DAFTAR HARGA SATUAN UPAH DAN BAHAN

BAHAN DAN UPAH 2019

HARGA SATUAN
NO KOMPONEN SATUAN
( Rp )
1 2 3 4

I UPAH
1 Mandor HOK 133,200.00
2 Kepala Tukang HOK 133,200.00
3 Tukang HOK 111,900.00
4 Pembantu Tukang HOK 125,700.00

II BAHAN / MATERIAL
1 Atras (tanah urug) M3 223,850.00
2 Bata merah BH 1,210.00
3 Batu belah 10/15 cm M3 251,790.00
4 Besi beton 10 mm Kg 97,900.00
5 Cat dasar / menie sejenis F-TALIT Kg 35,090.00
6 Cat penutup tembok sejenis Vinilex Kg 25,440.00
7 Granit 60x60 bh 162,000.00
8 Genteng nok metal m 52,470.00
9 Genteng Metal Lbr 101,420.00
10 GRC tebal 4 mm Lbr 66,000.00
11 Lisplank GRC m 35,000.00
12 Kawat beton Kg 35,090.00
13 List keliling gypsum lebar 8 cm M' 17,050.00
14 Paku biasa 1/2" - 1" Kg 21,010.00
15 Paku biasa 2" - 5" Kg 21,010.00
16 Paku pancing 60 x 230
17 Paku sekrup 3" - 5" Kg 17,000.00
18 Paku ulir 21,700.00
16 Pasir beton M3 223,850.00
17 Pasir pasang M3 223,850.00
18 Pasir urug M3 223,850.00
19 Pelumas bekisting Ltr 44,000.00
20 Plamir kayu / kualitas 1 Kg 27,500.00
21 Plamir tembok Kg 22,000.00
22 Portland cemen (PC) Kg 1,300.00
23 Split ( batu pecah mesin ) 2/3 M3 343,750.00
24 Triplek 3 mm Lbr 90,970.00
25 Triplek 9 mm Lbr 177,760.00
26 Pintu Alumunium ( 160 X 250 ) UNIT 2,400,500.00
27 Jendela Alumunium ( 220 X 140 ) UNIT 850,500.00

1 2 3 4

28 Besi Holo 2 cm M' 4,345.00


29 Besi Holo 4 cm M' 6,187.50
30 Baja Ringan 0.75 SNI M2 125,000.00
31 Buis Beton setengah dia 30 cm M 20,000.00
32 Kaca 5mm M2 228,960.00
33 Kusen Pintu Alumunium M' 180,000.00
34 Rangka Pintu Alumunium M' 90,000.00
35 Lockcase BH 95,000.00
36 Double Cylinder BH 80,000.00
37 Full Handle BH 490,000.00
38 Engsel Pintu BH 44,600.00
39 Kayu Kaso bt 39,000.00
40 Kayu Papan bt 35,000.00
41 Kayu Dolken bt 45,000.00
ANALISA SATUAN PEKERJAAN

KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL


KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

ABK.100.04 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN


0.02 HOK Pembantu tukang 125,700.00 2,514.00
0.006 HOK Mandor 133,200.00 799.20 3,313.20
3,313.20
ABK.100.05 1 M2 PENGUKURAN DAN PEMASANGAN BOUWPLANK / PROPIL
0.012 M3 Kayu kaso (kayu hutan) 39,000.00 468.00
0.007 M3 Kayu papan (kayu hutan) 3/20 35,000.00 245.00
0.02 Kg Paku biasa 2" - 5" 21,010.00 420.20 1,133.20

0.02 HOK Pembantu tukang 125,700.00 2,514.00


0.02 HOK Tukang kayu 111,900.00 2,238.00
0.01 HOK Kepala tukang 133,200.00 1,332.00
0.006 HOK Mandor 133,200.00 799.20 6,883.20
8,016.40
ABK.100.12 1 M2 PEMBUATAN LOS KERJA / DIREKSIKEET
1.25 bt Kayu dolken 8 - 10/4 m' 45,000.00 56,250.00
0.12 M3 Kayu hutan 35,000.00 4,200.00
4.32 kg Semen portland 1,300.00 5,616.00
0.022 M3 Pasir Pasang 223,850.00 4,924.70
0.25 lbr Seng Gelombang 3"-6" BJLS 30 0.00
0.08 M2 Raam kawat 0.00
0.15 bh Kunci gembok 0.00
0.15 set engsel pintu 0.00
0.2 kg Paku biasa 2" - 5" 0.00
0.06 lbr Triplek 3 mm 0.00 70,990.70

0.5 HOK Pembantu tukang 125,700.00 62,850.00


0.6 HOK Tukang kayu 111,900.00 67,140.00
0.06 HOK Kepala tukang 133,200.00 7,992.00
0.03 HOK Mandor 133,200.00 3,996.00 141,978.00
212,968.70
ABK. 200.01 1 M3 GALIAN TANAH BIASA
0.4 HOK Pembantu tukang 125,700.00 50,280.00
0.04 HOK Mandor 133,200.00 5,328.00 55,608.00
55,608.00
ABK. 200.09 1 M3 URUGAN KEMBALI BEKAS GALIAN
0.192 HOK Pembantu tukang 125,700.00 24,134.40
0.019 HOK Mandor 133,200.00 2,530.80 26,665.20
26,665.20

1 2 3 4 5 6

ABK. 200.10 1 M3 PEMADATAN TANAH


0.5 HOK Pembantu tukang 125,700.00 62,850.00
0.05 HOK Mandor 133,200.00 6,660.00 69,510.00
69,510.00
ABK. 200.11 1 M3 URUGAN PASIR
1.2 M3 Pasir urug 223,850.00 268,620.00 268,620.00

0.3 HOK Pembantu tukang 125,700.00 37,710.00


0.01 HOK Mandor 133,200.00 1,332.00 39,042.00
307,662.00
ABK. 200.12 1 M3 URUGAN TANAH
1.2 M3 Tanah Urug 223,850.00 268,620.00 268,620.00

0.3 HOK Pembantu tukang 125,700.00 37,710.00


0.01 HOK Mandor 133,200.00 1,332.00 39,042.00
307,662.00
ABK.250.06 1 M3 PASANGAN PONDASI BATU BELAH AD. 1:4
1.1 M3 Batu belah 15/20 cm 251,790.00 276,969.00
163 Kg Semen portland 1,300.00 211,900.00
0.52 M3 Pasir Pasang 223,850.00 116,402.00 605,271.00
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

1.5 HOK Pembantu tukang 125,700.00 188,550.00


0.6 HOK Tukang batu 111,900.00 67,140.00
0.06 HOK Kepala tukang 133,200.00 7,992.00
0.075 HOK Mandor 133,200.00 9,990.00 273,672.00
878,943.00
ABK.250.07 1 M3 PASANGAN PONDASI BATU BELAH AD. 1:5
1.1 M3 Batu belah 15/20 cm 251,790.00 276,969.00
136 Kg Semen portland 1,300.00 176,800.00
0.544 M3 Pasir Pasang 223,850.00 121,774.40 575,543.40

1.5 HOK Pembantu tukang 125,700.00 188,550.00


0.6 HOK Tukang batu 111,900.00 67,140.00
0.06 HOK Kepala tukang 133,200.00 7,992.00
0.075 HOK Mandor 133,200.00 9,990.00 273,672.00
849,215.40
ABK.250.14 1 M3 PASANGAN BATU KOSONG
1.2 M3 Batu belah 10/15 cm 251,790.00 302,148.00
0.3 M3 Pasir urug 223,850.00 67,155.00 369,303.00

0.78 HOK Pembantu tukang 125,700.00 98,046.00


0.39 HOK Tukang batu 111,900.00 43,641.00
0.039 HOK Kepala tukang 133,200.00 5,194.80
0.039 HOK Mandor 133,200.00 5,194.80 152,076.60
521,379.60

ABK.300.08 1 M3 MEMBUAT BETON TUMBUK AD. 1:3:6 TEBAL 5 CM


197 Kg Semen portland 1,300.00 256,100.00
0.47 M3 Pasir beton 223,850.00 105,209.50
0.94 M3 Kerikil 343,750.00 323,125.00 684,434.50

1.65 HOK Pembantu tukang 125,700.00 207,405.00


0.25 HOK Tukang batu 111,900.00 27,975.00
0.025 HOK Kepala tukang 133,200.00 3,330.00
0.08 HOK Mandor 133,200.00 10,656.00 249,366.00
933,800.50
ABK. 300.19 1 M3 BETON BERTULANG AD. 1:2:3
232 Kg Semen portland 1,300.00 301,600.00
0.52 M3 Pasir beton 223,850.00 116,402.00
0.78 M3 Spleet 2/3 cm 343,750.00 268,125.00 686,127.00

1.65 HOK Pembantu tukang 125,700.00 207,405.00


0.25 HOK Tukang batu 111,900.00 27,975.00
0.025 HOK Kepala tukang 133,200.00 3,330.00
0.08 HOK Mandor 133,200.00 10,656.00 249,366.00
935,493.00
ABK. 300.32 1 KG PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR
1.05 Kg Besi beton 97,900.00 102,795.00
0.015 Kg Kawat beton 35,090.00 526.35 103,321.35

