DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 8 3.27% 6 2.45% 7
Closed 65 26.53% 40 16.33% -25 1 0 66
On Progress 2 0.82% 29 11.84% 27 0 0 2
BARATA 98 98 98
Open 22 8.98% 13 5.31% 22
Closed 64 26.12% 38 15.51% -26 2 0 66
On Progress 12 4.90% 47 19.18% 35 -2 0 10
MULTINAS 72 72 72
Open 15 6.12% 14 5.71% 14
Closed 50 20.41% 27 11.02% -23 0 0 50
On Progress 7 2.86% 31 12.65% 24 1 0 8
TOTAL
OPEN 45 18.37% 33 13.47% 43
CLOSED 179 73.06% 105 42.86% -74 3 0 182
ON PROGGRESS 21 8.57% 107 43.67% 20
Total 245 100.00% 245 23.67% 245
TOTAL = 69 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
2.86% 6 2.45%
26.94% 40 16.33% -26 66
0.82% 29 11.84% 27 2
98
8.98% 13 5.31%
26.94% 38 15.51% -28 66
4.08% 47 19.18% 37 10
72
5.71% 14 5.71%
20.41% 27 11.02% -23 50
3.27% 31 12.65% 23 8
17.55% 33 13.47%
74.29% 105 42.86% -77
8.16% 107 43.67%
100.00% 245 100.00%
UPDATE PROGRESS PERALATAN PERLU PERBAIKAN LMG 2021 PG ASSEMBAGOES
UPDATE 29 Maret 2021
Note Fill Warna Merah: Butuh diskusi internal untuk keputusan pekerjaan
Pelaksanaan: Pelaksanaan dikerjakan oleh Tim KSO (KSO, Barata, dan Multinas) Tim PTPN XI (PG. Assembagoes) dengan tanda (x)
PIC: Pemilik scope pekerjaan
Untuk setiap pekerjaan yang akan dikerjakan didalam list, dikerjakan oleh Pelaksana Pekerjaan (Man Power, Material dan Tools)
Sedangkan beban biaya yang timbul akan diselesaikan antara manajemen PTPN XI dan KSO WBM sesuai hasil media dengan JPN
Manpo Pelaksanaan
Durasi
No Item Action Plan Start Finish wer PIC Status Keterangan
(Hari)
(orang) KSO BRT MSI PG
CANE PREPARATION & MILL 1/20/2021 5/4/2021
1 Tippler Oil Flushing 3/1/2021 3/8/2021 7 Barata x Open Tunggu Tenaga dan Pengadaan Oli
Pengecekan Filter 3/1/2021 3/8/2021 7 Barata x On Progress Tunggu pengadaan part
Tunggu tenaga
3/1/2021 3/8/2021 7 Barata x Closed hari ini selesai dan menunggu pengecekan bersama
Perbaikan clamp pipa dan fitting (20-3-21)
Tunggu Pengadaan coupling
3/1/2021 3/8/2021 7 Barata x Closed hari ini dibelikan (20-03-21 on site)
Ganti chain coupling oil pump Material Masih dibesali
Ganti oli 3/1/2021 3/8/2021 7 Barata x On Progress Tunggu pengadaan oli tippler by by PTPN/PG
Remaining tera metrologi, hasil tera oke
2/25/2021 3/20/2021 23 Barata x Closed
Ganti load cell dan indicator tippler nomor 1 2 3 oke, cek bersama PG
- Proses check bearing
- Perlu penggantian spacer, cover bearing dan oil
2 Auxilary Carrier Pembongkaran gearbox Auxilary 3/1/2021 3/3/2021 2 Barata x Closed
seal TC 170x200x15
- rencana akan dibawa ke barata (4/3/2021)
Pengecekan oli Barata x x On Progress Tunggu pengadaan oli auxilary carier by PTPN/PG
2/25/2021 2/25/2021 0 Barata x Closed Rantai masih layak terpakai 100%
Pengecekan rantai - akan dicek bersama
- Menunggu Pengadaan bolt & nut Barata ( m12 x 45
Pengecekan dan pengadaan bolt & nut 2/26/2021 3/31/2021 33 Barata x x On Progress )
- Sudah dicheck perlu penggantian sebagian baut &
nut uk Ø1/2 x 3 inch = 2000 bh by barata
Regreasing Block Bearing 3/2/2021 3/5/2021 3 Barata x Closed Sudah regreasing
- Menunggu ganti oli by barata
3 3/1/2021 3/8/2021 7 Barata x Closed
Main Cane Carrier Pengecekan oli sudah dicek
Manpo Pelaksanaan
Durasi
No Item Action Plan Start Finish wer PIC Status Keterangan
(Hari)
(orang) KSO BRT MSI PG
- Sudah dicheck perlu penggantian sebagian pen dan
bushing
3/1/2021 3/8/2021 7 Barata x x On Progress (note : rantai sudah dipasang pakai material dari PG,
Barata diminta mengetahui)
- proses pelumasan rantai.
Pengecekan rantai
- Sudah dicheck perlu penggantian sebagian bolt &
3/1/2021 3/8/2021 7 Barata x Closed nut uk Ø1/2 x 2,5 mm = 1000 bh by barata,
Pengecekan bolt & nut Pengadaan baut
Regreasing Block Bearing 3/1/2021 3/8/2021 7 Barata x Closed Sudah regreasing
Pemasangan gearbox 3/1/2021 3/8/2021 7 Barata x Closed - Reparasi base plate
10 IMC Inventarisasi & Penggantian Rantai 1796 3/25/2021 3/28/2021 3 Barata x On Progress - proses pengadaan
- proses pemasangan
Perbaikan rake imc Barata x Closed
- Pengadaan bolt & nut Barata uk 5/8 x 3 inch = 1000
Penggantian Bolt & Nut 3/1/2021 3/4/2021 3 Barata x On Progress bh
- proses pengadaan M16 x 70 (on site 20-03-21) ,
sudah datang 80 pcs
Manpo Pelaksanaan
Durasi
No Item Action Plan Start Finish wer PIC Status Keterangan
(Hari)
(orang) KSO BRT MSI PG
1/20/2021 3/31/2021 70 Barata x On Progress - remaining IMC no.1
Install IMC - no 2, 3 sudah individual test
Impeller sdh dibawa MSI, impeler sudah di bengkel
11 2/25/2021 3/27/2021 30 Multinas x x On Progress
Rotary Screen Impeller + as + bearing pompa rusak (akhir april onsite)
- RV-3050 ok
- LIC-3037 mekanik tidak bisa nol
- LIC-3000 (ok)
- PIC-3033 ok
15 Instrument Pengecekan dan kalibrasi 3/14/2021 3/24/2021 10 Multinas x Closed - TIC 3035 ok
- TIC-3036 Mekanik tidak nol
- LT-3003 level transmitter (ok )
- LT-3028 Level transmitter (ok)
- kompresor torak (ok)
perlu pengecekan valve (LIC3037 dan TIC3036
Tinggal TTD Form Pengecekan ke PG dan PMC
3 Receiver Pengecekan & Perbaikan 1/20/2021 3/31/2021 70 Barata x On Progress - remaining palung D sisi utara
3 Pompa Perbaikan kabel power injeksi 355 kW Multinas x x Closed - Pengecekan bersama 10/3/21
- Remaining individual test
4 Nozzle spray pond Cleaning spray nozzle 3/15/2021 4/4/2021 20 6 Barata x x Open Tunggu Tim Barata
- material dan manpower ready
5 3/15/2021 4/4/2021 20 4 Barata x On Progress
Keramba microba Pembersihan sarana - proses fabrikasi keramba
PUTERAN 1/20/2021 4/24/2021
material onsite
1 3/11/2021 3/13/2021 2 3 Multinas x Closed
HGF R1 no.1 Perbaikan feeding valve sudah terpasang tinggal dites
Magger Motor, Magger Blower, R1 oven (03)
2 3/13/2021 3/28/2021 15 3 Multinas x On Progress
HGF R Pengecekan dan Perbaikan oven motor HGF R1-1, HGF R1-2
-treatment panel
3 3/29/2021 4/2/2021 4 3 Barata x x On Progress - siap pengecekan bersama
HGF Afinasi continue Pengecekan dan Perbaikan - ruangan control room masih diperbaiki
- troubleshooting
4/3/2021 4/8/2021 5 3 Barata x x On Progress - akan di kalibrasi bersama
Pengecekan dan Perbaikan feeding valve - ruangan control room masih diperbaiki
(scope BARATA)
- Inv Afinasi 1 ok remaining uji coba
- Inv afinasi 2 ok remaining uji coba
9 Instrument Pengecekan dan kalibrasi Multinas x On Progress
- inv afinasi 3 proses pasang
- inv afinasi cont ok remaining uji coba
- selenoid HGF afinasi No1 ok
4 Belt Conveyor Ash Perbaikan belt 3/2/2021 3/5/2021 3 4 KSO x On Progress Proses sambung,
Penggantian bearing 3/15/2021 3/17/2021 2 4 KSO x On Progress Proses bongkar, tunggu bearing, sudah dicleaning
Perbaikan Feeder drum 3/19/2021 3/29/2021 10 4 KSO x x On Progress Proses ganti bearing
Manpo Pelaksanaan
Durasi
No Item Action Plan Start Finish wer PIC Status Keterangan
(Hari)
(orang) KSO BRT MSI PG
- Cleaning strainer
