PROGRAM MUTU

PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : i/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

LEMBAR PENGESAHAN

PROGRAM MUTU

PAKET -10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN


MALABO – MAMASA – BTS. PROV. SULSEL

PERIODE PELAKSANAAN

22 Mei 2023 S/D 31 DESEMBER 2023

PERSETUJUAN

Pihak Penyedia Jasa Pihak Pengguna Jasa


Dibuat Oleh : Di setujui Oleh :
Team Leader Penanggung Jawab Kegiatan

Ir. BAHARUDDIN MUS AKHMAD, ST.MT


NIP. 1975051 12005021 001
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : ii/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

DAFTAR ISI

Uraian
Hal

Cover Dokumen
Lembar Pengesahan.................................................................. i
Daftar Isi.................................................................................. ii

Bab. I. Informasi Pekerjaan..................................................... 1

Bab. II. Organisasi Pekerjaan.................................................... 3


Bab. III. Jadwal Pelaksanaan...................................................... 13
Bab. IV. Methode Pelaksanaan................................................... 14

Bab. V. Pengendalian Pekerjaan................................................ 30


Bab. VI. Pelaporan..................................................................... 32
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 1/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

BAB I
INFORMASI PEKERJAAN

Nama Pekerjaan : Paket – 10. Pengawasan Teknis Jalan Jembatan


Malabo – Mamasa – Bts. Prov. Sulsel
Lokasi Pekerjaan : Kabupaten Mamasa
No. Kontrak/Tanggal : HK.02.01-Bb31/P2JN/0073 / 20 Januari 2023
No. SPMK/Tanggal : HK.01.02-Bb1/P2JN/0076 / 20 Januari 2023
Nama Pengguna Jasa : Pejabat Pembuat Komitmen, Satker P2JN Prov. Sulbar
Satuan Kerja : Satker P2JN Provinsi Sulawesi Barat
PPK : Akhmad, ST.MT
Alamat : Jl. Gatot Subroto No. 1 Mamuju, Sulawesi Barat
Nama Penyedia Jasa : PT. Bintang Inti Rekatama
Alamat : Jln. Bonton Ramba No. 8 Makassar Sulawesi Selatan
Email : arcipratama@ymail.com
Nilai Kontrak : Rp. 1.632.477.666,00.-
(Satu Milyar Enam Ratus Tiga Puluh Dua Juta
Empat Ratus Tujuh Puluh Tujuh Ribu Enam Ratus
Enam Puluh Enam Rupiah)
Sistim Kontrak : Kontrak Kerja Konsultan Konstruksi Waktu Penugasan
Sumber Dana : APBN Murni Tahun Anggaran 2023
Waktu Pelaksanaan : 7,3 Bulan
Lingkup Kegiatan :
- Preservasi Pemeliharaan Rutin Jalan Sepanjang = 36,40 KM
- Preservasi Rekonstruksi, Rehabilatasi Jalan Sepanjang = 3,52 KM
- Preservasi Rutin Jembatan Sepanjang = 133,50 M
 Jembatan S. KAPIDISAN (KM 138+450)
 Jembatan S. AMPILLI (KM 142+200)
 Jembatan S. KOKI (KM 144+020)
 Jembatan S. SALOBOUEI (KM 145+700)
 Jembatan S. BUNGIN (KM 161+800)
 Jembatan S. MAWAI (KM 177+750)
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 2/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

 Jembatan S. MASUPPU (KM 184+400)


- Preservasi Jembatan Sepanjang = 18,00 M
 Jembatan S. KOPIAN (KM 154+700)
 Jembatan S. SALUMAMA (KM 157+950)
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 3/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

BAB II
ORGANISASI PEKERJAAN

2.1 Struktur Organisasi

TEAM LEADER
IR. BAHARUDDIN MUS

PESURUH KANTOR OPERATOR KOMPUTER


FRIHARWAN AR. M A. HISYAM HAMDAN

SE/QUANTITY ENGINEER HSE ENGINEER QUALITY ENGINEER


JASDAR, ST. HARDIANSYAH, ST IBNU HAMKA, ST.

INPECTOR 1 SURVEYOR MATERIAL TECHNICHIAN


AFGANI MUH NUR, ST. KURNIAWAN, ST ISMAIL, ST.