0.007 HOK Pembantu tukang 125,700.00 879.90


0.007 HOK Tukang besi 111,900.00 783.30
0.0007 HOK Kepala tukang 133,200.00 93.24
0.0003 HOK Mandor 133,200.00 39.96 1,796.40
105,117.75
ABK. 300.35 1 M2 PASANG BEKISTING UNTUK PONDASI
0.04 M3 Kayu hutan/papan/kaso 1,800,000.00 72,000.00
0.3 Kg Paku biasa 2" - 5" 21,010.00 6,303.00
0.1 Ltr Pelumas bekisting 44,000.00 4,400.00 82,703.00

0.3 HOK Pembantu tukang 125,700.00 37,710.00


0.26 HOK Tukang kayu 111,900.00 29,094.00
0.026 HOK Kepala tukang 133,200.00 3,463.20
0.005 HOK Mandor 133,200.00 666.00 70,933.20
153,636.20

1 M2 PASANG BEKISTING UNTUK TANGGA


KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

0.0300 m3 Kayu papan Albasia 1,850,000.00 55,500.00


0.4000 kg Paku biasa 2" - 5" 21,010.00 8,404.00
0.1500 Lt Minyak bekisting 44,000.00 6,600.00
0.0150 m3 Balok kayu Borneo 5/7 1,850,000.00 27,750.00
0.3500 Lbr Plywood tebal 9 mm 177,760.00 62,216.00
2.0000 Btg Dolken dia 8 - 10/400 cm 30,000.00 60,000.00 220,470.00

0.3200 Oh Pekerja 125,700.00 40,224.00


0.3300 Oh Tukang 111,900.00 36,927.00
0.0330 Oh Kepala Tukang 133,200.00 4,395.60
0.0060 Oh Mandor 133,200.00 799.20 82,345.80
Jumlah 302,815.80
ABK. 300.36 1 M2 PASANG BEKISTING UNTUK SLOOP, KOLOM BIASA & RINGBALK
0.045 M3 Kayu hutan/papan/kaso 1,850,000.00 83,250.00
0.3 Kg Paku biasa 2" - 5" 21,010.00 6,303.00
0.1 Ltr Pelumas bekisting 44,000.00 4,400.00 93,953.00
2 x pakai, diambil 62.5% 58,720.63

0.3 HOK Pembantu tukang 125,700.00 37,710.00


0.26 HOK Tukang kayu 111,900.00 29,094.00
0.026 HOK Kepala tukang 133,200.00 3,463.20
0.005 HOK Mandor 133,200.00 666.00 70,933.20
2 x pakai, diambil 62% 44,333.25

103,053.88

ABK. 300.37 1 M2 PASANG BEKISTING UNTUK KOLOM STRUKTUR


0.04 M3 Kayu hutan/papan/kaso 1,850,000.00 74,000.00
0.015 M3 Balok kayu hutan 1,850,000.00 27,750.00
0.4 Kg Paku biasa 2" - 5" 21,010.00 8,404.00
0.2 Ltr Pelumas bekisting 44,000.00 8,800.00
0.35 Lbr Triplex tebal 9 mm 177,760.00 62,216.00
2 Btg Dolken kayu Ø 8-10/4' 30,000.00 60,000.00 241,170.00

0.3 HOK Pembantu tukang 125,700.00 37,710.00


0.33 HOK Tukang kayu 111,900.00 36,927.00
0.033 HOK Kepala tukang 133,200.00 4,395.60
0.006 HOK Mandor 133,200.00 799.20 79,831.80
321,001.80
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

ABK. 300.38 1 M2 PASANG BEKISTING UNTUK BALOK


0.04 M3 Kayu hutan/papan/kaso 1,850,000.00 74,000.00
0.018 M3 Balok kayu hutan 1,850,000.00 33,300.00
0.4 Kg Paku biasa 2" - 5" 21,010.00 8,404.00
0.2 Ltr Pelumas bekisting 44,000.00 8,800.00
0.35 Lbr Triplex tebal 9 mm 177,760.00 62,216.00
2 Btg Dolken kayu Ø 8-10/4' 30,000.00 60,000.00 246,720.00

0.32 HOK Pembantu tukang 125,700.00 40,224.00


0.33 HOK Tukang kayu 111,900.00 36,927.00
0.033 HOK Kepala tukang 133,200.00 4,395.60
0.006 HOK Mandor 133,200.00 799.20 82,345.80
329,065.80
ABK.300.39 1 M2 PASANG BEKISTING UNTUK LANTAI
0.04 M3 Kayu hutan/papan/kaso 1,850,000.00 74,000.00
0.015 Kg Balok kayu hutan 1,850,000.00 27,750.00
0.2 Ltr Pelumas bekisting 21,010.00 4,202.00
0.4 Kg Paku biasa 2" - 5" 21,010.00 8,404.00
0.35 Lbr Triplex tebal 9 mm 177,760.00 62,216.00
6 Btg Dolken kayu Ø 8-10/4' 30,000.00 180,000.00 356,572.00

0.32 HOK Pembantu tukang 125,700.00 40,224.00


0.33 HOK Tukang kayu 111,900.00 36,927.00
0.033 HOK Kepala tukang 133,200.00 4,395.60
0.006 HOK Mandor 133,200.00 799.20 82,345.80
438,917.80
ABK.300.42 1 M2 MEMBUAT BETON DENGAN MUTU K 225
388 Kg semen portland 1,300.00 504,400.00
0.65 M3 Pasir beton 223,850.00 145,502.50
0.65 M3 Kerikil 343,750.00 223,437.50 873,340.00

6 HOK Pembantu tukang 125,700.00 754,200.00


1 HOK Tukang batu 111,900.00 111,900.00
0.1 HOK Kepala tukang 133,200.00 13,320.00
0.3 HOK Mandor 133,200.00 39,960.00 919,380.00
1,792,720.00
ABK.350.10 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA AD. 1:2
70 Bh Bata merah 5 x 11 x 22 cm 1,210.00 84,700.00
18.95 Kg Semen portland 1,300.00 24,635.00
0.038 M3 Pasir pasang 223,850.00 8,506.30 117,841.30

0.32 HOK Pembantu tukang 125,700.00 40,224.00


0.1 HOK Tukang batu 111,900.00 11,190.00
0.01 HOK Kepala tukang 133,200.00 1,332.00
0.015 HOK Mandor 133,200.00 1,998.00 54,744.00
172,585.30
ABK.350.11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA AD. 1:3
70 Bh Bata merah 5x11x22 cm 1,210.00 84,700.00
14.37 Kg Semen portland 1,300.00 18,681.00
0.04 M3 Pasir pasang 223,850.00 8,954.00 112,335.00

0.32 HOK Pembantu tukang 125,700.00 40,224.00


0.1 HOK Tukang batu 111,900.00 11,190.00
0.01 HOK Kepala tukang 133,200.00 1,332.00
0.015 HOK Mandor 133,200.00 1,998.00 54,744.00
167,079.00

ABK.350.12 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA AD. 1:4


70 Bh Bata merah 5 x 11 x 22 cm 1,210.00 84,700.00
11.5 Kg Semen Portland 1,300.00 14,950.00
0.043 M3 Pasir Pasang 223,850.00 9,625.55 109,275.55

0.32 HOK Pembantu tukang 125,700.00 40,224.00


0.1 HOK Tukang batu 111,900.00 11,190.00
0.01 HOK Kepala tukang 133,200.00 1,332.00
0.015 HOK Mandor 133,200.00 1,998.00 54,744.00
164,019.55
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

ABK.350.13 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA AD. 1:5


70 Bh Bata merah 5 x 11 x 22 cm 1,210.00 84,700.00
9.68 Kg Semen Portland 1,300.00 12,584.00
0.045 M3 Pasir Pasang 223,850.00 10,073.25 107,357.25

0.32 HOK Pembantu tukang 125,700.00 40,224.00


0.1 HOK Tukang batu 111,900.00 11,190.00
0.01 HOK Kepala tukang 133,200.00 1,332.00
0.015 HOK Mandor 133,200.00 1,998.00 54,744.00
162,101.25
ABK.350.28 1 M2 PASANG DINDING ROOSTER / KERAWANG 12 X 11 X 24 CM
36 Bh Rooster / batu kerawang 10,000.00 360,000.00
12.8 Kg Semen Portland 1,300.00 16,640.00
0.035 M3 Pasir Pasang 223,850.00 7,834.75 384,474.75

0.3 HOK Pembantu tukang 125,700.00 37,710.00


0.1 HOK Tukang batu 111,900.00 11,190.00
0.01 HOK Kepala tukang 133,200.00 1,332.00 50,232.00
434,706.75
ABK.360.02 1 M2 PLESTERAN AD. 1:2 TEBAL 15 MM
8.52 Kg Semen Portland 1,300.00 11,076.00
0.017 M3 Pasir Pasang 223,850.00 3,805.45 14,881.45