- perbaikan jalur cooling pump
- Remaining Re alligment BFWP #2,3 masih proses
5 feed water pump Pengecekan dan service 3/2/2021 3/8/2021 6 3 KSO x On Progress pengerjaan ( BFWP #1 sudah selesai)
- proses pengetesan ampere motor
- Remaining pengecekan bersama
Reparasi roller
16 3/21/2021 3/26/2021 5 4 KSO x x Closed - remaining pengecekan bersama
- minta penambahan roller
BC 9 Perbaikan chute dan sambungan belt
17 Blowdown Perbaikan jalur air 3/15/2021 3/22/2021 7 3 KSO x Closed Dibuatkan handrail
Menunggu tenaga
menunggu baut stainless
18 Electrical 3/2/2021 3/5/2021 3 2 KSO x x Closed
rencana 19/03/21 On site
Menunggu cek bersama (20-3-21)
Perbaikan panel SA Fan dan electrical yang terbakar
- Pengecekan terminasi
3/6/2021 3/11/2021 5 2 KSO x On Progress - proses cleaning trafo 13MW, trafo 5, trafo 6
Pengecekan terminasi pada panel - proses cleaning panel MV SS3
Evaluasi inverter IDF (DC Overvoltage) 3/2/2021 3/5/2021 3 1 KSO x x On Progress Menunggu konfirmasi thermax
Manpo Pelaksanaan
Durasi
No Item Action Plan Start Finish wer PIC Status Keterangan
(Hari)
(orang) KSO BRT MSI PG
19 Bagasse reclaimer Perbaikan electrical bagasse reclaimer 3/12/2021 3/15/2021 3 2 KSO x x Closed Menunggu tenaga dan material
Perbaikan rantai 3/27/2021 4/3/2021 7 4 KSO x Closed
Perbaikan block bearing 4/4/2021 4/9/2021 5 3 KSO x Closed
- Cleaning peti labyrint
- remaining penggantian flange 6"
20 WTP Pengecekan dan perbaikan jalur dan tangki 3/3/2021 3/13/2021 10 3 KSO x Closed - flange sudah on site
- Proses pengerjaan pasang flange
- remaining pengecekan bersama
Turbin 10 MW:
2 3/12/2021 3/22/2021 10 2 KSO x x On Progress
- Proses pengecekan transmitter dan termoelemen
Instrument Pengecekan dan kalibrasi
3 Turbine 10 MW 2/26/2021 3/3/2021 5 1 KSO x x On Progress Menunggu konfirmasi MAN
Konfirmasi terkait Annual Maintenance dengan MAN
- Pengecekan rumah bearing
4 4/26/2021 4/29/2021 3 2 KSO x x Open - menunggu vendor dosing pump waktu komisioning
Dosing pump Pengujian dosing pump
5 Return Cooloing Pump Pengecekan 3/1/2021 3/3/2021 2 2 KSO x x Closed
DIESEL ENGINE GENERATOR 3/1/2021 3/15/2021
1 Accu Pengecekan 3/1/2021 3/4/2021 3 1 KSO x x Closed
2 sincronizer funtional check 3/5/2021 3/8/2021 3 1 KSO x x Closed Sudah test internal
3 Oli Penggantian oli 3/10/2021 3/15/2021 5 2 KSO x x On Progress - menunggu pengadaan oli by PG
- Oli by PG
3/10/2021 3/12/2021 2 1 KSO x x On Progress - filter genset perlu diganti menunggu selesai ganti
Pengecekan filter solar dan oli Oli genset
ELECTRCAL 12/30/1899 12/30/1899
- Pin trip exces power pecah, part di bawa barat
- Check kapasitor bank SS2 : kap rusak 50 kvar = 1 bh
1 Panel Pengecekan terminasi panel sentral Barata x x On Progress (ok)
- sedang pekerjaan SS1 dan SS3
- Megger trafo
2 Control Room Pengecekan dan perbaikan kebocoran Barata x x On Progress - proses perbaikan control room HGF
GENERAL 3/8/2021 3/23/2021
1 Atap Supergravity Pengecekan dan perbaikan 12/30/1899 Barata x On Progress - proses pengecekan
2 Inhouse keeping Pengecekan dan perbaikan 3/8/2021 3/23/2021 15 8 KSO x On Progress - proses pengecekan
Manpower Pelaksanaan Maret 2021 Apr-21 Mei 2021
Durasi (orang)
No Item Action Plan Biaya Start Finish (Hari) PIC Status
KSO BRT MSI PG 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
CANE PREPARATION & MILL 1/20/2021 5/4/2021
Pengecekan Filter 3/1/2021 3/8/2021 7 Barata x P P P P P P P P P P P P P P P P P P P P P P P P P P P On Progress
3/1/2021 3/8/2021 7 Barata x P P P P P P P P P P P P P P P P P P P P P P P P P P P On Progress
Ganti oli
Barata x x P P P P P P P P P P P P P P P P P P P P P P P P P P P On Progress
Pengecekan oli
Pengecekan dan pengadaan bolt & nut 2/26/2021 3/31/2021 33 Barata x x P P P P P P P P P P P P P P P P P P P P P P P P P P P On Progress
Barata P P P P P P P P P P P P P P P P P P On Progress
Teflon Hidraulic Aus + Cuil
Oil Gearbox Barata x P P P P On Progress
10 IMC Inventarisasi & Penggantian Rantai 1796 3/25/2021 3/28/2021 3 Barata x P P P P P P P P P P P P P P P P P P P P P P P P P P P On Progress
11 Rotary Screen Impeller + as + bearing pompa rusak 2/25/2021 3/27/2021 30 Multinas x x P P P P P P P P P P P P P P P P P P P P P P P P P P P On Progress
Cleaning 3/28/2021 3/30/2021 2 Multinas x P P P P P P P P P P P P P On Progress
12 Pompa Gilingan Pengecekan dan Perbaikan Casing pompa nira 2/25/2021 3/27/2021 30 Multinas x x P P P P P P P P P P P P P P P P P P P P P P P P P P P On Progress
gilingan 4 & 5 keropos
13 Pipe & Fitting Gilingan Pipa nira gilingan bocor 2/25/2021 3/17/2021 20 Multinas P P P P P P P P P P P P P P P P P P P P P P P P P P P On Progress
Pengecekan & Perbaikan pompa clear liquor 2/26/2021 3/28/2021 30 Multinas x P P P P P P P P P P P P P P P P P P P P P P P P P P P On Progress
Pengecekan & Perbaikan pompa sludge 2/26/2021 3/28/2021 30 Multinas x P P P P P P P P P P P P P P P P P P P P P P P P P P P On Progress
14 Elevating Carrier Inventarisasi & Penggantian Rantai 1796 3/25/2021 3/28/2021 3 KSO x x P P On Progress
3 Instrument Pengecekan dan kalibrasi 3/10/2021 3/17/2021 7 2 KSO x P P On Progress
6 Pompa sumur Pendalaman sumur 3/10/2021 3/20/2021 10 4 KSO x x P P P P P On Progress
8 Valve Pengecekan & perbaikan valve di area masakan 3/1/2021 3/4/2021 3 6 KSO x x P P P P P P P P P P P P P P P P P P P P P P P On Progress
1 Kanal Injeksi Pengecekan dan perbaikan 3/1/2021 KSO x P P P P P P P P P P P P P P P P P P P P P P P On Progress
5 feed water pump Pengecekan dan service 3/2/2021 3/8/2021 6 3 KSO x P P P P P P P P P P P P P P P P P P P P P P On Progress
- Proses machining
- masih proses di besali untuk dibuatkan lubang
Penggantian bushing 3/4/2021 3/11/2021 KSO Closed
pelumas
- proses install
2 Dinding Boiler Perbaikan dinding dan roof boiler 1/23/2021 3/4/2021 KSO Closed
Remaining cassing plat
- menunggu hand bor
Perbaikan Isolasi 2/28/2021 3/15/2021 KSO On Progress sisi ESP utara-selatan selesai
lanjut pengerjaan sisi boiler
tunggu pengecekan bersama
- Menunggu tenaga
- PCV-301 Boiler 1 feed back bermasalah
(pengadaan)
- FDF boiler 1 feed back bermasalah (pengadaan)
Positioner 0-50% (perlu service) & FB problem
(perlu pengadaan modul feed back card)
- IDF Boiler 1 Feed back bermasalah (pengadaan)
perlu pengadaan sparepart type CP-2 FB (b) J
(resistan 10k) Error.
- IDF boiler 2 feed back bermasalah (pengadaan)
Calibartion OK dan feed back masih proses
pengecekan
- FDF boiler 2 feed back bermasalah (pengadaan)
perlu pengadaan modul feed back card
- SAF boiler 2 feed back bermasalah (pengadaan)
3 Instrument Konfirmasi Thermax 2/26/2021 3/3/2021 KSO On Progress perlu pengadaan modul feed back card
- CV PRDS masih berfungsi, respon lambat
positioner dan mechanical part bermasalah (perlu
servis).
