ZONA 1

EXCAVATOR
Data yang diketahui :
Jenis alat = Komatsu 200
Pengisian bucket = 10 detik
Mengangkut dan swing = 8 detik
Menumpahkan = 7 detik
Swing kembali = 5 detik
3 detik
Percepatan dan waktu =
33 detik
= 33/60
Cycle Time (CT)
= 0.55 menit
= 60/0.55
Banyak trip /jam
= 109.090909 trip/jam
Kapasitas bucket (q) = 0.7 m3
= 1.24 x 0.7
Volume backhoe (loose)
= 0.868 m3
= 0.868 x 109.0909
Produksi teoritis
= 94.6909091 m3/jam

DUMP TRUCK
Data yang diketahui :
Jenis alat = Mistubishi FM 517
Kapasitas angkut (q) = 4 m3
= 600 m
Jarak angkut (J)
= 0.6 km
Fixed time (FT) = 10 menit
Kecepatan isi (V1) = 10 km/jam
Kecepatan kosong (V2) = 14 km/jam
Efisiensi (E) = 0.75
60𝑥0.6/10+60𝑥0.6/14
= +10
Cycle Time (CT)
= 16.6 menit
4𝑥60𝑥0.75/16.6
=
Produksi
= 10.84 m3/jam

BULLDOZER
Data yang diketahui :
Jenis alat = Komatsu D53A 16
Daya mesin = 110 HP
Dozer blade = Tipe Angle
Kapasitas blade (q) = 2850 m3
Jarak gusur (DL) = 48.96 m
Kecepatan maju (F) = 3 km/jam
Kecepatan mundur (R) = 7.5 km/jam
F. Peralatan (E1) = 0.8 (tabel 5.19)
F. Operator (E2) = 0.7 (tabel 5.19)
F. material (E3) = 0.75 (tabel 5.19)
F. Manejemen (E4) = 0.82 (tabel 5.19)
Cuaca (E5) = 0.8 (tabel 5.19)
Perlengkapan (E6) = 0.75 (tabel 5.19)
Lapangan (E7) = 0.75 (tabel 5.19)
Total faktor (E) = 0.15
Fixed time = 0.1 menit
=
60𝑥𝐷𝐿/𝐹+60𝑥𝐷𝐿/𝑅 +FT
Cycle time
=
60𝑥48.96/3000+60𝑥48.96/7500 +0.1
= 1.471 menit
= 𝑞𝑥60𝑥𝐸/𝐶𝑇
Produksi
=2.85𝑥60𝑥0.15/1.471
= 17.44 m3/jam

SHEEPFOOT ROLLER
Data yang diketahui :
Jenis alat = Sankai SV 512 D
Faktor peralatan (E1) = 0.9 (tabel 5.19)
Faktor material (E2) = 0.8 (tabel 5.19)
F. manajemen (E3) = 0.9 (tabel 5.19)
Faktor cuaca (E4) = 0.92 (tabel 5.19)
Faktor pelengkap (E5) = 1 (tabel 5.19)
Faktor lapangan (E7) = 0.8 (tabel 5.19)
Total faktor (E) = 0.477
Lebar gilas efektif (W) = 0.2 m
Kecepatan gilas (V) = 1.5 km/jam
Tebal lapis (H) = 0.3 m
Jumlah laluan (N) = 6
Lebar gilas = 2 m
𝑊𝑥𝑉𝑥𝐻𝑥1000/𝑁
=
Qv'
= (2−0.2)5𝑥0.3𝑥1000/6
= 135
= Qv' x E
Qv = 135 x 0.477
= 64.4 m3/jam

ZONA 2
BULLDOZER
Data yang diketahui :
Jenis alat = Komatsu D53A 16
Daya mesin = 110 HP
Dozer blade = Tipe Angle
Kapasitas blade (q) = 2850 m3
Jarak gusur (DL) = 7.16 m
Kecepatan maju (F) = 3 km/jam
Kecepatan mundur (R) = 7.5 km/jam
F. Peralatan (E1) = 0.8 (tabel 5.19)
F. Operator (E2) = 0.7 (tabel 5.19)
F. material (E3) = 0.75 (tabel 5.19)
F. Manejemen (E4) = 0.82 (tabel 5.19)
Cuaca (E5) = 0.8 (tabel 5.19)
Perlengkapan (E6) = 0.75 (tabel 5.19)
Lapangan (E7) = 0.75 (tabel 5.19)
Total faktor (E) = 0.15
Fixed time = 0.1 menit
60𝑥𝐷𝐿/𝐹+60𝑥𝐷𝐿/𝑅 +FT
=
Cycle time
60𝑥7.16/3000+60𝑥7.16/7500 +0.1
=
= 0.301 menit
= 𝑞𝑥60𝑥𝐸/𝐶𝑇
Produksi
=2.85𝑥60𝑥0.15/0.301
= 85.25 m3/jam