0.2 HOK Pembantu tukang 125,700.00 25,140.00


0.15 HOK Tukang batu 111,900.00 16,785.00
0.015 HOK Kepala tukang 133,200.00 1,998.00
0.01 HOK Mandor 133,200.00 1,332.00 45,255.00
60,136.45
ABK.360.03 1 M2 PLESTERAN AD. 1:3 TEBAL 15 MM
6.48 Kg Semen Portland 1,300.00 8,424.00
0.019 M3 Pasir Pasang 223,850.00 4,253.15 12,677.15

0.2 HOK Pembantu tukang 125,700.00 25,140.00


0.15 HOK Tukang batu 111,900.00 16,785.00
0.015 HOK Kepala tukang 133,200.00 1,998.00
0.01 HOK Mandor 133,200.00 1,332.00 45,255.00
57,932.15
ABK.360.04 1 M2 PLESTERAN AD. 1:4 TEBAL 15 MM
5.2 Kg Semen Portland 1,300.00 6,760.00
0.02 M3 Pasir Pasang 223,850.00 4,477.00 11,237.00

0.2 HOK Pembantu tukang 125,700.00 25,140.00


0.15 HOK Tukang batu 111,900.00 16,785.00
0.015 HOK Kepala tukang 133,200.00 1,998.00
0.01 HOK Mandor 133,200.00 1,332.00 45,255.00
56,492.00
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

SNI 6.24.2 1 M2 PLESTERAN AD. 1:5 TEBAL 30 MM


12.96 Kg Semen Portland 1,300.00 16,848.00
0.038 M3 Pasir Pasang 223,850.00 8,506.30 25,354.30

0.32 HOK Pembantu tukang 125,700.00 40,224.00


0.25 HOK Tukang batu 111,900.00 27,975.00
0.025 HOK Kepala tukang 133,200.00 3,330.00
0.015 HOK Mandor 133,200.00 1,998.00 73,527.00
98,881.30
ABK. 360.06 1 M2 PLESTERAN ADDICTIVE UNTUK BETON
0.5 Kg Zat addictive 0.00 0.00

0.2 HOK Pembantu tukang 125,700.00 25,140.00


0.15 HOK Tukang kayu 111,900.00 16,785.00
0.015 HOK Kepala tukang 133,200.00 1,998.00
0.01 HOK Mandor 133,200.00 1,332.00 45,255.00
45,255.00
1 M2 ACIAN

3.25 m2 Semen Portland 1,300.00 4,225.00 4,225.00

0.2 Oh Pekerja 125,700.00 25,140.00


0.1 Oh Tukang 111,900.00 11,190.00
0.01 Oh Kepala Tukang 133,200.00 1,332.00
0.01 Oh Mandor 133,200.00 1,332.00 38,994.00
Jumlah 43,219.00
1 M' PASANG LISTPLANK GRC
1 M Listplang GRC 35,000.00 35,000.00
0.05 Kg Paku biasa 2" - 5" 21,010.00 1,050.50 36,050.50

0.1 HOK Pembantu tukang 125,700.00 12,570.00


0.2 HOK Tukang kayu 111,900.00 22,380.00
0.02 HOK Kepala tukang 133,200.00 2,664.00
0.005 HOK Mandor 133,200.00 666.00 38,280.00
74,330.50
ABK.452.36 1 M' PASANG LIST KELILING (TS.5) GYPSUM
1 M' List keliling gypsum 17,050.00 17,050.00
0.05 Kg Paku biasa 1/2' -1' 21,010.00 1,050.50 18,100.50

0.1 HOK Pembantu tukang 125,700.00 12,570.00


0.2 HOK Tukang kayu 111,900.00 22,380.00
0.02 HOK Kepala tukang 133,200.00 2,664.00
0.005 HOK Mandor 133,200.00 666.00 38,280.00
56,380.50

ABK.452.37 1 M' PASANG LIST DROP (SB) GYPSUM


1 M' List drop (SB) gypsum 0.00
0.05 Kg Paku biasa 1/2' -1' 0.00 0.00

0.1 HOK Pembantu tukang 125,700.00 12,570.00


0.2 HOK Tukang kayu 111,900.00 22,380.00
0.02 HOK Kepala tukang 133,200.00 2,664.00
0.005 HOK Mandor 133,200.00 666.00 38,280.00
38,280.00
ABK.452.38 1 M' PASANG BEADING PENURUNAN (PC) GYPSUM
1 M' Beading penurunan (PC) Gypsum 0.00
0.05 Kg Paku biasa 1/2' -1' 0.00 0.00

0.1 HOK Pembantu tukang 125,700.00 12,570.00


0.2 HOK Tukang kayu 111,900.00 22,380.00
0.02 HOK Kepala tukang 133,200.00 2,664.00
0.005 HOK Mandor 133,200.00 666.00 38,280.00
38,280.00
ABK.452.39 1 M' PASANG BEADING HORISON GYPSUM
1 M' Beading horison Gypsum 0.00
0.05 Kg Paku biasa 1/2' -1' 0.00 0.00
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

0.1 HOK Pembantu tukang 125,700.00 12,570.00


0.2 HOK Tukang kayu 111,900.00 22,380.00
0.02 HOK Kepala tukang 133,200.00 2,664.00
0.005 HOK Mandor 133,200.00 666.00 38,280.00
38,280.00
ABK. 452.40 1 M2 PASANG GYPSUM BOARD UNTUK PLAFOND
0.364 Lbr Gypsum board 0.00
0.11 Kg Paku biasa 1/2 - 1' 0.00 0.00

0.1 HOK Pembantu tukang 125,700.00 12,570.00


0.05 HOK Tukang kayu 111,900.00 5,595.00
0.005 HOK Kepala tukang 133,200.00 666.00
0.005 HOK Mandor 133,200.00 666.00 19,497.00
19,497.00
1 M2 PASANG GENTENG METAL
1.36 Lbr Genteng metal 80,000.00 108,800.00
0.2 Kg Paku biasa 1/2 - 1' 21,010.00 4,202.00 113,002.00

0.2 HOK Pembantu tukang 125,700.00 25,140.00


0.1 HOK Tukang kayu 111,900.00 11,190.00
0.01 HOK Kepala tukang 133,200.00 1,332.00
0.001 HOK Mandor 133,200.00 133.20 37,795.20
150,797.20
ABK.460.01 1 M2 ATAP GENTENG PRESS TANGAN EX JATIWANGI
25 Bh Genteng press tangan 0.00 0.00

0.15 HOK Pembantu tukang 125,700.00 18,855.00


0.075 HOK Tukang kayu/batu 111,900.00 8,392.50
0.008 HOK Kepala tukang 133,200.00 1,065.60
0.008 HOK Mandor 133,200.00 1,065.60 29,378.70
29,378.70

ABK.460.02 1 M2 ATAP GENTENG PRESS MESIN EX JATIWANGI


25 Bh Genteng press mesin 0.00 0.00

0.15 HOK Pembantu tukang 125,700.00 18,855.00


0.075 HOK Tukang kayu/batu 111,900.00 8,392.50
0.008 HOK Kepala tukang 133,200.00 1,065.60
0.008 HOK Mandor 133,200.00 1,065.60 29,378.70
29,378.70
ABK.460.03 1 M2 ATAP GENTENG PRESS DIGLAZUUR EX JATIWANGI
25 Bh Genteng press diglazuur 0.00 0.00

0.15 HOK Pembantu tukang 125,700.00 18,855.00


0.075 HOK Tukang kayu/batu 111,900.00 8,392.50
0.008 HOK Kepala tukang 133,200.00 1,065.60
0.008 HOK Mandor 133,200.00 1,065.60 29,378.70
29,378.70
ABK.460.04 1 M2 ATAP GENTENG GLAZUUR TURBO EX JATIWANGI
18 Bh Genteng diglazuur turbo 0.00 0.00

0.15 HOK Pembantu tukang 125,700.00 18,855.00


0.06 HOK Tukang kayu/batu 111,900.00 6,714.00
0.006 HOK Kepala tukang 133,200.00 799.20
0.008 HOK Mandor 133,200.00 1,065.60 27,433.80
27,433.80
ABK.460.05 1 M2 ATAP GENTENG NOK/BUBUNG PRESS TANGAN EX JATIWANGI
5 Bh Genteng nok / bubung 0.00
8 Kg Semen portland 0.00
0.032 M3 Pasir pasang 0.00 0.00

0.4 HOK Pembantu tukang 125,700.00 50,280.00


0.2 HOK Tukang kayu/batu 111,900.00 22,380.00
0.02 HOK Kepala tukang 133,200.00 2,664.00
0.002 HOK Mandor 133,200.00 266.40 75,590.40
75,590.40
ABK.460.06 1 M2 ATAP GENTENG NOK/BUBUNG PRESS MESIN EX JATIWANGI
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

5 Bh Genteng nok / bubung 0.00


8 Kg Semen portland 0.00
0.032 M3 Pasir pasang 0.00 0.00

0.4 HOK Pembantu tukang 125,700.00 50,280.00


0.2 HOK Tukang kayu/batu 111,900.00 22,380.00
0.02 HOK Kepala tukang 133,200.00 2,664.00
0.002 HOK Mandor 133,200.00 266.40 75,590.40
75,590.40

