Penyedia Jasa :

JADWAL PELAKSANAAN PEKERJAAN


( TIME SCHEDULLE ) PT. MENARA ARMADA PRATAMA
GENERAL CONTRACTOR
PAKET PEKERJAAN : PENANGANAN LONG SEGMENT (Pemeliharaan Rutin, Pemeliharaan Jalan Arabika No. 27 Telp. (0385) 22233 - Fax. (0385) 22232
Berkala, Peningkatan/Rekonstruksi) WAE PESI - CADONG - NGANCAR E-mail : ptmapruteng@yahoo.co.id
NO/TGL. KONTRAK : PUPR.600.762/277/IV/2023 Tgl. 27 APRIL 2023 RUTENG - NTT
NILAI KONTRAK : Rp. 17.459.873.000,-
SUMBER DANA : DANA ALOKASI KHUSUS (DAK) TA. 2023

JANGKA WAKTU PELAKSANAAN 150 HARI KALENDER


No. Mata HARGA SATUAN JUMLAH HARGA BOBOT MEI 2023 JUNI 2023 JULI 2023 AGUSTUS 2023 SEPTEMBER 2023
URAIAN KEGIATAN KUANTITAS
Pembay (Rp.) (Rp.) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
02-07 08-14 15-21 22-28 29-04 05-11 12-18 19-25 26-02 03-09 10-16 17-23 24-30 31-06 07-13 14-20 21-27 28-03 04-10 11-17 18-24 25-28
Divisi 1. UMUM
1.2 Mobilisasi 1,00 170.533.485,00 170.533.485,00 1,084 0,190 0,190 0,190 0,190 0,325
Divisi 2. SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI (SMKK)
2.1(2) Pembuatan Prosedur dan Instruksi Kerja 1,00 45.000,00 45.000,00 0,000 0,000
2.2(8) Spanduk (Banner) 1,00 45.000,00 45.000,00 0,000 0,000
2.3(2) APD, antara lain :
- Topi Pelindung (Safety Helmet) 10,00 45.000,00 450.000,00 0,003 0,003
- Pelindung Pernapasan dan Mulut (Masker, respirator) 2,00 45.000,00 90.000,00 0,001 0,001
- Sarung Tangan (Safety Gloves) 50,00 5.000,00 250.000,00 0,002 0,002
- Rompi Keselamatan (Safety Vest) 10,00 20.000,00 200.000,00 0,001 0,001
2.4(1) Asuransi (Construction All Risk/CAR) 1,00 900.000,00 900.000,00 0,006 0,006
2.5(8) Petugas Pengatur Lalu Lintas 2,00 800.000,00 1.600.000,00 0,010 0,010
2.6(1) Peralatan P3K 1,00 140.000,00 140.000,00 0,001 0,001
2.6(4) Biaya Protokol Kesehatan Wabah menular (misal tempat cuci tangan, 1,00 75.000,00 75.000,00 0,000 0,000
2.7(1) Rambu Petunjuk 2,00 50.000,00 100.000,00 0,001 0,001
2.7(3) Rambu Peringatan 4,00 50.000,00 200.000,00 0,001 0,001
2.7(5) Rambu Informasi 1,00 80.000,00 80.000,00 0,001 0,001
2.7(8) Kerucut Lalu Lintas (Traffic Cone) 10,00 100.000,00 1.000.000,00 0,006 0,006
2.9(4) Bendera K3 1,00 50.000,00 50.000,00 0,000 0,000
Divisi 3. DRAINASE - 0,000
3.1(1) Galian Selokan, Drainase dan Saluran Air 15.182,00 56.295,75 854.682.076,50 5,434 0,679 0,679 0,679 0,679 0,679 0,679 0,679 0,679
3.2(1) Pasangan Batu Dengan Mortar 100,00 763.050,56 76.305.056,20 0,485 0,243 0,243
Divisi 4. PEKERJAAN TANAH
4.1(1) Galian Biasa 10.020,12 54.651,98 547.619.417,88 3,481 0,435 0,435 0,435 0,435 0,435 0,435 0,435 0,435
4.3(1) Penyiapan Badan Jalan 44.546,00 6.040,23 269.068.041,03 1,711 0,428 0,428 0,428 0,428
Divisi 6. PERKERASAN BERBUTIR
6.1(1) Lapis Pondasi Agregat Kelas A 5.693,25 892.397,23 5.080.640.541,08 32,300 5,383 5,383 5,383 5,383 5,383 5,383
6.1(2) Lapis Pondasi Agregat Kelas B 731,89 681.049,99 498.453.677,18 3,169 3,169
Divisi 7. PERKERASAN ASPAL
7.1(1) Lapis Resap Pengikat - Aspal Cair/Emulsi 22.773,00 20.542,82 467.821.708,18 2,974 0,744 0,744 0,744 0,744
7.3(5a) Laston - Lapis Aus (AC-WC) 2.049,57 1.666.209,10 3.415.012.178,94 21,711 5,428 5,428 5,428 5,428
Divisi 8. STRUKTUR
8.1(8a) Beton fc'=15 Mpa 3.415,95 1.189.429,42 4.063.031.427,25 25,830 6,458 6,458 6,458 6,458
8.8(1) Pasangan Batu 100,00 752.380,90 75.238.089,80 0,478 0,239 0,239
Divisi 10. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
10.2(1) Marka Jalan Thermoplastic 637,64 130.704,98 83.342.720,26 0,530 0,530
Divisi 11. PEKERJAAN PEMELIHARAAN KINERJA
11.1(9) Perbaikan Campuran Aspal Panas 28,80 3.741.356,66 107.751.071,81 0,685 0,685
11.1(21) Pembersihan Drainase dan Saluran Samping 200,00 31.675,61 6.335.121,40 0,040 0,040
11.1(22) Pengendalian Tanaman 4.800,00 1.782,50 8.556.000,00 0,054 0,054

JUMLAH HARGA 15.729.615.612,51 100,00


PPN 11% 1.730.257.717,38
TOTAL HARGA 17.459.873.329,89
DIBULATKAN 17.459.873.000,00
KEMAJUAN PERMINGGU (%) 0,190 0,213 1,304 1,304 1,125 1,114 1,542 2,024 2,118 4,711 5,383 5,383 5,383 5,383 5,383 6,068 6,171 12,63 12,63 12,63 6,987 0,325
RENCANA
KUMULATIF PERMINGGU (%) 0,190 0,403 1,707 3,011 4,135 5,250 6,792 8,815 10,93 15,64 21,03 26,41 31,79 37,18 42,56 48,63 54,80 67,43 80,06 92,69 99,67 100,00
REALISASI PERMINGGU (%)
REALISASI
JUMLAH KUMULATIF PERMINGGU (%)
DEVIASI PERMINGGU (%)
DEVIASI
JUMLAH KUMULATIF PERMINGGU (%)
Catatan : Rencana Serah Terima Pertama (PHO) tanggal 28 September 2023.

Disetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


Pejabat Pembuat Komitmen (PPK) Dinas Pekerjaan Umum Dan Penataan Ruang Kontraktor Pelaksana
Pembangunan Jalan Sumber Dana Alokasi Khusus (DAK) Kabupaten Manggarai PT. MENARA ARMADA PRATAMA
Bidang Bina Marga TA. 2023 Direksi Teknis,

STEFANUS KONJONG, ST. FRANSISKUS B. HUDI, ST. PAUL SUMITO


NIP. 19760424 200903 1 001 NIP. Direktur Utama