FORMULIR STANDAR UNTUK

PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PAKET PEKERJAAN
RUAS JALAN
PROV. / KAB. /KODYA

ITEM PEMBAYARAN NO. : 1.19


JENIS PEKERJAAN : KESELAMATAN DAN KESEHATAN KERJA
SATUAN PEMBAYARAN : LS

PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

A. Penyiapan RK3K

1. Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja Dan Formulir Set 10.000
2. Pembuatan Kartu Identitas Kerja (KIP) Lb 100.000

JUMLAH HARGA T

B. Sosialisasi dan Promosi K3

1. Induksi K3 (Safety Induction) Org 100.000


2. Pengarahan K3 (safety briefing) : Pertemuan Keselamatan Org 100.000
(Safety Talk dan/atau Tool Box Meeti ng)
3. Pelatihan K3 Org 2.000
4. Simulasi K3 Org 100.000
5. Spanduk (banner Lb 5.000
6. Poster Lb 5.000
7. Papan Informasi K3 Bh 2.000

JUMLAH HARGA

C. Alat Pelindung Kerja terdiri

1. Jaring Pengaman (Safety Net) Ls 1.0000


2. Tali Keselamatan (Life Line) Ls 50.0000
3. Penahan Jatuh (Safety Deck) Ls 1.0000
4. Pagar Pengaman (Guard Railling) Ls 1.0000
5. Pembatas Area (Restri cted Area ) Ls 1.0000

UMLAH HARGA PERA

D. Alat Pelindung Diri Terdiri Atas

1. Topi Pelindung (Safety Helmet) Bh 200.000


2. Pelindung Mata (Goggles, Spectacles) Psg 10.000
3. Tameng Muka (Face Shield) Bh
4. Masker Selam (Breathing Apparatus) Bh
5. Pelindung Telinga (Ear Plug, Ear Muff) Psg
6. Pelindung Pernafasan Dan Mulut (Masker) Bh 200.000
7. Sarung Tangan (Safety Gloves) Psg 20.000
8. Sepatu Keselamatan (Safety Shoes) Psg 100.000
9. Penunjang Seluruh Tubuh (Full Body Harness) Bh
10. Jaket Pelampung (Life Vest) Bh
11. Rompi Keselamatan (Safety Vest) Bh 100.000
12. Celemek (Apron/ Coveralls) Bh
13. Pelindung Jatuh (Fall Arrester) Bh 10.000

UMLAH HARGA PERA

E. Asuransi Dan Perijinan


1. BPJS Ketenagakerjaan Dan Kesehatan Kerja Ls 100.000
2. Surat Ijin Kelaikan Alat Alat/Kend 3.000
3. Surat Ijin Operator Lb/Alat 3.000
Surat Ijin Pengesahan Panitia Pembina Keselamatan
4. Ls 1.000
(P2K3)
Dan Kesehatan Kerja

UMLAH HARGA PERA


PERKIRAAN
NO. KOMPONEN SATUAN KUANTITAS

F. Personil K3

1. Ahli K3 OB 12.000
Petugas K3 OB 12.000
2. Petugas Tanggap Darurat OB 12.000
3. Petugas P3K OB 12.000
4. Petugas Pengatur Lalu Lintas (Flagman) OB 24.000
5. Petugas Medis OB 12.000

JUMLAH HARGA T

G. Fasilitas sarana kesehatan

1. Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Ls 1.0000


Obat Luka, Perban, dll)
2. Ruang P3K (Tempat Tidur Pasien, Stetoskop, Timbangan Berat Ls 1.0000
Badan, Tensi Meter, dll);
3. Peralatan Pengasapan (Fogging) Lb 1.0000
4. Obat Pengasapan Lb 1.0000

JUMLAH HARGA

H. Rambu - Rambu

1. Rambu Petunjuk Bh 80.0000


2. Rambu Larangan Bh 50.0000
3. Rambu Peringatan Bh 50.0000
4. Rambu Kewajiban Bh 50.0000
5. Rambu Informasi Bh 5.0000
6. Rambu Pekerjaan Sementara Bh 20.0000
7. Tongkat Pengatur Lalu Lintas (Warning Lights Stick) Bh 10.0000
8. Kerucut Lalu Lintas (Traffic Cone) Bh 20.0000
9. Lampu Putar (Rotary Lamp) Bh 2.0000
10. Lampu Selang Lalu Lintas Ls 1.0000

UMLAH HARGA PERA

I. Lain- Lain Terkait Pengendalian Risiko K3

1. Alat Pemadam Api Ringan (APAR) Bh 4.0000


2. Sirine Bh 2.0000
3. Bendera K3 Bh 2.0000
4. Jalur Evakuasi (Escape Route) Ls
5. Lampu Darurat (Emergency Lamp) Bh 4.0000
6. Program Inspeksi Dan Audit Internal Ls 1.0000
7. Pelaporan dan Penyelidikan Insiden Ls 1.0000
UMLAH HARGA PERA

J. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C + D + E + F + G + H + I )


K. OVERHEAD & PROFIT % x D
L. HARGA SATUAN PEKERJAAN ( D + E )

contoh : masa pelaksanaan pekerjaan 12 Bln


Analisa 1.19

TUAN

PERKIRAAN VOL. PEK. : 0.00


TOTAL HARGA (Rp.) : 353,200,000.00
% THD. BIAYA PROYEK : #DIV/0!

