Anda di halaman 1dari 8

Urgency Standar 

/  Keterangan
No Item Area Rekomendasi UMRO Action Plant Paiton PIC Keterangan
Referensi Foto
Low High Kondisi Saat Ini

BIDANG MESIN 1

Normal / Sesuai 
1 Baut kopling HIP - LP A Turbin utama V Rusak,jumlah  5 ea Ganti baru 4 ea
standard

Normal / Sesuai 
2 Baut kopling LP A - LP B Turbin utama V Normal, tidak ada kerusakan Ganti baru 4 ea
standard

Baut kopling LP B-Gen (Normal / Sesuai 


3 Turbin utama V baut rusak 3 ea Ganti baru 4 ea
standard)

(Normal / Sesuai  Clearance Maksimum (0.23) 
4 Bearing MOP Turbin utama V Rebabit/ganti baru
standard) standard (0.15 ‐ 0.20)

Block Valve Line Discharge (Normal / Sesuai  Housing Seat Mengalami 


5  Turbin Lt 1 V Repair / ganti Baru 
BFP 1 ABC standard) Lost Material Dan Keropos

Check Valve Line Discharge (Normal / Sesuai  Housing Seat Mengalami 


6 Turbin lt.1 V Repair / ganti Baru 
BFP 1 ABC standard) Lost Material Dan Keropos

Block Valve Line Suction BFP (Normal / Sesuai  Sisi Outlet Contact Check 


7 Turbin lt.3 V Repair / ganti baru
1A standard) Tidak Contact

8 Lever RSV sisi L Turbin Lt 3 V Manual Book Bengkok Repair/ganti baru


Urgency Standar /  Keterangan
No Item Area Rekomendasi UMRO Action Plant Paiton PIC Keterangan
Referensi Foto
Low High Kondisi Saat Ini

(Normal / Sesuai 
9 Seat MSV sisi L Turbin Lt 3 V Porosity Repair
standard)

Bearing cover voith BFP 1B (Normal / Sesuai 


10 Turbin lt.1 V Oli keluar Identifikasi
sisi kopling motor standard)

Catridge filter oil conditioner (Normal / Sesuai 


11 Turbin lt.1 V Jenuh Ganti baru
MOT standard)

(Normal / Sesuai 
12 Pompa circulating CAEP 1B Turbin lt.1 V Keropos Ganti baru
standard)

 ‐ Ganti sleeve
(Normal / Sesuai 
13 ACWP 1C CWP area V Vibrasi axial tinggi  ‐ Balancing
standard)
 ‐ R/O check

CV Emergency drain LPH 2 to (Normal / Sesuai 


14 Turbin lt.1 V Leaktrough Ganti /repair vlv
Cond standard)

CV Normally drain LPH 1 (Normal / Sesuai 


15 Turbin lt.1 V Leaktrough Ganti /repair vlv
to Cond standard)

CV Normally drain HPH 6 to (Normal / Sesuai 


16 Turbin lt.4 V Leaktrough Ganti /repair vlv
HPH 5 standard)

Penggantian expantion joint lantai 1.5 atas  Expantion joint outlet dan 


17 V Manual book Dilakukan welding repair
outlet dan inlet SAH baru FDFan inlet SAH kropos

Dilakukan inspeksi pada area Scooptube voith ID Fan 1B 


18 scooptube ID Fan 1B pada ID Fan V Normal vibrasi saat bukaan sekitar  Dilakukan adjusting scooptube
OH selanjutnya 50%
Urgency Standar /  Keterangan
No Item Area Rekomendasi UMRO Action Plant Paiton PIC Keterangan
Referensi Foto
Low High Kondisi Saat Ini

Kondisi tinggi  level motor ID 
19 Scrap pondasi motor ID Fan V Normal Fan 1B terhadap voith sudah  Alignment
maksimal

Kondisi bearing ID Fan 1A  Sudah dilakukan penggantian 
20 Rebabit bearing ID Fan V Normal
dan 1B defect dengan bearing spare

Terdapat impact saat 
Pengadaan voith coupling Penggantian bearing dan oil seal 
21 SAH V Normal running SAH A baik yang 
SAH A baru voith SAH
original maupun spare

Dilakukan penggantian dengan 
Penggantian lube oil pump Lube oil pump PA Fan 1A 
22 PA Fan V Normal pompa spare (Hasil not okay, 
baru indikasi impact saat running
dijadikan standby)

Kondisi element PAH 1A dan 
23 Penggantian element baru PAH V Normal
1B cold end korosif

Kondisi shaft & shaft sleeve 
Repair shaft & shaft sleeve Dilakukan penggantian dengan 
24 PAH V Normal guide bearing (existing) PAH 
guide bearing spare
1B aus 

Penggantian baru / Repair PA Fan & FD  Kondisi silencer PA Fan dan 


25 V Normal Dilakukan repair parsial
total silencer Fan ID Fan 1A dan 1B keropos

Penggantian expantion joint Kondisi expantion joint duct 


26 FD Fan V Normal Dilakukan welding repair
baru simphone FD Fan keropos

Penggantian cover Kondisi indikasi cover 


manhole/rekondisi cover manhole scrapper mill B 
27 Mill V Normal
manhole scrapper mill B timur, timur, manhole E timur 
manhole E timur mulet

