RENCANA ANGGARAN BIAYA (RAB)

No. Mata Perkiraan Harga Satuan Jumlah Harga-Harga


Uraian Satuan
Pembayaran Kuantitas (Rupiah) (Rupiah)

a b c d e f = (d x e)

DIVISI 1. UMUM
1.2 Mobilisasi LS 1.00 23,930,000.00 23,930,000.00

Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 23,930,000.00

DIVISI 2. SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK)


2.3.(2) APD, antara lain :
Topi pelindung (Safety Helmet ) Bh 10.00 75,000.00 750,000.00
Pelindung mata (Googles, Spectacles ) Bh 10.00 40,000.00 400,000.00
Pelindung pernafasan dan mulut (masker, masker respirator) Bh 10.00 1,500.00 15,000.00
Sarung tangan (Safety Gloves) Psg 10.00 6,000.00 60,000.00
Sepatu keselamatan (Safety Shoes, rubber safety shoes and toe cap) Psg 10.00 150,000.00 1,500,000.00
Rompi keselamatan (Safety Vest) Bh 10.00 65,000.00 650,000.00
Peralatan P3K Set 1.00 1,500,000.00 1,500,000.00

Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 4,875,000.00

DIVISI 4. PEKERJAAN TANAH DAN GEOSINTETIK


4.1.(1) Galian Biasa M3 75.75 42,640.40 3,230,010.57
4.2.(1a) Timbunan Biasa dari sumber galian M3 330.00 52,436.39 17,304,010.20
4.2.(1b) Timbunan Pilihan dari sumber galian M3 40.00 220,089.78 8,803,591.19

Jumlah Harga Pekerjaan DIVISI 4 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 29,337,611.97

DIVISI 8. STRUKTUR
8.1 (7a) Beton struktur, fc20 MPa M3 59.72 2,113,570.14 126,222,409.01
8.1 (10) Beton, fc10 Mpa M3 4.50 1,871,857.15 8,423,357.16
8.3 (3) Baja Tulangan Sirip BjTS 420A Kg 6,127.30 20,889.75 127,997,765.18
8.1 (10) Penyediaan Baja Struktur Grade 355 (Kuat Leleh 355 MPa) Kg 28,757.17 21,057.47 605,553,243.35
8.4 (1b) Pemasangan Baja Struktur Kg 28,757.17 2,128.30 61,203,959.88
8.4 (2) Pasangan Batu M3 70.00 1,329,571.89 93,070,032.20
8.8.(1) Sambungan Siar Muai Tipe Strip seal M1 7.10 1,442,152.06 10,239,279.60
Landasan Elastomerik Karet Alam Berlapis Baja Ukuran 45 Mm x 450 Mm x
8.10.(3) Buah 4.00 1,307,358.33 5,229,433.33
400 Mm
8.10.(3) Pembuatan/Fabrikasi Struktur Jembatan Kg 28,757.17 18,757.47 539,411,752.35
8.11.(2) Baut Hex Baja M27 x 3 x 65 (grade 8.8 + 1 mur + 2 ring) set 16.00 85,000.00 1,360,000.00
Baut Hex Baja M27 x 3 x 80 (grade 8.8 + 1 mur + 2 ring) set 224.00 105,000.00 23,520,000.00
Baut Hex Baja M22 x 1,5 x 55 (grade 8.8 + 1 mur + 2 ring) set 18.00 77,000.00 1,386,000.00
Baut Hex Baja M22 x 1,5 x 70 (grade 8.8 + 1 mur + 2 ring) set 18.00 93,000.00 1,674,000.00
Baut Hex Baja M22 x 1,5 x 150 (grade 8.8 + 1 mur + 2 ring) set 18.00 135,000.00 2,430,000.00
Baut Hex Baja M20 x 1,5 x 55 (grade 8.8 + 1 mur + 2 ring) set 80.00 76,000.00 6,080,000.00
Baut L baja grade 8.8 dia. 3\/4 + 1 mur set 96.00 25,500.00 2,448,000.00
Angkur diameter 22 mm set 8.00 115,000.00 920,000.00

Jumlah Harga Pekerjaan DIVISI 8 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 1,617,169,232.06

DIVISI 9. REHABILITASI JEMBATAN


9.7.(1b) Pengecatan struktur baja pada daerah kering tebal 240 mikron M2 305.13 241,912.90 73,814,884.24

Jumlah Harga Pekerjaan DIVISI 9 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 73,814,884.24

DIVISI 10. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN


10.2.(5) Patok Pengarah M2 48.00 60,152.09 2,887,300.29

Jumlah Harga Pekerjaan DIVISI 10 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 2,887,300.29