1 2 3 4 5 6

ABK.460.07 1 M2 ATAP GENTENG NOK/BUBUNG DIGLAZUUR EX JATIWANGI


5 Bh Genteng nok / bubung diglazuur 0.00
8 Kg Semen portland 0.00
0.032 M3 Pasir pasang 0.00 0.00

0.4 HOK Pembantu tukang 125,700.00 50,280.00


0.2 HOK Tukang kayu/batu 111,900.00 22,380.00
0.02 HOK Kepala tukang 133,200.00 2,664.00
0.002 HOK Mandor 133,200.00 266.40 75,590.40
75,590.40
ABK.460.16 1 M2 PASANG GENTENG BETON
11 Bh Genteng beton Err:509 Err:509
0.03 Kg Paku biasa 2" - 5" 21,010.00 630.30 Err:509

0.2 HOK Pembantu tukang 125,700.00 25,140.00


0.1 HOK Tukang kayu 111,900.00 11,190.00
0.01 HOK Kepala tukang 133,200.00 1,332.00
0.01 HOK Mandor 133,200.00 1,332.00 38,994.00
Err:509
ABK.460.17 1 M PASANG NOK BUBUNG GENTENG
3.5 Bh Nok bubung genteng 52,470.00 183,645.00
0.05 Bh Paku biasa 2" - 5" 21,010.00 1,050.50
10.8 Kg Semen portland 1,300.00 14,040.00
0.032 M3 Pasir pasang 223,850.00 7,163.20
1 Kg Semen warna 0.00 205,898.70

0.4 HOK Pembantu tukang 125,700.00 50,280.00


0.2 HOK Tukang kayu 111,900.00 22,380.00
0.02 HOK Kepala tukang 133,200.00 2,664.00
0.02 HOK Mandor 133,200.00 2,664.00 77,988.00
283,886.70
ABK.470.06 1 M2 LANGIT - LANGIT GRC TEBAL 4 MM
0.36 Lbr GRC tebal 4 mm 66,000.00 23,760.00
0.01 Kg Paku biasa 1/2" - 1" 21,010.00 210.10 23,970.10

0.07 HOK Pembantu tukang 125,700.00 8,799.00


0.1 HOK Tukang kayu 111,900.00 11,190.00
0.01 HOK Kepala tukang 133,200.00 1,332.00
0.0035 HOK Mandor 133,200.00 466.20 21,787.20
45,757.30

1 M2 PASANG LANTAI KERAMIK 40 X 40 CM


7 Bh Keramik 60 x 60 cm 11,000.00 77,000.00
9.3 Kg Semen portland 1,300.00 12,090.00
0.018 M3 Pasir pasang 223,850.00 4,029.30
1.5 Kg Semen warna 2,000.00 3,000.00 96,119.30

0.27 HOK Pembantu tukang 125,700.00 33,939.00


0.13 HOK Tukang kayu 111,900.00 14,547.00
0.013 HOK Kepala tukang 133,200.00 1,731.60
0.014 HOK Mandor 133,200.00 1,864.80 52,082.40
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

148,201.70
ABK.650.06 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM
25 Bh Keramik 20 x 20 cm Err:509 Err:509
11.38 Kg Semen portland 1,300.00 14,794.00
0.042 M3 Pasir pasang 223,850.00 9,401.70
1.5 Kg Semen warna 2,000.00 3,000.00 Err:509

0.62 HOK Pembantu tukang 125,700.00 77,934.00


0.35 HOK Tukang kayu 111,900.00 39,165.00
0.035 HOK Kepala tukang 133,200.00 4,662.00
0.03 HOK Mandor 133,200.00 3,996.00 125,757.00
Err:509
ABK.650.08 1 M2 PASANG DINDING KERAMIK 30 X 30 CM
11 Bh Keramik 30 x 30 cm 5,000.00 55,000.00
9.3 Kg Semen portland 1,300.00 12,090.00
0.018 M3 Pasir pasang 223,850.00 4,029.30
1.5 Kg Semen warna 2,000.00 3,000.00 74,119.30

0.6 HOK Pembantu tukang 125,700.00 75,420.00


0.45 HOK Tukang kayu 111,900.00 50,355.00
0.045 HOK Kepala tukang 133,200.00 5,994.00
0.03 HOK Mandor 133,200.00 3,996.00 135,765.00
209,884.30
ABK.650.09 1 M2 PASANG DINDING KERAMIK 20 X 25 CM
20 Bh Keramik 20 x 25 cm 4,250.00 85,000.00
9.3 Kg Semen portland 1,300.00 12,090.00
0.018 M3 Pasir pasang 223,850.00 4,029.30
1.5 Kg Semen warna 2,000.00 3,000.00 104,119.30

0.6 HOK Pembantu tukang 125,700.00 75,420.00


0.45 HOK Tukang kayu 111,900.00 50,355.00
0.045 HOK Kepala tukang 133,200.00 5,994.00
0.03 HOK Mandor 133,200.00 3,996.00 135,765.00
239,884.30

ABK.650.10 1 M2 PASANG DINDING KERAMIK 10 X 20 CM


50 Bh Keramik 10 x 20 cm 0.00
9.3 Kg Semen portland 0.00
0.018 M3 Pasir pasang 0.00
1.5 Kg Semen warna 0.00 0.00

0.6 HOK Pembantu tukang 125,700.00 75,420.00


0.45 HOK Tukang kayu 111,900.00 50,355.00
0.045 HOK Kepala tukang 133,200.00 5,994.00
0.03 HOK Mandor 133,200.00 3,996.00 135,765.00
135,765.00
ABK.650.11 1 M2 PASANG DINDING KERAMIK 20 X 25 CM
20 Bh Keramik 20 x 25 cm 4,250.00 85,000.00
9.3 Kg Semen portland 1,300.00 12,090.00
0.018 M3 Pasir pasang 150,000.00 2,700.00
1.5 Kg Semen warna 2,000.00 3,000.00 102,790.00

0.6 HOK Pembantu tukang 125,700.00 75,420.00


0.45 HOK Tukang kayu 111,900.00 50,355.00
0.045 HOK Kepala tukang 133,200.00 5,994.00
0.03 HOK Mandor 133,200.00 3,996.00 135,765.00
238,555.00
ABK. 650.18 1 M2 PASANG LANTAI 40 X 40 CM
6.4 Bh Keramik 40 x 40 cm 10,000.00 64,000.00
9.3 Kg Semen portland 1,300.00 12,090.00
0.018 M3 Pasir pasang 150,000.00 2,700.00
1.5 Kg Semen warna 2,000.00 3,000.00 81,790.00

0.27 HOK Pembantu tukang 125,700.00 33,939.00


0.13 HOK Tukang kayu 111,900.00 14,547.00
0.013 HOK Kepala tukang 133,200.00 1,731.60
0.0135 HOK Mandor 133,200.00 1,798.20 52,015.80
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

133,805.80
ABK.850.02 PASANG 1 BUAH KUNCI PINTU UKURAN BESAR
1 Bh Kunci tanam pintu ukuran besar 250,000.00 250,000.00

0.01 HOK Pembantu tukang 125,700.00 1,257.00


0.5 HOK Tukang kayu 111,900.00 55,950.00
0.01 HOK Kepala tukang 133,200.00 1,332.00
0.005 HOK Mandor 133,200.00 666.00 59,205.00
309,205.00

1 M2 PASANG GRASS BLOK UKURAN 30 X 45 CM TEBAL 10 CM

7.3 m2 Grassblok uk.30 X 45 cm 11,600.00 84,680.00


0.1 m3 Pasir beton 150,000.00 15,000.00 99,680.00

0.25 Oh Pekerja 125,700.00 31,425.00


0.5 Oh Tukang batu 111,900.00 55,950.00
0.025 Oh Kepala tukang batu 133,200.00 3,330.00
0.003 Oh Mandor 133,200.00 399.60 91,104.60
190,784.60

1 M2 PEK.BATU ALAM ANDESIT

1.1 m2 Batu Alam Andesit 175,000.00 192,500.00


0.034 Zak Semen 1,300.00 44.20
0.032 m3 Pasir pasang 150,000.00 4,800.00 197,344.20
1 m2 Finishing Coating Vernis

0.3 org Pekerja 125,700.00 37,710.00


0.75 org Tukang 111,900.00 83,925.00
0.185 org Kepala Tukang 133,200.00 24,642.00
0.025 org Mandor 133,200.00 3,330.00 149,607.00
1 ls Alat Bantu
Jumlah 346,951.20
ABK.850.05 PASANG 1 SET ENGSEL NYLON UNTUK PINTU
1 Bh Engsel pintu Err:509 Err:509 Err:509

0.015 HOK Pembantu tukang 125,700.00 1,885.50


0.15 HOK Tukang kayu 111,900.00 16,785.00
0.015 HOK Kepala tukang 133,200.00 1,998.00
0.00075 HOK Mandor 133,200.00 99.90 20,768.40
Err:509
ABK.850.06 PASANG 1 SET ENGSEL NYLON UNTUK JENDELA
1 Bh Engsel jendela Err:509 Err:509 Err:509