- FT-501 Boiler 2 masih belum bisa nol (perlu
kalibrasi ulang) Tunggu agenda tim PG
- FI-302 Flow Ind Boiler 2 masih cek kalibrasi
Proses sambung,
4 3/2/2021 3/5/2021 KSO On Progress
Belt Conveyor Ash Perbaikan belt tunggu cek bersama
- Cleaning strainer
- perbaikan jalur cooling pump
- Remaining Re alligment BFWP #2,3 masih proses
5 feed water pump Pengecekan dan service 3/2/2021 3/8/2021 KSO On Progress pengerjaan ( BFWP #1 sudah selesai)
- proses pengetesan ampere motor
- Remaining pengecekan bersama
7 Bagasse Belt Conveyor Perbaikan chute dan sambungan belt 3/1/2021 3/29/2021 KSO Closed Cek roll penghantar
8 ESP Pengecekan dan perbaikan inerpart 3/11/2021 3/16/2021 KSO Closed Perbaikan staging
Fine Tuning 6/5/2021 6/12/2021 KSO Open Menunggu Thermax
- Pengecekan terminasi
- proses cleaning trafo 13MW, trafo 5, trafo 6
3/6/2021 3/11/2021 KSO On Progress - proses cleaning panel MV SS3
tunggu pengecekan bersama
Pengecekan terminasi pada panel
Evaluasi inverter IDF (DC Overvoltage) 3/2/2021 3/5/2021 KSO On Progress Menunggu konfirmasi thermax
- Pengecekan rumah bearing
Turbin 10 MW:
2 Instrument Pengecekan dan kalibrasi 3/12/2021 3/22/2021 KSO On Progress
- Proses pengecekan transmitter dan termoelemen
12 Pompa Gilingan Pengecekan dan Perbaikan Casing pompa nira 2/25/2021 3/27/2021 Multinas On Progress
gilingan 4 & 5 keropos
13 Pipe & Fitting Gilingan Pipa nira gilingan bocor 2/25/2021 3/17/2021 Multinas On Progress
Pengecekan Skat
3/2/2021 3/22/2021 Multinas On Progress
Pemasangan deksel
7 Single Tray Clarifier Pengecekan kebersihan 3/1/2021 3/2/2021 Multinas Closed
Water Filling 3/3/2021 3/8/2021 Multinas Open
Pengecekan & Perbaikan pompa clear liquor 2/26/2021 3/28/2021 Multinas On Progress
2/26/2021 3/28/2021 Multinas On Progress
Pengecekan & Perbaikan pompa sludge
13 Filter Press Pengecekan & Pembersihan filter 2/26/2021 2/27/2021 Multinas Closed
Pengecekan Hydraulic system 3/15/2021 3/17/2021 Multinas Closed
14 Fine Liquor Evaporator Hydro Test 3/16/2021 3/23/2021 Multinas Open
Vacum Test 3/24/2021 3/28/2021 Multinas Open
Pembersihan dan pengecekan 3/10/2021 3/15/2021 Multinas Open
15 CVC Pengecekan dan perbaikan pipa output 2/25/2021 Multinas Open
Pengecekan cooling water pump cvc 2/25/2021 Multinas Open
Regreasing Block Bearing 3/2/2021 3/5/2021 Barata Closed Sudah regreasing dan sudah dicek
- Menunggu ganti oli by barata
3 3/1/2021 3/8/2021 Barata Closed
Main Cane Carrier Pengecekan oli sudah dicek
Pengecekan bearing 3/3/2021 3/5/2021 Barata Open menunggu konfirmasi five cail
Balancing Inline 3/25/2021 3/27/2021 Barata Open Sebelum melakukan balancing, dipersiapkan
untuk membalik kabel trafo excess power
10 IMC Inventarisasi & Penggantian Rantai 1796 3/25/2021 3/28/2021 Barata On Progress - proses pengadaan
- proses pemasangan
Perbaikan rake imc Barata Closed
- Meminjam consumable PG
1 3/1/2021 3/31/2021 Barata Closed - sedang proses pengerjaan
- Tinggal BA
Platform evaporator Perbaikan Stagging evap badan 7, 8, dan 9
- Proses pengelasan no 7
2 2/15/2021 3/15/2021 Barata On Progress - eva 7 top belum insulasi
- eva 2 proses pengelasan dome
Top Cone Evaporator Evaporator Nomor 2 & 7
7 Pengujian Hydro Test 2/20/2021 4/1/2021 Barata On Progress - Hydrotest body no.2 belum selesai
Perbaikan tray
- pencucian keramik
- remaining perbaikan tray dan penataan
Penataan keramic 3/3/2021 3/10/2021 Barata On Progress
keramik
- penggantian pipa karbon menjadi pipa
stainless 4 inch
4 Nozzle spray pond Cleaning spray nozzle 3/15/2021 4/4/2021 Barata Open
2 Control Room Pengecekan dan perbaikan kebocoran Barata On Progress - proses perbaikan control room HGF
1 Atap Supergravity Pengecekan dan perbaikan 12/30/1899 Barata On Progress - proses pengecekan
(scope BARATA)
- menunggu control room selesai perbaikan
- Inv Afinasi 1 ok remaining uji coba
- Inv afinasi 2 ok remaining uji coba
9 Instrument Pengecekan dan kalibrasi Multinas On Progress
- inv afinasi 3 proses pasang
- inv afinasi cont ok remaining uji coba
- selenoid HGF afinasi No1 ok
- menunggu control room masih diperbaiki.
Manpower Pelaksanaan Maret 2021 Apr-21 Mei 2021
Durasi (orang)
No Item Action Plan Biaya Start Finish (Hari) PIC Status
KSO BRT MSI PG 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
CANE PREPARATION & MILL 1/20/2021 5/4/2021
Pengecekan Filter 3/1/2021 3/8/2021 7 Barata x P P P P P P P C On Progress
Ganti chain coupling oil pump 3/1/2021 3/8/2021 7 Barata x P P P P P P P C On Progress
Ganti oli 3/1/2021 3/8/2021 7 Barata x P P P P P P P C On Progress
Penggantian ring bearing dan oil seal gearbox Barata x On Progress
Pengecekan dan pengadaan bolt & nut 2/26/2021 3/31/2021 33 Barata x x P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P C On Progress
5 Carding Drum Penambahan lapisan hard facing 3/3/2021 3/10/2021 7 Barata x P P P P P P P P C On Progress
Penggantian oli Barata x On Progress
6 Feeding Drum Penambahan lapisan hard facing 3/15/2021 3/22/2021 7 Barata x P P P P P P P C On Progress
Install Kabel rotor 3/4/2021 3/6/2021 2 Barata x P P C On Progress
Pembuatan scraper + adaptor + tangkai 2/1/2021 3/31/2021 58 Barata x P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P C On Progress
Perbaikan roll gilingan 1/20/2021 3/31/2021 70 Barata x P P P P P P P P P P P P P P P P P P P P P P P P P P P P P P C On Progress
Hard facing trash plate 2/1/2021 3/8/2021 35 Barata x P P P P P P P C On Progress
10 IMC Inventarisasi & Penggantian Rantai 1796 3/25/2021 3/28/2021 3 Barata x P P P C On Progress
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 8 3.27% 8 3.27% 8
Closed 63 25.71% 40 16.33% -23 2 0 65
On Progress 4 1.63% 27 11.02% 23 -2 2 2
BARATA 98 98 98
Open 23 9.39% 13 5.31% 22
Closed 64 26.12% 38 15.51% -26 0 0 64
On Progress 11 4.49% 47 19.18% 36 1 0 12
MULTINAS 72 72 72
Open 15 6.12% 14 5.71% 15
Closed 49 20.00% 27 11.02% -22 1 0 50
On Progress 8 3.27% 31 12.65% 23 -1 0 7
TOTAL
OPEN 46 18.78% 35 14.29% 45
CLOSED 176 71.84% 105 42.86% -71 3 0 179
ON PROGGRESS 23 9.39% 105 42.86% 21
Total 245 100.00% 245 23.67% 245
TOTAL = 69 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
3.27% 6 2.45%
26.53% 40 16.33% -25 66
0.82% 29 11.84% 27 2
98
8.98% 13 5.31%
26.12% 38 15.51% -26 66
4.90% 47 19.18% 35 12
72
6.12% 14 5.71%
20.41% 27 11.02% -23 50
2.86% 31 12.65% 24 7
