Anda di halaman 1dari 3

ITEM PEMBAYARAN NO. : 1.

2
JENIS PEKERJAAN : MOBILISASI

Lembar 1.2-1
HARGA JUMLAH
No. URAIAN SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)

A. Sewa Tanah (Fasilitas Kontraktor) M2


Sewa Tanah (Disposal Galian) M2

B. PERALATAN
Periksa lembar 1.2-2 542.500.000

C. MOBILISASI FASILITAS KONTRAKTOR


1 Base Camp M2 400,00 500.000 200.000.000
2 Kantor : 0
3 - Ruang PPK M2 0
Ruang MK M2
Ruang Project Manager M2
Ruang Project Finace Manager M2
Ruang Project Engineering Manager & Project Production Manager
M2
Ruang Engineering M2
Ruang Rapat/Nego M2
Ruang Tamu M2
Ruang Sekretaris M2
Ruang Rapat Utama M2
Ruang Arsip M2
Barak M2
Bengkel M2
Gudang M2
Kantin M2
Ruang QHSE M2
Ruang Klinik M2
Pos Security M2
Mushola M2
Tempat Parkir Roda Empat M2
Tempat Parkir Roda Dua M2
Sewa Drone Phantom 4 Bulan
Kantor Direksi Teknis M2
Pos Polisi M2
D. MOBILISASI FASILITAS LABORATORIUM set
1 Ruang Laboratorium (Sesuai Gambar) M2 108 200.000 21.600.000

1 Soil & Agregate Testing


Compaction Test
CBR Test
Specific Gravity
Atterberg Limits
Grain Size Analysis
Field Density Test by Sand Cone Methode
Moisture Content
Abrasion of Aggregate by Los Angeles Machine

3 Bituminous Testing
Marshall Asphalt Test
Extraction Test, Centrifuge/Refflux Methode
Specific Gravity for Coarse Aggregate
Mix Air Void Content (Accurate Methode)
Core Drill
Metal Thermometer
Accessories and Tolls
Penetration Test
Softening Point
Refusal Density Compactor

4 Concrete Testing
Slump Cone
Cylinder/Cube Mould for Compressive Strength
Beam Mould for Flexural Strength (RIGID)
Crushing Machine

Pendukung

Operasional

E. MOBILISASI LAINNYA
E.I. PEKERJAAN DARURAT 1 0
1 Perkuatan Jembatan Lama
2 Pemeliharaan Jalan Kerja / Samping
3 …...........................
4 …...........................
5 …...........................

E.II. LAIN-LAIN
1 Komunikasi Lapangan Lengkap Ls 1,00 0
2 Papan Nama Kegiatan Ls 2,00 200.000 0
3 Dokumentasi dan Pelaporan Ls 1,00 0

G. DEMOBILISASI LS 1,00 162.750.000 162.750.000

Total Biaya Mobilisasi 905.250.000

Catatan : Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
ITEM PEMBAYARAN NO. : 1.2
JENIS PEKERJAAN : MOBILISASI
Lembar 1.2-2
KODE HARGA JUMLAH
No. JENIS ALAT ALAT SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)

B. PERALATAN

1 ASPHALT FINISHER E02 Unit 1,00 25.000.000 25.000.000


2 COMPRESSOR 4000-6500 L/M E05 Unit 1,00 5.000.000 5.000.000
3 CONCRETE MIXER 0.3 - 0.6 M3 E06 Unit 3,00 6.000.000 18.000.000
4 CRANE 10 - 15 TON E07 Unit 1,00 50.000.000 50.000.000
5 DUMP TRUCK 3.5 TON E08 Unit 5,00 2.000.000 10.000.000
6 DUMP TRUCK 10 TON E09 Unit 3,00 2.500.000 7.500.000
7 EXCAVATOR 80 - 140 HP E10 Unit 4,00 25.000.000 100.000.000
8 FLAT BED TRUCK 3 - 4 M3 E11 Unit 1,00 15.000.000 15.000.000
9 MOTOR GRADER > 100 HP E13 Unit 1,00 25.000.000 25.000.000
10 WHEEL LOADER 6 - 8 TON E15 Unit 1,00 20.000.000 20.000.000
11 TANDEM ROLLER 5 - 8 TON E17 Unit 1,00 25.000.000 25.000.000
12 TIRE ROLLER 8 - 10 T E18 Unit 1,00 15.000.000 15.000.000
13 VIBRATORY ROLLER 5 - 8 TON E19 Unit 1,00 25.000.000 25.000.000
14 CONCRETE VIBRATOR E20 Unit 5,00 800.000 4.000.000
15 WATER PUMP 70 - 100 mm E22 Unit 1,00 800.000 800.000
16 WATER TANKER 3000 - 4500 L E23 Unit 2,00 5.000.000 10.000.000
17 PEDESTRIAN ROLLER E24 Unit 1,00 5.000.000 5.000.000
18 TAMPER E25 Unit 2,00 800.000 1.600.000
19 JACK HAMMER E26 Unit 2,00 800.000 1.600.000
20 CONCRETE PUMP E28 Unit 2,00 25.000.000 50.000.000
21 TRAILER 20 TON E29 Unit 1,00 15.000.000 15.000.000
22 WELDING SET E32 Unit 2,00 3.500.000 7.000.000
23 ASPHALT DISTRIBUTOR E41 Unit 1,00 10.000.000 10.000.000
24 CONCRETE PAN MIXER / BATCHING PLANT E43 Unit 1,00 1.000.000 1.000.000
25 TRUCK MIXER (AGITATOR) E49 Unit 6,00 3.500.000 21.000.000
26 BORE PILE MACHINE E50 Unit 2,00 20.000.000 40.000.000
27 BAR BENDER E53 Unit 2,00 1.000.000 2.000.000
28 BAR CUTTER E54 Unit 2,00 1.000.000 2.000.000
29 FLAT BED TRUCK 10 TON E11a Unit 1,00 4.000.000 4.000.000
30 THERMOPLASTIC SPREADING MACHINE' E66 Unit 1,00 700.000 700.000
31 TRUCK 2 TON E67 Unit 1,00 3.000.000 3.000.000
32 CONCRETE CUTTER 130 feet/mnt E72 Unit 1,00 300.000 300.000
33 FOAM MACHINE E80 Unit 1,00 3.000.000 3.000.000
34 GENERATOR SET E12 Unit 1,00 20.000.000 20.000.000

Total untuk Item B pada Lembar 1 542.500.000