Harga Jumlah
BOBOT
NO. URAIAN PEKERJAAN Satuan Kuantitas Satuan Harga-Harga
(Rp.) (Rp.) (%)
DIV-1 UMUM
1.2 Mobilisasi LS 1.00 317,050,000.00 317,050,000.00 2.429
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1.00 31,850,000.00 31,850,000.00 0.244
1.8.(2) Jembatan Sementara LS 1.00 209,083,020.00 209,083,020.00 1.602
1.20.1 Pengeboran Termasuk SPT dan Laporan M' 90.00 412,500.00 37,125,000.00 0.284
1,21 Manajemen Mutu LS 1.00 155,000,000.00 155,000,000.00 1.187
DIV-2 DRAINASE
2.1.(1) Galian Struktur dengan kedalaman 0 - 2 meter M3 40.00
2.2.(1) Pasangan Batu dengan Mortar M3 700.00 1,508,075.45 60,323,018.00 0.462
DIV-7 STRUKTUR
7.1 (5) a Beton Mutu Sedang fc’ = 30 MPa (lantai jembatan) M3 144.00 2,520,699.60 362,980,742.40 2.781
7.1 (6) Beton Mutu Sedang fc’ = 20 MPa M3 381.32 2,476,679.29 944,407,346.86 7.234
7.1 (7) a Beton Mutu rendah fc’ = 10 MPa M3 26.80 2,440,496.90 65,405,316.92 0.501
7.1 (8) Penyediaan Unit Pracetak Gelagar Tipoe 1 Bentang 20 meter Buah 11.00 2,127,629.78 23,403,927.58 0.179
7.1 (10) Pemasangan Unit Pracetak Gelagar Tipoe 1 Bentang 20 meter Buah 11.00 1,785,373.05 19,639,103.55 0.150
7.3 (4) Baja Tulangan BJ 24 Polos Kg 261.88 18,288.43 4,789,374.05 0.037
7.4 (1) a Baja Tulangan BJ 32 Ulir Kg 76,719.58 18,770.15 1,440,038,024.54 11.031
7.4 (2) a Penyediaan Baja Struktur BJ 34 (titik Leleh 210 Mpa) Kg 68,188.00 898.66 61,277,828.08 0.469
7.5 (2) Pemasangan Baja Struktur BJ 34 (titik Leleh 210 Mpa) Kg 68,188.00 2,045.57 139,483,327.16 1.068
7.6 (1) Pengangkutan Bahan Jembatan Kg 68,188.00 18,982.73 1,294,394,393.24 9.915
7.6 (10) b Penyediaan Tiang Pancang Beton Pratekan Pracetak dia 500 mm M' 4,032.00 1,115,855.53 4,499,129,496.96 34.465
7.6 (16) a Pemancangan Tiang Pancang Beton Pratekan Pracetak dia 500 mm M' 4,032.00 58,123.39 234,353,508.48 1.795
7.9.(1) Pasangan Batu M3 131.00 1,695,465.62 222,105,996.22 1.701
7.11.(6) Expansion Joint Tipe Baja Bersudut M' 140.00 400,000.00 56,000,000.00 0.429
7.12.(2) Perletakan Elastomer Alam Ukuran 300 mm x300 mm x 36 mm Buah 42.00 1,200,000.00 50,400,000.00 0.386
7.13.(1) Sandaran (Railing) M' 89.00 39,646.25 3,528,516.25 0.027
7.14.(1) Papan Nama Jembatan Buah 4.00 336,518.75 1,346,075.00 0.010
7.15.(8) Pembongkaran Lantai jembatan Kayu M2 640.00 359,167.98 229,867,507.20 1.761
7.16.(4) Pembongkaran Jembatan Kayu M2 640.00 230,000.00 147,200,000.00 1.128
7.16.(4) Pipa drainase PVC Diameter 7,5 cm M' 60.00
Jumlah
BOBOT
NO. URAIAN PEKERJAAN Harga-Harga
(Rp.) (%)
PROSENTASE
BOBOT BULAN KE-1 BULAN KE-2
NO. URAIAN PEKERJAAN SATUAN KUANTITAS FISIK MINGGU KE -1 MINGGU KE -2 MINGGU KE -3 MINGGU KE -4 MINGGU KE -5 MINGGU KE -6 MINGGU KE -7
PEKERJAAN 12-Oct 19-Oct 26-Oct 2-Nov 9-Nov 16-Nov 23-Nov
(%) s/d s/d s/d s/d s/d s/d s/d
18-Oct 25-Oct 1-Nov 8-Nov 15-Nov 22-Nov 25-Nov
I PEKERJAAN PERSIAPAN 2.591 100
