-275 M.09g m3 Rp 1,105,100.00
8 Beton ready mixed K-300 M.09h m3 Rp 1,132,400.00
9 Beton ready mixed K-350 M.09i m3 Rp 1,200,000.00

Harga Dasar Upah dan Bahan 5 dari 205


HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
10 Beton ready mixed K-400 M.09j m3 Rp 1,253,900.00
11 Beton ready mixed K-450 M.09k m3 Rp 1,323,700.00
12 Beton ready mixed K-500 M.09l m3 Rp 1,354,800.00
13 Kerb Type A M77 Bh Rp - Base Camp
14 Paving block t = 6 cm type I k.175 (Warna Merah ) Bh Rp 5,500.00
15 Paving block t = 6 cm type balok k.175 (Warna Natural) Bh Rp 4,500.00
16 Paving block t = 6 cm type hexagon k.175 (Warna Merah) Bh Rp 8,800.00
17 Paving block t = 8 cm type I k.250 (Warna Merah) Bh Rp 12,500.00
18 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp 10,800.00
19 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp -
20 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp -
21 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp -
22 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp -
23 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp -
24 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp -
25 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp -
26 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp -
27 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp -
28 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp -
29 Paving block t = 8 cm type hexagon k.250 (Warna Merah) Bh Rp -
30 Paving block t = 8 cm type hexagon k.250 (Warna Merah) M78 Bh Rp - Lokasi Pekerjaan
31 Paving block t = 8 cm type hexagon k.250 (Warna Merah) M38 Bh Rp - Lokasi Pekerjaan
32 Paving block t = 8 cm type hexagon k.250 (Warna Merah) M50 Bh Rp - Pelabuhan terdekat
33 Kerb Tipe L mutu K-300 Bh Rp 176,000.00
34 Kerb Tipe I mutu K-300 Bh Rp 143,000.00
35 Kerb Tipe C mutu K-300 Bh Rp 159,500.00
36 Paving Block 10 x 20 cm t = 6 cm (Natural), Beton Mutu Sedang Pcs Rp 5,935.00 1 M2 = 50 Pcs
37 Paving Block 10 x 20 cm t = 6 cm (Berwarna), Beton Mutu Sedang Pcs Rp 6,580.00 1 M2 = 50 Pcs
38 Paving Block 10 x 20 cm t = 8 cm (Natural), Beton Mutu Sedang Pcs Rp 7,240.00 1 M2 = 50 Pcs
39 Paving Block 10 x 20 cm t = 8 cm (Berwarna), Beton Mutu Sedang Pcs Rp 7,886.00 1 M2 = 50 Pcs
40 Paving Block 10 x 20 cm t = 10 cm (Natural), Beton Mutu Sedang Pcs Rp 8,599.00 1 M2 = 50 Pcs
41 Paving Block 10 x 20 cm t = 10 cm (Berwarna), Beton Mutu Sedang Pcs Rp 9,160.00 1 M2 = 50 Pcs
42 Paving Block 20 x 20 cm t = 6 cm (Natural), Beton Mutu Sedang Pcs Rp 12,128.00 1 M2 = 25 Pcs
43 Paving Block 20 x 20 cm t = 6 cm (Berwarna), Beton Mutu Sedang Pcs Rp 13,161.00 1 M2 = 25 Pcs
44 Paving Block 30 x 30 cm t = 6 cm (Natural), Beton Mutu Sedang Pcs Rp 28,655.00 1 M2 = 11 Pcs
45 Paving Block 30 x 30 cm t = 6 cm (Berwarna), Beton Mutu Sedang Pcs Rp 31,438.00 1 M2 = 11 Pcs
46 Ubin Pemandu (30 x 30 x 4 cm), Beton Mutu Sedang Pcs Rp 41,232.00 1 M2 = 11 Pcs
47 Paving Pemandu (30 x 30 x 6 cm), Beton Mutu Sedang Pcs Rp 45,100.00 1 M2 = 11 Pcs
48 Box Culvert 60 cm x 60 cm p = 100 cm t = 15 cm K-350 Pcs Rp 2,490,000.00 Besi Ø10 mm
49 Box Culvert 100 cm x 100 cm p = 100 cm t = 23 cm K-350 Pcs Rp 5,597,800.00 Besi Ulir 10 mm
50 Box Culvert 120 cm x 120 cm p = 300 cm t = 15 cm K-350 Pcs Rp - Besi Ulir 10 dan 19 mm
51 Box Culvert 150 cm x 150 cm p = 100 cm t = 25 cm K-350 Pcs Rp 10,709,700.00 Besi 12 dan 16 mm
52 Box Culvert 160 cm x 140 cm p = 120 cm t = 15 cm K-350 Pcs Rp - Besi Ø12, Ø10 dan Ø16 mm
53 Box Culvert 60 cm x 60 cm p = 100 cm t = 15 cm K-300 Pcs Rp 2,431,600.00 Besi Ø10 mm
54 Box Culvert 75 cm x 75 cm p = 300 cm t = 12,5 cm K-300 Pcs Rp - Besi Ulir 10 dan 19 mm
55 Box Culvert 100 cm x 100 cm p = 100 cm t = 23 cm K-300 Pcs Rp 4,656,700.00 Besi Ulir 10 mm
56 Box Culvert 100 cm x 150 cm p = 100 cm t = 20 cm K-300 Pcs Rp - Besi Ø12, Ulir 10 dan 16 mm
57 Box Culvert 120 cm x 120 cm p = 300 cm t = 15 cm K-300 Pcs Rp - Besi Ulir 10 dan 19 mm
58 Box Culvert 150 cm x 150 cm p = 100 cm t = 25 cm K-300 Pcs Rp 10,485,800.00 Besi 12 dan 16 mm
59 Box Culvert 160 cm x 140 cm p = 120 cm t = 15 cm K-300 Pcs Rp - Besi Ø12, Ø10 dan Ø16 mm
60 Box Culvert 150 cm x 150 cm p = 100 cm t = 25 cm K-350 Pcs Rp 10,709,700.00
61 Box Culvert 100 cm x 100 cm p = 100 cm t = 23 cm K-300 Pcs Rp 4,656,700.00
62 Box Culvert 220 cm x 220 cm p = 150 cm t = 25 cm K-350 Pcs Rp 29,277,800.00
63 U-Ditch 60 cm x 80 cm p = 100 cm t = 10 cm K-350 Pcs Rp 993,000.00 Besi 8 mm
64 U-Ditch 80 cm x 120 cm p = 100 cm t = 7 cm K-350 Pcs Rp 987,495.00 Besi 8 mm
65 U-Ditch 160 cm x 140 cm p = 120 cm t = 13 cm K-350 Pcs Rp 3,101,000.00 Besi Ulir 13 mm
66 U-Ditch 60 cm x 80 cm p = 100 cm t = 10 cm K-300 Pcs Rp 964,000.00 Besi 8 mm
67 U-Ditch 80 cm x 120 cm p = 100 cm t = 7 cm K-300 Pcs Rp 1,680,800.00 Besi 8 mm
68 U-Ditch 160 cm x 140 cm p = 120 cm t = 13 cm K-300 Pcs Rp 5,082,000.00 Besi Ulir 13 mm
69 U-Ditch 30 cm x 30 cm p = 120 cm t = 4.5 cm K-400 Pcs Rp 250,000.00
70 U-Ditch 60 cm x 60 cm p = 100 cm t = 10 cm K-400 Pcs Rp 900,000.00
71 U-Ditch 80 cm x 80 cm p = 100 cm t = 7 cm K-400 Pcs Rp 1,150,000.00
72 U-Ditch 150 cm x 120 cm p = 100 cm t = 20 cm K-350 Pcs Rp 1,300,000.00
73 U-Ditch 30 cm x 30 cm p = 120 cm t = 4.5 cm K-350 Pcs Rp 233,000.00
74 Sheet Pile Type W-325-A t = 32,5 cm p = 6 s/d 15 m M1 Rp 859,100.00 tebal = 11 cm
75 Sheet Pile Type W-325-A t = 32,5 cm p = 6 s/d 15 m M1 Rp 889,900.00 tebal = 11 cm
76 Sheet Pile Type W-350-A t = 32,5 cm p = 6 s/d 15 m M1 Rp 954,800.00 tebal = 12 cm
77 Sheet Pile Type W-350-A t = 32,5 cm p = 6 s/d 15 m M1 Rp 984,500.00 tebal = 12 cm
78 Mini Pile 20 x 20 cm Type A p = 3 s/d 12 m K-400 M1 Rp 209,000.00 Bottom/middle
79 Mini Pile 25 x 25 cm Type A p = 3 s/d 12 m K-400 M1 Rp 305,800.00 Bottom/middle
80 Square Pile 30 x 30 cm Type A p = 6 s/d 12 m K-500 M1 Rp 458,700.00 Bottom
Harga Dasar Upah dan Bahan 6 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
81 Square Pile 30 x 30 cm Type A p = 6 s/d 12 m K-500 M1 Rp 475,200.00 Middle
82 Square Pile 35 x 35 cm Type A p = 6 s/d 12 m K-500 M1 Rp 696,300.00 Bottom
83 Square Pile 35 x 35 cm Type A p = 6 s/d 12 m K-500 M1 Rp 807,400.00 Middle
84 Square Pile 40 x 40 cm Type A p = 6 s/d 12 m K-500 M1 Rp 867,900.00 Bottom
85 Square Pile 40 x 40 cm Type A p = 6 s/d 12 m K-500 M1 Rp 954,800.00 Middle
86 Square Pile 45 x 45 cm Type A p = 6 s/d 12 m K-500 M1 Rp 1,091,200.00 Bottom
87 Square Pile 45 x 45 cm Type A p = 6 s/d 12 m K-500 M1 Rp 1,195,700.00 Middle
88 Square Pile 50 x 50 cm Type A p = 6 s/d 12 m K-500 M1 Rp 1,474,000.00 Bottom
89 Square Pile 50 x 50 cm Type A p = 6 s/d 12 m K-500 M1 Rp 1,588,400.00 Middle
90 Gorong-gorong Ø 20 cm t = 5 cm K-175 Pcs Rp 272,000.00 Tulangan M6
91 Gorong-gorong Ø 20 cm t = 5 cm K-175 Pcs Rp 305,000.00 Tulangan M8
92 Gorong-gorong Ø 20 cm t = 5 cm K-175 Pcs Rp 209,000.00 NRCP
93 Gorong-gorong Ø 20 cm t = 5 cm K-250 Pcs Rp 246,000.00 Tulangan M6
94 Gorong-gorong Ø 20 cm t = 5 cm K-250 Pcs Rp 315,000.00 Tulangan M8
95 Gorong-gorong Ø 20 cm t = 5 cm K-250 Pcs Rp 213,000.00 NRCP
96 Gorong-gorong Ø 30 cm t = 5 cm K-175 Pcs Rp 393,000.00 Tulangan M6
97 Gorong-gorong Ø 30 cm t = 5 cm K-175 Pcs Rp 438,000.00 Tulangan M8
98 Gorong-gorong Ø 30 cm t = 5 cm K-175 Pcs Rp 300,000.00 NRCP
99 Gorong-gorong Ø 30 cm t = 5 cm K-250 Pcs Rp 399,000.00 Tulangan M6
100 Gorong-gorong Ø 30 cm t = 5 cm K-250 Pcs Rp 445,000.00 Tulangan M8
101 Gorong-gorong Ø 30 cm t = 5 cm K-250 Pcs Rp 310,000.00 NRCP
102 Gorong-gorong Ø 40 cm t = 5 cm K-175 Pcs Rp 477,000.00 Tulangan M6
103 Gorong-gorong Ø 40 cm t = 5 cm K-175 Pcs Rp 528,000.00 Tulangan M8
104 Gorong-gorong Ø 40 cm t = 5 cm K-175 Pcs Rp 370,000.00 NRCP
105 Gorong-gorong Ø 40 cm t = 5 cm K-250 Pcs Rp 485,000.00 Tulangan M6
106 Gorong-gorong Ø 40 cm t = 5 cm K-250 Pcs Rp 536,000.00 Tulangan M8
107 Gorong-gorong Ø 40 cm t = 5 cm K-250 Pcs Rp 377,500.00 NRCP
108 Gorong-gorong Ø 60 cm t = 6 cm K-175 Pcs Rp 681,000.00 Tulangan M6
109 Gorong-gorong Ø 60 cm t = 6 cm K-175 Pcs Rp 756,000.00 Tulangan M8
110 Gorong-gorong Ø 60 cm t = 6 cm K-175 Pcs Rp 527,500.00 NRCP
111 Gorong-gorong Ø 60 cm t = 6 cm K-250 Pcs Rp 694,300.00 Tulangan M6
112 Gorong-gorong Ø 60 cm t = 6 cm K-250 Pcs Rp 771,500.00 Tulangan M8
113 Gorong-gorong Ø 60 cm t = 6 cm K-250 Pcs Rp 551,000.00 NRCP
114 Gorong-gorong Ø 80 cm t = 8 cm K-175 Pcs Rp 986,000.00 Tulangan M6
115 Gorong-gorong Ø 80 cm t = 8 cm K-175 Pcs Rp 1,086,000.00 Tulangan M8
116 Gorong-gorong Ø 80 cm t = 8 cm K-175 Pcs Rp 787,000.00 NRCP
117 Gorong-gorong Ø 80 cm t = 8 cm K-250 Pcs Rp 1,010,000.00 Tulangan M6
118 Gorong-gorong Ø 80 cm t = 8 cm K-250 Pcs Rp 1,113,000.00 Tulangan M8
119 Gorong-gorong Ø 80 cm t = 8 cm K-250 Pcs Rp 811,000.00 NRCP
120 Gorong-gorong Ø 100 cm t = 10 cm K-175 Pcs Rp 1,427,000.00 Tulangan M6
121 Gorong-gorong Ø 100 cm t = 10 cm K-175 Pcs Rp 1,581,500.00 Tulangan M8
122 Gorong-gorong Ø 100 cm t = 10 cm K-175 Pcs Rp 1,136,000.00 NRCP
123 Gorong-gorong Ø 100 cm t = 10 cm K-250 Pcs Rp 1,466,300.00 Tulangan M6
124 Gorong-gorong Ø 100 cm t = 10 cm K-250 Pcs Rp 1,621,000.00 Tulangan M8
125 Gorong-gorong Ø 100 cm t = 10 cm K-250 Pcs Rp 1,175,500.00 NRCP
126 Gorong-gorong Ø 120 cm t = 10 cm K-175 Pcs Rp 1,566,300.00 Tulangan M6
127 Gorong-gorong Ø 120 cm t = 10 cm K-175 Pcs Rp 1,730,000.00 Tulangan M8
128 Gorong-gorong Ø 120 cm t = 10 cm K-175 Pcs Rp 1,275,500.00 NRCP
129 Gorong-gorong Ø 120 cm t = 10 cm K-250 Pcs Rp 1,611,200.00 Tulangan M6
130 Gorong-gorong Ø 120 cm t = 10 cm K-250 Pcs Rp 1,766,000.00 Tulangan M8
131 Gorong-gorong Ø 120 cm t = 10 cm K-250 Pcs Rp 1,320,300.00 NRCP
132 U-Ditch 30 x 30 x 120 cm t = 5 cm K-400 Unit Rp 480,000.00 Kunango Jantan
133 U-Ditch 30 x 30 x 120 cm t = 5 cm K-300 Unit Rp 465,000.00 Kunango Jantan
134 U-Ditch 60 x 80 x 100 cm t = 10 cm K-400 Unit Rp 1,455,000.00 Kunango Jantan
135 U-Ditch 60 x 80 x 100 cm t = 10 cm K-300 Unit Rp 1,405,000.00 Kunango Jantan
136 U-Ditch 80 x 80 x 100 cm t = 10 cm K-400 Unit Rp 1,525,000.00 Kunango Jantan
137 U-Ditch 80 x 80 x 100 cm t = 10 cm K-300 Unit Rp 1,470,000.00 Kunango Jantan
138 U-Ditch 80 x 80 x 120 cm t = 10 cm K-400 Unit Rp 1,700,000.00 Kunango Jantan
139 U-Ditch 80 x 80 x 120 cm t = 10 cm K-300 Unit Rp 1,620,000.00 Kunango Jantan
140 Box Culvert 150 x 150 x 100 cm t = 25 cm K-400 Unit Rp 13,750,000.00 Kunango Jantan
141 Box Culvert 150 x 150 x 100 cm t = 25 cm K-350 Unit Rp 13,600,000.00 Kunango Jantan
142 Box Culvert 100 x 100 x 100 cm t = 23 cm K-400 Unit Rp 5,525,000.00 Kunango Jantan
143 Box Culvert 100 x 100 x 100 cm t = 23 cm K-350 Unit Rp 5,400,000.00 Kunango Jantan
144 Box Culvert 60 x 60 x 100 cm t = 15 cm K-400 Unit Rp 2,550,000.00 Kunango Jantan
145 Box Culvert 60 x 60 x 100 cm t = 15 cm K-350 Unit Rp 2,500,000.00 Kunango Jantan
146 Box Culvert 220 x 220 x 150 cm t = 25 cm K-400 Unit Rp 28,300,000.00 Kunango Jantan
147 Box Culvert 220 x 220 x 150 cm t = 25 cm K-350 Unit Rp 27,800,000.00 Kunango Jantan
148 Box Culvert 300 x 300 x 100 cm t = 30 cm K-400 Unit Rp 25,000,000.00 Kunango Jantan
149 Box Culvert 300 x 300 x 100 cm t = 30 cm K-300 Unit Rp 24,600,000.00 Kunango Jantan
150 Box Culvert 200 x 150 x 200 cm t = 20 cm K-350 Unit Rp 25,850,000.00 Kunango Jantan
151 Box Culvert 120 x 120 x 100 cm t = 25 cm K-350 Unit Rp 7,500,000.00 Kunango Jantan
Harga Dasar Upah dan Bahan 7 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
152 Box Culvert 120 x 120 x 300 cm t = 25 cm K-350 Unit Rp 18,750,000.00 Kunango Jantan
153 Box Culvert 200 x 150 x 100 cm t = 20 cm K-350 Unit Rp 16,950,000.00 Kunango Jantan
154 Box Culvert 200 x 120 x 100 cm t = 25 cm K-350 Unit Rp 13,800,000.00 Kunango Jantan
155 Spun Pile Ø 30 cm Type A t = 6 cm M1 Rp 242,000.00 Bottom
156 Spun Pile Ø 30 cm Type A t = 6 cm M1 Rp 250,800.00 Upper
157 Spun Pile Ø 30 cm Type B t = 6 cm M1 Rp 281,600.00 Bottom
158 Spun Pile Ø 30 cm Type B t = 6 cm M1 Rp 290,400.00 Upper
159 Spun Pile Ø 35 cm Type A t = 6.5 cm M1 Rp 309,100.00 Bottom
160 Spun Pile Ø 35 cm Type A t = 6.5 cm M1 Rp 343,200.00 Upper
161 Spun Pile Ø 35 cm Type B t = 6.5 cm M1 Rp 370,700.00 Bottom
162 Spun Pile Ø 35 cm Type B t = 6.5 cm M1 Rp 382,800.00 Upper
163 Spun Pile Ø 40 cm Type A t = 7.5 cm M1 Rp 407,000.00 Bottom
164 Spun Pile Ø 40 cm Type A t = 7.5 cm M1 Rp 422,400.00 Upper
165 Spun Pile Ø 40 cm Type B t = 7.5 cm M1 Rp 459,800.00 Bottom
166 Spun Pile Ø 40 cm Type B t = 7.5 cm M1 Rp 475,200.00 Upper
167 Spun Pile Ø 45 cm Type A t = 8 cm M1 Rp 477,400.00 Bottom
168 Spun Pile Ø 45 cm Type A t = 8 cm M1 Rp 501,600.00 Upper
169 Spun Pile Ø 45 cm Type B t = 8 cm M1 Rp 543,400.00 Bottom
170 Spun Pile Ø 45 cm Type B t = 8 cm M1 Rp 567,600.00 Upper
171 Spun Pile Ø 50 cm Type A t = 9 cm M1 Rp 634,700.00 Bottom
172 Spun Pile Ø 50 cm Type A t = 9 cm M1 Rp 668,800.00 Upper
173 Spun Pile Ø 50 cm Type B t = 9 cm M1 Rp 727,100.00 Bottom
174 Spun Pile Ø 50 cm Type B t = 9 cm M1 Rp 761,200.00 Upper
175 Spun Pile Ø 60 cm Type A t = 10 cm M1 Rp 888,800.00 Bottom
176 Spun Pile Ø 60 cm Type A t = 10 cm M1 Rp 644,600.00 Upper
177 Spun Pile Ø 60 cm Type B t = 10 cm M1 Rp 921,800.00 Bottom
178 Spun Pile Ø 60 cm Type B t = 10 cm M1 Rp 977,900.00 Upper
179 Spun Pile Ø 60 cm Type C t = 10 cm M1 Rp 985,600.00 Bottom
180 Spun Pile Ø 60 cm Type C t = 10 cm M1 Rp 1,041,700.00 Upper
181 Kanstein K-200 Unit Rp 130,000.00 Kunango Jantan
182 Dinding Panel 240 cm x 40 cm t = 5 cm K-250 Unit Rp 280,000.00 Kunango Jantan
183 Tiang Panel 20 cm x 20 cm x 370 cm K-250 Unit Rp 695,000.00 Kunango Jantan
184 Paving Block 30 cm x 30 cm x 6 cm Unit Rp 15,695.00 Kunango Jantan
185 Paving Block 20 cm x 20 cm x 10 cm Unit Rp 6,000.00 Kunango Jantan
186 Paving Block 20 cm x 10 cm x 8 cm Unit Rp 5,600.00 Kunango Jantan
187 Bata Ringan t = 11 cm Unit Rp 14,200.00 Kunango Jantan
188 Bata Ringan t = 10 cm Unit Rp 11,515.00 Kunango Jantan
189 Bata Ringan t = 7,5 cm Unit Rp 10,300.00 Kunango Jantan
190 Glass Block t = 8 cm Unit Rp 23,200.00 Kunango Jantan
191 Barrier Type A Unit Rp 795,000.00 Kunango Jantan
192 Barrier Type B Unit Rp 600,000.00 Kunango Jantan
193 Buis Beton Bertulang dia 100 cm K-350 Unit Rp 1,281,000.00 Kunango Jantan
194 Buis Beton Tidak Bertulang dia 100 cm K-350 Unit Rp 825,000.00 Kunango Jantan
195 Tiang PJU Octagonal - Sigle Ornament Type Parabola t = 7 m Btg Rp 3,000,000.00 Kunango Jantan
196 Tiang PJU Octagonal - Sigle Ornament Type Parabola t = 8 m Btg Rp 3,300,000.00 Kunango Jantan
197 Tiang PJU Octagonal - Sigle Ornament Type Parabola t = 9 m Btg Rp 4,150,000.00 Kunango Jantan
198 Tiang PJU Octagonal - Sigle Ornament Type Parabola t = 10 m Btg Rp 5,100,000.00 Kunango Jantan
199 Tiang PJU Octagonal - Sigle Ornament Type Parabola t = 11 m Btg Rp 5,500,000.00 Kunango Jantan
200 Tiang PJU Octagonal - Sigle Ornament Type Parabola t = 12 m Btg Rp 6,000,000.00 Kunango Jantan
201 Tiang PJU Octagonal - Sigle Ornament Type Parabola t = 13 m Btg Rp 6,850,000.00 Kunango Jantan
202 Tiang PJU Octagonal - Double Ornament Type Parabola t = 7 m Btg Rp 3,400,000.00 Kunango Jantan
203 Tiang PJU Octagonal - Double Ornament Type Parabola t = 8 m Btg Rp 4,000,000.00 Kunango Jantan
204 Tiang PJU Octagonal - Double Ornament Type Parabola t = 9 m Btg Rp 4,700,000.00 Kunango Jantan
205 Tiang PJU Octagonal - Double Ornament Type Parabola t = 10 m Btg Rp 5,800,000.00 Kunango Jantan
206 Tiang PJU Octagonal - Double Ornament Type Parabola t = 11 m Btg Rp 6,150,000.00 Kunango Jantan
207 Tiang PJU Octagonal - Double Ornament Type Parabola t = 12 m Btg Rp 6,650,000.00 Kunango Jantan
208 Tiang PJU Octagonal - Double Ornament Type Parabola t = 13 m Btg Rp 7,500,000.00 Kunango Jantan
209 Tiang PJU Bulat - Sigle Ornament Type Parabola t = 6 m Btg Rp 3,000,000.00 Kunango Jantan
210 Tiang PJU Bulat - Sigle Ornament Type Parabola t = 7 m Btg Rp 3,300,000.00 Kunango Jantan
211 Tiang PJU Bulat - Sigle Ornament Type Parabola t = 8 m Btg Rp 3,500,000.00 Kunango Jantan
212 Tiang PJU Bulat - Sigle Ornament Type Parabola t = 9 m Btg Rp 4,250,000.00 Kunango Jantan
213 Tiang PJU Bulat - Sigle Ornament Type Parabola t = 10 m Btg Rp 5,100,000.00 Kunango Jantan
214 Tiang PJU Bulat - Sigle Ornament Type Parabola t = 11 m Btg Rp 5,900,000.00 Kunango Jantan
215 Tiang PJU Bulat - Sigle Ornament Type Parabola t = 12 m Btg Rp 6,150,000.00 Kunango Jantan
216 Tiang PJU Bulat - Sigle Ornament Type Parabola t = 13 m Btg Rp 6,600,000.00 Kunango Jantan
217 Tiang PJU Bulat - Double Ornament Type Parabola t = 6 m Btg Rp 3,000,000.00 Kunango Jantan
218 Tiang PJU Bulat - Double Ornament Type Parabola t = 7 m Btg Rp 3,600,000.00 Kunango Jantan
219 Tiang PJU Bulat - Double Ornament Type Parabola t = 8 m Btg Rp 3,850,000.00 Kunango Jantan
220 Tiang PJU Bulat - Double Ornament Type Parabola t = 9 m Btg Rp 4,550,000.00 Kunango Jantan
221 Tiang PJU Bulat - Double Ornament Type Parabola t = 10 m Btg Rp 5,500,000.00 Kunango Jantan
222 Tiang PJU Bulat - Double Ornament Type Parabola t = 11 m Btg Rp 6,300,000.00 Kunango Jantan
Harga Dasar Upah dan Bahan 8 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
223 Tiang PJU Bulat - Double Ornament Type Parabola t = 12 m Btg Rp 6,550,000.00 Kunango Jantan
224 Tiang PJU Bulat - Double Ornament Type Parabola t = 13 m Btg Rp 7,000,000.00 Kunango Jantan
225 Tiang Lampu Taman Octa t = 4,5 m Btg Rp 3,500,000.00 Kunango Jantan
226 Tiang Lampu Taman 2 Pole Btg Rp 3,250,000.00 Kunango Jantan
227 Tiang Lampu Taman t = 4,5 m 3 Pole Btg Rp 4,150,000.00 Kunango Jantan
228 Tiang Lampu Taman t = 4,0 m 2 Pole Btg Rp 4,000,000.00 Kunango Jantan
229 PCI Girder H = 1,25 m, L = 17,6 m, Ctc = 1,85 m M58a Bh Rp 260,000,000.00 Pelabuhan terdekat
230 PCI Girder H = 1,25 m, L = 20,6 m, Ctc = 1,85 m M58b Bh Rp 285,000,000.00 Pelabuhan terdekat
231 PCI Girder H = 1,25 m, L = 25,6 m, Ctc = 1,85 m M58c Bh Rp 340,000,000.00 Pelabuhan terdekat
232 PCI Girder H = 1,60 m, L = 30,8 m, Ctc = 1,85 m M58d Bh Rp 410,000,000.00 Pelabuhan terdekat
233 PCI Girder H = 1,60 m, L = 33,8 m, Ctc = 1,85 m M58e Bh Rp 445,000,000.00 Pelabuhan terdekat
234 PCI Girder H = 1,60 m, L = 35,8 m, Ctc = 1,85 m M58f Bh Rp 500,000,000.00 Pelabuhan terdekat
235 PCI Girder H = 2,10 m, L = 40,8 m, Ctc = 1,85 m M58g Bh Rp 625,000,000.00
236 PCI Girder H = 2,10 m, L = 45,8 m, Ctc = 1,85 m M58h Bh Rp 715,000,000.00
237 Tiang Pancang Petak 25 x 25 cm, p = 6 m (Manual) M1 Rp 245,000.00
238 Tiang Pancang PCA 300 type A (bearing capacity 70 ton) M.18a M' Rp 234,000.00
239 Tiang Pancang PCA 300 type AB (bearing capacity 70 ton) M.18b M' Rp 264,000.00
240 Tiang Pancang PCA 300 type B (bearing capacity 70 ton) M.18c M' Rp 288,000.00
241 Tiang Pancang PCA 350 type A (bearing capacity 90 ton) M.18d M' Rp 300,000.00
242 Tiang Pancang PCA 350 type AB (bearing capacity 90 ton) M.18e M' Rp 342,000.00
243 Tiang Pancang PCA 350 type B (bearing capacity 90 ton) M.18f M' Rp 378,000.00
244 Tiang Pancang PCA 400 type A (bearing capacity 118 ton) M.18g M' Rp 396,000.00
245 Tiang Pancang PCA 400 type AB (bearing capacity 118 ton) M.18h M' Rp 450,000.00
246 Tiang Pancang PCA 400 type B (bearing capacity 118 ton) M.18i M' Rp 474,000.00
247 Tiang Pancang PCA 450 type A (bearing capacity 143 ton) M.18j M' Rp 480,000.00
248 Tiang Pancang PCA 450 type AB (bearing capacity 143 ton) M.18k M' Rp 540,000.00
249 Tiang Pancang PCA 450 type B (bearing capacity 143 ton) M.18.l M' Rp 582,000.00
250 Tiang Pancang PCA 500 type A (bearing capacity 178 ton) M.18.m M' Rp 612,000.00
251 Tiang Pancang PCA 500 type AB (bearing capacity 178 ton) M.18.n M' Rp 684,000.00
252 Tiang Pancang PCA 500 type B (bearing capacity 178 ton) M.18.o M' Rp 726,000.00
253 Tiang Pancang PCA 600 type A (bearing capacity 242 ton) M.18.p M' Rp 834,000.00
254 Tiang Pancang PCA 600 type AB (bearing capacity 242 ton) M.18.q M' Rp 918,000.00
255 Tiang Pancang PCA 600 type B (bearing capacity 242 ton) M.18.r M' Rp 972,000.00
256 Buis Beton dia 15 cm tanpa tulangan, pig 0,5m M.10.a Bh Rp 39,400.00
257 Buis Beton dia 20 cm tanpa tulangan, pig 0,5m M.10.b Bh Rp 55,600.00
258 Buis Beton dia 30 cm tanpa tulangan, pig 0,5m M.10.c Bh Rp 100,700.00
259 Buis Beton dia 40 cm tanpa tulangan, pig 0,5m M.10.d Bh Rp 126,400.00
260 Buis Beton dia 60 cm tanpa tulangan, pig 0,5m M.10.e Bh Rp 158,000.00
261 Buis Beton dia 80 cm tanpa tulangan, pig 0,5m M.10.f Bh Rp 195,700.00
262 Buis Beton dia 100 cm tanpa tulangan, pig 0,5m M.10.g Bh Rp 247,300.00
263 Buis Beton dia 100 cm BerBertulang, pig 1 m Bh Rp 563,000.00
264 Buis Beton dia 80 cm BerBertulang, pig 1 m Bh Rp 459,000.00
265 Buis Beton dia 60 cm BerBertulang, pig 1 m Bh Rp 354,000.00
266 Buis Beton dia 40 cm BerBertulang, pig 1 m Bh Rp 249,000.00
267 Buis Beton dia 30 cm BerBertulang, pig 1 m Bh Rp 197,000.00
268 Buis Beton dia 20 cm BerBertulang, pig 1 m Bh Rp 144,000.00
269 Hollow Brick (H.15) Bh Rp 3,600.00
270 Hollow Brick (H.10) Bh Rp 3,300.00
271 Hollow Brick (H.20) Bh Rp 5,000.00
272 Batu Andesit 300 x 300 mm t. 13 mm (Luxery grey) M2 Rp 247,500.00 Finishing = Bakar
273 Batu Andesit 400 x 600 mm t. 13 mm (Luxery grey) M2 Rp 315,000.00 Finishing = Bakar
274 Batu Andesit 300 x 300 mm t. 18-20 mm (Luxery grey) M2 Rp 275,000.00 Finishing = Bakar
275 Batu Andesit 400 x 600 mm t. 18-20 mm (Luxery grey) M2 Rp 357,500.00 Finishing = Bakar
276 Batu Andesit 300 x 300 mm t. 18-20 mm (Luxery grey) M2 Rp 347,500.00 Finishing = Matte
277 Batu Andesit 400 x 600 mm t. 18-20 mm (Luxery grey) M2 Rp 423,750.00 Finishing = Matte
278 Batu Andesit 300 x 300 mm t. 18-20 mm (Luxery grey) M2 Rp 407,500.00 Finishing = Polish
279 Batu Andesit 400 x 600 mm t. 18-20 mm (Luxery grey) M2 Rp 423,750.00 Finishing = Polish
280 Batu Andesit 300 x 300 mm t. 30 mm (Luxery grey) M2 Rp 446,250.00 Finishing = Bakar
281 Batu Andesit 400 x 600 mm t. 30 mm (Luxery grey) M2 Rp 522,500.00 Finishing = Bakar
282 Batu Andesit 300 x 300 mm t. 30 mm (Luxery grey) M2 Rp 512,500.00 Finishing = Matte
283 Batu Andesit 400 x 600 mm t. 30 mm (Luxery grey) M2 Rp 588,750.00 Finishing = Matte
284 Batu Andesit 300 x 300 mm t. 30 mm (Luxery grey) M2 Rp 572,500.00 Finishing = Polish
285 Batu Andesit 400 x 600 mm t. 30 mm (Luxery grey) M2 Rp 650,000.00 Finishing = Polish
286 Batu Andesit 300 x 300 mm t. 40 mm (Luxery grey) M2 Rp 588,750.00 Finishing = Bakar
287 Batu Andesit 400 x 600 mm t. 40 mm (Luxery grey) M2 Rp 671,250.00 Finishing = Bakar
288 Batu Andesit 300 x 300 mm t. 50 mm (Luxery grey) M2 Rp 737,500.00 Finishing = Bakar
289 Batu Andesit 400 x 600 mm t. 50 mm (Luxery grey) M2 Rp 820,000.00 Finishing = Bakar
290 Granit 40 x 40 (pearls white, Setara Granito) Bh Rp 64,500.00 Polished
291 Granit 40 x 40 (pearls white, Setara Granito) Bh Rp 64,500.00 Unpolished
292 Granit 60 x 60 (silver pearls, Setara Granito) Bh Rp 126,500.00 Polished
293 Granit 60 x 60 (silver pearls, Setara Granito) Bh Rp 126,500.00 Unpolished
Harga Dasar Upah dan Bahan 9 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
294
295 Granit 30 x 30 (silver pearls, Setara Granito) Bh Rp 35,100.00 Polished
296 Granit 30 x 30 (silver pearls, Setara Granito) Bh Rp 35,100.00 Unpolished
297 Granit 40 x 40 (Setara Ikad ) Bh Rp 35,100.00
298 Keramik 33 x 33 (Asia Tile) Doos Rp 68,000.00
299 Keramik 60 x 60 (Setara Roman) Bh Rp 31,250.00
300 Keramik 40 x 40 (Asia Tile) Bh Rp 10,000.00
301 Keramik 30 x 30 (Setara Roman) Bh Rp 5,000.00
302 Keramik 20 x 20 (Setara Roman) Bh Rp -
Keramik Lantai 25x25 ( IKAD ) Kasar Bh Rp 5,000.00
303 Keramik, Lantai 60 x 60 Bh Rp 125,000.00
304 Keramik, Lantai 40 x 40 Doos Rp 60,600.00
305 Keramik, Lantai 30 x 30 Doos Rp 60,000.00
306 Keramik, Lantai 20 x 20 Doos Rp 62,000.00
307 Keramik, dinding 20 x 40 Bh Rp -
Keramik, dinding 25 x 40 Bh Rp 8,000.00
308 Keramik, dinding 20 x 25 Bh Rp -
309 Keramik, dinding 20 x 20 Bh Rp -
310 Plint Keramik 10 x 40 Bh Rp 11,700.00
311 Plint Keramik 10 x 30 Bh Rp 10,100.00
312 Plint Keramik 10 x 20 Bh Rp 4,200.00
313 Plint Keramik 10 x 10 Bh Rp 3,800.00
314 Plint Keramik 5 x 20 Bh Rp 6,000.00
315 Plint Vynil Karet ukuran 15 Cm x 30 Cm Bh Rp 57,500.00
316 Step Nosing Granit pjg = 60 cm Bh Rp 47,300.00
317 Step Nosing Granit pjg = 40 cm Bh Rp 22,165.00
318 Step Nosing Granit pjg = 30 cm Bh Rp 16,956.23
319 Batu Andesit M2 Rp 236,500.00
320 Internal cove Bh Rp 9,500.00
321 Bon-bon Keramik M' Rp 6,000.00
322 Floor hardener Kg Rp 32,500.00
323 Patok Beton uk 20 x 20 cm ptk
324 Pintu Angin Ukuran ( Rooster 20 x 20 cm) Bh Rp 10,300.00
325 Pintu Angin Ukuran ( Rooster 25 x 25 cm) Bh Rp 14,900.00
326 Cuka Bibit Liter Rp 52,000.00

B. KELOMPOK BAHAN KAYU


1 Bambu dia 2", pjg 6m btg Rp 17,000.00
2 Bambu dia 3-4", pjg 6-8m btg Rp 26,200.00
3 Dolken kayu galam dia 10 cm, pjg 4 m (Perancah) btg Rp 48,500.00
4 Dolken kayu galam dia 8-10 cm, pjg 4 m (Perancah) btg Rp 34,100.00
5 Ijuk kg Rp 24,000.00
6 Kayu Banio ( Papan ) Klas I m³ Rp 4,103,500.00
7 Kayu Banio ( Balok) Klas I m³ Rp 4,035,700.00
8 Kayu Marsawa ( Papan ) Klas II m³ Rp 3,129,900.00
9 Kayu Marsawa ( Balok ) Klas II m³ Rp 3,029,100.00
10 Kayu Merantih ( Papan ) Klas III m³ Rp 2,582,700.00
11 Kayu Merantih ( Balok ) Klas III m³ Rp 2,446,500.00
12 Kayu untuk Perancah Kayu Klas III m³ Rp 2,110,800.00
13 Kayu Bekisting ( Papan ) Klas IV m³ Rp 1,890,600.00
14 Kayu Bekisting ( Balok ) Klas IV m³ Rp 1,962,100.00
15 Kayu Acuan M99 m³ Rp 2,169,700.00
16 Kayu Perancah 5/7 Cm M.37.b m³ Rp 2,426,600.00 Lokasi Pekerjaan
17 Dolken Ø-8 cm-4 m btg Rp 45,500.00
18 Penjaga jarak bekising/spacer btg Rp 19,500.00
19 Kayu reng 2 x 3 kelas 2 m3 Rp 3,029,100.00
20 Multiplek tebal 6 mm Lbr Rp 92,300.00
21 Multiplek tebal 9 mm Lbr Rp 126,000.00
22 Multipleks 12 mm M73 Lbr Rp 175,200.00
23 Multiplek tebal 18 mm Lbr Rp 262,300.00
24 Plywood 4 mm Lbr Rp 83,700.00
25 Plywood 9 mm Lbr Rp 183,400.00
26 Phenol film 12 mm Lbr Rp 215,000.00
27 Teakwood 3mm 120 x 240 Lbr Rp 90,000.00
28 Triflex t= 3mm Lbr Rp 56,700.00
29 Triflex t= 4mm Lbr Rp 68,800.00
30 Triflex t= 6mm Lbr Rp 90,500.00
31 Triflex Jati t = 3 mm Lbr Rp 97,100.00
32 Triflex jati t = 4 mm Lbr Rp 99,500.00
33 Triflex jati t = 6 mm Lbr Rp 146,600.00
34 Lamberseering M' Rp 17,400.00
Harga Dasar Upah dan Bahan 10 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
35 Papan Lamberseering btg Rp 16,000.00
36 Les Profil (3x3.5x400) M' Rp 4,000.00
37 Les kaca (1x3x400) M' Rp 2,000.00
38 Lem kayu kg Rp 18,800.00
39 Jendela naco ( 15 x 90 ) cm + Rangka Bh Rp 189,100.00
40 Gypsum Board t.9 mm Lbr Rp 81,500.00
Plafound PVC ( Javapond ) m Rp 25,000.00
Lest PVC m Rp 12,000.00
41 Formika Lbr Rp 105,700.00
42 Selinder (cisa) Bh Rp 85,000.00
43 Door Closer Bh Rp 225,000.00
44 Door Stoper Bh Rp 72,500.00
45 List Profil Gypsumb 5 cm M1 Rp 18,500.00
46 GRC t.6 mm M2 Rp 145,000.00
47 Spring Knip bh Rp 65,000.00

A. KELOMPOK BAHAN LOGAM


1 Main Truss Canal m1 Rp 12,500.00
2 Roof Botton/Reng m1 Rp 7,500.00
3 Self Drilling Screw dia. 6x20 mm (Truss) pcs Rp 400.00
Hollow Zinclaume m1 Rp 6,000.00
Sekrup BH Rp 300.00
Sekrup kg Rp 25,000.00
4 Self Drilling Screw dia. 4x16 mm (Truss) pcs Rp 400.00 Lokasi Pekerjaan
5 Dynabolt pcs Rp 1,500.00 Lokasi Pekerjaan
6 Joint Tape Roll Rp 16,000.00 Lokasi Pekerjaan
Besi Polos / Ulir M13 Kg Rp 10,600.00 Lokasi Pekerjaan
Kawat Beton M14 Kg Rp 18,700.00 Lokasi Pekerjaan
Paku 5 - 10 cm kg Rp 18,600.00
Sealent Kg Rp 35,000.00
6 Paku 5 dan 10 Cm kg Rp 18,600.00
Profil Alumanium m1 Rp 110,000.00
Sekrup fixer Bh Rp 7,500.00
Pintu alumanium M' Rp 280,000.00
Besi Profil Kg Rp 24,000.00

B. KELOMPOK BAHAN ATAP DAN GRC


Atap UPVC
1 Atap UPVC M2 Rp 325,000.00
1 - Seng BJLS 0.20 x 3' x 6' bd 9 Lbr Rp 47,500.00
2 - Seng BJLS 0.30 x 3' x 6' bd 9 Lbr Rp 55,200.00
3 - Seng BJLS 0.20 x 3' x 6' bd 11 Lbr Rp 50,400.00
4 - Seng BJLS 0.30 x 3' x 6' bd 11 Lbr Rp 67,400.00

Atap Plastik :
1 - Warna Putih Arcylic Lbr Rp 107,700.00
2 - Fiber Class Lbr Rp 123,300.00
- Asbes gelombang besar uk. 105 x 180,5 mm Lbr #DIV/0!
- Asbes gelombang besar uk. 80 x 180,4 mm Lbr #DIV/0!
- Asbes gelombang uk 92 x 250 Lbr #DIV/0!
3 - Asbes semen Lbr Rp 37,200.00
#DIV/0!
- Genteng palentong Lbr #DIV/0!
- Genteng kodok Lbr #DIV/0!
- Nok paten 92 cm Lbr #DIV/0!
- Genteng Beton Lbr #DIV/0!
- Genteng aspal Lbr #DIV/0!
- Genteng Metal Lbr #DIV/0!

Atap Seng Warna :


1 - Tebal 0.20 11 bd merk Swan Brand/Gjh. Berlian Lbr Rp 108,200.00
2 - Tebal 0.20 11 bd merk Gold Fish/Swallow Lbr Rp 53,000.00
3 - Genteng Metal ( Polycolor ) 0.20 cm Lbr Rp 59,400.00
4 - Genteng Metal ( Polycolor ) 0.30 cm Lbr Rp 57,500.00
5 - Atap Asbes Gelombang Lbr Rp 48,500.00

Perabung Atap Seng


1 - Perabung Seng Plat BJLS 20 Lbr Rp 26,200.00
- Perabung Seng Plat BJLS 30 Lbr Rp 39,900.00
Harga Dasar Upah dan Bahan 11 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
2 - Seng Plat BJLS 20 Lbr Rp 51,200.00
3 - Seng Plat BJLS 30 Lbr Rp 71,900.00
4 - Perabung Abes Lbr Rp 23,100.00
5 - Perabung Geteng metal Lbr Rp 32,200.00
6 - Seng Plat BJLS 20 Warna Lbr Rp 65,900.00
- Seng Plat BJLS 30 Warna Lbr #DIV/0!
Perabung Atap Seng #DIV/0!
- Pintu Angin Ukuran 20x20 cm bh #DIV/0!
Pintu Angin Ukuran 25x25 cm bh #DIV/0!

Onduline
- Genteng Bitumen Selusa Uk. 160 cm x 40 cm Lembar Rp 47,700.00
- Asesoris Nok/Ridge Lembar Rp 82,500.00
- Nok Asesoris Flashing Samping/Verge Piece Lembar Rp 76,800.00
- Atap Bitumen Bergelombang 3 mm H 38 Lembar Rp 152,500.00
- Screw Bh Rp 1,200.00

BAHAN MUKA Lantai / DINDING


Ukuran ( 32 x 32 ) cm ( KW I )
- Type P M² Rp -
- Type Q M² Rp -
- Type W M² Rp -

KERAMIK
Bentuk OFF/FWT ( KW I )
- Type G (20 x 20) cm M² Rp -
- Type H (20 x 20) cm M² Rp -
- Type J (20 x 20) cm M² Rp -
- Type K (20 x 20) cm M² Rp -
- Type D (10 x 10) cm M² Rp -
- Type E (10 x 10) cm/Masterina M² Rp -
- Type F (10 x 10) cm M² Rp -

Bentuk OFF/FWT ( KW II )
- Type G (20 x 20) cm M² Rp 82,400.00
- Type H (20 x 20) cm M² Rp 93,800.00

Keramik Untuk Lantai


- Uk. (15 x 15) cm M² Rp -
- Uk. (20 x 20) cm M² Rp 142,100.00
- Uk. (30 x 30) cm M² Rp 181,700.00
- Uk. (20 x 40) cm M² #DIV/0!
- Uk. (40 x 40) cm M² #DIV/0!

Untuk Dinding :
- Uk. (10 x 20) cm M² #DIV/0!
- Uk. (20 x 20) cm M² #DIV/0!
- Uk. (20 x 25) cm M² Rp -

E. KELOMPOK BAHAN KACA


Kaca Polos
1 - Tebal 3 mm M² Rp 94,900.00
2 - Tebal 5 mm M² Rp 105,700.00
3 - Tebal 8 mm M² Rp 208,400.00
- Tebal 12 mm M² Rp 144,900.00
Kaca Raiben
1 - Tebal 3 mm M² Rp 180,900.00
2 - Tebal 5 mm M² Rp 231,400.00
Raso #DIV/0!
- Tebal 3 mm M² #DIV/0!
- Tebal 5 mm M² #DIV/0!
Kaca Es : #DIV/0!
- Tebal 3 mm M² #DIV/0!
- Tebal 5 mm M² #DIV/0!
Kaca Naco Polos
- ( 15 x 90 ) cm + Rangka M² Rp 243,000.00

F. PENGGANTUNG/PENGUNCI
- Merk Jangkar 9702 RRC/692 LD/MAXEL/KODAI/dll Set Rp 101,400.00
- Jangkar 746/Kodai/dll Set Rp 87,500.00
Harga Dasar Upah dan Bahan 12 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
- Merk Ciga Brown 5404 Set Rp 136,800.00
- Merk Ciga Brown 5009 Set #DIV/0!
- Kunci Mandili 450 Itali/Seiss Set #DIV/0!
- Kunci Antik A/C Itali/Seiss Set Rp 274,200.00
- Kunci Shanghai 9702 LD Set Rp 91,700.00
- Grendel Antik 2 Set Rp 14,400.00
- Tarikan Antik Jendela Set Rp 33,600.00
- Engsel Nylon Set Rp 20,600.00
- Engsel Lokal Set Rp 16,400.00
- Engsel 4" (Kuningan) Set Rp 31,200.00
- Engsel 4' (Biasa) Set Rp 21,000.00
- Engsel 3" (Kuningan) Set Rp 22,600.00
- Engsel 3" (Biasa) Set Rp 14,900.00
- Hak Angin unit Rp 15,200.00
- Handle Pintu (cisa) Unit Rp 199,100.00
- Kunci Mandili 450 Itali/Seiss Set Rp 287,400.00
- Kunci Lemari Set Rp 22,500.00

H. ASPAL, BAHAN BAKAR, MINYAK, DAN CAT


1 Aspal M10 KG Rp 14,000.00
2 Aspal (drum) M10a KG Rp 13,500.00
3 Aspal Emulsi M31 Kg Rp 12,700.00 Base Camp
Asbuton Halus M55 Ton #DIV/0! Base Camp
Bunker Oil M54 Ltr #DIV/0! Base Camp
4 Oxygen M87 Botol Rp 82,500.00 Lokasi Pekerjaan
5 Batu Bara M88 Kg Rp 1,200.00 Lokasi Pekerjaan
Premium non subsidi M20 Ltr #DIV/0! Pertamina
6 Premium non subsidi M21 Ltr Rp 8,500.00 Pertamina
6 Dexlite Ltr Rp 11,600.00
7 Minyak Pelumas / Olie M22 Ltr Rp 38,700.00 Pertamina
8 Kerosen / Minyak Tanah M11 Ltr Rp 8,800.00 Base Camp
9 Bahan pengawet: kreosot M63 Ltr Rp 10,700.00
Assetilline M86 Botol #DIV/0! Lokasi Pekerjaan
10 Thinner M33 Ltr Rp 18,600.00 Lokasi Pekerjaan
11 Minyak Fluks M53 Ltr Rp 12,000.00 Base Camp
12 Joint Sealent M94 Kg Rp 37,500.00
13 Glass Bead M34 Kg Rp 68,800.00 Lokasi Pekerjaan
14 Pemantul Cahaya (Reflector) M43 Bh. Rp 23,000.00 Base Camp
15 Mata Kucing M64 Bh Rp 137,000.00
16 Anchorage M65 Bh Rp 739,200.00
17 Anti strpping agent M66 Kg Rp 75,000.00
18 Bahan Modifikasi M67 1 Kg Rp 2,100.00
19 Platone Cat Tembok/Digatex/dll Kg Rp 65,800.00
20 Nagaltex Cat Tembok/Sanalux Kg Rp 44,000.00
21 Rimatex Dempul Tembok/Hommer Kg Rp 29,500.00
22 Platone Cat Besi Kg Rp 55,200.00
Supervinex Cat Tembok Kg #DIV/0!
23 Multi Seal Cat Seng Kg Rp 67,000.00
24 Cat Minyak M42 Kg Rp 55,500.00 Base Camp
25 Cat Anti Karat (epoxy) M95 Kg Rp 73,900.00
26 Cat Marka (Non Thermoplas) M17a Kg Rp 50,000.00 Lokasi Pekerjaan
27 Cat Marka (Thermoplastic) M17b Kg Rp 23,000.00 Lokasi Pekerjaan
28 Cat Ultra Politur Kg Rp 61,100.00
29 Plemer Kayu Kg Rp 28,700.00
30 Plemer Tembok Kg Rp 31,800.00
31 Meni kayu - warna Kg Rp 30,700.00
32 Meni besi - warna Kg Rp 40,300.00
33 Cat tembok matex Kg Rp 25,200.00
34 Cat tembok venilex Kg Rp 31,100.00
35 Cat tembok catilax Kg Rp 51,500.00
Cat Tembok Jotun Interior Kg Rp 28,000.00
Cat Tembok Jotun Exterior Rp 90,000.00
36 Residu Ltr Rp 34,000.00
37 Minyak Cat Ltr Rp 14,800.00
38 Dempul Kg Rp 26,200.00
39 Amplas M1 Rp 9,200.00
Maxilete Cat Tembok Kg Rp 24,000.00
40 Cat Dasar ( Alkali ) Kg Rp 45,000.00
41 Pylox Btl Rp 24,500.00
42 Minyak bekisting Ltr Rp 13,800.00
43 Soda api Ltr Rp 27,000.00
Harga Dasar Upah dan Bahan 13 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
44 Kuas Bh Rp 20,700.00
45 Resin Tube Rp 95,000.00
46 Vernis Ltr Rp 93,100.00
47 Aqua Proof kg Rp 56,200.00
48 Sealtape bh Rp 10,000.00
49 Cat Dasar Kerb Kg Rp 52,400.00
50 Cat Penutup Kerb (Hitam) Kg Rp 52,400.00
51 Cat Penutup Kerb (Putih) Kg Rp 67,000.00

H. KELOMPOK BAHAN SANITAIR


1 Closet Jongkok Merk KIA Type EX RAPI ( 1273A010)/DUTY)/DONI/AS Bh Rp 268,000.00
2 Closet Jongkok Merk KIA Type DX RAPI ( 1273A010)/RIMO Bh Rp 250,000.00
3 Closet Jongkok Merk Toto Standar Bh Rp 328,400.00
4 Closet Jongkok Merk Campion Bh Rp 177,500.00
5 Closet Duduk Merk Toto /DONI/LEXUS/RENOVO/A Stdr Bh Rp 2,274,500.00
6 Closet Duduk Merk Toto Type C Warna Tua/DUTY Bh Rp 2,193,000.00
7 Wastafel Merk Toto Bh Rp 854,000.00
8 Wastafel Merk KIA Type1207 F210/DUTY Bh Rp 870,700.00
9 Bak Fiberglass Uk 65 x 65 Bh Rp 270,000.00
10 Bak Fiberglass 1 m3 Bh Rp 300,000.00
11 Urinoir (Toto) Unit Rp 1,882,500.00
12 Bathup Unit Rp 3,950,000.00
13 Bak cuci piring Unit Rp 186,666.67
14 Waterdrain Bh Rp 227,800.00
15 Sabun kg Rp 6,000.00
16 Floordrain (Setara Toto) Bh Rp 46,666.67
17 Pelampung Otomatis Bh Rp 135,000.00
18 Tangki Air 1000 Liter (Penguin) Bh Rp 1,684,300.00
19 Tangki Air 500 Liter (Penguin) Bh Rp 1,084,500.00
20 Mesin Pompa tekan Kap.150 watt Bh #DIV/0!
20 Shower Set Bh Rp 431,200.00
21 Roof Drain Metal Bh Rp 175,000.00
22 Mesin Jet Pump. Kap. 250 watt Bh #DIV/0!
23 Kran Dinding (Toto) Bh Rp 169,800.00
24 Tempat Sabun (Toto) Set Rp 250,200.00
2 lisplang GRC m1 Rp 30,000.00

Pintu Fiber PVC Bh Rp 600,000.00


K. KELOMPOK BAHAN PIPA
Pipa GIP SNI 0039-2010 Klas Medium
- Diameter 1/2" M' Rp 28,300.00
- Diameter 3/4" M' Rp 36,500.00
- Diameter 1" M' Rp 39,000.00
- Diameter 1 1/2" M' Rp 55,900.00
- Diameter 50 mm M' Rp 115,600.00
- Diameter 75 mm M' Rp 190,600.00
- Diameter 100 mm M' Rp 276,200.00
- Diameter 150 mm M' Rp 442,600.00
- Diameter 200 mm M' Rp 654,100.00
- Diameter 250 mm M' Rp 1,277,600.00
- Diameter 300 mm M' Rp 1,510,000.00
- Diameter 350 mm M' Rp 1,750,000.00
- Diameter 450 mm M' Rp 2,000,000.00
- Diameter 500 mm M' Rp 2,600,000.00

Pipa PVC (RRJ) ISO Standard SNI 06.0084-2002 Class S.