INSPECTOR 2
ANDY SAPUTRA, ST
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 4/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

2.2 Tugas, Tanggung Jawab dan Wewenang

1. Tim Konsultan Supervisi

Tugas, Tanggung Jawab dan Wewenang penyedia jasa pengawasan konstruksi


sebagai berikut:

1) Penyedia jasa pengawasan konstruksi adalah perusahaan/Badan Usaha


yang memenuhi persyarataan yang ditetapkan untuk melaksanakan tugas-
tugas konsultan dalam bidang jasa pengawasan konstruksi

2) Tugas penyedia jasa pengawasan konstruksi antara lain :

a. Memeriksa dan mempelajari dokumen untik pelaksanaan konstruksi


yang akan dijadikan dasar dalam pengawasan pekerjaan dilapangan.
b. Mengawasi pemakaian bahan, peralatan, dan method pelaksanaan,
serta mengawasi ketepatan waktu, dan biaya pekerjaan konstruksi.
c. Mengawasi pelaksanaan pekerjaan konstruksi dari segi kualitas bahan
dan material, kualitas pelaksanaan, kuantitas fisik untuk setiap
item/bagian pekerjaan yang terurai dalam rincian kontrak fisik, dan laju
pencapaian volume/realisasi fisik yang dicapai disetiap laporan berkala.
d. Mengawasi kepatuhan pelaksana pekerjaan terhadap pemenuhan
syarat-syarat kesehatan, keselamatan kerja, dan lingkungan (HSE) oleh
pelaksana
e. Mengumpulkan data dan informasi di lapangan untuk memberikan
rekomendasi teknis opsi pemecahan masalah yang terjadi selama
pekerjaan konstruksi
f. Membantu menyelenggarakan rapat lapangan secara berkala serta
membuat laporan mingguan dan bulanan pekerjaan pengawasan;
g. Meneliti gambar-gambar untuk pelaksanaan (shop drawings) yang
diajukan oleh Pelaksana Konstruksi;
h. Meneliti gambar-gambar yang sesuai dengan pelaksanaan di lapangan
(as-built drawings) sebelum serah terima;
i. Menyusun daftar cacat/kerusakan sebelum Serah Terima Pertama,
mengawasi perbaikannya pada masa pemeliharaan, dan menyusun
laporan akhir pekerjaan pengawasan
j. Membantu menyusun berita acara persetujuan kemajuan pekerjaan,
dan Serah Terima Pertama (PHO); dan
k. Membantu memeriksa dokumen operasi dan pemeliharaan yang
disusun oleh pelaksan.
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 5/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

3) Tanggung Jawab Penyedia Jasa Pengawasan Konstruksi meliputi:


a. Melaksanakan pengawasan pekerjaan di lapangan, sehingga tetap
terlaksana dengan baik sesuai dengan rencana kerja dan
syarat/spesifikasi teknis pelaksanaan pekerjaan;
b. Menampung persoalan terkait pelaksanaan konstruksi di lapangan dan
menyampaikan serta memberikan rekomendasi opsi solutif kepada PPK;
dan
c. Meneliti kebenaran atau membandingkan laporan progres pekerjaan
yang di klaim/dinyatakan oleh pelaksana pekerjaan dengan yang
diperoleh dari laporan tenaga konsultan supervisi di lapangan

4) Wewenang Penyedia Jasa Pengawasan Konstruksi meliputi:


a. Memberikan peringatan dan teguran tertulis kepada pihak pelaksana
pekerjaan jika terjadi penyimpangan terhadap dokumen kontrak;
b. Meneliti dan memberikan persetujuan pada gambar pelaksanaan (shop
drawing) yang diajukan oleh kontraktor sebelum dilaksanakan
c. Merekomendasikan kepada pengguna jasa untuk menghentikan
pelaksanaan pekerjaan sementara jika pelaksana pekerjaan tidak
memperhatikan peringatan yang diberikan
d. Memberikan masukan pendapat teknis tentang permintaan tambah
kurang pekerjaan yang diajukan oleh pelaksana fisik yang dapat
mempengaruhi biaya dan waktu pekerjaan serta berpengaruh pada
ketentuan kontrak;
e. Mengusulkan perubahan jika terjadi ketidaksesuaian dengan kondisi di
lapangan;
f. Mengkoreksi pekerjaan yang dilaksanakan oleh pelaksana pekerjaan,
termasuk pekerjaan fisik konstruksi yang telah dilaksanakan agar sesuai
dengan kontrak kerja yang disepakati; dan
g. Merekomendasikan kepada PPK untuk menolak material dan peralatan
konstruksi yang tidak sesuai spesifikasi
2. Tenaga Ahli Konsultan Supervisi (Professional Staff )

1) Team Leader
Tugas - tugas Team Leader akan meliputi, namun tidak terbatas pada hal-
hal yang tersebut di bawah ini :
a. Mengoordinasikan seluruh tenaga ahli pengawasan konstruksi untuk
setiap pelaksanaan pengukuran atau rekasaya lapangan yang dilakukan
penyedia jasa pekerjaan konstruksi dan menyampaikan laporan kepada
PPK sehingga dapat segera diambil keputusan yang diperlukan, termasuk
untuk pekerjaan pengembalian kondisi, pekerjaan minor yang
mendahului pekerjaan utama dan rekayasa terperinci lainnya ;
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 6/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

