REKAPITULASI
PENYEDIAAN SARANA MAUPUN PRASARANA KLASTER INDUSTRI
KABUPATEN PINRANG TAHUN ANGGARAN 2016
SUKARMAN
Direktur
RENCANA ANGGARAN BIAYA (RAB)
PENYEDIAAN SARANA MAUPUN PRASARANA KLASTER INDUSTRI
KABUPATEN PINRANG TAHUN ANGGARAN 2016
Jumlah 1,712,144.41
IV PEKERJAAN DINDING DAN LANTAI
1 Timb. Tanah Bawah Lantai 2.930 m3 98,587.50 288,812.08
2 Timb. Pasir Bawah Lantai Tebal 5 cm 1.953 m3 138,435.00 270,363.56
3 Pekerjaan Rabat Beton Bwh Lantai = 5 cm
Cor Beton 0.977 m3 662,683.78 647,110.72
4 Pas. Dinding 1Pc : 4 Ps 35.353 m 2
113,802.26 4,023,251.30
5 Plesteran Dinding 1Pc : 4 Ps 70.706 m2 61,194.01 4,326,783.81
6 Roster 3.000 bh 15,000.00 45,000.00
Jumlah 9,601,321.46
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu & Jendela Klas II (Lokal) 0.079 m3 7,693,290.00 608,154.57
2 Daun Jendela Ungkit Klas II 0.483 m2 492,426.00 237,940.24
3 Daun Pintu Panel Kayu Klas II (Lokal) 1.320 m 2
658,845.00 869,675.40
4 Kaca Bening 5 mm 1.134 m2 155,093.40 175,875.92
5 Kunci Tanam Biasa 1.000 bh 140,112.50 140,112.50
6 Grendel 2.000 bh 29,858.40 59,716.80
7 Engsel Pintu 1.000 bh 43,718.40 43,718.40
8 Engsel Jendela 2.000 bh 33,376.75 66,753.50
9 Hak Angin 2.000 bh 37,943.40 75,886.80
Jumlah 2,277,834.13
VI PEKERJAAN PENGECATAN
1 Cat Tembok 70.706 m2 19,760.07 1,397,155.51
2 Cat Kayu Kusen, Pintu & Jendela 3.236 m2 42,315.90 136,951.18
Jumlah 1,534,106.69
VII PEKERJAAN PEMBERSIHAN 1.000 LS 200,000.00 200,000.00
Jumlah 200,000.00
JUMLAH ( I + II + III + IV + V + VI + VII ) 20,220,497.27
RENCANA ANGGARAN BIAYA (RAB)
PENYEDIAAN SARANA MAUPUN PRASARANA KLASTER INDUSTRI
KABUPATEN PINRANG TAHUN ANGGARAN 2016
Jumlah 1,674,102.96
IV PEKERJAAN DINDING DAN LANTAI
1 Timb. Tanah Bawah Lantai 2.567 m3 98,587.50 253,024.82
2 Timb. Pasir Bawah Lantai Tebal 5 cm 1.711 m3 138,435.00 236,862.29
3 Pekerjaan Rabat Beton Bwh Lantai = 5 cm
Cor Beton 0.856 m3 662,683.78 566,925.98
4 Pas. Dinding 1Pc : 4 Ps 34.153 m2 113,802.26 3,886,688.59
5 Plesteran Dinding 1Pc : 4 Ps 68.306 m2 61,194.01 4,179,918.18
6 Roster 3.000 bh 15,000.00 45,000.00
Jumlah 9,168,419.85
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu & Jendela Klas II (Lokal) 0.079 m3 7,693,290.00 608,154.57
2 Daun Jendela Ungkit Klas II 0.483 m 2
492,426.00 237,940.24
3 Daun Pintu Panel Kayu Klas II (Lokal) 1.320 m2 658,845.00 869,675.40
4 Kaca Bening 5 mm 1.134 m 2
155,093.40 175,875.92
5 Kunci Tanam Biasa 1.000 bh 140,112.50 140,112.50
6 Grendel 2.000 bh 29,858.40 59,716.80
7 Engsel Pintu 1.000 bh 43,718.40 43,718.40
8 Engsel Jendela 2.000 bh 33,376.75 66,753.50
9 Hak Angin 2.000 bh 37,943.40 75,886.80
Jumlah 2,277,834.13
VI PEKERJAAN PENGECATAN
1 Cat Tembok 68.306 m2 19,760.07 1,349,731.34
2 Cat Kayu Kusen, Pintu & Jendela 3.236 m2 42,315.90 136,951.18
Jumlah 1,486,682.52
VII PEKERJAAN PEMBERSIHAN 1.000 LS 200,000.00 200,000.00
Jumlah 200,000.00
JUMLAH ( I + II + III + IV + V + VI + VII ) 19,164,783.47
RENCANA ANGGARAN BIAYA (RAB)
PENYEDIAAN SARANA MAUPUN PRASARANA KLASTER INDUSTRI
KABUPATEN PINRANG TAHUN ANGGARAN 2016
Jumlah 1,614,449.85
IV PEKERJAAN DINDING DAN LANTAI
1 Timb. Tanah Bawah Lantai 2.930 m3 98,587.50 288,812.08
2 Timb. Pasir Bawah Lantai Tebal 5 cm 1.953 m 3
138,435.00 270,363.56
3 Pekerjaan Rabat Beton Bwh Lantai = 5 cm
Cor Beton 0.977 m3 662,683.78 647,110.72
4 Pas. Dinding 1Pc : 4 Ps 36.953 m2 113,802.26 4,205,334.91
5 Plesteran Dinding 1Pc : 4 Ps 73.906 m2 61,194.01 4,522,604.65
6 Roster 3.000 bh 15,000.00 45,000.00
Jumlah 9,979,225.92
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu & Jendela Klas II (Lokal) 0.079 m3 7,693,290.00 608,154.57
2 Daun Jendela Ungkit Klas II 0.483 m 2
492,426.00 237,940.24
3 Daun Pintu Panel Kayu Klas II (Lokal) 1.320 m2 658,845.00 869,675.40