12,5 / 8 Bar
- Diameter 20 mm S. 6.3 M' Rp 8,100.00
- Diameter 25 mm S. 6.3 M' Rp 10,700.00
- Diameter 32 mm S. 10 M' Rp 13,300.00
- Diameter 40 mm S. 12.5 M' Rp 13,800.00
- Diameter 50 mm S. 12.5 M' Rp 19,500.00
- Diameter 63 mm S. 12,5 M' Rp 27,700.00
- Diameter 75 mm S. 12,5 M' Rp 39,000.00
- Diameter 90 mm S. 12,5 M' Rp 54,100.00
- Diameter 110 mm S. 12,5 M' Rp 83,800.00
- Diameter 150 mm S. 12,5 M' Rp 161,600.00
- Diameter 160 mm S. 12,5 M' Rp 130,000.00
- Diameter 200 mm S. 12,5 M' Rp 295,500.00
Harga Dasar Upah dan Bahan 14 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
- Diameter 225 mm S. 12,5 M' Rp 392,500.00
- Diameter 250 mm S. 12,5 M' Rp 534,800.00
- Diameter 300 mm S. 12,5 M' Rp 918,100.00
- Diameter 355 mm S. 12,5 M' Rp 1,191,900.00
- Diameter 400 mm S. 12,5 M' Rp 1,507,600.00
- Diameter 500 mm S. 12,5 M' Rp 2,391,200.00
- Diameter 630 mm S. 12,5 M' Rp 3,852,300.00

Pipa HDPE PE-100 PN 10, SDR 17 SNI 06-4829-2005


- Diameter 16 mm S-5, SDR 11 / PN 16 M' Rp 7,300.00
- Diameter 20 mm S-8, SDR 17 / PN 10 M' Rp 9,400.00
- Diameter 25 mm M' Rp 13,700.00
- Diameter 32 mm M' Rp 18,100.00
- Diameter 40 mm M' Rp 25,000.00
- Diameter 50 mm M' Rp 39,200.00
- Diameter 75 mm M' Rp 86,800.00
- Diameter 90 mm M' Rp 123,400.00
- Diameter 100 mm M' Rp 184,500.00
- Diameter 160 mm M' Rp 386,100.00
- Diameter 200 mm M' Rp 601,100.00
- Diameter 250 mm M' Rp 934,000.00
- Diameter 315 mm M' Rp 1,484,400.00
- Diameter 355 mm M' Rp 1,884,300.00
- Diameter 400 mm M' Rp 2,385,600.00
- Diameter 450 mm M' Rp 2,946,500.00
- Diameter 500 mm M' Rp 3,645,700.00
- Diameter 700 mm M' Rp 7,341,600.00
- Diameter 800 mm M' Rp 9,314,400.00

Pipa PVC AW
- Diameter 10 " M' Rp 425,600.00
- Diameter 8 " M' Rp 273,700.00
- Diameter 6 " M' Rp 163,600.00
- Diameter 4 " M' Rp 69,900.00
- Diameter 3 " M' Rp 49,200.00
- Diameter 2 1/2 " M' Rp 34,000.00
- Diameter 2 " M' Rp 22,700.00
- Diameter 1 1/2" M' Rp 17,600.00
- Diameter 1 " M' Rp 14,100.00
- Diameter 3/4 " M' Rp 10,700.00
- Diameter 1/2 " M' Rp 7,600.00

Gate Valve (Flange Joint)


- Diameter 50 mm M' Rp 1,325,000.00
- Diameter 75 mm M' Rp 1,840,000.00
- Diameter 100 mm M' Rp 2,350,000.00
- Diameter 150 mm M' Rp 4,100,000.00
- Diameter 200 mm M' Rp 6,400,000.00
Diameter 250 mm M' Rp 8,000,000.00
- Diameter 300 mm M' Rp 13,200,000.00
- Diameter 400 mm M' Rp 19,700,000.00
- Diameter 450 mm M' Rp 29,300,000.00

Tee PVC
- Diameter 8" M' Rp 402,900.00
- Diameter 6" M' Rp 194,300.00
- Diameter 4" M' Rp 77,100.00
- Diameter 3" M' Rp 38,600.00
- Diameter 2 1/2 " M' Rp 25,000.00
- Diameter 2" M' Rp 16,500.00
- Diameter 1 1/2" M' Rp 10,300.00
- Diameter 1" M' Rp 4,700.00
- Diameter 3/4 " M' Rp 2,800.00
- Diameter 1/2 " M' Rp 2,000.00

Tee All Flange GIP


- Diameter Nominal 200 x 200 mm Bh Rp 2,545,000.00
- Diameter Nominal 200 x 150 mm Bh Rp 2,339,000.00
- Diameter Nominal 200 x 100 mm Bh Rp 2,081,000.00
- Diameter Nominal 200 x 75 mm Bh Rp 2,046,000.00
- Diameter Nominal 200 x 50 mm Bh Rp 1,940,000.00
Harga Dasar Upah dan Bahan 15 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
- Diameter Nominal 150 x 150 mm Bh Rp 484,800.00
- Diameter Nominal 150 x 100 mm Bh Rp 415,800.00
- Diameter Nominal 150 x 75 mm Bh Rp 406,500.00
- Diameter Nominal 150 x 50 mm Bh Rp 378,600.00
- Diameter Nominal 100 x 100 mm Bh Rp 268,000.00
- Diameter Nominal 100 x 75 mm Bh Rp 258,000.00
- Diameter Nominal 100 x 50 mm Bh Rp 233,100.00
- Diameter Nominal 75 x 75 mm Bh Rp 216,600.00
- Diameter Nominal 75 x 50 mm Bh Rp 192,000.00
- Diameter Nominal 50 x 50 mm Bh Rp 134,100.00

All Socket Tee PVC (RRJ)


- Diameter Nominal 200 x 200 mm Bh Rp 1,415,000.00
- Diameter Nominal 200 x 150 mm Bh Rp 1,270,000.00
- Diameter Nominal 200 x 100 mm Bh Rp 1,155,000.00
- Diameter Nominal 200 x 75 mm Bh Rp 1,095,000.00
- Diameter Nominal 150 x 150 mm Bh Rp 615,000.00
- Diameter Nominal 150 x 100 mm Bh Rp 533,000.00
- Diameter Nominal 150 x 75 mm Bh Rp 480,000.00
- Diameter Nominal 150 x 50 mm Bh Rp 412,000.00
- Diameter Nominal 100 x 100 mm Bh Rp 330,000.00
- Diameter Nominal 100 x 75 mm Bh Rp 300,000.00
- Diameter Nominal 100 x 50 mm Bh Rp 270,000.00
- Diameter Nominal 75 x 75 mm Bh Rp 179,500.00
- Diameter Nominal 75 x 50 mm Bh Rp 157,500.00
- Diameter Nominal 50 x 50 mm Bh Rp 122,000.00

Saddle Clamp PVC


- Diameter Nominal 200 x 50 mm Bh Rp 310,000.00
- Diameter Nominal 200 x 40 mm Bh Rp 310,000.00
- Diameter Nominal 200 x 32 mm Bh Rp 309,000.00
- Diameter Nominal 200 x 25 mm Bh Rp 199,500.00
- Diameter Nominal 200 x 20 mm Bh Rp 192,500.00
- Diameter Nominal 150 x 50 mm Bh Rp 261,000.00
- Diameter Nominal 150 x 40 mm Bh Rp 261,000.00
- Diameter Nominal 150 x 32 mm Bh Rp 243,600.00
- Diameter Nominal 150 x 25 mm Bh Rp 158,000.00
- Diameter Nominal 150 x 20 mm Bh Rp 151,000.00
- Diameter Nominal 100 x 50 mm Bh Rp 206,000.00
- Diameter Nominal 100 x 40 mm Bh Rp 206,000.00
- Diameter Nominal 100 x 32 mm Bh Rp 71,500.00
- Diameter Nominal 100 x 25 mm Bh Rp 65,000.00
- Diameter Nominal 100 x 20 mm Bh Rp 62,000.00
- Diameter Nominal 75 x 50 mm Bh Rp 165,000.00
- Diameter Nominal 75 x 40 mm Bh Rp 165,000.00
- Diameter Nominal 75 x 32 mm Bh Rp 62,000.00
- Diameter Nominal 75 x 25 mm Bh Rp 55,000.00
- Diameter Nominal 75 x 20 mm Bh Rp 51,500.00
- Diameter Nominal 50 x 25 mm Bh Rp 41,200.00
- Diameter Nominal 50 x 20 mm Bh Rp 37,800.00
- Diameter Nominal 50 x 15 mm Bh Rp 37,800.00
- Diameter Nominal 40 x 20 mm Bh Rp 34,500.00

All Flanged Bend Diameter 90 degree ( GIP )


- Diameter Nominal 200 mm Bh Rp 1,855,000.00
- Diameter Nominal 150 mm Bh Rp 466,000.00
- Diameter Nominal 125 mm Bh Rp 344,000.00
- Diameter Nominal 100 mm Bh Rp 261,200.00
- Diameter Nominal 75 mm Bh Rp 206,400.00
- Diameter Nominal 50 mm Bh Rp 137,600.00

All Flanged Bend Diameter 45, 22, 1/2 ; 11, 1/4 degree ( GIP )
- Diameter Nominal 200 mm Bh Rp 1,620,000.00
- Diameter Nominal 150 mm Bh Rp 1,025,000.00
- Diameter Nominal 125 mm Bh Rp 760,000.00
- Diameter Nominal 100 mm Bh Rp 560,000.00
- Diameter Nominal 75 mm Bh Rp 430,000.00
- Diameter Nominal 50 mm Bh Rp 265,000.00

Bend Diameter Socket / Spigot 90 degree (PVC) S-12,5


- Diameter Nominal 200 mm Bh Rp 691,500.00
Harga Dasar Upah dan Bahan 16 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
- Diameter Nominal 150 mm Bh Rp 383,000.00
- Diameter Nominal 100 mm Bh Rp 180,000.00
- Diameter Nominal 75 mm Bh Rp 125,000.00
- Diameter Nominal 50 mm Bh Rp 81,400.00

Bend Diameter Socket / Spigot 45 degree (PVC)


- Diameter Nominal 200 mm Bh Rp 592,000.00
- Diameter Nominal 150 mm Bh Rp 335,000.00
- Diameter Nominal 100 mm Bh Rp 156,500.00
- Diameter Nominal 75 mm Bh Rp 110,500.00
- Diameter Nominal 50 mm Bh Rp 74,800.00

Bend Diameter Socket / Spigot 22,5 degree (PVC)


- Diameter Nominal 200 mm Bh Rp 495,000.00
- Diameter Nominal 150 mm Bh Rp 285,000.00
- Diameter Nominal 100 mm Bh Rp 141,000.00
- Diameter Nominal 75 mm Bh Rp 106,700.00
- Diameter Nominal 50 mm Bh Rp 59,500.00

Bend Diameter Socket / Spigot 11,25 degree (PVC)


- Diameter Nominal 200 mm Bh Rp 432,000.00
- Diameter Nominal 150 mm Bh Rp 252,000.00
- Diameter Nominal 100 mm Bh Rp 129,000.00
- Diameter Nominal 75 mm Bh Rp 90,000.00
- Diameter Nominal 50 mm Bh Rp 56,000.00

Flange Socket PVC


- Diameter Nominal 200 mm Bh Rp 1,415,000.00
- Diameter Nominal 150 mm Bh Rp 881,000.00
- Diameter Nominal 100 mm Bh Rp 505,500.00
- Diameter Nominal 75 mm Bh Rp 223,900.00
- Diameter Nominal 50 mm Bh Rp 174,000.00

Flange Spigot for Steel / PVC


- Diameter Nominal 200 mm Bh Rp 1,290,000.00
- Diameter Nominal 150 mm Bh Rp 760,000.00
- Diameter Nominal 100 mm Bh Rp 464,000.00
- Diameter Nominal 75 mm Bh Rp 197,500.00
- Diameter Nominal 50 mm Bh Rp 161,000.00

End cap PVC (RRJ)


- Diameter Nominal 200 mm Bh Rp 359,000.00
- Diameter Nominal 150 mm Bh Rp 93,000.00
- Diameter Nominal 100 mm Bh Rp 42,500.00
- Diameter Nominal 75 mm Bh Rp 25,000.00
- Diameter Nominal 50 mm Bh Rp 14,000.00

Giboult joint untuk PVC / Steel


- Diameter Nominal 200 mm Bh Rp 927,500.00
- Diameter Nominal 150 mm Bh Rp 550,000.00
- Diameter Nominal 100 mm Bh Rp 330,000.00
- Diameter Nominal 75 mm Bh Rp 289,000.00
- Diameter Nominal 50 mm Bh Rp 210,000.00

Flange Ring
- Diameter Nominal 400 mm Bh Rp 796,000.00
- Diameter Nominal 350 mm Bh Rp 632,000.00
- Diameter Nominal 300 mm Bh Rp 408,000.00
- Diameter Nominal 250 mm Bh Rp 385,000.00
- Diameter Nominal 200 mm Bh Rp 258,000.00
- Diameter Nominal 150 mm Bh Rp 193,000.00
- Diameter Nominal 125 mm Bh Rp 135,500.00
- Diameter Nominal 100 mm Bh Rp 105,000.00
- Diameter Nominal 75 mm Bh Rp 90,000.00
- Diameter Nominal 50 mm Bh Rp 75,000.00

Blank Flange
- Diameter Nominal 200 mm Bh Rp 529,500.00
- Diameter Nominal 150 mm Bh Rp 364,500.00
- Diameter Nominal 125 mm Bh Rp 265,000.00
- Diameter Nominal 100 mm Bh Rp 199,500.00
Harga Dasar Upah dan Bahan 17 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
- Diameter Nominal 75 mm Bh Rp 165,000.00
- Diameter Nominal 50 mm Bh Rp 99,500.00

Box Street CI
- Diameter Nominal 200 mm Bh Rp 399,000.00
- Diameter Nominal 150 mm Bh Rp 235,100.00
- Diameter Nominal 125 mm Bh Rp 194,700.00
- Diameter Nominal 100 mm Bh Rp 169,500.00
- Diameter Nominal 75 mm Bh Rp 123,500.00
- Diameter Nominal 50 mm Bh Rp 104,500.00

Air Valve
- Diameter Nominal 100 mm Bh Rp 5,150,000.00
- Diameter Nominal 75 mm Bh Rp 3,650,000.00
- Diameter Nominal 50 mm Bh Rp 3,000,000.00
- Diameter Nominal 25 mm Bh Rp 1,000,000.00

Karet Packing
- Diameter Nominal 200 mm Bh Rp 32,500.00
- Diameter Nominal 150 mm Bh Rp 24,500.00
- Diameter Nominal 100 mm Bh Rp 15,500.00
- Diameter Nominal 75 mm Bh Rp 12,000.00
- Diameter Nominal 50 mm Bh Rp 7,800.00

Reducer PVC
- Diameter Nominal 200 x 150 mm Bh Rp 799,100.00
- Diameter Nominal 200 x 100 mm Bh Rp 1,155,500.00
- Diameter Nominal 200 x 75 mm Bh Rp 1,118,500.00
- Diameter Nominal 200 x 50 mm Bh Rp 1,052,700.00
- Diameter Nominal 150 x 100 mm Bh Rp 438,800.00
- Diameter Nominal 150 x 75 mm Bh Rp 562,300.00
- Diameter Nominal 150 x 50 mm Bh Rp 462,700.00
- Diameter Nominal 100 x 75 mm Bh Rp 228,700.00
- Diameter Nominal 100 x 50 mm Bh Rp 218,100.00
- Diameter Nominal 75 x 50 mm Bh Rp 234,800.00

Water Meter
- Diameter Nominal 200 mm Bh Rp 19,000,000.00
- Diameter Nominal 150 mm Bh Rp 14,500,000.00
- Diameter Nominal 100 mm Bh Rp 8,500,000.00
- Diameter Nominal 75 mm Bh Rp 7,000,000.00
- Diameter Nominal 50 mm Bh Rp 5,800,000.00
- Diameter Nominal 40 mm Bh Rp 2,500,000.00
- Diameter Nominal 32 mm Bh Rp 2,000,000.00
- Diameter Nominal 25 mm Bh Rp 1,750,000.00
- Diameter Nominal 20 mm Bh Rp 720,000.00
- Diameter Nominal 15 mm Bh Rp 330,000.00

Reducer all Flange GIP


- Diameter Nominal 200 x 150 mm Bh Rp 1,221,000.00
- Diameter Nominal 200 x 100 mm Bh Rp 1,025,000.00
- Diameter Nominal 200 x 75 mm Bh Rp 960,000.00
- Diameter Nominal 200 x 50 mm Bh Rp 825,000.00
- Diameter Nominal 150 x 100 mm Bh Rp 825,000.00
- Diameter Nominal 150 x 75 mm Bh Rp 760,000.00
- Diameter Nominal 150 x 50 mm Bh Rp 695,000.00
- Diameter Nominal 100 x 75 mm Bh Rp 430,000.00
- Diameter Nominal 100 x 50 mm Bh Rp 365,000.00
- Diameter Nominal 75 x 50 mm Bh Rp 330,000.00

Baut - Mour
- Baut dia. 5/8'' x 3'' Bh Rp 5,000.00
- Baut dia. 5/8'' x 4'' Bh Rp 7,200.00
- Baut dia. 3/4'' x 3'' Bh Rp 10,700.00
- Baut dia. 3/4'' x 4'' Bh Rp 12,700.00

Knie GIP 90 degree (Thread Joint)


- Diameter Nominal 100 mm ( 4'' ) Bh Rp 116,000.00
- Diameter Nominal 75 mm ( 3" ) Bh Rp 64,000.00
- Diameter Nominal 50 mm ( 2'' ) Bh Rp 22,000.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 14,000.00
Harga Dasar Upah dan Bahan 18 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 11,200.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 7,000.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 4,800.00
- Diameter Nominal 15 mm ( 1/2'' ) Bh Rp 3,400.00

Knie GIP 45 degree (Thread Joint)


- Diameter Nominal 100 mm ( 4'' ) Bh Rp 130,000.00
- Diameter Nominal 75 mm ( 3" ) Bh Rp 76,000.00
- Diameter Nominal 50 mm ( 2'' ) Bh Rp 24,000.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 16,000.00
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 13,000.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 8,000.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 5,400.00
- Diameter Nominal 15 mm ( 1/2'' ) Bh Rp 3,600.00

Double Nipple GIP ( Thread joint )


- Diameter Nominal 100 mm ( 4'' ) Bh Rp 70,000.00
- Diameter Nominal 75 mm ( 3" ) Bh Rp 44,000.00
- Diameter Nominal 50 mm ( 2'' ) Bh Rp 15,600.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 11,400.00
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 8,200.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 5,600.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 15,600.00
- Diameter Nominal 15 mm ( 1/2'' ) Bh Rp 3,000.00

Plug GIP ( Thread Joint )


- Diameter Nominal 150 mm ( 6'' ) Bh Rp 55,000.00
- Diameter Nominal 125 mm ( 5'' ) Bh Rp 50,000.00
- Diameter Nominal 100 mm ( 4'' ) Bh Rp 28,000.00
- Diameter Nominal 75 mm ( 3" ) Bh Rp 10,000.00
- Diameter Nominal 50 mm ( 2'' ) Bh Rp 7,000.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 6,000.00
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 4,000.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 3,000.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 2,400.00

Dop GIP ( Thred Joint )


- Diameter Nominal 150 mm ( 6'' ) Bh Rp 65,000.00
- Diameter Nominal 125 mm ( 5'' ) Bh Rp 60,000.00
- Diameter Nominal 100 mm ( 4'' ) Bh Rp 36,000.00
- Diameter Nominal 75 mm ( 3" ) Bh Rp 12,800.00
- Diameter Nominal 50 mm ( 2'' ) Bh Rp 9,200.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 7,000.00
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 4,800.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 3,400.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 2,800.00

Verlop Ring GIP ( Thread Joint )


- Diameter Nominal 125 x 100 mm ( 5'' x 4'' ) Bh Rp 60,000.00
- Diameter Nominal 100 x 75 mm ( 4'' x 3'' ) Bh Rp 21,000.00
- Diameter Nominal 50 x 40 mm ( 2'' x 1 1/2'' ) Bh Rp 10,000.00
- Diameter Nominal 40 x 32 mm ( 1 1/2'' x 1 1/4'' ) Bh Rp 7,200.00
- Diameter Nominal 32 x 25 mm ( 1 1/4'' x 1'' ) Bh Rp 6,000.00
- Diameter Nominal 25 x 20 mm ( 1'' x 3/4'' ) Bh Rp 4,500.00
- Diameter Nominal 20 x 15 mm ( 3/4" x 1/2'' ) Bh Rp 3,700.00

Verlop Socket / Reducer GIP ( Thread Joint )


- Diameter Nominal 150 x 125 mm ( 6'' x 5'' ) Bh Rp 92,000.00
- Diameter Nominal 125 x 100 mm ( 5'' x 4'' ) Bh Rp 50,000.00
- Diameter Nominal 100 x 75 mm ( 4'' x 3'' ) Bh Rp 17,000.00
- Diameter Nominal 50 x 40 mm ( 2'' x 1 1/2 ) Bh Rp 11,200.00
- Diameter Nominal 40 x 32 mm ( 1 1/2'' x 1 1/4'' ) Bh Rp 9,400.00
- Diameter Nominal 32 x 25 mm ( 1 1/4'' x 1'' ) Bh Rp 6,400.00
- Diameter Nominal 25 x 20 mm ( 1'' x 3/4'' ) Bh Rp 4,800.00

Verlop Tee GIP ( Thread Joint )


- Diameter Nominal 150 x 125 mm ( 6'' x 5'' ) Bh Rp 190,000.00
- Diameter Nominal 125 x 100 mm ( 5'' x 4'' ) Bh Rp 100,000.00
- Diameter Nominal 100 x 75 mm ( 4'' x 3'' ) Bh Rp 34,000.00
- Diameter Nominal 50 x 40 mm ( 2'' x 1 1/2 ) Bh Rp 24,000.00
- Diameter Nominal 40 x 32 mm ( 1 1/2'' x 1 1/4'' ) Bh Rp 19,000.00
Harga Dasar Upah dan Bahan 19 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
- Diameter Nominal 32 x 25 mm ( 1 1/4'' x 1'' ) Bh Rp 12,600.00
- Diameter Nominal 25 x 20 mm ( 1'' x 3/4'' ) Bh Rp 8,200.00

Socket GIP ( Thread Joint )


- Diameter Nominal 150 mm ( 6'' ) Bh Rp 220,000.00
- Diameter Nominal 125 mm ( 5'' ) Bh Rp 170,000.00
- Diameter Nominal 100 mm ( 4'' ) Bh Rp 72,000.00
- Diameter Nominal 75 mm ( 3" ) Bh Rp 44,000.00
- Diameter Nominal 50 mm ( 2'' ) Bh Rp 16,000.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 10,400.00
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 4,200.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 6,000.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 3,600.00
- Diameter Nominal 15 mm ( 1/2'' ) Bh Rp 2,800.00

Water Moer GIP (Thread Joint)


- Diameter Nominal 150 mm ( 6'' ) Bh Rp 540,000.00
- Diameter Nominal 125 mm ( 5'' ) Bh Rp 420,000.00
- Diameter Nominal 100 mm ( 4'' ) Bh Rp 240,000.00
- Diameter Nominal 75 mm ( 3" ) Bh Rp 126,000.00
- Diameter Nominal 50 mm ( 2'' ) Bh Rp 46,000.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 32,000.00
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 24,000.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 17,000.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 14,000.00
- Diameter Nominal 15 mm ( 1/2'' ) Bh Rp 11,400.00

Tee Stuk GIP ( Thread Joint )


- Diameter Nominal 150 x 150 mm ( 6'' x 6'' ) Bh Rp 540,000.00
- Diameter Nominal 125 x 125 mm ( 5'' x 5'' ) Bh Rp 400,000.00
- Diameter Nominal 100 x 100 mm ( 4'' x 4'' ) Bh Rp 152,000.00
- Diameter Nominal 75 x 75 mm ( 3" x 3'' ) Bh Rp 84,000.00
- Diameter Nominal 50 x 50 mm ( 2'' x 2'' ) Bh Rp 28,000.00
- Diameter Nominal 40 x 40 mm ( 1 1/2'' x 1 1/2'' ) Bh Rp 18,800.00
- Diameter Nominal 32 x 32 mm ( 1 1/4'' x 1 1/4'' ) Bh Rp 14,800.00
- Diameter Nominal 25 x 25 mm ( 1'' x 1'' ) Bh Rp 9,800.00
- Diameter Nominal 20 x 20 mm ( 3/4" x 3/4'' ) Bh Rp 6,200.00
- Diameter Nominal 15 x 15 mm ( 1/2" x 1/2'' ) Bh Rp 4,200.00

Bochten / Long Bow GIP (Thread Joint )


- Diameter Nominal 150 mm ( 6'' ) Bh Rp 1,000,000.00
- Diameter Nominal 125 mm ( 5'' ) Bh Rp 600,000.00
- Diameter Nominal 100 mm ( 4'' ) Bh Rp 280,000.00
- Diameter Nominal 75 mm ( 3" ) Bh Rp 136,000.00
- Diameter Nominal 50 mm ( 2'' ) Bh Rp 46,000.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 30,000.00
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 22,000.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 13,600.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 9,200.00
- Diameter Nominal 15 mm ( 1/2'' ) Bh Rp 6,800.00

Stop Kran ( Thread Joint )


- Diameter Nominal 150 mm ( 6'' ) Bh Rp 300,000.00
- Diameter Nominal 125 mm ( 5'' ) Bh Rp 250,000.00
- Diameter Nominal 100 mm ( 4'' ) Bh Rp 200,000.00
- Diameter Nominal 75 mm ( 3" ) Bh Rp 150,000.00
- Diameter Nominal 50 mm ( 2'' ) Bh Rp 100,000.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 80,000.00
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 64,000.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 50,000.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 25,000.00
- Diameter Nominal 15 mm ( 1/2'' ) Bh Rp 22,000.00

Kran ( Thread Joint )


- Diameter Nominal 25 mm ( 1'' ) Bh Rp 25,000.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 20,000.00
- Diameter Nominal 15 mm ( 1/2'' ) Bh Rp 15,000.00

Adaptor PVC - GIP ( Socket / Thread Joint )


- Diameter Nominal 50 mm ( 2'' ) Bh Rp 25,000.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 20,000.00
Harga Dasar Upah dan Bahan 20 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 16,000.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 12,500.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 10,000.00
- Diameter Nominal 15 mm ( 1/2'' ) Bh Rp 7,500.00

Stop Cock DN 15 mm ( Sambungan Lem )


- Diameter Nominal 50 mm ( 2'' ) Bh Rp 50,000.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 40,000.00
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 32,000.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 25,000.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 20,000.00
- Diameter Nominal 15 mm ( 1/2'' ) Bh Rp 15,000.00

Knee PVC ( Sambungan Lem)


- Diameter Nominal 50 mm ( 2'' ) Bh Rp 11,800.00
- Diameter Nominal 40 mm ( 1 1/2'' ) Bh Rp 9,100.00
- Diameter Nominal 32 mm ( 1 1/4'' ) Bh Rp 7,500.00
- Diameter Nominal 25 mm ( 1'' ) Bh Rp 5,000.00
- Diameter Nominal 20 mm ( 3/4" ) Bh Rp 3,500.00
- Diameter Nominal 15 mm ( 1/2'' ) Bh Rp 2,900.00

Tee PVC ( Sambungan Lem)


- Diameter Nominal 50 x 50 mm ( 2'' x 2'' ) Bh Rp 17,000.00
- Diameter Nominal 40 x 40 mm ( 1 1/2'' x 1 1/2'' ) Bh Rp 12,500.00
- Diameter Nominal 32 x 32 mm ( 1 1/4'' x 1 1/4'' ) Bh Rp 9,600.00
- Diameter Nominal 25 x 25 mm ( 1'' x 1'') Bh Rp 7,000.00
- Diameter Nominal 20 x 20 mm ( 3/4" x 3/4'' ) Bh Rp 4,400.00
- Diameter Nominal 15 x 15 mm ( 1/2'' x 1/2'' ) Bh Rp 6,400.00

Strainer Flange Joint


- Diameter Nominal 200 mm Bh Rp 927,500.00
- Diameter Nominal 150 mm Bh Rp 550,000.00
- Diameter Nominal 125 mm Bh Rp 445,000.00
- Diameter Nominal 100 mm Bh Rp 330,000.00
- Diameter Nominal 75 mm Bh Rp 289,000.00
- Diameter Nominal 50 mm Bh Rp 210,000.00

Screen Diameter
- Screen Diameter 4" Bh Rp 445,000.00
- Screen Diameter 6" Bh Rp 550,000.00
- Screen Diameter 8" Bh Rp 927,500.00

Wall Pipe GIP


- Diameter 150 mm - 0.60 M' Bh Rp 2,596,600.00
- Diameter 100 mm - 0.60 M' Bh Rp 1,595,900.00
- Diameter 75 mm - 1.00 M' Bh Rp 735,000.00
- Diameter 75 mm - 0.60 M' Bh Rp 685,000.00
- Diameter 75 mm - 0.50 M' Bh Rp 650,000.00

Stop Kran Brass


- Diameter 25 mm (1') Bh Rp 92,500.00
- Diameter 20 mm (3/4') Bh Rp 56,500.00
- Diameter 18 mm (1/2') Bh Rp 38,300.00

Tangki Hidrant Umum (Vibreglass)


- 2 M3 Unt Rp 4,414,700.00
- 3 M3 Unt Rp 6,323,100.00
- 4 M3 Unt Rp 7,563,800.00

Water Stop
- Waterstop PVC 150 mm M Rp 96,300.00
- Waterstop PVC 200 mm M Rp 125,900.00
- Waterstop PVC 270 mm M Rp 135,000.00
- Waterstop rubber lebar 150 mm - 200 mm M Rp 103,200.00

L. KELOMPOK BAHAN LAIN-LAIN


- Ajir acuan tanaman Bh Err:509
- Akustik Bh Err:509
- Blue/black print uk A1 Lbr
- Blue/black print uk A2 Lbr
- Blue/black print uk A3 Lbr
Harga Dasar Upah dan Bahan 21 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
- Karpet M2 Err:509
- Cetakan armor kg Err:509
- Copy CD (soft file) Bh #NAME?
- Foto Album Bh #NAME?
- Foto cuci film selulosa kimia rol Err:509
- Foto film selulosa kimia rol Err:509
- Foto printing Lbr #NAME?
- Foto copy kalkir A1 ke kalkir Lbr
- Foto copy kertas letter, legal, A4 Lbr
- Geo listrik sewa-hari Rp 1,500,000.00
- Geotekstil A M2 #DIV/0!
- Geotekstil B (Polyfelt, dll) M2 #DIV/0!
- Geotekstil C M2 #DIV/0!
- Geotekstil tali M2 #DIV/0!
- Geotekstil mesin jahit sewa-hari #DIV/0!
- Kalkarium kg #DIV/0!
- Karung plastik/bagor Bh Rp 2,900.00
- Karung Goni M2 Rp 13,500.00
- Kertas HVS 80 gr ukuran A0 M2 #DIV/0!
- Kertas HVS 80 gr ukuran A1 M2 #DIV/0!
- Kertas HVS 80 gr ukuran A2 M2 #DIV/0!
- Kertas HVS 80 gr ukuran A3 Lbr #DIV/0!
- Kertas HVS 70 gr ukuran A4/legal/letter/B5 Lbr #DIV/0!
- Kertas HVS 80 gr ukuran A4/legal/leter/B5 Lbr #DIV/0!
- Kertas kalkir 80 gr ukuran A0 rol #DIV/0!
- Kertas kalkir 80 gr ukuran A1 rol #DIV/0!
- Lem Kertas kg #DIV/0!
- Menjilid pakai kertas di lakban A4 Bh #DIV/0!
- Menjilid pakai kertas langsung A4 Bh #DIV/0!
- Menjilid pakai kertas langsung A4 + laminasi Bh #DIV/0!
- Menjilid uk A1 Bh #DIV/0!
- Menjilid uk A2 Bh #DIV/0!
- Menjilid uk A3 Bh #DIV/0!
- Motor 2 KW 1350 rpm + pengkabelan Bh #DIV/0!
- Motor 5 KW 1350 rpm + pengkabelan Bh #DIV/0!
- Motor 10 KW 1350 rpm + pengkabelan Bh #DIV/0!
- Parquet M2 #DIV/0!
- Plastik aerator Bh #DIV/0!
- Pemotong rumput #DIV/0!
- Pena rapido Bh #DIV/0!
- Perlengkapan ruang jaga meja kursi set #DIV/0!
- Rakit Bh #DIV/0!
- Ramset Bh #DIV/0!
- Reduksi kalkir A2 ke kertas A4 Lbr #DIV/0!
- Reduksi kalkir dari A1 ke A2 Lbr #DIV/0!
- Roda dorong Bh #DIV/0!
- Sewa komputer utk Drafting CAD sewa-bulan #DIV/0!
- Sewa scaner A4 sewa-bulan #DIV/0!
- Sewa plotter uk A1 sewa-bulan #DIV/0!
- Tali pengikat/tambang nylon m Rp 3,000.00
- Tali pengikat/tambang nylon btl #DIV/0!
- Tali pengikat/tambang nylon btl #DIV/0!
- Tali pengikat/tambang nylon Bh #DIV/0!
- Tali pengikat/tambang nylon set #DIV/0!
- Tali pengikat/tambang nylon Bh #DIV/0!
- Tali pengikat/tambang nylon Unit #DIV/0!
- Tali pengikat/tambang nylon paket #DIV/0!
- Tali pengikat/tambang nylon paket #DIV/0!
- Tali pengikat/tambang nylon paket #DIV/0!
- Tali pengikat/tambang nylon Ls #DIV/0!
- Tali pengikat/tambang nylon m #DIV/0!
- Tali pengikat/tambang nylon ls #DIV/0!
- Tali pengikat/tambang nylon Bh #DIV/0!
- Tali pengikat/tambang nylon Bh #DIV/0!
- Tali pengikat/tambang nylon sewa #DIV/0!
- Pahat Beton Bh Rp 33,700.00
- Gergaji Besi (lengkap) Bh Rp 87,500.00
- Palu/Godam Bh Rp 52,700.00
- Gundar Kawat Bh Rp 7,500.00

Kabel NYM 3 x 2.5 mm2 M1 Rp 11,000.00


Harga Dasar Upah dan Bahan 22 dari 205
HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
( Rp.)
PVC Hight Impact dia. 20 mm2 M1 Rp 5,000.00
Coupling / Socket dia. 20 mm2 Bh Rp 1,000.00
Clamp Cable dia. 20 mm2 Bh Rp 1,000.00
Junction Box Bh Rp 5,000.00
Lampu Downligh 8 Watt ( Philip ) Bh Rp 150,000.00
Lampu Downligh 18 Watt ( Philip ) Bh Rp 50,000.00
Saklar Tunggal Unit Rp 25,000.00
Saklar Ganda Unit Rp 30,000.00
Inbowdus Unit Rp 7,000.00
Kran Stainless bh Rp 60,000.00
Mesin pompa air Bh Rp 850,000.00

Harga Dasar Upah dan Bahan 23 dari 205


DAFTAR HARGA SATUAN PEKERJAAN BIDANG CIPTA KARYA

PROGRAM : PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM ( PSU )


KEGIATAN : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
SUBKEGIATAN : PERENCANAAN PENYEDIAAN PSU PERMUKIMAN
PEKERJAAN : PERENCANAAN PEMBANGUNAN MCK JORONG LOMPATAN KABUPATEN TANAH DATAR
LOKASI : JORONG LOMPATAN KABUPATEN TANAH DATAR
TAHUN ANGGARAN : 2021

KODE HARGA SATUAN


NO URAIAN PEKERJAAN SAT KET
ANALISA PEKERJAAN (Rp)

I PEKERJAAN PERSIAPAN

A PEKERJAAN PENDAHULUAN & PERSIAPAN


I Plank Nama Proyek Ls Rp 250,000.00
II Perlengkapan K3
1 Safety helmet Bh Rp 45,000.00
2 Sarung tangan Bh Rp 25,000.00
3 Rompi Bh Rp 75,000.00
4 Rambu Peringatan Bh Rp 100,000.00
5 sepatu Boot Bh Rp 65,000.00
6 Prokest Covid Ls Rp 400,000.00

III Managemen Mutu Ls Rp 2,000,000.00

1 Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter A.2.2.1.1 M2 Rp 314,889.74


2 Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter A.2.2.1.2 M2 Rp 399,232.24
3 Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter A.2.2.1.3 M2 Err:509
1 Pengukuran dan pemasangan 1 M" Bouwplank A.2.2.1.4 M1 Rp 83,527.29
5 Pembuatan 1 m2 kantor sementara Lantai Plesteran A.2.2.1.5 M2 Err:509
6 Pembuatan 1 m2 rumah jaga (konstruksi kayu) A.2.2.1.6 M2 Rp 1,403,539.72
7 Pembuatan 1 m2 gudang semen dan peralatan A.2.2.1.7 M2 Err:509
8 Pembuatan 1 m2 bedeng pekerja A.2.2.1.8 M2 Rp 1,330,408.42
2 Pembersihan 1 m2 lapangan dan perataan A.2.2.1.9 M2 Rp 21,175.00
10 Pembuatan 1 m2 steger/perancah dari bambu A.2.2.1.10 M2 #VALUE!
10 Pembuatan 1 buah kotak adukan ukuran 40 Cm x 50 Cm x 25 Cm A.2.2.1.11 Bh Rp 196,862.82
11 Pembuatan 1 m2 jalan sementara A.2.2.1.12 M2 Rp 224,427.50

II PEKERJAAN BONGKARAN
1 Pembongkaran 1 m3 dinding tembok bata A.2.2.1.14 M3 Rp 834,141.00
2 Pembongkaran 1 m2 Keramik A.2.2.1.14.a M2 Rp 7,700.00

III PEKERJAAN TANAH


1 Penggalian 1 m3 tanah biasa sedalam 1 m A.2.3.1.1 M3 Rp 91,437.50

IV PEKERJAAN BETON
1 Membuat Lantai kerja beton mutu f3c = 14,5 Mpa (K 175), slump (12 ± 2) Cm, w/c 0,66 A.4.1.1.5 M3 Rp 957,798.73
2 Pembesian 10 kg dengan besi polos atau besi ulir A.4.1.1.17 Kg Rp 14,726.80
3 Pemasangan 1 m2 bekisting untuk sloof A.4.1.1.21 M2 Rp 248,469.65
4 Pemasangan 1 m2 bekisting untuk Lantai A.4.1.1.24 M2 Rp 388,832.95

V PEKERJAAN DINDING
1 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1PC : 4 Pasir Pasang A.4.4.1.9 M2 Rp 133,901.68

VI PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 Plesteran 1PC : 4 Pasir Pasang tebal 15 mm A.4.4.2.4 M2 Rp 78,348.60
2 Pemasangan 1 m2 Acian A.4.4.2.27 M2 Rp 47,883.00

VII PEKERJAAN PENUTUP DINDING DAN LANTAI


1 Pemasangan 1 m2 Lantai keramik ukuran 25 Cm x 25 Cm A.4.4.3.36.a M2 Rp 296,666.70
2 Pemasangan 1 m2 dinding keramik 25Cm x 40 Cm Rp 361,170.48

VIII PEKERJAAN PLAFOND


1 Pekerjaan Pasangan Plafound Pvc ( JAVAPOND ) + Rangka Hollow Zinclaume4x4cm - M2 Rp 207,477.60
2 Pekerjaan Pasangan Lest Pvc ( JAVAPOND ) Cutting L - m Rp 16,527.50

IX PEKERJAAN KAYU
1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III A.4.6.1.2 M3 Rp 8,111,917.00
2 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II A.4.6.1.5 M2 Rp 816,624.60

X PEKERJAAN KUNCI DAN KACA


1 Pemasangan 1 buah kunci tanam antik A.4.6.2.1 Bh Rp 419,677.50
2 Pemasangan 1 buah kunci tanam biasa A.4.6.2.2 Bh Rp 195,112.50
3 Pemasangan 1 buah engsel pintu A.4.6.2.5 Bh Rp 54,384.00
4 Pemasangan 1 buah Spring Knip A.4.6.2.8 Bh Rp 102,410.00
5 Pemasangan 1 m2 kaca tebal 5 mm A.4.6.2.17 M2 Rp 159,346.00

XI PEKERJAAN PENGECATAN
1 Pengikisan/pengerokan permukaan cat lama A.4.7.1.1 M2 Rp 19,387.50
2 Pengecatan bidang kayu baru (1lapis plamuur, 1 lapis cat dasar,2 lapis cat penutup) A.4.7.1.4 M2 Rp 49,820.10

Harga Satuan Bidang Cipta Karya 24 dari 205


KODE HARGA SATUAN
NO URAIAN PEKERJAAN SAT KET
ANALISA PEKERJAAN (Rp)
3 Pengecatan 1 m2 tembok lama dinding dalam jotun Interior (1 lapis Alkalir, 2 lapis cat penutup) A.4.7.1.11 M2 Rp 23,034.00
4 Pengecatan 1 m2 tembok lama dinding Luar jotun Exterior (1 lapis Alkalir, 2 lapis cat penutup) A.4.7.1.11.a M2 Rp 35,310.00

XII PEKERJAAN SANITASI DALAM GEDUNG


1 Pemasangan 1 buah kran diameter 1/2" atau 3/4" A.5.1.1.19 M1 Rp 142,092.50
2 Pemasangan 1 M1 pipa PVC tipe AW diameter 3/4" A.5.1.1.26 M1 Rp 31,992.40
3 Pemasangan 1 M1 pipa PVC tipe AW diameter 1½" A.5.1.1.28 M1 Rp 51,374.40

Harga Satuan Bidang Cipta Karya 25 dari 205


KODE HARGA SATUAN
NO URAIAN PEKERJAAN SAT KET
ANALISA PEKERJAAN (Rp)
XIII PEKERJAAN ELEKTRIKAL
1 Pas. Instalasi Titik Lampu Downlight 18 Watt Titik Rp 355,300.00
2 Pas. Instalasi Titik Lampu Downlight 8 Watt titik Rp 245,300.00
3 Pas. Saklar Tunggal Schneider bh Rp 35,200.00
4 Pas. Saklar Ganda Schneider bh Rp 40,700.00

:Dibuat oleh
KONSULTAN PERENCANA
CV. GREEN RISE CONSULTANT

ALDY, ST
Team Leader

Harga Satuan Bidang Cipta Karya 26 dari 205


ANALISA HARGA SATUAN PEKERJAAN BIDANG CIPTA KARYA

PROGRAM : PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM ( PSU )


KEGIATAN : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
SUBKEGIATAN : PERENCANAAN PENYEDIAAN PSU PERMUKIMAN
PEKERJAAN : PERENCANAAN PEMBANGUNAN MCK JORONG LOMPATAN KABUPATEN TANAH DATAR
LOKASI : JORONG LOMPATAN KABUPATEN TANAH DATAR
TAHUN ANGGARAN : 2021

HARGA SATUAN PEKERJAAN PERSIAPAN

JENIS PEKERJAAN : A.2.2.1.1 Pembuatan 1 m2 pagar sementara dari kayu tinggi 2 meter
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 314,889.74

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4000 105,000.00 42,000.00
Tukang Kayu L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0200 175,000.00 3,500.00
JUMLAH TENAGA KERJA 79,000.00
B BAHAN
Dolken kayu φ 8-10 Cm Batang 1.2500 34,100.00 42,625.00
Semen Portland Kg 5.0000 1,240.00 6,200.00
Pasir beton m3 0.0050 176,500.00 882.50
Koral beton m3 0.0090 174,300.00 1,568.70
Kayu 5/7 m3 0.0720 1,962,100.00 141,271.20
Paku biasa 2" - 5" Kg 0.0600 18,600.00 1,116.00
Residu Liter 0.4000 34,000.00 13,600.00
JUMLAH HARGA BAHAN 207,263.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 286,263.40
E Overhead & profit 10% x Jumlah 28,626.34
F Harga Satuan Pekerjaan (D+E) 314,889.74

JENIS PEKERJAAN : A.2.2.1.2 Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 399,232.24

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang Kayu L.02 OH 0.4000 150,000.00 60,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0200 175,000.00 3,500.00
JUMLAH TENAGA KERJA 88,000.00
B BAHAN
Dolken kayu φ 8-10 Cm Batang 1.2500 34,100.00 42,625.00
Semen Portland Kg 2.5000 1,240.00 3,100.00
Seng gelombang Lbr 1.2000 55,200.00 66,240.00
Pasir beton m3 0.0050 176,500.00 882.50
Koral beton m3 0.0090 174,300.00 1,568.70
Kayu 5/7 m3 0.0720 1,962,100.00 141,271.20
Paku biasa 2" - 5" Kg 0.0600 18,600.00 1,116.00
Meni besi Liter 0.4500 40,300.00 18,135.00
JUMLAH HARGA BAHAN 274,938.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 362,938.40
E Overhead & profit 10% x Jumlah 36,293.84
F Harga Satuan Pekerjaan (D+E) 399,232.24

JENIS PEKERJAAN : A.2.2.1.3 Pembuatan 1 m2 pagar sementara dari kawat duri tinggi 1,8 meter
SATUAN : M2
HARGA SATUAN PEKERJAAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang Kayu L.02 OH 0.3000 150,000.00 45,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0200 175,000.00 3,500.00
JUMLAH TENAGA KERJA 73,000.00
B BAHAN
Dolken kayu φ 8-10 Cm Batang 1.0000 34,100.00 34,100.00
Semen Portland Kg 2.0000 1,240.00 2,480.00
Kawat duri M1 25.0000 Err:509 Err:509
Pasir beton m3 0.0050 176,500.00 882.50
Koral beton m3 0.0090 174,300.00 1,568.70
Paku biasa 2" - 5" Kg 0.0600 18,600.00 1,116.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.2.2.1.4 Pengukuran dan pemasangan 1 M" Bouwplank


SATUAN : M1
HARGA SATUAN PEKERJAAN : Rp 83,527.29

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang Kayu L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 28,125.00
B BAHAN
Kayu balok 5/7 m3 0.0120 2,446,500.00 29,358.00
Paku biasa 2" - 5" Kg 0.0200 18,600.00 372.00
Kayu papan 3/20 m3 0.0070 2,582,700.00 18,078.90
JUMLAH HARGA BAHAN 47,808.90
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 75,933.90
E Overhead & profit 10% x Jumlah 7,593.39
F Harga Satuan Pekerjaan (D+E) 83,527.29

JENIS PEKERJAAN : A.2.2.1.5 Pembuatan 1 m2 kantor sementara Lantai Plesteran


SATUAN : M2
HARGA SATUAN PEKERJAAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 2.0000 105,000.00 210,000.00
Tukang Kayu L.02 OH 2.0000 150,000.00 300,000.00
Tukang Batu L.02 OH 1.0000 150,000.00 150,000.00
Kepala tukang L.03 OH 0.3000 175,000.00 52,500.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 721,250.00
B BAHAN
Dolken kayu φ 8-10 Cm/400 Batang 1.2500 34,100.00 42,625.00
Kayu m3 0.1800 2,582,700.00 464,886.00
Paku biasa Kg 0.0800 18,600.00 1,488.00
Besi Strip Kg 1.1000 Err:509 Err:509
Semen Portland Kg 35.0000 1,240.00 43,400.00
Pasir Pasang m3 0.1500 176,600.00 26,490.00
Pasir beton m3 0.1000 176,500.00 17,650.00
Koral beton m3 0.1500 174,300.00 26,145.00
Bata Merah Bh 30.0000 700.00 21,000.00
Seng plat Lbr 0.2500 Err:509 Err:509
Jendela naco bh 0.2000 189,100.00 37,820.00
Kaca polos m2 0.0800 105,700.00 8,456.00
Kunci tanam Bh 0.1500 91,700.00 13,755.00
Plywood 4 mm Lbr 0.0600 83,700.00 5,022.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.2.2.1.6 Pembuatan 1 m2 rumah jaga (konstruksi kayu)


SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 1,403,539.72
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang Kayu L.02 OH 1.5000 150,000.00 225,000.00
Kepala tukang L.03 OH 0.1500 175,000.00 26,250.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 365,000.00
B BAHAN
Dolken kayu φ 8-10 Cm/400 cm Batang 3.0000 34,100.00 102,300.00
Kayu m3 0.2760 2,582,700.00 712,825.20
Paku biasa Kg 0.7000 18,600.00 13,020.00
Seng gelombang lbr 1.5000 55,200.00 82,800.00
JUMLAH HARGA BAHAN 910,945.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 1,275,945.20
E Overhead & profit 10% x Jumlah 127,594.52
F Harga Satuan Pekerjaan (D+E) 1,403,539.72

JENIS PEKERJAAN : A.2.2.1.7 Pembuatan 1 m2 gudang semen dan peralatan


SATUAN : M2
HARGA SATUAN PEKERJAAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang Kayu L.02 OH 2.0000 150,000.00 300,000.00
Kepala tukang L.03 OH 0.2000 175,000.00 35,000.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 448,750.00
B BAHAN
Dolken kayu φ 8-10 Cm Batang 1.7000 34,100.00 57,970.00
Kayu m3 0.2100 2,582,700.00 542,367.00
Paku biasa Kg 0.3000 18,600.00 5,580.00
Semen Portland Kg 10.5000 1,240.00 13,020.00
Pasir beton m3 0.0300 176,500.00 5,295.00
Koral beton m3 0.0500 174,300.00 8,715.00
Seng gelombang lbr 1.5000 55,200.00 82,800.00
Seng plat lbr 0.2500 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.2.2.1.8 Pembuatan 1 m2 bedeng pekerja


SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 1,330,408.42

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang Kayu L.02 OH 2.0000 150,000.00 300,000.00
Kepala tukang L.03 OH 0.2000 175,000.00 35,000.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 448,750.00
B BAHAN
Dolken kayu φ 8-10 Cm Batang 1.2500 34,100.00 42,625.00
Kayu m3 0.1860 2,582,700.00 480,382.20
Paku biasa Kg 0.3000 18,600.00 5,580.00
Semen Portland Kg 18.0000 1,240.00 22,320.00
Pasir beton m3 0.0300 176,500.00 5,295.00
Koral beton m3 0.0500 174,300.00 8,715.00
Seng gelombang lbr 1.5000 55,200.00 82,800.00
Plywood 4 mm lbr 1.3500 83,700.00 112,995.00
JUMLAH HARGA BAHAN 760,712.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 1,209,462.20
E Overhead & profit 10% x Jumlah 120,946.22
F Harga Satuan Pekerjaan (D+E) 1,330,408.42
JENIS PEKERJAAN : A.2.2.1.9 Pembersihan 1 m2 lapangan dan perataan
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 21,175.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 19,250.00
B BAHAN
-
JUMLAH HARGA BAHAN -
C PERALATAN
-
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 19,250.00
E Overhead & profit 10% x Jumlah 1,925.00
F Harga Satuan Pekerjaan (D+E) 21,175.00

JENIS PEKERJAAN : A.2.2.1.10 Pembuatan 1 m2 steger/perancah dari bambu


SATUAN : M2
HARGA SATUAN PEKERJAAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang Kayu L.02 OH 2.0000 150,000.00 300,000.00
Kepala tukang L.03 OH 0.2000 175,000.00 35,000.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 448,750.00
B BAHAN
Bambu diameter 6-8/600 Cm Batang 1.2500 a #VALUE!
Tali ijuk m3 0.1860 24,000.00 4,464.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.2.2.1.11 Pembuatan 1 buah kotak adukan ukuran 40 Cm x 50 Cm x 25 Cm


SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 196,862.82

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Tukang Kayu L.02 OH 0.3000 150,000.00 45,000.00
Kepala tukang L.03 OH 0.0300 175,000.00 5,250.00
JUMLAH TENAGA KERJA 50,250.00
B BAHAN
Kayu papan kelas III m2 0.0360 2,582,700.00 92,977.20
Kayu Balok kelas III m3 0.0140 2,446,500.00 34,251.00

Paku biasa Kg 0.0800 18,600.00 1,488.00


JUMLAH HARGA BAHAN 128,716.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 178,966.20
E Overhead & profit 10% x Jumlah 17,896.62
F Harga Satuan Pekerjaan (D+E) 196,862.82

JENIS PEKERJAAN : A.2.2.1.12 Pembuatan 1 m2 jalan sementara


SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 224,427.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 150,000.00 150,000.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 150,875.00
B BAHAN
Batu belah m3 0.1500 172,400.00 25,860.00
Batu pecah m3 0.0900 283,600.00 25,524.00
Pasir Pasang Kg 0.0100 176,600.00 1,766.00
JUMLAH HARGA BAHAN 53,150.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 204,025.00
E Overhead & profit 10% x Jumlah 20,402.50
F Harga Satuan Pekerjaan (D+E) 224,427.50

JENIS PEKERJAAN : A.2.2.1.13 Pembongkaran 1 m3 beton bertulang


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,668,282.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 13.3340 105,000.00 1,400,070.00
Mandor L.04 OH 0.6660 175,000.00 116,550.00
JUMLAH TENAGA KERJA 1,516,620.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 1,516,620.00
E Overhead & profit 10% x Jumlah 151,662.00
F Harga Satuan Pekerjaan (D+E) 1,668,282.00

JENIS PEKERJAAN : A.2.2.1.14 Pembongkaran 1 m3 dinding tembok bata


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 834,141.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 6.6670 105,000.00 700,035.00
Mandor L.04 OH 0.3330 175,000.00 58,275.00
JUMLAH TENAGA KERJA 758,310.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 758,310.00
E Overhead & profit 10% x Jumlah 75,831.00
F Harga Satuan Pekerjaan (D+E) 834,141.00

JENIS PEKERJAAN : A.2.2.1.14.a Pembongkaran 1 m2 Keramik


SATUAN : m2
HARGA SATUAN PEKERJAAN : Rp 7,700.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0500 105,000.00 5,250.00
Mandor L.04 OH 0.0100 175,000.00 1,750.00
JUMLAH TENAGA KERJA 7,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 7,000.00
E Overhead & profit 10% x Jumlah 700.00
F Harga Satuan Pekerjaan (D+E) 7,700.00
JENIS PEKERJAAN : A.2.2.1.15 Pemasangan 1 m2 pagar kawat jaring galvanis panjang 240 Cm
SATUAN : M2
HARGA SATUAN PEKERJAAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0420 105,000.00 4,410.00
Tukang Kayu L.02 OH 0.0040 150,000.00 600.00
Kepala tukang L.03 OH 0.0020 175,000.00 350.00
Mandor L.04 OH 0.0420 175,000.00 7,350.00
JUMLAH TENAGA KERJA 12,710.00
B BAHAN
Kawat jaring Lbr 0.1434 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.2.2.1.16 Pemasangan 1 m2 panel beton pracetak 5x50x213 Cm


SATUAN : M2
HARGA SATUAN PEKERJAAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3750 105,000.00 39,375.00
Tukang Kayu L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0190 175,000.00 3,325.00
JUMLAH TENAGA KERJA 63,550.00
B BAHAN
Panel beton pracetak Lbr 0.9860 a #VALUE!
Kolom beton pracetak Batang 0.5250 a #VALUE!
Semen Portland Kg 45.0000 1,240.00 55,800.00
Pasir beton m3 0.0740 176,500.00 13,061.00
Koral m3 0.1460 174,300.00 25,447.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

HARGA SATUAN PEKERJAAN TANAH

JENIS PEKERJAAN : A.2.3.1.1 Penggalian 1 m3 tanah biasa sedalam 1 m


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 91,437.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7500 105,000.00 78,750.00
Mandor L.04 OH 0.0250 175,000.00 4,375.00
JUMLAH TENAGA KERJA 83,125.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 83,125.00
E Overhead & profit 10% x Jumlah 8,312.50
F Harga Satuan Pekerjaan (D+E) 91,437.50

JENIS PEKERJAAN : A.2.3.1.2 Penggalian 1 m3 tanah biasa sedalam 2 m


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 112,612.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 102,375.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 102,375.00
E Overhead & profit 10% x Jumlah 10,237.50
F Harga Satuan Pekerjaan (D+E) 112,612.50

JENIS PEKERJAAN : A.2.3.1.3 Penggalian 1 m3 tanah biasa sedalam 3 m


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 134,172.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0500 105,000.00 110,250.00
Mandor L.04 OH 0.0670 175,000.00 11,725.00
JUMLAH TENAGA KERJA 121,975.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 121,975.00
E Overhead & profit 10% x Jumlah 12,197.50
F Harga Satuan Pekerjaan (D+E) 134,172.50