18.37% 33 13.47%
73.06% 105 42.86% -74
8.57% 107 43.67%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 2 April 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 8 3.27% 8 3.27% 8
Closed 63 25.71% 40 16.33% -23 0 0 63
On Progress 4 1.63% 27 11.02% 23 0 0 4
BARATA 98 98 98
Open 24 9.80% 13 5.31% 23
Closed 62 25.31% 38 15.51% -24 2 0 64
On Progress 12 4.90% 47 19.18% 35 -1 0 11
MULTINAS 72 72 72
Open 15 6.12% 14 5.71% 15
Closed 49 20.00% 27 11.02% -22 0 0 49
On Progress 8 3.27% 31 12.65% 23 0 0 8
TOTAL
OPEN 47 19.18% 35 14.29% 46
CLOSED 174 71.02% 105 42.86% -69 2 0 176
ON PROGGRESS 24 9.80% 105 42.86% 23
Total 245 100.00% 245 23.67% 245
TOTAL = 69 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
3.27% 8 3.27%
25.71% 40 16.33% -23 66
1.63% 27 11.02% 23 4
98
9.39% 13 5.31%
26.12% 38 15.51% -26 66
4.49% 47 19.18% 36 11
72
6.12% 14 5.71%
20.00% 27 11.02% -22 50
3.27% 31 12.65% 23 8
18.78% 35 14.29%
71.84% 105 42.86% -71
9.39% 105 42.86%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 1 April 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 11 4.49% 9 3.67% 8
Closed 63 25.71% 39 15.92% -24 0 1 63
On Progress 1 0.41% 27 11.02% 26 3 0 4
BARATA 98 98 98
Open 24 9.80% 15 6.12% 24
Closed 61 24.90% 38 15.51% -23 1 0 62
On Progress 13 5.31% 45 18.37% 32 -1 2 12
MULTINAS 72 72 72
Open 15 6.12% 15 6.12% 15
Closed 49 20.00% 27 11.02% -22 0 0 49
On Progress 8 3.27% 30 12.24% 22 0 1 8
TOTAL
OPEN 50 20.41% 39 15.92% 47
CLOSED 173 70.61% 104 42.45% -69 1 1 174
ON PROGGRESS 22 8.98% 102 41.63% 24
Total 245 100.00% 245 23.27% 245
TOTAL = 69 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
3.27% 8 3.27%
25.71% 40 16.33% -23 66
1.63% 27 11.02% 23 4
98
9.80% 13 5.31%
25.31% 38 15.51% -24 66
4.90% 47 19.18% 35 12
72
6.12% 14 5.71%
20.00% 27 11.02% -22 50
3.27% 31 12.65% 23 8
19.18% 35 14.29%
71.02% 105 42.86% -69
9.80% 105 42.86%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 31 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 11 4.49% 11 4.49% 11
Closed 63 25.71% 38 15.51% -25 0 1 63
On Progress 1 0.41% 26 10.61% 25 0 1 1
BARATA 98 98 98
Open 24 9.80% 16 6.53% 24
Closed 52 21.22% 35 14.29% -17 9 3 61
On Progress 22 8.98% 47 19.18% 25 -9 -2 13
MULTINAS 72 72 72
Open 15 6.12% 17 6.94% 15
Closed 49 20.00% 24 9.80% -25 0 3 49
On Progress 8 3.27% 31 12.65% 23 0 -1 8
TOTAL
OPEN 50 20.41% 44 17.96% 50
CLOSED 164 66.94% 97 39.59% -67 9 7 173
ON PROGGRESS 31 12.65% 104 42.45% 22
Total 245 100.00% 245 22.45% 245
TOTAL = 69 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
4.49% 9 3.67%
25.71% 39 15.92% -24 66
0.41% 27 11.02% 26 1
98
9.80% 15 6.12%
24.90% 38 15.51% -23 66
5.31% 45 18.37% 32 13
72
6.12% 15 6.12%
20.00% 27 11.02% -22 50
3.27% 30 12.24% 22 8
20.41% 39 15.92%
70.61% 104 42.45% -69
8.98% 102 41.63%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 29 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 11 4.49% 11 4.49% 11
Closed 63 25.71% 38 15.51% -25 0 0 63
On Progress 1 0.41% 26 10.61% 25 0 0 1
BARATA 98 98 98
Open 24 9.80% 16 6.53% 24
Closed 52 21.22% 31 12.65% -21 0 4 52
On Progress 22 8.98% 51 20.82% 29 0 -4 22
MULTINAS 72 72 72
Open 16 6.53% 17 6.94% 15
Closed 48 19.59% 24 9.80% -24 1 0 49
On Progress 8 3.27% 31 12.65% 23 0 0 8
TOTAL
OPEN 51 20.82% 44 17.96% 50
CLOSED 163 66.53% 93 37.96% -70 1 4 164
ON PROGGRESS 31 12.65% 108 44.08% 31
Total 245 100.00% 245 22.45% 245
TOTAL = 67 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
4.49% 11 4.49%
25.71% 38 15.51% -25 66
0.41% 26 10.61% 25 1
98
9.80% 16 6.53%
21.22% 35 14.29% -17 66
8.98% 47 19.18% 25 22
72
6.12% 17 6.94%
20.00% 24 9.80% -25 50
3.27% 31 12.65% 23 8
20.41% 44 17.96%
66.94% 97 39.59% -67
12.65% 104 42.45%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 29 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 11 4.49% 13 5.31% 11
Closed 61 24.90% 35 14.29% -26 2 3 63
On Progress 3 1.22% 27 11.02% 24 -2 -1 1
BARATA 98 98 98
Open 24 9.80% 19 7.76% 24
Closed 51 20.82% 30 12.24% -21 1 1 52
On Progress 23 9.39% 49 20.00% 26 -1 2 22
MULTINAS 72 72 72
Open 16 6.53% 17 6.94% 16
Closed 48 19.59% 24 9.80% -24 0 0 48
On Progress 8 3.27% 31 12.65% 23 0 0 8
TOTAL
OPEN 51 20.82% 49 20.00% 51
CLOSED 160 65.31% 89 36.33% -71 3 4 163
ON PROGGRESS 34 13.88% 107 43.67% 31
Total 245 100.00% 245 22.45% 245
TOTAL = 67 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
4.49% 11 4.49%
25.71% 38 15.51% -25 66
0.41% 26 10.61% 25 1
98
9.80% 16 6.53%
21.22% 31 12.65% -21 66
8.98% 51 20.82% 29 22
72
6.53% 17 6.94%
19.59% 24 9.80% -24 50
3.27% 31 12.65% 23 8
20.82% 44 17.96%
66.53% 93 37.96% -70
12.65% 108 44.08%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 28 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 11 4.49% 13 5.31% 11
Closed 59 24.08% 35 14.29% -24 2 0 61
On Progress 5 2.04% 27 11.02% 22 -2 0 3
BARATA 98 98 98
Open 25 10.20% 19 7.76% 24
Closed 50 20.41% 30 12.24% -20 1 0 51
On Progress 23 9.39% 49 20.00% 26 0 0 23
MULTINAS 72 72 72
Open 17 6.94% 17 6.94% 16
Closed 44 17.96% 24 9.80% -20 4 0 48
On Progress 11 4.49% 31 12.65% 20 -3 0 8
TOTAL
OPEN 53 21.63% 49 20.00% 51
CLOSED 153 62.45% 89 36.33% -64 7 0 160
ON PROGGRESS 39 15.92% 107 43.67% 34
Total 245 100.00% 245 22.45% 245
TOTAL = 66 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
4.49% 13 5.31%
24.90% 35 14.29% -26 66
1.22% 27 11.02% 24 3
98
9.80% 19 7.76%
20.82% 30 12.24% -21 66
9.39% 49 20.00% 26 23
72
6.53% 17 6.94%
19.59% 24 9.80% -24 50
3.27% 31 12.65% 23 8
20.82% 49 20.00%
65.31% 89 36.33% -71
13.88% 107 43.67%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 27 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 12 4.90% 13 5.31% 11
Closed 58 23.67% 33 13.47% -25 1 2 59
On Progress 5 2.04% 29 11.84% 24 0 -2 5
BARATA 98 98 98
Open 25 10.20% 19 7.76% 25
Closed 48 19.59% 30 12.24% -18 2 0 50
On Progress 25 10.20% 49 20.00% 24 -2 0 23
MULTINAS 72 72 72
Open 17 6.94% 17 6.94% 17
Closed 42 17.14% 24 9.80% -18 2 0 44
On Progress 13 5.31% 31 12.65% 18 -2 0 11
TOTAL
OPEN 54 22.04% 49 20.00% 53
CLOSED 148 60.41% 87 35.51% -61 5 2 153
ON PROGGRESS 43 17.55% 109 44.49% 39
Total 245 100.00% 245 22.45% 245
TOTAL = 64 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
4.49% 13 5.31%
24.08% 35 14.29% -24 66
2.04% 27 11.02% 22 5
98
10.20% 19 7.76%
20.41% 30 12.24% -20 66
9.39% 49 20.00% 26 23
72