VIBRATION ROLLER
Data yang diketahui :
Jenis alat = Sankai SV 512 D
Faktor peralatan (E1) = 0.9 (tabel 5.19)
Faktor material (E2) = 0.8 (tabel 5.19)
F. manajemen (E3) = 0.9 (tabel 5.19)
Faktor cuaca (E4) = 0.92 (tabel 5.19)
Faktor pelengkap (E5) = 1 (tabel 5.19)
Faktor lapangan (E7) = 0.8 (tabel 5.19)
Total faktor (E) = 0.477
Lebar gilas efektif (W) = 0.2 m
Kecepatan gilas (V) = 1.5 km/jam
Tebal lapis (H) = 0.3 m
Jumlah laluan (N) = 5
Lebar gilas = 2 m
𝑊𝑥𝑉𝑥𝐻𝑥1000/𝑁
=
Qv'
= (2−0.2)5𝑥0.3𝑥1000/6
Qv'

= 162
= Qv' x E
Qv = 162 x 0.477
= 77.3 m3/jam

ZONA 3
BULLDOZER
Data yang diketahui :
Volume = 1246386 m3
Jenis alat = Komatsu D53A 16
Daya mesin = 110 HP
Dozer blade = Tipe Angle
Kapasitas blade (q) = 2850 m3
Jarak gusur (DL) = 152.85 m
Kecepatan maju (F) = 3 km/jam
Kecepatan mundur (R) = 7.5 km/jam
F. Peralatan (E1) = 0.8 (tabel 5.19)
F. Operator (E2) = 0.7 (tabel 5.19)
F. material (E3) = 0.75 (tabel 5.19)
F. Manejemen (E4) = 0.82 (tabel 5.19)
Cuaca (E5) = 0.8 (tabel 5.19)
Perlengkapan (E6) = 0.75 (tabel 5.19)
Lapangan (E7) = 0.75 (tabel 5.19)
Total faktor (E) = 0.15
Fixed time = 0.1 menit
=
60𝑥𝐷𝐿/𝐹+60𝑥𝐷𝐿/𝑅 +FT
Cycle time
=
60𝑥152.85/3000+60𝑥152.85/7500 +0.1
= 4.4 menit
= 𝑞𝑥60𝑥𝐸/𝐶𝑇
Produksi
= 2.85𝑥60𝑥0.15/4.4
= 5.86 m3/jam

VIBRATION ROLLER
Data yang diketahui :
Jenis alat = Sankai SV 512 D
Faktor peralatan (E1) = 0.9 (tabel 5.19)
Faktor material (E2) = 0.8 (tabel 5.19)
F. manajemen (E3) = 0.9 (tabel 5.19)
Faktor cuaca (E4) = 0.92 (tabel 5.19)
Faktor pelengkap (E5) = 1 (tabel 5.19)
Faktor lapangan (E7) = 0.8 (tabel 5.19)
Total faktor (E) = 0.477
Lebar gilas efektif (W) = 0.2 m
Kecepatan gilas (V) = 1.5 km/jam
Tebal lapis (H) = 0.3 m
Jumlah laluan (N) = 6
Lebar gilas = 2 m
𝑊𝑥𝑉𝑥𝐻𝑥1000/𝑁
=
Qv'
= (2−0.2)5𝑥0.3𝑥1000/6
= 135
= Qv' x E
Qv = 162 x 0.477
= 64.4 m3/jam

ZONA 4
EXCAVATOR DAN DUMP TRUCK SAJA
Faktor-faktor koreksi :
Efisiensi kerja 50 s/jam = 0.83
Kondisi pekerjaan & tata laksana sedang = 0.65 (tabel 5.16)
Kedalaman optimum 120%, swing 180˚ = 0.7 (tabel 5.17)
Faktor pengisian (bucket) = 0.85 (tabel 5.18)
= 0.85 x 0/65 x 0.7 x 0.85
Faktor koreksi total
= 0.321
= 94.691 x 0.321
Produksi sebenarnya
= 30.396019 m3/jam
85/7500 +0.1
ZONA PRODUKTIVITAS ALAT (M3/JAM)
NO PEKERJAA
N Excavator Dump Truck Bulldozer Vibration Roller
1 Zona 1 30.396 10.84 17.44 64.395
2 Zona 2 30.396 10.84 85.25 77.274
3 Zona 3 30.396 10.84 5.86 64.395
4 Zona 4 30.396 10.84 - -