JENIS PEKERJAAN : A.2.3.1.4 Penggalian 1 m3 tanah keras sedalam 1 m


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 121,660.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Mandor L.04 OH 0.0320 175,000.00 5,600.00
JUMLAH TENAGA KERJA 110,600.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 110,600.00
E Overhead & profit 10% x Jumlah 11,060.00
F Harga Satuan Pekerjaan (D+E) 121,660.00

JENIS PEKERJAAN : A.2.3.1.5 Penggalian 1 m3 tanah cadas sedalam 1 m


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 184,800.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.5000 105,000.00 157,500.00
Mandor L.04 OH 0.0600 175,000.00 10,500.00
JUMLAH TENAGA KERJA 168,000.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 168,000.00
E Overhead & profit 10% x Jumlah 16,800.00
F Harga Satuan Pekerjaan (D+E) 184,800.00

JENIS PEKERJAAN : A.2.3.1.6 Penggalian 1 m3 tanah lumpur sedalam 1 m


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 147,262.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.2000 105,000.00 126,000.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 133,875.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 133,875.00
E Overhead & profit 10% x Jumlah 13,387.50
F Harga Satuan Pekerjaan (D+E) 147,262.50

JENIS PEKERJAAN : A.2.3.1.7 Pengerjaan striping 1 m2 tanah tebing setinggi 1 meter


SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 6,737.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0500 105,000.00 5,250.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 6,125.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 6,125.00
E Overhead & profit 10% x Jumlah 612.50
F Harga Satuan Pekerjaan (D+E) 6,737.50

JENIS PEKERJAAN : A.2.3.1.8 Pembuangan 1 m3 tanah sejauh 30 meter


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 40,040.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3300 105,000.00 34,650.00
Mandor L.04 OH 0.0100 175,000.00 1,750.00
JUMLAH TENAGA KERJA 36,400.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 36,400.00
E Overhead & profit 10% x Jumlah 3,640.00
F Harga Satuan Pekerjaan (D+E) 40,040.00

JENIS PEKERJAAN : A.2.3.1.9 Pengurugan kembali 1 m3 galian tanah


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 67,375.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.5000 105,000.00 52,500.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 61,250.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 61,250.00
E Overhead & profit 10% x Jumlah 6,125.00
F Harga Satuan Pekerjaan (D+E) 67,375.00

JENIS PEKERJAAN : A.2.3.1.10 Pemadatan tanah 1 m3 tanah (per 20 Cm)


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 67,375.00
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.5000 105,000.00 52,500.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 61,250.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 61,250.00
E Overhead & profit 10% x Jumlah 6,125.00
F Harga Satuan Pekerjaan (D+E) 67,375.00

JENIS PEKERJAAN : A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 189,431.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Mandor L.04 OH 0.0100 175,000.00 1,750.00
JUMLAH TENAGA KERJA 33,250.00
B BAHAN
Pasir urug m3 1.2000 115,800.00 138,960.00
JUMLAH HARGA BAHAN 138,960.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 172,210.00
E Overhead & profit 10% x Jumlah 17,221.00
F Harga Satuan Pekerjaan (D+E) 189,431.00

JENIS PEKERJAAN : A.2.3.1.12 Pemasangan 1 m3 lapisan pudel Camp, 1Kapur Padam : 3 Pasir Pasang : 7TL
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 502,143.40

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.8000 105,000.00 84,000.00
Tukang L.02 OH 0.4000 150,000.00 60,000.00
Kepala tukang L.03 OH 0.0400 175,000.00 7,000.00
Mandor L.04 OH 0.0800 175,000.00 14,000.00
JUMLAH TENAGA KERJA 165,000.00
B BAHAN
Kapur m3 0.1350 860,000.00 116,100.00
Pasir Pasang m3 0.4000 176,600.00 70,640.00
Tanah liat m3 0.9480 110,500.00 104,754.00
JUMLAH HARGA BAHAN 291,494.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 456,494.00
E Overhead & profit 10% x Jumlah 45,649.40
F Harga Satuan Pekerjaan (D+E) 502,143.40

JENIS PEKERJAAN : A.2.3.1.13 Pemasangan 1 m2 lapisan ijuk tebal 10 Cm untuk bidang resapan
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 178,612.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 18,375.00
B BAHAN
Ijuk m3 6.0000 24,000.00 144,000.00
JUMLAH HARGA BAHAN 144,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 162,375.00
E Overhead & profit 10% x Jumlah 16,237.50
F Harga Satuan Pekerjaan (D+E) 178,612.50

JENIS PEKERJAAN : A.2.3.1.14 Pengurugan 1 m3 sirtu padat


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 259,935.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Mandor L.04 OH 0.0250 175,000.00 4,375.00
JUMLAH TENAGA KERJA 30,625.00
B BAHAN
Sirtu m3 1.2000 171,400.00 205,680.00
JUMLAH HARGA BAHAN 205,680.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 236,305.00
E Overhead & profit 10% x Jumlah 23,630.50
F Harga Satuan Pekerjaan (D+E) 259,935.50

HARGA SATUAN PEKERJAAN PONDASI

JENIS PEKERJAAN : A.3.2.1.1 Pemasangan 1 m3 pondasi batu belah Camp, 1PC : 3 Pasir Pasang
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 923,187.10

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.5000 105,000.00 157,500.00
Tukang L.02 OH 0.7500 150,000.00 112,500.00
Kepala tukang L.03 OH 0.0750 175,000.00 13,125.00
Mandor L.04 OH 0.0750 175,000.00 13,125.00
JUMLAH TENAGA KERJA 296,250.00
B BAHAN
Batu belah m3 1.2000 172,400.00 206,880.00
Semen Portland Kg 202.0000 1,240.00 250,480.00
Pasir Pasang m3 0.4850 176,600.00 85,651.00
JUMLAH HARGA BAHAN 543,011.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 839,261.00
E Overhead & profit 10% x Jumlah 83,926.10
F Harga Satuan Pekerjaan (D+E) 923,187.10

JENIS PEKERJAAN : A.3.2.1.2 Pemasangan 1 m3 pondasi batu belah Camp, 1PC : 4 Pasir Pasang
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 876,790.20

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.5000 105,000.00 157,500.00
Tukang L.02 OH 0.7500 150,000.00 112,500.00
Kepala tukang L.03 OH 0.0750 175,000.00 13,125.00
Mandor L.04 OH 0.0750 175,000.00 13,125.00
JUMLAH TENAGA KERJA 296,250.00
B BAHAN
Batu belah m3 1.2000 172,400.00 206,880.00
Semen Portland Kg 163.0000 1,240.00 202,120.00
Pasir Pasang m3 0.5200 176,600.00 91,832.00
JUMLAH HARGA BAHAN 500,832.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 797,082.00
E Overhead & profit 10% x Jumlah 79,708.20
F Harga Satuan Pekerjaan (D+E) 876,790.20
JENIS PEKERJAAN : A.3.2.1.3 Pemasangan 1 m3 pondasi batu belah Camp, 1PC : 5 Pasir Pasang
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 844,624.44

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.5000 105,000.00 157,500.00
Tukang L.02 OH 0.7500 150,000.00 112,500.00
Kepala tukang L.03 OH 0.0750 175,000.00 13,125.00
Mandor L.04 OH 0.0750 175,000.00 13,125.00
JUMLAH TENAGA KERJA 296,250.00
B BAHAN
Batu belah m3 1.2000 172,400.00 206,880.00
Semen Portland Kg 136.0000 1,240.00 168,640.00
Pasir Pasang m3 0.5440 176,600.00 96,070.40
JUMLAH HARGA BAHAN 471,590.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 767,840.40
E Overhead & profit 10% x Jumlah 76,784.04
F Harga Satuan Pekerjaan (D+E) 844,624.44

JENIS PEKERJAAN : A.3.2.1.4 Pemasangan 1 m3 pondasi batu belah Camp, 1PC : 6 Pasir Pasang
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 822,010.86

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.5000 105,000.00 157,500.00
Tukang L.02 OH 0.7500 150,000.00 112,500.00
Kepala tukang L.03 OH 0.0750 175,000.00 13,125.00
Mandor L.04 OH 0.0750 175,000.00 13,125.00
JUMLAH TENAGA KERJA 296,250.00
B BAHAN
Batu belah m3 1.2000 172,400.00 206,880.00
Semen Portland Kg 117.0000 1,240.00 145,080.00
Pasir Pasang m3 0.5610 176,600.00 99,072.60
JUMLAH HARGA BAHAN 451,032.60
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 747,282.60
E Overhead & profit 10% x Jumlah 74,728.26
F Harga Satuan Pekerjaan (D+E) 822,010.86

JENIS PEKERJAAN : A.3.2.1.5 Pemasangan 1 m3 pondasi batu belah Camp, 1PC : 8 Pasir Pasang
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 791,014.84

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.5000 105,000.00 157,500.00
Tukang L.02 OH 0.7500 150,000.00 112,500.00
Kepala tukang L.03 OH 0.0750 175,000.00 13,125.00
Mandor L.04 OH 0.0750 175,000.00 13,125.00
JUMLAH TENAGA KERJA 296,250.00
B BAHAN
Batu belah m3 1.2000 172,400.00 206,880.00
Semen Portland Kg 91.0000 1,240.00 112,840.00
Pasir Pasang m3 0.5840 176,600.00 103,134.40
JUMLAH HARGA BAHAN 422,854.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 719,104.40
E Overhead & profit 10% x Jumlah 71,910.44
F Harga Satuan Pekerjaan (D+E) 791,014.84
JENIS PEKERJAAN : A.3.2.1.6 Pemasangan 1 m3 pondasi batu belah Camp, 1PC : 1Kapur Padam : 2 Pasir Pasang
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 780,543.28

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.5000 105,000.00 157,500.00
Tukang L.02 OH 0.7500 150,000.00 112,500.00
Kepala tukang L.03 OH 0.0750 175,000.00 13,125.00
Mandor L.04 OH 0.0750 175,000.00 13,125.00
JUMLAH TENAGA KERJA 296,250.00
B BAHAN
Batu belah m3 1.2000 172,400.00 206,880.00
Kapur m3 0.1700 860,000.00 146,200.00
Semen Portland Kg 0.1700 1,240.00 210.80
Pasir Pasang m3 0.3400 176,600.00 60,044.00
JUMLAH HARGA BAHAN 413,334.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 709,584.80
E Overhead & profit 10% x Jumlah 70,958.48
F Harga Satuan Pekerjaan (D+E) 780,543.28

JENIS PEKERJAAN : A.3.2.1.7 Pemasangan 1 m3 pondasi batu belah Camp, 1PC : 3Kapur Padam : 10 Pasir Pasang
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 871,284.92

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.5000 105,000.00 157,500.00
Tukang L.02 OH 0.7500 150,000.00 112,500.00
Kepala tukang L.03 OH 0.0750 175,000.00 13,125.00
Mandor L.04 OH 0.0750 175,000.00 13,125.00
JUMLAH TENAGA KERJA 296,250.00
B BAHAN
Batu belah m3 1.2000 172,400.00 206,880.00
Semen Portland Kg 61.0000 1,240.00 75,640.00
Kapur m3 0.1470 860,000.00 126,420.00
Pasir Pasang m3 0.4920 176,600.00 86,887.20
JUMLAH HARGA BAHAN 495,827.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 792,077.20
E Overhead & profit 10% x Jumlah 79,207.72
F Harga Satuan Pekerjaan (D+E) 871,284.92

JENIS PEKERJAAN : A.3.2.1.8 Pemasangan 1 m3 pondasi batu belah Camp, 1/4 PC : 1Kapur Padam : 4 Pasir Pasang
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 834,890.98

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.5000 105,000.00 157,500.00
Tukang batu L.02 OH 0.7500 150,000.00 112,500.00
Kepala tukang L.03 OH 0.0750 175,000.00 13,125.00
Mandor L.04 OH 0.0750 175,000.00 13,125.00
JUMLAH TENAGA KERJA 296,250.00
B BAHAN
Batu belah m3 1.2000 172,400.00 206,880.00
Semen Portland Kg 41.0000 1,240.00 50,840.00
Kapur m3 0.1310 860,000.00 112,660.00
Pasir Pasang m3 0.5230 176,600.00 92,361.80
JUMLAH HARGA BAHAN 462,741.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 758,991.80
E Overhead & profit 10% x Jumlah 75,899.18
F Harga Satuan Pekerjaan (D+E) 834,890.98

JENIS PEKERJAAN : A.3.2.1.9 Pemasangan 1 m3 pondasi batu kosong (Aanstampang)


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 452,051.16
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7800 105,000.00 81,900.00
Tukang Batu L.02 OH 0.3900 150,000.00 58,500.00
Kepala tukang L.03 OH 0.0390 175,000.00 6,825.00
Mandor L.04 OH 0.0390 175,000.00 6,825.00
JUMLAH TENAGA KERJA 154,050.00
B BAHAN
Batu belah m3 1.2000 172,400.00 206,880.00
Pasir urug m3 0.4320 115,800.00 50,025.60
JUMLAH HARGA BAHAN 256,905.60
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 410,955.60
E Overhead & profit 10% x Jumlah 41,095.56
F Harga Satuan Pekerjaan (D+E) 452,051.16

JENIS PEKERJAAN : A.3.2.1.10 Pemasangan 1 m3 pondasi siklop, 60% beton Camp, 1PC : 2 PB : 3 Kr dan
40% batu belah
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 2,594,171.14

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 3.4000 105,000.00 357,000.00
Tukang Batu L.02 OH 0.8500 150,000.00 127,500.00
Kepala tukang L.03 OH 0.0850 175,000.00 14,875.00
Mandor L.04 OH 0.1700 175,000.00 29,750.00
JUMLAH TENAGA KERJA 529,125.00
B BAHAN
Batu belah m3 0.4800 172,400.00 82,752.00
Semen Portland Kg 194.0000 1,240.00 240,560.00
Pasir beton m3 0.3120 176,500.00 55,068.00
Kerikil m3 0.4680 174,300.00 81,572.40
Besi beton Kg 126.0000 10,600.00 1,335,600.00
Kawat beton Kg 1.8000 18,700.00 33,660.00
JUMLAH HARGA BAHAN 1,829,212.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 2,358,337.40
E Overhead & profit 10% x Jumlah 235,833.74
F Harga Satuan Pekerjaan (D+E) 2,594,171.14

JENIS PEKERJAAN : A.3.2.1.11 Pemasangan 1 m3 pondasi sumuran, diameter 100 Cm


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 947,765.94

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 2.4000 105,000.00 252,000.00
Tukang Batu L.02 OH 0.8000 150,000.00 120,000.00
Kepala tukang L.03 OH 0.0800 175,000.00 14,000.00
Mandor L.04 OH 0.1190 175,000.00 20,825.00
JUMLAH TENAGA KERJA 406,825.00
B BAHAN
Batu belah m3 0.4500 172,400.00 77,580.00
Semen Portland Kg 194.0000 1,240.00 240,560.00
Pasir beton m3 0.3120 176,500.00 55,068.00
Kerikil m3 0.4680 174,300.00 81,572.40
JUMLAH HARGA BAHAN 454,780.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 861,605.40
E Overhead & profit 10% x Jumlah 86,160.54
F Harga Satuan Pekerjaan (D+E) 947,765.94

HARGA SATUAN PEKERJAAN BETON

JENIS PEKERJAAN : A.4.1.1.1 Membuat beton mutu f3c = 7,4 Mpa (K 100), slump (12 ± 2) Cm, w/c 0,87
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 860,898.03
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6500 105,000.00 173,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Kepala tukang L.03 OH 0.0280 175,000.00 4,900.00
Mandor L.04 OH 0.0830 175,000.00 14,525.00
JUMLAH TENAGA KERJA 233,925.00
B BAHAN
Semen Portland Kg 247.0000 1,240.00 306,280.00
Pasir beton Kg 869.0000 126.07 109,556.07
Kerikil (Maks 30 mm) Kg 999.0000 129.11 128,982.00
Air Liter 215.0000 18.10 3,891.50
JUMLAH HARGA BAHAN 548,709.57
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 782,634.57
E Overhead & profit 10% x Jumlah 78,263.46
F Harga Satuan Pekerjaan (D+E) 860,898.03

JENIS PEKERJAAN : A.4.1.1.2 Membuat beton mutu f3c = 9,8 Mpa (K 125), slump (12 ± 2) Cm, w/c 0,78
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 896,614.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6500 105,000.00 173,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Kepala tukang L.03 OH 0.0280 175,000.00 4,900.00
Mandor L.04 OH 0.0830 175,000.00 14,525.00
JUMLAH TENAGA KERJA 233,925.00
B BAHAN
Semen Portland Kg 276.0000 1,240.00 342,240.00
Pasir beton Kg 828.0000 126.07 104,387.14
Kerikil (Maks 30 mm) Kg 1012.0000 129.11 130,660.44
Air Liter 215.0000 18.10 3,891.50
JUMLAH HARGA BAHAN 581,179.09
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 815,104.09
E Overhead & profit 10% x Jumlah 81,510.41
F Harga Satuan Pekerjaan (D+E) 896,614.50

JENIS PEKERJAAN : A.4.1.1.3 Membuat beton mutu f3c = 12,2 Mpa (K 150), slump (12 ± 2) Cm, w/c 0,72
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 924,674.93

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6500 105,000.00 173,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Kepala tukang L.03 OH 0.0280 175,000.00 4,900.00
Mandor L.04 OH 0.0830 175,000.00 14,525.00
JUMLAH TENAGA KERJA 233,925.00
B BAHAN
Semen Portland Kg 299.0000 1,240.00 370,760.00
Pasir beton Kg 799.0000 126.07 100,731.07
Kerikil (Maks 30 mm) Kg 1017.0000 129.11 131,306.00
Air Liter 215.0000 18.10 3,891.50
JUMLAH HARGA BAHAN 606,688.57
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 840,613.57
E Overhead & profit 10% x Jumlah 84,061.36
F Harga Satuan Pekerjaan (D+E) 924,674.93

JENIS PEKERJAAN : A.4.1.1.4 Membuat Lantai kerja beton mutu f3c = 7,4 Mpa (K 100), slump (3 - 6) Cm, w/c 0,87
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 774,398.79

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.2000 105,000.00 126,000.00
Tukang Batu L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0600 175,000.00 10,500.00
JUMLAH TENAGA KERJA 170,000.00
B BAHAN
Semen Portland Kg 230.0000 1,240.00 285,200.00
Pasir beton Kg 893.0000 126.07 112,581.79
Kerikil (Maks 30 mm) Kg 1027.0000 129.11 132,597.11
Air Liter 200.0000 18.10 3,620.00
JUMLAH HARGA BAHAN 533,998.90
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 703,998.90
E Overhead & profit 10% x Jumlah 70,399.89
F Harga Satuan Pekerjaan (D+E) 774,398.79

JENIS PEKERJAAN : A.4.1.1.5 Membuat Lantai kerja beton mutu f3c = 14,5 Mpa (K 175), slump (12 ± 2) Cm, w/c 0,66

SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 957,798.73

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6500 105,000.00 173,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Kepala tukang L.03 OH 0.0280 175,000.00 4,900.00
Mandor L.04 OH 0.0830 175,000.00 14,525.00
JUMLAH TENAGA KERJA 233,925.00
B BAHAN
Semen Portland Kg 326.0000 1,240.00 404,240.00
Pasir beton Kg 760.0000 126.07 95,814.29
Kerikil (Maks 30 mm) Kg 1029.0000 129.11 132,855.33
Air Liter 215.0000 18.10 3,891.50
JUMLAH HARGA BAHAN 636,801.12
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 870,726.12
E Overhead & profit 10% x Jumlah 87,072.61
F Harga Satuan Pekerjaan (D+E) 957,798.73

JENIS PEKERJAAN : A.4.1.1.6 Membuat Lantai kerja beton mutu f3c = 16,9 Mpa (K 200), slump (12 ± 2) Cm, w/c 0,61
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 989,525.10

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6500 105,000.00 173,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Kepala tukang L.03 OH 0.0280 175,000.00 4,900.00
Mandor L.04 OH 0.0830 175,000.00 14,525.00
JUMLAH TENAGA KERJA 233,925.00
B BAHAN
Semen Portland Kg 352.0000 1,240.00 436,480.00
Pasir beton Kg 731.0000 126.07 92,158.21
Kerikil (Maks 30 mm) Kg 1031.0000 129.11 133,113.56
Air Liter 215.0000 18.10 3,891.50
JUMLAH HARGA BAHAN 665,643.27
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 899,568.27
E Overhead & profit 10% x Jumlah 89,956.83
F Harga Satuan Pekerjaan (D+E) 989,525.10

JENIS PEKERJAAN : A.4.1.1.7 Membuat Lantai kerja beton mutu f3c = 19,3 Mpa (K 225), slump (12 ± 2) Cm, w/c 0,58
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,013,137.06

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6500 105,000.00 173,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Kepala tukang L.03 OH 0.0280 175,000.00 4,900.00
Mandor L.04 OH 0.0830 175,000.00 14,525.00
JUMLAH TENAGA KERJA 233,925.00
B BAHAN
Semen Portland Kg 371.0000 1,240.00 460,040.00
Pasir beton Kg 698.0000 126.07 87,997.86
Kerikil (Maks 30 mm) Kg 1047.0000 129.11 135,179.33
Air Liter 215.0000 18.10 3,891.50
JUMLAH HARGA BAHAN 687,108.69
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 921,033.69
E Overhead & profit 10% x Jumlah 92,103.37
F Harga Satuan Pekerjaan (D+E) 1,013,137.06

JENIS PEKERJAAN : A.4.1.1.8 Membuat Lantai kerja beton mutu f3c = 21,7 Mpa (K 250), slump (12 ± 2) Cm, w/c 0,56
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,028,900.81

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6500 105,000.00 173,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Kepala tukang L.03 OH 0.0280 175,000.00 4,900.00
Mandor L.04 OH 0.0830 175,000.00 14,525.00
JUMLAH TENAGA KERJA 233,925.00
B BAHAN
Semen Portland Kg 384.0000 1,240.00 476,160.00
Pasir beton Kg 692.0000 126.07 87,241.43
Kerikil (Maks 30 mm) Kg 1039.0000 129.11 134,146.44
Air Liter 215.0000 18.10 3,891.50
JUMLAH HARGA BAHAN 701,439.37
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 935,364.37
E Overhead & profit 10% x Jumlah 93,536.44
F Harga Satuan Pekerjaan (D+E) 1,028,900.81

JENIS PEKERJAAN : A.4.1.1.9 Membuat Lantai kerja beton mutu f3c = 24,0 Mpa (K 275), slump (12 ± 2) Cm, w/c 0,53
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,055,953.09

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6500 105,000.00 173,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Kepala tukang L.03 OH 0.0280 175,000.00 4,900.00
Mandor L.04 OH 0.0830 175,000.00 14,525.00
JUMLAH TENAGA KERJA 233,925.00
B BAHAN
Semen Portland Kg 406.0000 1,240.00 503,440.00
Pasir beton Kg 684.0000 126.07 86,232.86
Kerikil (Maks 30 mm) Kg 1026.0000 129.11 132,468.00
Air Liter 215.0000 18.10 3,891.50
JUMLAH HARGA BAHAN 726,032.36
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 959,957.36
E Overhead & profit 10% x Jumlah 95,995.74
F Harga Satuan Pekerjaan (D+E) 1,055,953.09

JENIS PEKERJAAN : A.4.1.1.10 Membuat Lantai kerja beton mutu f3c = 26,4 Mpa (K 300), slump (12 ± 2) Cm, w/c 0,52
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,064,374.95

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6500 105,000.00 173,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Kepala tukang L.03 OH 0.0280 175,000.00 4,900.00
Mandor L.04 OH 0.0830 175,000.00 14,525.00
JUMLAH TENAGA KERJA 233,925.00
B BAHAN
Semen Portland Kg 413.0000 1,240.00 512,120.00
Pasir beton Kg 681.0000 126.07 85,854.64
Kerikil (Maks 30 mm) Kg 1021.0000 129.11 131,822.44
Air Liter 215.0000 18.10 3,891.50
JUMLAH HARGA BAHAN 733,688.59
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 967,613.59
E Overhead & profit 10% x Jumlah 96,761.36
F Harga Satuan Pekerjaan (D+E) 1,064,374.95

JENIS PEKERJAAN : A.4.1.1.11 Membuat Lantai kerja beton mutu f3c = 28,8 Mpa (K 325), slump (12 ± 2) Cm, w/c 0,49

SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,166,115.65

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 2.1000 105,000.00 220,500.00
Tukang Batu L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.1050 175,000.00 18,375.00
JUMLAH TENAGA KERJA 297,500.00
B BAHAN
Semen Portland Kg 439.0000 1,240.00 544,360.00
Pasir beton Kg 670.0000 126.07 84,467.86
Kerikil (Maks 30 mm) Kg 1006.0000 129.11 129,885.78
Air Liter 215.0000 18.10 3,891.50
JUMLAH HARGA BAHAN 762,605.13
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 1,060,105.13
E Overhead & profit 10% x Jumlah 106,010.51
F Harga Satuan Pekerjaan (D+E) 1,166,115.65

JENIS PEKERJAAN : A.4.1.1.12 Membuat Lantai kerja beton mutu f3c = 31,2 Mpa (K 350), slump (12 ± 2) Cm, w/c 0,48
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,177,123.48

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 2.1000 105,000.00 220,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.1050 175,000.00 18,375.00
JUMLAH TENAGA KERJA 297,500.00
B BAHAN
Semen Portland Kg 448.0000 1,240.00 555,520.00
Pasir beton Kg 667.0000 126.07 84,089.64
Kerikil (Maks 30 mm) Kg 1000.0000 129.11 129,111.11
Air Liter 215.0000 18.10 3,891.50
JUMLAH HARGA BAHAN 772,612.25
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 1,070,112.25
E Overhead & profit 10% x Jumlah 107,011.23
F Harga Satuan Pekerjaan (D+E) 1,177,123.48

JENIS PEKERJAAN : A.4.1.1.13 Membuat beton kedap air dengan strorox - 100
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,185,954.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 2.1000 105,000.00 220,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.1050 175,000.00 18,375.00
JUMLAH TENAGA KERJA 297,500.00
B BAHAN
Semen Portland Kg 400.0000 1,240.00 496,000.00
Pasir beton m3 0.4800 176,500.00 84,720.00
Kerikil (2 Cm/3 Cm) m3 0.8000 174,300.00 139,440.00
Strorox - 100 Kg 1.2000 50,400.00 60,480.00
JUMLAH HARGA BAHAN 780,640.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 1,078,140.00
E Overhead & profit 10% x Jumlah 107,814.00
F Harga Satuan Pekerjaan (D+E) 1,185,954.00

JENIS PEKERJAAN : A.4.1.1.14 Pemasangan 1 m PVC Waterstop lebar 150 mm


SATUAN : M1
HARGA SATUAN PEKERJAAN : Rp 124,261.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0600 105,000.00 6,300.00
Tukang L.02 OH 0.0300 150,000.00 4,500.00
Kepala tukang L.03 OH 0.0030 175,000.00 525.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 11,850.00
B BAHAN
Waterstop lebar 150 mm m 1.0500 96,300.00 101,115.00

JUMLAH HARGA BAHAN 101,115.00


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 112,965.00
E Overhead & profit 10% x Jumlah 11,296.50
F Harga Satuan Pekerjaan (D+E) 124,261.50

JENIS PEKERJAAN : A.4.1.1.15 Pemasangan 1 m PVC Waterstop lebar 200 mm


SATUAN : M1
HARGA SATUAN PEKERJAAN : Rp 161,392.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0700 105,000.00 7,350.00
Tukang L.02 OH 0.0350 150,000.00 5,250.00
Kepala tukang L.03 OH 0.0040 175,000.00 700.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 14,525.00
B BAHAN
Waterstop lebar 200 mm m 1.0500 125,900.00 132,195.00

JUMLAH HARGA BAHAN 132,195.00


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 146,720.00
E Overhead & profit 10% x Jumlah 14,672.00
F Harga Satuan Pekerjaan (D+E) 161,392.00

JENIS PEKERJAAN : A.4.1.1.16 Pemasangan 1 m PVC Waterstop lebar 230 mm - 320 mm


SATUAN : M1
HARGA SATUAN : Rp 173,305.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0800 105,000.00 8,400.00
Tukang L.02 OH 0.0400 150,000.00 6,000.00
Kepala tukang L.03 OH 0.0040 175,000.00 700.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 15,800.00
B BAHAN
Waterstop lebar 230 mm - 320 mm m 1.0500 135,000.00 141,750.00

JUMLAH HARGA BAHAN 141,750.00


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 157,550.00
E Overhead & profit 10% x Jumlah 15,755.00
F Harga Satuan Pekerjaan (D+E) 173,305.00

JENIS PEKERJAAN : A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir
SATUAN : Kg
HARGA SATUAN : Rp 147,268.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0700 105,000.00 7,350.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 19,775.00
B BAHAN
Besi beton Kg 10.5000 10,600.00 111,300.00
Kawat beton Kg 0.1500 18,700.00 2,805.00
JUMLAH HARGA BAHAN 114,105.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 133,880.00
E Overhead & profit 10% x Jumlah 13,388.00
F Harga Satuan Pekerjaan (D+E) 147,268.00
1kg 14,726.80

JENIS PEKERJAAN : A.4.1.1.18 Pemasangan 10 Kg kabel presstressed polos/strands


SATUAN : Kg
HARGA SATUAN : Rp 140,052.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0500 105,000.00 5,250.00
Tukang L.02 OH 0.0500 150,000.00 7,500.00
Kepala tukang L.03 OH 0.0050 175,000.00 875.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 14,150.00
B BAHAN
Besi beton (polos/ulir) Kg 10.5000 10,600.00 111,300.00
Kawat beton Kg 0.1000 18,700.00 1,870.00
JUMLAH HARGA BAHAN 113,170.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 127,320.00
E Overhead & profit 10% x Jumlah 12,732.00
F Harga Satuan Pekerjaan (D+E) 140,052.00

JENIS PEKERJAAN : A.4.1.1.19 Pemasangan 10 Kg jaring kawat baja (wiremesh)


SATUAN : Kg
HARGA SATUAN PEKERJAAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0250 105,000.00 2,625.00
Tukang besi L.02 OH 0.0250 150,000.00 3,750.00
Kepala tukang L.03 OH 0.0250 175,000.00 4,375.00
Mandor L.04 OH 0.0010 175,000.00 175.00
JUMLAH TENAGA KERJA 10,925.00
B BAHAN
Jaring kawat baja di las Kg 10.2000 Err:509 Err:509
Kawat beton Kg 0.0500 18,700.00 935.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.1.1.20 Pemasangan 1 m2 bekisting untuk pondasi


SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 234,264.80
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.5200 105,000.00 54,600.00
Tukang L.02 OH 0.2600 150,000.00 39,000.00
Kepala tukang L.03 OH 0.0260 175,000.00 4,550.00
Mandor L.04 OH 0.0260 175,000.00 4,550.00
JUMLAH TENAGA KERJA 102,700.00
B BAHAN
Kayu kelas III m3 0.0400 2,582,700.00 103,308.00
Paku 5 - 10 Cm Kg 0.3000 18,600.00 5,580.00
Minyak bekisting Liter 0.1000 13,800.00 1,380.00
JUMLAH HARGA BAHAN 110,268.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 212,968.00
E Overhead & profit 10% x Jumlah 21,296.80
F Harga Satuan Pekerjaan (D+E) 234,264.80

JENIS PEKERJAAN : A.4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof


SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 248,469.65

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.5200 105,000.00 54,600.00
Tukang L.02 OH 0.2600 150,000.00 39,000.00
Kepala tukang L.03 OH 0.0260 175,000.00 4,550.00
Mandor L.04 OH 0.0260 175,000.00 4,550.00
JUMLAH TENAGA KERJA 102,700.00
B BAHAN
Kayu kelas III m3 0.0450 2,582,700.00 116,221.50
Paku 5 - 10 Cm Kg 0.3000 18,600.00 5,580.00
Minyak bekisting Liter 0.1000 13,800.00 1,380.00
JUMLAH HARGA BAHAN 123,181.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 225,881.50
E Overhead & profit 10% x Jumlah 22,588.15
F Harga Satuan Pekerjaan (D+E) 248,469.65

JENIS PEKERJAAN : A.4.1.1.22 Pemasangan 1 m2 bekisting untuk kolom


SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 463,852.95

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6600 105,000.00 69,300.00
Tukang L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 175,000.00 5,775.00
Mandor L.04 OH 0.0330 175,000.00 5,775.00
JUMLAH TENAGA KERJA 130,350.00
B BAHAN
Kayu kelas III m3 0.0400 2,582,700.00 103,308.00
Paku 5 - 10 Cm Kg 0.4000 18,600.00 7,440.00
Minyak bekisting Liter 0.2000 13,800.00 2,760.00
Balok kayu kelas II m3 0.0150 3,029,100.00 45,436.50
Plywod tebal 9 mm Lbr 0.3500 183,400.00 64,190.00
Dolken kayu φ 8-10 Cm Batang 2.0000 34,100.00 68,200.00
JUMLAH HARGA BAHAN 291,334.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 421,684.50
E Overhead & profit 10% x Jumlah 42,168.45
F Harga Satuan Pekerjaan (D+E) 463,852.95

JENIS PEKERJAAN : A.4.1.1.23 Pemasangan 1 m2 bekisting untuk balok


SATUAN : M2
HARGA SATUAN : Rp 473,848.98

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6600 105,000.00 69,300.00
Tukang L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 175,000.00 5,775.00
Mandor L.04 OH 0.0330 175,000.00 5,775.00
JUMLAH TENAGA KERJA 130,350.00
B BAHAN
Kayu kelas III m3 0.0400 2,582,700.00 103,308.00
Paku 5 - 10 Cm Kg 0.4000 18,600.00 7,440.00
Minyak bekisting Liter 0.2000 13,800.00 2,760.00
Balok kayu kelas II m3 0.0180 3,029,100.00 54,523.80
Plywod tebal 9 mm Lbr 0.3500 183,400.00 64,190.00
Dolken kayu φ 8-10 Cm Batang 2.0000 34,100.00 68,200.00
JUMLAH HARGA BAHAN 300,421.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 430,771.80
E Overhead & profit 10% x Jumlah 43,077.18
F Harga Satuan Pekerjaan (D+E) 473,848.98

JENIS PEKERJAAN : A.4.1.1.24 Pemasangan 1 m2 bekisting untuk Lantai


SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 388,832.95

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6600 105,000.00 69,300.00
Tukang L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 175,000.00 5,775.00
Mandor L.04 OH 0.0330 175,000.00 5,775.00
JUMLAH TENAGA KERJA 130,350.00
B BAHAN
Kayu kelas III m3 0.0400 2,582,700.00 103,308.00
Paku 5 - 10 Cm Kg 0.4000 18,600.00 7,440.00
Minyak bekisting Liter 0.2000 13,800.00 2,760.00
Balok kayu kelas II m3 0.0150 3,029,100.00 45,436.50
Plywod tebal 9 mm Lbr 0.3500 183,400.00 64,190.00
Dolken kayu φ 8-10 Batang -
JUMLAH HARGA BAHAN 223,134.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 353,484.50
E Overhead & profit 10% x Jumlah 35,348.45
F Harga Satuan Pekerjaan (D+E) 388,832.95

JENIS PEKERJAAN : A.4.1.1.25 Pemasangan 1 m2 bekisting untuk dinding


SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 462,883.30

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6600 105,000.00 69,300.00
Tukang L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 175,000.00 5,775.00
Mandor L.04 OH 0.0330 175,000.00 5,775.00
JUMLAH TENAGA KERJA 130,350.00
B BAHAN
Kayu kelas III m3 0.0300 2,582,700.00 77,481.00
Paku 5 - 10 Cm Kg 0.4000 18,600.00 7,440.00
Minyak bekisting Liter 0.2000 13,800.00 2,760.00
Balok kayu kelas II m3 0.0200 3,029,100.00 60,582.00
Plywod tebal 9 mm Lbr 0.3500 183,400.00 64,190.00
Dolken kayu φ 8-10 Cm Batang 3.0000 - -
Penjaga jarak bekising/Spacer Bh 4.0000 19,500.00 78,000.00
JUMLAH HARGA BAHAN 290,453.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 420,803.00
E Overhead & profit 10% x Jumlah 42,080.30
F Harga Satuan Pekerjaan (D+E) 462,883.30

JENIS PEKERJAAN : A.4.1.1.26 Pemasangan 1 m2 bekisting untuk tangga


SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 359,664.25

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6600 105,000.00 69,300.00
Tukang L.02 OH 0.3300 150,000.00 49,500.00
Kepala tukang L.03 OH 0.0330 175,000.00 5,775.00
Mandor L.04 OH 0.0330 175,000.00 5,775.00
JUMLAH TENAGA KERJA 130,350.00
B BAHAN
Kayu kelas III m3 0.0300 2,582,700.00 77,481.00
Paku 5 - 10 Cm Kg 0.4000 18,600.00 7,440.00
Minyak bekisting Liter 0.1500 13,800.00 2,070.00
Balok kayu kelas II m3 0.0150 3,029,100.00 45,436.50
Plywod tebal 9 mm Lbr 0.3500 183,400.00 64,190.00
Dolken kayu φ 8-10 Cm Batang 2.0000 - -
JUMLAH HARGA BAHAN 196,617.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 326,967.50
E Overhead & profit 10% x Jumlah 32,696.75
F Harga Satuan Pekerjaan (D+E) 359,664.25

JENIS PEKERJAAN : A.4.1.1.27 Pemasangan 1 m2 jembatan untuk pengecoran beton


SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 115,355.11

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.0500 150,000.00 7,500.00
Kepala tukang L.03 OH 0.0050 175,000.00 875.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 25,525.00
B BAHAN
Kayu kelas III (papan) m3 0.0264 2,582,700.00 68,183.28
Paku 5 - 10 Cm Kg 0.6000 18,600.00 11,160.00
Dolken kayu φ 8-10 Cm Batang 0.5000 - -
JUMLAH HARGA BAHAN 79,343.28
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 104,868.28
E Overhead & profit 10% x Jumlah 10,486.83
F Harga Satuan Pekerjaan (D+E) 115,355.11

JENIS PEKERJAAN : A.4.1.1.28 Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting)
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 4,351,164.40

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 5.3000 105,000.00 556,500.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Tukang kayu L.02 OH 1.3000 150,000.00 195,000.00
Tukang besi L.02 OH 1.0500 150,000.00 157,500.00
Kepala tukang L.03 OH 0.2620 175,000.00 45,850.00
Mandor L.04 OH 0.2650 175,000.00 46,375.00
JUMLAH TENAGA KERJA 1,042,475.00
B BAHAN
Kayu kelas III m3 0.2000 2,582,700.00 516,540.00
Paku 5 - 12 Cm Kg 1.5000 18,600.00 27,900.00
Minyak bekisting Liter 0.4000 13,800.00 5,520.00
Besi beton polos Kg 157.5000 10,600.00 1,669,500.00
Kawat beton Kg 2.2500 18,700.00 42,075.00
Semen Portland Kg 336.0000 1,240.00 416,640.00
Pasir beton m3 0.5400 176,500.00 95,310.00
Kerikil m3 0.8100 172,400.00 139,644.00
JUMLAH HARGA BAHAN 2,913,129.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 3,955,604.00
E Overhead & profit 10% x Jumlah 395,560.40
F Harga Satuan Pekerjaan (D+E) 4,351,164.40

JENIS PEKERJAAN : A.4.1.1.29 Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 5,347,158.30

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 5.6500 105,000.00 593,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Tukang kayu L.02 OH 1.5600 150,000.00 234,000.00
Tukang besi L.02 OH 1.4000 150,000.00 210,000.00
Kepala tukang L.03 OH 0.3230 175,000.00 56,525.00
Mandor L.04 OH 0.2830 175,000.00 49,525.00
JUMLAH TENAGA KERJA 1,184,550.00
B BAHAN
Kayu kelas III m3 0.2700 2,582,700.00 697,329.00
Paku 5 - 12 Cm Kg 2.0000 18,600.00 37,200.00
Minyak bekisting Liter 0.6000 13,800.00 8,280.00
Besi beton polos Kg 210.0000 10,600.00 2,226,000.00
Kawat beton Kg 3.0000 18,700.00 56,100.00
Semen Portland Kg 336.0000 1,240.00 416,640.00
Pasir beton m3 0.5400 176,500.00 95,310.00
Kerikil m3 0.8100 172,400.00 139,644.00
JUMLAH HARGA BAHAN 3,676,503.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 4,861,053.00
E Overhead & profit 10% x Jumlah 486,105.30
F Harga Satuan Pekerjaan (D+E) 5,347,158.30

JENIS PEKERJAAN : A.4.1.1.30 Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting)
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 8,411,247.90

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 7.0500 105,000.00 740,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Tukang kayu L.02 OH 1.6500 150,000.00 247,500.00
Tukang besi L.02 OH 2.1000 150,000.00 315,000.00
Kepala tukang L.03 OH 0.4030 175,000.00 70,525.00
Mandor L.04 OH 0.3530 175,000.00 61,775.00
JUMLAH TENAGA KERJA 1,476,300.00
B BAHAN
Kayu kelas III m3 0.4000 2,582,700.00 1,033,080.00
Paku 5 - 12 Cm Kg 4.0000 18,600.00 74,400.00
Minyak bekisting Liter 2.0000 13,800.00 27,600.00
Besi beton polos Kg 315.0000 10,600.00 3,339,000.00
Kawat beton Kg 4.5000 18,700.00 84,150.00
Semen Portland Kg 336.0000 1,240.00 416,640.00
Pasir beton m3 0.5400 176,500.00 95,310.00
Kerikil m3 0.8100 172,400.00 139,644.00
Kayu Kelas II balok m3 0.1500 3,029,100.00 454,365.00
Plywood 9 mm Lbr 3.5000 144,600.00 506,100.00
Dolken kayu φ (8-10) Cm, panj 4 m Batang 20.0000 - -
JUMLAH HARGA BAHAN 6,170,289.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 7,646,589.00
E Overhead & profit 10% x Jumlah 764,658.90
F Harga Satuan Pekerjaan (D+E) 8,411,247.90

JENIS PEKERJAAN : A.4.1.1.31 Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting)
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 6,545,150.70

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 6.3500 105,000.00 666,750.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Tukang kayu L.02 OH 1.6500 150,000.00 247,500.00
Tukang besi L.02 OH 1.4000 150,000.00 210,000.00
Kepala tukang L.03 OH 0.3330 175,000.00 58,275.00
Mandor L.04 OH 0.3180 175,000.00 55,650.00
JUMLAH TENAGA KERJA 1,279,425.00
B BAHAN
Kayu kelas III m3 0.3200 2,582,700.00 826,464.00
Paku 5 - 12 Cm Kg 3.2000 18,600.00 59,520.00
Minyak bekisting Liter 1.6000 13,800.00 22,080.00
Besi beton polos Kg 210.0000 10,600.00 2,226,000.00
Kawat beton Kg 3.0000 18,700.00 56,100.00
Semen Portland Kg 336.0000 1,240.00 416,640.00
Pasir beton m3 0.5400 176,500.00 95,310.00
Kerikil m3 0.8100 172,400.00 139,644.00
Kayu Kelas II balok m3 0.1400 3,029,100.00 424,074.00
Plywood 9 mm Lbr 2.8000 144,600.00 404,880.00
Dolken kayu φ (8-10) Cm, panj 4 m Batang 16.0000 - -
JUMLAH HARGA BAHAN 4,670,712.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 5,950,137.00
E Overhead & profit 10% x Jumlah 595,013.70
F Harga Satuan Pekerjaan (D+E) 6,545,150.70

JENIS PEKERJAAN : A.4.1.1.32 Membuat 1 m3 balok beton bertulang (150 kg besi + bekisting)
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 5,590,865.50

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 5.3000 105,000.00 556,500.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Tukang kayu L.02 OH 1.3000 150,000.00 195,000.00
Tukang besi L.02 OH 1.0500 150,000.00 157,500.00
Kepala tukang L.03 OH 0.2650 175,000.00 46,375.00
Mandor L.04 OH 0.2650 175,000.00 46,375.00
JUMLAH TENAGA KERJA 1,043,000.00
B BAHAN
Kayu kelas III m3 0.3200 2,582,700.00 826,464.00
Paku 5 - 12 Cm Kg 3.2000 18,600.00 59,520.00
Minyak bekisting Liter 1.6000 13,800.00 22,080.00
Besi beton polos Kg 157.5000 10,600.00 1,669,500.00
Kawa beton Kg 2.2500 18,700.00 42,075.00
Semen Portland Kg 336.0000 1,240.00 416,640.00
Pasir beton m3 0.5400 176,500.00 95,310.00
Kerikil m3 0.8100 172,400.00 139,644.00
Kayu Kelas II balok m3 0.1200 3,029,100.00 363,492.00
Plywood 9 mm Lbr 2.8000 144,600.00 404,880.00
Dolken kayu φ (8-10) Cm, panj 4 m Batang 32.0000 - -
JUMLAH HARGA BAHAN 4,039,605.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 5,082,605.00
E Overhead & profit 10% x Jumlah 508,260.50
F Harga Satuan Pekerjaan (D+E) 5,590,865.50

JENIS PEKERJAAN : A.4.1.1.33 Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting)
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 5,496,290.80

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 5.3000 105,000.00 556,500.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Tukang kayu L.02 OH 1.3000 150,000.00 195,000.00
Tukang besi L.02 OH 1.0500 150,000.00 157,500.00
Kepala tukang L.03 OH 0.2620 175,000.00 45,850.00
Mandor L.04 OH 0.2650 175,000.00 46,375.00
JUMLAH TENAGA KERJA 1,042,475.00
B BAHAN
Kayu kelas III m3 0.2400 2,582,700.00 619,848.00
Paku 5 - 12 Cm Kg 3.2000 18,600.00 59,520.00
Minyak bekisting Liter 1.6000 13,800.00 22,080.00
Besi beton polos Kg 157.5000 10,600.00 1,669,500.00
Kawa beton Kg 2.2500 18,700.00 42,075.00
Semen Portland Kg 336.0000 1,240.00 416,640.00
Pasir beton m3 0.5400 176,500.00 95,310.00
Kerikil m3 0.8100 172,400.00 139,644.00
Kayu Kelas II balok m3 0.1600 3,029,100.00 484,656.00
Plywood 9 mm Lbr 2.8000 144,600.00 404,880.00
Dolken kayu φ (8-10) Cm, panj 4 m Batang 24.0000 - -
JUMLAH HARGA BAHAN 3,954,153.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 4,996,628.00
E Overhead & profit 10% x Jumlah 499,662.80
F Harga Satuan Pekerjaan (D+E) 5,496,290.80

JENIS PEKERJAAN : A.4.1.1.34 Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting)
SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 6,067,417.95

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 5.6500 105,000.00 593,250.00
Tukang Batu L.02 OH 0.2750 150,000.00 41,250.00
Tukang kayu L.02 OH 1.5600 150,000.00 234,000.00
Tukang besi L.02 OH 1.4000 150,000.00 210,000.00
Kepala tukang L.03 OH 0.3230 175,000.00 56,525.00
Mandor L.04 OH 0.2830 175,000.00 49,525.00
JUMLAH TENAGA KERJA 1,184,550.00
B BAHAN
Kayu kelas III m3 0.2500 2,582,700.00 645,675.00
Paku 5 - 12 Cm Kg 3.0000 18,600.00 55,800.00
Minyak bekisting Liter 1.2000 13,800.00 16,560.00
Besi beton polos Kg 210.0000 10,600.00 2,226,000.00
Kawa beton Kg 3.0000 18,700.00 56,100.00
Semen Portland Kg 336.0000 1,240.00 416,640.00
Pasir beton m3 0.5400 176,500.00 95,310.00
Kerikil m3 0.8100 172,400.00 139,644.00
Kayu Kelas II balok m3 0.1050 3,029,100.00 318,055.50
Plywood 9 mm Lbr 2.5000 144,600.00 361,500.00
Dolken kayu φ (8-10) Cm, panj 4 m Batang 14.0000 - -
JUMLAH HARGA BAHAN 4,331,284.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 5,515,834.50
E Overhead & profit 10% x Jumlah 551,583.45
F Harga Satuan Pekerjaan (D+E) 6,067,417.95

JENIS PEKERJAAN : A.4.1.1.35 Membuat 1 m kolom praktis beton bertulang (11 x 11) Cm
SATUAN : M'
HARGA SATUAN PEKERJAAN : Rp 109,972.94

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1800 105,000.00 18,900.00
Tukang Batu L.02 OH 0.0200 150,000.00 3,000.00
Tukang kayu L.02 OH 0.0200 150,000.00 3,000.00
Tukang besi L.02 OH 0.0200 150,000.00 3,000.00
Kepala tukang L.03 OH 0.0060 175,000.00 1,050.00
Mandor L.04 OH 0.0090 175,000.00 1,575.00
JUMLAH TENAGA KERJA 30,525.00
B BAHAN
Kayu kelas III m3 0.0020 2,582,700.00 5,165.40
Paku 5 - 12 Cm Kg 0.0100 18,600.00 186.00
Minyak bekisting Liter 1.2000 13,800.00 16,560.00
Besi beton polos Kg 3.0000 10,600.00 31,800.00
Kawat beton Kg 0.4500 18,700.00 8,415.00
Semen Portland Kg 4.0000 1,240.00 4,960.00
Pasir beton m3 0.0060 176,500.00 1,059.00
Kerikil m3 0.0090 145,000.00 1,305.00
JUMLAH HARGA BAHAN 69,450.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 99,975.40
E Overhead & profit 10% x Jumlah 9,997.54
F Harga Satuan Pekerjaan (D+E) 109,972.94

JENIS PEKERJAAN : A.4.1.1.36 Membuat 1 m ring balok beton bertulang (10 x 15) Cm
SATUAN : M'
HARGA SATUAN PEKERJAAN : Rp 134,209.46

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2970 105,000.00 31,185.00
Tukang Batu L.02 OH 0.0330 150,000.00 4,950.00
Tukang kayu L.02 OH 0.0330 150,000.00 4,950.00
Tukang besi L.02 OH 0.0330 150,000.00 4,950.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,410.00
B BAHAN
Kayu kelas III m3 0.0030 2,582,700.00 7,748.10
Paku 5 - 12 Cm Kg 0.0200 18,600.00 372.00
Minyak bekisting Liter 1.0000 13,800.00 13,800.00
Besi beton polos Kg 3.6000 10,600.00 38,160.00
Kawat beton Kg 0.0500 18,700.00 935.00
Semen Portland Kg 5.5000 1,240.00 6,820.00
Pasir beton m3 0.0090 176,500.00 1,588.50
Kerikil m3 0.0150 145,000.00 2,175.00
JUMLAH HARGA BAHAN 71,598.60
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 122,008.60
E Overhead & profit 10% x Jumlah 12,200.86
F Harga Satuan Pekerjaan (D+E) 134,209.46

HARGA SATUAN PEKERJAAN BETON PRACETAK

JENIS PEKERJAAN : A.4.1.2.1 Membuat 1 m2 lahan produksi tebal 8 Cm beton f'c = 14,5 Mpa (K 175), slump (12 ± 2) Cm
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 74,681.68

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1320 105,000.00 13,860.00
Tukang Batu L.02 OH 0.0220 150,000.00 3,300.00
Kepala tukang L.03 OH 0.0020 175,000.00 350.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 18,735.00
B BAHAN
Semen Portland Kg 26.0800 1,240.00 32,339.20
Pasir beton Kg 60.8000 126.07 7,665.14
Kerikil (Maks 30 mm) Kg 82.3200 107.41 8,841.78
Air Liter 17.2000 18.10 311.32
JUMLAH HARGA BAHAN 49,157.44
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 67,892.44
E Overhead & profit 10% x Jumlah 6,789.24
F Harga Satuan Pekerjaan (D+E) 74,681.68

JENIS PEKERJAAN : A.4.1.2.2 Membuat 1 m2 lahan produksi tebal 10 Cm beton f'c = 14,5 Mpa (K 175), slump (12 ± 2) Cm
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 93,386.48

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1650 105,000.00 17,325.00
Tukang Batu L.02 OH 0.0280 150,000.00 4,200.00
Kepala tukang L.03 OH 0.0030 175,000.00 525.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 23,450.00
B BAHAN
Semen Portland Kg 32.6000 1,240.00 40,424.00
Pasir beton Kg 76.0000 126.07 9,581.43
Kerikil (Maks 30 mm) Kg 102.9000 107.41 11,052.22
Air Liter 21.5000 18.10 389.15
JUMLAH HARGA BAHAN 61,446.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 84,896.80
E Overhead & profit 10% x Jumlah 8,489.68
F Harga Satuan Pekerjaan (D+E) 93,386.48

JENIS PEKERJAAN : A.4.1.2.3 Membuat 1 m2 lahan produksi tebal 12 Cm beton f'c = 14,5 Mpa (K 175), slump (12 ± 2) Cm
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 111,926.28

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1980 105,000.00 20,790.00
Tukang Batu L.02 OH 0.0330 150,000.00 4,950.00
Kepala tukang L.03 OH 0.0030 175,000.00 525.00
Mandor L.04 OH 0.0100 175,000.00 1,750.00
JUMLAH TENAGA KERJA 28,015.00
B BAHAN
Semen Portland Kg 39.1200 1,240.00 48,508.80
Pasir beton Kg 91.2000 126.07 11,497.71
Kerikil (Maks 30 mm) Kg 123.4800 107.41 13,262.67
Air Liter 25.8000 18.10 466.98
JUMLAH HARGA BAHAN 73,736.16
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 101,751.16
E Overhead & profit 10% x Jumlah 10,175.12
F Harga Satuan Pekerjaan (D+E) 111,926.28

JENIS PEKERJAAN : A.4.1.2.4 Membuat 1 m2 lahan produksi tebal 15 Cm beton f'c = 14,5 Mpa (K 175), slump (12 ± 2) Cm
SATUAN : M2
HARGA SATUAN PEKERJAAN : Rp 140,068.72

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2480 105,000.00 26,040.00
Tukang Batu L.02 OH 0.0410 150,000.00 6,150.00
Kepala tukang L.03 OH 0.0040 175,000.00 700.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 35,165.00
B BAHAN
Semen Portland Kg 48.9000 1,240.00 60,636.00
Pasir beton Kg 114.0000 126.07 14,372.14
Kerikil (Maks 30 mm) Kg 154.3500 107.41 16,578.33
Air Liter 32.2500 18.10 583.73
JUMLAH HARGA BAHAN 92,170.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 127,335.20
E Overhead & profit 10% x Jumlah 12,733.52
F Harga Satuan Pekerjaan (D+E) 140,068.72

JENIS PEKERJAAN : A.4.1.2.5 Membuat 1 m2 bekisting untuk plat beton pracetak ( 5 kali pakai )
SATUAN : M2
HARGA SATUAN PEKERJAAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0070 105,000.00 735.00
Tukang Batu L.02 OH 0.0760 150,000.00 11,400.00
Kepala tukang L.03 OH 0.0080 175,000.00 1,400.00
Mandor L.04 OH 0.0010 175,000.00 175.00
JUMLAH TENAGA KERJA 13,710.00
B BAHAN
Lantai kerja tebal 10 Cm m3 0.0800 957,798.73 76,623.90
Besi hollow 50.50.3 Kg 9.3940 Err:509 Err:509
Kayu kaso 5/7 m3 0.0050 1,962,100.00 9,810.50
Phenol film 12 mm Lbr 0.0800 215,000.00 17,200.00
Minyak bekisting L 0.2000 13,800.00 2,760.00
Dinabolt dia 12 mm (10-15 Cm) Bh 3.8820 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.1.2.6 Membuat 1 m2 bekisting untuk balok beton pracetak ( 10-12 kali pakai )
SATUAN : M2
HARGA SATUAN PEKERJAAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
A TENAGA
Pekerja L.01 OH 0.0040 105,000.00 420.00
Tukang Batu L.02 OH 0.0380 150,000.00 5,700.00
Kepala tukang L.03 OH 0.0040 175,000.00 700.00
Mandor L.04 OH 0.0010 175,000.00 175.00
JUMLAH TENAGA KERJA 6,995.00
B BAHAN
Kayu kaso 5/7 m3 0.0050 1,962,100.00 9,810.50
Phenol film 12 mm Lbr 0.0430 215,000.00 9,245.00
Minyak bekisting L 0.2000 13,800.00 2,760.00
Paku (5 s.d. 7) cm kg 0.0460 18,600.00 855.60
Dinabolt dia 12 mm (10-15 Cm) Bh 0.6930 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.1.2.7 Membuat 1 m2 bekisting untuk kolom beton pracetak ( 10-12 kali pakai )
SATUAN : M2
HARGA SATUAN PEKERJAAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0040 105,000.00 420.00
Tukang Batu L.02 OH 0.0380 150,000.00 5,700.00
Kepala tukang L.03 OH 0.0040 175,000.00 700.00
Mandor L.04 OH 0.0010 175,000.00 175.00
JUMLAH TENAGA KERJA 6,995.00
B BAHAN
Kayu kaso 5/7 m3 0.0040 1,962,100.00 7,848.40
Phenol film 12 mm Lbr 0.0480 215,000.00 10,320.00
Minyak bekisting L 0.2000 13,800.00 2,760.00
Paku 5-7 Cm Kg 0.0460 18,600.00 855.60
Dinabolt dia 12 mm (10-15 Cm) Bh 0.6930 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.1.2.8 Pemasangan dan membuka bekisting 1 buah komponen plat beton pracetak
SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 10,054.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0530 105,000.00 5,565.00
Tukang kayu L.02 OH 0.0180 150,000.00 2,700.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 9,140.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 9,140.00
E Overhead & profit 10% x Jumlah 914.00
F Harga Satuan Pekerjaan (D+E) 10,054.00