6.94% 17 6.94%
17.96% 24 9.80% -20 50
4.49% 31 12.65% 20 11
21.63% 49 20.00%
62.45% 89 36.33% -64
15.92% 107 43.67%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 26 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 12 4.90% 13 5.31% 12
Closed 58 23.67% 33 13.47% -25 0 0 58
On Progress 5 2.04% 29 11.84% 24 0 0 5
BARATA 98 98 98
Open 26 10.61% 19 7.76% 25
Closed 47 19.18% 30 12.24% -17 1 0 48
On Progress 25 10.20% 49 20.00% 24 0 0 25
MULTINAS 72 72 72
Open 17 6.94% 18 7.35% 17
Closed 41 16.73% 24 9.80% -17 1 0 42
On Progress 14 5.71% 30 12.24% 16 -1 1 13
TOTAL
OPEN 55 22.45% 50 20.41% 54
CLOSED 146 59.59% 87 35.51% -59 2 0 148
ON PROGGRESS 44 17.96% 108 44.08% 43
Total 245 100.00% 245 22.04% 245
TOTAL = 64 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
4.90% 13 5.31%
23.67% 33 13.47% -25 66
2.04% 29 11.84% 24 5
98
10.20% 19 7.76%
19.59% 30 12.24% -18 66
10.20% 49 20.00% 24 25
72
6.94% 17 6.94%
17.14% 24 9.80% -18 50
5.31% 31 12.65% 18 13
22.04% 49 20.00%
60.41% 87 35.51% -61
17.55% 109 44.49%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 24 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 14 5.71% 13 5.31% 12
Closed 57 23.27% 33 13.47% -24 1 0 58
On Progress 4 1.63% 29 11.84% 25 1 0 5
BARATA 98 98 98
Open 29 11.84% 19 7.76% 26
Closed 45 18.37% 30 12.24% -15 2 0 47
On Progress 24 9.80% 49 20.00% 25 1 0 25
MULTINAS 72 72 72
Open 18 7.35% 19 7.76% 17
Closed 41 16.73% 24 9.80% -17 0 0 41
On Progress 13 5.31% 29 11.84% 16 1 1 14
TOTAL
OPEN 61 24.90% 51 20.82% 55
CLOSED 143 58.37% 87 35.51% -56 3 0 146
ON PROGGRESS 41 16.73% 107 43.67% 44
Total 245 100.00% 245 21.63% 245
TOTAL = 64 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
4.90% 13 5.31%
23.67% 33 13.47% -25 66
2.04% 29 11.84% 24 5
98
10.61% 19 7.76%
19.18% 30 12.24% -17 66
10.20% 49 20.00% 24 25
72
6.94% 18 7.35%
16.73% 24 9.80% -17 50
5.71% 30 12.24% 16 14
22.45% 50 20.41%
59.59% 87 35.51% -59
17.96% 108 44.08%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 24 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 14 5.71% 17 6.94% 14
Closed 55 22.45% 32 13.06% -23 2 1 57
On Progress 6 2.45% 26 10.61% 20 -2 3 4
BARATA 98 98 98
Open 29 11.84% 21 8.57% 29
Closed 45 18.37% 29 11.84% -16 0 1 45
On Progress 24 9.80% 48 19.59% 24 0 1 24
MULTINAS 72 72 72
Open 19 7.76% 19 7.76% 18
Closed 39 15.92% 24 9.80% -15 2 0 41
On Progress 14 5.71% 29 11.84% 15 -1 0 13
TOTAL
OPEN 62 25.31% 57 23.27% 61
CLOSED 139 56.73% 85 34.69% -54 4 2 143
ON PROGGRESS 44 17.96% 103 42.04% 41
Total 245 100.00% 245 21.63% 245
TOTAL = 64 Orang
PG
LAPANGAN = 135 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
5.71% 13 5.31%
23.27% 33 13.47% -24 66
1.63% 29 11.84% 25 4
98
11.84% 19 7.76%
18.37% 30 12.24% -15 66
9.80% 49 20.00% 25 24
72
7.35% 19 7.76%
16.73% 24 9.80% -17 50
5.31% 29 11.84% 16 13
24.90% 51 20.82%
58.37% 87 35.51% -56
16.73% 107 43.67%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 23 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 14 5.71% 17 6.94% 14
Closed 54 22.04% 30 12.24% -24 1 2 55
On Progress 7 2.86% 28 11.43% 21 -1 -2 6
BARATA 98 98 98
Open 29 11.84% 22 8.98% 29
Closed 45 18.37% 28 11.43% -17 0 1 45
On Progress 24 9.80% 48 19.59% 24 0 0 24
MULTINAS 72 72 72
Open 19 7.76% 21 8.57% 19
Closed 37 15.10% 23 9.39% -14 2 1 39
On Progress 16 6.53% 28 11.43% 12 -2 1 14
TOTAL
OPEN 62 25.31% 60 24.49% 62
CLOSED 136 55.51% 81 33.06% -55 3 4 139
ON PROGGRESS 47 19.18% 104 42.45% 44
Total 245 100.00% 245 20.82% 245
TOTAL = 59 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
5.71% 17 6.94%
22.45% 32 13.06% -23 66
2.45% 26 10.61% 20 6
98
11.84% 21 8.57%
18.37% 29 11.84% -16 66
9.80% 48 19.59% 24 24
72
7.76% 19 7.76%
15.92% 24 9.80% -15 50
5.71% 29 11.84% 15 14
25.31% 57 23.27%
56.73% 85 34.69% -54
17.96% 103 42.04%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 22 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 14 5.71% 20 8.16% 14
Closed 50 20.41% 28 11.43% -22 4 2 54
On Progress 11 4.49% 27 11.02% 16 -4 1 7
BARATA 98 98 98
Open 30 12.24% 24 9.80% 29
Closed 43 17.55% 27 11.02% -16 2 1 45
On Progress 25 10.20% 47 19.18% 22 -1 1 24
MULTINAS 72 72 72
Open 20 8.16% 21 8.57% 19
Closed 34 13.88% 23 9.39% -11 3 0 37
On Progress 18 7.35% 28 11.43% 10 -2 0 16
TOTAL
OPEN 64 26.12% 65 26.53% 62
CLOSED 127 51.84% 78 31.84% -49 9 3 136
ON PROGGRESS 54 22.04% 102 41.63% 47
Total 245 100.00% 245 20.82% 245
TOTAL = 59 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
5.71% 17 6.94%
22.04% 30 12.24% -24 66
2.86% 28 11.43% 21 7
98
11.84% 22 8.98%
18.37% 28 11.43% -17 66
9.80% 48 19.59% 24 24
72
7.76% 21 8.57%
15.10% 23 9.39% -14 50
6.53% 28 11.43% 12 16
25.31% 60 24.49%
55.51% 81 33.06% -55
19.18% 104 42.45%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 21 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 15 6.12% 20 8.16% 14
Closed 50 20.41% 27 11.02% -23 0 1 50
On Progress 10 4.08% 28 11.43% 18 1 -1 11
BARATA 98 98 98
Open 31 12.65% 24 9.80% 30
Closed 42 17.14% 27 11.02% -15 1 0 43
On Progress 25 10.20% 47 19.18% 22 0 0 25
MULTINAS 72 72 72
Open 20 8.16% 21 8.57% 20
Closed 34 13.88% 23 9.39% -11 0 0 34
On Progress 18 7.35% 28 11.43% 10 0 0 18
TOTAL
OPEN 66 26.94% 65 26.53% 64
CLOSED 126 51.43% 77 31.43% -49 1 1 127
ON PROGGRESS 53 21.63% 103 42.04% 54
Total 245 100.00% 245 20.82% 245
TOTAL = 59 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
5.71% 20 8.16%
20.41% 28 11.43% -22 66
4.49% 27 11.02% 16 11
98
12.24% 24 9.80%
17.55% 27 11.02% -16 66
10.20% 47 19.18% 22 25
72
8.16% 21 8.57%
13.88% 23 9.39% -11 50
7.35% 28 11.43% 10 18
26.12% 65 26.53%
51.84% 78 31.84% -49
22.04% 102 41.63%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 20 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 15 6.12% 21 8.57% 15
Closed 47 19.18% 24 9.80% -23 3 3 50
On Progress 13 5.31% 30 12.24% 17 -3 -2 10
BARATA 98 98 98
Open 31 12.65% 25 10.20% 31
Closed 36 14.69% 25 10.20% -11 6 2 42
On Progress 31 12.65% 48 19.59% 17 -6 -1 25
MULTINAS 72 72 72
Open 21 8.57% 22 8.98% 20
Closed 32 13.06% 22 8.98% -10 2 1 34
On Progress 19 7.76% 28 11.43% 9 -1 0 18
TOTAL
OPEN 67 27.35% 68 27.76% 66
CLOSED 115 46.94% 71 28.98% -44 11 6 126
ON PROGGRESS 63 25.71% 106 43.27% 53
Total 245 100.00% 245 20.41% 245
TOTAL = 56 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
6.12% 20 8.16%