4 Kaca Bening 5 mm 1.134 m 2
155,093.40 175,875.92
5 Kunci Tanam Biasa 1.000 bh 140,112.50 140,112.50
6 Grendel 2.000 bh 29,858.40 59,716.80
7 Engsel Pintu 1.000 bh 43,718.40 43,718.40
8 Engsel Jendela 2.000 bh 33,376.75 66,753.50
9 Hak Angin 2.000 bh 37,943.40 75,886.80
Jumlah 2,277,834.13
VI PEKERJAAN PENGECATAN
1 Cat Tembok 46.706 m2 19,760.07 922,913.83
2 Cat Kayu Kusen, Pintu & Jendela 3.236 m2 42,315.90 136,951.18
Jumlah 1,059,865.01
VII PEKERJAAN PEMBERSIHAN 1.000 LS 200,000.00 200,000.00
Jumlah 200,000.00
JUMLAH ( I + II + III + IV + V + VI + VII ) 19,809,594.27
RENCANA ANGGARAN BIAYA (RAB)
PENYEDIAAN SARANA MAUPUN PRASARANA KLASTER INDUSTRI
KABUPATEN PINRANG TAHUN ANGGARAN 2016
Jumlah 1,661,422.48
IV PEKERJAAN DINDING DAN LANTAI
1 Timb. Tanah Bawah Lantai 2.651 m3 98,587.50 261,306.17
2 Timb. Pasir Bawah Lantai Tebal 5 cm 1.767 m3 138,435.00 244,614.65
3 Pekerjaan Rabat Beton Bwh Lantai = 5 cm
Cor Beton 0.884 m3 662,683.78 585,481.12
4 Pas. Dinding 1Pc : 4 Ps 33.753 m2 113,802.26 3,841,167.68
5 Plesteran Dinding 1Pc : 4 Ps 67.506 m2 61,194.01 4,130,962.97
6 Roster 3.000 bh 15,000.00 45,000.00
Jumlah 9,108,532.59
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu & Jendela Klas II (Lokal) 0.079 m3 7,693,290.00 608,154.57
2 Daun Jendela Ungkit Klas II 0.483 m 2
492,426.00 237,940.24
3 Daun Pintu Panel Kayu Klas II (Lokal) 1.320 m2 658,845.00 869,675.40
4 Kaca Bening 5 mm 1.134 m 2
155,093.40 175,875.92
5 Kunci Tanam Biasa 1.000 bh 140,112.50 140,112.50
6 Grendel 2.000 bh 29,858.40 59,716.80
7 Engsel Pintu 1.000 bh 43,718.40 43,718.40
8 Engsel Jendela 2.000 bh 33,376.75 66,753.50
9 Hak Angin 2.000 bh 37,943.40 75,886.80
Jumlah 2,277,834.13
VI PEKERJAAN PENGECATAN
1 Cat Tembok 67.506 m2 19,760.07 1,333,923.29
2 Cat Kayu Kusen, Pintu & Jendela 3.236 m2 42,315.90 136,951.18
Jumlah 1,470,874.46
VII PEKERJAAN PEMBERSIHAN 1.000 LS 200,000.00 200,000.00
Jumlah 200,000.00
JUMLAH ( I + II + III + IV + V + VI + VII ) 19,030,625.48
RENCANA ANGGARAN BIAYA (RAB)
PENYEDIAAN SARANA MAUPUN PRASARANA KLASTER INDUSTRI
KABUPATEN PINRANG TAHUN ANGGARAN 2016
Jumlah 1,618,888.02
IV PEKERJAAN DINDING DAN LANTAI
1 Timb. Tanah Bawah Lantai 2.993 m3 98,587.50 295,023.09
2 Timb. Pasir Bawah Lantai Tebal 5 cm 1.995 m3 138,435.00 276,177.83
3 Pekerjaan Rabat Beton Bwh Lantai = 5 cm
Cor Beton 0.998 m3 662,683.78 661,027.08
4 Pas. Dinding 1Pc : 4 Ps 36.853 m2 113,802.26 4,193,954.69
5 Plesteran Dinding 1Pc : 4 Ps 73.706 m2 61,194.01 4,510,365.85
6 Roster 3.000 bh 15,000.00 45,000.00
Jumlah 9,981,548.53
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu & Jendela Klas II (Lokal) 0.079 m3 7,693,290.00 608,154.57
2 Daun Jendela Ungkit Klas II 0.483 m 2
492,426.00 237,940.24
3 Daun Pintu Panel Kayu Klas II (Lokal) 1.320 m2 658,845.00 869,675.40
4 Kaca Bening 5 mm 1.134 m 2
155,093.40 175,875.92
5 Kunci Tanam Biasa 1.000 bh 140,112.50 140,112.50
6 Grendel 2.000 bh 29,858.40 59,716.80
7 Engsel Pintu 1.000 bh 43,718.40 43,718.40
8 Engsel Jendela 2.000 bh 33,376.75 66,753.50
9 Hak Angin 2.000 bh 37,943.40 75,886.80
Jumlah 2,277,834.13
VI PEKERJAAN PENGECATAN
1 Cat Tembok 73.706 m2 19,760.07 1,456,435.72
2 Cat Kayu Kusen, Pintu & Jendela 3.236 m2 42,315.90 136,951.18
Jumlah 1,593,386.90
VII PEKERJAAN PEMBERSIHAN 1.000 LS 200,000.00 200,000.00
Jumlah 200,000.00
JUMLAH ( I + II + III + IV + V + VI + VII ) 20,258,312.56
RENCANA ANGGARAN BIAYA (RAB)
PENYEDIAAN SARANA MAUPUN PRASARANA KLASTER INDUSTRI
KABUPATEN PINRANG TAHUN ANGGARAN 2016
Jumlah 1,555,485.61
IV PEKERJAAN DINDING DAN LANTAI
1 Timb. Tanah Bawah Lantai 2.565 m3 98,587.50 252,876.94
2 Timb. Pasir Bawah Lantai Tebal 5 cm 1.711 m3 138,435.00 236,862.29
3 Pekerjaan Rabat Beton Bwh Lantai = 5 cm
Cor Beton 0.855 m3 662,683.78 566,594.64
