Anda di halaman 1dari 1

LAMPIRAN

DAFTAR KUANTITAS DAN HARGA


PEKERJAAN : PEKERJAAN PONDASI IPA KAP. 10 L/DT = 1 UNIT
LOKASI : IPA AMUNTAI SELATAN
PROPINSI : KALIMANTAN SELATAN

HARGA
NO. URAIAN PEKERJAAN ANALISA VOLUME SATUAN SATUAN JUMLAH
Rp Rp
1 2 3 4 5 6 7

I PEKERJAAN TANAH DAN PASIR


1 Galian tanah 8 14.69 m3 56,000.00 822,528.00
2 Urugan tanah kembali 11 4.89 m3 26,850.00 131,296.50
3 Urugan pasir 12 2.18 m3 279,000.00 607,104.00

II PEKERJAAN PANCANGAN
1 Pengadaan kayu galam Ø 10-12 cm -47 m - 195.00 Btg 14,820.00 2,889,900.00
2 Pek. Pancangan kayu galam Ø 10-12 cm - 4 m - 195.00 Btg 25,000.00 4,875,000.00

III PEKERJAAN BETON


1 Pek. Beton lantai kerja dan rabat beton campuran 1:3:5 30 2.62 m3 1,200,500.00 3,145,310.00
2 Poer 120x120x30
a. Beton Campuran 1 : 2 : 3 31 4.32 M3 1,486,870.00 6,423,278.40
b. Tulangan Besi 12 35 319.32 Kg 20,427.50 6,522,909.30
c. Bekisting 39 14.40 M2 221,070.00 3,183,408.00
2 Neut 40x40
a. Beton Campuran 1 : 2 : 3 31 1.60 M3 1,486,870.00 2,378,992.00
b. Tulangan Besi 12 35 220.10 Kg 20,427.50 4,496,164.25
c. Bekisting 41 16.00 M2 341,150.00 5,458,400.00
3 Sloof 30x30
a. Beton Campuran 1 : 2 : 3 31 3.42 M3 1,486,870.00 5,085,095.40
b. Tulangan Besi 12 35 374.28 Kg 20,427.50 7,645,691.52
c. Bekisting 40 34.20 M2 233,570.00 7,988,094.00
3 Pekerjaan Pondasi Batu Kali,camp 1 : 4 19 13.65 m3 1,148,530.00 15,677,434.50
4 Pek. Plesteran campuran 1 : 4 tebal 10 cm 46 17.68 m2 66,962.00 1,183,888.16

JUMLAH 78,514,494.02
DIBULATKAN 78,514,000.00