1 Pekerjaan Pembersihan Lokasi m2 173.60 0.871 0.871
2 Pekerjaan Banner Plang Nama Kegiatan Lsm 1.00 0.214 0.214
3 Kesehatan dan Keselamatan Kerja (K3) Lsm 1.00 0.305 0.305
4 Pekerjaan Pengukuran dan Pemasangan Bouwplank m 21.00 1.201 1.201
KONTRAK AWAL BOBOT RENCANA 100.000 3.491 19.100 19.099 18.184 15.690 15.690 8.747
KOMULATIF BOBOT RENCANA - 3.491 22.591 41.689 59.873 75.563 91.253 100.000
BOBOT REALISASI 2.347 15.892 22.508 36.923
REALISASI KOMULATIF BOBOT REALISASI 0 2.347 18.238 40.747 77.669
DEVIASI (+ / -) -1.144 -4.352 -0.943 17.796
KETERANGAN :
: Kurva Realisasi
: Kurva Rencana Kontrak Awal
Pejabat Pelaksana Teknis Kegiatan Pembantu Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas
CV. HAFIZH PRATAMA SEMESTA
1 Pekerjaan Galian Tanah 49.91 M3 2.699 0.000 0.000 49.910 0.000 49.910 0.000 100.000 2.699 2.699 0.000
2 Pekerjaan Pasir Urug T = 5 cm 8.27 M3 1.248 0.000 0.000 8.270 0.000 8.270 0.000 100.000 1.248 1.248 0.000
3 Pekerjaan Lantai Kerja T = 5 cm 8.27 M3 6.267 0.000 0.000 8.270 0.000 8.270 0.000 100.000 6.267 6.267 0.000
4 Pekerjaan Saluran Beton
- Pekerjaan Bekisting 277.75 M2 26.793 0.000 0.000 277.750 55.644 277.750 55.644 100.000 26.793 14.460 12.333
- Tulangan besi dia.8-200 mm 1477.03 Kg 12.704 0.000 0.000 996.220 34.238 996.220 34.238 67.448 8.568 6.870 1.698
- Pekerjaan Cor Beton bertulang 49.07 M3 46.298 0.000 0.000 30.530 37.110 30.530 37.110 62.217 28.806 24.990 3.816
5 Pipa pembuangan PVC 1'' P= 25 cm jarak 1 m 83.00 M' 1.401 0.000 0.000 45.000 30.120 45.000 30.120 54.217 0.760 0.750 0.010
Pejabat Pelaksana Teknis Kegiatan Pembantu Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas
CV. HAFIZH PRATAMA SEMESTA
Marselinus Kristoporus Beby, ST ........................................ .....................................
NIP. 197911152011011003 NIP. .......................................... Team Leader
LAPORAN MINGGUAN
PROGRAM KEGIATAN : PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN KONTRAKTOR / PELAKSANA : CV. SELNI BARU JAYA
KEGIATAN : PENGEMBANGAN DAN PENGELOLAAN SISTEM DRAINASE KAWASAN PERDESAAN DAN PERMUKIMAN PERKOTAAN KONSULTAN PENGAWAS/SUPERVISI : CV. HAFIZH PRATAMA SEMESTA
PAKET PEKERJAAN : PEMBANGUNAN DRAINASE KELURAHAN PASIRAN KOTA SINGKAWANG MINGGU KE : ke - 1
LOKASI PEKERJAAN : KOTA SINGKAWANG MULAI TANGGAL : 12 Oktober 2020
NO. KONTRAK : 14/18.01-06/FS.SKW/SPK-PL/AMPL/APBD/2020 SAMPAI DENGAN TANGGAL : 18 oktober 2020
NILAI PEKERJAAN : Rp. 179.070.000,00
TANGGAL KONTRAK : 09 Oktober 2020
WAKTU PELAKSANAAN : 45 ( Empat Puluh Lima) Hari Kalender
TAHUN ANGGARAN : 2020
1 Pekerjaan Galian Tanah 49.91 M3 2.699 - - 49.910 100.000 49.910 100.000 100.000 2.699 1.800 98.20
2 Pekerjaan Pasir Urug T = 5 cm 8.27 M3 1.248 - - 8.270 100.000 8.270 100.000 100.000 1.248 0.420 99.58
3 Pekerjaan Lantai Kerja T = 5 cm 8.27 M3 6.267 - - - - - - - - 2.090 -2.09