Penggantian deflector linner


Kondisi deflector linner sisi 
28 sisi bawah (plat hardok) mill A- Mill V Normal Dilakukan perbaikan partial
bawah rusak 15 ea
E 15 ea
Urgency Standar /  Keterangan
No Item Area Rekomendasi UMRO Action Plant Paiton PIC Keterangan
Referensi Foto
Low High Kondisi Saat Ini

PCV Bocor Dan Kondisi Dari 
Dilakukan Repair pada PCV Lantai 9 
29 V Sesuai standart Comisioning sampai saat ini 
Main Steam Line Boiler
Tidak Dioperasikan

Dibuatkan gritting dan modif Kondisi tidak ada grittng di 


30 casing alumunium di support APH V support bearing PAH 1A dan 
bearing PAH 1A dan B B

Kondisi tidak terdapat line 
Dibuatkan line drain pada
31 SAH A & B V drain pada saat 
SAH
waterwashing

BIDANG MESIN 2

Teeth Smallwheel   Normal, setelah dilakukan 
Penggantian small wheel ERM 
1 Smallwheel ERM #1A Aus ESP#1 V Normal/Sesuai  repair teeth  Smallwheel  Outage
1A yg aus
Standard yang Aus

LINE  Open close 
disk enable valve 62A Penggantian/ repair disk enable 
2 VACUUMBLO V normal/ sesuai   Operasi Valve  bisa full close Outage
Abnormal valve 62A
WER standar

Normal/Sesuai  Penggantian  Rantai & Sprocket 
3 Rantai & Sprocket SSC SSC V Rantai & Sprocket SSC Aus Outage
Standard SSC baru

Rubber mounting Vacuum VACUUM  Normal/Sesuai  Rubber mounting vacuum  Penggantian Rubber mounting 


4 V Outage
blower#1B BLOWER Standard blower  #11B expired baru 6 ea

Flexible joint vacuum blower 
Flexible joint vacuum blower
VACUUM  Normal/Sesuai  1B (rubber flange) sisi  Penggantian Rubber flexible 
5 1B (rubber flange) sisi suction V Outage
BLOWER Standard suction kondisi retak pada  Joint
kondisi retak
permukaan

Slidegate Valve Eco LINE ECO  Normal/Sesuai  disk valve macet, normaly 


6 V Penormalan /Repair Valve Outage
hopper#1B HOPPER Standard open
Urgency Standar /  Keterangan
No Item Area Rekomendasi UMRO Action Plant Paiton PIC Keterangan
Referensi Foto
Low High Kondisi Saat Ini

Valve FLY ASH Normal/Sesuai 


7 V Housing air seal aus Penggantian  Valve 1 set  Outage
Balancing Primary #1 TRANSPORT Standard

Threway valve FLY ASH Normal/Sesuai 


8 V Penggantian Valve 1 Set Outage
Secondary Separator#1 TRANSPORT Standard

BIDANG KONTROL DAN INSTRUMENT

Level Oil UAT A & B penggantian baru 2 set


Range Pembacaan 
1 Abnormal (SC 109003) Turbin V maksimal pembacaan di 0.8 (RAB 135 juta / set) Outage
Normal (0 ‐ 1)
SC 109003

penggantian proximitor 
penggantian Proximitor sensor Hasil kalibrasi error  proximitor menggunakan  menggunakan type baru BFP A 2 
2 Turbin V Outage
vibrasi BFP < 5% type lama ea, BFP B 5 ea,BFP C 4 Eea)
(RAB 60 juta ) SC 317743

Penyesuaian support sensor HP 
Support sensor HP 
sensor HP differensial Diferential expantion 
3 Turbin v differensial expansion  Outage
expansion (RAB ‐0 menggunakan material 
ukuran tidak sesuai
eksisting)

DPIS generator inlet cooiling switch abnormal


4 Turbin v 0‐1000 mmH2O penggantian baru DPIS Outage
water flow low Indicator normal

penggantian 1 set level 
pressure 0‐60  transmitter
5 Level Transmitter HPH 7 Turbin v abnormal Outage
kg/cm  (RAB 150 juta)
SC 955492

Piston OVA corner 3 & 4  penggantian baru 2 set
Piston OVA corner 3 & 4 piston beroperasi 
6 Burner v kondisi bocor tapi masih  (RAB 50 juta / set) Outage
kondisi bocor normal
bisa dimanuver SC 631606
Urgency Standar /  Keterangan
No Item Area Rekomendasi UMRO Action Plant Paiton PIC Keterangan
Referensi Foto
Low High Kondisi Saat Ini

penggantian sensor dan 
Sensor extention vibrasi SAC  extention vibrasi SAC 3 set
extention vibrasi SAC
7 SAC v error<2% A stage 1, 2 dan 3 hasil uji  (Ingersoll Rand) panjang 6,5 m,  Rendal har
(Ingersoll Rand)
statis diluar standar CCN : 2267769
(RAB 60 Juta / set)

ganti flame dan fiber optik 2 set
(flame obsolate, material 
Kondisi modul Flame 
upgrade unit 2 kondisi tidak 
detector dan fiber optic 
8 Flame detector dan fiber optic Burner v normal optimal dan hanya ada 2) Outage
rusak 2 set (AA2, AA4 Flame 
sudah diusulkan RKAP ijin 
+ Fiber Optic)
proses 2024

