CADANGAN MEMBINA DAN MENYIAPKAN KERJA KLINIK KESIHATAN JENIS KK7 DI JALAN SUNGAI BERTEK, MUKIM KLANG, DAERAH

KLANG, SELANGOR DARUL EHSAN


ID Task Name Duration Start Finish Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
J J A S O N D J F M A M J J A S O N D J F M A M J J A
1 MEMBINA DAN MENYIAPKAN KK SUNGAI BERTEK 16 mons 1/7/22 10/11/23 MEMBINA DAN MENYIAPKAN KK SUNGAI BERTEK (JENSI
(JENSI KK7)
2 Serahan Tapak Kepada Kontraktor 0 days 1/7/22 1/7/22 1/7
3 KERJA AWALAN 15.81 mons 1/7/22 4/11/23 KERJA AWALAN
4 PEMATUHAN KONTRAK 1.73 mons 1/7/22 24/8/22 PEMATUHAN KONTRAK
5 Program Kerja (CPM) 14 days 1/7/22 18/7/22 Program Kerja (CPM)
6 Bon Perlaksanaan 14 days 1/7/22 18/7/22 Bon Perlaksanaan
7 Insuran 7 days 1/7/22 8/7/22 Insuran
8 SOCSO 7 days 1/7/22 8/7/22 SOCSO
9 Ukur Tanah & Penentuan 7 days 11/7/22 18/7/22 Ukur Tanah & Penentuan
10 Penghadang Sementara 7 days 19/7/22 26/7/22 Penghadang Sementara
11 Papan Tanda Projek 3 days 19/7/22 21/7/22 Papan Tanda Projek
12 Bekalan Air & Elektrik Sementara 3 days 27/7/22 29/7/22 Bekalan Air & Elektrik Sementara
13 Penempatan Kontraktor 7 days 1/8/22 8/8/22 Penempatan Kontraktor
14 Pejabat Kontraktor 7 days 9/8/22 16/8/22 Pejabat Kontraktor
15 Pejabat SO & Peralatan Pejabat 7 days 17/8/22 24/8/22 Pejabat SO & Peralatan Pejabat
16 KERJA BERULANG 15.81 mons 1/7/22 4/11/23 KERJA BERULANG
17 Ukur Tanah & Penentuan 14.69 mons 1/7/22 2/10/23 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
18 Ukur Tanah & Penentuan 1 1 day 1/7/22 1/7/22 Ukur Tanah & Penentuan 1
19 Ukur Tanah & Penentuan 2 1 day 1/8/22 1/8/22 Ukur Tanah & Penentuan 2
20 Ukur Tanah & Penentuan 3 1 day 1/9/22 1/9/22 Ukur Tanah & Penentuan 3
21 Ukur Tanah & Penentuan 4 1 day 1/10/22 1/10/22 Ukur Tanah & Penentuan 4
22 Ukur Tanah & Penentuan 5 1 day 1/11/22 1/11/22 Ukur Tanah & Penentuan 5
23 Ukur Tanah & Penentuan 6 1 day 1/12/22 1/12/22 Ukur Tanah & Penentuan 6
24 Ukur Tanah & Penentuan 7 1 day 3/1/23 3/1/23 Ukur Tanah & Penentuan 7
25 Ukur Tanah & Penentuan 8 1 day 1/2/23 1/2/23 Ukur Tanah & Penentuan 8
26 Ukur Tanah & Penentuan 9 1 day 1/3/23 1/3/23 Ukur Tanah & Penentuan 9
27 Ukur Tanah & Penentuan 10 1 day 1/4/23 1/4/23 Ukur Tanah & Penentuan 10
28 Ukur Tanah & Penentuan 11 1 day 1/5/23 1/5/23 Ukur Tanah & Penentuan 11
29 Ukur Tanah & Penentuan 12 1 day 1/6/23 1/6/23 Ukur Tanah & Penentuan 12
30 Ukur Tanah & Penentuan 13 1 day 1/7/23 1/7/23 Ukur Tanah & Penentuan 13
31 Ukur Tanah & Penentuan 14 1 day 1/8/23 1/8/23 Ukur Tanah & Penentuan 14
32 Ukur Tanah & Penentuan 15 1 day 1/9/23 1/9/23 Ukur Tanah & Penentuan 15
33 Ukur Tanah & Penentuan 16 1 day 2/10/23 2/10/23 Ukur Tanah & Penentuan 16
34 Lukisan Bengkel & Contoh 14.85 mons 1/7/22 6/10/23 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
35 Lukisan Bengkel & Contoh 1 5 days 1/7/22 6/7/22 Lukisan Bengkel & Contoh 1
36 Lukisan Bengkel & Contoh 2 5 days 1/8/22 5/8/22 Lukisan Bengkel & Contoh 2
37 Lukisan Bengkel & Contoh 3 5 days 1/9/22 6/9/22 Lukisan Bengkel & Contoh 3
38 Lukisan Bengkel & Contoh 4 5 days 1/10/22 6/10/22 Lukisan Bengkel & Contoh 4