JENIS PEKERJAAN : A.4.1.2.9 Pemasangan dan membuka bekisting 1 buah komponen balok beton pracetak
SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 16,192.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0890 105,000.00 9,345.00
Tukang kayu L.02 OH 0.0300 150,000.00 4,500.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 14,720.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 14,720.00
E Overhead & profit 10% x Jumlah 1,472.00
F Harga Satuan Pekerjaan (D+E) 16,192.00

JENIS PEKERJAAN : A.4.1.2.10 Pemasangan dan membuka bekisting 1 buah komponen kolom beton pracetak
SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 13,123.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0710 105,000.00 7,455.00
Tukang kayu L.02 OH 0.0240 150,000.00 3,600.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 11,930.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 11,930.00
E Overhead & profit 10% x Jumlah 1,193.00
F Harga Satuan Pekerjaan (D+E) 13,123.00

JENIS PEKERJAAN : A.4.1.2.11 Penuangan/menebar beton untuk 1 buah komponen plat pracetak
SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 89,369.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0640 105,000.00 6,720.00
Tukang batu L.02 OH 0.2440 150,000.00 36,600.00
Tukang vibrator L.02 OH 0.1280 150,000.00 19,200.00
Kepala tukang L.03 OH 0.0340 175,000.00 5,950.00
Mandor L.04 OH 0.0730 175,000.00 12,775.00
JUMLAH TENAGA KERJA 81,245.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 81,245.00
E Overhead & profit 10% x Jumlah 8,124.50
F Harga Satuan Pekerjaan (D+E) 89,369.50

JENIS PEKERJAAN : A.4.1.2.12 Penuangan/menebar beton untuk 1 buah komponen balok pracetak
SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 91,844.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0690 105,000.00 7,245.00
Tukang batu L.02 OH 0.2420 150,000.00 36,300.00
Tukang vibrator L.02 OH 0.1380 150,000.00 20,700.00
Kepala tukang L.03 OH 0.0370 175,000.00 6,475.00
Mandor L.04 OH 0.0730 175,000.00 12,775.00
JUMLAH TENAGA KERJA 83,495.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 83,495.00
E Overhead & profit 10% x Jumlah 8,349.50
F Harga Satuan Pekerjaan (D+E) 91,844.50

JENIS PEKERJAAN : A.4.1.2.13 Penuangan/menebar beton untuk 1 buah komponen kolom pracetak
SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 82,725.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0610 105,000.00 6,405.00
Tukang batu L.02 OH 0.2130 150,000.00 31,950.00
Tukang vibrator L.02 OH 0.1220 150,000.00 18,300.00
Kepala tukang L.03 OH 0.0330 175,000.00 5,775.00
Mandor L.04 OH 0.0730 175,000.00 12,775.00
JUMLAH TENAGA KERJA 75,205.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 75,205.00
E Overhead & profit 10% x Jumlah 7,520.50
F Harga Satuan Pekerjaan (D+E) 82,725.50

JENIS PEKERJAAN : A.4.1.2.14 Mendirikan 1 buah komponen plat pracetak


SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 287,838.76

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Operator Crane L.08 OH 0.0670 180,000.00 12,060.00
Pembantu Operator Crane L.09 OH 0.0670 105,000.00 7,035.00
Pekerja L.01 OH 0.0670 105,000.00 7,035.00
Tukang batu L.02 OH 0.0670 150,000.00 10,050.00
Tukang ereksi L.02 OH 0.1340 150,000.00 20,100.00
Kepala tukang L.03 OH 0.0670 175,000.00 11,725.00
Mandor L.04 OH 0.0670 175,000.00 11,725.00
JUMLAH TENAGA KERJA 79,730.00
B BAHAN
Solar L 6.6760 11,600.00 77,441.60

JUMLAH HARGA BAHAN 77,441.60


C PERALATAN
Sewa crane Unit Hari 0.0670 - -
Sewa pipe support Unit Hari 1.1000 95,000.00 104,500.00
JUMLAH HARGA ALAT 104,500.00
D JUMLAH (A+B+C) 261,671.60
E Overhead & profit 10% x Jumlah 26,167.16
F Harga Satuan Pekerjaan (D+E) 287,838.76

JENIS PEKERJAAN : A.4.1.2.15 Mendirikan 1 buah komponen balok pracetak


SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 272,762.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0610 105,000.00 6,405.00
Tukang batu L.02 OH 0.0610 150,000.00 9,150.00
Tukang ereksi L.02 OH 0.1220 150,000.00 18,300.00
Operator crane L.08 OH 0.0610 180,000.00 10,980.00
Pembantu operator crane L.09 OH 0.0610 105,000.00 6,405.00
Kepala tukang L.03 OH 0.0610 175,000.00 10,675.00
Mandor L.04 OH 0.0610 175,000.00 10,675.00
JUMLAH TENAGA KERJA 72,590.00
B BAHAN
Solar L 6.1100 11,600.00 70,876.00

JUMLAH HARGA BAHAN 70,876.00


C PERALATAN
Sewa crane Unit Hari 0.0610 - -
Sewa pipe support Unit Hari 1.1000 95,000.00 104,500.00
JUMLAH HARGA ALAT 104,500.00
D JUMLAH (A+B+C) 247,966.00
E Overhead & profit 10% x Jumlah 24,796.60
F Harga Satuan Pekerjaan (D+E) 272,762.60

JENIS PEKERJAAN : A.4.1.2.16 Mendirikan 1 buah komponen kolom pracetak


SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 444,161.52

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0830 105,000.00 8,715.00
Tukang batu L.02 OH 0.0830 150,000.00 12,450.00
Tukang erection L.02 OH 0.1660 150,000.00 24,900.00
Operator crane L.08 OH 0.0830 180,000.00 14,940.00
Pembantu operator crane L.09 OH 0.0830 105,000.00 8,715.00
Kepala tukang L.03 OH 0.0830 175,000.00 14,525.00
Mandor L.04 OH 0.0830 175,000.00 14,525.00
JUMLAH TENAGA KERJA 98,770.00
B BAHAN
Solar L 8.2770 11,600.00 96,013.20

JUMLAH HARGA BAHAN 96,013.20


C PERALATAN
Sewa crane Unit Hari 0.0830 - -
Sewa pipe support Unit Hari 2.2000 95,000.00 209,000.00
JUMLAH HARGA ALAT 209,000.00
D JUMLAH (A+B+C) 403,783.20
E Overhead & profit 10% x Jumlah 40,378.32
F Harga Satuan Pekerjaan (D+E) 444,161.52

JENIS PEKERJAAN : A.4.1.2.17 Melangsir 1 buah komponen plat pracetak (± 20 m)


SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 38,626.72

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0190 105,000.00 1,995.00
Tukang batu L.02 OH 0.0380 150,000.00 5,700.00
Operator crane L.08 OH 0.0190 180,000.00 3,420.00
Pembantu operator crane L.09 OH 0.0190 105,000.00 1,995.00
JUMLAH TENAGA KERJA 13,110.00
B BAHAN
Solar L 1.8970 11,600.00 22,005.20

JUMLAH HARGA BAHAN 22,005.20


C PERALATAN
Sewa crane UH 0.0190 - -
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 35,115.20
E Overhead & profit 10% x Jumlah 3,511.52
F Harga Satuan Pekerjaan (D+E) 38,626.72

JENIS PEKERJAAN : A.4.1.2.18 Melangsir 1 buah komponen balok pracetak (± 20 m)


SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 38,626.72

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0190 105,000.00 1,995.00
Tukang batu L.02 OH 0.0380 150,000.00 5,700.00
Operator crane L.08 OH 0.0190 180,000.00 3,420.00
Pembantu operator crane L.09 OH 0.0190 105,000.00 1,995.00
JUMLAH TENAGA KERJA 13,110.00
B BAHAN
Solar L 1.8970 11,600.00 22,005.20

JUMLAH HARGA BAHAN 22,005.20


C PERALATAN
Sewa crane UH 0.0190 - -
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 35,115.20
E Overhead & profit 10% x Jumlah 3,511.52
F Harga Satuan Pekerjaan (D+E) 38,626.72

JENIS PEKERJAAN : A.4.1.2.19 Melangsir 1 buah komponen kolom pracetak (± 20 m)


SATUAN : Bh
HARGA SATUAN PEKERJAAN : Rp 38,626.72

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0190 105,000.00 1,995.00
Tukang batu L.02 OH 0.0380 150,000.00 5,700.00
Operator crane L.08 OH 0.0190 180,000.00 3,420.00
Pembantu operator crane L.09 OH 0.0190 105,000.00 1,995.00
JUMLAH TENAGA KERJA 13,110.00
B BAHAN
Solar L 1.8970 11,600.00 22,005.20

JUMLAH HARGA BAHAN 22,005.20


C PERALATAN
Sewa crane UH 0.0190 - -
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 35,115.20
E Overhead & profit 10% x Jumlah 3,511.52
F Harga Satuan Pekerjaan (D+E) 38,626.72

JENIS PEKERJAAN : A.4.1.2.20 Bahan 1 m3 grouting campuran


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 1,778,029.61

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA

JUMLAH TENAGA KERJA -


B BAHAN
Semen grount Kg 1200.0000 1,240.00 1,488,000.00
Screening Kg 650.0000 187.78 122,055.56
Air L 350.0000 18.10 6,335.00
JUMLAH HARGA BAHAN 1,616,390.56
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 1,616,390.56
E Overhead & profit 10% x Jumlah 161,639.06
F Harga Satuan Pekerjaan (D+E) 1,778,029.61

JENIS PEKERJAAN : A.4.1.2.21 Bahan 1 m3 grouting (tidak campuran)


SATUAN : M3
HARGA SATUAN PEKERJAAN : Rp 2,531,364.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
JUMLAH TENAGA KERJA -
B BAHAN
Semen grount Kg 1850.0000 1,240.00 2,294,000.00
Air L 400.0000 18.10 7,240.00
JUMLAH HARGA BAHAN 2,301,240.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 2,301,240.00
E Overhead & profit 10% x Jumlah 230,124.00
F Harga Satuan Pekerjaan (D+E) 2,531,364.00

JENIS PEKERJAAN : A.4.1.2.22 Upah melakukan 1 titik grouting pada join pracetak
SATUAN : Titik
HARGA SATUAN PEKERJAAN : Rp 81,922.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Tukang batu L.02 OH 0.3670 150,000.00 55,050.00
Kepala tukang L.03 OH 0.0740 175,000.00 12,950.00
Mandor L.04 OH 0.0370 175,000.00 6,475.00
JUMLAH TENAGA KERJA 74,475.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 74,475.00
E Overhead & profit 10% x Jumlah 7,447.50
F Harga Satuan Pekerjaan (D+E) 81,922.50

JENIS PEKERJAAN : A.4.1.2.23 Pemasangan 1 titik bekisting join pracetak


SATUAN : titik
HARGA SATUAN PEKERJAAN : Rp 94,142.62

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1470 105,000.00 15,435.00
Tukang kayu L.02 OH 0.1470 150,000.00 22,050.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 40,985.00
B BAHAN
Kayu kaso 5/7 m3 0.0120 2,446,500.00 29,358.00
Papan cor m3 0.0040 2,582,700.00 10,330.80
Paku 5-7 Cm Kg 0.2640 18,600.00 4,910.40
JUMLAH HARGA BAHAN 44,599.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 85,584.20
E Overhead & profit 10% x Jumlah 8,558.42
F Harga Satuan Pekerjaan (D+E) 94,142.62

JENIS PEKERJAAN : A.4.1.2.24 Upah 1 titik join dengan Sling


SATUAN : Titik
HARGA SATUAN PEKERJAAN : Rp 67,457.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2200 105,000.00 23,100.00
Tukang besi L.02 OH 0.2200 150,000.00 33,000.00
Tukang kayu L.02 OH 0.0220 150,000.00 3,300.00
Mandor L.04 OH 0.0110 175,000.00 1,925.00
JUMLAH TENAGA KERJA 61,325.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 61,325.00
E Overhead & profit 10% x Jumlah 6,132.50
F Harga Satuan Pekerjaan (D+E) 67,457.50

HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM

JENIS PEKERJAAN : A.4.2.1.1 Pemasangan 1 kg besi profil


SATUAN : Kg
HARGA SATUAN PEKERJAAN : Rp 48,922.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0600 105,000.00 6,300.00
Tukang Las konstruksi L.02 OH 0.0600 150,000.00 9,000.00
Kepala tukang L.03 OH 0.0060 175,000.00 1,050.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 16,875.00
B BAHAN
Besi profil Kg 1.1500 24,000.00 27,600.00

JUMLAH HARGA BAHAN 27,600.00


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 44,475.00
E Overhead & profit 10% x Jumlah 4,447.50
F Harga Satuan Pekerjaan (D+E) 48,922.50

JENIS PEKERJAAN : A.4.2.1.2 Pemasangan 1 kg rangka kuda-kuda baja IWF


SATUAN : Kg
HARGA SATUAN PEKERJAAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0600 105,000.00 6,300.00
Tukang Las konstruksi L.02 OH 0.0600 150,000.00 9,000.00
Kepala tukang L.03 OH 0.0060 175,000.00 1,050.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 16,875.00
B BAHAN
Besi baja IWF Kg 1.1500 Err:509 Err:509

JUMLAH HARGA BAHAN Err:509


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.3 Pengerjaan 100 kg pekerjaan perakitan


SATUAN : Kg
HARGA SATUAN PEKERJAAN : Rp 61,936.29

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang besi konstruksi L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0010 175,000.00 175.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 26,550.00
B BAHAN
Solar L 1.0000 11,600.00 11,600.00
Minyak pelumas L 0.1000 38,700.00 3,870.00
JUMLAH HARGA BAHAN 15,470.00
C PERALATAN
Sewa alat Jam 0.8000 17,857.14 14,285.71
JUMLAH HARGA ALAT 14,285.71
D JUMLAH (A+B+C) 56,305.71
E Overhead & profit 10% x Jumlah 5,630.57
F Harga Satuan Pekerjaan (D+E) 61,936.29

JENIS PEKERJAAN : A.4.2.1.4 Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
SATUAN : M2
HARGA SATUAN PEKERJAAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
A TENAGA
Pekerja L.01 OH 1.0500 105,000.00 110,250.00
Tukang Las L.02 OH 1.0500 150,000.00 157,500.00
Kepala tukang L.03 OH 0.1050 175,000.00 18,375.00
Mandor L.04 OH 0.0520 175,000.00 9,100.00
JUMLAH TENAGA KERJA 295,225.00
B BAHAN
Besi siku L 30.30.3 Kg 15.0000 Err:509 Err:509
Besi plat baja Kg 32.8000 a #VALUE!
Kawat las Kg 0.0500 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.5 Pengerjaan 10 cm pengelasan dengan las listrik


SATUAN : Cm
HARGA SATUAN PEKERJAAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0400 105,000.00 4,200.00
Tukang besi L.02 OH 0.0200 150,000.00 3,000.00
Kepala tukang L.03 OH 0.0020 175,000.00 350.00
Mandor L.04 OH 0.0020 175,000.00 350.00
JUMLAH TENAGA KERJA 7,900.00
B BAHAN
Kawat las listrik Kg 0.4000 Err:509 Err:509
Solar L 0.3000 11,600.00 3,480.00
Minyak pelumas L 0.0400 38,700.00 1,548.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN
Sewa alat Jam 0.1700 17,857.14 3,035.71
JUMLAH HARGA ALAT 3,035.71
D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.6 Pembuatan 1 m2 rangka jendela besi scuare tube


SATUAN : M2
HARGA SATUAN PEKERJAAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6500 105,000.00 68,250.00
Tukang las L.02 OH 0.6500 150,000.00 97,500.00
Kepala tukang L.03 OH 0.0650 175,000.00 11,375.00
Mandor L.04 OH 0.0320 175,000.00 5,600.00
JUMLAH TENAGA KERJA 182,725.00
B BAHAN
Besi scuare tube m 4.7600 a #VALUE!
Besi lis kaca (1 x 1) Cm m 4.5220 a #VALUE!
Pengelasan Cm 20.0000 Err:509 Err:509
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.2.1.7 Pemasangan 1 m2 pintu rolling door besi


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.2000 105,000.00 126,000.00
Tukang las L.02 OH 1.2000 150,000.00 180,000.00
Kepala tukang L.03 OH 0.1200 175,000.00 21,000.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 328,050.00
B BAHAN
Pintu gulung besi m2 1.0000 Err:509 Err:509

JUMLAH HARGA BAHAN Err:509


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.8 Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVC
SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4400 105,000.00 46,200.00
Tukang L.02 OH 0.4400 150,000.00 66,000.00
Kepala tukang L.03 OH 0.0440 175,000.00 7,700.00
Mandor L.04 OH 0.0220 175,000.00 3,850.00
JUMLAH TENAGA KERJA 123,750.00
B BAHAN
Pintu lipat m2 1.0000 Err:509 Err:509

JUMLAH HARGA BAHAN Err:509


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.9 Pemasangan 1 m2 sunscreen alluminium


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0800 105,000.00 8,400.00
Tukang L.02 OH 0.8000 150,000.00 120,000.00
Kepala tukang L.03 OH 0.0800 175,000.00 14,000.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 143,100.00
B BAHAN
Sunscreen alluminium m2 1.0000 Err:509 Err:509

JUMLAH HARGA BAHAN Err:509


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.10 Pemasangan 1 m2 Folding Gate 0.4mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang L.02 OH 1.0000 150,000.00 150,000.00
Kepala tukang L.03 OH 0.1000 175,000.00 17,500.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 281,250.00
B BAHAN
Folding Gate 0.4mm m2 1.0000 Err:509 Err:509

JUMLAH HARGA BAHAN Err:509


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509
JENIS PEKERJAAN : A.4.2.1.11 Pemasangan 1 m1 kusen pintu alluminium
SATUAN : M1
HARGA SATUAN : Rp 165,203.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0430 105,000.00 4,515.00
Tukang L.02 OH 0.0430 150,000.00 6,450.00
Kepala tukang L.03 OH 0.0043 175,000.00 752.50
Mandor L.04 OH 0.0021 175,000.00 367.50
JUMLAH TENAGA KERJA 12,085.00
B BAHAN
Profil alluminium m 1.1000 110,000.00 121,000.00
Skrup fixer bh 2.0000 7,500.00 15,000.00
Sealant Tube 0.0600 35,000.00 2,100.00
JUMLAH HARGA BAHAN 138,100.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 150,185.00
E Overhead & profit 10% x Jumlah 15,018.50
F Harga Satuan Pekerjaan (D+E) 165,203.50

JENIS PEKERJAAN : A.4.2.1.12 Pemasangan 1 m2 pintu alluminium


SATUAN : M2
HARGA SATUAN : Rp 558,687.25

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.0850 105,000.00 8,925.00
Tukang L.02 OH 0.0850 150,000.00 12,750.00
Kepala tukang L.03 OH 0.0085 175,000.00 1,487.50
Mandor L.04 OH 0.0042 175,000.00 735.00
JUMLAH TENAGA KERJA 23,897.50
B BAHAN
Profil alluminium m 4.4000 110,000.00 484,000.00

JUMLAH HARGA BAHAN 484,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 507,897.50
E Overhead & profit 10% x Jumlah 50,789.75
F Harga Satuan Pekerjaan (D+E) 558,687.25
JENIS PEKERJAAN : A.4.2.1.13 Pemasangan 1 m2 pintu kaca rangka alluminium
SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.0850 105,000.00 8,925.00
Tukang L.02 OH 0.0850 150,000.00 12,750.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 24,125.00
B BAHAN
Pintu alluminium m 4.4000 Err:509 Err:509
Profil kaca m 4.5000 Err:509 Err:509
Sealant Tube 0.0600 35,000.00 2,100.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.14 Pemasangan 1 m2 venetions blinds dan vertical blinds


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.3500 105,000.00 36,750.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 98,525.00
B BAHAN
Venetions blinds dan vertical m2 1.0000 a #VALUE!
blinds (tirai)
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.2.1.15 Pemasangan 1 m2 teralis besi strip (2 x 3) mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6700 105,000.00 175,350.00
Tukang las L.02 OH 1.6700 150,000.00 250,500.00
Kepala tukang L.03 OH 0.1670 175,000.00 29,225.00
Mandor L.04 OH 0.0830 175,000.00 14,525.00
JUMLAH TENAGA KERJA 469,600.00
B BAHAN
Besi strip kg 6.1770 Err:509 Err:509
Pengelasan Cm 27.0800 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.16 Pemasangan 1 m2 kawat nyamuk


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang las L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 28,125.00
B BAHAN
Kawat nyamuk m2 1.1000 Err:509 Err:509
Pengelasan Cm 11.1100 Err:509 Err:509
Baja strip (0,2 x 2) Cm kg 1.7160 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.17 Pemasangan 1 m2 jendela nako & tralis


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0010 175,000.00 175.00
JUMLAH TENAGA KERJA 54,675.00
B BAHAN
Jendela nako (rangka + kaca 5 mm) m2 1.1000 243,000.00 267,300.00
Paku skrup 1 Cm - 2,5 Cm buah 10.0000 Err:509 Err:509
Baja strip kg 7.0000 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.18 Pemasangan 1 M1 talang datar/ jurai seng bjls 28 lebar 90 Cm
SATUAN : M1
HARGA SATUAN : Rp 114,120.93

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0010 175,000.00 175.00
JUMLAH TENAGA KERJA 54,675.00
B BAHAN
Seng plat m 1.0500 Err:509 Err:509
Paku 1 Cm - 2,5 Cm kg 0.0150 18,600.00 279.00
Papan kayu kelas II atau III m3 0.0190 2,582,700.00 49,071.30
JUMLAH HARGA BAHAN 49,071.30
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 103,746.30
E Overhead & profit 10% x Jumlah 10,374.63
F Harga Satuan Pekerjaan (D+E) 114,120.93

JENIS PEKERJAAN : A.4.2.1.19 Pemasangan 1 m talang 1/2 lingkaran D-15 Cm, seng plat bjls 30 lebar 45 Cm
SATUAN : M1
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.3000 150,000.00 45,000.00
Kepala tukang L.03 OH 0.0300 175,000.00 5,250.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 67,400.00
B BAHAN
Seng plat m2 1.0500 Err:509 Err:509
Paku 1 Cm - 2,5 Cm kg 0.0100 18,600.00 186.00
Besi strip kg 0.5000 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.20 Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul 60 x 120 Cm untuk partisi
SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang besi L.02 OH 0.2500 150,000.00 37,500.00
Kepala tukang L.03 OH 0.0250 175,000.00 4,375.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 70,400.00
B BAHAN
Rangka metal hollow 40.40.2 mm m1 3.5000 Err:509 Err:509
Assesoris (perkuatan, las dll) Ls 1.0000 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul 60 x 60 Cm, untuk plafon
SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3500 105,000.00 36,750.00
Tukang besi L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 98,525.00
B BAHAN
Rangka metal hollow 40.40.2 mm m1 4.0000 Err:509 Err:509
Assesoris (perkuatan, las dll) Ls 1.0000 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

HARGA SATUAN PEKERJAAN PASANGAN DINDING

JENIS PEKERJAAN : A.4.4.1.1 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1 batu Camp, 1PC : 2 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 294,599.80

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6000 105,000.00 63,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0300 175,000.00 5,250.00
JUMLAH TENAGA KERJA 101,750.00
B BAHAN
Bata Merah Bh 140.0000 700.00 98,000.00
Semen Portland Kg 43.5000 1,240.00 53,940.00
Pasir Pasang m3 0.0800 176,600.00 14,128.00
JUMLAH HARGA BAHAN 166,068.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 267,818.00
E Overhead & profit 10% x Jumlah 26,781.80
F Harga Satuan Pekerjaan (D+E) 294,599.80

JENIS PEKERJAAN : A.4.4.1.2 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1 batu Camp, 1PC : 3 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 282,346.46

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6000 105,000.00 63,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0300 175,000.00 5,250.00
JUMLAH TENAGA KERJA 101,750.00
B BAHAN
Bata Merah m3 140.0000 700.00 98,000.00
Semen Portland Kg 32.9500 1,240.00 40,858.00
Pasir Pasang m3 0.0910 176,600.00 16,070.60
JUMLAH HARGA BAHAN 154,928.60
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 256,678.60
E Overhead & profit 10% x Jumlah 25,667.86
F Harga Satuan Pekerjaan (D+E) 282,346.46

JENIS PEKERJAAN : A.4.4.1.3 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1 batu Camp, 1PC : 4 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 274,005.38

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6000 105,000.00 63,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0300 175,000.00 5,250.00
JUMLAH TENAGA KERJA 101,750.00
B BAHAN
Bata Merah m3 140.0000 700.00 98,000.00
Semen Portland Kg 26.5500 1,240.00 32,922.00
Pasir Pasang m3 0.0930 176,600.00 16,423.80
JUMLAH HARGA BAHAN 147,345.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 249,095.80
E Overhead & profit 10% x Jumlah 24,909.58
F Harga Satuan Pekerjaan (D+E) 274,005.38

JENIS PEKERJAAN : A.4.4.1.4 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1 batu Camp, 1PC : 5 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 269,820.32

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6000 105,000.00 63,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0300 175,000.00 5,250.00
JUMLAH TENAGA KERJA 101,750.00
B BAHAN
Bata Merah m3 140.0000 700.00 98,000.00
Semen Portland Kg 22.2000 1,240.00 27,528.00
Pasir Pasang m3 0.1020 176,600.00 18,013.20
JUMLAH HARGA BAHAN 143,541.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 245,291.20
E Overhead & profit 10% x Jumlah 24,529.12
F Harga Satuan Pekerjaan (D+E) 269,820.32

JENIS PEKERJAAN : A.4.4.1.5 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1 batu Camp, 1PC : 6 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 268,658.72

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6000 105,000.00 63,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0300 175,000.00 5,250.00
JUMLAH TENAGA KERJA 101,750.00
B BAHAN
Bata Merah m3 140.0000 700.00 98,000.00
Semen Portland Kg 18.5000 1,240.00 22,940.00
Pasir Pasang m3 0.1220 176,600.00 21,545.20
JUMLAH HARGA BAHAN 142,485.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 244,235.20
E Overhead & profit 10% x Jumlah 24,423.52
F Harga Satuan Pekerjaan (D+E) 268,658.72

JENIS PEKERJAAN : A.4.4.1.6 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1 batu Camp, 1PC : 3Kapur Padam : 10 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 277,458.17

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.6000 105,000.00 63,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0300 175,000.00 5,250.00
JUMLAH TENAGA KERJA 101,750.00
B BAHAN
Bata Merah buah 140.0000 700.00 98,000.00
Semen Portland Kg 10.0800 1,240.00 12,499.20
kapur M3 0.0275 860,000.00 23,650.00
Pasir Pasang m3 0.0925 176,600.00 16,335.50
JUMLAH HARGA BAHAN 150,484.70
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 252,234.70
E Overhead & profit 10% x Jumlah 25,223.47
F Harga Satuan Pekerjaan (D+E) 277,458.17

JENIS PEKERJAAN : A.4.4.1.7 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1PC : 2 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 143,092.18

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Bata Merah m3 70.0000 700.00 49,000.00
Semen Portland Kg 18.9500 1,240.00 23,498.00
Pasir Pasang m3 0.0380 176,600.00 6,710.80
JUMLAH HARGA BAHAN 79,208.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 130,083.80
E Overhead & profit 10% x Jumlah 13,008.38
F Harga Satuan Pekerjaan (D+E) 143,092.18

JENIS PEKERJAAN : A.4.4.1.8 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1PC : 3 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 137,233.58

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Bata Merah m3 70.0000 700.00 49,000.00
Semen Portland Kg 14.3700 1,240.00 17,818.80
Pasir Pasang m3 0.0400 176,600.00 7,064.00
JUMLAH HARGA BAHAN 73,882.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 124,757.80
E Overhead & profit 10% x Jumlah 12,475.78
F Harga Satuan Pekerjaan (D+E) 137,233.58

JENIS PEKERJAAN : A.4.4.1.9 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1PC : 4 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 133,901.68

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Bata Merah m3 70.0000 700.00 49,000.00
Semen Portland Kg 11.5000 1,240.00 14,260.00
Pasir Pasang m3 0.0430 176,600.00 7,593.80
JUMLAH HARGA BAHAN 70,853.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 121,728.80
E Overhead & profit 10% x Jumlah 12,172.88
F Harga Satuan Pekerjaan (D+E) 133,901.68

JENIS PEKERJAAN : A.4.4.1.10 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1PC : 5 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 131,807.72

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Bata Merah m3 70.0000 700.00 49,000.00
Semen Portland Kg 9.6800 1,240.00 12,003.20
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN 68,950.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 119,825.20
E Overhead & profit 10% x Jumlah 11,982.52
F Harga Satuan Pekerjaan (D+E) 131,807.72

JENIS PEKERJAAN : A.4.4.1.11 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1PC : 6 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 130,729.72

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Bata Merah m3 70.0000 700.00 49,000.00
Semen Portland Kg 8.3200 1,240.00 10,316.80
Pasir Pasang m3 0.0490 176,600.00 8,653.40
JUMLAH HARGA BAHAN 67,970.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 118,845.20
E Overhead & profit 10% x Jumlah 11,884.52
F Harga Satuan Pekerjaan (D+E) 130,729.72

JENIS PEKERJAAN : A.4.4.1.12 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1PC : 8 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 128,441.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Bata Merah m3 70.0000 700.00 49,000.00
Semen Portland Kg 6.5000 1,240.00 8,060.00
Pasir Pasang m3 0.0500 176,600.00 8,830.00
JUMLAH HARGA BAHAN 65,890.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 116,765.00
E Overhead & profit 10% x Jumlah 11,676.50
F Harga Satuan Pekerjaan (D+E) 128,441.50

JENIS PEKERJAAN : A.4.4.1.13 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1PC : 3Kapur Padam : 10 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 139,903.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Bata Merah m3 70.0000 700.00 49,000.00
Semen Portland Kg 4.5000 1,240.00 5,580.00
kapur m3 0.0150 860,000.00 12,900.00
Pasir Pasang m3 0.0500 176,600.00 8,830.00
JUMLAH HARGA BAHAN 76,310.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 127,185.00
E Overhead & profit 10% x Jumlah 12,718.50
F Harga Satuan Pekerjaan (D+E) 139,903.50

JENIS PEKERJAAN : A.4.4.1.14 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1 SP : 1 KP : 1 PP
SATUAN : M2
HARGA SATUAN : Rp 130,411.73

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Bata Merah m3 70.0000 700.00 49,000.00
Semen Portland Kg 0.0180 1,240.00 22.32
kapur m3 0.0180 860,000.00 15,480.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
JUMLAH HARGA BAHAN 67,681.12
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 118,556.12
E Overhead & profit 10% x Jumlah 11,855.61
F Harga Satuan Pekerjaan (D+E) 130,411.73

JENIS PEKERJAAN : A.4.4.1.15 Pemasangan 1 m2 dinding Bata Merah (5x11x22) Cm tebal 1/2 batu Camp, 1 SP: 1KP : 2 PP
SATUAN : M2
HARGA SATUAN : Rp 128,564.88

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Bata Merah m3 70.0000 700.00 49,000.00
Semen Portland Kg 0.0140 1,240.00 17.36
kapur m3 0.0140 860,000.00 12,040.00
Pasir Pasang m3 0.0280 176,600.00 4,944.80
JUMLAH HARGA BAHAN 66,002.16
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 116,877.16
E Overhead & profit 10% x Jumlah 11,687.72
F Harga Satuan Pekerjaan (D+E) 128,564.88

JENIS PEKERJAAN : A.4.4.1.16 Pemasangan 1 m2 dinding conblock Hollow Brick (H.20) Camp, 1PC : 3 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 326,320.06

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3500 105,000.00 36,750.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 65,025.00
B BAHAN
Hollow Brick (H.20) m3 12.5000 5,000.00 62,500.00
Semen Portland Kg 30.3200 1,240.00 37,596.80
Pasir Pasang m3 0.7280 176,600.00 128,564.80
Besi angker diameter 8 Kg 0.2800 10,600.00 2,968.00
JUMLAH HARGA BAHAN 231,629.60
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 296,654.60
E Overhead & profit 10% x Jumlah 29,665.46
F Harga Satuan Pekerjaan (D+E) 326,320.06

JENIS PEKERJAAN : A.4.4.1.17 Pemasangan 1 m2 dinding conblock Hollow Brick (H.20) Camp, 1PC : 4 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 326,601.66

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3500 105,000.00 36,750.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 65,025.00
B BAHAN
Hollow Brick (H.20) m3 12.5000 5,000.00 62,500.00
Semen Portland Kg 24.2600 1,240.00 30,082.40
Pasir Pasang m3 0.7720 176,600.00 136,335.20
Besi angker diameter 8 Kg 0.2800 10,600.00 2,968.00
JUMLAH HARGA BAHAN 231,885.60
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 296,910.60
E Overhead & profit 10% x Jumlah 29,691.06
F Harga Satuan Pekerjaan (D+E) 326,601.66

JENIS PEKERJAAN : A.4.4.1.18 Pemasangan 1 m2 dinding conblock Hollow Brick (H.15) Camp, 1PC : 3 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 252,775.16

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3200 105,000.00 33,600.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0160 175,000.00 2,800.00
JUMLAH TENAGA KERJA 56,500.00
B BAHAN
Hollow Brick (H.15) m3 12.5000 3,600.00 45,000.00
Semen Portland Kg 22.7400 1,240.00 28,197.60
Pasir Pasang m3 0.5500 176,600.00 97,130.00
Besi angker diameter 8 Kg 0.2800 10,600.00 2,968.00
JUMLAH HARGA BAHAN 173,295.60
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 229,795.60
E Overhead & profit 10% x Jumlah 22,979.56
F Harga Satuan Pekerjaan (D+E) 252,775.16

JENIS PEKERJAAN : A.4.4.1.19 Pemasangan 1 m2 dinding conblock Hollow Brick (H.15) Camp, 1PC : 4 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 252,798.92

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3200 105,000.00 33,600.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0160 175,000.00 2,800.00
JUMLAH TENAGA KERJA 56,500.00
B BAHAN
Hollow Brick (H.15) m3 12.5000 3,600.00 45,000.00
Semen Portland Kg 18.2000 1,240.00 22,568.00
Pasir Pasang m3 0.5820 176,600.00 102,781.20
Besi angker diameter 8 Kg 0.2800 10,600.00 2,968.00
JUMLAH HARGA BAHAN 173,317.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 229,817.20
E Overhead & profit 10% x Jumlah 22,981.72
F Harga Satuan Pekerjaan (D+E) 252,798.92

JENIS PEKERJAAN : A.4.4.1.20 Pemasangan 1 m2 dinding conblock Hollow Brick (H.10) Camp, 1PC : 3 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 195,991.18

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Hollow Brick (H.10) m3 12.5000 3,300.00 41,250.00
Semen Portland Kg 15.1600 1,240.00 18,798.40
Pasir Pasang m3 0.3640 176,600.00 64,282.40
Besi angker diameter 8 Kg 0.2800 10,600.00 2,968.00
JUMLAH HARGA BAHAN 127,298.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 178,173.80
E Overhead & profit 10% x Jumlah 17,817.38
F Harga Satuan Pekerjaan (D+E) 195,991.18
JENIS PEKERJAAN : A.4.4.1.21 Pemasangan 1 m2 dinding conblock Hollow Brick (H.10) Camp, 1PC : 4 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 196,520.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Hollow Brick (H.10) m3 12.5000 3,300.00 41,250.00
Semen Portland Kg 12.1300 1,240.00 15,041.20
Pasir Pasang m3 0.3880 176,600.00 68,520.80
Besi angker diameter 8 Kg 0.2800 10,600.00 2,968.00
JUMLAH HARGA BAHAN 127,780.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 178,655.00
E Overhead & profit 10% x Jumlah 17,865.50
F Harga Satuan Pekerjaan (D+E) 196,520.50

JENIS PEKERJAAN : A.4.4.1.22 Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 Camp, 1PC : 3 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 417,665.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Rooster 20x20 m3 30.0000 10,300.00 309,000.00
Semen Portland Kg 11.0000 1,240.00 13,640.00
Pasir Pasang m3 0.0350 176,600.00 6,181.00
JUMLAH HARGA BAHAN 328,821.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 379,696.00
E Overhead & profit 10% x Jumlah 37,969.60
F Harga Satuan Pekerjaan (D+E) 417,665.60

JENIS PEKERJAAN : A.4.4.1.23 Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 Camp, 1PC : 4 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 417,665.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Bata Berongga m3 30.0000 10,300.00 309,000.00
Semen Portland Kg 11.0000 1,240.00 13,640.00
Pasir Pasang m3 0.0350 176,600.00 6,181.00
JUMLAH HARGA BAHAN 328,821.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 379,696.00
E Overhead & profit 10% x Jumlah 37,969.60
F Harga Satuan Pekerjaan (D+E) 417,665.60

JENIS PEKERJAAN : A.4.4.1.24 Pemasangan 1 m2 dinding bata berongga 12x11x24 Camp, 1PC : 3 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 883,587.32

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Bata Rooster m3 70.0000 10,300.00 721,000.00
Semen Portland Kg 14.0000 1,240.00 17,360.00
Pasir Pasang m3 0.0320 176,600.00 5,651.20
JUMLAH HARGA BAHAN 744,011.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 803,261.20
E Overhead & profit 10% x Jumlah 80,326.12
F Harga Satuan Pekerjaan (D+E) 883,587.32

HARGA SATUAN PEKERJAAN Plesteran

JENIS PEKERJAAN : A.4.4.2.1 Pemasangan 1 m2 Plesteran 1PC : 1 Pasir Pasang tebal 15 mm


SATUAN : M2
HARGA SATUAN : Rp 89,430.62

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Semen Portland Kg 15.5040 1,240.00 19,224.96
Pasir Pasang m3 0.0160 176,600.00 2,825.60
JUMLAH HARGA BAHAN 22,050.56
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 81,300.56
E Overhead & profit 10% x Jumlah 8,130.06
F Harga Satuan Pekerjaan (D+E) 89,430.62

JENIS PEKERJAAN : A.4.4.2.2 Pemasangan 1 m2 Plesteran 1PC : 2 Pasir Pasang tebal 15 mm


SATUAN : M2
HARGA SATUAN : Rp 83,005.74

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Semen Portland Kg 10.2240 1,240.00 12,677.76
Pasir Pasang m3 0.0200 176,600.00 3,532.00
JUMLAH HARGA BAHAN 16,209.76
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 75,459.76
E Overhead & profit 10% x Jumlah 7,545.98
F Harga Satuan Pekerjaan (D+E) 83,005.74

JENIS PEKERJAAN : A.4.4.2.3 Pemasangan 1 m2 Plesteran 1PC : 2 Pasir Pasang tebal 15 mm


SATUAN : M2
HARGA SATUAN : Rp 83,005.74

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Semen Portland Kg 10.2240 1,240.00 12,677.76
Pasir Pasang m3 0.0200 176,600.00 3,532.00
JUMLAH HARGA BAHAN 16,209.76
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 75,459.76
E Overhead & profit 10% x Jumlah 7,545.98
F Harga Satuan Pekerjaan (D+E) 83,005.74

JENIS PEKERJAAN : A.4.4.2.3 Pemasangan 1 m2 Plesteran 1PC : 3 Pasir Pasang tebal 15 mm


SATUAN : M2
HARGA SATUAN : Rp 80,249.44

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Semen Portland Kg 7.7760 1,240.00 9,642.24
Pasir Pasang m3 0.0230 176,600.00 4,061.80
JUMLAH HARGA BAHAN 13,704.04
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 72,954.04
E Overhead & profit 10% x Jumlah 7,295.40
F Harga Satuan Pekerjaan (D+E) 80,249.44

JENIS PEKERJAAN : A.4.4.2.4 Pemasangan 1 m2 Plesteran 1PC : 4 Pasir Pasang tebal 15 mm


SATUAN : M2
HARGA SATUAN : Rp 78,348.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Semen Portland Kg 6.2400 1,240.00 7,737.60
Pasir Pasang m3 0.0240 176,600.00 4,238.40
JUMLAH HARGA BAHAN 11,976.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 71,226.00
E Overhead & profit 10% x Jumlah 7,122.60
F Harga Satuan Pekerjaan (D+E) 78,348.60

JENIS PEKERJAAN : A.4.4.2.5 Pemasangan 1 m2 Plesteran 1PC : 5 Pasir Pasang tebal 15 mm


SATUAN : M2
HARGA SATUAN : Rp 77,296.74

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Semen Portland Kg 5.1840 1,240.00 6,428.16
Pasir Pasang m3 0.0260 176,600.00 4,591.60
JUMLAH HARGA BAHAN 11,019.76
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 70,269.76
E Overhead & profit 10% x Jumlah 7,026.98
F Harga Satuan Pekerjaan (D+E) 77,296.74
JENIS PEKERJAAN : A.4.4.2.6 Pemasangan 1 m2 Plesteran 1PC : 6 Pasir Pasang tebal 15 mm
SATUAN : M2
HARGA SATUAN : Rp 76,443.44

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Semen Portland Kg 4.4160 1,240.00 5,475.84
Pasir Pasang m3 0.0270 176,600.00 4,768.20
JUMLAH HARGA BAHAN 10,244.04
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 69,494.04
E Overhead & profit 10% x Jumlah 6,949.40
F Harga Satuan Pekerjaan (D+E) 76,443.44

JENIS PEKERJAAN : A.4.4.2.7 Pemasangan 1 m2 Plesteran 1PC : 7 Pasir Pasang tebal 15 mm


SATUAN : M2
HARGA SATUAN : Rp 75,982.98

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Semen Portland Kg 3.9360 1,240.00 4,880.64
Pasir Pasang m3 0.0280 176,600.00 4,944.80
JUMLAH HARGA BAHAN 9,825.44
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 69,075.44
E Overhead & profit 10% x Jumlah 6,907.54
F Harga Satuan Pekerjaan (D+E) 75,982.98

JENIS PEKERJAAN : A.4.4.2.8 Pemasangan 1 m2 Plesteran 1PC : 8 Pasir Pasang tebal 15 mm


SATUAN : M2
HARGA SATUAN : Rp 75,522.52

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Semen Portland Kg 3.4560 1,240.00 4,285.44
Pasir Pasang m3 0.0290 176,600.00 5,121.40
JUMLAH HARGA BAHAN 9,406.84
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 68,656.84
E Overhead & profit 10% x Jumlah 6,865.68
F Harga Satuan Pekerjaan (D+E) 75,522.52

JENIS PEKERJAAN : A.4.4.2.9 Pemasangan 1 m2 Plesteran 1PC : 1/2Kapur Padam : 3 Pasir Pasang tebal 15 mm
SATUAN : M2
HARGA SATUAN : Rp 80,375.02

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3600 105,000.00 37,800.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 61,050.00
B BAHAN
Semen Portland Kg 5.7600 1,240.00 7,142.40
Kapur Padam m3 0.0030 860,000.00 2,580.00
Pasir Pasang m3 0.0130 176,600.00 2,295.80
JUMLAH HARGA BAHAN 12,018.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 73,068.20
E Overhead & profit 10% x Jumlah 7,306.82
F Harga Satuan Pekerjaan (D+E) 80,375.02

JENIS PEKERJAAN : A.4.4.2.10 Pemasangan 1 m2 Plesteran 1PC : 2Kapur Padam : 8 Pasir Pasang tebal 15 mm
SATUAN : M2
HARGA SATUAN : Rp 79,862.20

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3600 105,000.00 37,800.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 61,050.00
B BAHAN
Semen Portland Kg 3.0000 1,240.00 3,720.00
Kapur Padam m3 0.0050 860,000.00 4,300.00
Pasir Pasang m3 0.0200 176,600.00 3,532.00
JUMLAH HARGA BAHAN 11,552.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 72,602.00
E Overhead & profit 10% x Jumlah 7,260.20
F Harga Satuan Pekerjaan (D+E) 79,862.20

JENIS PEKERJAAN : A.4.4.2.11 Pemasangan 1 m2 Plesteran 1Semen Portland : 1Kapur Padam : 1 Pasir Pasang tebal 15 mm
SATUAN : M2
HARGA SATUAN : Rp 77,429.62

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3600 105,000.00 37,800.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 61,050.00
B BAHAN
Semen Portland m3 0.0090 1,240.00 11.16
Kapur Padam m3 0.0090 860,000.00 7,740.00
Pasir Pasang m3 0.0090 176,600.00 1,589.40
JUMLAH HARGA BAHAN 9,340.56
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 70,390.56
E Overhead & profit 10% x Jumlah 7,039.06
F Harga Satuan Pekerjaan (D+E) 77,429.62

JENIS PEKERJAAN : A.4.4.2.12 Pemasangan 1 m2 Plesteran 1Semen Portland : 1Kapur Padam : 2 Pasir Pasang tebal 15 mm
SATUAN : M2
HARGA SATUAN : Rp 76,700.45

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3600 105,000.00 37,800.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 61,050.00
B BAHAN
Semen Portland m3 0.0070 1,240.00 8.68
Kapur Padam m3 0.0070 860,000.00 6,020.00
Pasir Pasang m3 0.0150 176,600.00 2,649.00
JUMLAH HARGA BAHAN 8,677.68
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 69,727.68
E Overhead & profit 10% x Jumlah 6,972.77
F Harga Satuan Pekerjaan (D+E) 76,700.45

JENIS PEKERJAAN : A.4.4.2.13 Pemasangan 1 m2 Plesteran 1PC : 1 Pasir Pasang tebal 20 mm


SATUAN : M2
HARGA SATUAN : Rp 111,124.07

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4000 105,000.00 42,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0220 175,000.00 3,850.00
JUMLAH TENAGA KERJA 79,350.00
B BAHAN
Semen Portland Kg 13.6320 1,240.00 16,903.68
Pasir Pasang m3 0.0270 176,600.00 4,768.20
JUMLAH HARGA BAHAN 21,671.88
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 101,021.88
E Overhead & profit 10% x Jumlah 10,102.19
F Harga Satuan Pekerjaan (D+E) 111,124.07

JENIS PEKERJAAN : A.4.4.2.14 Pemasangan 1 m2 Plesteran 1PC : 3 Pasir Pasang tebal 20 mm


SATUAN : M2
HARGA SATUAN : Rp 89,546.51

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2600 105,000.00 27,300.00
Tukang batu L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 63,075.00
B BAHAN
Semen Portland Kg 10.3680 1,240.00 12,856.32
Pasir Pasang m3 0.0310 176,600.00 5,474.60
JUMLAH HARGA BAHAN 18,330.92
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 81,405.92
E Overhead & profit 10% x Jumlah 8,140.59
F Harga Satuan Pekerjaan (D+E) 89,546.51

JENIS PEKERJAAN : A.4.4.2.15 Pemasangan 1 m2 Plesteran 1PC : 4 Pasir Pasang tebal 20 mm


SATUAN : M2
HARGA SATUAN : Rp 104,849.80

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4000 105,000.00 42,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0220 175,000.00 3,850.00
JUMLAH TENAGA KERJA 79,350.00
B BAHAN
Semen Portland Kg 8.3200 1,240.00 10,316.80
Pasir Pasang m3 0.0320 176,600.00 5,651.20
JUMLAH HARGA BAHAN 15,968.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 95,318.00
E Overhead & profit 10% x Jumlah 9,531.80
F Harga Satuan Pekerjaan (D+E) 104,849.80

JENIS PEKERJAAN : A.4.4.2.16 Pemasangan 1 m2 Plesteran 1PC : 5 Pasir Pasang tebal 20 mm


SATUAN : M2
HARGA SATUAN : Rp 103,512.07

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4000 105,000.00 42,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0220 175,000.00 3,850.00
JUMLAH TENAGA KERJA 79,350.00
B BAHAN
Semen Portland Kg 6.9120 1,240.00 8,570.88
Pasir Pasang m3 0.0350 176,600.00 6,181.00
JUMLAH HARGA BAHAN 14,751.88
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 94,101.88
E Overhead & profit 10% x Jumlah 9,410.19
F Harga Satuan Pekerjaan (D+E) 103,512.07

JENIS PEKERJAAN : A.4.4.2.17 Pemasangan 1 m2 Plesteran 1PC : 6 Pasir Pasang tebal 20 mm


SATUAN : M2
HARGA SATUAN : Rp 102,309.59

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4000 105,000.00 42,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0220 175,000.00 3,850.00
JUMLAH TENAGA KERJA 79,350.00
B BAHAN
Semen Portland Kg 5.8880 1,240.00 7,301.12
Pasir Pasang m3 0.0360 176,600.00 6,357.60
JUMLAH HARGA BAHAN 13,658.72
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 93,008.72
E Overhead & profit 10% x Jumlah 9,300.87
F Harga Satuan Pekerjaan (D+E) 102,309.59

JENIS PEKERJAAN : A.4.4.2.18 Pemasangan 1 m2 Plesteran 1Semen Portland : 1Kapur Padam : 2 Pasir Pasang tebal 20 mm
SATUAN : M2
HARGA SATUAN : Rp 107,612.96

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.4400 105,000.00 46,200.00
Tukang L.02 OH 0.2200 150,000.00 33,000.00
Kepala tukang L.03 OH 0.0220 175,000.00 3,850.00
Mandor L.04 OH 0.0220 175,000.00 3,850.00
JUMLAH TENAGA KERJA 86,900.00
B BAHAN
Semen Portland m3 0.0090 1,240.00 11.16
Kapur Padam m3 0.0090 860,000.00 7,740.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
JUMLAH HARGA BAHAN 10,929.96
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 97,829.96
E Overhead & profit 10% x Jumlah 9,783.00
F Harga Satuan Pekerjaan (D+E) 107,612.96

JENIS PEKERJAAN : A.4.4.2.19 Pemasangan 1 m2 berapen 1PC : 5 Pasir Pasang tebal 15 mm


SATUAN : M2
HARGA SATUAN : Rp 44,901.74

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.0750 150,000.00 11,250.00
Kepala tukang L.03 OH 0.0080 175,000.00 1,400.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 29,800.00
B BAHAN
Semen Portland kg 5.1840 1,240.00 6,428.16
Pasir Pasang m3 0.0260 176,600.00 4,591.60
JUMLAH HARGA BAHAN 11,019.76
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 40,819.76
E Overhead & profit 10% x Jumlah 4,081.98
F Harga Satuan Pekerjaan (D+E) 44,901.74

JENIS PEKERJAAN : A.4.4.2.20 Pemasangan 1 m2 Plesteran skoning 1PC : 3 Pasir Pasang lebar 10 Cm
SATUAN : M2
HARGA SATUAN : Rp 86,917.38

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0800 105,000.00 8,400.00
Tukang L.02 OH 0.4000 150,000.00 60,000.00
Kepala tukang L.03 OH 0.0400 175,000.00 7,000.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 76,100.00
B BAHAN
Semen Portland Kg 0.5000 1,240.00 620.00
Pasir Pasang m3 0.0130 176,600.00 2,295.80
JUMLAH HARGA BAHAN 2,915.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 79,015.80
E Overhead & profit 10% x Jumlah 7,901.58
F Harga Satuan Pekerjaan (D+E) 86,917.38

JENIS PEKERJAAN : A.4.4.2.21 Pemasangan 1 m2 Plesteran skoning 1PC : 2 Granit tebal 1 Cm


SATUAN : M2
HARGA SATUAN : Rp 692,230.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4500 105,000.00 47,250.00
Tukang L.02 OH 0.2250 150,000.00 33,750.00
Kepala tukang L.03 OH 0.0230 175,000.00 4,025.00
Mandor L.04 OH 0.0230 175,000.00 4,025.00
JUMLAH TENAGA KERJA 89,050.00
B BAHAN
Semen Portland Kg 10.0000 1,240.00 12,400.00
Batu Granit Kg 15.0000 35,190.00 527,850.00
JUMLAH HARGA BAHAN 540,250.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 629,300.00
E Overhead & profit 10% x Jumlah 62,930.00
F Harga Satuan Pekerjaan (D+E) 692,230.00

JENIS PEKERJAAN : A.4.4.2.22 Pemasangan 1 m2 Plesteran traso 1PC ; 2 traso tebal 1 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.4500 105,000.00 47,250.00
Tukang L.02 OH 0.2250 150,000.00 33,750.00
Kepala tukang L.03 OH 0.0230 175,000.00 4,025.00
Mandor L.04 OH 0.0230 175,000.00 4,025.00
JUMLAH TENAGA KERJA 89,050.00
B BAHAN
Semen Portland Kg 10.0000 1,240.00 12,400.00
Batu traso Kg 15.0000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.2.23 Pemasangan 1 m2 Plesteran ciprat 1PC : 2 Pasir Pasang


SATUAN : M2
HARGA SATUAN : Rp 63,020.54

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 50,875.00
B BAHAN
Semen Portland Kg 4.3200 1,240.00 5,356.80
Pasir Pasang Kg 0.0060 176,600.00 1,059.60
JUMLAH HARGA BAHAN 6,416.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 57,291.40
E Overhead & profit 10% x Jumlah 5,729.14
F Harga Satuan Pekerjaan (D+E) 63,020.54

JENIS PEKERJAAN : A.4.4.2.24 Pemasangan 1 m2 finishing siar pasangan Bata Merah


SATUAN : M2
HARGA SATUAN : Rp 37,019.31

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.0750 150,000.00 11,250.00
Kepala tukang L.03 OH 0.0080 175,000.00 1,400.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 29,800.00
B BAHAN
Semen Portland Kg 3.1080 1,240.00 3,853.92
JUMLAH HARGA BAHAN 3,853.92
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 33,653.92
E Overhead & profit 10% x Jumlah 3,365.39
F Harga Satuan Pekerjaan (D+E) 37,019.31

JENIS PEKERJAAN : A.4.4.2.25 Pemasangan 1 m2 finishing siar pasangan conblock ekspose


SATUAN : M2
HARGA SATUAN : Rp 17,582.40

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0700 105,000.00 7,350.00
Tukang L.02 OH 0.0350 150,000.00 5,250.00
Kepala tukang L.03 OH 0.0040 175,000.00 700.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 14,000.00
B BAHAN
Semen Portland Kg 1.6000 1,240.00 1,984.00
JUMLAH HARGA BAHAN 1,984.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 15,984.00
E Overhead & profit 10% x Jumlah 1,598.40
F Harga Satuan Pekerjaan (D+E) 17,582.40

JENIS PEKERJAAN : A.4.4.2.26 Pemasangan 1 m2 finishing siar pasangan batu kali, Camp, 1PC : 2 Pasir Pasang
SATUAN : M2
HARGA SATUAN : Rp 67,506.12

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 59,250.00
B BAHAN
Semen Portland Kg 6.3400 1,240.00 7,861.60
Pasir Pasang Kg 0.0120 176,600.00 2,119.20
JUMLAH HARGA BAHAN 2,119.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 61,369.20
E Overhead & profit 10% x Jumlah 6,136.92
F Harga Satuan Pekerjaan (D+E) 67,506.12