20.41% 27 11.02% -23 66
4.08% 28 11.43% 18 10
98
12.65% 24 9.80%
17.14% 27 11.02% -15 66
10.20% 47 19.18% 22 25
72
8.16% 21 8.57%
13.88% 23 9.39% -11 50
7.35% 28 11.43% 10 18
26.94% 65 26.53%
51.43% 77 31.43% -49
21.63% 103 42.04%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 19 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 16 6.53% 23 9.39% 15
Closed 45 18.37% 24 9.80% -21 2 0 47
On Progress 14 5.71% 28 11.43% 14 -1 2 13
BARATA 98 98 98
Open 33 13.47% 33 13.47% 31
Closed 36 14.69% 25 10.20% -11 0 0 36
On Progress 29 11.84% 40 16.33% 11 2 8 31
MULTINAS 72 72 72
Open 21 8.57% 23 9.39% 21
Closed 31 12.65% 22 8.98% -9 1 0 32
On Progress 20 8.16% 27 11.02% 7 -1 1 19
TOTAL
OPEN 70 28.57% 79 32.24% 67
CLOSED 112 45.71% 71 28.98% -41 3 0 115
ON PROGGRESS 63 25.71% 95 38.78% 63
Total 245 100.00% 245 20.00% 245
TOTAL = 56 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
6.12% 21 8.57%
19.18% 24 9.80% -23 66
5.31% 30 12.24% 17 13
98
12.65% 25 10.20%
14.69% 25 10.20% -11 66
12.65% 48 19.59% 17 31
72
8.57% 22 8.98%
13.06% 22 8.98% -10 50
7.76% 28 11.43% 9 19
27.35% 68 27.76%
46.94% 71 28.98% -44
25.71% 106 43.27%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 18 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 16 6.53% 23 9.39% 16
Closed 44 17.96% 24 9.80% -20 1 0 45
On Progress 15 6.12% 28 11.43% 13 -1 0 14
BARATA 98 98 98
Open 33 13.47% 39 15.92% 33
Closed 33 13.47% 23 9.39% -10 3 2 36
On Progress 32 13.06% 36 14.69% 4 -3 4 29
MULTINAS 72 72 72
Open 21 8.57% 26 10.61% 21
Closed 30 12.24% 21 8.57% -9 1 1 31
On Progress 21 8.57% 25 10.20% 4 -1 2 20
TOTAL
OPEN 70 28.57% 88 35.92% 70
CLOSED 107 43.67% 68 27.76% -39 5 3 112
ON PROGGRESS 68 27.76% 89 36.33% 63
Total 245 100.00% 245 18.78% 245
TOTAL = 56 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
6.53% 23 9.39%
18.37% 24 9.80% -21 66
5.71% 28 11.43% 14 14
98
13.47% 33 13.47%
14.69% 25 10.20% -11 66
11.84% 40 16.33% 11 29
72
8.57% 23 9.39%
12.65% 22 8.98% -9 50
8.16% 27 11.02% 7 20
28.57% 79 32.24%
45.71% 71 28.98% -41
25.71% 95 38.78%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 17 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 16 6.53% 24 9.80% 16
Closed 41 16.73% 22 8.98% -19 3 2 44
On Progress 18 7.35% 29 11.84% 11 -3 -1 15
BARATA 98 98 98
Open 34 13.88% 41 16.73% 33
Closed 33 13.47% 23 9.39% -10 0 0 33
On Progress 31 12.65% 34 13.88% 3 1 2 32
MULTINAS 72 72 72
Open 21 8.57% 30 12.24% 21
Closed 27 11.02% 20 8.16% -7 3 1 30
On Progress 24 9.80% 22 8.98% -2 -3 3 21
TOTAL
OPEN 71 28.98% 95 38.78% 70
CLOSED 101 41.22% 65 26.53% -36 6 3 107
ON PROGGRESS 73 29.80% 85 34.69% 68
Total 245 100.00% 245 17.14% 245
TOTAL = 56 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
6.53% 23 9.39%
17.96% 24 9.80% -20 66
6.12% 28 11.43% 13 15
98
13.47% 39 15.92%
13.47% 23 9.39% -10 66
13.06% 36 14.69% 4 32
72
8.57% 26 10.61%
12.24% 21 8.57% -9 50
8.57% 25 10.20% 4 21
28.57% 88 35.92%
43.67% 68 27.76% -39
27.76% 89 36.33%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 16 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 16 6.53% 26 10.61% 16
Closed 38 15.51% 20 8.16% -18 3 2 41
On Progress 21 8.57% 29 11.84% 8 -3 0 18
BARATA 98 98 98
Open 34 13.88% 41 16.73% 34
Closed 31 12.65% 19 7.76% -12 2 4 33
On Progress 33 13.47% 38 15.51% 5 -2 -4 31
MULTINAS 72 72 72
Open 21 8.57% 30 12.24% 21
Closed 25 10.20% 20 8.16% -5 2 0 27
On Progress 26 10.61% 22 8.98% -4 -2 0 24
TOTAL
OPEN 71 28.98% 97 39.59% 71
CLOSED 94 38.37% 59 24.08% -35 7 6 101
ON PROGGRESS 80 32.65% 89 36.33% 73
Total 245 100.00% 245 17.14% 245
TOTAL = 56 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
6.53% 24 9.80%
16.73% 22 8.98% -19 66
7.35% 29 11.84% 11 18
98
13.88% 41 16.73%
13.47% 23 9.39% -10 66
12.65% 34 13.88% 3 31
72
8.57% 30 12.24%
11.02% 20 8.16% -7 50
9.80% 22 8.98% -2 24
28.98% 95 38.78%
41.22% 65 26.53% -36
29.80% 85 34.69%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 15 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 22 8.98% 28 11.43% 16
Closed 34 13.88% 18 7.35% -16 4 2 38
On Progress 19 7.76% 29 11.84% 10 2 0 21
BARATA 98 98 98
Open 40 16.33% 42 17.14% 34
Closed 30 12.24% 16 6.53% -14 1 3 31
On Progress 28 11.43% 40 16.33% 12 5 -2 33
MULTINAS 72 72 72
Open 27 11.02% 31 12.65% 21
Closed 22 8.98% 20 8.16% -2 3 0 25
On Progress 23 9.39% 21 8.57% -2 3 1 26
TOTAL
OPEN 89 36.33% 101 41.22% 71
CLOSED 86 35.10% 54 22.04% -32 8 5 94
ON PROGGRESS 70 28.57% 90 36.73% 80
Total 245 100.00% 245 16.73% 245
TOTAL = 56 Orang
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75 Check
6.53% 26 10.61%
15.51% 20 8.16% -18 66
8.57% 29 11.84% 8 18
98
13.88% 41 16.73%
12.65% 19 7.76% -12 66
13.47% 38 15.51% 5 31
72
8.57% 30 12.24%
10.20% 20 8.16% -5 50
10.61% 22 8.98% -4 24
28.98% 97 39.59%
38.37% 59 24.08% -35
32.65% 89 36.33%
100.00% 245 100.00%
UPDATE SAMPAI DENGAN 14 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 23 9.39% 34 13.88% 22
Closed 33 13.47% 18 7.35% -15 1 0 34
On Progress 19 7.76% 23 9.39% 4 0 6 19
BARATA 98 98 98
Open 40 16.33% 42 17.14% 40
Closed 29 11.84% 15 6.12% -14 1 1 30
On Progress 29 11.84% 41 16.73% 12 -1 -1 28
MULTINAS 72 72 72
Open 30 12.24% 31 12.65% 27
Closed 22 8.98% 20 8.16% -2 0 0 22
On Progress 20 8.16% 21 8.57% 1 3 0 23
TOTAL
OPEN 93 37.96% 107 43.67% 89
CLOSED 84 34.29% 53 21.63% -31 2 1 86
ON PROGGRESS 68 27.76% 85 34.69% 70
Total 245 100.00% 245 16.73% 245
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75
8.98% 28 11.43% 37.3%
13.88% 18 7.35% -16 24.0%
7.76% 29 11.84% 10 38.7% 19
98
16.33% 42 17.14% 42.9%
12.24% 16 6.53% -14 16.3%
11.43% 40 16.33% 12 40.8% 28
72
11.02% 31 12.65% 43.1%
8.98% 20 8.16% -2 27.8%
9.39% 21 8.57% -2 29.2% 23
OPEN 101
CLOSED 54
ON PROGGRESS 90
245
UPDATE SAMPAI DENGAN 13 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 24 9.80% 39 15.92% 23
Closed 31 12.65% 15 6.12% -16 2 3 33
On Progress 20 8.16% 21 8.57% 1 -1 2 19
BARATA 98 98 98
Open 41 16.73% 42 17.14% 40
Closed 29 11.84% 15 6.12% -14 0 0 29
On Progress 28 11.43% 41 16.73% 13 1 0 29
MULTINAS 72 72 72
Open 31 12.65% 31 12.65% 30
Closed 19 7.76% 20 8.16% 1 3 0 22
On Progress 22 8.98% 21 8.57% -1 -2 0 20
TOTAL
OPEN 96 39.18% 112 45.71% 93
CLOSED 79 32.24% 50 20.41% -29 5 3 84
ON PROGGRESS 70 28.57% 83 33.88% 68
Total 245 100.00% 245 16.73% 245