4 Pas. Dinding 1Pc : 4 Ps 26.153 m2 113,802.26 2,976,270.51
5 Plesteran Dinding 1Pc : 4 Ps 52.306 m2 61,194.01 3,200,813.99
6 Pas. Tegel 40 x 40 cm 17.100 m2 131,027.77 2,240,574.78
7 Roster 3.000 bh 15,000.00 45,000.00
Jumlah 9,518,993.14
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu & Jendela Klas II (Lokal) 0.079 m3 7,693,290.00 608,154.57
2 Daun Jendela Ungkit Klas II 0.483 m2 492,426.00 237,940.24
3 Daun Pintu Panel Kayu Klas II (Lokal) 1.320 m 2
658,845.00 869,675.40
4 Kaca Bening 5 mm 1.134 m2 155,093.40 175,875.92
5 Kunci Tanam Biasa 1.000 bh 140,112.50 140,112.50
6 Grendel 2.000 bh 29,858.40 59,716.80
7 Engsel Pintu 1.000 bh 43,718.40 43,718.40
8 Engsel Jendela 2.000 bh 33,376.75 66,753.50
9 Hak Angin 2.000 bh 37,943.40 75,886.80
Jumlah 2,277,834.13
VI PEKERJAAN PENGECATAN
1 Cat Tembok 52.306 m2 19,760.07 1,033,570.22
2 Cat Kayu Kusen, Pintu & Jendela 3.236 m 2
42,315.90 136,951.18
Jumlah 1,170,521.40
VII PEKERJAAN PEMBERSIHAN 1.000 LS 200,000.00 200,000.00
Jumlah 200,000.00
JUMLAH ( I + II + III + IV + V + VI + VII ) 19,080,578.29
RENCANA ANGGARAN BIAYA (RAB)
PENYEDIAAN SARANA MAUPUN PRASARANA KLASTER INDUSTRI
KABUPATEN PINRANG TAHUN ANGGARAN 2016
Jumlah 1,699,463.92
IV PEKERJAAN DINDING DAN LANTAI
1 Timb. Tanah Bawah Lantai 4.019 m3 98,587.50 396,173.87
2 Timb. Pasir Bawah Lantai Tebal 5 cm 2.679 m3 138,435.00 370,867.37
3 Pekerjaan Rabat Beton Bwh Lantai = 5 cm
Cor Beton 1.340 m3 662,683.78 887,664.93
4 Pas. Dinding 1Pc : 4 Ps 34.953 m2 113,802.26 3,977,730.39
5 Plesteran Dinding 1Pc : 4 Ps 69.906 m2 61,194.01 4,277,828.60
6 Roster 3.000 bh 15,000.00 45,000.00
Jumlah 9,955,265.16
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu & Jendela Klas II (Lokal) 0.079 m3 7,693,290.00 608,154.57
2 Daun Jendela Ungkit Klas II 0.483 m 2
492,426.00 237,940.24
3 Daun Pintu Panel Kayu Klas II (Lokal) 1.320 m2 658,845.00 869,675.40
4 Kaca Bening 5 mm 1.134 m 2
155,093.40 175,875.92
5 Kunci Tanam Biasa 1.000 bh 140,112.50 140,112.50
6 Grendel 2.000 bh 29,858.40 59,716.80
7 Engsel Pintu 1.000 bh 43,718.40 43,718.40
8 Engsel Jendela 2.000 bh 33,376.75 66,753.50
9 Hak Angin 2.000 bh 37,943.40 75,886.80
Jumlah 2,277,834.13
VI PEKERJAAN PENGECATAN
1 Cat Tembok 69.906 m2 19,760.07 1,381,347.45
2 Cat Kayu Kusen, Pintu & Jendela 3.236 m2 42,315.90 136,951.18
Jumlah 1,518,298.63
VII PEKERJAAN PEMBERSIHAN 1.000 LS 200,000.00 200,000.00
Jumlah 200,000.00
JUMLAH ( I + II + III + IV + V + VI + VII ) 20,100,170.24
RENCANA ANGGARAN BIAYA (RAB)
PENYEDIAAN SARANA MAUPUN PRASARANA KLASTER INDUSTRI
KABUPATEN PINRANG TAHUN ANGGARAN 2016
Jumlah 1,441,361.27
IV PEKERJAAN DINDING DAN LANTAI
1 Timb. Tanah Bawah Lantai 2.066 m3 98,587.50 203,632.48
2 Timb. Pasir Bawah Lantai Tebal 5 cm 1.377 m3 138,435.00 190,625.00
3 Pekerjaan Rabat Beton Bwh Lantai = 5 cm
Cor Beton 0.689 m3 662,683.78 456,257.79
4 Pas. Dinding 1Pc : 4 Ps 30.553 m2 113,802.26 3,477,000.45
5 Plesteran Dinding 1Pc : 4 Ps 61.106 m2 61,194.01 3,739,321.30
6 Roster 3.000 bh 15,000.00 45,000.00
Jumlah 8,111,837.01
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu & Jendela Klas II (Lokal) 0.079 m3 7,693,290.00 608,154.57
2 Daun Jendela Ungkit Klas II 0.483 m 2
492,426.00 237,940.24
3 Daun Pintu Panel Kayu Klas II (Lokal) 1.320 m2 658,845.00 869,675.40
4 Kaca Bening 5 mm 1.134 m 2
155,093.40 175,875.92
5 Kunci Tanam Biasa 1.000 bh 140,112.50 140,112.50
6 Grendel 2.000 bh 29,858.40 59,716.80
7 Engsel Pintu 1.000 bh 43,718.40 43,718.40
8 Engsel Jendela 2.000 bh 33,376.75 66,753.50
9 Hak Angin 2.000 bh 37,943.40 75,886.80
Jumlah 2,277,834.13
VI PEKERJAAN PENGECATAN
1 Cat Tembok 61.106 m2 19,760.07 1,207,458.84
2 Cat Kayu Kusen, Pintu & Jendela 3.236 m2 42,315.90 136,951.18
Jumlah 1,344,410.02