4 Pekerjaan Saluran Beton
- Pekerjaan Bekisting 277.75 M2 26.793 - - 123.200 44.356 123.200 44.356 44.356 11.885 4.820 39.54
- Tulangan besi dia.8-200 mm 1477.03 Kg 12.704 - - - - - - - - 2.290 -2.29
- Pekerjaan Cor Beton bertulang 49.07 M3 46.298 - - - - - - - - 8.330 -8.33
5 Pipa pembuangan PVC 1'' P= 25 cm jarak 1 m 83.00 M' 1.401 - - - - - - - - 0.250 -0.25
1 Pekerjaan Galian Tanah 49.91 M3 2.699 49.910 100.000 - - 49.910 100.000 100.000 2.699 2.699 97.30
2 Pekerjaan Pasir Urug T = 5 cm 8.27 M3 1.248 8.270 100.000 - - 8.270 100.000 100.000 1.248 0.840 99.16
3 Pekerjaan Lantai Kerja T = 5 cm 8.27 M3 6.267 - - 8.270 100.000 8.270 100.000 100.000 6.267 4.180 95.82
4 Pekerjaan Saluran Beton
- Pekerjaan Bekisting 277.75 M2 26.793 123.200 44.356 - - 123.200 44.356 44.356 11.885 9.640 34.72
- Tulangan besi dia.8-200 mm 1477.03 Kg 12.704 - - 490.520 33.210 490.520 33.210 33.210 4.219 4.580 28.63
- Pekerjaan Cor Beton bertulang 49.07 M3 46.298 - - 12.320 25.107 12.320 25.107 25.107 11.624 16.660 8.45
5 Pipa pembuangan PVC 1'' P= 25 cm jarak 1 m 83.00 M' 1.401 - - 20.000 24.096 20.000 24.096 24.096 0.338 0.500 23.60
1 Pekerjaan Galian Tanah 49.91 M3 2.699 49.910 100.000 - - 49.910 100.000 100.000 2.699 2.699 97.30
2 Pekerjaan Pasir Urug T = 5 cm 8.27 M3 1.248 8.270 100.000 - - 8.270 100.000 100.000 1.248 1.248 98.75
3 Pekerjaan Lantai Kerja T = 5 cm 8.27 M3 6.267 8.270 100.000 - - 8.270 100.000 100.000 6.267 6.267 93.73
4 Pekerjaan Saluran Beton
- Pekerjaan Bekisting 277.75 M2 26.793 123.200 44.356 154.550 55.644 277.750 100.000 100.000 26.793 14.460 85.54
- Tulangan besi dia.8-200 mm 1477.03 Kg 12.704 490.520 33.210 505.700 34.238 996.220 67.448 67.448 8.568 6.870 60.58
- Pekerjaan Cor Beton bertulang 49.07 M3 46.298 12.320 25.107 18.210 37.110 30.530 62.217 62.217 28.806 24.990 37.23
5 Pipa pembuangan PVC 1'' P= 25 cm jarak 1 m 83.00 M' 1.401 20.000 24.096 25.000 30.120 45.000 54.217 54.217 0.760 0.750 53.47
PROSENTASE
BOBOT BULAN KE-1 BULAN KE-2
NO. URAIAN PEKERJAAN SATUAN KUANTITAS FISIK MINGGU KE -1 MINGGU KE -2 MINGGU KE -3 MINGGU KE -4 MINGGU KE -5 MINGGU KE -6 MINGGU KE -7
PEKERJAAN 12-Oct 19-Oct 26-Oct 2-Nov 9-Nov 16-Nov 23-Nov
(%) s/d s/d s/d s/d s/d s/d s/d
18-Oct 25-Oct 1-Nov 8-Nov 15-Nov 22-Nov 25-Nov
I PEKERJAAN PERSIAPAN 2.591 100
1 Pekerjaan Pembersihan Lokasi m2 173.60 0.871 0.871
2 Pekerjaan Banner Plang Nama Kegiatan Lsm 1.00 0.214 0.214
3 Kesehatan dan Keselamatan Kerja (K3) Lsm 1.00 0.305 0.305
4 Pekerjaan Pengukuran dan Pemasangan Bouwplank m 21.00 1.201 1.201
KONTRAK AWAL BOBOT RENCANA 100.000 3.491 19.100 19.099 18.184 15.690 15.690 8.747
KOMULATIF BOBOT RENCANA - 3.491 22.591 41.689 59.873 75.563 91.253 100.000
BOBOT REALISASI 2.347 15.892 22.508 36.923 22.331
REALISASI KOMULATIF BOBOT REALISASI 0 2.347 18.238 40.747 77.669 100.000
DEVIASI (+ / -) -1.144 -4.352 -0.943 17.796 24.437