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75
9.39% 34 13.88% 45.3%
13.47% 18 7.35% -15 24.0%
7.76% 23 9.39% 4 30.7% 19
98
16.33% 42 17.14% 42.9%
11.84% 15 6.12% -14 15.3%
11.84% 41 16.73% 12 41.8% 29
72
12.24% 31 12.65% 43.1%
8.98% 20 8.16% -2 27.8%
8.16% 21 8.57% 1 29.2% 20
OPEN 107
CLOSED 53
ON PROGGRESS 85
245
UPDATE SAMPAI DENGAN 12 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 27 11.02% 39 15.92% 24
Closed 30 12.24% 15 6.12% -15 1 0 31
On Progress 18 7.35% 21 8.57% 3 2 0 20
BARATA 98 98 98
Open 41 16.73% 42 17.14% 41
Closed 28 11.43% 15 6.12% -13 1 0 29
On Progress 29 11.84% 41 16.73% 12 -1 0 28
MULTINAS 72 72 72
Open 32 13.06% 31 12.65% 31
Closed 19 7.76% 20 8.16% 1 0 0 19
On Progress 21 8.57% 21 8.57% 0 1 0 22
TOTAL
OPEN 100 40.82% 112 45.71% 96
CLOSED 77 31.43% 50 20.41% -27 2 0 79
ON PROGGRESS 68 27.76% 83 33.88% 70
Total 245 100.00% 245 16.73% 245
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75
9.80% 39 15.92% 52.0%
12.65% 15 6.12% -16 20.0%
8.16% 21 8.57% 1 28.0% 20
98
16.73% 42 17.14% 42.9%
11.84% 15 6.12% -14 15.3%
11.43% 41 16.73% 13 41.8% 28
72
12.65% 31 12.65% 43.1%
7.76% 20 8.16% 1 27.8%
8.98% 21 8.57% -1 29.2% 22
OPEN 112
CLOSED 50
ON PROGGRESS 83
245
UPDATE SAMPAI DENGAN 11 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 28 11.43% 39 15.92% 27
Closed 26 10.61% 15 6.12% -11 4 0 30
On Progress 21 8.57% 21 8.57% 0 -3 0 18
BARATA 98 98 98
Open 42 17.14% 42 17.14% 41
Closed 27 11.02% 15 6.12% -12 1 0 28
On Progress 29 11.84% 41 16.73% 12 0 0 29
MULTINAS 72 72 72
Open 33 13.47% 31 12.65% 32
Closed 17 6.94% 20 8.16% 3 2 0 19
On Progress 22 8.98% 21 8.57% -1 -1 0 21
TOTAL
OPEN 103 42.04% 112 45.71% 100
CLOSED 70 28.57% 50 20.41% -20 7 0 77
ON PROGGRESS 72 29.39% 83 33.88% 68
Total 245 100.00% 245 16.73% 245
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75
11.02% 39 15.92% 52.0%
12.24% 15 6.12% -15 20.0%
7.35% 21 8.57% 3 28.0% 18
98
16.73% 42 17.14% 42.9%
11.43% 15 6.12% -13 15.3%
11.84% 41 16.73% 12 41.8% 29
72
13.06% 31 12.65% 43.1%
7.76% 20 8.16% 1 27.8%
8.57% 21 8.57% 0 29.2% 21
OPEN 112
CLOSED 50
ON PROGGRESS 83
245
UPDATE SAMPAI DENGAN 10 MARET 2021
DAETAIL PROGGRESS
KEMARIN HARI INI SAMPAI DEN
STATUS JUMLAH JUMLAH JUM
Ra % Ri % Deviasi Ra Ri Ra
KSO 75 75 75
Open 33 13.47% 40 16.33% 28
Closed 26 10.61% 14 5.71% -12 0 1 26
On Progress 16 6.53% 21 8.57% 5 5 0 21
BARATA 98 98 98
Open 42 17.14% 42 17.14% 42
Closed 24 9.80% 14 5.71% -10 3 1 27
On Progress 32 13.06% 42 17.14% 10 -3 -1 29
MULTINAS 72 72 72
Open 36 14.69% 31 12.65% 33
Closed 17 6.94% 20 8.16% 3 0 0 17
On Progress 19 7.76% 21 8.57% 2 3 0 22
TOTAL
OPEN 111 45.31% 113 46.12% 103
CLOSED 67 27.35% 48 19.59% -19 3 2 70
ON PROGGRESS 67 27.35% 84 34.29% 17 5 -1 72
Total 245 100.00% 245 16.73% 245
SAMPAI DENGAN HARI INI
JUMLAH
% Ri % Deviasi
75
11.43% 39 15.92% 52.0%
10.61% 15 6.12% -11 20.0%
8.57% 21 8.57% 0 28.0% 21
98
17.14% 42 17.14% 42.9%
11.02% 15 6.12% -12 15.3%
11.84% 41 16.73% 12 41.8% 29
72
13.47% 31 12.65% 43.1%
6.94% 20 8.16% 3 27.8%
8.98% 21 8.57% -1 29.2% 22
OPEN 112
CLOSED 50
ON PROGGRESS 83
245
Manpo
Biaya consumable Durasi wer Pelaksanaan
No Item Action Plan Start Finish (orang) PIC Status
(Hari)
KSO BRT MSI PG
CANE PREPARATION & MILL 1/20/2021 5/4/2021
1 Tippler Oil Flushing 3/1/2021 3/8/2021 7 Barata x Open
Pengecekan Filter 3/1/2021 3/8/2021 7 Barata x On Progress
Ganti chain coupling oil pump 3/1/2021 3/8/2021 7 Barata x On Progress
Ganti load cell dan indicator 2/25/2021 3/20/2021 23 Barata x Closed
2 Auxilary Carrier Pengecekan oli Barata x x On Progress
Pengecekan rantai 2/25/2021 2/25/2021 0 Barata x Closed
3 Main Cane Carrier Pengecekan oli 3/1/2021 3/8/2021 7 Barata x On Progress
3/1/2021 3/8/2021 7 Barata x x On Progress
Pengecekan rantai
Pemasangan gearbox 3/1/2021 3/8/2021 7 Barata x On Progress
4 Cane Knife Install Pisau 3/22/2021 3/25/2021 3 Barata x On Progress
Install Frame Block Bearing Rotor 3/2/2021 3/5/2021 3 Barata x Closed
Install electro motor 5/1/2021 5/4/2021 3 Barata x Open
6 Feeding Drum Pengecekan Starting device oil pump 3/2/2021 3/4/2021 2 Barata x Open
8 Shredded Belt Conveyor Install Belt 3/19/2021 3/29/2021 10 Barata x Open
2 Auxilary Carrier Pengecekan dan pengadaan bolt & nut Rp 17,000,000 2/26/2021 3/31/2021 33 Barata x x On Progress
Penggantian Bolt & Nut Pisau Rp 9,000,000 3/1/2021 3/21/2021 20 Barata x Open
5 Carding Drum Penambahan lapisan hard facing Rp 17,500,000 3/3/2021 3/10/2021 7 Barata x On Progress
Barata open
Teflon Hidraulic Aus + Cuil Rp 25,000,000
Seal oil gearbox Rp 4,000,000 Barata x Closed
Oil Gearbox Barata x Open
Rp 48,000,000
Selang pipa hiraulic Rp 2,000,000 Barata x Closed
10 IMC Perbaikan rake imc Rp 3,000,000 Barata x Closed
Penggantian Bolt & Nut Rp 5,000,000 3/1/2021 3/4/2021 3 Barata x Open
11 Rotary Screen Cleaning Rp 2,500,000 3/28/2021 3/30/2021 2 Multinas x Open
14 Penggantian bushing Rp 5,000,000 3/4/2021 3/11/2021 7 KSO x On Progress
Elevating Carrier
2 Top Cone Evaporator Evaporator Nomor 2 & 7 Rp 200,000,000 2/15/2021 3/15/2021 28 Barata x On Progress
4 Nozzle spray pond Cleaning spray nozzle 3/15/2021 4/4/2021 20 6 Barata x x Open
PUTERAN 1/20/2021 3/20/2021
4 TSK Afinasi Perbaikan panel Rp 350,000,000 1/20/2021 3/20/2021 59 3 Barata x x On Progress
10 Magma Mingler Perbaikan as mingler D2 Rp 10,000,000 Multinas x Closed
SUGAR HANDLING 1/20/2021 3/31/2021
1 SDC Perbaikan bottom plate Rp 5,000,000 3/8/2021 3/15/2021 7 4 Multinas x Open
3 Bucket Elevator Penurunan ketinggian Rp 200,000,000 1/20/2021 3/31/2021 70 6 Barata x On Progress
Penggantian bucket Rp 100,000,000 1/20/2021 3/31/2021 70 6 Barata x On Progress
UPLC Err:504 Err:504
BOILER 1/23/2021 4/9/2021
2 Dinding Boiler Perbaikan dinding dan roof boiler Rp 275,000,000 1/23/2021 3/4/2021 40 6 KSO x x Closed
Perbaikan Isolasi 2/28/2021 3/15/2021 15 6 KSO x On Progress
4 3/2/2021 3/5/2021 3 4 KSO x On Progress
Belt Conveyor Ash Perbaikan belt Rp 20,000,000
3/15/2021 3/17/2021 2 4 KSO x On Progress
Penggantian bearing Rp 50,000,000
Perbaikan Feeder drum Rp 5,000,000 3/19/2021 3/29/2021 10 4 KSO x x On Progress
7 Bagasse Belt Conveyor Perbaikan chute dan sambungan belt Rp 20,000,000 3/1/2021 3/29/2021 28 4 KSO x On Progress
10 BC 2 - Pengecekan dan perbaikan komponen rantai Rp 400,000,000 3/4/2021 3/19/2021 15 6 KSO x x On Progress