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Kontraktor : K1 Sdn Bhd Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Tarikh : 16/6/22 Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Page 1 of 5
CADANGAN MEMBINA DAN MENYIAPKAN KERJA KLINIK KESIHATAN JENIS KK7 DI JALAN SUNGAI BERTEK, MUKIM KLANG, DAERAH KLANG, SELANGOR DARUL EHSAN
ID Task Name Duration Start Finish Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
J J A S O N D J F M A M J J A S O N D J F M A M J J A
39 Lukisan Bengkel & Contoh 5 5 days 1/11/22 5/11/22 Lukisan Bengkel & Contoh 5
40 Lukisan Bengkel & Contoh 6 5 days 1/12/22 6/12/22 Lukisan Bengkel & Contoh 6
41 Lukisan Bengkel & Contoh 7 5 days 3/1/23 7/1/23 Lukisan Bengkel & Contoh 7
42 Lukisan Bengkel & Contoh 8 5 days 1/2/23 6/2/23 Lukisan Bengkel & Contoh 8
43 Lukisan Bengkel & Contoh 9 5 days 1/3/23 6/3/23 Lukisan Bengkel & Contoh 9
44 Lukisan Bengkel & Contoh 10 5 days 1/4/23 6/4/23 Lukisan Bengkel & Contoh 10
45 Lukisan Bengkel & Contoh 11 5 days 1/5/23 5/5/23 Lukisan Bengkel & Contoh 11
46 Lukisan Bengkel & Contoh 12 5 days 1/6/23 6/6/23 Lukisan Bengkel & Contoh 12
47 Lukisan Bengkel & Contoh 13 5 days 1/7/23 6/7/23 Lukisan Bengkel & Contoh 13
48 Lukisan Bengkel & Contoh 14 5 days 1/8/23 5/8/23 Lukisan Bengkel & Contoh 14
49 Lukisan Bengkel & Contoh 15 5 days 1/9/23 6/9/23 Lukisan Bengkel & Contoh 15
50 Lukisan Bengkel & Contoh 16 5 days 2/10/23 6/10/23 Lukisan Bengkel & Contoh 16
51 Laporan Keselamatan 14.69 mons 1/7/22 2/10/23 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
52 Laporan Keselamatan 1 1 day 1/7/22 1/7/22 Laporan Keselamatan 1
53 Laporan Keselamatan 2 1 day 1/8/22 1/8/22 Laporan Keselamatan 2
54 Laporan Keselamatan 3 1 day 1/9/22 1/9/22 Laporan Keselamatan 3
55 Laporan Keselamatan 4 1 day 1/10/22 1/10/22 Laporan Keselamatan 4
56 Laporan Keselamatan 5 1 day 1/11/22 1/11/22 Laporan Keselamatan 5
57 Laporan Keselamatan 6 1 day 1/12/22 1/12/22 Laporan Keselamatan 6
58 Laporan Keselamatan 7 1 day 3/1/23 3/1/23 Laporan Keselamatan 7
59 Laporan Keselamatan 8 1 day 1/2/23 1/2/23 Laporan Keselamatan 8
60 Laporan Keselamatan 9 1 day 1/3/23 1/3/23 Laporan Keselamatan 9
61 Laporan Keselamatan 10 1 day 1/4/23 1/4/23 Laporan Keselamatan 10
62 Laporan Keselamatan 11 1 day 1/5/23 1/5/23 Laporan Keselamatan 11
63 Laporan Keselamatan 12 1 day 1/6/23 1/6/23 Laporan Keselamatan 12
64 Laporan Keselamatan 13 1 day 1/7/23 1/7/23 Laporan Keselamatan 13
65 Laporan Keselamatan 14 1 day 1/8/23 1/8/23 Laporan Keselamatan 14
66 Laporan Keselamatan 15 1 day 1/9/23 1/9/23 Laporan Keselamatan 15
67 Laporan Keselamatan 16 1 day 2/10/23 2/10/23 Laporan Keselamatan 16
68 Gambar Kemajuan 14.69 mons 1/7/22 2/10/23 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
69 Gambar Kemajuan 1 1 day 1/7/22 1/7/22 Gambar Kemajuan 1
70 Gambar Kemajuan 2 1 day 1/8/22 1/8/22 Gambar Kemajuan 2
71 Gambar Kemajuan 3 1 day 1/9/22 1/9/22 Gambar Kemajuan 3
72 Gambar Kemajuan 4 1 day 1/10/22 1/10/22 Gambar Kemajuan 4
73 Gambar Kemajuan 5 1 day 1/11/22 1/11/22 Gambar Kemajuan 5
74 Gambar Kemajuan 6 1 day 1/12/22 1/12/22 Gambar Kemajuan 6
75 Gambar Kemajuan 7 1 day 3/1/23 3/1/23 Gambar Kemajuan 7
76 Gambar Kemajuan 8 1 day 1/2/23 1/2/23 Gambar Kemajuan 8
77 Gambar Kemajuan 9 1 day 1/3/23 1/3/23 Gambar Kemajuan 9

