DAFTAR UPAH, BAHAN DAN PERALATAN

PEKERJAAN : PEMBANGUNAN JARINGAN IRIGASI D.I. LHOK GUCI (18.542 HA) DI KABUPATEN
SATUAN KERJA : SNVT PELAKSANAAN JARINGAN PEMANFAATAN AIR SUMATERA I
KEGIATAN : IRIGASI DAN RAWA I
TAHUN ANGGARAN : 2023

HARGA SATUAN
NO. URAIAN Kode SAT. KETERANGAN
(Rp.)
A DAFTAR TENAGA KERJA

1 Pekerja L.01 OH 117.000,00


2 Tukang Batu/ Besi/ Pipa/ Beton L.02 OH 130.000,00
3 Tukang Kayu/ Cat/ Listrik/ Las L.02 OH 130.000,00
4 Kepala Tukang Batu/ Besi/ Pipa/ Beton L.03 OH 135.000,00
5 Kepala Tukang Kayu/ Cat/ Listrik/ Las L.03 OH 135.000,00
6 Mandor L.04 OH 140.000,00
7 Akhli alat berat L.08 OH 150.000,00
8 Pelaksana /Pengguna L.08 OH 150.000,00
9 Staf (kontraktor) L.07 OH 150.000,00

B DAFTAR BAHAN/MATERIAL

1 Geotextile - Geogrid Composite M.10 M2 34.300,00


2 Tanah Timbun M.38 m3 65.000,00
3 Pipa Galvanis f 3" tebal 3.2 mm M.24 m' 196.000,00
4 Plastik cor M.28 Kg 11.700,00
5 Pasir beton/Kerikil M.19 m3 225.400,00
6 Besi pengaku M.6 Kg 14.700,00
7 Kawat las listrik M.13 Kg 34.300,00
8 Beton K-225 M3 1.330.200,00
9 Pasangan Bata M3 1.393.100,00
10 Pintu sorong baja roda gigi (stang tunggal) M.26 Bh 27.440.000,00
b =0,9m, h=0,7m
11 Pintu angkat b =0,3m, h=0,4m M.26 Bh 16.660.000,00
12 Wire Mesh M8 M.94.a Kg 17.600,00
13 Kawat beton M.60 Kg 22.500,00
14 Multiflex Tebal 12 M.39.d Lembar 142.100,00
15 Multiplek tebal 18 mm M.33.d Lembar 289.100,00
16 Tiang kayu 8/12 kelas II, tinggi 4m M.33.a m3 4.410.000,00
17 Frame besi L.30.30.3 M.54.g kg 17.100,00
18 Paku campuran 5 cm + 7cm M.72.b kg 21.500,00
19 Cat kayu M.128.b kg 42.100,00
20 Kaso 5/7 cm M.37.a m3 4.900.000,00
21 Kaso 4/6 cm (Kelas 3) M.50.d m3 3.920.000,00
22 Papan 2/20 (Kelas 3) M.48.e m3 3.920.000,00
23 Paku 5 cm dan 7 cm M.77.d kg 21.500,00
24 Minyak Bekisting M.141 Liter 14.700,00
25 PC / Portland cement Zak 73.500,00
26 PC / Portland cement M.23 kg 1.800,00
27 PB / Pasir beton M3 186.200,00
28 PB / Pasir beton M.05.a.3 kg 133,00
29 Kr / Kerikil M3 225.400,00
30 Kr / Kerikil M.04.d.3 kg 166,96
31 Air M.02.a.3) Liter 75,00
32 Batu belah M.23 m3 303.800,00
33 Batu belah M.03.d.3 m3 303.800,00
34 Pasir pasang M.05.a.3 m3 186.200,00
35 Batu - Bata M.04.c Buah 750,00
36 Besi Beton M.23 Kg 17.100,00
37 Kawat Beton M.05.a.3 Kg 21.500,00
38 Pipa PVC ø2" M.117.b-e m’ 9.800,00
39 Ijuk M.43 kg 24.500,00
40 Kerikil M.04.b.3 m3 225.400,00
41 Water stop PVC-200mm M.156.b m 156.800,00
42 Kawat Beton M.72 kg 22.500,00
26 Solar (Non Subsidi) Ltr 17.600,00
28 Minyak Pelumas/Oli Ltr 24.500,00
30 Multipleks 12 mm Lbr 166.600,00
32 Multipleks 18 mm Lbr 274.400,00

C DAFTAR PERALATAN

1 Mesin las 250Va E.01 Hari 150.000,00


2 Bulldozer E.04 Jam 698.873,26
3 Dump Truck 4 M3 E.08 Jam 396.143,83
4 Single Drum Roller E.09 Jam 417.141,49
5 Excavator E.10 Jam 563.556,49
6 Motor Grader E.13 Jam 743.825,96
7 Water Tanker 3000 - 4500 Ltr E.23 Jam 366.416,43
8 Tripod E.50 Sewa - Hr 50.000,00
9 Palu/Godam . Buah 75.000,00
10 Pompa air diesel 15 KW; Q = 100 L/s E.39.c Jam 175.000,00
11 Concrete Mixer 0,35 m3 E.29.c Sewa - Hr 150.000,00
12 Concrete Mixer 0,30 m3 E.32.a Sewa - Hr 150.000,00
13 Concrete Vibrator To.42.a Sewa - Hr 100.000,00
14 Waterpass To.43 Sewa - Hr 150.000,00
15 Theodolith To.35.a Sewa - Hr 150.000,00

Anda mungkin juga menyukai