VII PEKERJAAN PEMBERSIHAN 1.000 LS 200,000.00 200,000.00
Jumlah 200,000.00
JUMLAH ( I + II + III + IV + V + VI + VII ) 17,321,146.70
RENCANA ANGGARAN BIAYA (RAB)
PENYEDIAAN SARANA MAUPUN PRASARANA KLASTER INDUSTRI
KABUPATEN PINRANG TAHUN ANGGARAN 2016
Jumlah 1,352,597.90
IV PEKERJAAN DINDING DAN LANTAI
1 Timb. Tanah Bawah Lantai 1.887 m3 98,587.50 186,034.61
2 Timb. Pasir Bawah Lantai Tebal 5 cm 1.258 m3 138,435.00 174,151.23
3 Pekerjaan Rabat Beton Bwh Lantai = 5 cm
Cor Beton 0.629 m3 662,683.78 416,828.10
4 Pas. Dinding 1Pc : 4 Ps 27.753 m2 113,802.26 3,158,354.12
5 Plesteran Dinding 1Pc : 4 Ps 55.506 m2 61,194.01 3,396,634.83
6 Roster 3.000 bh 15,000.00 45,000.00
Jumlah 7,377,002.89
V PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu & Jendela Klas II (Lokal) 0.079 m3 7,693,290.00 608,154.57
2 Daun Jendela Ungkit Klas II 0.483 m 2
492,426.00 237,940.24
3 Daun Pintu Panel Kayu Klas II (Lokal) 1.320 m2 658,845.00 869,675.40
4 Kaca Bening 5 mm 1.134 m 2
155,093.40 175,875.92
5 Kunci Tanam Biasa 1.000 bh 140,112.50 140,112.50
6 Grendel 2.000 bh 29,858.40 59,716.80
7 Engsel Pintu 1.000 bh 43,718.40 43,718.40
8 Engsel Jendela 2.000 bh 33,376.75 66,753.50
9 Hak Angin 2.000 bh 37,943.40 75,886.80
Jumlah 2,277,834.13
VI PEKERJAAN PENGECATAN
1 Cat Tembok 55.506 m2 19,760.07 1,096,802.45
2 Cat Kayu Kusen, Pintu & Jendela 3.236 m2 42,315.90 136,951.18
Jumlah 1,233,753.62
VII PEKERJAAN PEMBERSIHAN 1.000 LS 200,000.00 200,000.00
Jumlah 200,000.00
JUMLAH ( I + II + III + IV + V + VI + VII ) 16,066,417.46
RENCANA ANGGARAN BIAYA (RAB)
PENYEDIAAN SARANA MAUPUN PRASARANA KLASTER INDUSTRI
KABUPATEN PINRANG TAHUN ANGGARAN 2016
Jumlah 8,275,108.50
III PEKERJAAN PENGECATAN
1 Cat Tembok 80.306 m2 19,760.07 1,586,852.18
Jumlah 1,586,852.18
IV PEKERJAAN PEMBERSIHAN 1.000 LS 150,000.00 150,000.00
Jumlah 150,000.00
JUMLAH ( I + II + III + IV ) 10,111,960.68
ANALISA HARGA SATUAN PEKERJAAN BERDASARKAN SNI 2013
A.4.6.1.1. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II
Bahan :
1.100 M3 Balok Kayu Klas II (lokal) @ Rp. 3,500,000.00 Rp. 3,850,000.00
1.250 Kg Paku 10 cm @ Rp. 15,000.00 Rp. 18,750.00
1.000 Kg Lem Kayu @ Rp. 35,000.00 Rp. 35,000.00
1 Rp. 3,903,750.00
Tenaga :
7.000 Oh Pekerja @ Rp. 90,000.00 Rp. 630,000.00
21.000 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 2,171,400.00
2.100 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 252,000.00
0.350 Oh Mandor @ Rp. 105,000.00 Rp. 36,750.00
2 3,090,150.00
JUMLAH C (1) + (2) Rp. 6,993,900.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 699,390.00
TOTAL C+D Rp. 7,693,290.00
A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas II
Bahan :
0.040 M3 Papan Kelas II (Lokal) @ Rp. 3,500,000.00 Rp. 140,000.00
0.500 Kg Lem Kayu @ Rp. 35,000.00 Rp. 17,500.00
1 Rp. 157,500.00
Tenaga :
1.000 Oh Pekerja @ Rp. 90,000.00 Rp. 90,000.00
3.000 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 310,200.00
0.300 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 36,000.00
0.050 Oh Mandor @ Rp. 105,000.00 Rp. 5,250.00
2 441,450.00
JUMLAH C (1) + (2) Rp. 598,950.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 59,895.00
TOTAL C+D Rp. 658,845.00
A.4.6.1.6. 1 M2 Pasang Daun jendela kaca kayu (KLS II)
Bahan :
0.024 M3 Papan Kelas II @ Rp. 3,500,000.00 Rp. 84,000.00
0.300 Kg Lem Kayu @ Rp. 35,000.00 Rp. 10,500.00
1 Rp. 94,500.00
Tenaga :
0.800 Oh Pekerja @ Rp. 90,000.00 Rp. 72,000.00
2.400 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 248,160.00
0.240 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 28,800.00
0.040 Oh Mandor @ Rp. 105,000.00 Rp. 4,200.00
2 353,160.00
JUMLAH C (1) + (2) Rp. 447,660.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 44,766.00
TOTAL C+D Rp. 492,426.00