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Kontraktor : K1 Sdn Bhd Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Tarikh : 16/6/22 Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Page 2 of 5
CADANGAN MEMBINA DAN MENYIAPKAN KERJA KLINIK KESIHATAN JENIS KK7 DI JALAN SUNGAI BERTEK, MUKIM KLANG, DAERAH KLANG, SELANGOR DARUL EHSAN
ID Task Name Duration Start Finish Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
J J A S O N D J F M A M J J A S O N D J F M A M J J A
78 Gambar Kemajuan 10 1 day 1/4/23 1/4/23 Gambar Kemajuan 10
79 Gambar Kemajuan 11 1 day 1/5/23 1/5/23 Gambar Kemajuan 11
80 Gambar Kemajuan 12 1 day 1/6/23 1/6/23 Gambar Kemajuan 12
81 Gambar Kemajuan 13 1 day 1/7/23 1/7/23 Gambar Kemajuan 13
82 Gambar Kemajuan 14 1 day 1/8/23 1/8/23 Gambar Kemajuan 14
83 Gambar Kemajuan 15 1 day 1/9/23 1/9/23 Gambar Kemajuan 15
84 Gambar Kemajuan 16 1 day 2/10/23 2/10/23 Gambar Kemajuan 16
85 Pembersihan Tapak 15.81 mons 1/7/22 4/11/23 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
86 Pembersihan Tapak 1 30 days 1/7/22 6/8/22 Pembersihan Tapak 1
87 Pembersihan Tapak 2 30 days 1/8/22 5/9/22 Pembersihan Tapak 2
88 Pembersihan Tapak 3 30 days 1/9/22 6/10/22 Pembersihan Tapak 3
89 Pembersihan Tapak 4 30 days 1/10/22 7/11/22 Pembersihan Tapak 4
90 Pembersihan Tapak 5 30 days 1/11/22 5/12/22 Pembersihan Tapak 5
91 Pembersihan Tapak 6 30 days 1/12/22 6/1/23 Pembersihan Tapak 6
92 Pembersihan Tapak 7 30 days 3/1/23 8/2/23 Pembersihan Tapak 7
93 Pembersihan Tapak 8 30 days 1/2/23 7/3/23 Pembersihan Tapak 8
94 Pembersihan Tapak 9 30 days 1/3/23 4/4/23 Pembersihan Tapak 9
95 Pembersihan Tapak 10 30 days 1/4/23 6/5/23 Pembersihan Tapak 10
96 Pembersihan Tapak 11 30 days 1/5/23 3/6/23 Pembersihan Tapak 11
97 Pembersihan Tapak 12 30 days 1/6/23 5/7/23 Pembersihan Tapak 12
98 Pembersihan Tapak 13 30 days 1/7/23 4/8/23 Pembersihan Tapak 13
99 Pembersihan Tapak 14 30 days 1/8/23 4/9/23 Pembersihan Tapak 14
100 Pembersihan Tapak 15 30 days 1/9/23 5/10/23 Pembersihan Tapak 15
101 Pembersihan Tapak 16 30 days 2/10/23 4/11/23 Pembersihan Tapak 16
102 KERJA BANGUNAN 12.62 mons 25/8/22 21/9/23 KERJA BANGUNAN
103 SUB-STRUKTUR 1.38 mons 25/8/22 7/10/22 SUB-STRUKTUR
104 ASAS PAPAK 0.85 mons 25/8/22 21/9/22 ASAS PAPAK
105 Kerja Korekan Asas 7 days 25/8/22 2/9/22 Kerja Korekan Asas
106 Ubat Anai-Anai 3 days 3/9/22 6/9/22 Ubat Anai-Anai
107 Konkrit G15 1 day 7/9/22 7/9/22 Konkrit G15
108 Kotak Bentuk 7 days 8/9/22 15/9/22 Kotak Bentuk
109 Tetulang 3 days 17/9/22 20/9/22 Tetulang
110 Konkrit G30 1 day 21/9/22 21/9/22 Konkrit G30
111 TIANG STUMP 0.54 mons 22/9/22 7/10/22 TIANG STUMP
112 Tetulang 3 days 22/9/22 24/9/22 Tetulang
113 Kotak Bentuk 9 days 26/9/22 5/10/22 Kotak Bentuk
114 Konkrit G30 2 days 6/10/22 7/10/22 Konkrit G30
115 SUPER-STRUKTUR 4.27 mons 10/10/22 21/2/23 SUPER-STRUKTUR
116 RASUK BUMI 1.35 mons 10/10/22 19/11/22 RASUK BUMI

