Anda di halaman 1dari 1

RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : PERENCANAAN OPTIMALISASI SPAM IKK SILIAN


LOKASI KEGIATAN : SILIAN RAYA
KABUPATEN : MINAHASA TENGGARA
SUMBER DANA : APBD
TAHUN ANGGARAN : 2022

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KODE VOLUME SAT.
(Rp) (Rp)
1 2 3 4 5 6 7
I. PEKERJAAN PERSIAPAN A.2.2.1.1.
1. Mobilisasi dan Demobilisasi Peralatan LA.04 1.00 Ls 20.000.000.00 20.000.000.00
2. Pengukuran dan Pemasangan Patok Trase Jaringan Pipa T.02.a 1.234.00 m' 7.680.72 9.478.011.22
3. Papan Proyek LA.03a 1.00 Bh 1.418.309.69 1.418.309.69
JUMLAH I 30.896.320.92
II. PEKERJAAN TANAH
1. Penimbun kembali /pemadatan 1 m3 bekas galian A.2.3.1.9. 1.363.53 M3 86.123.00 117.431.294.19
2. Urugan Pasir A.2.3.1.11. 129.86 M3 353.897.00 45.957.064.42
JUMLAH II 163.388.358.61
III. PEKERJAAN PASANGAN
A. BRONCAPTERING
1. Pas. Batu Belah (1:4) A.3.2.1.2. 4.25 M3 1.122.481.00 4.770.544.25
2. Plesteran (1:3) A.4.4.2.3. 6.80 M2 99.204.00 674.587.20
3. Pemasangan PIPA GIP SNI Ø 6" mm A.8.4.1.36 3.20 Bh 135.728.00 434.329.60
4. Pemasangan Get Valve GIP Ø 6" SNI A.8.4.3.4 1.00 Bh 4.766.449.00 4.766.449.00
5. Pemasangan Flange GIP Ø 6" SNI A.8.4.3.4 2.00 Bh 1.917.353.00 3.834.706.00
B. BOKS FILTER (uk. 3 x 2,5 m2)
1. Galian Tanah sedalam 1 m A.2.3.1.1. 16.77 M3 120.223.00 2.015.779.04
2. Pondasi Batu Belah 1:4 A.3.2.1.2. 2.80 M3 1.122.481.00 3.142.946.80
3. Beton K.175 A.4.1.1.5. 4.38 M3 1.307.117.00 5.721.251.11
4. Plesteran (1:3) A.4.4.2.3. 28.79 M2 99.204.00 2.855.835.15
5. Acian A.4.4.2.27. 28.79 M2 59.132.00 1.702.262.45
6. Pek. Pengecatan (1 Lapis Dasar 2 Lapis Penutup) A.4.7.1.10. 28.79 M2 30.312.00 872.606.70
7. Manhole - 1.00 Bh 750.000.00 750.000.00
8. Ventilasi Udara - 1.00 Bh 350.000.00 350.000.00
9. Instalasi Pipa - 1.00 Ls 3.500.000.00 3.500.000.00
JUMLAH III 35.391.297.30
IV. PEKERJAAN PIPA DAN AKSESORIS
A. PIPA INDUK/PRIMER 8.1
1. Pemasangan Pipa PVC SNI Ø 165 mm" (6") S12.5 A.8.4.3.1 6.493.00 M1 247.900.04 1.609.614.943.49
2. Pemasangan Pressure Reducing Valve SNI Ø 165 mm A.8.4.3.2 3.00 Bh 4.766.449.00 14.299.347.00
3. Pemasangan Flow Meter SNI Ø 165 mm A.8.4.3.3 1.00 Bh 4.766.449.00 4.766.449.00
4. Pemasangan Reducing Socket Ø 6"x 6" SNI A.8.4.3.4 1.00 Bh 1.351.064.00 1.351.064.00
JUMLAH IV 1.630.031.803.49
V. PEK. LAIN-LAIN
1. Pek. Pengadaan/Pasangan Prasasti 40 x 30 cm - 1.00 Ls 1.000.000.00 1.000.000.00
2. Pengujian Kualitas Air - 1.00 Ls 2.500.000.00 2.500.000.00
JUMLAH V 3.500.000.00
JUMLAH REAL COAST 1.863.207.780.31