0.015 HOK Pembantu tukang 125,700.00 1,885.50


0.15 HOK Tukang kayu 111,900.00 16,785.00
0.015 HOK Kepala tukang 133,200.00 1,998.00
0.00075 HOK Mandor 133,200.00 99.90 20,768.40
Err:509
ABK.850.07 PASANG 1 BUAH GRENDEL PERNEKEL JENDELA/PINTU
1 Bh Grendel Jendela/Pintu Err:509 Err:509 Err:509

0.02 HOK Pembantu tukang 125,700.00 2,514.00


0.2 HOK Tukang kayu 111,900.00 22,380.00
0.02 HOK Kepala tukang 133,200.00 2,664.00
0.001 HOK Mandor 133,200.00 133.20 27,691.20
Err:509
ABK.850.09 PASANG 1 BUAH KAIT ANGIN
1 Bh Kait angin Err:509 Err:509 Err:509

0.015 HOK Pembantu tukang 125,700.00 1,885.50


0.15 HOK Tukang kayu 111,900.00 16,785.00
0.015 HOK Kepala tukang 133,200.00 1,998.00
0.00075 HOK Mandor 133,200.00 99.90 20,768.40
Err:509
ABK.850.16 1 M2 PASANG KACA POLOS TEBAL 3 MM
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

1.1 M2 Kaca polos Err:509 Err:509 Err:509

0.015 HOK Pembantu tukang 125,700.00 1,885.50


0.15 HOK Tukang kayu 111,900.00 16,785.00
0.015 HOK Kepala tukang 133,200.00 1,998.00
0.00075 HOK Mandor 133,200.00 99.90 20,768.40
Err:509
ABK.850.17 1 M2 PASANG KACA POLOS TEBAL 5 MM
1.1 M2 Kaca polos Err:509 Err:509 Err:509

0.015 HOK Pembantu tukang 125,700.00 1,885.50


0.15 HOK Tukang kayu 111,900.00 16,785.00 18,670.50
Err:509

ABK.850.17 1 M2 PASANG KACA POLOS TEBAL 5 MM


1.1 M2 Kaca polos Err:509 Err:509 Err:509

0.015 HOK Pembantu tukang 125,700.00 1,885.50


0.15 HOK Tukang kayu 111,900.00 16,785.00 18,670.50
Err:509
ABK. 900,18 1 M' PASANG TALANG DATAR SENG BJLS - 30
0.5 Lbr Seng BJLS - 30 0.00
0.015 Kg Paku biasa 2" - 5" 0.00
0.0096 M3 Kayu papan meranti 0.00
0.25 Ltr Flincote 0.00 0.00

0.15 HOK Pembantu tukang 125,700.00 18,855.00


0.4 HOK Tukang kayu 111,900.00 44,760.00
0.025 HOK Kepala tukang 133,200.00 3,330.00
0.00125 HOK Mandor 133,200.00 166.50 67,111.50
67,111.50

ABK. 900,19 1 M' PASANG TALANG MIRING SENG BJLS - 30


0.5 Lbr Seng BJLS - 30 0.00
0.015 Kg Paku biasa 2" - 5" 0.00
0.019 M3 Kayu papan meranti 0.00
0.3 Ltr Flincote 0.00 0.00

0.15 HOK Pembantu tukang 125,700.00 18,855.00


0.4 HOK Tukang kayu 111,900.00 44,760.00
0.025 HOK Kepala tukang 133,200.00 3,330.00 66,945.00
66,945.00
ABK. 950,06 1 M2 MENDEMPUL DAN MENGGOSOK KAYU YANG AKAN DIPLISTUR
0.08 Kg Dempul jadi 0.00
0.02 Kg Minyak cat 0.00
0.01 Kg Batu apung 0.00 0.00

0.04 HOK Pembantu tukang 125,700.00 5,028.00


0.04 HOK Tukang kayu 111,900.00 4,476.00
0.004 HOK Kepala tukang 133,200.00 532.80
0.0025 HOK Mandor 133,200.00 333.00 10,369.80
10,369.80

ABK. 950.07 1 M2 PENGECATAN BIDANG KAYU/BESI BERIKUT PLAMIR SEJENIS CAT KANSAI
0.15 Kg Plamir 27,500.00 4,125.00
0.2 Kg Menie 35,090.00 7,018.00
0.26 Kg Cat penutup kayu/besi Err:509 Err:509
0.17 Kg Cat dasar 0.00 Err:509

0.07 HOK Pembantu tukang 125,700.00 8,799.00


0.009 HOK Tukang cat 111,900.00 1,007.10
0.006 HOK Kepala tukang 133,200.00 799.20
0.0025 HOK Mandor 133,200.00 333.00 10,938.30
Err:509
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

ABK. 950,15 1 M2 PENGECATAN TEMBOK BARU ( 1 LPS PLAMIR +1 LPS CAT DASAR + 2 LPS CAT PENUTUP )
MUTU CAT SEJENIS VINILEX
0.1 Kg Plamir tembok 22,000.00 2,200.00
0.26 Kg Cat penutup 2 x ( tembok ) 25,440.00 6,614.40
0.1 Kg Cat dasar / menie 0.00 8,814.40

0.02 HOK Pembantu tukang 125,700.00 2,514.00


0.063 HOK ` 111,900.00 7,049.70
0.0063 HOK Kepala tukang 133,200.00 839.16
0.0025 HOK Mandor 133,200.00 333.00 10,735.86
19,550.26
ABK. 950,15. rob 1 M2 PENGECATAN TEMBOK BARU ( 2 LPS CAT PENUTUP )
MUTU CAT SEJENIS VINILEX
0.26 Kg Cat penutup 2 x ( tembok ) 25,440.00 6,614.40 6,614.40

0.02 HOK Pembantu tukang 125,700.00 2,514.00


0.063 HOK Tukang cat 111,900.00 7,049.70
0.0063 HOK Kepala tukang 133,200.00 839.16
0.0025 HOK Mandor 133,200.00 333.00 10,735.86
17,350.26
ABK. 955.28 1 M3 MENGERJAKAN KUSEN-KUSEN PINTU & JENDELA DARI KAYU BALAU
1.2 M3 Kayu balau Err:509 Err:509 Err:509

6 HOK Pembantu tukang 125,700.00 754,200.00


20 HOK Tukang kayu 111,900.00 2,238,000.00
2 HOK Kepala tukang 133,200.00 266,400.00
0.3 HOK Mandor 133,200.00 39,960.00 3,298,560.00
Upah kerja 2/3 Err:509

ABK. 960.38 1 M2 MENGERJAKAN RANGKA DAUN PINTU & JENDELA DARI KAYU BALAU
0.035 M3 Kayu balau Err:509 Err:509 Err:509

0.8 HOK Pembantu tukang 125,700.00 100,560.00


2 HOK Tukang kayu 111,900.00 223,800.00
0.2 HOK Kepala tukang 133,200.00 26,640.00
0.04 HOK Mandor 133,200.00 5,328.00 356,328.00
Err:509
ABK. 970.34 1 M2 PASANGAN JALUSI DARI KAYU BALAU
0.02 M3 Kayu balau Err:509 Err:509
0.075 Kg Paku biasa 1/2" - 1" 21,010.00 1,575.75 Err:509

0.025 HOK Pembantu tukang 125,700.00 3,142.50


0.9 HOK Tukang kayu 111,900.00 100,710.00
0.09 HOK Kepala tukang 133,200.00 11,988.00
0.012 HOK Mandor 133,200.00 1,598.40 117,438.90
Upah kerja Err:509

1 2 3 4 5 6
ABK. BJR.01.a 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL OMEGA (μ) UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PELANA BENTANG < 9 m
0.786 M' Profil kuda-kuda UK-75 tebal 0.83 mm 0.00
2.100 M' Profil kuda-kuda UK-75 tebal 0.83 mm 0.00
5.263 M' Profil reng GD-B tebal 0.48 mm 0.00
0.738 M' Wind Bracing PS-30 0.00
0.170 Pcs Tensioner TS-2 0.00
0.340 Pcs Foot Plate PK 1,50 mm 0.00
5.000 Pcs Plat Diafragma 0.00
0.680 Pcs Dynabolt 0.00
30.000 Pcs Self Drilling Screw # 8-18 X 13 0.00
25.000 Pcs Self Drilling Screw # 12-24 X 16 0.00 0.00

0.093 HOK Supervisor 133,200.00 12,387.60


0.086 HOK Kepala tukang 133,200.00 11,455.20
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

0.076 HOK Tukang 111,900.00 8,504.40


0.056 HOK Pekerja 125,700.00 7,039.20 39,386.40
39,386.40
ABK. BJR.01.b 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL OMEGA (μ) UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PERISAI BENTANG < 9 m
0.789 M' Profil kuda-kuda UK-75 tebal 0.83 mm 0.00
2.105 M' Profil kuda-kuda UK-75 tebal 0.83 mm 0.00
5.264 M' Profil reng GD-B tebal 0.48 mm 0.00
0.450 M' Wind Bracing PS-30 0.00
0.055 Pcs Tensioner TS-2 0.00
0.341 Pcs Foot Plate PK 1,50 mm 0.00
5.874 Pcs Plat Diafragma 0.00
0.550 Pcs Dynabolt 0.00
30.500 Pcs Self Drilling Screw # 8-18 X 13 0.00
25.500 Pcs Self Drilling Screw # 12-24 X 16 0.00 0.00