JENIS PEKERJAAN : A.4.4.2.27 Pemasangan 1 m2 Acian


SATUAN : M2
HARGA SATUAN : Rp 47,883.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0100 175,000.00 1,750.00
JUMLAH TENAGA KERJA 39,500.00
B BAHAN
Semen Portland Kg 3.2500 1,240.00 4,030.00
JUMLAH HARGA BAHAN 4,030.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 43,530.00
E Overhead & profit 10% x Jumlah 4,353.00
F Harga Satuan Pekerjaan (D+E) 47,883.00

HARGA SATUAN PEKERJAAN PENUTUP Lantai DAN PENUTUP DINDING

JENIS PEKERJAAN : A.4.4.3.1 Pemasangan 1 m2 Lantai ubin Semen Portland abu-abu ukuran 40 Cm x 40 Cm
SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 49,550.00
B BAHAN
Ubin abu-abu Bh 6.6300 a #VALUE!
Semen Portland Kg 9.8000 1,240.00 12,152.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.2 Pemasangan 1 m2 Lantai ubin Semen Portland abu-abu ukuran 30 Cm x 30 Cm
SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 49,550.00
B BAHAN
Ubin abu-abu Bh 11.8700 a #VALUE!
Semen Portland Kg 10.0000 1,240.00 12,400.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.3 Pemasangan 1 m2 Lantai ubin Semen Portland abu-abu ukuran 20 Cm x20 Cm
SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.2700 105,000.00 28,350.00
Tukang L.02 OH 0.1350 150,000.00 20,250.00
Kepala tukang L.03 OH 0.0140 175,000.00 2,450.00
Mandor L.04 OH 0.0140 175,000.00 2,450.00
JUMLAH TENAGA KERJA 53,500.00
B BAHAN
Ubin abu-abu Bh 26.5000 a #VALUE!
Semen Portland Kg 10.4000 1,240.00 12,896.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.4 Pemasangan 1 m2 Lantai ubin warna ukuran 40 Cm x 40 Cm


SATUAN : M2
HARGA SATUAN : Rp 196,172.90

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 49,550.00
B BAHAN
Ubin warna Bh 6.6300 15,000.00 99,450.00
Semen Portland Kg 9.8000 1,240.00 12,152.00
Semen warna (tepung affa) Kg 0.6000 15,400.00 9,240.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN 128,789.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 178,339.00
E Overhead & profit 10% x Jumlah 17,833.90
F Harga Satuan Pekerjaan (D+E) 196,172.90

JENIS PEKERJAAN : A.4.4.3.5 Pemasangan 1 m2 Lantai ubin warna ukuran 30 Cm x 30 Cm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.2600 105,000.00 27,300.00
Tukang L.02 OH 0.1300 150,000.00 19,500.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 51,350.00
B BAHAN
Ubin warna Bh 11.8700 Err:509 Err:509
Semen Portland Kg 10.0000 1,240.00 12,400.00
Semen warna (tepung affa) Kg 0.6000 15,400.00 9,240.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.4.3.6 Pemasangan 1 m2 Lantai ubin warna ukuran 20 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.2700 105,000.00 28,350.00
Tukang L.02 OH 0.1350 150,000.00 20,250.00
Kepala tukang L.03 OH 0.0140 175,000.00 2,450.00
Mandor L.04 OH 0.0140 175,000.00 2,450.00
JUMLAH TENAGA KERJA 53,500.00
B BAHAN
Ubin warna Bh 26.5000 Err:509 Err:509
Semen Portland Kg 10.4000 1,240.00 12,896.00
Semen warna (tepung affa) Kg 1.0000 15,400.00 15,400.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.4.3.7 Pemasangan 1 m2 Lantai ubin teraso ukuran 40 Cm x 40 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 49,550.00
B BAHAN
Ubin teraso Bh 6.6300 A #VALUE!
Semen Portland Kg 9.8000 1,240.00 12,152.00
Semen warna (tepung affa) Kg 1.3000 15,400.00 20,020.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.8 Pemasangan 1 m2 Lantai ubin teraso ukuran 30 Cm x 30 Cm


SATUAN : M2
HARGA SATUAN : #DIV/0!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.2600 105,000.00 27,300.00
Tukang L.02 OH 0.1300 150,000.00 19,500.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 51,350.00
B BAHAN
Ubin teraso Bh 11.8700 #DIV/0! #DIV/0!
Semen Portland Kg 10.0000 1,240.00 12,400.00
Semen warna (tepung affa) Kg 1.5000 15,400.00 23,100.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN #DIV/0!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #DIV/0!
E Overhead & profit 10% x Jumlah #DIV/0!
F Harga Satuan Pekerjaan (D+E) #DIV/0!
JENIS PEKERJAAN : A.4.4.3.9 Pemasangan 1 m2 Lantai Granit ukuran 40 Cm x 40 Cm
SATUAN : M2
HARGA SATUAN : Rp 355,276.57

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 49,550.00
B BAHAN
Granit ukuran 40 Cm x 40 Cm Bh 6.6300 35,190.00 233,309.70
Semen Portland Kg 9.8000 1,240.00 12,152.00
Semen warna (tepung affa) Kg 1.3000 15,400.00 20,020.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN 273,428.70
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 322,978.70
E Overhead & profit 10% x Jumlah 32,297.87
F Harga Satuan Pekerjaan (D+E) 355,276.57

JENIS PEKERJAAN : A.4.4.3.10 Pemasangan 1 m2 Lantai Granit ukuran 30 Cm x 30 Cm


SATUAN : M2
HARGA SATUAN : Rp 562,577.40

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2600 105,000.00 27,300.00
Tukang L.02 OH 0.1300 150,000.00 19,500.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 51,350.00
B BAHAN
Granit ukuran 30 Cm x 30 Cm Bh 11.8700 35,100.00 416,637.00
Semen Portland Kg 10.0000 1,240.00 12,400.00
Semen warna (tepung affa) Kg 1.5000 15,400.00 23,100.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN 460,084.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 511,434.00
E Overhead & profit 10% x Jumlah 51,143.40
F Harga Satuan Pekerjaan (D+E) 562,577.40

JENIS PEKERJAAN : A.4.4.3.11 Pemasangan 1 m2 Lantai ubin teralux ukuran 40 Cm x 40 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 49,550.00
B BAHAN
Ubin teralux Bh 6.6300 a #VALUE!
Semen Portland Kg 9.8000 1,240.00 12,152.00
Semen warna (tepung affa) Kg 1.3000 15,400.00 20,020.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.12 Pemasangan 1 m2 Lantai ubin teralux ukuran 30 Cm x 30 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2600 105,000.00 27,300.00
Tukang L.02 OH 0.1300 150,000.00 19,500.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 51,350.00
B BAHAN
Ubin teralux Bh 11.8700 a #VALUE!
Semen Portland Kg 10.0000 1,240.00 12,400.00
Semen warna (tepung affa) Kg 1.5000 15,400.00 23,100.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.13 Pemasangan 1 m2 Lantai ubin teralux marmer (Keramik) ukuran 60 Cm x 60 Cm
SATUAN : M2
HARGA SATUAN : Rp 525,636.10

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2400 105,000.00 25,200.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0120 175,000.00 2,100.00
JUMLAH TENAGA KERJA 47,400.00
B BAHAN
Keramik 60 x 60 cm Bh 3.1000 125,000.00 387,500.00
Semen Portland Kg 9.6000 1,240.00 11,904.00
Semen warna (tepung affa) Kg 1.5000 15,400.00 23,100.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN 430,451.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 477,851.00
E Overhead & profit 10% x Jumlah 47,785.10
F Harga Satuan Pekerjaan (D+E) 525,636.10

JENIS PEKERJAAN : A.4.4.3.14 Pemasangan 1 m2 Lantai ubin teralux marmer ukuran 40 Cm x 40 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 49,550.00
B BAHAN
Ubin teralux marmer Bh 6.6300 a #VALUE!
Semen Portland Kg 9.8000 1,240.00 12,152.00
Semen warna (tepung affa) Kg 1.3000 15,400.00 20,020.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.15 Pemasangan 1 m2 Lantai ubin teralux marmer ukuran 30 Cm x 30 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2600 105,000.00 27,300.00
Tukang L.02 OH 0.1300 150,000.00 19,500.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 51,350.00
B BAHAN
Ubin teralux marmer Bh 11.8700 a #VALUE!
Semen Portland Kg 10.0000 1,240.00 12,400.00
Semen warna (tepung affa) Kg 1.5000 15,400.00 23,100.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.16 Pemasangan 1 M1 plint ubin Semen Portland abu-abu ukuran 15 Cm x 20 Cm
SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint ubin Semen Portland Bh 5.3000 a #VALUE!
Semen Portland Kg 1.6500 1,240.00 2,046.00
Pasir Pasang m3 0.0040 176,600.00 706.40
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.17 Pemasangan 1 M1 plint ubin Semen Portland abu-abu ukuran 10 Cm x 30 Cm
SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint ubin Semen Portland Bh 3.5300 a #VALUE!
Semen Portland Kg 1.2400 1,240.00 1,537.60
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.18 Pemasangan 1 M1 plint ubin Semen Portland abu-abu ukuran 10 Cm x 40 Cm
SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint ubin Semen Portland Bh 2.6500 a #VALUE!
Semen Portland Kg 1.2400 1,240.00 1,537.60
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.19 Pemasangan 1 M1 plint ubin warna ukuran 10 Cm x 20 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint ubin warna Bh 2.6500 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1500 15,400.00 2,310.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.20 Pemasangan 1 M1 plint ubin warna ukuran 10 Cm x 30 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint ubin warna Bh 3.5300 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.21 Pemasangan 1 M1 plint ubin warna ukuran 10 Cm x 40 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint ubin warna Bh 2.6500 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.22 Pemasangan 1 M1 plint ubin teraso ukuran 10 Cm x 30 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint ubin teraso Bh 3.5300 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.23 Pemasangan 1 M1 plint ubin teraso ukuran 10 Cm x 40 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint ubin teraso Bh 2.6500 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.24 Pemasangan 1 M1 plint ubin Granit ukuran 10 Cm x 40 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint ubin Granit Bh 2.6500 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.25 Pemasangan 1 M1 plint ubin Granit ukuran 10 Cm x 30 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint ubin Granit Bh 3.5300 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.26 Pemasangan 1 M1 plint ubin teralux kerang ukuran 10 Cm x 40 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint teralux kerang Bh 2.6300 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.27 Pemasangan 1 M1 plint ubin teralux kerang ukuran 10 Cm x 30 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint teralux kerang Bh 3.5300 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.28 Pemasangan 1 M1 plint ubin teralux marmer ukuran 10 Cm x 60 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint teralux marmer Bh 1.7000 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.29 Pemasangan 1 M1 plint ubin teralux marmer ukuran 10 Cm x 40 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint teralux marmer Bh 2.6500 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.30 Pemasangan 1 M1 plint ubin teralux marmer ukuran 10 Cm x 30 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 25,400.00
B BAHAN
Plint teralux marmer Bh 3.5300 a #VALUE!
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
Pasir Pasang m3 0.0030 176,600.00 529.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.31 Pemasangan 1 M1 Lantai teraso cor di tempat, tebal 3 Cm


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3600 105,000.00 37,800.00
Tukang L.02 OH 0.1800 150,000.00 27,000.00
Kepala tukang L.03 OH 0.0180 175,000.00 3,150.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 71,100.00
B BAHAN
Teraso Bh 0.0360 a #VALUE!
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.32 Pemasangan 1 m2 Lantai keramik artistik 10 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
Ubin keramik Bh 53.0000 a #VALUE!
Semen Portland Kg 8.1900 1,240.00 10,155.60
Pasir Pasang m3 0.0450 176,600.00 7,947.00
Semen warna (tepung affa) Kg 2.7500 15,400.00 42,350.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.33 Pemasangan 1 m2 Lantai keramik artistik 10 Cm x 10 Cm atau 5 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
Ubin keramik Bh 106.0000 a #VALUE!
Semen Portland Kg 8.1900 1,240.00 10,155.60
Pasir Pasang m3 0.0450 176,600.00 7,947.00
Semen warna (tepung affa) Kg 3.2000 15,400.00 49,280.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.34 Pemasangan 1 m2 Lantai keramik ukuran 40 Cm x 40 Cm


SATUAN : M2
HARGA SATUAN : Rp 258,997.86

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
Keramik 40x40 Doos 1.0500 68,000.00 71,400.00
Semen Portland Kg 8.1900 1,240.00 10,155.60
Pasir Pasang m3 0.0450 176,600.00 7,947.00
Semen warna (tepung affa) Kg 0.5000 15,400.00 7,700.00
JUMLAH HARGA BAHAN 97,202.60
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 235,452.60
E Overhead & profit 10% x Jumlah 23,545.26
F Harga Satuan Pekerjaan (D+E) 258,997.86

JENIS PEKERJAAN : - Pemasangan 1 m2 Lantai keramik ukuran 60 Cm x 60 Cm


SATUAN : M2
HARGA SATUAN : Rp 581,811.14

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
keramik ukuran 60 Cm x 60 Cm Bh 2.7778 125,000.00 347,222.22
Semen Portland Kg 10.0000 1,240.00 12,400.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
Semen warna (tepung affa) Kg 1.5000 15,400.00 23,100.00
JUMLAH HARGA BAHAN 390,669.22
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 528,919.22
E Overhead & profit 10% x Jumlah 52,891.92
F Harga Satuan Pekerjaan (D+E) 581,811.14

JENIS PEKERJAAN : - Pemasangan 1 m2 Lantai keramik ukuran 40 Cm x 40 Cm


SATUAN : M2
HARGA SATUAN : Rp 616,491.70

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
keramik ukuran 40 Cm x 40 Cm Bh 6.2500 60,600.00 378,750.00
Semen Portland Kg 10.0000 1,240.00 12,400.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
Semen warna (tepung affa) Kg 1.5000 15,400.00 23,100.00
JUMLAH HARGA BAHAN 422,197.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 560,447.00
E Overhead & profit 10% x Jumlah 56,044.70
F Harga Satuan Pekerjaan (D+E) 616,491.70

JENIS PEKERJAAN : A.4.4.3.35 Pemasangan 1 m2 Lantai keramik ukuran 30 Cm x 30 Cm


SATUAN : M2
HARGA SATUAN : Rp 252,226.70

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
keramik ukuran 30 Cm x 30 Cm Doos 1.0500 60,000.00 63,000.00
Semen Portland Kg 10.0000 1,240.00 12,400.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
Semen warna (tepung affa) Kg 0.5000 15,400.00 7,700.00
JUMLAH HARGA BAHAN 91,047.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 229,297.00
E Overhead & profit 10% x Jumlah 22,929.70
F Harga Satuan Pekerjaan (D+E) 252,226.70

JENIS PEKERJAAN : A.4.4.3.36 Pemasangan 1 m2 Lantai keramik ukuran 20 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : Rp 255,082.30

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
keramik ukuran 20 Cm x 20 Cm Doos 1.0500 62,000.00 65,100.00
Semen Portland Kg 10.4000 1,240.00 12,896.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
Semen warna (tepung affa) Kg 0.5000 15,400.00 7,700.00
JUMLAH HARGA BAHAN 93,643.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 231,893.00
E Overhead & profit 10% x Jumlah 23,189.30
F Harga Satuan Pekerjaan (D+E) 255,082.30

JENIS PEKERJAAN : A.4.4.3.36.a Pemasangan 1 m2 Lantai keramik ukuran 25 Cm x 25 Cm


SATUAN : M2
HARGA SATUAN : Rp 296,666.70

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
keramik ukuran 25 Cm x 25 Cm Doos 17.6000 5,000.00 88,000.00
Semen Portland Kg 10.0000 1,240.00 12,400.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
Semen warna (tepung affa) Kg 1.5000 15,400.00 23,100.00
JUMLAH HARGA BAHAN 131,447.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 269,697.00
E Overhead & profit 10% x Jumlah 26,969.70
F Harga Satuan Pekerjaan (D+E) 296,666.70

JENIS PEKERJAAN : A.4.4.3.37 Pemasangan 1 m2 Lantai keramik ukuran 10 Cm x 33 Cm untuk variasi/border


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 1.0500 105,000.00 110,250.00
Tukang L.02 OH 0.5250 150,000.00 78,750.00
Kepala tukang L.03 OH 0.0530 175,000.00 9,275.00
Mandor L.04 OH 0.0530 175,000.00 9,275.00
JUMLAH TENAGA KERJA 207,550.00
B BAHAN
Ubin keramik Bh 33.0000 a #VALUE!
Semen Portland Kg 9.8000 1,240.00 12,152.00
Pasir Pasang m3 0.0450 176,600.00 7,947.00
Semen warna (tepung affa) Kg 4.3700 15,400.00 67,298.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 15 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.38 Pemasangan 1 m2 Lantai keramik mozaik ukuran 30 Cm x 30 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
Ubin keramik Bh 11.8700 a #VALUE!
Semen Portland Kg 14.1500 1,240.00 17,546.00
Pasir Pasang m3 0.0390 176,600.00 6,887.40
Semen warna (tepung affa) Kg 2.0000 15,400.00 30,800.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 15 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.39 Pemasangan 1 M1 plint keramik ukuran 10 Cm x 20 Cm


SATUAN : M1
HARGA SATUAN : Rp 59,992.24

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 29,950.00
B BAHAN
Plint keramik 10 Cm x 20 Cm Bh 5.3000 4,200.00 22,260.00
Semen Portland Kg 1.1400 1,240.00 1,413.60
Pasir Pasang m3 0.0030 176,600.00 529.80
Semen warna (tepung affa) Kg 0.0250 15,400.00 385.00
JUMLAH HARGA BAHAN 24,588.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 54,538.40
E Overhead & profit 10% x Jumlah 5,453.84
F Harga Satuan Pekerjaan (D+E) 59,992.24

JENIS PEKERJAAN : A.4.4.3.40 Pemasangan 1 M1 plint keramik ukuran 10 Cm x 10 Cm


SATUAN : M1
HARGA SATUAN : Rp 80,237.74

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 29,950.00
B BAHAN
Plint keramik 10 Cm x 10 Cm Bh 10.6000 3,800.00 40,280.00
Semen Portland Kg 1.1400 1,240.00 1,413.60
Pasir Pasang m3 0.0030 176,600.00 529.80
Semen warna (tepung affa) Kg 0.0500 15,400.00 770.00
JUMLAH HARGA BAHAN 42,993.40
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 72,943.40
E Overhead & profit 10% x Jumlah 7,294.34
F Harga Satuan Pekerjaan (D+E) 80,237.74

JENIS PEKERJAAN : - Pemasangan 1 M1 plint keramik ukuran 10 Cm x 30 Cm


SATUAN : M1
HARGA SATUAN : Rp 76,032.07

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 29,950.00
B BAHAN
Plint keramik 10 Cm x 30 Cm Bh 3.5333 10,100.00 35,686.67
Semen Portland Kg 1.1400 1,240.00 1,413.60
Pasir Pasang m3 0.0030 176,600.00 529.80
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
JUMLAH HARGA BAHAN 39,170.07
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 69,120.07
E Overhead & profit 10% x Jumlah 6,912.01
F Harga Satuan Pekerjaan (D+E) 76,032.07

JENIS PEKERJAAN : - Pemasangan 1 M1 plint keramik ukuran 10 Cm x 40 Cm


SATUAN : M1
HARGA SATUAN : Rp 70,882.24

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 29,950.00
B BAHAN
Plint keramik 10 Cm x 40 Cm Bh 2.6500 11,700.00 31,005.00
Semen Portland Kg 1.1400 1,240.00 1,413.60
Pasir Pasang m3 0.0030 176,600.00 529.80
Semen warna (tepung affa) Kg 0.1000 15,400.00 1,540.00
JUMLAH HARGA BAHAN 34,488.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 64,438.40
E Overhead & profit 10% x Jumlah 6,443.84
F Harga Satuan Pekerjaan (D+E) 70,882.24

JENIS PEKERJAAN : A.4.4.3.41 Pemasangan 1 M1 plint keramik ukuran 5 Cm x 20 Cm


SATUAN : M1
HARGA SATUAN : Rp 69,214.09

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0900 105,000.00 9,450.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 29,950.00
B BAHAN
Plint keramik Bh 5.3000 6,000.00 31,800.00
Semen Portland Kg 0.5700 1,240.00 706.80
Pasir Pasang m3 0.0015 176,600.00 264.90
Semen warna (tepung affa) Kg 0.0130 15,400.00 200.20
JUMLAH HARGA BAHAN 32,971.90
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 62,921.90
E Overhead & profit 10% x Jumlah 6,292.19
F Harga Satuan Pekerjaan (D+E) 69,214.09

JENIS PEKERJAAN : A.4.4.3.42 Pemasangan 1 M1 plint internal cove artistik 5 Cm x 5 Cm x 20 Cm


SATUAN : M1
HARGA SATUAN : Rp 291,344.24

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7500 105,000.00 78,750.00
Tukang L.02 OH 0.7500 150,000.00 112,500.00
Kepala tukang L.03 OH 0.0750 175,000.00 13,125.00
Mandor L.04 OH 0.0380 175,000.00 6,650.00
JUMLAH TENAGA KERJA 211,025.00
B BAHAN
Internal cove Bh 5.3000 9,500.00 50,350.00
Semen Portland Kg 1.1400 1,240.00 1,413.60
Semen warna (tepung affa) kg 0.0030 176,600.00 529.80
Pasir Pasang m3 0.1000 15,400.00 1,540.00
JUMLAH HARGA BAHAN 53,833.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 264,858.40
E Overhead & profit 10% x Jumlah 26,485.84
F Harga Satuan Pekerjaan (D+E) 291,344.24

JENIS PEKERJAAN : A.4.4.3.43 Pemasangan 1 m2 Lantai marmer untuk ukuran 100 Cm x 100 Cm
SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
Marmer Bh 1.0600 z #VALUE!
Semen Portland Kg 8.1900 1,240.00 10,155.60
Semen warna (tepung affa) kg 0.1340 15,400.00 2,063.60
Pasir Pasang m3 0.0450 176,600.00 7,947.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.44 Pemasangan 1 m2 Lantai karpet


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1700 105,000.00 17,850.00
Tukang L.02 OH 0.1700 150,000.00 25,500.00
Kepala tukang L.03 OH 0.0170 175,000.00 2,975.00
Mandor L.04 OH 0.0090 175,000.00 1,575.00
JUMLAH TENAGA KERJA 47,900.00
B BAHAN
Karpet m2 1.0500 z #VALUE!
Lem Kg 0.3500 18,800.00 6,580.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.45 Pemasangan 1 m2 underlayer (pelapis bawah karpet)


SATUAN : M2
HARGA SATUAN : #VALUE!
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1200 105,000.00 12,600.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 33,750.00
B BAHAN
Underlayer m2 1.0500 z #VALUE!
Lem Kg 0.3500 18,800.00 6,580.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.46 Pemasangan 1 m2 Lantai parquet kayu


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
Parquet m2 1.0500 z #VALUE!
Lem Kg 0.6000 18,800.00 11,280.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.47 Pemasangan 1 m2 Lantai kayu gymfloor


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
Parquet m2 1.0500 z #VALUE!
Lem Kg 0.6000 18,800.00 11,280.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.48 Pemasangan 1 m2 dinding porselen 11 Cm x 11 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 197,500.00
B BAHAN
Porselen Doos 1.0500 z #VALUE!
Semen Portland Kg 9.3000 1,240.00 11,532.00
Semen warna (tepung affa) kg 0.5000 15,400.00 7,700.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.49 Pemasangan 1 m2 dinding Porselen 10 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN
Porselen Bh 53.0000 z #VALUE!
Semen Portland Kg 9.3000 1,240.00 11,532.00
Semen warna (tepung affa) kg 2.7500 15,400.00 42,350.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.50 Pemasangan 1 m2 dinding Porselen 20 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN
Porselen Bh 26.0000 z #VALUE!
Semen Portland Kg 9.3000 1,240.00 11,532.00
Semen warna (tepung affa) kg 1.9400 15,400.00 29,876.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.51 Pemasangan 1 m2 dinding keramik artistik 10 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN
Keramik artistik Bh 53.0000 z #VALUE!
Semen Portland Kg 9.3000 1,240.00 11,532.00
Semen warna (tepung affa) kg 2.7500 15,400.00 42,350.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.52 Pemasangan 1 m2 dinding keramik artistik 5 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN
Keramik artistik Bh 106.0000 z #VALUE!
Semen Portland Kg 9.3000 1,240.00 11,532.00
Semen warna (tepung affa) kg 2.9000 15,400.00 44,660.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.53 Pemasangan 1 m2 dinding keramik artistik 10 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN
Keramik artistik Bh 53.0000 a #VALUE!
Semen Portland Kg 9.3000 1,240.00 11,532.00
Semen warna (tepung affa) kg 2.7500 15,400.00 42,350.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.54 Pemasangan 1 m2 dinding keramik artistik 20 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN
Keramik artistik Bh 26.5000 Err:509 Err:509
Semen Portland Kg 9.3000 1,240.00 11,532.00
Semen warna (tepung affa) kg 1.9400 15,400.00 29,876.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.4.3.53 Pemasangan 1 m2 dinding keramik 10 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN
Keramik 20 Cm x 20 Cm Bh 53.0000 z #VALUE!
Semen Portland Kg 9.3000 1,240.00 11,532.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
Semen warna (tepung affa) Kg 2.7500 15,400.00 42,350.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.54 Pemasangan 1 m2 dinding keramik 20 Cm x 20 Cm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN
Keramik 20 Cm x 20 Cm Bh 26.5000 Err:509 Err:509
Semen Portland Kg 9.3000 1,240.00 11,532.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
Semen warna (tepung affa) Kg 1.9400 15,400.00 29,876.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A,4,4,3,54a Pemasangan 1 m2 dinding keramik 20 Cm x 25 Cm


SATUAN : M2
HARGA SATUAN : Rp 244,570.48

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN
Keramik 20 Cm x 25 Cm Bh 21.2000 - -
Semen Portland Kg 9.3000 1,240.00 11,532.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
Semen warna (tepung affa) Kg 1.9400 15,400.00 29,876.00
JUMLAH HARGA BAHAN 44,586.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 222,336.80
E Overhead & profit 10% x Jumlah 22,233.68
F Harga Satuan Pekerjaan (D+E) 244,570.48
JENIS PEKERJAAN : A,4,4,3,54b Pemasangan 1 m2 dinding keramik 20 Cm x 40 Cm
SATUAN : M2
HARGA SATUAN : Rp 244,570.48

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN
Keramik 20 Cm x 40 Cm Bh 13.2500 - -
Semen Portland Kg 9.3000 1,240.00 11,532.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
Semen warna (tepung affa) Kg 1.9400 15,400.00 29,876.00
JUMLAH HARGA BAHAN 44,586.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 222,336.80
E Overhead & profit 10% x Jumlah 22,233.68
F Harga Satuan Pekerjaan (D+E) 244,570.48

JENIS PEKERJAAN : A,4,4,3,54c Pemasangan 1 m2 dinding keramik 25Cm x 40 Cm


SATUAN : M2
HARGA SATUAN : Rp 361,170.48

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9000 105,000.00 94,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0450 175,000.00 7,875.00
JUMLAH TENAGA KERJA 177,750.00
B BAHAN
Keramik 25 Cm x 40 Cm Bh 13.2500 8,000.00 106,000.00
Semen Portland Kg 9.3000 1,240.00 11,532.00
Pasir Pasang m3 0.0180 176,600.00 3,178.80
Semen warna (tepung affa) Kg 1.9400 15,400.00 29,876.00
JUMLAH HARGA BAHAN 150,586.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 328,336.80
E Overhead & profit 10% x Jumlah 32,833.68
F Harga Satuan Pekerjaan (D+E) 361,170.48

JENIS PEKERJAAN : A.4.4.3.55 Pemasangan 1 m2 dinding marmer 100 Cm x 100 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.3000 105,000.00 136,500.00
Tukang L.02 OH 0.6500 150,000.00 97,500.00
Kepala tukang L.03 OH 0.0650 175,000.00 11,375.00
Mandor L.04 OH 0.0650 175,000.00 11,375.00
JUMLAH TENAGA KERJA 256,750.00
B BAHAN
Marmer Bh 1.0600 z #VALUE!
Semen Portland Kg 12.4400 1,240.00 15,425.60
Semen warna (tepung affa) m3 0.6500 15,400.00 10,010.00
Pasir Pasang Kg 0.0250 176,600.00 4,415.00
Paku 12 Cm Bh 3.0300 Err:509 Err:509
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!
JENIS PEKERJAAN : A.4.4.3.56 Pemasangan 1 m2 dinding bata pelapis 3 Cm x 7 Cm x 24 Cm
SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 197,500.00
B BAHAN
Bata pelapis Bh 63.0000 z #VALUE!
Semen Portland Kg 12.4400 1,240.00 15,425.60
Semen warna (tepung affa) m3 2.7500 15,400.00 42,350.00
Pasir Pasang Kg 0.0250 176,600.00 4,415.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.57 Pemasangan 1 m2 dinding batu paras


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
Batu paras Bh 1.1000 z #VALUE!
Semen Portland Kg 11.7500 1,240.00 14,570.00
Pasir Pasang m3 0.0350 176,600.00 6,181.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.58 Pemasangan 1 m2 dinding batu tempel hitam


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 0.3500 150,000.00 52,500.00
Kepala tukang L.03 OH 0.0350 175,000.00 6,125.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 138,250.00
B BAHAN
Batu tempel hitam Bh 1.1000 z #VALUE!
Semen Portland Kg 11.7500 1,240.00 14,570.00
Pasir Pasang m3 0.0350 176,600.00 6,181.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.59 Pemasangan 1 m2 Lantai vynil ukuran 30 Cm x 30 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 42,275.00
B BAHAN
Vynil Bh 11.8700 a #VALUE!
Lem Kg 0.3500 18,800.00 6,580.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.60 Pemasangan 1 m2 walpaper lebar 50 Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3500 105,000.00 36,750.00
Tukang L.02 OH 0.1750 150,000.00 26,250.00
Kepala tukang L.03 OH 0.0170 175,000.00 2,975.00
Mandor L.04 OH 0.0020 175,000.00 350.00
JUMLAH TENAGA KERJA 66,325.00
B BAHAN
Walpaper Bh 2.2000 a #VALUE!
Lem Kg 0.2500 18,800.00 4,700.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 15 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.4.3.61 Pemasangan 1 m2 Floor Harderner


SATUAN : M2
HARGA SATUAN : Rp 215,875

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1200 105,000.00 12,600.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 33,750.00
B BAHAN
Floor harderner Kg 5.0000 32,500.00 162,500.00
JUMLAH HARGA BAHAN 162,500.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 196,250.00
E Overhead & profit 10% x Jumlah 19,625.00
F Harga Satuan Pekerjaan (D+E) 215,875.00

JENIS PEKERJAAN : A.4.4.3.62 Pemasangan 1 M1 plint Karet Vynil ukuran 15 Cm x 30 Cm


SATUAN : M1
HARGA SATUAN : Rp 138,494

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0800 105,000.00 8,400.00
Tukang L.02 OH 0.0800 150,000.00 12,000.00
Kepala tukang L.03 OH 0.0080 175,000.00 1,400.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 23,200.00
B BAHAN
plint vynil ukuran 15 Cm x 30 Cm Bh 1.7600 57,500.00 101,200.00
Lem Kg 0.0800 18,800.00 1,504.00
JUMLAH HARGA BAHAN 102,704.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 125,904.00
E Overhead & profit 10% x Jumlah 12,590.40
F Harga Satuan Pekerjaan (D+E) 138,494.40

JENIS PEKERJAAN : A.4.4.3.63 Pemasangan 1 M1 plint kayu tebal 2 Cm lebar 10 Cm


SATUAN : M1
HARGA SATUAN : Rp 51,690

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1200 105,000.00 12,600.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 33,750.00
B BAHAN
Papan kayu kelas I m3 0.0030 4,103,500.00 12,310.50
Paku/skrup 5 Cm Kg 0.0500 18,600.00 930.00
JUMLAH HARGA BAHAN 13,240.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 46,990.50
E Overhead & profit 10% x Jumlah 4,699.05
F Harga Satuan Pekerjaan (D+E) 51,689.55

JENIS PEKERJAAN : A.4.4.3.64 Pemasangan 1 M2 Paving Block natural tebal 6 cm (Type Balok)
SATUAN : M2
HARGA SATUAN : Rp 416,004

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 112,275.00
B BAHAN `
Paving Block 6 cm m2 1.0100 220,500.00 222,705.00
Pasir Beton m3 0.0500 176,500.00 8,825.00
JUMLAH HARGA BAHAN 231,530.00
C PERALATAN
Peralatan % 10.0000 343,805.00 34,380.50
JUMLAH HARGA ALAT 34,380.50
D JUMLAH (A+B+C) 378,185.50
E Overhead & profit 10% x Jumlah 37,818.55
F Harga Satuan Pekerjaan (D+E) 416,004.05

JENIS PEKERJAAN : A.4.4.3.65 Pemasangan 1 M2 Paving Block natural tebal 8 cm (Type Balok)
SATUAN : M2
HARGA SATUAN : Rp 862,188

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.5000 105,000.00 52,500.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 138,525.00
B BAHAN `
Paving Block 8 cm m2 1.0100 354,760.00 358,307.60
Pasir Beton m3 2.0700 176,500.00 365,355.00
JUMLAH HARGA BAHAN 723,662.60
C PERALATAN
Peralatan % 10.0000
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 862,187.60
E Overhead & profit 10% x Jumlah -
F Harga Satuan Pekerjaan (D+E) 862,187.60

JENIS PEKERJAAN : A.4.4.3.66 Pemasangan 1 M2 Paving Block warna tebal 6 cm (Type I)


SATUAN : M2
HARGA SATUAN : Rp 459,743
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.5000 105,000.00 52,500.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 138,525.00
B BAHAN `
Paving Block 6 cm m2 1.0100 230,300.00 232,603.00
Pasir Beton Kg 0.0500 176,500.00 8,825.00
JUMLAH HARGA BAHAN 241,428.00
C PERALATAN
Peralatan % 10.0000 379,953.00 37,995.30
JUMLAH HARGA ALAT 37,995.30
D JUMLAH (A+B+C) 417,948.30
E Overhead & profit 10% x Jumlah 41,794.83
F Harga Satuan Pekerjaan (D+E) 459,743.13

JENIS PEKERJAAN : A.4.4.3.67 Pemasangan 1 M2 Paving Block warna tebal 8 cm (Type I)


SATUAN : M2
HARGA SATUAN : Rp 515,605

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.5000 105,000.00 52,500.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 138,525.00
B BAHAN `
Paving Block 8 cm m2 1.0100 276,010.00 278,770.10
Pasir Beton Kg 0.0500 176,500.00 8,825.00
JUMLAH HARGA BAHAN 287,595.10
C PERALATAN
Peralatan % 10.0000 426,120.10 42,612.01
JUMLAH HARGA ALAT 42,612.01
D JUMLAH (A+B+C) 468,732.11
E Overhead & profit 10% x Jumlah 46,873.21
F Harga Satuan Pekerjaan (D+E) 515,605.32

JENIS PEKERJAAN : A.4.4.3.68 Pemasangan 1 M2 Paving Block warna tebal 8 cm (Type Balok)
SATUAN : M2
HARGA SATUAN : Rp 650,530

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.5000 105,000.00 52,500.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 138,525.00
B BAHAN `
Paving Block 8 cm m2 1.0100 386,414.00 390,278.14
Pasir Beton Kg 0.0500 176,500.00 8,825.00
JUMLAH HARGA BAHAN 399,103.14
C PERALATAN
Peralatan % 10.0000 537,628.14 53,762.81
JUMLAH HARGA ALAT 53,762.81
D JUMLAH (A+B+C) 591,390.95
E Overhead & profit 10% x Jumlah 59,139.10
F Harga Satuan Pekerjaan (D+E) 650,530.05

HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

JENIS PEKERJAAN : A.4.5.1.1 Pemasangan 1 m2 langit-langit asbes semen, tebal 4 mm, 5 mm, dan 6 mm
SATUAN : M2
HARGA SATUAN : Rp 62,349

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0300 105,000.00 3,150.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 15,575.00
B BAHAN
Asbes semen m2 1.1000 37,200.00 40,920.00
Paku triplek Kg 0.0100 18,600.00 186.00
JUMLAH HARGA BAHAN 41,106.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 56,681.00
E Overhead & profit 10% x Jumlah 5,668.10
F Harga Satuan Pekerjaan (D+E) 62,349.10

JENIS PEKERJAAN : A.4.5.1.2 Pemasangan 1 m2 langit-langit akustik ukuran (30 x 30) Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1200 105,000.00 12,600.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 33,750.00
B BAHAN
Akustik Bh 12.0000 z #VALUE!
Paku triplek Kg 0.0500 18,600.00 930.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 15 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.1.3 Pemasangan 1 m2 langit-langit akustik ukuran (30 x 60) Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1200 105,000.00 12,600.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 33,750.00
B BAHAN
Akustik Bh 5.8000 z #VALUE!
Paku triplek Kg 0.0500 18,600.00 930.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 15 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.1.4 Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) Cm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 28,125.00
B BAHAN
Akustik Bh 1.5000 a #VALUE!
Paku triplek Kg 0.0500 18,600.00 930.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 15 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.1.5 Pemasangan 1 m2 langit-langit tripleks ukuran (120 x 240) Cm, tebal 3 mm, 4 m & 6 mm
SATUAN : M2
HARGA SATUAN : Rp 59,931

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 28,125.00
B BAHAN
Tripleks Lembar 0.3750 68,800.00 25,800.00
Paku triplek Kg 0.0300 18,600.00 558.00
JUMLAH HARGA BAHAN 26,358.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 54,483.00
E Overhead & profit 10% x Jumlah 5,448.30
F Harga Satuan Pekerjaan (D+E) 59,931.30

JENIS PEKERJAAN : A.4.5.1.6 Pemasangan 1 m2 langit-langit lambersering kayu, tebal 9 mm


SATUAN : M2
HARGA SATUAN : Rp 290,319

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.8000 105,000.00 84,000.00
Tukang L.02 OH 0.8000 150,000.00 120,000.00
Kepala tukang L.03 OH 0.0800 175,000.00 14,000.00
Mandor L.04 OH 0.0400 175,000.00 7,000.00
JUMLAH TENAGA KERJA 225,000.00
B BAHAN
Kayu papan m3 0.0150 2,582,700.00 38,740.50
Paku triplek Kg 0.0100 18,600.00 186.00
JUMLAH HARGA BAHAN 38,926.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 263,926.50
E Overhead & profit 10% x Jumlah 26,392.65
F Harga Satuan Pekerjaan (D+E) 290,319.15

JENIS PEKERJAAN : A.4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm, tebal 9 mm

SATUAN : M2
HARGA SATUAN : Rp 56,608

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 0.0500 150,000.00 7,500.00
Kepala tukang L.03 OH 0.0050 175,000.00 875.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 19,750.00
B BAHAN
Gypsum board Lembar 0.3640 81,500.00 29,666.00
Paku triplek Kg 0.1100 18,600.00 2,046.00
JUMLAH HARGA BAHAN 31,712.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 51,462.00
E Overhead & profit 10% x Jumlah 5,146.20
F Harga Satuan Pekerjaan (D+E) 56,608.20

JENIS PEKERJAAN : A.4.5.1.8 Pemasangan 1 m2 langit-langit akustik ukuran (60 x 120) Cm berikut rangka alluminium

SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.5000 105,000.00 52,500.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0250 175,000.00 4,375.00
JUMLAH TENAGA KERJA 140,625.00
B BAHAN
Profil Allum "T" m 3.6000 Err:509 Err:509
Kawat dia 4 mm Kg 0.1500 z #VALUE!
Ramset Bh 1.0500 Err:509 Err:509
Akustik 60 x 120 Lbr 1.5000 z #VALUE!
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 15 % x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.1.9 Pemasangan 1 M1 langit-langit kayu profil


SATUAN : M1
HARGA SATUAN : Rp 34,474

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0500 105,000.00 5,250.00
Tukang L.02 OH 0.0500 150,000.00 7,500.00
Kepala tukang L.03 OH 0.0050 175,000.00 875.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 14,150.00
B BAHAN
List Kayu Profil m 3.6000 4,000.00 14,400.00
Paku Kg 0.1500 18,600.00 2,790.00
JUMLAH HARGA BAHAN 17,190.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 31,340.00
E Overhead & profit 15 % x Jumlah 3,134.00
F Harga Satuan Pekerjaan (D+E) 34,474.00

JENIS PEKERJAAN : - Pekerjaan Pasangan Plafound Pvc ( JAVAPOND ) + Rangka Hollow Zinclaume4x4cm
SATUAN : M1
HARGA SATUAN : Rp 207,478

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 0.0500 150,000.00 7,500.00
Kepala tukang L.03 OH 0.0050 175,000.00 875.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 19,750.00
B BAHAN
Besi Hollow 40.20.2 M1 2.0000 6,000.00 12,000.00
Besi Hollow 20.20.2 M1 3.5000 6,000.00 21,000.00
Palafound PVC ( JavaFond) M1 5.0000 25,000.00 125,000.00
Sekrup Bh 0.2200 300.00 66.00
Joint Tape Roll 0.0500 16,000.00 800.00
Alat Bantu Ls 1.0000 10,000.00 10,000.00

-
JUMLAH HARGA BAHAN 168,866.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 188,616.00
E Overhead & profit 15 % x Jumlah 18,861.60
F Harga Satuan Pekerjaan (D+E) 207,477.60

JENIS PEKERJAAN : - Pekerjaan Pasangan Lest Pvc ( JAVAPOND ) Cutting L


SATUAN : M1
HARGA SATUAN : Rp 16,528

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
A TENAGA
Pekerja L.01 OH 0.0100 105,000.00 1,050.00
Tukang L.02 OH 0.0050 150,000.00 750.00
Kepala tukang L.03 OH 0.0010 175,000.00 175.00
Mandor L.04 OH 0.0010 175,000.00 175.00
JUMLAH TENAGA KERJA 2,150.00
B BAHAN
List PVC M1 1.0500 12,000.00 12,600.00
Sekrup Kg 0.0110 25,000.00 275.00

-
JUMLAH HARGA BAHAN 12,875.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 15,025.00
E Overhead & profit 15 % x Jumlah 1,502.50
F Harga Satuan Pekerjaan (D+E) 16,527.50

JENIS PEKERJAAN : A.4.5.2.0 Pemasangan 1 M2 Rangka Plafond Kayu


SATUAN : M2
HARGA SATUAN :

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang L.02 OH 0.3000 150,000.00 45,000.00
Kepala tukang L.03 OH 0.0300 105,000.00 3,150.00
Mandor L.04 OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 70,650.00
B BAHAN
Kayu balok Klas II M3 0.0160 3,029,100.00 48,465.60
Paku Kg 0.2500 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 15 % x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

HARGA SATUAN PEKERJAAN PENUTUP ATAP

JENIS PEKERJAAN : A.4.5.2.1 Pemasangan 1 m2 atap genteng palentong kecil


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.0750 150,000.00 11,250.00
Kepala tukang L.03 OH 0.0075 175,000.00 1,312.50
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 29,712.50
B BAHAN
Genteng palentong Bh 25.0000 z #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 15 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.2 Pemasangan 1 m2 atap genteng kodok glazuur


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.0750 150,000.00 11,250.00
Kepala tukang L.03 OH 0.0075 175,000.00 1,312.50
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 29,712.50
B BAHAN
Genteng kodok Bh 25.0000 z #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.3 Pemasangan 1 m2 atap genteng palentong besar/super


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.0750 150,000.00 11,250.00
Kepala tukang L.03 OH 0.0080 175,000.00 1,400.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 29,800.00
B BAHAN
Genteng kodok Bh 12.0000 z #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 15 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.4 Pemasangan 1 m2 bubung genteng palentong


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4000 105,000.00 42,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0020 175,000.00 350.00
JUMLAH TENAGA KERJA 75,850.00
B BAHAN
Genteng palentong Bh 5.0000 z #VALUE!
Semen Portland Kg 8.0000 1,240.00 9,920.00
Pasir Pasang m3 0.0320 176,600.00 5,651.20
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 15 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.5 Pemasangan 1 m2 bubung genteng kodok glazuur


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4000 105,000.00 42,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0020 175,000.00 350.00
JUMLAH TENAGA KERJA 75,850.00
B BAHAN
Genteng palentong Bh 5.0000 z #VALUE!
Semen Portland Kg 8.0000 1,240.00 9,920.00
Pasir Pasang m3 0.0320 176,600.00 5,651.20
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 15 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!
JENIS PEKERJAAN : A.4.5.2.6 Pemasangan 1 m2 bubung genteng palentong besar
SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4000 105,000.00 42,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0020 175,000.00 350.00
JUMLAH TENAGA KERJA 75,850.00
B BAHAN
Genteng palentong Bh 4.0000 z #VALUE!
Semen Portland Kg 8.0000 1,240.00 9,920.00
Pasir Pasang m3 0.0320 176,600.00 5,651.20
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 15 % x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.7 Pemasangan 1 m2 roof light fibreglass 90 x 180


SATUAN : M2
HARGA SATUAN : Rp 112,321

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0670 150,000.00 10,050.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,200.00
B BAHAN
Rooflight 90 x 180 Lbr 0.6000 123,300.00 73,980.00
Paku biasa 1/2" - 1" Kg 0.0500 18,600.00 930.00
JUMLAH HARGA BAHAN 74,910.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 102,110.00
E Overhead & profit 10% x Jumlah 10,211.00
F Harga Satuan Pekerjaan (D+E) 112,321.00

JENIS PEKERJAAN : A.4.5.2.8 Pemasangan 1 m2 atap asbes gelombang 0,92m x 2,5m x 5 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0750 150,000.00 11,250.00
Kepala tukang L.03 OH 0.0080 175,000.00 1,400.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 28,750.00
B BAHAN
Asbes gelombang 92 x 250 Lbr 0.5000 48,500.00 24,250.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 15% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.9 Pemasangan 1 m2 atap asbes gelombang 0,92m x 2,25m x 5 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0750 150,000.00 11,250.00
Kepala tukang L.03 OH 0.0080 175,000.00 1,400.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 28,750.00
B BAHAN
Asbes gelombang 95 x 250 Lbr 0.6000 48,500.00 29,100.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 15% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.10 Pemasangan 1 m2 atap asbes gelombang 0,92m x 2,00m x 5 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.6000 48,500.00 29,100.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 15% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.11 Pemasangan 1 m2 atap asbes gelombang 0,92m x 1,80m x 5 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.7500 48,500.00 36,375.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 15% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.12 Pemasangan 1 m2 atap asbes gelombang 1,05m x 3,00m x 4 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.3500 48,500.00 16,975.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.13 Pemasangan 1 m2 atap asbes gelombang 1,05m x 2,70m x 4 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.4200 48,500.00 20,370.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.14 Pemasangan 1 m2 atap asbes gelombang 1,05m x 2,40m x 4 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.4400 48,500.00 21,340.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.15 Pemasangan 1 m2 atap asbes gelombang 1,05m x 2,10m x 4 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.5100 48,500.00 24,735.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.16 Pemasangan 1 m2 atap asbes gelombang 1,05m x 1,50m x 4 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.8000 48,500.00 38,800.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.17 Pemasangan 1 m2 atap asbes gelombang 1,08m x 3,00m x 6 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.3700 48,500.00 17,945.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.18 Pemasangan 1 m2 atap asbes gelombang 1,08m x 2,70m x 6 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.3800 48,500.00 18,430.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.19 Pemasangan 1 m2 atap asbes gelombang 1,08m x 2,40m x 6 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.4600 48,500.00 22,310.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.20 Pemasangan 1 m2 atap asbes gelombang 1,08m x 2,10m x 6 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.4900 48,500.00 23,765.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.21 Pemasangan 1 m2 atap asbes gelombang 1,08m x 1,80m x 6 mm


SATUAN : M2
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Asbes gelombang Lbr 0.5700 48,500.00 27,645.00
Paku pancing 6 x 23 Kg 0.1200 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.22 Pemasangan 1 M1 bubung stel gelombang 0,92m


SATUAN : M1
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0840 105,000.00 8,820.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 30,545.00
B BAHAN
Bubung stel gel 0,92m Lbr 2.4000 26,200.00 62,880.00
Paku skrup 3,5" Bh 6.0000 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.23 Pemasangan 1 M1 bubung stel gelombang 1,05m


SATUAN : M1
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0840 105,000.00 8,820.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 30,545.00
B BAHAN
Bubung stel gel 0,92m Lbr 2.1000 26,200.00 55,020.00
Paku skrup 3,5" Bh 6.0000 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.24 Pemasangan 1 M1 bubung stel gelombang 1,08m


SATUAN : M1
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0840 105,000.00 8,820.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 30,545.00
B BAHAN
Bubung stel gel 0,92m Lbr 2.0500 26,200.00 53,710.00
Paku skrup 3,5" Bh 6.0000 Err:509 Err:509
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.5.2.25 Pemasangan 1 M1 nok paten 0,92m


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0840 105,000.00 8,820.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 30,545.00
B BAHAN
Nok paten 92 Cm Lbr 1.2000 a #VALUE!
Paku skrup 3,5" Bh 6.0000 Err:509 Err:509
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.26 Pemasangan 1 M1 nok paten 1,05m


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0840 105,000.00 8,820.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 30,545.00
B BAHAN
Nok paten 92 Cm Lbr 1.2000 z #VALUE!
Paku skrup 3,5" Bh 6.0000 Err:509 Err:509
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.27 Pemasangan 1 M1 nok paten 1,08m


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0840 105,000.00 8,820.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 30,545.00
B BAHAN
Nok paten 92 Cm Lbr 1.2000 z #VALUE!
Paku skrup 3,5" Bh 6.0000 Err:509 Err:509
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.28 Pemasangan 1 M1 nok stel rata 0,92m


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 35,975.00
B BAHAN
Nok paten 92 Cm Lbr 1.1000 z #VALUE!
Paku skrup 3,5" Bh 6.0000 Err:509 Err:509
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.29 Pemasangan 1 M1 nok stel rata 1,05m


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0840 105,000.00 8,820.00
Tukang L.02 OH 0.1250 150,000.00 18,750.00
Kepala tukang L.03 OH 0.0130 175,000.00 2,275.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 30,545.00
B BAHAN
Nok paten 92 Cm Lbr 1.1000 z #VALUE!
Paku skrup 3,5" Bh 6.0000 Err:509 Err:509
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.30 Pemasangan 1 m2 genteng beton


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0100 175,000.00 1,750.00
JUMLAH TENAGA KERJA 39,500.00
B BAHAN
Genteng beton Bh 11.0000 z #VALUE!
Paku biasa 2" - 5" Kg 0.0300 18,600.00 558.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.31 Pemasangan 1 m2 genteng aspal


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang L.02 OH 0.3000 150,000.00 45,000.00
Kepala tukang L.03 OH 0.0030 175,000.00 525.00
Mandor L.04 OH 0.0100 175,000.00 1,750.00
JUMLAH TENAGA KERJA 68,275.00
B BAHAN
Genteng Aspal lbr 6.9000 z #VALUE!
Plywood 6 mm Lbr 0.3500 z #VALUE!
Paku biasa 1/2" - 1" Kg 0.0300 18,600.00 558.00
Plastik aerator Bh 0.5000 z #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.32 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana
SATUAN : M2
HARGA SATUAN : Rp 128,035

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0010 175,000.00 175.00
JUMLAH TENAGA KERJA 37,925.00
B BAHAN
Genteng metal bh 1.3000 57,500.00 74,750.00
Paku Biasa 1/2" - 1" Kg 0.2000 18,600.00 3,720.00
JUMLAH HARGA BAHAN 78,470.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 116,395.00
E Overhead & profit 10% x Jumlah 11,639.50
F Harga Satuan Pekerjaan (D+E) 128,034.50

JENIS PEKERJAAN : A.4.5.2.33 Pemasangan 1 m2 UPVC


SATUAN : M2
HARGA SATUAN : Rp 444,868

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0010 175,000.00 175.00
JUMLAH TENAGA KERJA 37,925.00
B BAHAN
Atap UVPC m2 1.1000 325,000.00 357,500.00
Self Drilling Screw pcs 9.0000 1,000.00 9,000.00
JUMLAH HARGA BAHAN 366,500.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 404,425.00
E Overhead & profit 10% x Jumlah 40,442.50
F Harga Satuan Pekerjaan (D+E) 444,867.50

JENIS PEKERJAAN : A.4.5.2.33 Pemasangan 1 m2 Rangka Atap BaJa Ringan


SATUAN : M2
HARGA SATUAN : Rp 212,060

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2100 105,000.00 22,050.00
Tukang L.02 OH 0.1760 150,000.00 26,400.00
Kepala tukang L.03 OH 0.1170 175,000.00 20,475.00
Mandor L.04 OH 0.1170 175,000.00 20,475.00
JUMLAH TENAGA KERJA 89,400.00
B BAHAN
Main Truss Canal m1 2.5000 12,500.00 31,250.00
Roof Botton/Reng m1 5.1000 7,500.00 38,250.00
Self Drilling Screw dia. 6x20 mm (Truss) pcs 25.0000 400.00 10,000.00
Self Drilling Screw dia. 4x16 mm (Truss) pcs 35.0000 400.00 14,000.00
Dynabolt pcs 1.0000 1,500.00 1,500.00

JUMLAH HARGA BAHAN 95,000.00


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 184,400.00
E Overhead & profit 10% x Jumlah 27,660.00
F Harga Satuan Pekerjaan (D+E) 212,060.00

JENIS PEKERJAAN : A.4.5.2.34 Pemasangan 1 m2 atap sirap kayu


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.1660 105,000.00 17,430.00
Tukang L.02 OH 0.2500 150,000.00 37,500.00
Kepala tukang L.03 OH 0.0250 175,000.00 4,375.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 60,705.00
B BAHAN
Sirap kayu Bh 30.0000 z #VALUE!
Paku Kg 0.2000 18,600.00 3,720.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.35 Pemasangan 1 M1 nok genteng beton


SATUAN : M1
HARGA SATUAN : #VALUE!
NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
SATUAN

A TENAGA
Pekerja L.01 OH 0.4000 105,000.00 42,000.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0200 175,000.00 3,500.00
JUMLAH TENAGA KERJA 79,000.00
B BAHAN
Nok genteng beton Bh 3.5000 z #VALUE!
Paku biasa 1/2" - 1" Kg 0.0500 18,600.00 930.00
Semen Portland Kg 10.8000 1,240.00 13,392.00
Semen warna (tepung affa) m3 0.0320 15,400.00 492.80
Pasir Pasang Kg 1.0000 176,600.00 176,600.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.36 Pemasangan 1 M1 nok genteng aspal


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.1250 105,000.00 13,125.00
Tukang L.02 OH 0.2500 150,000.00 37,500.00
Kepala tukang L.03 OH 0.0250 175,000.00 4,375.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 56,050.00
B BAHAN
Nok genteng aspal Bh 2.0000 z #VALUE!
Paku biasa 1/2" - 1" Kg 0.0500 18,600.00 930.00
Kayu balok borneo m3 0.0035 4,035,700.00 14,124.95
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.37 Pemasangan 1 M1 nok genteng metal


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0130 175,000.00 2,275.00
JUMLAH TENAGA KERJA 53,650.00
B BAHAN
Nok genteng metal Bh 1.1000 z #VALUE!
Paku biasa 1/2" - 1" Kg 0.0500 18,600.00 930.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.38 Pemasangan 1 M1 nok sirap


SATUAN : M1
HARGA SATUAN : Rp 81,257

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.1250 105,000.00 13,125.00
Tukang L.02 OH 0.2500 150,000.00 37,500.00
Kepala tukang L.03 OH 0.0250 175,000.00 4,375.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 56,050.00
B BAHAN
Seng plat 3 x 6" Lbr 0.4000 39,900.00 15,960.00
Paku biasa 1/2" - 1" Kg 0.0500 18,600.00 930.00
Paku biasa 2" - 5" Kg 0.0500 18,600.00 930.00
JUMLAH HARGA BAHAN 17,820.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 73,870.00
E Overhead & profit 10% x Jumlah 7,387.00
F Harga Satuan Pekerjaan (D+E) 81,257.00

