PEMBANGUNAN JALAN TOL PEKANBARU - PADANG SEKSI SICINCIN - LUBUK ALUNG - PADANG

Nama Pekerjaan :
LANJUTAN
Nomor Kontrak :
Tanggal Kontrak :
Nilai Kontrak :
Subkontraktor : PT. PETRONESIA BENIMEL
Tagihan : TAGIHAN KE - 9
PENGGUNA JASA SUBKONTRAKTOR
REKAPITULASI HIT. GALIAN UNTUK DIBUANG MAX 5 KM (WASTE)
NO ITEM VOLUME S/D TAGIHAN LALU VOLUME TAGIHAN 9 VOLUME S/D TAGIHAN 9
PEMBAYARAN PEKERJAAN SAT KET KET KET
LOKASI STA VOLUME ( m3 ) LOKASI STA VOLUME ( m3 ) LOKASI STA VOLUME ( m3 )

M3 STA 7+200 - 7+575 606.85 GALIAN STRUKTUR STA 7+200 - 7+575 - GALIAN STRUKTUR STA 7+200 - 7+575 606.85 GALIAN STRUKTUR

M3 STA 9+450 - 9+850 5,505.16 MAINROAD STA 9+450 - 9+850 - MAINROAD STA 9+450 - 9+850 5,505.16 MAINROAD

M3 STA 9+850 - 10+800 1,839.05 MAINROAD STA 9+850 - 10+800 - MAINROAD STA 9+850 - 10+800 1,839.05 MAINROAD

M3 STA 10+800 - 11+500 16,446.34 MAINROAD STA 10+800 - 11+500 0.00 MAINROAD STA 10+800 - 11+500 16,446.34 MAINROAD

M3 STA 21+600 - 22+000 - MAINROAD STA 21+600 - 22+000 11,418.12 MAINROAD STA 21+600 - 22+000 11,418.12 MAINROAD

M3 STA 22+025 - 22+900 MAINROAD STA 22+025 - 22+900 MAINROAD STA 22+025 - 22+900 515,139.38 MAINROAD
25,716.70 80,191.38
M3 STA 22+450 - 23+100 MAINROAD STA 22+450 - 23+100 MAINROAD STA 22+450 - 23+100 283,774.63 MAINROAD

RA = 789,062.79
Total Galtim = 683,154.71

Total Galibuang RA = 105,908.08

M3 STA 23+100 - 23+450 10,123.02 MAINROAD STA 23+100 - 23+450 - MAINROAD STA 23+100 - 23+450 10,123.02 MAINROAD

M3 STA 23+625 - 24+400 78,624.52 MAINROAD STA 23+625 - 24+400 15,490.23 MAINROAD STA 23+625 - 24+400 94,114.75 MAINROAD

JUMLAH VOLUME 138,861.63 107,099.73 245,961.36

Diperiksa Oleh : Diajukan Oleh :


Subkontraktor
PT HUTAMA KARYA INFRASTRUKTUR PT PETRONESIA BENIMEL

RIZQI ALFIAN RAHMAT AFANDI


QUANTITY SURVEYOR QUANTITY SURVEYOR