0.093 HOK Supervisor 133,200.00 12,387.60


0.086 HOK Kepala tukang 133,200.00 11,455.20
0.076 HOK Tukang 111,900.00 8,504.40
0.056 HOK Pekerja 125,700.00 7,039.20 39,386.40
39,386.40
ABK. BJR.02.a 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PELANA BENTANG < 9 m
1.12 M' Profil U 75 53 mm Zinc Alumunium G. 550 0.00
0.94 M' Profil U 60 53 mm Zinc Alumunium G. 550 0.00
1.12 M' Profil U 75 83 mm Zinc Alumunium G. 550 0.00
6.06 M' Reng U 39 0.43 mm Zinc Alumunium G. 550 0.00
0.45 Bh Plat Tumpu 0.00
2.12 Bh Plat Diafragma 0.5 mm 0.00
0.75 Bh Dynabolt 0.00
19.40 Bh Baut Kuda - Kuda 0.00
20.42 Bh Baut Reng 0.00 0.00

0.086 HOK Kepala tukang 133,200.00 11,455.20


0.076 HOK Tukang 111,900.00 8,504.40
0.056 HOK Pekerja 125,700.00 7,039.20 26,998.80
26,998.80
ABK. BJR.02.b 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PERISAI BENTANG < 9 m
1.12 M' Profil U 75 53 mm Zinc Alumunium G. 550 0.00
0.945 M' Profil U 60 53 mm Zinc Alumunium G. 550 0.00
1.12 M' Profil U 75 83 mm Zinc Alumunium G. 550 0.00
6.09 M' Reng U 39 0.43 mm Zinc Alumunium G. 550 0.00
0.47 Bh Plat Tumpu 0.00
2.12 Bh Plat Diafragma 0.5 mm 0.00
0.80 Bh Dynabolt 0.00
19.48 Bh Baut Kuda - Kuda 0.00
20.50 Bh Baut Reng 0.00 0.00

0.086 HOK Kepala tukang 133,200.00 11,455.20


0.076 HOK Tukang 111,900.00 8,504.40
0.056 HOK Pekerja 125,700.00 7,039.20 26,998.80
26,998.80
ABK. BJR.02.c 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PELANA BENTANG 9-12 m
1.31 M' Profil U 75 53 mm Zinc Alumunium G. 550 0.00
0.96 M' Profil U 60 53 mm Zinc Alumunium G. 550 0.00
1.31 M' Profil U 75 83 mm Zinc Alumunium G. 550 0.00
6.06 M' Reng U 39 0.43 mm Zinc Alumunium G. 550 0.00
0.45 Bh Plat Tumpu 0.00
2.12 Bh Plat Diafragma 0.5 mm 0.00
0.73 Bh Dynabolt 0.00
21.00 Bh Baut Kuda - Kuda 0.00
22.53 Bh Baut Reng 0.00 0.00

0.086 HOK Kepala tukang 133,200.00 11,455.20


0.076 HOK Tukang 111,900.00 8,504.40
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

0.056 HOK Pekerja 125,700.00 7,039.20 26,998.80


26,998.80

ABK. BJR.02.d 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PERISAI BENTANG 9-12 m
1.31 M' Profil U 75 53 mm Zinc Alumunium G. 550 0.00
0.99 M' Profil U 60 53 mm Zinc Alumunium G. 550 0.00
1.31 M' Profil U 75 83 mm Zinc Alumunium G. 550 0.00
6.09 M' Reng U 39 0.43 mm Zinc Alumunium G. 550 0.00
0.45 Bh Plat Tumpu 0.00
2.12 Bh Plat Diafragma 0.5 mm 0.00
0.75 Bh Dynabolt 0.00
21.03 Bh Baut Kuda - Kuda 0.00
22.55 Bh Baut Reng 0.00 0.00

0.086 HOK Kepala tukang 133,200.00 11,455.20


0.076 HOK Tukang 111,900.00 8,504.40
0.056 HOK Pekerja 125,700.00 7,039.20 26,998.80
26,998.80
ABK. BJR.02.e 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PELANA BENTANG 12-15 m
1.48 M' Profil U 75 53 mm Zinc Alumunium G. 550 0.00
1.01 M' Profil U 60 53 mm Zinc Alumunium G. 550 0.00
1.48 M' Profil U 75 83 mm Zinc Alumunium G. 550 0.00
6.06 M' Reng U 39 0.43 mm Zinc Alumunium G. 550 0.00
0.45 Bh Plat Tumpu 0.00
2.12 Bh Plat Diafragma 0.5 mm 0.00
0.73 Bh Dynabolt 0.00
21.00 Bh Baut Kuda - Kuda 0.00
22.53 Bh Baut Reng 0.00 0.00

0.086 HOK Kepala tukang 133,200.00 11,455.20


0.076 HOK Tukang 111,900.00 8,504.40
0.056 HOK Pekerja 125,700.00 7,039.20 26,998.80
26,998.80
ABK. BJR.02.f 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL UK.75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PERISAI BENTANG 12-15 m
1.48 M' Profil U 75 53 mm Zinc Alumunium G. 550 0.00
1.01 M' Profil U 60 53 mm Zinc Alumunium G. 550 0.00
1.48 M' Profil U 75 83 mm Zinc Alumunium G. 550 0.00
6.32 M' Reng U 39 0.43 mm Zinc Alumunium G. 550 0.00
0.668 Bh Plat Tumpu 0.00
2.12 Bh Plat Diafragma 0.5 mm 0.00
0.84 Bh Dynabolt 0.00
22.5 Bh Baut Kuda - Kuda 0.00
24.25 Bh Baut Reng 0.00 0.00

0.086 HOK Kepala tukang 133,200.00 11,455.20


0.076 HOK Tukang 111,900.00 8,504.40
0.056 HOK Pekerja 125,700.00 7,039.20 26,998.80
26,998.80

1 2 3 4 5 6
ABK. BJR.03.a 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL Z GALVANISED COATING G.550
BENTUK ATAP PELANA BENTANG < 10 m
5.18 M' Profil 45 X 27 B50 0.00
0.42 M' Profil 65 X 26 C08 0.00
0.92 M' Profil 75 X 40 W08 0.00
1.57 M' Profil 95 X 33 Z08 0.00
1.78 Bh - Multigrip 0.00
0.17 Bh - Bolt 0.00
29 Bh - Screw 0.00 0.00

0.086 HOK Kepala tukang 133,200.00 11,455.20


0.076 HOK Tukang 111,900.00 8,504.40
0.056 HOK Pekerja 125,700.00 7,039.20 26,998.80
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

26,998.80
ABK. BJR.03.b 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL Z GALVANISED COATING G.550
BENTUK ATAP PERISAI BENTANG < 10 m
5.190 M' Profil 45 X 27 B50 0.00
0.425 M' Profil 65 X 26 C08 0.00
0.925 M' Profil 75 X 40 W08 0.00
1.575 M' Profil 95 X 33 Z08 0.00
1.785 Bh - Multigrip 0.00
0.175 Bh - Bolt 0.00
29.25 Bh - Screw 0.00 0.00

0.086 HOK Kepala tukang 133,200.00 11,455.20


0.076 HOK Tukang 111,900.00 8,504.40
0.056 HOK Pekerja 125,700.00 7,039.20 26,998.80
26,998.80
ABK. BJR.04a 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL C-75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PELANA BENTANG < 9 m
2.780 M' Material Truss C (C channel, roof batten) 0.00
5.326 M' Wind Bracing 0.00
0.836 M' Bottom Bracing 0.00
1.576 M' Support Connection 0.00
0.680 Bh Hexagonal Screw 12 0.00
15.300 Bh Hexagonal Screw 10 0.00
20.520 Bh Dynabolt & Gurinda 0.00 0.00

0.115 HOK Supervisor 133,200.00 15,318.00


0.108 HOK Kepala Tukang 133,200.00 11,455.20
0.077 HOK Tukang 111,900.00 8,504.40
0.063 HOK Pekerja 125,700.00 7,039.20 42,316.80
42,316.80

1 2 3 4 5 6
ABK. BJR.04b 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL C-75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PERISAI BENTANG < 9 m
2.793 M' Material Truss C (C channel, roof batten) 0.00
5.328 M' Wind Bracing 0.00
0.836 M' Bottom Bracing 0.00
1.576 M' Support Connection 0.00
0.68 Bh Hexagonal Screw 12 0.00
15.38 Bh Hexagonal Screw 10 0.00
21.23 Bh Dynabolt & Gurinda 0.00 0.00