JENIS PEKERJAAN : A.4.5.2.39 Pemasangan 1 m2 atap seng gelombang


SATUAN : M2
HARGA SATUAN : Rp 68,983

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1200 105,000.00 12,600.00
Tukang L.02 OH 0.0600 150,000.00 9,000.00
Kepala tukang L.03 OH 0.0060 175,000.00 1,050.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 23,700.00
B BAHAN
Seng gel 3" x 6" Lbr 0.7000 55,200.00 38,640.00
Paku biasa 1/2" - 1" Kg 0.0200 18,600.00 372.00
JUMLAH HARGA BAHAN 39,012.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 62,712.00
E Overhead & profit 10% x Jumlah 6,271.20
F Harga Satuan Pekerjaan (D+E) 68,983.20

JENIS PEKERJAAN : A.4.5.2.40 Pemasangan 1 M1 nok atap seng


SATUAN : M1
HARGA SATUAN : Rp 45,363

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 28,525.00
B BAHAN
Seng gel 3" x 6" bjls 28 Lbr 0.3000 39,900.00 11,970.00
Paku biasa 1/2" - 1" Kg 0.0400 18,600.00 744.00
JUMLAH HARGA BAHAN 12,714.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 41,239.00
E Overhead & profit 10% x Jumlah 4,123.90
F Harga Satuan Pekerjaan (D+E) 45,362.90

JENIS PEKERJAAN : A.4.5.2.41 Pemasangan 1 m2 atap alluminium


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.7500 150,000.00 112,500.00
Kepala tukang L.03 OH 0.0800 175,000.00 14,000.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 143,300.00
B BAHAN
Alluminium gel tbl 0,55 Lbr 1.0500 z #VALUE!
Paku hak panj 15 Cm Kg 0.0200 18,600.00 372.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.42 Pemasangan 1 M1 nok aluminium


SATUAN : M1
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 1.0000 150,000.00 150,000.00
Kepala tukang L.03 OH 0.1000 175,000.00 17,500.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 186,750.00
B BAHAN
Nok atap seng Lbr 1.2000 a #VALUE!
Paku hak panj 15 Cm Kg 0.0400 18,600.00 744.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.5.2.43 Pemasangan 1 m2 alluminium foil/sisalation


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.0500 150,000.00 7,500.00
Kepala tukang L.03 OH 0.0050 175,000.00 875.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 25,525.00
B BAHAN
Alluminium foil m2 1.0500 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

HARGA SATUAN PEKERJAAN KAYU

JENIS PEKERJAAN : A.4.6.1.1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kls I
SATUAN : M3
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 7.0000 105,000.00 735,000.00
Tukang L.02 OH 21.0000 150,000.00 3,150,000.00
Kepala tukang L.03 OH 2.1000 175,000.00 367,500.00
Mandor L.04 OH 0.3500 175,000.00 61,250.00
JUMLAH TENAGA KERJA 4,313,750.00
B BAHAN
Balok kayu m3 1.1000 4,035,700.00 4,439,270.00
Paku 10 Cm Kg 1.2500 Err:509 Err:509
Lem kayu Kg 1.0000 18,800.00 18,800.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.6.1.2 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
SATUAN : M3
HARGA SATUAN : Rp 8,111,917

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 6.0000 105,000.00 630,000.00
Tukang L.02 OH 18.0000 150,000.00 2,700,000.00
Kepala tukang L.03 OH 1.8000 175,000.00 315,000.00
Mandor L.04 OH 0.3000 175,000.00 52,500.00
JUMLAH TENAGA KERJA 3,697,500.00
B BAHAN
Balok kayu m3 1.2000 3,029,100.00 3,634,920.00
Paku 10 Cm Kg 1.2500 18,600.00 23,250.00
Lem kayu Kg 1.0000 18,800.00 18,800.00
JUMLAH HARGA BAHAN 3,676,970.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 7,374,470.00
E Overhead & profit 10% x Jumlah 737,447.00
F Harga Satuan Pekerjaan (D+E) 8,111,917.00

JENIS PEKERJAAN : A.4.6.1.3 Pembuatan dan pemasangan 1 m2 kusen klamp standar, kayu kelas II
SATUAN : M2
HARGA SATUAN : Rp 376,091

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3500 105,000.00 36,750.00
Tukang L.02 OH 1.0500 150,000.00 157,500.00
Kepala tukang L.03 OH 0.1050 175,000.00 18,375.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 215,775.00
B BAHAN
Papan kayu m3 0.0400 3,129,900.00 125,196.00
Paku 5 - 7 Cm Kg 0.0500 18,600.00 930.00
JUMLAH HARGA BAHAN 126,126.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 341,901.00
E Overhead & profit 10% x Jumlah 34,190.10
F Harga Satuan Pekerjaan (D+E) 376,091.10

JENIS PEKERJAAN : A.4.6.1.4 Pembuatan dan pemasangan 1 m2 kusen klamp sederhana, kayu kelas III
SATUAN : M2
HARGA SATUAN : Rp 352,014

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3500 105,000.00 36,750.00
Tukang L.02 OH 1.0500 150,000.00 157,500.00
Kepala tukang L.03 OH 0.1050 175,000.00 18,375.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 215,775.00
B BAHAN
Papan kayu m3 0.0400 2,582,700.00 103,308.00
Paku 5 - 7 Cm Kg 0.0500 18,600.00 930.00
JUMLAH HARGA BAHAN 104,238.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 320,013.00
E Overhead & profit 10% x Jumlah 32,001.30
F Harga Satuan Pekerjaan (D+E) 352,014.30

JENIS PEKERJAAN : A.4.6.1.5 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II
SATUAN : M2
HARGA SATUAN : Rp 816,625
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang L.02 OH 3.0000 150,000.00 450,000.00
Kepala tukang L.03 OH 0.3000 175,000.00 52,500.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 616,250.00
B BAHAN
Papan kayu m3 0.0400 3,129,900.00 125,196.00
Lem kayu Kg 0.0500 18,800.00 940.00
JUMLAH HARGA BAHAN 126,136.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 742,386.00
E Overhead & profit 10% x Jumlah 74,238.60
F Harga Satuan Pekerjaan (D+E) 816,624.60

JENIS PEKERJAAN : A.4.6.1.6 Pembuatan dan Pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I dan II
SATUAN : M2
HARGA SATUAN : Rp 681,050

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.8000 105,000.00 84,000.00
Tukang L.02 OH 2.4000 150,000.00 360,000.00
Kepala tukang L.03 OH 0.2400 175,000.00 42,000.00
Mandor L.04 OH 0.0400 175,000.00 7,000.00
JUMLAH TENAGA KERJA 493,000.00
B BAHAN
Papan kayu m3 0.0400 3,129,900.00 125,196.00
Lem kayu Kg 0.0500 18,800.00 940.00
JUMLAH HARGA BAHAN 126,136.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 619,136.00
E Overhead & profit 10% x Jumlah 61,913.60
F Harga Satuan Pekerjaan (D+E) 681,049.60

JENIS PEKERJAAN : A.4.6.1.7 Pembuatan dan pemasangan 1 m2 pintu dan jendela jalusi kayu kelas I atau II
SATUAN : M2
HARGA SATUAN : Rp 908,560

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang L.02 OH 3.0000 150,000.00 450,000.00
Kepala tukang L.03 OH 0.3000 175,000.00 52,500.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 616,250.00
B BAHAN
Papan kayu m3 0.0640 3,129,900.00 200,313.60
Lem kayu Kg 0.5000 18,800.00 9,400.00
JUMLAH HARGA BAHAN 209,713.60
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 825,963.60
E Overhead & profit 10% x Jumlah 82,596.36
F Harga Satuan Pekerjaan (D+E) 908,559.96

JENIS PEKERJAAN : A.4.6.1.8 Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar sampai 90 Cm)

SATUAN : M2
HARGA SATUAN : Rp 663,609

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.7000 105,000.00 73,500.00
Tukang L.02 OH 2.1000 150,000.00 315,000.00
Kepala tukang L.03 OH 0.2100 175,000.00 36,750.00
Mandor L.04 OH 0.0350 175,000.00 6,125.00
JUMLAH TENAGA KERJA 431,375.00
B BAHAN
Papan kayu m3 0.0250 3,129,900.00 78,247.50
Paku 1 Cm - 2,5 Cm Kg 0.0300 18,600.00 558.00
Lem kayu Kg 0.5000 18,800.00 9,400.00
plywood tebal 4 mm uk 90x220 Cm Lbr 1.0000 83,700.00 83,700.00
JUMLAH HARGA BAHAN 171,905.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 603,280.50
E Overhead & profit 10% x Jumlah 60,328.05
F Harga Satuan Pekerjaan (D+E) 663,608.55

JENIS PEKERJAAN : A.4.6.1.9 Pembuatan 1 m2 pintu plywood rangkap, rangka expose kayu kelas I atau II
SATUAN : M2
HARGA SATUAN : Rp 733,462

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.8000 105,000.00 84,000.00
Tukang L.02 OH 2.4000 150,000.00 360,000.00
Kepala tukang L.03 OH 0.2400 175,000.00 42,000.00
Mandor L.04 OH 0.0400 175,000.00 7,000.00
JUMLAH TENAGA KERJA 493,000.00
B BAHAN
Papan kayu m3 0.0256 3,129,900.00 80,125.44
Paku 1 Cm - 2,5 Cm Kg 0.0300 18,600.00 558.00
Lem kayu Kg 0.5000 18,800.00 9,400.00
plywood tebal 4 mm uk 90x220 Cm Lbr 1.0000 83,700.00 83,700.00
JUMLAH HARGA BAHAN 173,783.44
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 666,783.44
E Overhead & profit 10% x Jumlah 66,678.34
F Harga Satuan Pekerjaan (D+E) 733,461.78

JENIS PEKERJAAN : A.4.6.1.10 Pemasangan 1 m2 jalusi kusen, kayu kelas I atau II


SATUAN : M2
HARGA SATUAN : Rp 720,015

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6700 105,000.00 70,350.00
Tukang L.02 OH 2.0000 150,000.00 300,000.00
Kepala tukang L.03 OH 0.2000 175,000.00 35,000.00
Mandor L.04 OH 0.3350 175,000.00 58,625.00
JUMLAH TENAGA KERJA 463,975.00
B BAHAN
Papan kayu m3 0.0600 3,129,900.00 187,794.00
Paku 1 Cm - 2,5 Cm Kg 0.1500 18,600.00 2,790.00
JUMLAH HARGA BAHAN 190,584.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 654,559.00
E Overhead & profit 10% x Jumlah 65,455.90
F Harga Satuan Pekerjaan (D+E) 720,014.90

JENIS PEKERJAAN : A.4.6.1.11 Pemasangan 1 m2 teakwood rangkap, rangka expose kayu kelas I
SATUAN : M2
HARGA SATUAN : Rp 754,034

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.8000 105,000.00 84,000.00
Tukang L.02 OH 2.4000 150,000.00 360,000.00
Kepala tukang L.03 OH 0.2400 175,000.00 42,000.00
Mandor L.04 OH 0.0400 175,000.00 7,000.00
JUMLAH TENAGA KERJA 493,000.00
B BAHAN
Papan kayu m3 0.0250 4,103,500.00 102,587.50
Paku 1 Cm - 2,5 Cm Kg 0.0300 18,600.00 558.00
Lem kayu Kg 0.3000 18,800.00 5,640.00
Teakwood 4 mm 90x220 Cm Lbr 1.0000 83,700.00 83,700.00
JUMLAH HARGA BAHAN 192,485.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 685,485.50
E Overhead & profit 10% x Jumlah 68,548.55
F Harga Satuan Pekerjaan (D+E) 754,034.05

JENIS PEKERJAAN : A.4.6.1.12 Pemasangan 1 m2 teakwood rangkap lapis formika, rangka expose kayu kls II
SATUAN : M2
HARGA SATUAN : Rp 829,725

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.8500 105,000.00 89,250.00
Tukang L.02 OH 2.5500 150,000.00 382,500.00
Kepala tukang L.03 OH 0.2550 175,000.00 44,625.00
Mandor L.04 OH 0.0430 175,000.00 7,525.00
JUMLAH TENAGA KERJA 523,900.00
B BAHAN
Papan kayu m3 0.0250 3,129,900.00 78,247.50
Paku 1 Cm - 2,5 Cm Kg 0.0300 18,600.00 558.00
Lem kayu Kg 0.8000 18,800.00 15,040.00
Teakwood 4 mm 90x220 Cm Lbr 1.0000 83,700.00 83,700.00
Formika Lbr 0.5000 105,700.00 52,850.00
JUMLAH HARGA BAHAN 230,395.50
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 754,295.50
E Overhead & profit 10% x Jumlah 75,429.55
F Harga Satuan Pekerjaan (D+E) 829,725.05

JENIS PEKERJAAN : A.4.6.1.13 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kls I, II dan III
SATUAN : M3
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 4.0000 105,000.00 420,000.00
Tukang L.02 OH 12.0000 150,000.00 1,800,000.00
Kepala tukang L.03 OH 1.2000 175,000.00 210,000.00
Mandor L.04 OH 0.2000 175,000.00 35,000.00
JUMLAH TENAGA KERJA 2,465,000.00
B BAHAN
Balok kayu m3 1.1000 3,029,100.00 3,332,010.00
Besi strip tebal 5 mm Kg 15.0000 Err:509 Err:509
Paku 12 Cm Kg 5.6000 18,600.00 104,160.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.6.1.14 Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas I


SATUAN : M3
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 6.7000 105,000.00 703,500.00
Tukang L.02 OH 20.1000 150,000.00 3,015,000.00
Kepala tukang L.03 OH 2.0100 175,000.00 351,750.00
Mandor L.04 OH 0.3350 175,000.00 58,625.00
JUMLAH TENAGA KERJA 4,128,875.00
B BAHAN
Balok kayu m3 1.2000 4,035,700.00 4,842,840.00
Besi strip tebal 5 mm Kg 15.0000 Err:509 Err:509
Paku 12 Cm Kg 5.6000 18,600.00 104,160.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.6.1.15 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II


SATUAN : M3
HARGA SATUAN : Err:509

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 6.7000 105,000.00 703,500.00
Tukang L.02 OH 20.1000 150,000.00 3,015,000.00
Kepala tukang L.03 OH 2.0100 175,000.00 351,750.00
Mandor L.04 OH 0.3350 175,000.00 58,625.00
JUMLAH TENAGA KERJA 4,128,875.00
B BAHAN
Balok kayu m3 1.1000 3,029,100.00 3,332,010.00
Besi strip tebal 5 mm Kg 15.0000 Err:509 Err:509
Paku 12 Cm Kg 3.0000 18,600.00 55,800.00
JUMLAH HARGA BAHAN Err:509
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) Err:509
E Overhead & profit 10% x Jumlah Err:509
F Harga Satuan Pekerjaan (D+E) Err:509

JENIS PEKERJAAN : A.4.6.1.16 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II
SATUAN : M2
HARGA SATUAN : Rp 202,653

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 28,125.00
B BAHAN
Kaso-kaso 5 x 7 Cm m3 0.0140 3,029,100.00 42,407.40
Reng 2 x 3 Cm m3 0.0360 3,029,100.00 109,047.60
Paku 5 dan 10 Cm Kg 0.2500 18,600.00 4,650.00
JUMLAH HARGA BAHAN 156,105.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 184,230.00
E Overhead & profit 10% x Jumlah 18,423.00
F Harga Satuan Pekerjaan (D+E) 202,653.00

JENIS PEKERJAAN : A.4.6.1.17 Pemasangan 1 m2 rangka atap genteng beton, kayu kelas II
SATUAN : M2
HARGA SATUAN : Rp 272,625

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 28,125.00
B BAHAN
Kaso-kaso 5 x 7 Cm m3 0.0140 3,029,100.00 42,407.40
Reng 2 x 3 Cm m3 0.0570 3,029,100.00 172,658.70
Paku 5 dan 10 Cm Kg 0.2500 18,600.00 4,650.00
JUMLAH HARGA BAHAN 219,716.10
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 247,841.10
E Overhead & profit 10% x Jumlah 24,784.11
F Harga Satuan Pekerjaan (D+E) 272,625.21

JENIS PEKERJAAN : A.4.6.1.18 Pemasangan 1 m2 rangka atap sirap, kayu kelas II


SATUAN : M2
HARGA SATUAN : Rp 84,939

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1200 105,000.00 12,600.00
Tukang L.02 OH 0.1200 150,000.00 18,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 33,750.00
B BAHAN
Kayu kelas II m3 0.0140 3,029,100.00 42,407.40
Paku 5 dan 10 Cm Kg 0.0570 18,600.00 1,060.20
JUMLAH HARGA BAHAN 43,467.60
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 77,217.60
E Overhead & profit 10% x Jumlah 7,721.76
F Harga Satuan Pekerjaan (D+E) 84,939.36

JENIS PEKERJAAN : A.4.6.1.19 Pemasangan 1 m2 rangka langit-langit (50 x 100) Cm, kayu kelas II atau III
SATUAN : M2
HARGA SATUAN : Rp 142,442

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.3000 150,000.00 45,000.00
Kepala tukang L.03 OH 0.0300 175,000.00 5,250.00
Mandor L.04 OH 0.0750 175,000.00 13,125.00
JUMLAH TENAGA KERJA 79,125.00
B BAHAN
Kaso-kaso 5 x 7 Cm m3 0.0154 3,029,100.00 46,648.14
Paku 7 dan 10 Cm Kg 0.2000 18,600.00 3,720.00
JUMLAH HARGA BAHAN 50,368.14
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 129,493.14
E Overhead & profit 10% x Jumlah 12,949.31
F Harga Satuan Pekerjaan (D+E) 142,442.45

JENIS PEKERJAAN : A.4.6.1.20 Pemasangan 1 m2 rangka langit-langit (60 x 60) Cm, kayu kelas II atau III
SATUAN : M2
HARGA SATUAN : Rp 139,727

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang L.02 OH 0.3000 150,000.00 45,000.00
Kepala tukang L.03 OH 0.0300 175,000.00 5,250.00
Mandor L.04 OH 0.0100 175,000.00 1,750.00
JUMLAH TENAGA KERJA 73,000.00
B BAHAN
Kaso-kaso 5 x 7 Cm m3 0.0163 3,029,100.00 49,374.33
Paku 7 dan 10 Cm Kg 0.2500 18,600.00 4,650.00
JUMLAH HARGA BAHAN 54,024.33
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 127,024.33
E Overhead & profit 10% x Jumlah 12,702.43
F Harga Satuan Pekerjaan (D+E) 139,726.76

JENIS PEKERJAAN : A.4.6.1.21 Pemasangan 1 m2 rangka langit-langit (3 x 20) Cm, kayu kelas II atau III
SATUAN : M2
HARGA SATUAN : Rp 82,091

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 44,875.00
B BAHAN
Papan kayu m3 0.0108 2,582,700.00 27,893.16
Paku 7 dan 10 Cm Kg 0.1000 18,600.00 1,860.00
JUMLAH HARGA BAHAN 29,753.16
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 74,628.16
E Overhead & profit 10% x Jumlah 7,462.82
F Harga Satuan Pekerjaan (D+E) 82,090.98

JENIS PEKERJAAN : A.4.6.1.22 Pemasangan 1 M1 liPClank GRC


SATUAN : M1
HARGA SATUAN : Rp 86,686

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 44,875.00
B BAHAN
lisplang GRC M1 1.1000 30,000.00 33,000.00
Paku 5 dan 10 Cm Kg 0.0500 18,600.00 930.00
JUMLAH HARGA BAHAN 33,930.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 78,805.00
E Overhead & profit 10% x Jumlah 7,880.50
F Harga Satuan Pekerjaan (D+E) 86,685.50

JENIS PEKERJAAN : A.4.6.1.23 Pemasangan 1 m2 rangka dinding pemisah (60 x 120) Cm, kayu kelas II atau III
SATUAN : M2
HARGA SATUAN : Rp 180,199

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 92,525.00
B BAHAN
Balok kayu m3 0.0280 2,446,500.00 68,502.00
Paku 5 dan 10 Cm Kg 0.1500 18,600.00 2,790.00
JUMLAH HARGA BAHAN 71,292.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 163,817.00
E Overhead & profit 10% x Jumlah 16,381.70
F Harga Satuan Pekerjaan (D+E) 180,198.70

JENIS PEKERJAAN : A.4.6.1.24 Pemasangan 1 m2 dinding pemisah teakwood rangkap, rangka kayu kelas II
SATUAN : M2
HARGA SATUAN : Rp 192,539

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 92,525.00
B BAHAN
Balok kayu 6 x 12 m3 0.0280 3,029,100.00 84,814.80
Paku 5 dan 10 Cm Kg 0.1500 18,600.00 2,790.00
Teakwood 4 mm, 120x240 Lbr 0.8600 83,700.00 71,982.00
Lem kayu Kg 0.5600 18,800.00 10,528.00
JUMLAH HARGA BAHAN 82,510.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 175,035.00
E Overhead & profit 10% x Jumlah 17,503.50
F Harga Satuan Pekerjaan (D+E) 192,538.50

JENIS PEKERJAAN : A.4.6.1.25 Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II
SATUAN : M2
HARGA SATUAN : Rp 226,336

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2000 105,000.00 21,000.00
Tukang L.02 OH 0.6000 150,000.00 90,000.00
Kepala tukang L.03 OH 0.0600 175,000.00 10,500.00
Mandor L.04 OH 0.0100 175,000.00 1,750.00
JUMLAH TENAGA KERJA 123,250.00
B BAHAN
Balok kayu 6 x 12 m3 0.0280 3,029,100.00 84,814.80
Paku 5 dan 10 Cm Kg 0.1500 18,600.00 2,790.00
Plywood 4 mm, 120x240 Lbr 0.8600 83,700.00 71,982.00
Lem kayu Kg 0.5600 18,800.00 10,528.00
JUMLAH HARGA BAHAN 82,510.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 205,760.00
E Overhead & profit 10% x Jumlah 20,576.00
F Harga Satuan Pekerjaan (D+E) 226,336.00

JENIS PEKERJAAN : A.4.6.1.26 Pemasangan 1 m2 dinding lambrisering dari papan kayu kelas I
SATUAN : M2
HARGA SATUAN : Rp 409,794

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6000 105,000.00 63,000.00
Tukang L.02 OH 1.8000 150,000.00 270,000.00
Kepala tukang L.03 OH 0.1800 175,000.00 31,500.00
Mandor L.04 OH 0.0300 175,000.00 5,250.00
JUMLAH TENAGA KERJA 369,750.00
B BAHAN
Papan kayu m3 0.0070 4,103,500.00 28,724.50
Paku 5 dan 10 Cm Kg 0.1000 18,600.00 1,860.00
Paku skrup 10 Cm Kg 0.1500 18,600.00 2,790.00
JUMLAH HARGA BAHAN 2,790.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 372,540.00
E Overhead & profit 10% x Jumlah 37,254.00
F Harga Satuan Pekerjaan (D+E) 409,794.00

JENIS PEKERJAAN : A.4.6.1.27 Pemasangan 1 m2 dinding lambrisering dari plywood ukuran (120x240) Cm
SATUAN : M2
HARGA SATUAN : Rp 54,846

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0250 105,000.00 2,625.00
Tukang L.02 OH 0.0750 150,000.00 11,250.00
Kepala tukang L.03 OH 0.0080 175,000.00 1,400.00
Mandor L.04 OH 0.0010 175,000.00 175.00
JUMLAH TENAGA KERJA 15,450.00
B BAHAN
Plywood 4 mm m3 0.4000 83,700.00 33,480.00
Paku 5 dan 10 Cm Kg 0.0500 18,600.00 930.00
JUMLAH HARGA BAHAN 34,410.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 49,860.00
E Overhead & profit 10% x Jumlah 4,986.00
F Harga Satuan Pekerjaan (D+E) 54,846.00

JENIS PEKERJAAN : A.4.6.1.28 Pemasangan 1 m2 dinding bilik, rangka kayu kelas III atau IV
SATUAN : M2
HARGA SATUAN : Rp 96,682

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 0.0500 150,000.00 7,500.00
Kepala tukang L.03 OH 0.0050 175,000.00 875.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 19,750.00
B BAHAN
Bilik bambu m2 1.5000 17,000.00 25,500.00
Kaso-kaso 5 x 7 m3 0.0140 3,029,100.00 42,407.40
Paku Kg 0.0120 18,600.00 223.20
List kayu 2/4 m3 0.0030 4,000.00 12.00
JUMLAH HARGA BAHAN 68,142.60
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 87,892.60
E Overhead & profit 10% x Jumlah 8,789.26
F Harga Satuan Pekerjaan (D+E) 96,681.86

HARGA SATUAN PEKERJAAN KUNCI DAN KACA

JENIS PEKERJAAN : A.4.6.2.1 Pemasangan 1 buah kunci tanam antik


SATUAN : Bh
HARGA SATUAN : Rp 419,678

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0600 105,000.00 6,300.00
Tukang L.02 OH 0.6000 150,000.00 90,000.00
Kepala tukang L.03 OH 0.0600 175,000.00 10,500.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 107,325.00
B BAHAN
Kunci tanam antik set 1.0000 274,200.00 274,200.00
JUMLAH HARGA BAHAN 274,200.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 381,525.00
E Overhead & profit 10% x Jumlah 38,152.50
F Harga Satuan Pekerjaan (D+E) 419,677.50
JENIS PEKERJAAN : A.4.6.2.2 Pemasangan 1 buah kunci tanam biasa
SATUAN : Bh
HARGA SATUAN : Rp 195,113

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0100 105,000.00 1,050.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 85,675.00
B BAHAN
Kunci tanam biasa Bh 1.0000 91,700.00 91,700.00
JUMLAH HARGA BAHAN 91,700.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 177,375.00
E Overhead & profit 10% x Jumlah 17,737.50
F Harga Satuan Pekerjaan (D+E) 195,112.50

JENIS PEKERJAAN : A.4.6.2.3 Pemasangan 1 buah kunci kamar mandi


SATUAN : Bh
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0050 105,000.00 525.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 84,800.00
B BAHAN
Kunci tanam KM Bh 1.0000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.6.2.4 Pemasangan 1 buah kunci silinder


SATUAN : Bh
HARGA SATUAN : Rp 186,780

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0050 105,000.00 525.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 84,800.00
B BAHAN
Kunci silinder Bh 1.0000 85,000.00 85,000.00
JUMLAH HARGA BAHAN 85,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 169,800.00
E Overhead & profit 10% x Jumlah 16,980.00
F Harga Satuan Pekerjaan (D+E) 186,780.00

JENIS PEKERJAAN : A.4.6.2.5 Pemasangan 1 buah engsel pintu


SATUAN : Bh
HARGA SATUAN : Rp 54,384

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0150 105,000.00 1,575.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0008 175,000.00 140.00
JUMLAH TENAGA KERJA 26,840.00
B BAHAN
Engsel pintu Bh 1.0000 22,600.00 22,600.00
JUMLAH HARGA BAHAN 22,600.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 49,440.00
E Overhead & profit 10% x Jumlah 4,944.00
F Harga Satuan Pekerjaan (D+E) 54,384.00

JENIS PEKERJAAN : A.4.6.2.6 Pemasangan 1 buah engsel jendela kupu-kupu


SATUAN : Bh
HARGA SATUAN : Rp 36,066

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0100 105,000.00 1,050.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0005 175,000.00 87.50
JUMLAH TENAGA KERJA 17,887.50
B BAHAN
Engsel kupu-kupu Bh 1.0000 14,900.00 14,900.00
JUMLAH HARGA BAHAN 14,900.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 32,787.50
E Overhead & profit 10% x Jumlah 3,278.75
F Harga Satuan Pekerjaan (D+E) 36,066.25

JENIS PEKERJAAN : A.4.6.2.7 Pemasangan 1 buah engsel angin


SATUAN : Bh
HARGA SATUAN : Rp 64,886

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0005 175,000.00 87.50
JUMLAH TENAGA KERJA 44,087.50
B BAHAN
Engsel angin Bh 1.0000 14,900.00 14,900.00
JUMLAH HARGA BAHAN 14,900.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 58,987.50
E Overhead & profit 10% x Jumlah 5,898.75
F Harga Satuan Pekerjaan (D+E) 64,886.25

JENIS PEKERJAAN : A.4.6.2.8 Pemasangan 1 buah Spring Knip


SATUAN : Bh
HARGA SATUAN : Rp 102,410

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0150 105,000.00 1,575.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 28,100.00
B BAHAN
Spring knip Bh 1.0000 65,000.00 65,000.00
JUMLAH HARGA BAHAN 65,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 93,100.00
E Overhead & profit 10% x Jumlah 9,310.00
F Harga Satuan Pekerjaan (D+E) 102,410.00

JENIS PEKERJAAN : A.4.6.2.9 Pemasangan 1 buah kait angin


SATUAN : Bh
HARGA SATUAN : Rp 47,630

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0150 105,000.00 1,575.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 28,100.00
B BAHAN
Kait angin Bh 1.0000 15,200.00 15,200.00
JUMLAH HARGA BAHAN 15,200.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 43,300.00
E Overhead & profit 10% x Jumlah 4,330.00
F Harga Satuan Pekerjaan (D+E) 47,630.00

JENIS PEKERJAAN : A.4.6.2.10 Pemasangan 1 buah door closer


SATUAN : Bh
HARGA SATUAN : Rp 345,978

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0500 105,000.00 5,250.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 89,525.00
B BAHAN
Door closer Bh 1.0000 225,000.00 225,000.00
JUMLAH HARGA BAHAN 225,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 314,525.00
E Overhead & profit 10% x Jumlah 31,452.50
F Harga Satuan Pekerjaan (D+E) 345,977.50

JENIS PEKERJAAN : A.4.6.2.11 Pemasangan 1 buah kunci slot


SATUAN : Bh
HARGA SATUAN : Rp 140,223

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0200 105,000.00 2,100.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0010 175,000.00 175.00
JUMLAH TENAGA KERJA 35,775.00
B BAHAN
Kunci slot Bh 1.0000 91,700.00 91,700.00
JUMLAH HARGA BAHAN 91,700.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 127,475.00
E Overhead & profit 10% x Jumlah 12,747.50
F Harga Satuan Pekerjaan (D+E) 140,222.50

JENIS PEKERJAAN : A.4.6.2.12 Pemasangan 1 buah door holder


SATUAN : Bh
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0500 105,000.00 5,250.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 89,525.00
B BAHAN
Door holder Bh 1.0000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.6.2.13 Pemasangan 1 buah door stop


SATUAN : Bh
HARGA SATUAN : Rp 100,293

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0100 105,000.00 1,050.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 18,675.00
B BAHAN
Door stop Bh 1.0000 72,500.00 72,500.00
JUMLAH HARGA BAHAN 72,500.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 91,175.00
E Overhead & profit 10% x Jumlah 9,117.50
F Harga Satuan Pekerjaan (D+E) 100,292.50

JENIS PEKERJAAN : A.4.6.2.14 Pemasangan 1 buah rel pintu sorong


SATUAN : Bh
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0600 105,000.00 6,300.00
Tukang L.02 OH 0.6000 150,000.00 90,000.00
Kepala tukang L.03 OH 0.0600 175,000.00 10,500.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 107,325.00
B BAHAN
Rel pintu sorong Set 1.0000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.6.2.15 Pemasangan 1 buah kunci lemari


SATUAN : Bh
HARGA SATUAN : Rp 73,950

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0250 105,000.00 2,625.00
Tukang L.02 OH 0.2500 150,000.00 37,500.00
Kepala tukang L.03 OH 0.0250 175,000.00 4,375.00
Mandor L.04 OH 0.0013 175,000.00 227.50
JUMLAH TENAGA KERJA 44,727.50
B BAHAN
Kunci lemari Set 1.0000 22,500.00 22,500.00
JUMLAH HARGA BAHAN 22,500.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 67,227.50
E Overhead & profit 10% x Jumlah 6,722.75
F Harga Satuan Pekerjaan (D+E) 73,950.25

JENIS PEKERJAAN : A.4.6.2.16 Pemasangan 1 m2 kaca tebal 3 mm


SATUAN : M2
HARGA SATUAN : Rp 146,278

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0150 105,000.00 1,575.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0008 175,000.00 140.00
JUMLAH TENAGA KERJA 26,840.00
B BAHAN
Kaca tebal 3 mm m2 1.1000 94,900.00 104,390.00
Sealant Kg 0.0500 35,000.00 1,750.00
JUMLAH HARGA BAHAN 106,140.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 132,980.00
E Overhead & profit 10% x Jumlah 13,298.00
F Harga Satuan Pekerjaan (D+E) 146,278.00

JENIS PEKERJAAN : A.4.6.2.17 Pemasangan 1 m2 kaca tebal 5 mm


SATUAN : M2
HARGA SATUAN : Rp 159,346

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0150 105,000.00 1,575.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0008 175,000.00 140.00
JUMLAH TENAGA KERJA 26,840.00
B BAHAN
Kaca tebal 5 mm m2 1.1000 105,700.00 116,270.00
Sealant Kg 0.0500 35,000.00 1,750.00
JUMLAH HARGA BAHAN 118,020.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 144,860.00
E Overhead & profit 10% x Jumlah 14,486.00
F Harga Satuan Pekerjaan (D+E) 159,346.00

JENIS PEKERJAAN : A.4.6.2.18 Pemasangan 1 m2 kaca tebal 8 mm


SATUAN : M2
HARGA SATUAN : Rp 288,318

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0170 105,000.00 1,785.00
Tukang L.02 OH 0.1700 150,000.00 25,500.00
Kepala tukang L.03 OH 0.0170 175,000.00 2,975.00
Mandor L.04 OH 0.0009 175,000.00 157.50
JUMLAH TENAGA KERJA 30,417.50
B BAHAN
Kaca tebal 8 mm m2 1.1000 208,400.00 229,240.00
Sealant Kg 0.0700 35,000.00 2,450.00
JUMLAH HARGA BAHAN 231,690.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 262,107.50
E Overhead & profit 10% x Jumlah 26,210.75
F Harga Satuan Pekerjaan (D+E) 288,318.25

JENIS PEKERJAAN : A.4.6.2.19 Pemasangan 1 m2 kaca buram tebal 12 mm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN
NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
SATUAN

A TENAGA
Pekerja L.01 OH 0.0250 105,000.00 2,625.00
Tukang L.02 OH 0.2500 150,000.00 37,500.00
Kepala tukang L.03 OH 0.0250 175,000.00 4,375.00
Mandor L.04 OH 0.0013 175,000.00 227.50
JUMLAH TENAGA KERJA 44,727.50
B BAHAN
Kaca buram 12 mm m2 1.1000 a #VALUE!
Sealant Kg 0.0700 35,000.00 2,450.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.6.2.20 Pemasangan 1 m2 kaca cermin tebal 5 mm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0150 105,000.00 1,575.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 28,100.00
B BAHAN
Kaca cermin 5 mm m2 1.1000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.6.2.21 Pemasangan 1 m2 kaca cermin tebal 8 mm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0170 105,000.00 1,785.00
Tukang L.02 OH 0.1700 150,000.00 25,500.00
Kepala tukang L.03 OH 0.0170 175,000.00 2,975.00
Mandor L.04 OH 0.0090 175,000.00 1,575.00
JUMLAH TENAGA KERJA 31,835.00
B BAHAN
Kaca cermin 8 mm m2 1.1000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.6.2.22 Pemasangan 1 m2 kaca wireglassed tebal 5 mm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0150 105,000.00 1,575.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 28,100.00
B BAHAN
Kaca wireglassed 5 mm m2 1.1000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.6.2.23 Pemasangan 1 m2 kaca patri tebal 5 mm


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0750 105,000.00 7,875.00
Tukang L.02 OH 0.1500 150,000.00 22,500.00
Kepala tukang L.03 OH 0.0150 175,000.00 2,625.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 33,700.00
B BAHAN
Kaca patri 5 mm m2 1.1000 a #VALUE!
Sealant Kg 0.0500 35,000.00 1,750.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

HARGA SATUAN PEKERJAAN PENGECATAN

JENIS PEKERJAAN : A.4.7.1.1 Pengikisan/pengerokan permukaan cat lama


SATUAN : M2
HARGA SATUAN : Rp 19,388

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 16,275.00
B BAHAN
Soda api Kg 0.0500 27,000.00 1,350.00
JUMLAH HARGA BAHAN 1,350.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 17,625.00
E Overhead & profit 10% x Jumlah 1,762.50
F Harga Satuan Pekerjaan (D+E) 19,387.50

JENIS PEKERJAAN : A.4.7.1.2 Pencucian bidang permukaan tembok yang perna dicat
SATUAN : M2
HARGA SATUAN : Rp 18,233

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 16,275.00
B BAHAN
Sabun Kg 0.0500 6,000.00 300.00
JUMLAH HARGA BAHAN 300.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 16,575.00
E Overhead & profit 10% x Jumlah 1,657.50
F Harga Satuan Pekerjaan (D+E) 18,232.50

JENIS PEKERJAAN : A.4.7.1.3 Pengerokan karat pada permukaan baja cara manual
SATUAN : M2
HARGA SATUAN : Rp 19,195

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 17,150.00
B BAHAN
Sabun Kg 0.0500 6,000.00 300.00
JUMLAH HARGA BAHAN 300.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 17,450.00
E Overhead & profit 10% x Jumlah 1,745.00
F Harga Satuan Pekerjaan (D+E) 19,195.00

JENIS PEKERJAAN : A.4.7.1.4 Pengecatan bidang kayu baru (1lapis plamuur, 1 lapis cat dasar,2 lapis cat penutup)

SATUAN : M2
HARGA SATUAN : Rp 49,820

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0700 105,000.00 7,350.00
Tukang L.02 OH 0.0090 150,000.00 1,350.00
Kepala tukang L.03 OH 0.0060 175,000.00 1,050.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 10,275.00
B BAHAN
Cat menie Kg 0.2000 30,700.00 6,140.00
Plamuur Kg 0.1500 28,700.00 4,305.00
Cat dasar Kg 0.1700 45,000.00 7,650.00
Cat penutup Kg 0.2600 55,500.00 14,430.00
Kuas Bh 0.0100 20,700.00 207.00
Pengencer ltr 0.0300 14,800.00 444.00
Ampelas Lbr 0.2000 9,200.00 1,840.00
JUMLAH HARGA BAHAN 35,016.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 45,291.00
E Overhead & profit 10% x Jumlah 4,529.10
F Harga Satuan Pekerjaan (D+E) 49,820.10

JENIS PEKERJAAN : A.4.7.1.5 Pengecatan bidang kayu baru (1lapis plamuur, 1 lapis cat dasar,3 lapis cat penutup)

SATUAN : M2
HARGA SATUAN : Rp 70,770

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0700 105,000.00 7,350.00
Tukang L.02 OH 0.1050 150,000.00 15,750.00
Kepala tukang L.03 OH 0.0040 175,000.00 700.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 24,325.00
B BAHAN
Cat menie Kg 0.2000 30,700.00 6,140.00
Plamuur Kg 0.1500 28,700.00 4,305.00
Cat dasar Kg 0.1700 45,000.00 7,650.00
Cat penutup Kg 0.3500 55,500.00 19,425.00
Kuas Bh 0.0100 20,700.00 207.00
Pengencer Kg 0.0300 14,800.00 444.00
Ampelas Lbr 0.2000 9,200.00 1,840.00
JUMLAH HARGA BAHAN 40,011.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 64,336.00
E Overhead & profit 10% x Jumlah 6,433.60
F Harga Satuan Pekerjaan (D+E) 70,769.60

JENIS PEKERJAAN : A.4.7.1.6 Peleburan 1 m2 bidang kayu dengan teak oil


SATUAN : M2
HARGA SATUAN : #VALUE!
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0400 105,000.00 4,200.00
Tukang L.02 OH 0.0630 150,000.00 9,450.00
Kepala tukang L.03 OH 0.0630 175,000.00 11,025.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 25,200.00
B BAHAN
Teak oil L 0.3600 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.7.1.7 Peleburan 1 m2 bidang kayu dengan politur


SATUAN : M2
HARGA SATUAN : Rp 73,501

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0400 105,000.00 4,200.00
Tukang L.02 OH 0.0600 150,000.00 9,000.00
Kepala tukang L.03 OH 0.0160 175,000.00 2,800.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 16,525.00
B BAHAN
Politur L 0.1500 61,100.00 9,165.00
Politur jadi L 0.3720 61,100.00 22,729.20
Ampelas Lbr 2.0000 9,200.00 18,400.00
JUMLAH HARGA BAHAN 50,294.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 66,819.20
E Overhead & profit 10% x Jumlah 6,681.92
F Harga Satuan Pekerjaan (D+E) 73,501.12

JENIS PEKERJAAN : A.4.7.1.8 Peleburan 1 m2 bidang kayu dengan cat residu dan ter
SATUAN : M2
HARGA SATUAN : Rp 25,795

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1000 105,000.00 10,500.00
Mandor L.04 OH 0.0060 175,000.00 1,050.00
JUMLAH TENAGA KERJA 11,550.00
B BAHAN
Residu atau ter L 0.3500 34,000.00 11,900.00
JUMLAH HARGA BAHAN 11,900.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 23,450.00
E Overhead & profit 10% x Jumlah 2,345.00
F Harga Satuan Pekerjaan (D+E) 25,795.00

JENIS PEKERJAAN : A.4.7.1.9 Peleburan 1 m2 bidang kayu dengan Vernis


SATUAN : M2
HARGA SATUAN : Rp 66,352

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1600 105,000.00 16,800.00
Tukang L.02 OH 0.1600 150,000.00 24,000.00
Kepala tukang L.03 OH 0.0160 175,000.00 2,800.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 44,125.00
B BAHAN
Vernis L 0.1500 93,100.00 13,965.00
Dempul Kg 0.0500 26,200.00 1,310.00
Ampelas Lbr 0.1000 9,200.00 920.00
JUMLAH HARGA BAHAN 16,195.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 60,320.00
E Overhead & profit 10% x Jumlah 6,032.00
F Harga Satuan Pekerjaan (D+E) 66,352.00

JENIS PEKERJAAN : A.4.7.1.10 Pengecatan 1 m2 tembok baru (1 lapis plamur, 1 lapis cat dasar, 2lapis cat penutup)
SATUAN : M2
HARGA SATUAN : Rp 35,494

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0200 105,000.00 2,100.00
Tukang L.02 OH 0.0630 150,000.00 9,450.00
Kepala tukang L.03 OH 0.0063 175,000.00 1,102.50
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 13,177.50
B BAHAN
Plamuur Kg 0.1000 31,800.00 3,180.00
Cat dasar Kg 0.1000 25,200.00 2,520.00
Cat penutup Kg 0.2600 51,500.00 13,390.00
JUMLAH HARGA BAHAN 19,090.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 32,267.50
E Overhead & profit 10% x Jumlah 3,226.75
F Harga Satuan Pekerjaan (D+E) 35,494.25

JENIS PEKERJAAN : A.4.7.1.11 Pengecatan 1 m2 tembok lama dinding dalam jotun Interior (1 lapis Alkalir, 2 lapis cat penutup)
SATUAN : M2
HARGA SATUAN : Rp 23,034

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0280 105,000.00 2,940.00
Tukang L.02 OH 0.0420 150,000.00 6,300.00
Kepala tukang L.03 OH 0.0042 175,000.00 735.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 10,500.00
B BAHAN
Cat dasar ( Alkali ) Kg 0.1200 45,000.00 5,400.00
Cat penutup ( Jotun Interior ) Kg 0.1800 28,000.00 5,040.00
JUMLAH HARGA BAHAN 10,440.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 20,940.00
E Overhead & profit 10% x Jumlah 2,094.00
F Harga Satuan Pekerjaan (D+E) 23,034.00

JENIS PEKERJAAN : A.4.7.1.11.a Pengecatan 1 m2 tembok lama dinding Luar jotun Exterior (1 lapis Alkalir, 2 lapis cat penutup)
SATUAN : M2
HARGA SATUAN : Rp 35,310

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0280 105,000.00 2,940.00
Tukang L.02 OH 0.0420 150,000.00 6,300.00
Kepala tukang L.03 OH 0.0042 175,000.00 735.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 10,500.00
B BAHAN
Cat dasar ( Alkali ) Kg 0.1200 45,000.00 5,400.00
Cat penutup ( Jotun Exterior ) Kg 0.1800 90,000.00 16,200.00
JUMLAH HARGA BAHAN 21,600.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 32,100.00
E Overhead & profit 10% x Jumlah 3,210.00
F Harga Satuan Pekerjaan (D+E) 35,310.00
` JENIS PEKERJAAN : A.4.7.1.12 Peleburan 1 m2 tembok dengan kalkarium
SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.0280 105,000.00 2,940.00
Tukang L.02 OH 0.0420 150,000.00 6,300.00
Kepala tukang L.03 OH 0.0042 175,000.00 735.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 10,500.00
B BAHAN
Kalkarium Kg 0.1000 a #VALUE!

JUMLAH HARGA BAHAN #VALUE!


C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.7.1.13 Peleburan 1 m2 tembok dengan kapur sirih


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Tukang L.02 OH 0.0010 150,000.00 150.00
Kepala tukang L.03 OH 0.0001 175,000.00 17.50
Mandor L.04 OH 0.0025 175,000.00 437.50
JUMLAH TENAGA KERJA 16,355.00
B BAHAN
Kapur sirih Kg 0.1500 a #VALUE!
Ampelas Lbr 0.1000 9,200.00 920.00
Kuas bh 0.2500 20,700.00 5,175.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.7.1.14 Peleburan 1 m2 tembok lama dengan kapur sirih (pemeliharaan)
SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0400 105,000.00 4,200.00
Tukang L.02 OH 0.0050 150,000.00 750.00
Kepala tukang L.03 OH 0.0005 175,000.00 87.50
Mandor L.04 OH 0.0025 175,000.00 437.50
JUMLAH TENAGA KERJA 5,475.00
B BAHAN
Kapur sirih Kg 0.3000 a #VALUE!
Ampelas Lbr 0.2000 9,200.00 1,840.00
Kuas bh 0.2500 20,700.00 5,175.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.7.1.15 Pemasangan 1 m2 wallpaper


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN
A TENAGA
Pekerja L.01 OH 0.0200 105,000.00 2,100.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0025 175,000.00 437.50
JUMLAH TENAGA KERJA 36,037.50
B BAHAN
Wallpaper Kg 1.2000 a #VALUE!
Lem Lbr 0.2000 18,800.00 3,760.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.7.1.16 Pengecatan 1 m2 permukaan baja dengan menie besi


SATUAN : M2
HARGA SATUAN : Rp 44,302

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0200 105,000.00 2,100.00
Tukang L.02 OH 0.2000 150,000.00 30,000.00
Kepala tukang L.03 OH 0.0200 175,000.00 3,500.00
Mandor L.04 OH 0.0025 175,000.00 437.50
JUMLAH TENAGA KERJA 36,037.50
B BAHAN
Menie besi Kg 0.1000 40,300.00 4,030.00
Kuas Lbr 0.0100 20,700.00 207.00
JUMLAH HARGA BAHAN 4,237.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 40,274.50
E Overhead & profit 10% x Jumlah 4,027.45
F Harga Satuan Pekerjaan (D+E) 44,301.95

JENIS PEKERJAAN : A.4.7.1.17 Pengecatan 1 m2 permukaan baja dengan menie besi dengan perancah
SATUAN : M2
HARGA SATUAN : Rp 76,599

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang L.02 OH 0.2250 150,000.00 33,750.00
Kepala tukang L.03 OH 0.0225 175,000.00 3,937.50
Mandor L.04 OH 0.0075 175,000.00 1,312.50
JUMLAH TENAGA KERJA 65,250.00
B BAHAN
Menie besi Kg 0.1000 40,300.00 4,030.00
Pengencer L 0.0100 14,800.00 148.00
Kuas Bh 0.0100 20,700.00 207.00
Perancah kayu m3 0.0020 - -
JUMLAH HARGA BAHAN 4,385.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 69,635.00
E Overhead & profit 10% x Jumlah 6,963.50
F Harga Satuan Pekerjaan (D+E) 76,598.50

JENIS PEKERJAAN : A.4.7.1.18 Pengecatan 1 m2 permukaan Baja / Galvanis secara manual 4 lapis
SATUAN : M2
HARGA SATUAN : Rp 89,055

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2500 105,000.00 26,250.00
Tukang L.02 OH 0.2500 150,000.00 37,500.00
Kepala tukang L.03 OH 0.0250 175,000.00 4,375.00
Mandor L.04 OH 0.0013 175,000.00 227.50
JUMLAH TENAGA KERJA 68,352.50
B BAHAN
Menie A Kg 0.1000 40,300.00 4,030.00
Menie B Kg 0.1000 40,300.00 4,030.00
Cat Minyak Kg 0.0800 52,400.00 4,192.00
Kuas Bh 0.0100 20,700.00 207.00
Pengencer L 0.0100 14,800.00 148.00
JUMLAH HARGA BAHAN 12,607.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 80,959.50
E Overhead & profit 10% x Jumlah 8,095.95
F Harga Satuan Pekerjaan (D+E) 89,055.45

JENIS PEKERJAAN : A.4.7.1.19 Pengecatan 1 m2 permukaan Baja / Galvanis secara manual sistem 1 lapis cat mutakhir
SATUAN : M2
HARGA SATUAN : 37,400.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0600 105,000.00 6,300.00
Tukang L.02 OH 0.0600 150,000.00 9,000.00
Kepala tukang L.03 OH 0.0120 175,000.00 2,100.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 17,925.00
B BAHAN
Cat Minyak Kg 0.3000 52,400.00 15,720.00
Kuas Bh 0.0100 20,700.00 207.00
Pengencer L 0.0100 14,800.00 148.00
JUMLAH HARGA BAHAN 16,075.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 34,000.00
E Overhead & profit 10% x Jumlah 3,400.00
F Harga Satuan Pekerjaan (D+E) 37,400.00

JENIS PEKERJAAN : A.4.7.1.20 Pengecatan 1 m2 permukaan Baja / Galvanis secara manual sistem 3 lapis
SATUAN : M2
HARGA SATUAN : Rp 220,772.20

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4000 105,000.00 42,000.00
Tukang L.02 OH 0.8000 150,000.00 120,000.00
Kepala tukang L.03 OH 0.0800 175,000.00 14,000.00
Mandor L.04 OH 0.0200 175,000.00 3,500.00
JUMLAH TENAGA KERJA 179,500.00
B BAHAN
Cat dasar Kg 0.1100 37,200.00 4,092.00
Cat antara Kg 0.1700 73,900.00 12,563.00
Cat penutup Kg 0.0800 52,400.00 4,192.00
Kuas Bh 0.0100 20,700.00 207.00
Pengencer L 0.0100 14,800.00 148.00
JUMLAH HARGA BAHAN 21,202.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 200,702.00
E Overhead & profit 10% x Jumlah 20,070.20
F Harga Satuan Pekerjaan (D+E) 220,772.20

JENIS PEKERJAAN : A.4.7.1.21 Pengecatan 1 m2 permukaan Baja / Galvanis secara semprot sistem 3 lapis
SATUAN : M2
HARGA SATUAN : Rp 191,463.80

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.4000 105,000.00 42,000.00
Tukang L.02 OH 0.7000 150,000.00 105,000.00
Kepala tukang L.03 OH 0.0700 175,000.00 12,250.00
Mandor L.04 OH 0.0200 175,000.00 3,500.00
JUMLAH TENAGA KERJA 162,750.00
B BAHAN
Cat dasar Kg 0.3000 37,200.00 11,160.00
Pengencer L 0.0100 14,800.00 148.00
JUMLAH HARGA BAHAN 11,308.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 174,058.00
E Overhead & profit 10% x Jumlah 17,405.80
F Harga Satuan Pekerjaan (D+E) 191,463.80

JENIS PEKERJAAN : A.4.7.1.22 Plituran 10 m2 dengan plitur melamic


SATUAN : M2
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 2.0000 105,000.00 210,000.00
Tukang L.02 OH 12.0000 150,000.00 1,800,000.00
Kepala tukang L.03 OH 1.2000 175,000.00 210,000.00
Mandor L.04 OH 0.1000 175,000.00 17,500.00
JUMLAH TENAGA KERJA 2,237,500.00
B BAHAN
Wood Filler kg 1.5000 a #VALUE!
Woodstain kg 1.5000 a #VALUE!
Sanding kg 1.5000 a #VALUE!
Melamic L 2.4000 a #VALUE!
Thinner Lbr 2.0000 17,300.00 34,600.00
Amplas Lbr 6.0000 14,800.00 88,800.00
JUMLAH HARGA BAHAN 123,400.00
C PERALATAN
Compressor jam a a #VALUE!
JUMLAH HARGA ALAT #VALUE!
D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.4.7.1.1 Pengikisan/pengerokan permukaan cat lama pada kerb


SATUAN : M2
HARGA SATUAN : Rp 19,388

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1500 105,000.00 15,750.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 16,275.00
B BAHAN
Gundar Kawat Bh 0.1800 7,500.00 1,350.00
JUMLAH HARGA BAHAN 1,350.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 17,625.00
E Overhead & profit 10% x Jumlah 1,762.50
F Harga Satuan Pekerjaan (D+E) 19,387.50

JENIS PEKERJAAN : A.4.7.1.5 Pengecatan Ulang Kerb Beton (1 lapis cat dasar, 2 lapis cat penutup)
SATUAN : M2
HARGA SATUAN : Rp 40,346

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0420 105,000.00 4,410.00
Tukang L.02 OH 0.0630 175,000.00 11,025.00
Kepala tukang L.03 OH 0.0040 - -
Mandor L.04 OH 0.0030 - -
JUMLAH TENAGA KERJA 15,435.00
B BAHAN
Cat Dasar Kg 0.1020 52,400.00 5,344.80
Plamuur Kg 0.1500 - -
Cat Penutup (Hitam) Kg 0.1167 52,400.00 6,115.08
Cat Penutup (Putih) Kg 0.1167 67,000.00 7,818.90
Kuas Bh 0.0060 18,300.00 109.80
Pengencer (Thinner) Kg 0.0180 19,700.00 354.60
Ampelas Lbr 0.2000 7,500.00 1,500.00
JUMLAH HARGA BAHAN 21,243.18
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 36,678.18
E Overhead & profit 10% x Jumlah 3,667.82
F Harga Satuan Pekerjaan (D+E) 40,346.00

HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

JENIS PEKERJAAN : A.5.1.1.1 Pemasangan 1 buah Closet Duduk Merk Toto


SATUAN : Bh
HARGA SATUAN : Rp 2,810,308.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 3.3000 105,000.00 346,500.00
Tukang L.02 OH 1.1000 150,000.00 165,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.1600 175,000.00 28,000.00
JUMLAH TENAGA KERJA 541,250.00
B BAHAN
Closet duduk Unit 1.0000 1,899,600.00 1,899,600.00
Perlengkapan Ls 0.0600 1,899,600.00 113,976.00
JUMLAH HARGA BAHAN 2,013,576.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 2,554,826.00
E Overhead & profit 10% x Jumlah 255,482.60
F Harga Satuan Pekerjaan (D+E) 2,810,308.60

JENIS PEKERJAAN : A.5.1.1.2 Pemasangan 1 buah Closet Jongkok Merk Toto


SATUAN : Bh
HARGA SATUAN : Rp 790,301.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang L.02 OH 1.5000 150,000.00 225,000.00
Kepala tukang L.03 OH 0.1500 175,000.00 26,250.00
Mandor L.04 OH 0.1600 175,000.00 28,000.00
JUMLAH TENAGA KERJA 384,250.00
B BAHAN
Closet jongkok Unit 1.0000 325,000.00 325,000.00
Semen Portland Kg 6.0000 1,240.00 7,440.00
Pasir Pasang m3 0.0100 176,600.00 1,766.00
JUMLAH HARGA BAHAN 334,206.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 718,456.00
E Overhead & profit 10% x Jumlah 71,845.60
F Harga Satuan Pekerjaan (D+E) 790,301.60

JENIS PEKERJAAN : A.5.1.1.3 Pemasangan 1 buah Closet Jongkok Merk KIA


SATUAN : Bh
HARGA SATUAN : Rp 692,016.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang L.02 OH 1.5000 150,000.00 225,000.00
Kepala tukang L.03 OH 0.1500 175,000.00 26,250.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 365,000.00
B BAHAN
Closet jongkok Unit 1.0000 250,000.00 250,000.00
Semen Portland Kg 6.0000 1,240.00 7,440.00
Pasir Pasang m3 0.0100 176,600.00 1,766.00
Bata Merah Bh 7.0000 700.00 4,900.00
JUMLAH HARGA BAHAN 264,106.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 629,106.00
E Overhead & profit 10% x Jumlah 62,910.60
F Harga Satuan Pekerjaan (D+E) 692,016.60