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

500,000.00 5,000,000.00
5,000.00 500,000.00

LAH HARGA TENAGA 5,500,000.00

50,000.00 5,000,000.00
10,000.00 1,000,000.00

1,500,000.00 3,000,000.00
25,000.00 2,500,000.00
250,000.00 1,250,000.00
150,000.00 750,000.00
250,000.00 500,000.00

MLAH HARGA BAHAN 14,000,000.00

500,000.00 500,000.00
80,000.00 4,000,000.00
1,000,000.00 1,000,000.00
2,500,000.00 2,500,000.00
1,500,000.00 1,500,000.00

HARGA PERALATAN 9,500,000.00

50,000.00 10,000,000
150,000.00 1,500,000
2,500.00 500,000
40,000.00 800,000
250,000.00 25,000,000
-
-
70,000.00 7,000,000
-
250,000.00 2,500,000

HARGA PERALATAN 47,300,000.00

250,000.00 25,000,000.00
1,000,000.00 3,000,000.00
2,500,000.00 7,500,000.00
1,000,000.00 1,000,000.00

HARGA PERALATAN 36,500,000.00


Berlanjut ke halaman berikut
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

3,500,000.00 42,000,000.00
2,500,000.00 30,000,000.00
1,750,000.00 21,000,000.00
2,000,000.00 24,000,000.00
1,750,000.00 42,000,000.00
2,750,000.00 33,000,000.00

LAH HARGA TENAGA 192,000,000.00

3,000,000.00 3,000,000.00

5,000,000.00 5,000,000.00

2,500,000.00 2,500,000.00
3,000,000 3,000,000.00

MLAH HARGA BAHAN 13,500,000.00

80,000.00 6,400,000.00
80,000.00 4,000,000.00
80,000.00 4,000,000.00
80,000.00 4,000,000.00
80,000.00 400,000.00
80,000.00 1,600,000.00
150,000.00 1,500,000.00
100,000.00 2,000,000.00
100,000.00 200,000.00
100,000.00 100,000.00

HARGA PERALATAN 24,200,000.00

600,000.00 2,400,000.00
100,000.00 200,000.00
100,000.00 200,000.00

100,000.00 400,000.00
2,500,000.00 2,500,000.00
5,000,000.00 5,000,000.00
HARGA PERALATAN 10,700,000.00

353,200,000.00
-
353,200,000.00

353,200,000.00
Analisa 1.19

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PAKET PEKERJAAN
RUAS JALAN
PROV. / KAB. /KODYA

ITEM PEMBAYARAN NO. : 1.19 PERKIRAAN VOL. PEK. : 0.00


JENIS PEKERJAAN : KESELAMATAN DAN KESEHATAN KERJA TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : LS % THD. BIAYA PROYEK : #DIV/0!

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

1 Sosialisasi dan Promosi K3

a Pengarahan K3 (safety briefing) : Pertemuan Keselamatan Org 50.00 10,000.00 500,000.00


(Safety Talk dan/atau Tool Box Meeti ng)
b Simulasi K3 Org 50.00 25,000.00 1,250,000.00
c Spanduk (banner Lb 3.00 250,000.00 750,000.00
d Poster Lb 3.00 350,000.00 1,050,000.00
e Papan Informasi K3 Bh 2.00 250,000.00 500,000.00

Sub Total 1 4,050,000.00

2 Alat Pelindung Diri Terdiri Atas

a Topi Pelindung (Safety Helmet) Bh 50.00 50,000.00 2,500,000.00


b Pelindung Pernafasan Dan Mulut (Masker) Bh 50.00 2,500.00 125,000.00
c Sarung Tangan (Safety Gloves) Psg 50.00 40,000.00 2,000,000.00
d Rompi Keselamatan (Safety Vest) Bh 50.00 70,000.00 3,500,000.00
e Sepatu Karet Keselamatan Psg 50.00 100,000.00 5,000,000.00
f Pelindung Jatuh (Fall Arrester) Bh 5.00 120,000.00 600,000.00
g Tali Keselamatan M1 100.00 250,000.00 25,000,000.00

Sub Total 2 38,725,000.00

3 Fasilitas Sarana Kesehatan

a Peralatan P3K (Kotak K3, Tandu, Obat Luka, Obat Umum, Perban Ls 1.00 2,500,000.00 2,500,000.00
b Alat Pemadam Kebakaran Bh 2.00 1,500,000.00 3,000,000.00

Sub Total 3 5,500,000.00


TOTAL 48,275,000.00