A. A.4.1.1.5 Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Bahan :
326.000 kg Semen PC @ Rp. 1,188.00 Rp. 387,288.00
760.000 kg Pasir Beton @ Rp. 69.43 Rp. 52,765.71
1,029.000 kg Kerikil @ Rp. 116.67 Rp. 120,053.43
215.000 Ltr Air @ Rp. 50.00 10,750.00
1 570,857.14
Tenaga :
1.650 Oh Pekerja @ Rp. 90,000.00 Rp. 148,500.00
0.275 Oh Tukang Batu @ Rp. 103,400.00 Rp. 28,435.00
0.028 Oh Kepala Tuk. Batu @ Rp. 120,000.00 Rp. 3,360.00
0.083 Oh Mandor @ Rp. 105,000.00 Rp. 8,715.00
2 189,010.00
JUMLAH C (1) + (2) Rp. 759,867.14
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 75,986.71
TOTAL C+D Rp. 835,853.86
A.4.1.1.17 10 Kg Pekerjaan Besi Untuk Tulangan Beton
Bahan :
10.500 kg Besi Beton Polos @ Rp. 7,350.00 Rp. 77,175.00
0.150 kg Kawat Beton @ Rp. 15,750.00 Rp. 2,362.50
1 79,537.50
Tenaga :
0.070 Oh Pekerja @ Rp. 90,000.00 Rp. 6,300.00
0.070 Oh Tukang Besi @ Rp. 103,400.00 Rp. 7,238.00
0.0070 Oh Kepala Tukang @ Rp. 120,000.00 Rp. 840.00
0.0040 Oh Mandor @ Rp. 105,000.00 Rp. 420.00
2 14,798.00
JUMLAH a (1) + (2) Rp. 94,335.50
Untuk 1 Kg Pekerjaan Pembesian
JUMLAH C a/10 Rp. 9,433.55
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 943.36
TOTAL C+D Rp. 10,376.91
A.4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof
Bahan :
0.045 m3 Kayu Terentang Klas III @ Rp. 2,500,000.00 Rp. 112,500.00
0.300 kg Paku 5 - 10 cm @ Rp. 15,000.00 Rp. 4,500.00
0.100 Lt Minyak Bekisting @ Rp. 10,000.00 Rp. 1,000.00
1 118,000.00
Tenaga :
0.520 Oh Pekerja @ Rp. 90,000.00 Rp. 46,800.00
0.260 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 26,884.00
0.026 Oh Kepala Tukang Kayu @ Rp. 120,000.00 Rp. 3,120.00
0.026 Oh Mandor @ Rp. 105,000.00 Rp. 2,730.00
2 79,534.00
JUMLAH a (1) + (2) Rp. 197,534.00
2 x pakai C a/2 98,767.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 9,876.70
TOTAL C+D Rp. 108,643.70
A.4.1.1.22 Pemasangan 1 m2 bekisting untuk kolom
Bahan :
0.040 m3 Kayu Terentang Klas III @ Rp. 2,500,000.00 Rp. 100,000.00
0.400 kg Paku 2"-5" @ Rp. 15,000.00 Rp. 6,000.00
0.200 Lt Minyak Bekisting @ Rp. 10,000.00 Rp. 2,000.00
0.015 m3 Balok Kayu Klas III @ Rp. 2,500,000.00 Rp. 37,500.00
0.350 Lbr Triplex tebal 9 mm @ Rp. 110,250.00 Rp. 38,587.50
2.000 Btg Dolken Bambu/Kayu Ø 8-10 per 4m @ Rp. 30,000.00 Rp. 60,000.00
1 244,087.50
Tenaga :
0.660 Oh Pekerja @ Rp. 90,000.00 Rp. 59,400.00
0.330 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 34,122.00
0.033 Oh Kepala Tukang @ Rp. 120,000.00 Rp. 3,960.00
0.033 Oh Mandor @ Rp. 105,000.00 Rp. 3,465.00
2 100,947.00
JUMLAH a (1) + (2) Rp. 345,034.50
2 x pakai C a/2 172,517.25
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 17,251.73
TOTAL C+D Rp. 189,768.98
A.4.1.1.24 1 M2 Pasang Bekisting untuk Plat lantai/Deck
Bahan :
0.040 m3 Kayu Klas III @ Rp. 2,500,000.00 Rp. 100,000.00
0.400 kg Paku 5 - 12 cm @ Rp. 15,000.00 Rp. 6,000.00
0.200 Lt Minyak Bekisting @ Rp. 10,000.00 Rp. 2,000.00
0.015 m3 Balok Kayu Klas III @ Rp. 2,500,000.00 Rp. 37,500.00
0.350 Lbr Plywood T= 9 mm @ Rp. 110,250.00 Rp. 38,587.50
6.000 Btg Dolken Bambu @ Rp. 30,000.00 Rp. 180,000.00
1 364,087.50
Tenaga :
0.660 Oh Pekerja @ Rp. 90,000.00 Rp. 59,400.00
0.330 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 34,122.00
0.033 Oh Kepala Tukang @ Rp. 120,000.00 Rp. 3,960.00
0.033 Oh Mandor @ Rp. 105,000.00 Rp. 3,465.00
2 100,947.00
JUMLAH (1) + (2) Rp. 465,034.50
2 x pakai C a/2 232,517.25
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 23,251.73
TOTAL C+D Rp. 255,768.98
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP
Bahan :
0.700 lbr Seng Spandeck @ Rp. 57,750.00 Rp. 40,425.00
0.020 kg Paku Seng (Payung) RRT @ Rp. 31,000.00 Rp. 620.00
1 41,045.00
Tenaga :
0.120 Oh Pekerja @ Rp. 90,000.00 Rp. 10,800.00