0.115 HOK Supervisor 133,200.00 15,318.00


0.108 HOK Kepala Tukang 133,200.00 11,455.20
0.077 HOK Tukang 111,900.00 8,504.40
0.063 HOK Pekerja 125,700.00 7,039.20 42,316.80
42,316.80
ABK. BJR.04c 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL C-75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PELANA BENTANG 9 - 15 m
3.251 M' Material Truss C (C channel, roof batten) 0.00
5.326 M' Wind Bracing 0.00
0.836 M' Bottom Bracing 0.00
1.576 M' Support Connection 0.00
0.680 Bh Hexagonal Screw 12 0.00
15.900 Bh Hexagonal Screw 10 0.00
20.800 Bh Dynabolt & Gurinda 0.00 0.00

0.115 HOK Supervisor 133,200.00 15,318.00


0.108 HOK Kepala Tukang 133,200.00 11,455.20
0.077 HOK Tukang 111,900.00 8,504.40
0.063 HOK Pekerja 125,700.00 7,039.20 42,316.80
42,316.80
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

ABK. BJR.04d 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL C-75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PERISAI BENTANG 9 - 15 m
3.267 M' Material Truss C (C channel, roof batten) 0.00
5.356 M' Wind Bracing 0.00
0.836 M' Bottom Bracing 0.00
1.576 M' Support Connection 0.00
0.680 Bh Hexagonal Screw 12 0.00
15.900 Bh Hexagonal Screw 10 0.00
20.800 Bh Dynabolt & Gurinda 0.00 0.00

0.115 HOK Supervisor 133,200.00 15,318.00


0.108 HOK Kepala Tukang 133,200.00 11,455.20
0.077 HOK Tukang 111,900.00 8,504.40
0.063 HOK Pekerja 125,700.00 7,039.20 42,316.80
42,316.80

1 2 3 4 5 6
ABK. BJR.05a 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN BENTUK ATAP PERISAI < 9 m
2.310 M' Profil web hollow HL-57 tebal 0.50 mm 0.00
1.320 M' Profil kuda-kuda hollow HL-57 tebal 0.55 mm 0.00
6.120 M' Reng bracing (PRT) 45 0.45 mm 0.00
0.151 M' Profil shock hollow HL-46 tebal 0.50 mm 0.00
18.000 Pcs Self Drilling screw Truss (SCT), 12 0.00
25.500 Pcs Self Drilling screw Reng (SCT), 12 0.00
1.136 Pcs Bracket 0.00
0.954 Pcs Dinabolt 0.00 0.00

0.100 HOK Supervisor 133,200.00 13,320.00


0.082 HOK Kepala Tukang 133,200.00 11,455.20
0.080 HOK Tukang Baja 111,900.00 8,504.40
0.070 HOK Pekerja 125,700.00 7,039.20 40,318.80
40,318.80
ABK. BJR.05b 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN BENTUK ATAP PELANA < 9 m
2.310 M' Profil web hollow HL-57 tebal 0.50 mm 0.00
1.320 M' Profil kuda-kuda hollow HL-57 tebal 0.55 mm 0.00
6.120 M' Reng bracing (PRT) 45 0.45 mm 0.00
0.151 M' Profil shock hollow HL-46 tebal 0.50 mm 0.00
18.000 Pcs Self Drilling screw Truss (SCT), 12 0.00
25.500 Pcs Self Drilling screw Reng (SCT), 12 0.00
1.236 Pcs Bracket 0.00
0.974 Pcs Dinabolt 0.00 0.00

0.100 HOK Supervisor 133,200.00 13,320.00


0.082 HOK Kepala Tukang 133,200.00 11,455.20
0.080 HOK Tukang Baja 111,900.00 8,504.40
0.070 HOK Pekerja 125,700.00 7,039.20 40,318.80
40,318.80
ABK. BJR.06a 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL C-75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PELANA BENTANG < 9 m
2.780 M' Material Truss C (C channel, roof batten) 0.00
5.326 M' Wind Bracing 0.00
0.836 M' Bottom Bracing 0.00
1.576 M' Support Connection 0.00
0.680 Bh Hexagonal Screw 12 0.00
15.300 Bh Hexagonal Screw 10 0.00
20.520 Bh Dynabolt & Gurinda 0.00 0.00

0.115 HOK Supervisor 133,200.00 15,318.00


0.108 HOK Kepala Tukang 133,200.00 11,455.20
0.077 HOK Tukang 111,900.00 8,504.40
0.063 HOK Pekerja 125,700.00 7,039.20 42,316.80
42,316.80
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

1 2 3 4 5 6
ABK. BJR.06b 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL C-75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PERISAI BENTANG < 9 m
2.793 M' Material Truss C (C channel, roof batten) 0.00
5.328 M' Wind Bracing 0.00
0.836 M' Bottom Bracing 0.00
1.576 M' Support Connection 0.00
0.68 Bh Hexagonal Screw 12 0.00
15.38 Bh Hexagonal Screw 10 0.00
21.23 Bh Dynabolt & Gurinda 0.00 0.00

0.115 HOK Supervisor 133,200.00 15,318.00


0.108 HOK Kepala Tukang 133,200.00 11,455.20
0.077 HOK Tukang 111,900.00 8,504.40
0.063 HOK Pekerja 125,700.00 7,039.20 42,316.80
42,316.80
ABK. BJR.06c 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL C-75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PELANA BENTANG 9 - 15 m
3.251 M' Material Truss C (C channel, roof batten) 0.00
5.326 M' Wind Bracing 0.00
0.836 M' Bottom Bracing 0.00
1.576 M' Support Connection 0.00
0.680 Bh Hexagonal Screw 12 0.00
15.900 Bh Hexagonal Screw 10 0.00
20.800 Bh Dynabolt & Gurinda 0.00 0.00

0.115 HOK Supervisor 133,200.00 15,318.00


0.108 HOK Kepala Tukang 133,200.00 11,455.20
0.077 HOK Tukang 111,900.00 8,504.40
0.063 HOK Pekerja 125,700.00 7,039.20 42,316.80
42,316.80
ABK. BJR.06d 1M2 MENGERJAKAN RANGKA ATAP BAJA RINGAN PROFIL C-75 ZINC-ALUMUNIUM G.550
BENTUK ATAP PERISAI BENTANG 9 - 15 m
3.267 M' Material Truss C (C channel, roof batten) 0.00
5.356 M' Wind Bracing 0.00
0.836 M' Bottom Bracing 0.00
1.576 M' Support Connection 0.00
0.680 Bh Hexagonal Screw 12 0.00
15.900 Bh Hexagonal Screw 10 0.00
20.800 Bh Dynabolt & Gurinda 0.00 0.00

0.115 HOK Supervisor 133,200.00 15,318.00


0.108 HOK Kepala Tukang 133,200.00 11,455.20
0.077 HOK Tukang 111,900.00 8,504.40
0.063 HOK Pekerja 125,700.00 7,039.20 42,316.80
42,316.80

ABK. PLAFOND 1M2 PASANG PLAFOND RANGKA HOLO DAN DENGAN PENUTUP
GRC BERIKUT PENGECATAN
1.00 M' GRC 4 mm 22,916.67 22,916.67
1.00 M' Holo 4/4 meni 6,187.50 6,187.50
2.92 M' Holo 2/4 meni 4,345.00 12,687.40
10.00 Kawat Bwg 12 0.00
0.01 Kg Paku screw 2.5 cm 21,010.00 210.10
42.50 Adhesive 0.00
0.50 Kain kasa 0.00
0.38 Kg Cat penutup 2 kali 25,440.00 9,540.00
0.25 Kg Paku beton 0.00 51,541.67

0.13 HOK Mandor 133,200.00 17,369.28


0.37 HOK Kepala tukang 133,200.00 48,844.44
0.06 HOK Tukang 111,900.00 7,228.74
0.12 HOK Pekerja 125,700.00 15,084.00 88,526.46
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

140,068.13
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

1 TITIK PENGADAAN DAN PEMASANGAN LAMPU DOWNLIGHT LENGKAP

1 bh Lampu Downlight Lengkap 105,000.00 105,000.00


5 m' Kabel NYM 2 x 1,5 sqmm 6,440.00 32,200.00
1 bh Kotak Sambung / T- Dus 3,500.00 3,500.00 140,700.00
1 ls Material Bantu 30 % 28,140.00 168,840.00

0.2 org Pekerja Trampil 65,000.00 13,000.00


0.1 org Tukang Listrik 80,000.00 8,000.00
0.1 org Kepala Tk Listrik 90,000.00 4,500.00
0.1 org Mandor 90,000.00 4,500.00 30,000.00
Jumlah 198,840.00
1 TITIK PENGADAAN DAN PEMASANGAN LAMPU TAMAN

1 bh Lampu Taman Lengkap 350,000.00 350,000.00


15 m' Kabel NYM 2 x 1,5 sqmm 6,440.00 96,600.00
15 m' Conduit dia. 15,8 mm (5/8") 3,100.00 46,500.00
1 bh Kotak Sambung / T- Dus 3,500.00 3,500.00
15 bh Klem Pipa 5/8" 330.00 4,950.00
1 bh Isolasi 2,500.00 2,500.00 504,050.00
1 ls Material Bantu 151,215.00 655,265.00