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Kontraktor : K1 Sdn Bhd Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Tarikh : 16/6/22 Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Page 3 of 5
CADANGAN MEMBINA DAN MENYIAPKAN KERJA KLINIK KESIHATAN JENIS KK7 DI JALAN SUNGAI BERTEK, MUKIM KLANG, DAERAH KLANG, SELANGOR DARUL EHSAN
ID Task Name Duration Start Finish Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
J J A S O N D J F M A M J J A S O N D J F M A M J J A
117 Ubat Anai-Anai 3 days 10/10/22 12/10/22 Ubat Anai-Anai
118 Konkrit G15 1 day 13/10/22 13/10/22 Konkrit G15
119 Kotak Bentuk 14 days 14/10/22 31/10/22 Kotak Bentuk
120 Tetulang 14 days 1/11/22 16/11/22 Tetulang
121 Konkrit G25 3 days 17/11/22 19/11/22 Konkrit G25
122 TIANG 1.46 mons 21/11/22 5/1/23 TIANG
123 Tetulang 14 days 21/11/22 6/12/22 Tetulang
124 Kotak Bentuk 21 days 7/12/22 31/12/22 Kotak Bentuk
125 Konkrit G25 3 days 3/1/23 5/1/23 Konkrit G25
126 RASUK BUMBUNG 1.46 mons 6/1/23 21/2/23 RASUK BUMBUNG
127 Kotak Bentuk 21 days 6/1/23 1/2/23 Kotak Bentuk
128 Tetulang 14 days 2/2/23 17/2/23 Tetulang
129 Konkrit G25 3 days 18/2/23 21/2/23 Konkrit G25
130 ARKITEKTUR 6.96 mons 22/2/23 21/9/23 ARKITEKTUR
131 DINDING 1.15 mons 22/2/23 28/3/23 DINDING
132 Ikat Bata 30 days 22/2/23 28/3/23 Ikat Bata
133 Lintol 30 days 22/2/23 28/3/23 Lintol
134 Bingkai Pintu 30 days 22/2/23 28/3/23 Bingkai Pintu
135 Bingkai Tingkap 30 days 22/2/23 28/3/23 Bingkai Tingkap
136 KEMASAN DINDING 1.96 mons 4/5/23 1/7/23 KEMASAN DINDING
137 Lepaan Simen 30 days 4/5/23 7/6/23 Lepaan Simen
138 Cat 7 days 8/6/23 15/6/23 Cat
139 Pintu 14 days 16/6/23 1/7/23 Pintu
140 BUMBUNG 1.15 mons 29/3/23 3/5/23 BUMBUNG
141 Rangka Bumbung 15 days 29/3/23 15/4/23 Rangka Bumbung
142 Jubin Bumbung dan Aksesori 15 days 17/4/23 3/5/23 Jubin Bumbung dan Aksesori
143 KEMASAN SILING 1.54 mons 3/7/23 17/8/23 KEMASAN SILING
144 Kerangka Siling 20 days 3/7/23 25/7/23 Kerangka Siling
145 Siling Plaster 20 days 26/7/23 17/8/23 Siling Plaster
146 KEMASAN LANTAI 1.15 mons 18/8/23 21/9/23 KEMASAN LANTAI
147 Jubin 30 days 18/8/23 21/9/23 Jubin
148 KERJA M&E 2.23 mons 4/5/23 10/7/23 KERJA M&E
149 Pemasangan paip uPVC 30 days 4/5/23 7/6/23 Pemasangan paip uPVC
150 Pendawaian 14 days 8/6/23 23/6/23 Pendawaian
151 Kelengkapan Elektrikal 7 days 24/6/23 1/7/23 Kelengkapan Elektrikal
152 Kelengkapan Pendingin Hawa 7 days 3/7/23 10/7/23 Kelengkapan Pendingin Hawa
153 KERJA LUARAN 4.27 mons 4/5/23 9/9/23 KERJA LUARAN
154 Kaki Lima 3.46 mons 20/5/23 1/9/23 Kaki Lima
155 Korekan 3 days 20/5/23 23/5/23 Korekan