0.060 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 6,204.00
0.006 Oh Kepala tukang Kayu @ Rp. 120,000.00 Rp. 720.00
0.006 Oh Mandor @ Rp. 105,000.00 Rp. 630.00
2 18,354.00
JUMLAH (1) + (2) Rp. 59,399.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 5,939.90
TOTAL C+D Rp. 65,338.90
A.4.5.2.25 1 m' Pasang Atap Nok Seng patent
Bahan :
1.200 lbr Nok Paten @ Rp. 29,400.00 Rp. 35,280.00
6.000 Bh Paku Skrup @ Rp. 200.00 Rp. 1,200.00
1 36,480.00
Tenaga :
0.084 Oh Pekerja @ Rp. 90,000.00 Rp. 7,560.00
0.125 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 12,925.00
0.013 Oh Kepala tukang Kayu @ Rp. 120,000.00 Rp. 1,560.00
0.040 Oh Mandor @ Rp. 105,000.00 Rp. 4,200.00
2 26,245.00
JUMLAH C (1) + (2) Rp. 62,725.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 6,272.50
TOTAL C+D Rp. 68,997.50
A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
A.4.2.1.21. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon
Bahan :
4.000 m Rangka metal Hollow 40.40.2 mm @ Rp. 6,500.00 Rp. 26,000.00
1.000 LS Assesoris (perkuatan, las dll) @ Rp. 26,000.00 Rp. 26,000.00
1 Rp. 52,000.00
Tenaga :
0.350 Oh Pekerja @ Rp. 90,000.00 Rp. 31,500.00
0.350 Oh Tukang kayu @ Rp. 103,400.00 Rp. 36,190.00
0.035 Oh Kepala Tukang Kayu @ Rp. 120,000.00 Rp. 4,200.00
0.018 Oh Mandor @ Rp. 105,000.00 Rp. 1,890.00
2 73,780.00
JUMLAH C (1) + (2) Rp. 125,780.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 12,578.00
TOTAL C+D Rp. 138,358.00
A.4.5.1 SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
Bahan :
1.050 m List Kayu Profil @ Rp. 5,000.00 Rp. 5,250.00
6.000 bh Paku skrup @ Rp. 200.00 Rp. 1,200.00
1 6,450.00
Tenaga :
0.050 Oh Pekerja @ Rp. 90,000.00 Rp. 4,500.00
0.050 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 5,170.00
0.005 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 600.00
0.003 Oh Mandor @ Rp. 105,000.00 Rp. 315.00
2 10,585.00
JUMLAH C (1) + (2) Rp. 17,035.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 1,703.50
TOTAL C+D Rp. 18,738.50
6.8R 1 M' List Profil Kalsi board
Bahan :
1.050 m List Profil Kalsi Board @ Rp. 16,000.00 Rp. 16,800.00
6.000 bh Paku skrup @ Rp. 200.00 Rp. 1,200.00
1 18,000.00
Tenaga :
0.060 Oh Pekerja @ Rp. 90,000.00 Rp. 5,400.00
0.060 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 6,204.00
0.006 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 720.00
0.0030 Oh Mandor @ Rp. 105,000.00 Rp. 315.00
2 12,639.00
JUMLAH (1) + (2) Rp. 30,639.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 3,063.90
TOTAL C+D Rp. 33,702.90
Bahan :
1.000 bh Floor Drain @ Rp. 15,000.00 Rp. 15,000.00
1 Rp. 15,000.00
Tenaga :
0.010 Oh Pekerja @ Rp. 90,000.00 Rp. 900.00
0.100 Oh Tukang Pipa @ Rp. 103,400.00 Rp. 10,340.00
0.010 Oh Kepala Tukang Pipa @ Rp. 120,000.00 Rp. 1,200.00
0.005 Oh Mandor @ Rp. 105,000.00 Rp. 525.00
2 12,965.00
JUMLAH C (1) + (2) Rp. 27,965.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 2,796.50
TOTAL C+D Rp. 30,761.50
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA
Bahan :
1.000 bh Kunci Tanam biasa @ Rp. 68,250.00 Rp. 68,250.00
1 Rp. 68,250.00
Tenaga :
0.010 Oh Pekerja @ Rp. 90,000.00 Rp. 900.00
0.500 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 51,700.00
0.050 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 6,000.00
0.0050 Oh Mandor @ Rp. 105,000.00 Rp. 525.00
2 59,125.00
JUMLAH C Rp. 127,375.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 12,737.50
TOTAL C+D Rp. 140,112.50
A.4.6.2.5. Pemasangan 1 buah engsel pintu
Bahan :
1.000 bh Engsel Pintu @ Rp. 21,000.00 Rp. 21,000.00
1 Rp. 21,000.00
Tenaga :
0.015 Oh Pekerja @ Rp. 90,000.00 Rp. 1,350.00
0.150 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 15,510.00
0.015 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 1,800.00