0.2 org Pekerja Trampil 65,000.00 13,000.00


0.1 org Tukang Listrik 80,000.00 8,000.00
0.1 org Kepala Tk Listrik 90,000.00 4,500.00
0.1 org Mandor 90,000.00 4,500.00 30,000.00
Jumlah 685,265.00
1 TITIK PENGADAAN DAN PEMASANGAN LAMPU SOROT

1 bh Lampu Sorot Halogen 250 W 250,000.00 250,000.00


15 m' Kabel NYM 2 x 1,5 sqmm 6,440.00 96,600.00
15 m' Conduit dia. 15,8 mm (5/8") 3,100.00 46,500.00
1 bh Kotak Sambung / T- Dus 3,500.00 3,500.00
15 bh Klem Pipa 5/8" 330.00 4,950.00
1 bh Isolasi 2,500.00 2,500.00 404,050.00
1 ls Material Bantu 121,215.00 525,265.00

0.2 org Pekerja Trampil 65,000.00 13,000.00


0.1 org Tukang Listrik 80,000.00 8,000.00
0.1 org Kepala Tk Listrik 90,000.00 4,500.00
0.1 org Mandor 90,000.00 4,500.00 30,000.00
Jumlah 555,265.00
1 BH PENGADAAN DAN PEMASANGAN STOP KONTAK 1 PHASE
Bahan :
1 bh Stop Kontak 1 Phase 12,500.00 12,500.00
10 m' Kabel NYM 3 x 1,5 sqmm 6,440.00 64,400.00
10 m' Conduit dia. 15,8 mm (5/8") 3,100.00 31,000.00
1 bh Kotak Sambung / T- Dus 3,500.00 3,500.00
10 bh Klem Pipa 5/8" 330.00 3,300.00 114,700.00
1 ls Material Bantu 34,410.00 149,110.00
Tenaga Kerja :
0.2 org Pekerja Trampil 65,000.00 13,000.00
0.1 org Tukang Listrik 80,000.00 8,000.00
0.05 org Kepala Tk Listrik 90,000.00 4,500.00
0.05 org Mandor 90,000.00 4,500.00 30,000.00
Jumlah 179,110.00

1 BH PENGADAAN DAN PEMASANGAN SAKLAR TUNGGAL


Bahan :
1 bh Saklar Tunggal 11,500.00 11,500.00
10 m' Kabel NYM 2 x 1,5 sqmm 6,440.00 64,400.00
10 m' Conduit dia. 15,8 mm (5/8") 3,100.00 31,000.00
1 bh Kotak Sambung / T- Dus 3,500.00 3,500.00
10 bh Klem Pipa 5/8" 330.00 3,300.00 113,700.00
1 ls Material Bantu 34,110.00 147,810.00
Tenaga Kerja :
KOEFESIEN HARGA SATUAN JUMLAH HARGA JUMLAH TOTAL
KODE ANALISA URAIAN
INDEX ( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6

0.2 org Pekerja Trampil 65,000.00 13,000.00


0.1 org Tukang Listrik 80,000.00 8,000.00
0.05 org Kepala Tk Listrik 90,000.00 4,500.00
0.05 org Mandor 90,000.00 4,500.00 30,000.00
Jumlah 177,810.00
RINCIAN RENCANA ANGGARAN BIAYA (RAB)
REHAB RUANG KELAS
HARGA JUMLAH
NO ITEM PEKERJAAN SAT VOL
SATUAN HARGA
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan LS 1 3,313.20 3,313.20
2 Pengukuran dan Pemasangan Bouplank LS 1 1,133.20 1,133.20
3 Pembuatan DireksiKeet LS 1 212,968.70 212,968.70

SUB JUMLAH I 217,415.10

II PEKERJAAN GALIAN DAN PONDASI


1 Galian Tanah M3 14.0 55,608.00 780,736.32
2 Urugan Tanah M2 14.04 307,662.00 4,319,574.48
3 Pondasi Foot Plat
- Pembesian Kg 766 105,117.75 80,520,196.50
- Bekisting M2 93.6 153,636.20 14,380,348.32
- Beton AD. 1:2:3 M3 0.65 935,493.00 608,070.45
4 Pasangan Pondasi Batu Belah M2 605,271.00 0.00

SUB JUMLAH II 100,608,926.07

III PEKERJAAN BETON/PEMBESIAN


1 SLOOF 25/35
- Pembesian Kg 672 105,117.75 70,639,128.00
- Bekisting M2 71.4 103,053.88 7,358,046.68
- Beton AD. 1:2:3 M3 8.93 935,493.00 8,353,952.49
2 KOLOM (K1)
- Pengerjaan Besi WF Kg 105,117.75 0.00
- Bekisting M2 103,053.88 0.00
- Beton AD. 1:2:3 M3 935,493.00 0.00
3 KOLOM (K2)
- Pembesian Kg 1,047.5 105,117.75 110,110,843.13
- Bekisting M2 133 321,001.80 42,693,239.40
- Beton AD. 1:2:3 M3 10.00 935,493.00 9,354,930.00
4 BALOK IWF
- Pengerjaan Besi WF Kg 105,117.75 0.00
5 BALOK PENGUAT KUSEN
- Pembesian Kg 1,188.500 105,117.75 124,932,445.88
- Bekisting M2 111.60 329,065.80 36,723,743.28
- Beton AD. 1:2:3 M3 13.95 935,493.00 13,050,127.35
6 ATAP BETON K250
- Wiremesh dia 8mm - 150 M2 240.000 538,339.89 129,201,573.82
- Bondek 0.75 M2 240.00 188,944.10 45,346,584.00
- Beton K225 M3 28.80 1,792,720.00 51,630,336.00

SUB JUMLAH II 649,394,950.01

IV PEKERJAAN PASANGAN DINDING BATA


1 Pasangan Dinding Bata AD. 1:5 M2 288.60 162,101.25 46,782,420.75
2 Plesteran Dinding Bata AD. 1:5 + Acian M2 577.20 98,881.30 57,074,286.36

SUB JUMLAH III 103,856,707.11

V PEKERJAAN KUSEN PINTU DAN JENDELA


1 P1 (uk. 220x150) Kusen Alumunium Daun Rangka Kayu Lapis Triplek UNIT 2.00 4,739,840.00 9,479,680.00
2 J1 (uk. 220x140) Kusen daun Jendela Alumunium UNIT 14.00 3,249,800.58 45,497,208.06
3 Bofenlife Kusen Alumunium UNIT 32 222,600 7,123,200.00

SUB JUMLAH IV 62,100,088.06

VI PEKERJAAN MENGECAT
1 Pengecatan tembok ex Vinilex M2 236.80 19,550.26 4,629,501.57
HARGA JUMLAH
NO ITEM PEKERJAAN SAT VOL
SATUAN HARGA
1 2 3 4 5 6
SUB JUMLAH VI 4,629,501.57

VII PEKERJAAN LANTAI DAN PLAFON


HARGA JUMLAH
NO ITEM PEKERJAAN SAT VOL
SATUAN HARGA
1 2 3 4 5 6
1 Pemasangan Lantai Keramik 40x40 M2 240.00 148,201.70 35,568,408.00
2 Pasang Plafon rangka Hollo lapis Gypsum M2 240 51,541.67 12,370,000.00
3 Pasang List Gypsum M 80 19,497.00 1,559,760.00

SUB JUMLAH VII 49,498,168.00

VIII PEKERJAAN LISTRIK


1 Pemasangan titik saklar ex brocco BH 2.00 177,810.00 355,620.00
2 Pemasangan titik stop kontak ex brocco BH 14 179,110.00 2,507,540.00
3 Pemasangan lampu downlight (lengkap accessories) BH 11 198,840.00 2,187,240.00

SUB JUMLAH VIII 5,050,400.00

IX PEKERJAAN LAIN

1 Beton tumbuk untuk tritisan M3 1.03 933,800.50 961,814.52


2 Pasangan Bata Merah untuk Drainase M2 0.0 0.00 0.00
3 Pembersihan Lokasi Pekerjaan LS 1 3,313.20 3,313.20

SUB JUMLAH IX 965,127.72

JUMLAH TOTAL 976,321,283.64


TERBILANG : -----

Banjarbaru,
Ketua Tim Perencana & Pengawas Kepala
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)
REHAB RUANG KELAS
TAHUN 2019

NO SUB PEKERJAAN HARGA (RP)

I PEKERJAAN PERSIAPAN 217,415.10


II PEKERJAAN GALIAN DAN PONDASI 100,608,926.07
III PEKERJAAN BETON/PEMBESIAN 649,394,950.01
IV PEKERJAAN PASANGAN DINDING BATA 103,856,707.11
V PEKERJAAN KUSEN PINTU DAN JENDELA 62,100,088.06
VI PEKERJAAN MENGECAT 4,629,501.57
VII PEKERJAAN LANTAI DAN PLAFON 49,498,168.00
VIII PEKERJAAN LISTRIK 5,050,400.00
IX PEKERJAAN LAIN 965,127.72
JUMLAH TOTAL BIAYA KONTRUKSI 976,321,283.64

TERBILANG : -----

Banjarbaru,
Ketua Tim Perencana & Pengawas Kepala