JENIS PEKERJAAN : A.5.1.1.4 Pemasangan 1 buah Urinoir Merk Toto


SATUAN : Bh
HARGA SATUAN : Rp 3,014,514.58
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.0000 105,000.00 105,000.00
Tukang L.02 OH 1.0000 150,000.00 150,000.00
Kepala tukang L.03 OH 0.1000 175,000.00 17,500.00
Mandor L.04 OH 0.0500 175,000.00 8,750.00
JUMLAH TENAGA KERJA 281,250.00
B BAHAN
Urinoir Unit 1.0000 1,882,500.00 1,882,500.00
Semen Portland Kg 6.0000 1,240.00 7,440.00
Pasir Pasang m3 0.0100 176,600.00 1,766.00
Perlengkapan % 30.0000 1,891,706.00 567,511.8000
JUMLAH HARGA BAHAN 2,459,217.80
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 2,740,467.80
E Overhead & profit 10% x Jumlah 274,046.78
F Harga Satuan Pekerjaan (D+E) 3,014,514.58

JENIS PEKERJAAN : A.5.1.1.5 Pemasangan 1 buah wastafel


SATUAN : Bh
HARGA SATUAN : Rp 1,692,658.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.2000 105,000.00 126,000.00
Tukang L.02 OH 1.4500 150,000.00 217,500.00
Kepala tukang L.03 OH 0.1500 175,000.00 26,250.00
Mandor L.04 OH 0.0600 175,000.00 10,500.00
JUMLAH TENAGA KERJA 380,250.00
B BAHAN
Wastafel Unit 1.2000 870,700.00 1,044,840.00
Semen Portland Kg 6.0000 1,240.00 7,440.00
Pasir Pasang m3 0.0100 176,600.00 1,766.00
Perlengkapan % 12.0000 870,700.00 104,484.00
JUMLAH HARGA BAHAN 1,158,530.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 1,538,780.00
E Overhead & profit 10% x Jumlah 153,878.00
F Harga Satuan Pekerjaan (D+E) 1,692,658.00

JENIS PEKERJAAN : A.5.1.1.6 Pemasangan 1 buah bathcuip porselen


SATUAN : Bh
HARGA SATUAN : Rp 5,361,427.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0750 105,000.00 7,875.00
Tukang L.02 OH 0.7500 150,000.00 112,500.00
Kepala tukang L.03 OH 0.0750 175,000.00 13,125.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 134,025.00
B BAHAN
Bathcuip Unit 1.0000 3,950,000.00 3,950,000.00
Perlengkapan % 20.0000 3,950,000.00 790,000.00
JUMLAH HARGA BAHAN 4,740,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 4,874,025.00
E Overhead & profit 10% x Jumlah 487,402.50
F Harga Satuan Pekerjaan (D+E) 5,361,427.50

JENIS PEKERJAAN : A.5.1.1.7 Pemasangan 1 buah bak fibreglass vol 1 m3


SATUAN : Bh
HARGA SATUAN : Rp 1,913,500.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 3.0000 105,000.00 315,000.00
Tukang L.02 OH 4.5000 150,000.00 675,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.9000 175,000.00 157,500.00
JUMLAH TENAGA KERJA 1,156,250.00
B BAHAN
Bak fibreglass Unit 1.0000 520,800.00 520,800.00
Perlengkapan % 12.0000 520,800.00 62,496.00
JUMLAH HARGA BAHAN 583,296.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 1,739,546.00
E Overhead & profit 10% x Jumlah 173,954.60
F Harga Satuan Pekerjaan (D+E) 1,913,500.60

JENIS PEKERJAAN : A.5.1.1.8 Pemasangan 1 buah bak mandi batu bata vol 0,30 m3
SATUAN : Bh
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 6.0000 105,000.00 630,000.00
Tukang L.02 OH 3.0000 150,000.00 450,000.00
Kepala tukang L.03 OH 0.3000 175,000.00 52,500.00
Mandor L.04 OH 0.0300 175,000.00 5,250.00
JUMLAH TENAGA KERJA 1,137,750.00
B BAHAN
Bata Merah m3 150.0000 700.00 105,000.00
Semen Portland Kg 120.0000 1,240.00 148,800.00
Pasir Pasang m3 0.3000 176,600.00 52,980.00
Porselen 11 x 11 cm bh 360.0000 a #VALUE!
Semen warna (tepung affa) Kg 6.0000 10,700.00 64,200.00
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.5.1.1.9 Pemasangan 1 buah bak mandi teraso vol 0,30 m3
SATUAN : Bh
HARGA SATUAN : Rp 1,604,515.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 3.0000 105,000.00 315,000.00
Tukang L.02 OH 4.5000 150,000.00 675,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.9000 175,000.00 157,500.00
JUMLAH TENAGA KERJA 1,156,250.00
B BAHAN
Bak fiberglass Unit 1.0000 270,000.00 270,000.00
Perlengkapan Ls 12.0000 270,000.00 32,400.00
JUMLAH HARGA BAHAN 302,400.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 1,458,650.00
E Overhead & profit 10% x Jumlah 145,865.00
F Harga Satuan Pekerjaan (D+E) 1,604,515.00

JENIS PEKERJAAN : A.5.1.1.10 Pemasangan 1 buah bak air fibreglass vol 1 m3


SATUAN : Bh
HARGA SATUAN : Rp 762,075.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3000 105,000.00 31,500.00
Tukang L.02 OH 0.4500 150,000.00 67,500.00
Kepala tukang L.03 OH 0.0450 175,000.00 7,875.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 109,500.00
B BAHAN
Bak fibreglass Unit 1.0000 520,800.00 520,800.00
Perlengkapan % 12.0000 520,800.00 62,496.00
JUMLAH HARGA BAHAN 583,296.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 692,796.00
E Overhead & profit 10% x Jumlah 69,279.60
F Harga Satuan Pekerjaan (D+E) 762,075.60

JENIS PEKERJAAN : A.5.1.1.11 Pemasangan 1 buah bak mandi beton vol 1 m3


SATUAN : Bh
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 3.5000 105,000.00 367,500.00
Tukang L.02 OH 4.5000 150,000.00 675,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0180 175,000.00 3,150.00
JUMLAH TENAGA KERJA 1,054,400.00
B BAHAN
Beton 1:2:3 m3 0.9000 1,115,285.00 1,003,756.50
Besi Beton Kg 180.0000 10,100.00 1,818,000.00
Kayu bekisting m2 8.0000 51,654.00 413,232.00
Ubin porselen bh 500.0000 a #VALUE!
Perlengkapan % 10.0000 #VALUE! #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.5.1.1.12 Pemasangan 1 buah bak cuci piring stainlessteel


SATUAN : Bh
HARGA SATUAN : Rp 556,627.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0300 105,000.00 3,150.00
Tukang L.02 OH 0.3000 150,000.00 45,000.00
Kepala tukang L.03 OH 0.0300 175,000.00 5,250.00
Mandor L.04 OH 0.0150 175,000.00 2,625.00
JUMLAH TENAGA KERJA 56,025.00
B BAHAN
Bak cuci piring Unit 1.0000 250,000.00 250,000.00
Waterdrain Bh 1.0000 200,000.00 200,000.00
JUMLAH HARGA BAHAN 450,000.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 506,025.00
E Overhead & profit 10% x Jumlah 50,602.50
F Harga Satuan Pekerjaan (D+E) 556,627.50

JENIS PEKERJAAN : A.5.1.1.13 Pemasangan 1 buah bak cuci piring teraso


SATUAN : Bh
HARGA SATUAN : Rp 634,705.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0500 105,000.00 5,250.00
Tukang L.02 OH 0.5000 150,000.00 75,000.00
Kepala tukang L.03 OH 0.0500 175,000.00 8,750.00
Mandor L.04 OH 0.0250 175,000.00 4,375.00
JUMLAH TENAGA KERJA 93,375.00
B BAHAN
Bak cuci piring Unit 1.0000 250,000.00 250,000.00
Waterdrain Bh 1.0000 200,000.00 200,000.00
Semen Portland Kg 20.0000 1,240.00 24,800.00
Pasir Pasang m3 0.0500 176,600.00 8,830.00
JUMLAH HARGA BAHAN 483,630.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 577,005.00
E Overhead & profit 10% x Jumlah 57,700.50
F Harga Satuan Pekerjaan (D+E) 634,705.50

JENIS PEKERJAAN : A.5.1.1.14 Pemasangan 1 buah floor drain


SATUAN : Bh
HARGA SATUAN : Rp 162,222.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0100 105,000.00 1,050.00
Tukang L.02 OH 0.1000 150,000.00 15,000.00
Kepala tukang L.03 OH 0.0100 175,000.00 1,750.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 18,675.00
B BAHAN
Floor Drain Unit 1.0000 128,800.00 128,800.00
JUMLAH HARGA BAHAN 128,800.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 147,475.00
E Overhead & profit 10% x Jumlah 14,747.50
F Harga Satuan Pekerjaan (D+E) 162,222.50

JENIS PEKERJAAN : A.5.1.1.15 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 Cm
SATUAN : Bh
HARGA SATUAN : Rp 531,517.80

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 2.1600 105,000.00 226,800.00
Tukang L.02 OH 0.7200 150,000.00 108,000.00
Kepala tukang L.03 OH 0.0720 175,000.00 12,600.00
Mandor L.04 OH 0.0110 175,000.00 1,925.00
JUMLAH TENAGA KERJA 349,325.00
B BAHAN
Bata Merah bh 40.0000 700.00 28,000.00
Semen Portland kg 44.0000 1,240.00 54,560.00
Pasir Pasang m3 0.0700 176,600.00 12,362.00
Pasir beton m3 0.0600 176,500.00 10,590.00
Kerikil m3 0.0700 174,300.00 12,201.00
Baja bertulang kg 1.6000 10,100.00 16,160.00
JUMLAH HARGA BAHAN 133,873.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 483,198.00
E Overhead & profit 10% x Jumlah 48,319.80
F Harga Satuan Pekerjaan (D+E) 531,517.80

JENIS PEKERJAAN : A.5.1.1.16 Pemasangan 1 buah bak kontrol pasangan bata 45x45 tinggi 50 Cm
SATUAN : Bh
HARGA SATUAN : Rp 798,923.40

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 3.2000 105,000.00 336,000.00
Tukang L.02 OH 1.1500 150,000.00 172,500.00
Kepala tukang L.03 OH 0.0110 175,000.00 1,925.00
Mandor L.04 OH 0.0160 175,000.00 2,800.00
JUMLAH TENAGA KERJA 513,225.00
B BAHAN
Bata Merah bh 70.0000 700.00 49,000.00
Semen Portland kg 77.0000 1,240.00 95,480.00
Pasir Pasang m3 0.1300 176,600.00 22,958.00
Pasir beton m3 0.0900 176,500.00 15,885.00
Kerikil m3 0.0200 174,300.00 3,486.00
Baja bertulang kg 2.6000 10,100.00 26,260.00
JUMLAH HARGA BAHAN 213,069.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 726,294.00
E Overhead & profit 10% x Jumlah 72,629.40
F Harga Satuan Pekerjaan (D+E) 798,923.40

JENIS PEKERJAAN : A.5.1.1.17 Pemasangan 1 buah bak kontrol pasangan bata 60x60 tinggi 65 Cm
SATUAN : Bh
HARGA SATUAN : Rp 934,005.93

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 3.2000 105,000.00 336,000.00
Tukang L.02 OH 1.1500 150,000.00 172,500.00
Kepala tukang L.03 OH 0.0110 175,000.00 1,925.00
Mandor L.04 OH 0.0160 175,000.00 2,800.00
JUMLAH TENAGA KERJA 513,225.00
B BAHAN
Bata Merah bh 123.0000 700.00 86,100.00
Semen Portland kg 114.0000 1,240.00 141,360.00
Pasir Pasang m3 0.1840 176,600.00 32,494.40
Pasir beton m3 0.1200 176,500.00 21,180.00
Kerikil m3 0.0330 174,300.00 5,751.90
Baja bertulang kg 4.8500 10,100.00 48,985.00
JUMLAH HARGA BAHAN 335,871.30
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 849,096.30
E Overhead & profit 10% x Jumlah 84,909.63
F Harga Satuan Pekerjaan (D+E) 934,005.93

JENIS PEKERJAAN : A.5.1.1.18 Pemasangan 1 M1 pipa galvanis diameter 1/2"


SATUAN : M1
HARGA SATUAN : Rp 78,447.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0540 105,000.00 5,670.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0270 175,000.00 4,725.00
JUMLAH TENAGA KERJA 25,470.00
B BAHAN
Pipa galvanis 1/2" m 1.2000 28,300.00 33,960.00
Perlengkapan Ls 35.0000 33,960.00 11,886.00
JUMLAH HARGA BAHAN 45,846.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 71,316.00
E Overhead & profit 10% x Jumlah 7,131.60
F Harga Satuan Pekerjaan (D+E) 78,447.60

JENIS PEKERJAAN : A.5.1.1.19 Pemasangan 1 buah kran diameter 1/2" atau 3/4"
SATUAN : M1
HARGA SATUAN : Rp 142,092.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0100 105,000.00 1,050.00
Tukang L.02 OH 0.4000 150,000.00 60,000.00
Kepala tukang L.03 OH 0.0400 175,000.00 7,000.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 68,925.00
B BAHAN
Kran Air stainless m 1.0000 60,000.00 60,000.00
Sealtape Bh 0.0250 10,000.00 250.00
JUMLAH HARGA BAHAN 60,250.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 129,175.00
E Overhead & profit 10% x Jumlah 12,917.50
F Harga Satuan Pekerjaan (D+E) 142,092.50

JENIS PEKERJAAN : A.5.1.1.20 Pemasangan 1 M1 pipa galvanis diameter ¾"


SATUAN : M1
HARGA SATUAN : Rp 93,060.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0540 105,000.00 5,670.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0270 175,000.00 4,725.00
JUMLAH TENAGA KERJA 25,470.00
B BAHAN
Pipa galvanis 3/4" m 1.2000 36,500.00 43,800.00
Perlengkapan % 35.0000 43,800.00 15,330.00
JUMLAH HARGA BAHAN 59,130.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 84,600.00
E Overhead & profit 10% x Jumlah 8,460.00
F Harga Satuan Pekerjaan (D+E) 93,060.00

JENIS PEKERJAAN : A.5.1.1.21 Pemasangan 1 M1 pipa galvanis diameter 1"


SATUAN : M1
HARGA SATUAN : Rp 97,515.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0540 105,000.00 5,670.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0270 175,000.00 4,725.00
JUMLAH TENAGA KERJA 25,470.00
B BAHAN
Pipa galvanis 1" m 1.2000 39,000.00 46,800.00
Perlengkapan % 35.0000 46,800.00 16,380.00
JUMLAH HARGA BAHAN 63,180.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 88,650.00
E Overhead & profit 10% x Jumlah 8,865.00
F Harga Satuan Pekerjaan (D+E) 97,515.00

JENIS PEKERJAAN : A.5.1.1.22 Pemasangan 1 M1 pipa galvanis diameter 1 ½"


SATUAN : M1
HARGA SATUAN : Rp 146,215.30

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1080 105,000.00 11,340.00
Tukang L.02 OH 0.1800 150,000.00 27,000.00
Kepala tukang L.03 OH 0.0180 175,000.00 3,150.00
Mandor L.04 OH 0.0050 175,000.00 875.00
JUMLAH TENAGA KERJA 42,365.00
B BAHAN
Pipa galvanis 1 1/2" m 1.2000 55,900.00 67,080.00
Perlengkapan % 35.0000 67,080.00 23,478.00
JUMLAH HARGA BAHAN 90,558.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 132,923.00
E Overhead & profit 10% x Jumlah 13,292.30
F Harga Satuan Pekerjaan (D+E) 146,215.30

JENIS PEKERJAAN : A.5.1.1.23 Pemasangan 1 M1 pipa galvanis diameter 3"


SATUAN : M1
HARGA SATUAN : Rp 398,141.70

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1350 105,000.00 14,175.00
Tukang L.02 OH 0.2250 150,000.00 33,750.00
Kepala tukang L.03 OH 0.0230 175,000.00 4,025.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 53,175.00
B BAHAN
Pipa galvanis 3" m 1.2000 190,600.00 228,720.00
Perlengkapan % 35.0000 228,720.00 80,052.00
JUMLAH HARGA BAHAN 308,772.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 361,947.00
E Overhead & profit 10% x Jumlah 36,194.70
F Harga Satuan Pekerjaan (D+E) 398,141.70

JENIS PEKERJAAN : A.5.1.1.24 Pemasangan 1 M1 pipa galvanis diameter 4"


SATUAN : M1
HARGA SATUAN : Rp 550,680.90

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1350 105,000.00 14,175.00
Tukang L.02 OH 0.2250 150,000.00 33,750.00
Kepala tukang L.03 OH 0.0230 175,000.00 4,025.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 53,175.00
B BAHAN
Pipa galvanis 4" m 1.2000 276,200.00 331,440.00
Perlengkapan % 35.0000 331,440.00 116,004.00
JUMLAH HARGA BAHAN 447,444.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 500,619.00
E Overhead & profit 10% x Jumlah 50,061.90
F Harga Satuan Pekerjaan (D+E) 550,680.90

JENIS PEKERJAAN : A.5.1.1.25 Pemasangan 1 M1 pipa PVC tipe AW diameter 1/2"


SATUAN : M1
HARGA SATUAN : Rp 28,606.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0360 105,000.00 3,780.00
Tukang L.02 OH 0.0600 150,000.00 9,000.00
Kepala tukang L.03 OH 0.0060 175,000.00 1,050.00
Mandor L.04 OH 0.0020 175,000.00 350.00
JUMLAH TENAGA KERJA 14,180.00
B BAHAN
Pipa PVC 1/2" M 1.2000 7,300.00 8,760.00
Perlengkapan % 35.0000 8,760.00 3,066.00
JUMLAH HARGA BAHAN 11,826.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 26,006.00
E Overhead & profit 10% x Jumlah 2,600.60
F Harga Satuan Pekerjaan (D+E) 28,606.60

JENIS PEKERJAAN : A.5.1.1.26 Pemasangan 1 M1 pipa PVC tipe AW diameter 3/4"


SATUAN : M1
HARGA SATUAN : Rp 31,992.40

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0360 105,000.00 3,780.00
Tukang L.02 OH 0.0600 150,000.00 9,000.00
Kepala tukang L.03 OH 0.0060 175,000.00 1,050.00
Mandor L.04 OH 0.0020 175,000.00 350.00
JUMLAH TENAGA KERJA 14,180.00
B BAHAN
Pipa PVC 3/4" m 1.2000 9,200.00 11,040.00
Perlengkapan % 35.0000 11,040.00 3,864.00
JUMLAH HARGA BAHAN 14,904.00
C PERALATAN
JUMLAH HARGA ALAT -
D JUMLAH (A+B+C) 29,084.00
E Overhead & profit 10% x Jumlah 2,908.40
F Harga Satuan Pekerjaan (D+E) 31,992.40

JENIS PEKERJAAN : A.5.1.1.27 Pemasangan 1 M1 pipa PVC tipe AW diameter 1"


SATUAN : M1
HARGA SATUAN : Rp 33,952.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0360 105,000.00 3,780.00
Tukang L.02 OH 0.0600 150,000.00 9,000.00
Kepala tukang L.03 OH 0.0060 175,000.00 1,050.00
Mandor L.04 OH 0.0020 175,000.00 350.00
JUMLAH TENAGA KERJA 14,180.00
B BAHAN
Pipa PVC 1" m 1.2000 10,300.00 12,360.00
Perlengkapan % 35.0000 12,360.00 4,326.00
JUMLAH HARGA BAHAN 16,686.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 30,866.00
E Overhead & profit 10% x Jumlah 3,086.60
F Harga Satuan Pekerjaan (D+E) 33,952.60

JENIS PEKERJAAN : A.5.1.1.28 Pemasangan 1 M1 pipa PVC tipe AW diameter 1½"


SATUAN : M1
HARGA SATUAN : Rp 51,374.40

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0540 105,000.00 5,670.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 21,270.00
B BAHAN
Pipa PVC 1½" m 1.2000 15,700.00 18,840.00
Perlengkapan % 35.0000 18,840.00 6,594.00
JUMLAH HARGA BAHAN 25,434.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 46,704.00
E Overhead & profit 10% x Jumlah 4,670.40
F Harga Satuan Pekerjaan (D+E) 51,374.40

JENIS PEKERJAAN : A.5.1.1.29 Pemasangan 1 M1 pipa PVC tipe AW diameter 2"


SATUAN : M1
HARGA SATUAN : Rp 58,680.60

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0540 105,000.00 5,670.00
Tukang L.02 OH 0.0900 150,000.00 13,500.00
Kepala tukang L.03 OH 0.0090 175,000.00 1,575.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 21,270.00
B BAHAN
Pipa PVC 2" m 1.2000 19,800.00 23,760.00
Perlengkapan % 35.0000 23,760.00 8,316.00
JUMLAH HARGA BAHAN 32,076.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 53,346.00
E Overhead & profit 10% x Jumlah 5,334.60
F Harga Satuan Pekerjaan (D+E) 58,680.60
JENIS PEKERJAAN : A.5.1.1.30 Pemasangan 1 M1 pipa PVC tipe AW diameter 2½"
SATUAN : M1
HARGA SATUAN : Rp 82,044.05

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0810 105,000.00 8,505.00
Tukang L.02 OH 0.1350 150,000.00 20,250.00
Kepala tukang L.03 OH 0.0135 175,000.00 2,362.50
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 31,817.50
B BAHAN
Pipa PVC 2½" m 1.2000 26,400.00 31,680.00
Perlengkapan % 35.0000 31,680.00 11,088.00
JUMLAH HARGA BAHAN 42,768.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 74,585.50
E Overhead & profit 10% x Jumlah 7,458.55
F Harga Satuan Pekerjaan (D+E) 82,044.05

JENIS PEKERJAAN : A.5.1.1.31 Pemasangan 1 M1 pipa PVC tipe AW diameter 3"


SATUAN : M1
HARGA SATUAN : Rp 97,725.65

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0810 105,000.00 8,505.00
Tukang L.02 OH 0.1350 150,000.00 20,250.00
Kepala tukang L.03 OH 0.0135 175,000.00 2,362.50
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 31,817.50
B BAHAN
Pipa PVC 3" m 1.2000 35,200.00 42,240.00
Perlengkapan % 35.0000 42,240.00 14,784.00
JUMLAH HARGA BAHAN 57,024.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 88,841.50
E Overhead & profit 10% x Jumlah 8,884.15
F Harga Satuan Pekerjaan (D+E) 97,725.65

JENIS PEKERJAAN : A.5.1.1.32 Pemasangan 1 M1 pipa PVC tipe AW diameter 4"


SATUAN : M1
HARGA SATUAN : Rp 132,652.85

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0810 105,000.00 8,505.00
Tukang L.02 OH 0.1350 150,000.00 20,250.00
Kepala tukang L.03 OH 0.0135 175,000.00 2,362.50
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 31,817.50
B BAHAN
Pipa PVC 4" m 1.2000 54,800.00 65,760.00
Perlengkapan % 35.0000 65,760.00 23,016.00
JUMLAH HARGA BAHAN 88,776.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 120,593.50
E Overhead & profit 10% x Jumlah 12,059.35
F Harga Satuan Pekerjaan (D+E) 132,652.85

JENIS PEKERJAAN : A.5.1.1.33 Pemasangan 1 M1 pipa air limbah jenis pipa tanah diameter 20 Cm
SATUAN : M1
HARGA SATUAN : Rp 592,171.80

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.8000 105,000.00 84,000.00
Tukang L.02 OH 0.0400 150,000.00 6,000.00
Kepala tukang L.03 OH 0.0040 175,000.00 700.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 91,400.00
B BAHAN
Pipa tanah m1 1.6000 249,700.00 399,520.00
Semen Portland kg 35.0000 1,240.00 43,400.00
Pasir Pasang m3 0.0140 176,600.00 2,472.40
Pasir urug m3 0.0140 110,400.00 1,545.60
JUMLAH HARGA BAHAN 446,938.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 538,338.00
E Overhead & profit 10% x Jumlah 53,833.80
F Harga Satuan Pekerjaan (D+E) 592,171.80

JENIS PEKERJAAN : A.5.1.1.34 Pemasangan 1 M1 pipa air limbah jenis pipa tanah diameter 15 cm
SATUAN : M1
HARGA SATUAN : Rp 280,415.74

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0600 105,000.00 6,300.00
Tukang L.02 OH 0.0300 150,000.00 4,500.00
Kepala tukang L.03 OH 0.0030 175,000.00 525.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 11,850.00
B BAHAN
Pipa AW diameter 4" m1 1.6000 149,200.00 238,720.00
Semen Portland kg 0.6800 1,240.00 843.20
Pasir Pasang m3 0.0130 176,600.00 2,295.80
Pasir urug m3 0.0110 110,400.00 1,214.40
JUMLAH HARGA BAHAN 243,073.40
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 254,923.40
E Overhead & profit 10% x Jumlah 25,492.34
F Harga Satuan Pekerjaan (D+E) 280,415.74

JENIS PEKERJAAN : A.5.1.1.35 Pemasangan 1 M1 pipa beton diameter 15 - 20 Cm


SATUAN : M1
HARGA SATUAN : Rp 230,087.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1400 105,000.00 14,700.00
Tukang L.02 OH 0.0700 150,000.00 10,500.00
Kepala tukang L.03 OH 0.0070 175,000.00 1,225.00
Mandor L.04 OH 0.0070 175,000.00 1,225.00
JUMLAH TENAGA KERJA 27,650.00
B BAHAN
Pipa AW diameter 6" m1 1.1000 149,200.00 164,120.00
Bata Merah m3 0.0270 - -
Semen Portland kg 3.9200 1,240.00 4,860.80
Pasir Pasang m3 0.0560 176,600.00 9,889.60
Pasir urug m3 0.0240 110,400.00 2,649.60
JUMLAH HARGA BAHAN 181,520.00
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 209,170.00
E Overhead & profit 10% x Jumlah 20,917.00
F Harga Satuan Pekerjaan (D+E) 230,087.00

JENIS PEKERJAAN : A.5.1.1.36 Pemasangan 1 M1 pipa beton diameter 30 - 100 cm


SATUAN : M1
HARGA SATUAN : Rp 418,970.42

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.3800 105,000.00 39,900.00
Tukang L.02 OH 0.1900 150,000.00 28,500.00
Kepala tukang L.03 OH 0.0190 175,000.00 3,325.00
Mandor L.04 OH 0.0190 175,000.00 3,325.00
JUMLAH TENAGA KERJA 75,050.00
B BAHAN
Pipa AW diameter 8" m1 1.1000 249,700.00 274,670.00
Bata Merah m3 0.5500 - -
Semen Portland kg 10.3000 1,240.00 12,772.00
Pasir Pasang m3 0.0610 176,600.00 10,772.60
Pasir urug m3 0.0690 110,400.00 7,617.60
JUMLAH HARGA BAHAN 305,832.20
C PERALATAN

JUMLAH HARGA ALAT -


D JUMLAH (A+B+C) 380,882.20
E Overhead & profit 10% x Jumlah 38,088.22
F Harga Satuan Pekerjaan (D+E) 418,970.42

HARGA SATUAN PEKERJAAN PEMASANGAN PIPA

JENIS PEKERJAAN : A.8.4.1.1 Pemasangan 1 m pipa PVC diameter 50 mm


SATUAN : M
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0810 105,000.00 8,505.00
Tukang L.02 OH 0.0410 150,000.00 6,150.00
Mandor L.04 OH 0.0080 175,000.00 1,400.00
JUMLAH TENAGA KERJA 16,055.00
B BAHAN
Pipa PVC dia 50 mm Unit 1.0000 27,700.00 27,700.00
JUMLAH HARGA BAHAN 27,700.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0060 A #VALUE!
handle crane 2 T
JUMLAH HARGA ALAT #VALUE!
D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.8.4.1.1 Pemasangan 1 m pipa PVC diameter 63 mm


SATUAN : M1
HARGA SATUAN : Rp 48,158.88

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0810 96,100.00 7,784.10
Tukang L.02 OH 0.0410 129,500.00 5,309.50
Mandor L.04 OH 0.0080 148,400.00 1,187.20
148400.000 14,280.80
B BAHAN
Pipa PVC dia 63 mm m 1.0000 27,700.00 27,700.00
JUMLAH HARGA BAHAN 27,700.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0060 300,000.00 1,800.00
handle crane 2 T
JUMLAH HARGA ALAT 1,800.00
D JUMLAH (A+B+C) 43,780.80
E Overhead & profit 10% x Jumlah 4,378.08
F Harga Satuan Pekerjaan (D+E) 48,158.88

JENIS PEKERJAAN : A.8.4.1.2 Pemasangan 1 m pipa PVC diameter 75 mm


SATUAN : M
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0880 105,000.00 9,240.00
Tukang L.02 OH 0.0440 150,000.00 6,600.00
Mandor L.04 OH 0.0088 175,000.00 1,540.00
JUMLAH TENAGA KERJA 17,380.00
B BAHAN
Pipa PVC dia 75 mm Unit 1.0000 39,000.00 39,000.00
JUMLAH HARGA BAHAN 39,000.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0080 A #VALUE!
handle crane 2 T
JUMLAH HARGA ALAT #VALUE!
D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.8.4.1.2 Pemasangan 1 m pipa PVC diameter 90 mm


SATUAN : M1
HARGA SATUAN : Rp 82,494.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0940 105,000.00 9,870.00
Tukang L.02 OH 0.0470 150,000.00 7,050.00
Mandor L.04 OH 0.0090 175,000.00 1,575.00
JUMLAH TENAGA KERJA 18,495.00
B BAHAN
Pipa PVC dia 90 mm m 1.0000 54,100.00 54,100.00
JUMLAH HARGA BAHAN 54,100.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0080 300,000.00 2,400.00
handle crane 2 T
JUMLAH HARGA ALAT 2,400.00
D JUMLAH (A+B+C) 74,995.00
E Overhead & profit 10% x Jumlah 7,499.50
F Harga Satuan Pekerjaan (D+E) 82,494.50

JENIS PEKERJAAN : A.8.4.1.3 Pemasangan 1 m pipa PVC diameter 110 mm


SATUAN : M1
HARGA SATUAN : Rp 118,470.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1050 105,000.00 11,025.00
Tukang L.02 OH 0.0530 150,000.00 7,950.00
Mandor L.04 OH 0.0110 175,000.00 1,925.00
JUMLAH TENAGA KERJA 20,900.00
B BAHAN
Pipa PVC dia 110 mm m 1.0000 83,800.00 83,800.00
JUMLAH HARGA BAHAN 83,800.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0100 300,000.00 3,000.00
handle crane 2 T
JUMLAH HARGA ALAT 3,000.00
D JUMLAH (A+B+C) 107,700.00
E Overhead & profit 10% x Jumlah 10,770.00
F Harga Satuan Pekerjaan (D+E) 118,470.00

JENIS PEKERJAAN : A.8.4.1.4 Pemasangan 1 m pipa PVC diameter 150 mm


SATUAN : M1
HARGA SATUAN : Rp 193,754.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1180 105,000.00 12,390.00
Tukang L.02 OH 0.0590 150,000.00 8,850.00
Mandor L.04 OH 0.0120 175,000.00 2,100.00
JUMLAH TENAGA KERJA 23,340.00
B BAHAN
Pipa PVC dia 150 mm m 1.0000 149,200.00 149,200.00
JUMLAH HARGA BAHAN 149,200.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0120 300,000.00 3,600.00
handle crane 2 T
JUMLAH HARGA ALAT 3,600.00
D JUMLAH (A+B+C) 176,140.00
E Overhead & profit 10% x Jumlah 17,614.00
F Harga Satuan Pekerjaan (D+E) 193,754.00

JENIS PEKERJAAN : A.8.4.1.5 Pemasangan 1 m pipa PVC diameter 200 mm


SATUAN : M1
HARGA SATUAN : Rp 374,132.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.1890 105,000.00 19,845.00
Tukang L.02 OH 0.0950 150,000.00 14,250.00
Mandor L.04 OH 0.0190 175,000.00 3,325.00
JUMLAH TENAGA KERJA 37,420.00
B BAHAN
Pipa PVC dia 200 mm m 1.0000 295,500.00 295,500.00
JUMLAH HARGA BAHAN 295,500.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0240 300,000.00 7,200.00
handle crane 2 T
JUMLAH HARGA ALAT 7,200.00
D JUMLAH (A+B+C) 340,120.00
E Overhead & profit 10% x Jumlah 34,012.00
F Harga Satuan Pekerjaan (D+E) 374,132.00

JENIS PEKERJAAN : A.8.4.1.6 Pemasangan 1 m pipa PVC diameter 250 mm


SATUAN : M1
HARGA SATUAN : Rp 655,193.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2560 105,000.00 26,880.00
Tukang L.02 OH 0.1280 150,000.00 19,200.00
Mandor L.04 OH 0.0260 175,000.00 4,550.00
JUMLAH TENAGA KERJA 50,630.00
B BAHAN
Pipa PVC dia 250 mm m 1.0000 534,800.00 534,800.00
JUMLAH HARGA BAHAN 534,800.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0340 300,000.00 10,200.00
handle crane 2 T
JUMLAH HARGA ALAT 10,200.00
D JUMLAH (A+B+C) 595,630.00
E Overhead & profit 10% x Jumlah 59,563.00
F Harga Satuan Pekerjaan (D+E) 655,193.00

JENIS PEKERJAAN : A.8.4.1.7 Pemasangan 1 m pipa PVC diameter 300 mm


SATUAN : M1
HARGA SATUAN : Rp 1,086,904.50

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.2940 105,000.00 30,870.00
Tukang L.02 OH 0.1470 150,000.00 22,050.00
Mandor L.04 OH 0.0290 175,000.00 5,075.00
JUMLAH TENAGA KERJA 57,995.00
B BAHAN
Pipa PVC dia 300 mm m 1.0000 918,100.00 918,100.00
JUMLAH HARGA BAHAN 918,100.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0400 300,000.00 12,000.00
handle crane 2 T
JUMLAH HARGA ALAT 12,000.00
D JUMLAH (A+B+C) 988,095.00
E Overhead & profit 10% x Jumlah 98,809.50
F Harga Satuan Pekerjaan (D+E) 1,086,904.50

JENIS PEKERJAAN : A.8.4.1.8 Pemasangan 1 m pipa PVC diameter 400 mm


SATUAN : M1
HARGA SATUAN : Rp 1,802,867.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.5440 105,000.00 57,120.00
Tukang L.02 OH 0.2720 150,000.00 40,800.00
Mandor L.04 OH 0.0540 175,000.00 9,450.00
JUMLAH TENAGA KERJA 107,370.00
B BAHAN
Pipa PVC dia 400 mm m 1.0000 1,507,600.00 1,507,600.00
JUMLAH HARGA BAHAN 1,507,600.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0800 300,000.00 24,000.00
handle crane 2 T
JUMLAH HARGA ALAT 24,000.00
D JUMLAH (A+B+C) 1,638,970.00
E Overhead & profit 10% x Jumlah 163,897.00
F Harga Satuan Pekerjaan (D+E) 1,802,867.00

JENIS PEKERJAAN : A.8.4.1.9 Pemasangan 1 m pipa PVC diameter 450 mm


SATUAN : M1
HARGA SATUAN : Rp 2,322,782

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.6690 105,000.00 70,245.00
Tukang L.02 OH 0.3350 150,000.00 50,250.00
Mandor L.04 OH 0.0670 175,000.00 11,725.00
JUMLAH TENAGA KERJA 132,220.00
B BAHAN
Pipa PVC dia 450 mm m 1.0000 1,949,400.00 1,949,400.00
JUMLAH HARGA BAHAN 1,949,400.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.1000 300,000.00 30,000.00
handle crane 2 T
JUMLAH HARGA ALAT 30,000.00
D JUMLAH (A+B+C) 2,111,620.00
E Overhead & profit 10% x Jumlah 211,162.00
F Harga Satuan Pekerjaan (D+E) 2,322,782.00

JENIS PEKERJAAN : A.8.4.1.10 Pemasangan 1 m pipa PVC diameter 500 mm


SATUAN : M1
HARGA SATUAN : Rp 2,846,437

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.8090 105,000.00 84,945.00
Tukang L.02 OH 0.4050 150,000.00 60,750.00
Mandor L.04 OH 0.0810 175,000.00 14,175.00
JUMLAH TENAGA KERJA 159,870.00
B BAHAN
Pipa PVC dia 500 mm m 1.0000 2,391,200.00 2,391,200.00
JUMLAH HARGA BAHAN 2,391,200.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.1220 300,000.00 36,600.00
handle crane 2 T
JUMLAH HARGA ALAT 36,600.00
D JUMLAH (A+B+C) 2,587,670.00
E Overhead & profit 10% x Jumlah 258,767.00
F Harga Satuan Pekerjaan (D+E) 2,846,437.00

JENIS PEKERJAAN : A.8.4.1.11 Pemasangan 1 m pipa PVC diameter 600 mm


SATUAN : M
HARGA SATUAN : Rp 4,493,429

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.9570 105,000.00 100,485.00
Tukang L.02 OH 0.4790 150,000.00 71,850.00
Mandor L.04 OH 0.0960 175,000.00 16,800.00
JUMLAH TENAGA KERJA 189,135.00
B BAHAN
Pipa PVC dia 600 mm m 1.0000 3,852,300.00 3,852,300.00
JUMLAH HARGA BAHAN 3,852,300.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.1450 300,000.00 43,500.00
handle crane 2 T
JUMLAH HARGA ALAT 43,500.00
D JUMLAH (A+B+C) 4,084,935.00
E Overhead & profit 10% x Jumlah 408,493.50
F Harga Satuan Pekerjaan (D+E) 4,493,428.50

JENIS PEKERJAAN : A.8.4.1.12 Pemasangan 1 m pipa PVC diameter 800 mm


SATUAN : M
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6180 105,000.00 169,890.00
Tukang L.02 OH 0.8090 150,000.00 121,350.00
Mandor L.04 OH 0.1620 175,000.00 28,350.00
JUMLAH TENAGA KERJA 319,590.00
B BAHAN
Pipa PVC dia 800 mm m 1.0000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN
Sewa Tripot/Tackel & Hari 0.2500 300,000.00 75,000.00
handle crane 2 T
JUMLAH HARGA ALAT 75,000.00
D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.8.4.1.13 Pemasangan 1 m pipa PVC diameter 900 mm


SATUAN : M
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.6910 105,000.00 177,555.00
Tukang L.02 OH 0.8460 150,000.00 126,900.00
Mandor L.04 OH 0.1690 175,000.00 29,575.00
JUMLAH TENAGA KERJA 334,030.00
B BAHAN
Pipa PVC dia 900 mm Unit 1.0000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN
Sewa Tripot/Tackel & Hari 0.2620 300,000.00 78,600.00
handle crane 2 T
JUMLAH HARGA ALAT 78,600.00
D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.8.4.1.14 Pemasangan 1 m pipa PVC diameter 1000 mm


SATUAN : M
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 1.8950 105,000.00 198,975.00
Tukang L.02 OH 0.9480 150,000.00 142,200.00
Mandor L.04 OH 0.1900 175,000.00 33,250.00
JUMLAH TENAGA KERJA 374,425.00
B BAHAN
Pipa PVC dia 1000 mm Unit 1.0000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN
Sewa Tripot/Tackel & Hari 0.2940 300,000.00 88,200.00
handle crane 2 T
JUMLAH HARGA ALAT 88,200.00
D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.8.4.1.15 Pemasangan 1 m pipa PVC diameter 1100 mm


SATUAN : M
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 2.0990 105,000.00 220,395.00
Tukang L.02 OH 1.0500 150,000.00 157,500.00
Mandor L.04 OH 0.2100 175,000.00 36,750.00
JUMLAH TENAGA KERJA 414,645.00
B BAHAN
Pipa PVC dia 1100 mm m 1.0000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN
Sewa Tripot/Tackel & Hari 0.3270 300,000.00 98,100.00
handle crane 2 T
JUMLAH HARGA ALAT 98,100.00
D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.8.4.1.16 Pemasangan 1 m pipa PVC diameter 1200 mm


SATUAN : M
HARGA SATUAN : #VALUE!

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 2.3030 105,000.00 241,815.00
Tukang L.02 OH 1.1520 150,000.00 172,800.00
Mandor L.04 OH 0.2300 175,000.00 40,250.00
JUMLAH TENAGA KERJA 454,865.00
B BAHAN
Pipa PVC dia 1200 mm m 1.0000 a #VALUE!
JUMLAH HARGA BAHAN #VALUE!
C PERALATAN
Sewa Tripot/Tackel & Hari 0.3590 300,000.00 107,700.00
handle crane 2 T
JUMLAH HARGA ALAT 107,700.00
D JUMLAH (A+B+C) #VALUE!
E Overhead & profit 10% x Jumlah #VALUE!
F Harga Satuan Pekerjaan (D+E) #VALUE!

JENIS PEKERJAAN : A.8.4.1.17 Pemasangan 1 m pipa HDPE diameter 63 mm


SATUAN : M
HARGA SATUAN : Rp 56,815.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0350 105,000.00 3,675.00
Tukang L.02 OH 0.0170 150,000.00 2,550.00
Mandor L.04 OH 0.0030 175,000.00 525.00
JUMLAH TENAGA KERJA 6,750.00
B BAHAN
Pipa HDPE dia 63 mm m 1.0000 39,200.00 39,200.00
JUMLAH HARGA BAHAN 39,200.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0190 300,000.00 5,700.00
handle crane 2 T
JUMLAH HARGA ALAT 5,700.00
D JUMLAH (A+B+C) 51,650.00
E Overhead & profit 10% x Jumlah 5,165.00
F Harga Satuan Pekerjaan (D+E) 56,815.00

JENIS PEKERJAAN : A.8.4.1.18 Pemasangan 1 m pipa HDPE diameter 100 mm


SATUAN : M
HARGA SATUAN : Rp 217,910.00

NO URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
Pekerja L.01 OH 0.0400 105,000.00 4,200.00
Tukang L.02 OH 0.0200 150,000.00 3,000.00
Mandor L.04 OH 0.0040 175,000.00 700.00
JUMLAH TENAGA KERJA 7,900.00
B BAHAN
Pipa HDPE dia 100 mm m 1.0000 184,500.00 184,500.00
JUMLAH HARGA BAHAN 184,500.00
C PERALATAN
Sewa Tripot/Tackel & Hari 0.0190 300,000.00 5,700.00
handle crane 2 T
JUMLAH HARGA ALAT 5,700.00
D JUMLAH (A+B+C) 198,100.00
E Overhead & profit 10% x Jumlah 19,810.00
F Harga Satuan Pekerjaan (D+E) 217,910.00

JENIS PEKERJAAN : A.8.4.1.19 Pemasangan 1 m pipa HDPE diameter 125 mm


SATUAN : M
HARGA SATUAN : Rp 330,055

NO URAIAN KODE KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)


SATUAN

A TENAGA
Pekerja L.01 OH 0.0450 105,000.00 4,725.00
Tukang L.02 OH 0.0230 150,000.00 3,450.00
Mandor L.04 OH 0.0050 175,000.00 875.00
RENCANA ANGGARAN BIAYA (RAB)

PROGRAM : PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM ( PSU )


KEGIATAN : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
SUBKEGIATAN : PERENCANAAN PENYEDIAAN PSU PERMUKIMAN
PEKERJAAN : PERENCANAAN PEMBANGUNAN MCK JORONG LOMPATAN KABUPATEN TANAH DATAR
LOKASI : JORONG LOMPATAN KABUPATEN TANAH DATAR
TAHUN ANGGARAN : 2021

HARGA JUMLAH TOTAL


NO URAIAN PEKERJAAN STN VLM SATUAN HARGA
(Rp.) (Rp.) (Rp.)

A PEKERJAAN PENDAHULUAN & PERSIAPAN 3,800,000.00

I Plank Nama Proyek Ls 1.00 250,000.00 250,000.00

II Perlengkapan K3
1 Safety helmet Bh 5.00 45,000.00 225,000.00
2 Sarung tangan Bh 5.00 25,000.00 125,000.00
3 Rompi Bh 5.00 75,000.00 375,000.00
4 Rambu Peringatan Bh 1.00 100,000.00 100,000.00
5 sepatu Boot Bh 5.00 65,000.00 325,000.00
6 Prokest Covid Ls 1.00 400,000.00 400,000.00

III Managemen Mutu Ls 1.00 2,000,000.00 2,000,000.00

B PEKERJAAN PEMBONGKARAN DAN PEMBERSIHAN 4,190,455.07

I Pekerjaan Pembongkaran Keramik Lama


1 Pembongkaran Keramik Lantai M2 26.67 7,700.00 205,339.75
2 Pembongkaran Keramik Dinding M2 43.12 7,700.00 332,024.00

II Pekerjaan Pembongkaran Dinding Bata dan Pipa


1 Pembongkaran Dinding Bata Pemisah Urinor T.Wudhu Wanita m3 0.45 834,141.00 371,609.82
2 Pembongkaran Pipa-Pipa Air Bersih Lama Ls 1.00 300,000.00 300,000.00
3 Pembuangan Sisa-Sisa Bongkaran Ke Tempat Pembuangan Ls 1.00 800,000.00 800,000.00
( Termasuk Sewa Mobil L300, Upah Muat dan Pembuangan )

III Pengikisan/pengerokan dan Pembersihan permukaan cat lama Bagian Dalam M2 112.52 19,387.50 2,181,481.50

C PEKRJAAN PASANGAN DINDING DAN KERAMIK 52,165,671.21

I PASANGAN DINDING 1/2 BATA SP 1:4


1 Dinding Pembatas Urinor Untuk T. Wudhu Wanita M2 2.31 133,901.68 309,312.88
2 Dinding Pembatas T.Wudhu M2 3.75 133,901.68 502,131.30

II PEKERJAAN PASANGAN KERAMIK


1 Pasangan Keramik Lantai 25x25 ( IKAD ) Kasar M2 27.49 296,666.70 8,154,625.92
2 Pasangan Dinding Keramik 25x40 Polished ( IKAD ) Type 1 m2 99.06 361,170.48 35,777,547.75
3 Pasangan Dinding Keramik 25x40 Polisher ( IKAD ) Type 2 M2 10.28 361,170.48 3,711,026.68

D PEKRJAAN KUZEN, DAUN PINTU DAN VENTILASI 7,486,729.21

I Pekerjaan Kuzen Kayu Kelas II


1 Kuzen Kayu Untuk Pinti P3 m3 0.03 8,111,917.00 256,985.53

II Pasangan Daun Pintu


1 Daun Pintu Panil Kayu Kelas II Untuk P1 M2 3.12 816,624.60 2,547,868.75
2 Daun Pintu Panil Kayu Kelas II Untuk P3 M2 1.20 816,624.60 977,499.65
3 Daun Pintu Fiber untuk P2 ( 0,7*1.95) Bh 2.00 600,000.00 1,200,000.00
4 Pasangan Kaca tbl. 5 mm untuk Ventilasi M2 3.18 159,346.00 506,720.28
5 Pasangan Kunci Tanam Pintu Antik Bh 2.00 419,677.50 839,355.00
6 Pasangan Engsel Pintu 4" Bh 10.00 54,384.00 543,840.00
7 Pasangan Grendel Pintu Bh 6.00 102,410.00 614,460.00

E PEKERJAAN PENGECATAN 4,181,604.94

I Pekerjaan Pengecatan Dinding


1 Pengecatan Dinding Dalam dengan Jotun Interior( 1 lapis Alkali, 2 Lapis Cat Penutup ) M2 84.01 23,034.00 1,935,086.34
2 Pengecatan Dinding Luar dengan Jotun Exterior ( 1 lapis Alkali, 2 Lapis Cat Penutup ) M2 32.87 35,310.00 1,160,639.70

II Pekerjaan Pengecatan Kayu


1 Pengecatan Kuzen Kayu (1lapis plamuur, 1 lapis cat dasar,2 lapis cat penutup) M2 11.74 49,820.10 584,688.69
2 Pengecatan Daun Pintu Kayu (1lapis plamuur, 1 lapis cat dasar,2 lapis cat penutup) M2 10.06 49,820.10 501,190.21

F PEKERJAAN PLAFOUND 9,554,307.53

I Pekerjaan Pasangan Plafound Pvc ( JAVAPOND ) + Rangka Hollow Zinclaume4x4cm


1 Plafound Area Wanita M2 15.88 207,477.60 3,293,810.64
2 Plafound Area Pria M2 15.88 207,477.60 3,293,810.64

II Pekerjaan Pasangan Lest Pvc ( JAVAPOND ) Cutting L


1 Plafound Area Wanita M 89.75 16,527.50 1,483,343.13
2 Plafound Area Pria M 89.75 16,527.50 1,483,343.13

G PEKERJAAN INSTALASI LISTRIK DAN LAMPU 4,587,000.00

1 Pemasangan Titik Lampu ( Downligh LED 18 Watt ) Putih ( Philips ) Ttk 4.00 355,300.00 1,421,200.00
2 Pemasangan Titik Lampu ( Downligh LED 8 Watt ) Kuning ( Philips ) Ttk 8.00 245,300.00 1,962,400.00
3 Pemasangan Titik Lampu ( Downligh LED 8 Watt ) Putih ( Philips ) Ttk 4.00 245,300.00 981,200.00
4 Pasangan Saklar Seri bh 2.00 40,700.00 81,400.00
5 Pasangan Saklar Tunggal bh 4.00 35,200.00 140,800.00

H PEKERJAAN SANITASI DALAM GEDUNG 3,294,962.66

1 Pasangan Pipa 1 x1/2" untuk Saluran Kran berwudhu, urinor dan Bak Toilet M 15.00 51,374.40 770,616.00
2 Pasangan Pipa 3/2" untuk Kran M 3.40 31,992.40 108,774.16
3 Pasangan Kran Stainlesee Bh 17.00 142,092.50 2,415,572.50
I PEKERJAAN PENAMBAHAN TEMPAT WUDHU BARU DISAMPING MASJID 15,204,306.79

I Pekerjaan Galian Tanah


1 Galian Tanah Untuk Penempatan Sloof m3 0.32 91,437.50 28,802.81

II Pekerjaan Pemasangan Sloof 15/20 cm


1 Beton Camp 1:2:3 setara K175 m3 0.14 957,798.73 129,302.83
2 Pembesian Kg 17.46 14,726.80 257,090.27
3 Bekisting Sloof m2 1.80 248,469.65 447,245.37

III Pekerjaan Pasangan Dinding


1 Pasangan 1/2 Bata Sp 1:4 m2 13.18 133,901.68 1,764,824.14
2 Plesteran Sp 1:4 m2 8.79 78,348.60 688,684.19
3 Acian m2 8.79 47,883.00 420,891.57

IV Pekerjaan Lantai dan Keramik


1 Cor Beton Lantai Camp 1:2:3 Setara K175 m3 0.35 957,798.73 338,749.47
2 Pasangan Keramik Lantai Ukuran 25*25 ( Ikad ) Kasar m2 5.05 296,666.70 1,498,908.50
3 Pasangan Dinding Keramik 25x40 ( Ikad ) Polished Type 1 m2 14.22 361,170.48 5,134,038.37

V Pekerjaan Pengecatan
1 Pengecatan Dinding Dalam dengan Jotun Interior( 1 lapis Alkali, 2 Lapis Cat Penutup ) m2 8.79 23,034.00 202,468.86

VI Pekerjaan Sanitasi
1 Pasangan Pipa 1 x1/2" untuk Saluran Kran berwudhu dari Tangki air ke lokasi M 46.00 51,374.40 2,363,222.40
2 Pasangan Pipa 3/2" untuk Kran M 0.40 31,992.40 12,796.96
3 Pasangan Kran Stainlesee Bh 4.00 142,092.50 568,370.00

VII Pekerjaab=n Instalasi Titik Lampu


1 Pemasangan Titik Lampu ( Downligh LED 8 Watt ) Putih ( Philips ) bh 1.00 245,300.00 245,300.00
2 Pasangan Saklar Tunggal bh 1.00 35,200.00 35,200.00

VIII Pekerjaan Plat Deker


1 Beton Camp 1:2:3 setara K175 m3 0.18 957,798.73 172,403.77
2 Pembesian Kg 13.32 14,726.80 196,107.96
3 Bekisting Lantai m2 1.80 388,832.95 699,899.31

J PEKERJAAN AKHIR 250,000.00

1 Pek. Pembersihan Akhir Ls 1.00 250,000.00 250,000.00

:Dibuat oleh
KONSULTAN PERENCANA
CV. GREEN RISE CONSULTANT

ALDY, ST
Team Leader
DAFTAR ANALISA
HARGA SATUAN PEKERJAAN MEKANIKA / ELEKTRIKAL

PROGRAM : PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM ( PSU )


KEGIATAN : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
SUBKEGIATAN : PERENCANAAN PENYEDIAAN PSU PERMUKIMAN
PEKERJAAN : PERENCANAAN PEMBANGUNAN MCK JORONG LOMPATAN KABUPATEN TANAH DATAR
LOKASI : JORONG LOMPATAN KABUPATEN TANAH DATAR
TAHUN ANGGARAN : 2021

HARGA SATUAN JUMLAH HARGA


No STN KOEFISIEN (Rp) (Rp)

A PEKERJAAN ELEKTRIKAL ARUS KUAT & ARUS LEMAH


INSTALASI
1. Pas. Instalasi Titik Lampu Downlight 18 Watt
Kabel NYM 3 x 2.5 mm2 M1 8.0000 11,000.00 88,000.00
PVC Hight Impact dia. 20 mm2 M1 8.0000 5,000.00 40,000.00
Coupling / Socket dia. 20 mm2 Bh 4.0000 1,000.00 4,000.00
Clamp Cable dia. 20 mm2 Bh 6.0000 1,000.00 6,000.00
Junction Box Bh 1.0000 5,000.00 5,000.00
Downligjt LED 18 Watt Bh 1.0000 150,000.00 150,000.00
Material / Alat Bantu Ls 1.0000 10,000.00 10,000.00
Upah Pasang Lot 1.0000 20,000.00 20,000.00
Jumlah 323,000.00
0 Overhead 10 % 32,300.00
Jumlah 355,300.00

1. Pas. Instalasi Titik Lampu Downlight 8 Watt


Kabel NYM 3 x 2.5 mm2 M1 8.0000 11,000.00 88,000.00
PVC Hight Impact dia. 20 mm2 M1 8.0000 5,000.00 40,000.00
Coupling / Socket dia. 20 mm2 Bh 4.0000 1,000.00 4,000.00
Clamp Cable dia. 20 mm2 Bh 6.0000 1,000.00 6,000.00
Junction Box Bh 1.0000 5,000.00 5,000.00
Downligjt LED 8 Watt Bh 1.0000 50,000.00 50,000.00
Material / Alat Bantu Ls 1.0000 10,000.00 10,000.00
Upah Pasang Lot 1.0000 20,000.00 20,000.00
Jumlah 223,000.00
0 Overhead 10 % 22,300.00
Jumlah 245,300.00
18. Pas. Saklar Tunggal Schneider
Saklar Tunggal Unit 1.0000 25,000.00 25,000.00
Inbow Dus Unit 1.0000 7,000.00 7,000.00
Jumlah 32,000.00
0 Overhead 10 % 3,200.00
Jumlah 35,200.00
Dibulatkan 35,200.00
19. Pas. Saklar Ganda Schneider
Saklar Ganda Unit 1.0000 30,000.00 30,000.00
Inbow Dus Unit 1.0000 7,000.00 7,000.00
Jumlah 37,000.00
0 Overhead 10 % 3,700.00
Jumlah 40,700.00
Dibulatkan 40,700.00
ADDENDUM

PROGRAM : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)