0.00080 Oh Mandor @ Rp. 105,000.00 Rp. 84.00
2 18,744.00
JUMLAH C (1) + (2) Rp. 39,744.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 3,974.40
TOTAL C+D Rp. 43,718.40
A.4.6.2.5. Pemasangan 1 buah Grendel
Bahan :
1.000 bh Grendel @ Rp. 8,400.00 Rp. 8,400.00
1 Rp. 8,400.00
Tenaga :
0.015 Oh Pekerja @ Rp. 90,000.00 Rp. 1,350.00
0.150 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 15,510.00
0.015 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 1,800.00
0.00080 Oh Mandor @ Rp. 105,000.00 Rp. 84.00
2 18,744.00
JUMLAH C (1) + (2) Rp. 27,144.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 2,714.40
TOTAL C+D Rp. 29,858.40
A.4.6.2.6. Pemasangan 1 buah engsel jendela
Bahan :
1.000 bh Engsel Jendela @ Rp. 17,850.00 17,850.00
1 Rp. 17,850.00
Tenaga :
0.010 Oh Pekerja @ Rp. 90,000.00 Rp. 900.00
0.100 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 10,340.00
0.010 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 1,200.00
0.00050 Oh Mandor @ Rp. 105,000.00 Rp. 52.50
2 12,492.50
JUMLAH C (1) + (2) Rp. 30,342.50
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 3,034.25
TOTAL C+D Rp. 33,376.75
A.4.6.2.9. Pemasangan 1 buah kait angin
Bahan :
1.000 Bh kait angin @ Rp. 15,750.00 Rp. 15,750.00
1 Rp. 15,750.00
Tenaga :
0.015 Oh Pekerja @ Rp. 90,000.00 Rp. 1,350.00
0.150 Oh Tukang @ Rp. 103,400.00 Rp. 15,510.00
0.015 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 1,800.00
0.00080 Oh Mandor @ Rp. 105,000.00 Rp. 84.00
2 18,744.00
JUMLAH (1) + (2) Rp. 34,494.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 3,449.40
TOTAL C+D Rp. 37,943.40
A.4.6.2.12. 1 Bh Pasang Pegangan Pintu/Door Holder
Bahan :
1.000 Bh Door Holder @ Rp. 70,000.00 Rp. 70,000.00
1 Rp. 70,000.00
Tenaga :
0.050 Oh Pekerja @ Rp. 90,000.00 Rp. 4,500.00
0.500 Oh Tukang Kayu @ Rp. 103,400.00 Rp. 51,700.00
0.050 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 6,000.00
0.0030 Oh Mandor @ Rp. 105,000.00 Rp. 315.00
2 62,515.00
JUMLAH C (1) + (2) Rp. 132,515.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 13,251.50
TOTAL C+D Rp. 145,766.50
A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm
Bahan :
1.100 m2 kaca bening 5 mm @ Rp. 110,000.00 Rp. 121,000.00
0.050 KG SEalant @ Rp. 25,000.00 Rp. 1,250.00
1 Rp. 122,250.00
Tenaga :
0.015 Oh Pekerja @ Rp. 90,000.00 Rp. 1,350.00
0.150 Oh Tukang @ Rp. 103,400.00 Rp. 15,510.00
0.015 Oh Kepala Tukang kayu @ Rp. 120,000.00 Rp. 1,800.00
0.00080 Oh Mandor @ Rp. 105,000.00 Rp. 84.00
2 18,744.00
JUMLAH C (1) + (2) Rp. 140,994.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 14,099.40
TOTAL C+D Rp. 155,093.40
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
A.4.4.3.11 1 m2 Pasang Lantai Tegel 40 x 40 cm
Bahan :
6.63 bh tegel 40 x 40 cm @ Rp. 6,825.00 Rp. 45,249.75
9.80 kg Semen PC @ Rp. 1,188.00 Rp. 11,642.40
0.045 m3 Pasir Pasangan @ Rp. 97,200.00 Rp. 4,374.00
1.300 kg Semen Warna @ Rp. 15,000.00 Rp. 19,500.00
1 80,766.15
Tenaga :
0.250 Oh Pekerja @ Rp. 90,000.00 Rp. 22,500.00
0.125 Oh Tukang Batu @ Rp. 103,400.00 Rp. 12,925.00
0.013 Oh Kepala Tukang Batu @ Rp. 120,000.00 Rp. 1,560.00
0.013 Oh Mandor @ Rp. 105,000.00 Rp. 1,365.00
2 Rp. 38,350.00
JUMLAH C (1) + (2) Rp. 119,116.15
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 11,911.62
TOTAL C+D Rp. 131,027.77
A.4.4.3.36 1 m2 Pasang Lantai Tegel Keramik 20 x 20 cm Warna
Bahan :
26.50 bh Tegel Keramik 20 x 20 cm @ Rp. 2,310.00 Rp. 61,215.00
10.40 kg Semen PC @ Rp. 1,188.00 Rp. 12,355.20
0.045 m3 Pasir Pasangan @ Rp. 97,200.00 Rp. 4,374.00
1.620 kg Semen Warna @ Rp. 15,000.00 Rp. 24,300.00
1 102,244.20
Tenaga :
0.700 Oh Pekerja @ Rp. 90,000.00 Rp. 63,000.00
0.350 Oh Tukang Batu @ Rp. 103,400.00 Rp. 36,190.00
0.035 Oh Kepala Tukang Batu @ Rp. 120,000.00 Rp. 4,200.00