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Kontraktor : K1 Sdn Bhd Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Tarikh : 16/6/22 Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline

Page 4 of 5
CADANGAN MEMBINA DAN MENYIAPKAN KERJA KLINIK KESIHATAN JENIS KK7 DI JALAN SUNGAI BERTEK, MUKIM KLANG, DAERAH KLANG, SELANGOR DARUL EHSAN
ID Task Name Duration Start Finish Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024
J J A S O N D J F M A M J J A S O N D J F M A M J J A
156 Hardcore 3 days 24/5/23 26/5/23 Hardcore
157 Lantai Konkrit 3 days 27/5/23 30/5/23 Lantai Konkrit
158 Lepaan Simen 7 days 31/5/23 7/6/23 Lepaan Simen
159 Jubin 14 days 17/8/23 1/9/23 Jubin
160 Longkang Perimeter 0.92 mons 8/6/23 5/7/23 Longkang Perimeter
161 Korekan 7 days 8/6/23 15/6/23 Korekan
162 Konkrit G15 3 days 16/6/23 19/6/23 Konkrit G15
163 Longkang U 14 days 20/6/23 5/7/23 Longkang U
164 Papan Cantik & Saliran Air Hujan 0.58 mons 6/7/23 22/7/23 Papan Cantik & Saliran Air Hujan
165 Papan Cantik 5 days 6/7/23 11/7/23 Papan Cantik
166 Longkang Bumbung 5 days 12/7/23 17/7/23 Longkang Bumbung
167 Paip Air Hujan uPVC 5 days 18/7/23 22/7/23 Paip Air Hujan uPVC
168 Kemasan Siling 0.54 mons 24/7/23 8/8/23 Kemasan Siling
169 Kerangka Siling 7 days 24/7/23 31/7/23 Kerangka Siling
170 Siling Plaster 7 days 1/8/23 8/8/23 Siling Plaster
171 Kemasan Dinding 4.27 mons 4/5/23 9/9/23 Kemasan Dinding
172 Lepaan Simen 14 days 4/5/23 19/5/23 Lepaan Simen
173 Cat 7 days 9/8/23 16/8/23 Cat
174 Pintu 7 days 2/9/23 9/9/23 Pintu
175 PROVISIONAL SUM 6.15 mons 4/5/23 6/11/23 PROVISIONAL SUM
176 Kerja Lanskap 21 days 11/9/23 4/10/23 Kerja Lanskap
177 Kerja Jalan 7 days 5/10/23 12/10/23 Kerja Jalan
178 Kerja Pagar Perimeter 21 days 13/10/23 6/11/23 Kerja Pagar Perimeter
179 Kerja Mekanikal 14 days 4/5/23 19/5/23 Kerja Mekanikal
180 Kerja Elektrikal 14 days 4/5/23 19/5/23 Kerja Elektrikal
181 Perabot Dalaman 14 days 4/5/23 19/5/23 Perabot Dalaman
182 SERAHAN TAPAK 0.15 mons 7/11/23 10/11/23 SERAHAN TAPAK
183 Pemeriksaan Tapak Bersama 3 days 7/11/23 9/11/23 Pemeriksaan Tapak Bersama
184 Sesi Serah Tapak 1 day 10/11/23 10/11/23 Sesi Serah Tapak
185 Projek Tamat 0 mons 10/11/23 10/11/23 10/11

Critical Split Finish-only Baseline Milestone Manual Summary Inactive Task

Kontraktor : K1 Sdn Bhd Critical Split Task Progress Duration-only Milestone Project Summary Inactive Milestone
Tarikh : 16/6/22 Critical Progress Manual Task Baseline Summary Progress External Tasks Inactive Summary

Task Start-only Baseline Split Summary External Milestone Deadline