KETERANGAN :
: Kurva Realisasi
: Kurva Rencana Kontrak Awal
Pejabat Pelaksana Teknis Kegiatan Pembantu Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas
CV. HAFIZH PRATAMA SEMESTA
1 Pekerjaan Galian Tanah 49.91 M3 2.699 49.910 0.000 49.910 0.000 49.910 100.000 100.000 2.699 2.699 0.000
2 Pekerjaan Pasir Urug T = 5 cm 8.27 M3 1.248 8.270 0.000 8.270 0.000 8.270 100.000 100.000 1.248 1.248 0.000
3 Pekerjaan Lantai Kerja T = 5 cm 8.27 M3 6.267 8.270 0.000 8.270 0.000 8.270 100.000 100.000 6.267 6.267 0.000
4 Pekerjaan Saluran Beton
- Pekerjaan Bekisting 277.75 M2 26.793 277.750 55.644 277.750 55.644 277.750 100.000 100.000 26.793 19.280 7.513
- Tulangan besi dia.8-200 mm 1477.03 Kg 12.704 996.220 34.238 996.220 34.238 1,477.030 100.000 100.000 12.704 9.160 3.544
- Pekerjaan Cor Beton bertulang 49.07 M3 46.298 30.530 37.110 30.530 37.110 49.070 100.000 100.000 46.298 33.320 12.978
5 Pipa pembuangan PVC 1'' P= 25 cm jarak 1 m 83.00 M' 1.401 45.000 30.120 45.000 30.120 83.000 100.000 100.000 1.401 1.000 0.401
Pejabat Pelaksana Teknis Kegiatan Pembantu Pejabat Pelaksana Teknis Kegiatan Konsultan Pengawas
CV. HAFIZH PRATAMA SEMESTA
Marselinus Kristoporus Beby, ST ........................................ .....................................
NIP. 197911152011011003 NIP. .......................................... Team Leader
LAPORAN MINGGUAN
PROGRAM KEGIATAN : PENGEMBANGAN SISTEM PENYEHATAN LINGKUNGAN KONTRAKTOR / PELAKSANA : CV. SELNI BARU JAYA
KEGIATAN : PENGEMBANGAN DAN PENGELOLAAN SISTEM DRAINASE KAWASAN PERDESAAN DAN PERMUKIMAN PERKOTAAN KONSULTAN PENGAWAS/SUPERVISI : CV. HAFIZH PRATAMA SEMESTA
PAKET PEKERJAAN : PEMBANGUNAN DRAINASE KELURAHAN PASIRAN KOTA SINGKAWANG MINGGU KE : ke - 5
LOKASI PEKERJAAN : KOTA SINGKAWANG MULAI TANGGAL : 09 Nopember 2020
NO. KONTRAK : 14/18.01-06/FS.SKW/SPK-PL/AMPL/APBD/2020 SAMPAI DENGAN TANGGAL : 15 Nopember 2020
NILAI PEKERJAAN : Rp. 179.070.000,00
TANGGAL KONTRAK : 09 Oktober 2020
WAKTU PELAKSANAAN : 45 ( Empat Puluh Lima) Hari Kalender
TAHUN ANGGARAN : 2020
1 Pekerjaan Galian Tanah 49.91 M3 2.699 49.910 100.000 - - 49.910 100.000 100.000 2.699 2.699 97.30
2 Pekerjaan Pasir Urug T = 5 cm 8.27 M3 1.248 8.270 100.000 - - 8.270 100.000 100.000 1.248 1.248 98.75
3 Pekerjaan Lantai Kerja T = 5 cm 8.27 M3 6.267 8.270 100.000 - - 8.270 100.000 100.000 6.267 6.267 93.73
4 Pekerjaan Saluran Beton
- Pekerjaan Bekisting 277.75 M2 26.793 277.750 100.000 - - 277.750 100.000 100.000 26.793 14.460 85.54
- Tulangan besi dia.8-200 mm 1477.03 Kg 12.704 996.220 67.448 480.810 32.552 1,477.030 100.000 100.000 12.704 6.870 93.13
- Pekerjaan Cor Beton bertulang 49.07 M3 46.298 30.530 62.217 18.540 37.783 49.070 100.000 100.000 46.298 24.990 75.01
5 Pipa pembuangan PVC 1'' P= 25 cm jarak 1 m 83.00 M' 1.401 45.000 54.217 38.000 45.783 83.000 100.000 100.000 1.401 0.750 99.25