BIDANG LISTRIK

Normal,( Dari 3 element 
Penggantian Baru Heater Tidak ada spare. Dilakukan
1 V Normal Heter ,1 Element Kondisi  Outage
CEP B pemasangan kembali
rusak)

Turbin Lt.1

Normal (indikasi Crack pada  Dilakukan weding pada


Penggantian Baru Motor Mill
2 Boiler Lt.1 V Normal pondasi Kaki dan Cover  pondasi support dan cover
Seal Air Fan
Bearing DE) bearing sisi DE

AbNormal (Change Over dari 
Penggantian Baru ATS pada
Emergency Ke normal  Tidak ada spare, Dilakukan
3 Panel Cooling System UAT Trafo V Normal
membutuhkan delay sedkit  penggantian
Trafo A
lama)
Urgency Standar /  Keterangan
No Item Area Rekomendasi UMRO Action Plant Paiton PIC Keterangan
Referensi Foto
Low High Kondisi Saat Ini

Penggantian Voltmeter PDC Tidak ada spare, Dilakukan


4 CCR V Normal Voltmeter abnormal/ rusak Outage
Turbin di APCB penggantian

Menstandbykan pompa Motor normal (Motor short 


5 portable untuk memback up Turbin Lt.1 V Normal karena terendam air  rewinding motor
sump pump outlet condensor sehingga direwinding)

Aux crane turbin #1 sering 
trip, hasil identifikasi motor 
Overhead Crane aux turbin #1
dan brake normal. Indikasi  resetting inverter motor aux
6 (25 ton) perlu penggantian Turbin Lt.3 V Normal Rendal
inverter abnormal karena  crane
inventer
mengirim sinyal trip padahal 
nilai arus di bawah setting

Motor terpapar steam dan 
Penggantian MOV equalizing
7 HPH 7 V Normal berpotensi merusak winding  belikan Motor spare
outlet HPH 7
dan modul kontrol MOV

Penggantian Baru Transducer Watt UAT 1A  Tidak ada spare, Dilakukan


8 PRP V Baik Outage
Transducer Watt UAT 1A kondisi rusak penggantian

Penggantian baru Wattmeter Wattmeter Incoming Feeder  Tidak ada spare, Dilakukan


9 SWIITCHGEAR V Baik Outage
Incoming Feeder 1A 1A kondisi rusak penggantian

Penggantian Baru Penthouse Penthouse heater putus  Tidak ada spare, Dilakukan


10 ESP V Baik
heater IPE02EA-2 IPE02EA‐2 kondisi putus penggantian

Pengadaan kontaktor spare Kondisi normal,tidak ada  Tidak ada spare, Dilakukan


11 ESP V Ready
MCC ESP spare baru spare untuk penggantian penggantian

Pengadaan Timer adaptor Kondisi normal,tidak ada  Tidak ada spare, Dilakukan


12 ESP V Ready
Vibrator spare baru spare untuk penggantian penggantian
Urgency Standar /  Keterangan
No Item Area Rekomendasi UMRO Action Plant Paiton PIC Keterangan
Referensi Foto
Low High Kondisi Saat Ini

Pengadaan kontaktor trafo Kondisi finger ada yang  Tidak ada spare, Dilakukan


13 ESP V Ready
EH160 spare baru sudah aus penggantian

Motor ERM2A rumah  Tidak ada spare, Dilakukan


14 Pengadaan motor spare baru ESP V Ready
bearing DE rusak penggantian

Kondisi Adaptor hopper 
Pengadaan Adaptor hopper
vibrator ESP lifetime. 
vibrator ESP beserta Tidak ada spare, Dilakukan
15 ESP V Ready Vibrator 17A kondisi tanpa 
dudukannya (Warna Orange) penggantian
adaptor karena tidak ada 
baru.
spare.

Kondisi CLR 9A, 4A, 2A  Tidak ada spare, Dilakukan


16 Penggantian CLR baru ESP V Baik Outage
berdengung ketika operasi penggantian

Uap blowdown mengarah ke 
Penambahan pipa dari
MCC Boiler menyebabkan  Dilakukan modifikasi line dan
17 blowdown diarahkan menjauh Blowdown V Normal
ruangan beruap dan sangat  pembuatan pit
dari bawah MCC Boiler
lembab rawan short

Penambahan indikator
Tidak terdapat indikator arus 
18 parameter arus di PAH dan PAH dan SAH V Penambahan CT dan tranducer
pada monitor CCR
SAH

Paiton, 8 Desember 2022

SPVS Outage management Manager Pemeliharaan

Hendrik Suyanto

Anda mungkin juga menyukai