DIVISI 1. UMUM
1,2 Mobilisasi 495.690.250 1,00 1,00 495.690.250,00 495.690.250,00 -
Skh-1.1.22 Sistem Manajemen Keselamatan Konstruksi (SMKK) 359.018.550 1,00 1,00 359.018.550,00 359.018.550,00 -
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air 65.919 146,90 146,90 9.683.472,63 9.683.472,63 -
2.2.(1) Pasangan Batu dengan Mortar 801.682 61,90 61,90 49.624.092,57 49.624.092,57 -
DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 MPa M3 1.997.231,94 561,16 561,16 1.120.766.674,46 1.120.766.674,46 -
7.1 (8) Beton , fc’15 Mpa M3 1.538.954,83 2.515,40 2.995,40 3.871.086.976,59 4.609.785.294,46 738.698.317,87
7.1 (10) Beton, fc’10 Mpa M3 1.420.246,05 45,49 45,49 64.606.992,88 64.606.992,88 -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 16.376,38 23.085,59 23085,59 378.058.375,33 378.058.375,33 -
7.3 (4) Baja Tulangan Sirip BjTS 420B Kg 25.653,83 43.510,72 43510,72 1.116.216.812,27 1.116.216.812,27 -
7.9.(1) Pasangan Batu M3 708.741,02 2.446,00 2446,00 1.733.580.541,13 1.733.580.541,13 -
7.15.(2) Pembongkaran Beton M3 666.476,18 561,16 561,16 373.999.775,08 373.999.775,08 -