0.035 Oh Mandor @ Rp. 105,000.00 Rp. 3,675.00
2 Rp. 107,065.00
JUMLAH C (1) + (2) Rp. 209,309.20
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 20,930.92
TOTAL C+D Rp. 230,240.12
A.4.4.3.54 1 m2 Pasang Dinding Tegel Keramik 20 x 20 cm Warna
Bahan :
26.50 bh Tegel Keramik 20 x 20 cm @ Rp. 2,310.00 Rp. 61,215.00
9.30 kg Semen PC @ Rp. 1,188.00 Rp. 11,048.40
0.018 m3 Pasir Pasangan @ Rp. 97,200.00 Rp. 1,749.60
1.940 kg Semen Warna @ Rp. 15,000.00 Rp. 29,100.00
1 103,113.00
Tenaga :
0.900 org/hr Pekerja @ Rp. 90,000.00 Rp. 81,000.00
0.450 org/hr Tukang Batu @ Rp. 103,400.00 Rp. 46,530.00
0.045 org/hr Kepala Tukang Batu @ Rp. 120,000.00 Rp. 5,400.00
0.045 org/hr Mandor @ Rp. 105,000.00 Rp. 4,725.00
2 Rp. 137,655.00
JUMLAH C (1) + (2) Rp. 240,768.00
Overhead & Keuntungan (10% ) x C )……………….. D Rp. 24,076.80
TOTAL C+D Rp. 264,844.80
1 2 4 5
A HARGA SATUAN BAHAN
I BAHAN DASAR
1 Pasir Urug M3 81,500.00
2 Tanah Urug M3 50,000.00
3 Kerikil KG 116.67
4 Pasir Pasang M3 97,200.00
5 Pasir Pasang KG 69.43
6 Pasir Beton/Pasir Kasar KG 69.43
7 Air ltr 50.00
8 Batu Gunung M3 150,000.00
9 Batu Merah Bakar Besar Uk. Standard Bh 650.00
10 Semen PC Zak 59,400.00
11 Semen PC Kg 1,188.00
12 Semen Warna Kg 15,000.00
II BAHAN KAYU
1 Kayu Papan Kelas I (Lokal) M3 6,500,000.00
2 Kayu Balok Kelas I (Lokal) M3 6,500,000.00
3 Kayu Papan Mal Kelas II M3 3,500,000.00
4 Kayu Balok Mal Kelas II M3 3,500,000.00
5 Kayu Papan Mal Kelas III M3 2,500,000.00
6 Kayu Balok Mal Kelas III M3 2,500,000.00
7 Dolken Bambu/Kayu Ø 8-10 per 4m Btg 30,000.00
8 List Kayu 2X3 M1 5,000.00
III BAHAN ATAP
1 Atap Seng Gelombang BWG 33" BJLS ) 0,22 mm =6kk Lbr 57,750.00
2 Nok Seng patent Setara perkasa Lbr 29,400.00
IV BAHAN LANGIT-LANGIT & DINDING PARTISI
1 Tripleks 122 x 244 x 9 mm Lbr 110,250.00
2 Klasiboard Lbr 90,000.00
3 List profil Kalsi board M1 16,000.00
4 Hollow Uk. 40x 40 mm,tebal 2 mm m 6,500.00
V BAHAN LANTAI
1 Tegel keramik/ granit 40 x 40 cm bh 6,825.00
2 Tegel Keramik 20 x 20 cm Putih bh 2,310.00
VI BAHAN CAT
1 Cat Tembok Kg 23,100.00
2 Plamur tembok (skin coat) Kg 2,625.00
3 Plamur Kayu Kg 15,100.00
4 Cat Avian Kg 55,000.00
5 Cat Meni Kg 17,342.00
6 Lem Kayu Kg 35,000.00
7 Minyak Bekisting Ltr 10,000.00
8 Kuas bh 8,000.00
9 Pengencer kg 8,000.00
10 Amplas lbr 2,500.00
VII BAHAN BESI DAN ALUMINIUM
1 Besi Beton Polos Kg 7,350.00
2 Besi Strip 50.6 mm Kg 15,000.00
3 Kawat Beton Kg 15,750.00
4 Paku Skrup kg 31,000.00
5 Paku Skrup bh 200.00
6 Paku 1 cm s/d 4 cm kg 15,000.00
7 Paku 2"-5" Kg 15,000.00
8 Paku Payung Kg 15,000.00
VIII BAHAN KACA
1 Kaca bening 5 mm M2 110,000.00
2 SEalant KG 25,000.00
IX BAHAN PENGGANTUNG
1 Kunci tanam 2xSlag biasa Bh 68,250.00
2 Kunci tanam Antik 2xSlag Bh 209,000.00
3 Engsel Pintu Bh 21,000.00
4 Engsel Jendela Bh 17,850.00
5 Hak Angin - Besar (Pasangan) Bh 15,750.00
6 Peganngan Pintu Bh 70,000.00
7 Grendel -Pintu Bh 26,250.00
8 Grendel Jendela Bh 8,400.00
X BAHAN LISTRIK
1 Kabel NYK 2X2,5 mm m 7,350.00
2 Lampu Hemat Energi 23 WATT Bh 47,250.00
3 Lampu SL 23 WATT Bh 68,250.00
4 Stop Kontak Bh 13,650.00
5 Saklar Double Bh 15,750.00
6 Saklar Tunggal Bh 17,850.00
7 Fitting Bh 10,500.00
8 Pipa Union Untuk Kabel 5/8"-4m btg 8,925.00
9 MCB BOX Bh 66,500.00
10 Isolator Bh 5,000.00
11 T Doos Pvc Bh 5,000.00
XI BAHAN SANITISER
1 Closet jongkok Bh 299,250.00
2 Pipa PVC dia. 3/4" m' 4,500.00
3 Pipa PVC dia. 3" m' 25,000.00
4 Kran Air Bh 15,750.00
5 Wastafel Cuci Piring Logam 1 lobang bh 367,500.00
6 WaterDrain bh 15,750.00
7 Penampungan Air 600 Liter bh 603,000.00
8 Floor Drain Bh 15,000.00
9 Seal Tape bh 3,150.00
B HARGA SATUAN UPAH PEKERJA
1 Pekerja Org/Hr 90,000.00
2 Tukang Batu, T.Kayu, T. Besi Org/Hr 103,400.00
3 Kepala Tukang Org/Hr 120,000.00
4 Mandor Org/Hr 105,000.00