Rp 3,465,105,000
Manpower
Biaya consumable Pelaksanaan
No Item Action Plan (orang) PIC Status Keterangan Start Finish
KSO BRT MSI PG
CANE PREPARATION & MILL 1/20/2021 4/30/2021
1 Tippler Ganti oli Rp 14,400,000 Barata x On Progress Tunggu pengadaan oli by barata 3/1/2021 3/8/2021
- Menunggu Pengadaan bolt & nut Barata
2 Auxilary Carrier Pengecekan dan pengadaan bolt & nut Rp 17,000,000 Barata x x On Progress - Sudah dicheck perlu penggantian sebagian baut & nut uk Ø1/2 x 3 inch = 2000 bh 2/26/2021 3/31/2021
by barata
Regreasing Block Bearing Rp 5,250,000 Barata x On Progress 3/2/2021 3/5/2021
3 Barata x On Progress -barata,
Sudah dicheck perlu penggantian sebagian bolt & nut uk Ø1/2 x 2,5 mm = 1000 bh by
Pengadaan baut
3/1/2021 3/8/2021
Main Cane Carrier Ganti bolt & nut Rp 11,000,000
Regreasing Block Bearing Rp 5,250,000 Barata x On Progress 3/1/2021 3/8/2021
4 Cane Knife Fabrikasi Pisau Rp 150,000,000 Barata x Closed
Pengadaan bolt & nut by Barata ( proses pengadaan) m27 x 100 mm jumlah 180 pcs
Penggantian Bolt & Nut Pisau Rp 9,000,000 Barata x Open (High Tention) 3/1/2021 3/21/2021
32
- Proses pengelasan no 7
2 Top Cone Evaporator Evaporator Nomor 2 & 7 Rp 200,000,000 Barata x On Progress 2/15/2021 3/15/2021
- bahan dan ongkos kerja ( ganti plat ≠16mm)
Penggantian ring bearing dan oil seal gearbox Rp 10,000,000 Barata x On Progress
3 Main Cane Carrier Penggantian komponen rantai (Pin, Bushing, Roller) Rp 150,000,000 3/1/2021 3/8/2021 7 Barata Open
8 Shredded Belt Conveyor perbaikan disc break motor Rp 50,000,000 3/7/2021 3/9/2021 2 Barata x Open
9 Mill Perbaikan sensor level chute Rp 100,000,000 3/4/2021 3/11/2021 7 Multinas x x Open
10 IMC Inventarisasi & Penggantian Rantai 1796 Rp 95,000,000 3/25/2021 3/28/2021 3 Barata x On Progress
11 Rotary Screen Impeller + as + bearing pompa rusak Rp 10,000,000 2/25/2021 3/27/2021 30 Multinas x x On Progress
12 Pompa Gilingan Pengecekan dan Perbaikan Casing pompa nira 2/25/2021 3/27/2021 30 Multinas x x On Progress
gilingan 4 & 5 keropos Rp 150,000,000
13 Pipe & Fitting Gilingan Pipa nira gilingan bocor Rp 200,000,000 2/25/2021 3/17/2021 20 Multinas On Progress
Pipa dan valve imbibisi rusak dan keropos Rp 20,000,000 2/26/2021 3/4/2021 6 4 KSO x On Progress
14 3/25/2021 3/28/2021 3 KSO x x Open
Elevating Carrier Inventarisasi & Penggantian Rantai 1796 Rp 100,000,000
Rp 1,150,000,000
PEMURNIAN 3/2/2021 4/13/2021
1 Liquid liquid Heater Pemasangan deksel Rp - 3/12/2021 3/15/2021 3 5 Multinas x x Open
2 Clarified Juice Tank Perbaikan Level Transmitter 3/10/2021 3/20/2021 10 Multinas x On Progress
4 Surface Condensor Pemasangan deksel Rp - 3/2/2021 3/22/2021 20 5 Multinas x Open
5 Final Heater Pemasangan deksel Rp - 3/2/2021 3/22/2021 20 5 Multinas x Open
6 Pre Heater Pemasangan deksel Rp 35,000,000 3/2/2021 3/22/2021 20 5 Multinas x Open
7 Single Tray Clarifier Water Filling Rp - 3/3/2021 3/8/2021 5 4 Multinas x x Open
Pengecekan scraper Rp - 3/3/2021 3/8/2021 5 2 Multinas x x Open
10 Pompa Perbaikan Pompa Screw Phospat 3/14/2021 4/13/2021 30 2 Multinas x Open
Perbaikan Pompa Screw Floculant 3/14/2021 4/13/2021 30 2 Multinas x Open
Perbaikan Pompa Screw Mud 3/14/2021 4/13/2021 30 2 Multinas x Open
Perbaikan Pompa lime saccharate 3/14/2021 4/13/2021 30 2 Multinas x Open
11 Tangki phospat Perbaikan kebocoran tangki dan perpipaan 3/15/2021 3/20/2021 5 2 Barata x On Progress
12 Condensate Cooler Pengecekan & Perbaikan jalur air panas 3/15/2021 3/20/2021 5 Multinas x Open
15 Instrument Pengecekan dan kalibrasi Rp 20,000,000 3/14/2021 3/24/2021 10 Multinas x On Progress
Modifikasi head shaft Rp 15,000,000 Barata x Open - Proses pengadaan dan modifikasi ###
setelah dilakukan pengecekan, sensor level chute
9 Mill Perbaikan sensor level chute Rp 100,000,000 Multinas x x Open MSI berbeda sistem dg level chute barata dan tidak###
sesuai diaplikasikan untuk level chute
SUGAR HANDLING
2 Belt Conveyor Perbaikan sambungan wet sugar conveyor Rp 5,000,000 3 Barata x Open Menunggu vendor ###
Perbaikan sambungan dry sugar conveyor Rp 5,000,000 Barata x Open Menunggu vendor ###
UPLC
1 Pompa perbaikan pompa penangkap minyak Barata x x Open Menunggu tenaga ###
perbaikan pompa equalisasi Barata x x Open Menunggu tenaga ###
perbaikan pompa endapan Barata x x Open Menunggu tenaga ###
8
perbaikan pompa filtrat Rp 200,000,000 Barata x x Open Menunggu tenaga ###
perbaikan blower Barata x x Open Menunggu tenaga ###
2 Piping perbaikan dan perbaiakan pipa aerator Barata x x Open Menunggu tenaga ###
perbaikan dan penggantian sarana penyaring Barata x x Open Menunggu tenaga ###
BOILER
- Tunggu info Indomarin & thermax
1 Pressure Part Tube Konfirmasi Thermax KSO x Open ###
- hydro test
- Menunggu tenaga (Ketut)
- PCV-301 Boiler 1 feed back bermasalah
- FT-501 Boiler 2 masih belum bisa nol
- FI-302 Flow Ind Boiler 2 error
- FDF boiler 1 feed back bermasalah
- IDF Boiler 1 Feed back bermasalah
3 Instrument Konfirmasi Thermax KSO x On Progress - IDF boiler 2 feed back bermasalah ###
- FDF boiler 2 feed back bermasalah
- SAF boiler 2 feed back bermasalah
- CV PRDS respon lambat
10
3 Turbine 10 MW KSO x x On Progress Menunggu tenaga MAN ###
Konfirmasi terkait Annual Maintenance dengan MAN
Pengecekan stang governor 10 KSO x x Open Menunggu tenaga MAN ###
Pengecekan check valve KSO x x On Progress Menunggu tenaga MAN ###
4 Turbin 13 MW Pengecekan control valve PRDS KSO x x Open Menunggu tenaga MAN ###
6 Pin trip coil cubical excess Pengadaan pin trip Rp 50,000,000 KSO x x On Progress tunggu pengadaan needle roller bearing NK6/12TV###
power
COMPRESSOR
Oil Penggantian selenoid valve compressor mark Rp 20,000,000 2 KSO x x Open ###
Perbaikan compressor torak Rp 15,000,000 KSO x x Open ###
COOLING TOWER
2 Cleaning Pembersihan filler dan pond Rp 5,000,000 KSO x x Open - Cleaning chemicalia ###
DIESEL ENGINE GENERATOR
1
3 Oli Pengecekan filter solar dan oli Rp 5,000,000 KSO x x Open ###
ELECTRICAL
2 Control Room Pengecekan dan perbaikan kebocoran Rp 220,000,000 MSI/BRT x x Open
GENERAL
1 Atap Supergravity Pengecekan dan perbaikan Rp 100,000,000 Barata x Open - Penggantian seng atap
- Perbaikan sarana inhouse keeping untuk
2 Inhouse keeping Pengecekan dan perbaikan Rp 250,000,000 KSO x Open mencegah ceceran gula bercampur dengan saluran###
limbah