KEGIATAN : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
SUB KEGIATAN : PERENCANAAN PENYEDIAAN PSU PERMUKIMAN
PEKERJAAN :
PERENCANAAN PEMBANGUNAN MCK JORONG LOMPATAN KABUPATEN TANAH DATAR
LOKASI : KAB. TANAH DATAR
NO. KONTRAK : 126/SPK.KPA/FISIK.PSU/KP-PERKIMTAN/X-2021
TANGGAL KONTRAK : 4 OKTOBER 2021
NO. KONTRAK ADD : 126.ADD-01/SPK.KPA/FISIK.PSU/KP-PERKIMTAN/X-2021
TANGGAL KONTRAK ADD : 7 OKTOBER 2021

MC-0 PEKERJAAN KURANG PEKERJAAN TAMBAH ADDENDUM


HARGA
NO. URAIAN PEKERJAAN STN JUMLAH HARGA Bobot JUMLAH JUMLAH JUMLAH Bobot KETERANGAN
VOLUME SATUAN VOLUME VOLUME VOLUME
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
A A. PEKERJAAN PENDAHULUAN & PERSIAPAN
I Plank Nama Proyek Ls 1.00 200,000 200,000 0.19 - - - - 1.00 200,000 0.19
II Perlengkapan K3 - - - - - - - - -
1 Safety helmet Bh 5.00 40,000 200,000 0.19 - - - - 5.00 200,000 0.19
2 Sarung tangan Bh 5.00 10,000 50,000 0.05 - - - - 5.00 50,000 0.05
3 Rompi Bh 5.00 75,000 375,000 0.36 - - - - 5.00 375,000 0.36
4 Rambu Peringatan Bh 1.00 100,000 100,000 0.10 - - - - 1.00 100,000 0.10
5 sepatu Boot Bh 1.00 70,000 70,000 0.07 - - - - 1.00 70,000 0.07
6 Prokest Covid Ls 1.00 300,000 300,000 0.29 - - - - 1.00 300,000 0.29
III Managemen Mutu Ls 1.00 1,900,000 1,900,000 1.82 - - - - 1.00 1,900,000 1.82
0.00 - - - - - - - - - -
B PEKERJAAN PEMBONGKARAN DAN PEMBERSIHAN 0.00 - - - - - - - - - -
I Pekerjaan Pembongkaran Keramik Lama - - - - - - - - - -
1 Pembongkaran Keramik Lantai M2 29.01 8,000 232,080 0.22 - - - - 29.01 232,080 0.22
2 Pembongkaran Keramik Dinding M2 53.30 8,500 453,050 0.43 - - - - 53.30 453,050 0.43
II Pekerjaan Pembongkaran Dinding Bata dan Pipa - - - - - - - - - -
1 Pembongkaran Dinding Bata Pemisah Urinor T.Wudhu Wanita m3 2.29 834,141 1,910,183 1.83 - - - - 2.29 1,910,183 1.83
2 Pembongkaran Pipa-Pipa Air Bersih Lama Ls 1.00 300,000 300,000 0.29 - - - - 1.00 300,000 0.29
3 Pembongkaran Pintu Toilet Lama Ls 1.00 100,000 100,000 0.10 - - - - 1.00 100,000 0.10
4 Pembongkaran Kozen Ventilasi Ls 1.00 100,000 100,000 0.10 - - - - 1.00 100,000 0.10
5 Pembuangan Sisa-Sisa Bongkaran Ke Tempat Pembuangan Ls 1.00 800,000 800,000 0.77 - - - - 1.00 800,000 0.77
( Termasuk Sewa Mobil L300, Upah Muat dan Pembuangan ) - - - - - - - - - -
6 Pembongkaran Toilet Lama Ls 1.00 300,000 300,000 0.29 - - - - 1.00 300,000 0.29
III M2 112.52 19,388 2,181,482 2.09 - - - - 112.52 2,181,482 2.09
Pengikisan/pengerokan dan Pembersihan permukaan cat lama Bagian Dalam
- - - - - - - - - -
C PEKERJAAN PASANGAN DINDING DAN KERAMIK - - - - - - - - - -
I PASANGAN DINDING 1/2 BATA SP 14 - - - - - - - - - -
1 Dinding Pembatas Urinor Untuk T. Wudhu Wanita M2 133,902 - - - - - - - - -
1 Dinding Pembatas T.Wudhu M2 6.72 133,902 899,819 0.86 - - - - 6.72 899,819 0.86
II PEKERJAAN PASANGAN KERAMIK 0.00 - - - - - - - - - -
1 Pasangan Keramik Lantai 25x25 ( IKAD ) Kasar M2 32.42 296,667 9,617,934 9.22 - - - - 32.42 9,617,934 9.22
2 Pasangan Dinding Keramik 25x40 Polished ( IKAD ) Type 1 m2 78.71 361,170 28,427,728 27.25 - - - - 78.71 28,427,728 27.25
3 Pasangan Dinding Keramik 25x40 Polisher ( IKAD ) Type 2 M2 361,170 - - - - - - - - -
3 Pasangan Bon-Bon Keramik m 56.74 69,214 3,927,207 3.76 - - - - 56.74 3,927,207 3.76
- - - - - - - - - -
D PEKERJAAN KUZEN, DAUN PINTU DAN VENTILASI - - - - - - - - - -
I Pekerjaan Kuzen Aluminium - - - - - - - - - -
1 Kuzen Kayu Untuk Pinti P3 m3 8,111,917 - - - - - - - - -
1 Kuzen Aluminium Untuk Pintu P2 m 9.20 165,204 1,519,872 1.46 - - - - 9.20 1,519,872 1.46
II Pekerjaan Daun Pintu Alumunium P2 - - - - - - - - - -
II Pasangan Daun Pintu - - - - - - - - - -
1 Daun Pintu Panil Kayu Kelas II Untuk P1 M2 816,625 - - - - - - - - -
2 Daun Pintu Panil Kayu Kelas II Untuk P3 M2 816,625 - - - - - - - - -
3 Daun Pintu Fiber untuk P2 ( 0,7*1.95) Bh 550,000 - - - - - - - - -
4 Pasangan Kaca tbl. 5 mm untuk Ventilasi M2 159,346 - - - - - - - - -
5 Pasangan Kunci Tanam Pintu Antik Bh 419,678 - - - - - - - - -
6 Pasangan Engsel Pintu 4 Bh 54,384 - - - - - - - - -
7 Pasangan Grendel Pintu Bh 102,410 - - - - - - - - -
1 Pekerjaan Daun Pintu Alumunium P2 M2 2.66 558,687 1,486,108 1.42 - - - - 2.66 1,486,108 1.42
2 Pekerjaan Kuzen Ventilasi M2 0.07 8,111,917 594,571 0.57 - - - - 0.07 594,571 0.57
3 Pas. Kaca tbl.5 mm untuk ventilasi Bh 2.81 159,346 446,966 0.43 - - - - 2.81 446,966 0.43
- - - - - - - - - -
E PEKERJAAN PENGECATAN - - - - - - - - - -
I Pekerjaan Pengecatan Dinding - - - - - - - - - -
1 Pengecatan Dinding Dalam dengan Jotun Interior( 1 lapis Alkali, 2 Lapis Cat Penutup ) M2 109.13 23,034 2,513,585 2.41 - - - - 109.13 2,513,585 2.41
2 Pengecatan Dinding Luar dengan Jotun Exterior ( 1 lapis Alkali, 2 Lapis Cat Penutup ) M2 7.13 35,310 251,584 0.24 - - - - 7.13 251,584 0.24
3 Pengecatan Dinding Masjid dan Dinding Luar MCK dengan Jotun Exterior ( 1 lapis Alkali, 2 Lapis Cat Penutup ) M2 139.22 35,310 4,915,954 4.71 139.22 4,915,954 4.71
II Pekerjaan Pengecatan Kayu - - - - - - - - - -
1 Pengecatan Kuzen Kayu (1lapis plamuur, 1 lapis cat dasar,2 lapis cat penutup) M2 1.33 49,820 66,012 0.06 - - - - 1.33 66,012 0.06
2 Pengecatan Daun Pintu Kayu (1lapis plamuur, 1 lapis cat dasar,2 lapis cat penutup) M2 49,820 - - - - - - - - -
- - - - - - - - - -
III Pekerjaan Pengecatan Besi - - - - - - - - - -
1 Pengecatan Pintu Besi M2 3.66 37,400 136,914 0.13 - - - - 3.66 136,914 0.13
- - - - - - - - - -
F PEKERJAAN PLAFOUND - - - - - - - - - -
I Pekerjaan Pasangan Plafound Pvc ( JAVAPOND ) + Rangka Hollow Zinclaume4x4cm - - - - - - - - - -
1 Plafound Area Wanita M2 207,478 - - - - - - - - -
2 Plafound Area Pria M2 207,478 - - - - - - - - -
II Pekerjaan Pasangan Lest Pvc ( JAVAPOND ) Cutting L - - - - - - - - - -
1 Plafound Area Wanita M 16,528 - - - - - - - - -
2 Plafound Area Pria M 16,528 - - - - - - - - -
- - - - - - - - - -
G PEKERJAAN INSTALASI LISTRIK DAN LAMPU - - - - - - - - - -
1 Pemasangan Titik Lampu ( Downligh LED 18 Watt ) Putih ( Philips ) Ttk 4.00 355,000 1,420,000 1.36 - - - - 4.00 1,420,000 1.36
2 Pemasangan Titik Lampu ( Downligh LED 8 Watt ) Kuning ( Philips ) Ttk 8.00 245,000 1,960,000 1.88 - - - - 8.00 1,960,000 1.88
3 Pemasangan Titik Lampu ( Downligh LED 8 Watt ) Putih ( Philips ) Ttk 4.00 245,000 980,000 0.94 - - - - 4.00 980,000 0.94
4 Pasangan Saklar Seri bh 2.00 40,000 80,000 0.08 - - - - 2.00 80,000 0.08
5 Pasangan Saklar Tunggal bh 4.00 35,000 140,000 0.13 - - - - 4.00 140,000 0.13
- - - - - - - - - -
H PEKERJAAN SANITASI - - - - - - - - - -
1 Pas. Kloset jongkok Bh 2.00 692,017 1,384,033 1.33 - - - - 2.00 1,384,033 1.33
2 Pas. Pipa PVC Ø 3/4" Saluran kran wudhu, urinor,toilet m' 20.80 31,992 665,442 0.64 - - - - 20.80 665,442 0.64
3 Pas. Pipa PVC Ø 3/4" untuk Kran m' 3.40 31,992 108,774 0.10 - - - - 3.40 108,774 0.10
4 Pas. Kran Air Ø 3/4 Bh 20.00 195,000 3,900,000 3.74 - - - - 20.00 3,900,000 3.74
5 Pas. Stop Kran Air Ø 3/4" Bh 3.00 25,000 75,000 0.07 - - - - 3.00 75,000 0.07
6 Pas. Pipa PVC Ø 4" m' 8.00 132,653 1,061,223 1.02 - - - - 8.00 1,061,223 1.02
7 Pas. Mesin pompa Air BH 1.00 850,000 850,000 0.81 - - - - 1.00 850,000 0.81
8 Pas. Septiktank 0.00 - - - - - - - - - -
a Galian Tanah Septiktank (Lingkaran) m3 3.14 91,438 287,114 0.28 - - - - 3.14 287,114 0.28
b Pembesian Penutup Septiktank Kg 5.46 14,727 80,335 0.08 - - - - 5.46 80,335 0.08
c Plat Lantai Beton t. 15 cm (Penutup Septiktank) m3 0.26 924,675 244,946 0.23 - - - - 0.26 244,946 0.23
d Pipa Beton Bertulan D100 Bh 1.00 1,980,785 1,980,785 1.90 - - - - 1.00 1,980,785 1.90
- - - - - - - - - -
1 Pasangan Pipa 1 x1/2 untuk Saluran Kran berwudhu, urinor dan Bak Toilet M 51,000 - - - - - - - - -
2 Pasangan Pipa 3/2 untuk Kran M 32,000 - - - - - - - - -
- - - - - - - - - -
I PEKERJAAN PENAMBAHAN TEMPAT WUDHU BARU DISAMPING MASJID - - - - - - - - - -
I Pekerjaan Galian Tanah - - - - - - - - - -
1 Galian Tanah Untuk Penempatan Sloof m3 86,625 - - - - - - - - -
1 Galian Tanah Untuk Tempat Wudhu Baru m3 1.22 91,438 111,698 0.11 - - - - 1.22 111,698 0.11
II Pekerjaan Pemasangan Sloof 15/20 cm 0.00 - - - - - - - - - -
1 Beton Camp 123 setara K175 m3 952,272 - - - - - - - - -
2 Pembesian Kg 16,000 - - - - - - - - -
3 Bekisting Sloof m2 178,090 - - - - - - - - -
III Pekerjaan Pasangan Dinding - - - - - - - - - -
1 Pasangan 1/2 Bata Sp 14 m2 2.04 133,902 272,490 0.26 - - - - 2.04 272,490 0.26
2 Plesteran Sp 14 m2 78,349 - - - - - - - - -
3 Acian m2 47,883 - - - - - - - - -
IV Pekerjaan Lantai dan Keramik - - - - - - - - - -
1 Pas. Beton K-175 t. 15 cm m3 1.65 952,272 1,571,249 1.51 - - - - 1.65 1,571,249 1.51
2 Pasangan Keramik Lantai Ukuran 25*25 ( Ikad ) Kasar m2 7.68 296,667 2,276,917 2.18 - - - - 7.68 2,276,917 2.18
3 Pasangan Dinding Keramik 25x40 ( Ikad ) Polished Type 1 m2 17.17 361,170 6,200,936 5.94 - - - - 17.17 6,200,936 5.94
4 Pas. Bon-Bon Keramik m' 34.47 69,214 2,385,810 2.29 - - - - 34.47 2,385,810 2.29
V Pekerjaan Pengecatan - - - - - - - - - -
1 Pengecatan Dinding Dalam dengan Jotun Interior( 1 lapis Alkali, 2 Lapis Cat Penutup ) m2 23,034 - - - - - - - - -
VI Pekerjaan Sanitasi - - - - - - - - - -
1 Pasangan Pipa 1 x1/2 untuk Saluran Kran berwudhu dari Tangki air ke lokasi M 51,000 - - - - - - - - -
2 Pasangan Pipa 3/2 untuk Kran M 32,000 - - - - - - - - -
1 Pas. Pipa PVC Ø 3/4" untuk saluran Kran berwudhu dari Tangki air ke lokasi M 46.00 31,992 1,471,650 1.41 - - - - 46.00 1,471,650 1.41
2 Pas. Pipa PVC Ø 3/4" untuk Kran M 0.70 31,992 22,395 0.02 - - - - 0.70 22,395 0.02
3 Pasangan Kran Stainlesee Bh 7.00 195,000 1,365,000 1.31 - - - - 7.00 1,365,000 1.31
VII Pekerjaan Instalasi Titik Lampu - - - - - - - - - -
1 Pemasangan Titik Lampu ( Downligh LED 8 Watt ) Putih ( Philips ) bh 245,000 - - - - - - - - -
2 Pasangan Saklar Tunggal bh 35,000 - - - - - - - - -
VIII Pekerjaan Plat Deker - - - - - - - - - -
1 Beton Camp 123 setara K175 m3 952,272 - - - - - - - - -
2 Pembesian Kg 16,000 - - - - - - - - -
3 Bekisting Lantai m2 388,824 - - - - - - - - -
- - - - - - - - - -
IX PEKERJAAN PAGAR BESI - - - - - - - - - -
1 Besi Holoow 20 x 40 x 1,2 mm Kg 117.25 48,923 5,736,170 5.50 - - - - 117.25 5,736,170 5.50
2 Besi Holoow 40 x 40 x 1,2 mm Kg 35.70 48,923 1,746,647 1.67 - - - - 35.70 1,746,647 1.67
Pengecatan Besi Holoow 20 x 40 x 1,2 mm M2 15.52 37,400 580,388 0.56 - - - - 15.52 580,388 0.56
Pengecatan Besi Holoow 40 x 40 x 1,2 mm M2 20.69 37,400 773,851 0.74 - - - - 20.69 773,851 0.74
- - - - - - - - - -
J PEKERJAAN AKHIR - - - - - - - - - -
1 Pek. Pembersihan Akhir Ls 1.00 230,000 230,000 0.22 - - - - 1.00 230,000 0.22
JUMLAH 104,338,902 100 - - 104,338,902 100
PPN 10% 10,433,890 - - 10,433,890
TOTAL 114,772,793 - - 114,772,793

Diperiksa dan Disetujui oleh,


KONSULTAN PENGAWAS Tanah Datar, …/ Desember/2021
CV, GESTALT ARCHITECTURE Dibuat oleh,
PENYEDIA
CV. FAHLEVI REALTY

ELAN ADRAYAZI, ST
Supervision Engineer AZMAWATI
Pelaksana
Pihak Owner
Nama Dinas : DINAS PERUMAHAN RAKYAT,KAWASAN PERMUKIMAN DAN PERTANAHAN
Kuasa Pengguna Anggaran : Ir.ICHSANUSATARUDDIN
NIP. : 19640622 199003 1 004
Pejabat Pelaksana Teknis Kegiatan (PPTK) : EFNI USLINDA, S.T, M.Eng
NIP. : 19690517 199703 2 005

Program : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)


Kegiatan : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
Sub Kegiatan : PERENCANAAN PENYEDIAAN PSU PERMUKIMAN
Pekerjaan : PEMBANGUNAN JALAN LINGKUNGAN CADUAK JORONG PITAMEH NAGARI PANGIAN KECAMATAN LINTAU BUO KABUPATEN TANAH DATAR
Lokasi : KAB. TANAH DATAR
Tahun Anggaran : 2022
No Kontrak : 046/SPK/PPK1-FISIK.PSU/PERKIMTAN/VI-2022
Tanggal Kontrak : Thursday, 07 July 2022
Waktu Pelaksanaan Kontrak : 126/SPK.KPA/FISIK.PSU/KP-PERKIMTAN/X-2021 Lama Hari : 30 Hari

Pihak Penyedia Jasa


Perusahaan Penyedia Jasa : CV. PUTRA BALEPOH
Direktur : Yusniarti, SE
Pelaksana : HERRU SEPTIADINATA

Pihak Konsultan Pengawas


Perusahaan Konsultan Pengawas : CV. INTEGRITAS ENGINEERING
Direktur : Erizal
Supervision Engineer : Edi Muklis, ST

Data Laporan
Lokasi Di Tanda Tangan : Padang

Data Waktu Pelaksanaan


1 Thursday, 07 July 2022 S/D Wednesday, 13 July 2022
2 Thursday, 14 July 2022 S/D Wednesday, 20 July 2022
3 Thursday, 21 July 2022 S/D Wednesday, 27 July 2022
4 Thursday, 28 July 2022 S/D Wednesday, 03 August 2022
5 Thursday, 04 August 2022 S/D Wednesday, 10 August 2022
6 Thursday, 11 August 2022 S/D Wednesday, 17 August 2022
7 Thursday, 18 August 2022 S/D Wednesday, 24 August 2022
8 Thursday, 25 August 2022 S/D Wednesday, 31 August 2022
9 Thursday, 01 September 2022 S/D ###
10 Thursday, 08 September 2022 S/D ###
11 Thursday, 15 September 2022 S/D ###
12 Thursday, 22 September 2022 S/D ###
13 Thursday, 29 September 2022 S/D Wednesday, 05 October 2022
14 Thursday, 06 October 2022 S/D Wednesday, 12 October 2022
LAPORAN MINGGUAN

MINGGU KE : 2 (Satu)

PERIODE TANGGAL : 14 Juli 2022 s/d 20 Juli 2022

PROGRAM : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)

KEGIATAN : URUSAN PENYELENGGARAAN PSU PERMUKIMAN

PEKERJAAN : PEMBANGUNAN JALAN LINGKUNGAN CADUAK JORONG PITAMEH NAGARI PANGIAN


KECAMATAN LINTAU BUO KABUPATEN TANAH DATAR

LOKASI : KAB. TANAH DATAR

NO. KONTRAK : 046/SPK/PPK1-FISIK.PSU/PERKIMTAN/VI-2022

TANGGAL KONTRAK : 7 July 2022

PENYEDIA : CV. PUTRA BALEPOH

TAHUN ANGGARAN : 2022

PENYEDIA

CV. PUTRA BALEPOH


GENERAL KONTRAKTOR
Head Office : Jl. Cindua Mato Cubadak Air Kota Pariaman
Email ; putrabalepoh10@gmail.com
Hp ; 085274626464
LAPORAN MINGGUAN

Program : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU) No./Tgl. Kontrak : 046/SPK/PPK1-FISIK.PSU/PERKIMTAN/VI-2022
Kegiatan : URUSAN PENYELENGGARAAN PSU PERMUKIMAN Penyedia : CV. PUTRA BALEPOH
Pekerjaan : PEMBANGUNAN JALAN LINGKUNGAN CADUAK JORONG PITAMEH NAGARI PANGIAN KECAMATAN LINTAU BUO KABUPATEN TANAH DATAR Minggu Ke : 2
Lokasi : KAB. TANAH DATAR Priode : 14-Jul-2022 S/D 20-Jul-2022
T. Anggaran : 2022

CCO KEMAJUAN PEKERJAAN


BOBOT
No. URAIAN PEKERJAAN BOBOT s/d MINGGU LALU MINGGU INI s/d MINGGU INI SISA
SATUAN VOLUME TERCAPAI (%)
(%)
VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
1 2 3 4 5 6 7 8 9 10
A PEKERJAAN PENDAHULUAN & PERSIAPAN
1.1 Mobilisasi ls 1.00 2.05 1.00 2.05 - 0.00 1.00 2.05 0.000 0.00 100.00

1.2 Sistem Manajemen Keselamatan Konstruksi (SMKK) ls 1.00 2.32 1.00 2.32 - 0.00 1.00 2.32 0.00 0.00 100.00
1.3 Managemen Mutu ls 1.00 2.54 0.33 0.85 - 0.00 0.33 0.85 0.67 1.69 33.33

1.4 Pembersihan Lapangan Badan Jalan m2 581.29 1.71 581.29 1.71 - 0.00 581.29 1.71 0.00 0.00 100.00
B PEKERJAAN PERKERASAN JALAN

2.1 Pengurugan Sirtu Badan Jalan m3 58.13 2.43 58.13 2.43 - 0.00 58.13 2.43 0.00 0.00 100.00

2.2 Pemasangan Mal Cor Beton Kiri/kanan per M2 m2 39.86 3.15 12.00 0.95 12.00 0.95 24.00 1.90 15.86 1.25 60.21
2.3 Pek. Plastik Alas Cor ( Polytene 125 Micro ) m2 631.12 3.43 - 0.00 190.00 1.03 190.00 1.03 441.12 2.40 30.11

2.4 Beton Mutu Fc=19,3 Mpa (K-225) Manual m3 69.76 82.38 - 0.00 21.00 24.80 21.00 24.80 48.76 57.58 30.11

JUMLAH PEKERJAAN PENDAHULUAN & PERSIAPAN 100 10.30 26.78 37.08 62.92

JUMLAH 100 10.30 26.78 37.08 62.92

Padang, 20/July/2022
Diperiksa dan Disetujui oleh, Dibuat oleh,
KONSULTAN PENGAWAS PENYEDIA
CV. INTEGRITAS ENGINEERING CV. PUTRA BALEPOH

Edi Muklis, ST HERRU SEPTIADINATA


Supervision Enginner Pelaksana
LAPORAN HARIAN

Program : No./Tgl. Kontrak :


Kegiatan : Penyedia :
Sub Kegiatan : HARI :
Pekerjaan : TANGGAL :
Lokasi :
T. Anggaran :

I. TENAGA KERJA II. JENIS BAHAN III. PEKERJAAN Y


No. JENIS TENAGA JUMLAH No. BAHAN MASUK VOLUME SAT. No. BAHAN TERPAKAI VOLUME SAT. No. JENIS PEKERJAAN

A PEKERJAAN PERSIAPAN
1.1 Mobilisasi
1.2 Sistem Manajemen Keselamatan Konstruksi (SMKK)
### ###
### ###
### ###
### ###
2.4 Beton Mutu Fc=19,3 Mpa (K-225) Manual

IV. CUACA/KONDISI PENTING V. JAM KERJA VI. PERALATAN


JAM TANGGAL KONDISI No. KEGIATAN JAM No. JENIS PERALATAN VOLUME SAT.
08.00 s/d 12.00 30 Desember 1899 Cerah 1 Pagi 08.00 s/d 12.00
12.00 s/d 13.00 30 Desember 1899 Cerah 2 Istirahat 12.00 s/d 13.00
13.00 s/d 15.00 30 Desember 1899 Hujan 3 Sore 13.00 s/d 17.00
15.00 s/d 17.00 30 Desember 1899 Hujan 4 Pekerjaan Terhenti s/d
Catatan :

Padang, 30 Desember 1899


Diperiksa dan Disetujui oleh : Dibuat oleh :
Konsultan Pengawas Penyedia
CV.ALIYAN FAZZA CONSULTANT PT. WIKI ARDI SEJAHTERA

WILMAULINO, AMD Nasrizon


Inspection Engineer Pelaksana
LAPORAN HARIAN

III. PEKERJAAN YANG DILAKSANAKAN


JENIS PEKERJAAN VOLUME SAT. KET.

1.00 ls
Sistem Manajemen Keselamatan Konstruksi (SMKK) 1.00 ls
#NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME?
#NAME? #NAME?
Beton Mutu Fc=19,3 Mpa (K-225) Manual 69.76 m3
- 0
No. Uraian

1 2
1 Mobilisasi
Upah
Pekerja 1
Tukang
Kepala Tukang
Mandor
Bahan
###
###
###
Peralatan
Alat 1
Alat 2

2 Sistem Manajemen Keselamatan Konstruksi (SMKK)


Upah
Pekerja 1
Tukang
Kepala Tukang
Mandor
Bahan
###
###
###
###
Peralatan
Alat 1
Alat 2

3 Managemen Mutu
Upah
Pekerja 1
Tukang
Kepala Tukang
Mandor
Bahan
###
###
###
###
Peralatan
Alat 1
Alat 2

4 Pembersihan Lapangan Badan Jalan


Upah
Pekerja 1
Tukang
Kepala Tukang
Mandor
Bahan
0
0
0
0
Peralatan
Baby Roller (1,3 -3 ton)
Alat Bantu

5 Pengurugan Sirtu Badan Jalan


Upah
Pekerja 1
Tukang
Kepala Tukang
Mandor
Bahan
Sirtu
Peralatan
Alat 1
Alat 2

6 Pemasangan Mal Cor Beton Kiri/kanan per M2


Upah
Pekerja 1
Tukang
Kepala Tukang
Mandor
Bahan
Kayu Klas 3
Paku 5-7 cm
Peralatan
Alat 1
Alat 2

7 Pek. Plastik Alas Cor ( Polytene 125 Micro )


Upah
Pekerja 1
Tukang
Kepala Tukang
Mandor
Bahan
Polytene 125 Mikrom
Peralatan
Alat 1
Alat 2

8 Beton Mutu Fc=19,3 Mpa (K-225) Manual


Upah
Pekerja 1
Tukang
Kepala Tukang
Mandor
Bahan
PC/ Portland Cement
PB / Pasir Beton
Split 1 - 2 cm
Air
Peralatan
Molen Kapasitas 0,35 m3

Total
No Uraian
100%
1 2 3
Upah
Pekerja 1 22.00
Tukang 6.00
Kepala Tukang 12.00
Mandor 6.00
Bahan
1 Sirtu 0.00
2 Paku 5-7 cm 3.60
10 Kayu Klas 3 0.14
24 Polytene 125 Mikrom 38.00
PC/ Portland Cement 7791.00
PB / Pasir Beton 14658.00
Split 1 - 2 cm 21987.00
Air 4515.00
Peralatan
Baby Roller (1,3 -3 ton) 0.00
Alat Bantu 0.00
Molen Kapasitas 0,35 m3 5.00
1-Mingguan
aian Indeks
Volume Satuan
2 3 4
-

0.300 - OH
0.100 - OH
0.010 - OH
0.015 - OH

70.000 - m3
11.500 - Kg
0.043 - m3

0.000 - Jam
0.000 - Jam

0.700 - OH
0.350 - OH
0.035 - OH
0.035 - OH

17.600 - Doos
10.000 - Kg
0.045 - M3
1.500 - Kg

0.000 - Jam
0.000 - Jam

0.900 - OH
0.450 - OH
0.045 - OH
0.045 - OH

13.250 - Bh
9.300 - Kg
0.018 - m3
1.940 - Kg
0.000 - Jam
0.000 - Jam

0.008 - OH
0.000 - OH
0.000 - OH
0.002 - OH

0.000 - Bh
0.000 - Kg
0.000 - m3
0.000 - Kg

0.002 - jam
1.000 - Ls

0.250 - OH
0.000 - OH
0.000 - OH
0.025 - OH

1.200 - m3

0.000 - Jam
0.000 - Jam

12.00

0.260 12.00 OH
0.000 12.00 OH
0.026 12.00 OH
0.000 12.00 OH

0.011 12.00 Mᶟ
0.300 12.00 Kg

0.000 12.00 Jam


0.000 12.00 Jam

190.00

0.013 190.00 OH
0.000 190.00 OH
0.000 190.00 OH
0.000 190.00 OH

0.200 190.00 Kg

0.000 190.00 Jam


0.000 190.00 Jam

21.00

0.400 21.00 OH
0.100 21.00 OH
0.010 21.00 OH
0.040 21.00 OH

371.000 21.00 Kg
698.000 21.00 Kg
1047.000 21.00 Kg
215.000 21.00 Liter

0.238 21.00 Hari

Kamis Jumat Sabtu


Satuan
20% 20% 30%
4 5 6 7

OH 4.00 4.00 5.00


OH 1.00 1.00 1.00
OH 2.00 2.00 2.00
OH 1.00 1.00 1.00

m3 0.00 0.00 0.00


Kg 0.72 0.72 1.08
Mᶟ 0.03 0.03 0.04
Kg 7.60 7.60 11.40
Kg 1558.20 1558.20 2337.30
Kg 2931.60 2931.60 4397.40
Kg 4397.40 4397.40 6596.10
Liter 903.00 903.00 1354.50

jam 0.00 0.00 0.00


Ls 0.00 0.00 0.00
Hari 1.00 1.00 1.50
Senin
1-Mingguan
20%
Upah Bahan Peralatan Volume Satuan Upah Bahan
4 4
- -

- - OH -
- - OH -
- - OH -
- - OH -

- - m3 -
- - Kg -
- - Kg -

- - Jam
- - Jam

- -

- - OH -
- - OH -
- - OH -
- - OH -

- - Doos -
- - Kg -
- - M3 -
- - Kg -

- - Jam
- - Jam

- - OH -
- - OH -
- - OH -
- - OH -

- - Bh -
- - Kg -
- - m3 -
- - Kg -
- - Jam
- - Jam

- - OH -
- - OH -
- - OH -
- - OH -

- - Bh -
- - Kg -
- - m3 -
- - Kg -

- - jam
- - Ls

- - OH -
- - OH -
- - OH -
- - OH -

- - m3 -

- - Jam
- - Jam

2.40

4.00 2.40 OH 1.00


- 2.40 OH -
1.00 2.40 OH 1.00
- 2.40 OH -

1.00 2.40 Mᶟ 0.03


4.00 2.40 Kg 0.72

- 2.40 Jam
- 2.40 Jam

38.00

3.00 38.00 OH 1.00


- 38.00 OH -
- 38.00 OH -
- 38.00 OH -

38.00 38.00 Kg 7.60

- 38.00 Jam
- 38.00 Jam

4.20

9.00 4.20 OH 2.00


3.00 4.20 OH 1.00
1.00 4.20 OH 1.00
1.00 4.20 OH 1.00

7,791.00 4.20 Kg 1,558.20


14,658.00 4.20 Kg 2,931.60
21,987.00 4.20 Kg 4,397.40
4,515.00 4.20 Liter 903.00

5.00 4.20 Hari

Senin Selasa Rabu


10% 10% 10%
8 9 10

3.00 3.00 3.00


1.00 1.00 1.00 #REF!
2.00 2.00 2.00 #REF!
1.00 1.00 1.00 #REF!

0.00 0.00 0.00 #REF! 0.60


0.36 0.36 0.36 #REF!
0.01 0.01 0.01 #REF!
3.80 3.80 3.80 #REF! 0.60
779.10 779.10 779.10
1465.80 1465.80 1465.80
2198.70 2198.70 2198.70
451.50 451.50 451.50

0.00 0.00 0.00


0.00 0.00 0.00
0.50 0.50 0.50
Selasa Rabu
20% 30%
Peralatan Volume Satuan Upah Bahan Peralatan Volume Satuan
4 4
- - - -

- OH - - OH
- OH - - OH
- OH - - OH
- OH - - OH

- m3 - - m3
- Kg - - Kg
- Kg - - Kg

- - Jam - - Jam
- - Jam - - Jam

- - - -

- OH - - OH
- OH - - OH
- OH - - OH
- OH - - OH

- Doos - - Doos
- Kg - - Kg
- M3 - - M3
- Kg - - Kg

- - Jam - - Jam
- - Jam - - Jam

- -

- OH - - OH
- OH - - OH
- OH - - OH
- OH - - OH

- Bh - - Bh
- Kg - - Kg
- m3 - - m3
- Kg - - Kg
- - Jam - - Jam
- - Jam - - Jam

- -

- OH - - OH
- OH - - OH
- OH - - OH
- OH - - OH

- Bh - - Bh
- Kg - - Kg
- m3 - - m3
- Kg - - Kg

- - jam - - jam
- - Ls - - Ls

- -

- OH - - OH
- OH - - OH
- OH - - OH
- OH - - OH

- m3 - - m3

- - Jam - - Jam
- - Jam - - Jam

2.40 3.60

2.40 OH 1.00 3.60 OH


2.40 OH - 3.60 OH
2.40 OH 1.00 3.60 OH
2.40 OH - 3.60 OH

2.40 Mᶟ 0.03 3.60 Mᶟ


2.40 Kg 0.72 3.60 Kg

- 2.40 Jam - 3.60 Jam


- 2.40 Jam - 3.60 Jam

38.00 57.00

38.00 OH 1.00 57.00 OH


38.00 OH - 57.00 OH
38.00 OH - 57.00 OH
38.00 OH - 57.00 OH

38.00 Kg 7.60 57.00 Kg

- 38.00 Jam - 57.00 Jam


- 38.00 Jam - 57.00 Jam

4.20 6.30

4.20 OH 2.00 6.30 OH


4.20 OH 1.00 6.30 OH
4.20 OH 1.00 6.30 OH
4.20 OH 1.00 6.30 OH

4.20 Kg 1,558.20 6.30 Kg


4.20 Kg 2,931.60 6.30 Kg
4.20 Kg 4,397.40 6.30 Kg
4.20 Liter 903.00 6.30 Liter

1.00 4.20 Hari 1.00 6.30 Hari

0.90 0.30 0.30 0.30

0.90 0.30 0.30 0.30


Rabu Kamis
30% 10%
Upah Bahan Peralatan Volume Satuan Upah Bahan Peralatan
4 4
- -

- - OH -
- - OH -
- - OH -
- - OH -

- - m3 -
- - Kg -
- - Kg -

- - Jam -
- - Jam -

- -

- - OH -
- - OH -
- - OH -
- - OH -

- - Doos -
- - Kg -
- - M3 -
- - Kg -

- - Jam -
- - Jam -

- - OH -
- - OH -
- - OH -
- - OH -

- - Bh -
- - Kg -
- - m3 -
- - Kg -
- - Jam -
- - Jam -

- - OH -
- - OH -
- - OH -
- - OH -

- - Bh -
- - Kg -
- - m3 -
- - Kg -

- - jam -
- - Ls -

- - OH -
- - OH -
- - OH -
- - OH -

- - m3 -

- - Jam -
- - Jam -

1.20

1.00 1.20 OH 1.00


- 1.20 OH -
1.00 1.20 OH 1.00
- 1.20 OH -

0.04 1.20 Mᶟ 0.01


1.08 1.20 Kg 0.36

- 1.20 Jam -
- 1.20 Jam -

19.00

1.00 19.00 OH 1.00


- 19.00 OH -
- 19.00 OH -
- 19.00 OH -

11.40 19.00 Kg 3.80

- 19.00 Jam -
- 19.00 Jam -

2.10

3.00 2.10 OH 1.00


1.00 2.10 OH 1.00
1.00 2.10 OH 1.00
1.00 2.10 OH 1.00

2,337.30 2.10 Kg 779.10


4,397.40 2.10 Kg 1,465.80
6,596.10 2.10 Kg 2,198.70
1,354.50 2.10 Liter 451.50

1.50 2.10 Hari 0.50


Jumat Sabtu
10% 10%
Volume Satuan Upah Bahan Peralatan Volume Satuan Upah
4 4
- - - -

- OH - - OH -
- OH - - OH -
- OH - - OH -
- OH - - OH -

- m3 - - m3
- Kg - - Kg
- Kg - - Kg

- Jam - - Jam
- Jam - - Jam

- - - -

- OH - - OH -
- OH - - OH -
- OH - - OH -
- OH - - OH -

- Doos - - Doos
- Kg - - Kg
- M3 - - M3
- Kg - - Kg

- Jam - - Jam
- Jam - - Jam

- -

- OH - - OH -
- OH - - OH -
- OH - - OH -
- OH - - OH -

- Bh - - Bh
- Kg - - Kg
- m3 - - m3
- Kg - - Kg
- Jam - - Jam
- Jam - - Jam

- -

- OH - - OH -
- OH - - OH -
- OH - - OH -
- OH - - OH -

- Bh - - Bh
- Kg - - Kg
- m3 - - m3
- Kg - - Kg

- jam - - jam
- Ls - - Ls

- -

- OH - - OH -
- OH - - OH -
- OH - - OH -
- OH - - OH -

- m3 - - m3

- Jam - - Jam
- Jam - - Jam

1.20 1.20

1.20 OH 1.00 1.20 OH 1.00


1.20 OH - 1.20 OH -
1.20 OH 1.00 1.20 OH 1.00
1.20 OH - 1.20 OH -

1.20 Mᶟ 0.01 1.20 Mᶟ


1.20 Kg 0.36 1.20 Kg

1.20 Jam - 1.20 Jam


1.20 Jam - 1.20 Jam

19.00 19.00

19.00 OH 1.00 19.00 OH 1.00


19.00 OH - 19.00 OH -
19.00 OH - 19.00 OH -
19.00 OH - 19.00 OH -

19.00 Kg 3.80 19.00 Kg

19.00 Jam - 19.00 Jam


19.00 Jam - 19.00 Jam

2.10 2.10

2.10 OH 1.00 2.10 OH 1.00


2.10 OH 1.00 2.10 OH 1.00
2.10 OH 1.00 2.10 OH 1.00
2.10 OH 1.00 2.10 OH 1.00

2.10 Kg 779.10 2.10 Kg


2.10 Kg 1,465.80 2.10 Kg
2.10 Kg 2,198.70 2.10 Kg
2.10 Liter 451.50 2.10 Liter

2.10 Hari 0.50 2.10 Hari


Sabtu
10%
Bahan Peralatan
4

-
-
-

-
-

-
-
-
-

-
-

-
-
-
-
-
-

-
-
-
-

-
-

-
-

0.01
0.36

-
-
3.80

-
-

779.10
1,465.80
2,198.70
451.50

0.50
LAPORAN HARIAN

Program : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)


Kegiatan : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
Pekerjaan : PEMBANGUNAN JALAN LINGKUNGAN CADUAK JORONG PITAMEH NAGARI PANGIAN KECAMATAN LINTAU BUO
KABUPATEN TANAH DATAR
Lokasi : KAB. TANAH DATAR
Tahun Anggaran : 2022
Penyedia : CV. PUTRA BALEPOH
Konsultan Pengawas : CV. INTEGRITAS ENGINEERING
Hari / Tanggal : Thursday, 14 July 2022

PEKERJAAN YANG DILAKSANAKAN

No Jenis Pekerjaan Volume Satuan


1 Pemasangan Mal Cor Beton Kiri/kanan per M2 2.40 m2
2 Pek. Plastik Alas Cor ( Polytene 125 Micro ) 38.00 m2
3 Beton Mutu Fc=19,3 Mpa (K-225) Manual 4.20 m3

Tenaga Kerja Bahan


No No
Tenaga Kerja Jumlah Satuan Jenis Bahan Volume Satuan Diterima Ditolak

1 Pekerja 1 4.00 OH 1 Paku 5-7 cm 0.72 Kg √ -


2 Tukang 1.00 OH 2 Kayu Klas 3 0.03 Mᶟ √ -
3 Kepala Tukang 2.00 OH 3 Polytene 125 Mikrom 7.60 Kg √ -
4 Mandor 1.00 OH 4 PC/ Portland Cement 1,558.20 Kg √ -
5 PB / Pasir Beton 2,931.60 Kg √ -
6 Split 1 - 2 cm 4,397.40 Kg √ -
7 Air 903.00 Liter √ -

Peralatan Cuaca
No No
Jenis Peralatan Jumlah Kondisi Waktu Cerah Berawan Hujan

1 Molen Kapasitas 0,35 m3 1.00 Baik a Pagi √ - -


2 - b Siang - √ -
3 - c Sore - √ -
4 - d Malam - √ -
Dst.
INSTRUKSI / SARAN

Diperiksa dan Disetujui oleh, Dibuat Oleh,


KONSULTAN PENGAWAS PENYEDIA
CV. INTEGRITAS ENGINEERING CV. PUTRA BALEPOH

Oddy Satrio Nugroho, ST HERRU SEPTIADINATA


Inspector Pelaksana
LAPORAN HARIAN

Program : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)


Kegiatan : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
Pekerjaan : PEMBANGUNAN JALAN LINGKUNGAN CADUAK JORONG PITAMEH NAGARI PANGIAN KECAMATAN LINTAU BUO
KABUPATEN TANAH DATAR
Lokasi : KAB. TANAH DATAR
Tahun Anggaran : 2022
Penyedia : CV. PUTRA BALEPOH
Konsultan Pengawas : CV. INTEGRITAS ENGINEERING
Hari / Tanggal : Friday, 15 July 2022

PEKERJAAN YANG DILAKSANAKAN

No Jenis Pekerjaan Volume Satuan


1 Pemasangan Mal Cor Beton Kiri/kanan per M2 2.40 m2
2 Pek. Plastik Alas Cor ( Polytene 125 Micro ) 38.00 m2
3 Beton Mutu Fc=19,3 Mpa (K-225) Manual 4.20 m3

Tenaga Kerja Bahan


No No
Tenaga Kerja Jumlah Satuan Jenis Bahan Volume Satuan Diterima Ditolak

1 Pekerja 1 4.00 OH 1 Paku 5-7 cm 0.72 Kg √ -


2 Tukang 1.00 OH 2 Kayu Klas 3 0.03 Mᶟ √ -
3 Kepala Tukang 2.00 OH 3 Polytene 125 Mikrom 7.60 Kg √ -
4 Mandor 1.00 OH 4 PC/ Portland Cement 1,558.20 Kg √ -
5 PB / Pasir Beton 2,931.60 Kg √ -
6 Split 1 - 2 cm 4,397.40 Kg √ -
7 Air 903.00 Liter √ -

Peralatan Cuaca
No No
Jenis Peralatan Jumlah Kondisi Waktu Cerah Berawan Hujan

1 Molen Kapasitas 0,35 m3 1.00 Baik a Pagi √ - -


2 - b Siang √ - -
3 - c Sore √ - -
4 - d Malam √ - -
Dst.
INSTRUKSI / SARAN

Diperiksa dan Disetujui oleh, Dibuat Oleh,


KONSULTAN PENGAWAS PENYEDIA
CV. INTEGRITAS ENGINEERING CV. PUTRA BALEPOH

Oddy Satrio Nugroho, ST HERRU SEPTIADINATA


Inspector Pelaksana
LAPORAN HARIAN

Program : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)


Kegiatan : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
Pekerjaan : PEMBANGUNAN JALAN LINGKUNGAN CADUAK JORONG PITAMEH NAGARI PANGIAN KECAMATAN LINTAU BUO
KABUPATEN TANAH DATAR
Lokasi : KAB. TANAH DATAR
Tahun Anggaran : 2022
Penyedia : CV. PUTRA BALEPOH
Konsultan Pengawas : CV. INTEGRITAS ENGINEERING
Hari / Tanggal : Saturday, 16 July 2022

PEKERJAAN YANG DILAKSANAKAN

No Jenis Pekerjaan Volume Satuan


1 Pemasangan Mal Cor Beton Kiri/kanan per M2 3.60 m2
2 Pek. Plastik Alas Cor ( Polytene 125 Micro ) 57.00 m2
3 Beton Mutu Fc=19,3 Mpa (K-225) Manual 6.30 m3

Tenaga Kerja Bahan


No No
Tenaga Kerja Jumlah Satuan Jenis Bahan Volume Satuan Diterima Ditolak

1 Pekerja 1 5.00 OH 1 Paku 5-7 cm 1.08 Kg √ -


2 Tukang 1.00 OH 2 Kayu Klas 3 0.04 Mᶟ √ -
3 Kepala Tukang 2.00 OH 3 Polytene 125 Mikrom 11.40 Kg √ -
4 Mandor 1.00 OH 4 PC/ Portland Cement 2,337.30 Kg √ -
5 PB / Pasir Beton 4,397.40 Kg √ -
6 Split 1 - 2 cm 6,596.10 Kg √ -
7 Air 1,354.50 Liter √ -

Peralatan Cuaca
No No
Jenis Peralatan Jumlah Kondisi Waktu Cerah Berawan Hujan

1 Molen Kapasitas 0,35 m3 1.50 Baik a Pagi √ - -


2 - b Siang √ - -
3 - c Sore √ - -
4 - d Malam √ - -
Dst.
INSTRUKSI / SARAN

Diperiksa dan Disetujui oleh, Dibuat Oleh,


KONSULTAN PENGAWAS PENYEDIA
CV. INTEGRITAS ENGINEERING CV. PUTRA BALEPOH

Oddy Satrio Nugroho, ST HERRU SEPTIADINATA


Inspector Pelaksana
LAPORAN HARIAN

Program : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)


Kegiatan : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
Pekerjaan : PEMBANGUNAN JALAN LINGKUNGAN CADUAK JORONG PITAMEH NAGARI PANGIAN KECAMATAN LINTAU BUO
KABUPATEN TANAH DATAR
Lokasi : KAB. TANAH DATAR
Tahun Anggaran : 2022
Penyedia : CV. PUTRA BALEPOH
Konsultan Pengawas : CV. INTEGRITAS ENGINEERING
Hari / Tanggal : Sunday, 17 July 2022

PEKERJAAN YANG DILAKSANAKAN

No Jenis Pekerjaan Volume Satuan

Tenaga Kerja Bahan


No
Tenaga Kerja Jumlah Satuan
No
] Jenis Bahan Volume Satuan Diterima Ditolak
UR

1 Pekerja 1 OH
IB

2 Tukang OH
3 Kepala Tukang OH
[L

4 Mandor OH

Peralatan Cuaca
No No
Jenis Peralatan Jumlah Kondisi Waktu Cerah Berawan Hujan

1 - a Pagi √ - -
2 - b Siang √ - -
3 - c Sore √ - -
4 - d Malam √ - -
Dst.
INSTRUKSI / SARAN

Diperiksa dan Disetujui oleh, Dibuat Oleh,


KONSULTAN PENGAWAS PENYEDIA
CV. INTEGRITAS ENGINEERING CV. PUTRA BALEPOH

Oddy Satrio Nugroho, ST HERRU SEPTIADINATA


Inspector Pelaksana
LAPORAN HARIAN

Program : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)


Kegiatan : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
Pekerjaan : PEMBANGUNAN JALAN LINGKUNGAN CADUAK JORONG PITAMEH NAGARI PANGIAN KECAMATAN LINTAU BUO
KABUPATEN TANAH DATAR
Lokasi : KAB. TANAH DATAR
Tahun Anggaran : 2022
Penyedia : CV. PUTRA BALEPOH
Konsultan Pengawas : CV. INTEGRITAS ENGINEERING
Hari / Tanggal : Monday, 18 July 2022

PEKERJAAN YANG DILAKSANAKAN

No Jenis Pekerjaan Volume Satuan


1 Pemasangan Mal Cor Beton Kiri/kanan per M2 1.20 m2
2 Pek. Plastik Alas Cor ( Polytene 125 Micro ) 19.00 m2
3 Beton Mutu Fc=19,3 Mpa (K-225) Manual 2.10 m3

Tenaga Kerja Bahan


No No
Tenaga Kerja Jumlah Satuan Jenis Bahan Volume Satuan Diterima Ditolak

1 Pekerja 1 3.00 OH 1 Paku 5-7 cm 0.36 Kg √ -


2 Tukang 1.00 OH 2 Kayu Klas 3 0.01 Mᶟ √ -
3 Kepala Tukang 2.00 OH 3 Polytene 125 Mikrom 3.80 Kg √ -
4 Mandor 1.00 OH 4 PC/ Portland Cement 779.10 Kg √ -
5 PB / Pasir Beton 1,465.80 Kg √ -
6 Split 1 - 2 cm 2,198.70 Kg √ -
7 Air 451.50 Liter √ -

Peralatan Cuaca
No No
Jenis Peralatan Jumlah Kondisi Waktu Cerah Berawan Hujan

1 Molen Kapasitas 0,35 m3 0.50 Baik a Pagi √ - -


2 - b Siang √ - -
3 - c Sore √ - -
4 - d Malam √ - -
Dst.
INSTRUKSI / SARAN

Diperiksa dan Disetujui oleh, Dibuat Oleh,


KONSULTAN PENGAWAS PENYEDIA
CV. INTEGRITAS ENGINEERING CV. PUTRA BALEPOH

Oddy Satrio Nugroho, ST HERRU SEPTIADINATA


Inspector Pelaksana
LAPORAN HARIAN

Program : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)


Kegiatan : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
Pekerjaan : PEMBANGUNAN JALAN LINGKUNGAN CADUAK JORONG PITAMEH NAGARI PANGIAN KECAMATAN LINTAU BUO
KABUPATEN TANAH DATAR
Lokasi : KAB. TANAH DATAR
Tahun Anggaran : 2022
Penyedia : CV. PUTRA BALEPOH
Konsultan Pengawas : CV. INTEGRITAS ENGINEERING
Hari / Tanggal : Tuesday, 19 July 2022

PEKERJAAN YANG DILAKSANAKAN

No Jenis Pekerjaan Volume Satuan


1 Pemasangan Mal Cor Beton Kiri/kanan per M2 1.20 m2
2 Pek. Plastik Alas Cor ( Polytene 125 Micro ) 19.00 m2
3 Beton Mutu Fc=19,3 Mpa (K-225) Manual 2.10 m3

Tenaga Kerja Bahan


No No
Tenaga Kerja Jumlah Satuan Jenis Bahan Volume Satuan Diterima Ditolak
Pekerja 1 3.00 1 Paku 5-7 cm 0.36 Kg √ -
Tukang 1.00 2 Kayu Klas 3 0.01 Mᶟ √ -
Kepala Tukang 2.00 3 Polytene 125 Mikrom 3.80 Kg √ -
Mandor 1.00 4 PC/ Portland Cement 779.10 Kg √ -
5 PB / Pasir Beton 1465.80 Kg √ -
6 Split 1 - 2 cm 2198.70 Kg √ -
7 Air 451.50 Liter √ -
Peralatan Cuaca
No No
Jenis Peralatan Jumlah Kondisi Waktu Cerah Berawan Hujan

1 Molen Kapasitas 0,35 m3 0.50 Baik a Pagi √ - -


2 b Siang √ - -
3 c Sore √ - -
4 d Malam √ - -
Dst.
INSTRUKSI / SARAN

Diperiksa dan Disetujui oleh, Dibuat Oleh,


KONSULTAN PENGAWAS PENYEDIA
CV. INTEGRITAS ENGINEERING CV. PUTRA BALEPOH

Oddy Satrio Nugroho, ST HERRU SEPTIADINATA


Inspector Pelaksana
LAPORAN HARIAN

Program : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)


Kegiatan : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
Pekerjaan : PEMBANGUNAN JALAN LINGKUNGAN CADUAK JORONG PITAMEH NAGARI PANGIAN KECAMATAN LINTAU BUO
KABUPATEN TANAH DATAR
Lokasi : KAB. TANAH DATAR
Tahun Anggaran : 2022
Penyedia : CV. PUTRA BALEPOH
Konsultan Pengawas : CV. INTEGRITAS ENGINEERING
Hari / Tanggal : Wednesday, 20 July 2022

PEKERJAAN YANG DILAKSANAKAN

No Jenis Pekerjaan Volume Satuan


1 Pemasangan Mal Cor Beton Kiri/kanan per M2 1.20 m2
2 Pek. Plastik Alas Cor ( Polytene 125 Micro ) 19.00 m2
3 Beton Mutu Fc=19,3 Mpa (K-225) Manual 2.10 m3

Tenaga Kerja Bahan


No No
Tenaga Kerja Jumlah Satuan Jenis Bahan Volume Satuan Diterima Ditolak
Pekerja 1 3.00 1 Paku 5-7 cm 0.36 Kg √ -
Tukang 1.00 2 Kayu Klas 3 0.01 Mᶟ √ -
Kepala Tukang 2.00 3 Polytene 125 Mikrom 3.80 Kg √ -
Mandor 1.00 4 PC/ Portland Cement 779.10 Kg √ -
5 PB / Pasir Beton 1465.80 Kg √ -
6 Split 1 - 2 cm 2198.70 Kg √ -
7 Air 451.50 Liter √ -

Peralatan Cuaca
No No
Jenis Peralatan Jumlah Kondisi Waktu Cerah Berawan Hujan

1 Molen Kapasitas 0,35 m3 0.50 Baik a Pagi √ - -


2 - b Siang √ - -
3 - c Sore √ - -
4 - d Malam √ - -
Dst.
INSTRUKSI / SARAN

Diperiksa dan Disetujui oleh, Dibuat Oleh,


KONSULTAN PENGAWAS PENYEDIA
CV. INTEGRITAS ENGINEERING CV. PUTRA BALEPOH

Oddy Satrio Nugroho, ST HERRU SEPTIADINATA


Inspector Pelaksana
TIME SCHEDULE

Program : PROGRAM PENINGKATAN PRASARANA, SARANA DAN UTILITAS UMUM (PSU)


Kegiatan : URUSAN PENYELENGGARAAN PSU PERMUKIMAN
Pekerjaan : PEMBANGUNAN JALAN LINGKUNGAN CADUAK JORONG PITAMEH NAGARI PANGIAN KECAMATAN LINTAU BUO KABUPATEN TANAH DATAR
Lokasi : KAB. TANAH DATAR
Tahun : 2022

MINGGU KE-
BOBOT
NO. URAIAN PEKERJAAN Persentase KETERANGAN
%
M. 1 M. 2 M. 3 M. 4
1 2 3 4 5 6 7 13 14
100%
A Mobilisasi 2.05 2.05

B Sistem Manajemen Keselamatan Konstruksi (SMKK) 2.32 2.32

C Managemen Mutu 2.54 0.85

D Pembersihan Lapangan Badan Jalan 1.71 1.71

E Pengurugan Sirtu Badan Jalan 2.43 2.43

F Pemasangan Mal Cor Beton Kiri/kanan per M2 3.15 0.95 0.95

G Pek. Plastik Alas Cor ( Polytene 125 Micro ) 3.43 0.00 1.03

H Beton Mutu Fc=19,3 Mpa (K-225) Manual 82.38 0.00 24.80

JUMLAH 100

RENCANA BOBOT 3.80 24.45 51.75 20.00

RENCANA KOMULATIF 3.80 28.25 80.00 100.00

BOBOT TERLAKSANA 10.30 26.78 0.00 0.00

BOBOT TERLAKSANA KOMULATIF 10.30 37.08 37.08 37.08

DEVIASI 6.50 8.83 -42.92 -62.92

** Waktu Pelaksanaan Pekerjaan 126/SPK.KPA/FISIK.PSU/KP-PERKIMTAN/X-2021 Lama Hari : hari Kalender


, 20/July/2022
Diperiksa dan Disetujui oleh, Dibuat oleh,
KONSULTAN PENGAWAS PENYEDIA
CV. PUTRA BALEPOH CV. PUTRA BALEPOH

Edi Muklis, ST HERRU SEPTIADINATA


Supervision Enginner Pelaksana

Anda mungkin juga menyukai