b. Mengoordinasikan seluruh Tenaga Ahli Konsultan Pengawas secara


teratur dan memeriksa seluruh pekerjaan dilapangan serta memberi
penjelasan tertulis kepada jasa pekerjaan konstruksi mengenai apa
yang sebenarnya dituntut dalam pekerjaan tersebut, jika dalam kontrak
pekerjaan konstruksi hanya dinyatakan secara umum;
c. Melakukan pengawasan secara teratur dan memeriksa pekerjaan pada
semua lokasi di lapangan dimana pekerjaan konstruksi sedang
dilaksanakan serta memberi penjelasan tertulis kepada Kontraktor
mengenai apa yang sebenarnya dituntut dalam pekerjaan tersebut,
dan kontrak hanya dinyatakan dalam umum.
d. Memastikan bahwa Penyedia jasa pekerjaan konstruksi memahami
Dokumen Kontrak pekerjaan konstruksi secara benar, melaksanakan
pekerjaannya sesuai dengan spesifikasi serta gambar-gambar, dan
menerapkan metode konstruksi yang tepat dengan kondisi lapangan
untuk setiap pelaksanaan pekerjaan;
e. Memeriksa dengan teliti setiap gambar-gambar kerja dan
analisa/perhitungan konstruksi dan kuantitasnya, yang dibuat oleh
Kontraktor sebelum pelaksanaan pekerjaan.
f. Melakukan inspeksi secara teratur dan memeriksa pekerjaan pada
semua lokasi pekerjaan dalam kontrak serta membuat laporan kepada
PPK terhadap hasil inspeksi lapangan;
g. Membuat rekomendasi kepada PPK untuk menerima atau menolak hasil
pekerjaan, material dan peralatan konstruksi yang tidak sesuai
dengan spesifikasi yang dipersyaratkan dalam Dokumen Kontrak
Pekerjaan Konstruksi.
h. Mengoorninasikan pencatatan kemajuan pekerjaan yang dicapai
Kontraktor setiap hari pada lembar kemajuan pekerjaan (progress
schedule) yang telah disetujui;
i. Memonitor dan mengevaluasi kemajuan pekerjaan dan segera
melaporkan kepada PPK jika terdapat kemajuan pekerjaan yang tidak
sesuai dengan Dokumen Kontrak Pekerjaan Konstruksi dan dapat
berpengaruh terhadap jadwal penyelesaian pekerjaan yang
direncanakan. Dalam kondisi tersebut, maka Team Leader membuat
rekomendasi kepada PPK secara tertulis untuk mengatasi
keterlambatan;
j. Memeriksa semua kuantitas dan volume hasil pengukuran setiap
pekerjaan yang telah selesai yang disampaikan oleh Quantity Engineer.
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 7/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

k. Menjamin bahwa sebelum Kontraktor diizinkan untuk melaksanakan


pekerjaan berikutnya, maka pekerjaan-pekerjaan sebelumnya yang
akan tertutup atau menjadi tidak tampak harus sudah diperiksa/diuji
dan sudah memenuhi persyaratan dalam Dokumen Kontrak Pekerjaan
Konstruksi.
l. Memberi rekomendasi kepada PPK menyangkut mutu, volume dan
jumlah pekerjaan yang telah selesai dan memeriksa kebenaran dari
setiap sertifikat pembayaran bulanan Kontraktor.
m. Mengoorninasikan perhitungan dan p e m b u a t a n sketsa yang benar
kepada PPK di setiap lokasi pekerjaan untuk bahan pertimbangan dalam
pengampilan keputusan/persetujuan.
n. Memberi rekomendasi kepada PPK terhadap pencapaian mutu dan
hasil pekerjaan yang sesuai dengan Dokumen Kontrak Pekerjaan
Konstruksi atas usulan pembayaran yang diajukan Kontraktor.
o. Mengoordinasikan penyusunana laporan mengenai kemajuan fisik dan
keuangan pekerjaan konstruksi yang menjadi kewenangannya dan
menyerahkannya kepada PPK
p. Mengawasi dan memeriksa pembuatan Gambar Terbangun/ Terpasang
(as- built drawings) dan mengupayakan agar semua gambar
tersebut dapat diselesaikan sebelum serah terima pertama (provisional
hand over); dan
q. Menyimpan arsip gambar desain dan menyusun korespondensi
kegiatan, laporan harian, laporan mingguan, laporan kemajuan
pekerjaan dan pengukuran pembayaran

2) Supervision Engineer / Quantity Engineer


Tugas Supervision Engineer/Quantity Engineer akan meliputi, namun tidak
terbatas yang antara lain :
a. Memeriksa kesesuaian antara gambar perencanaan dengan gambar
pelaksanaan pekerjaan dengan memperhatikan kondisi di lapangan.
b. Memastikan Kontraktor menerapkan ketentuan keselamatan
konstruksi.
c. Memastikan bahwa seluruh tenaga kerja konstruksi yang terlibat dalam
pekerjaan konstruksi memiliki Sertifikat Kerja Konstruksi (SKK)
d. Memastikan bahwa seluruh peralatan yang digunakan telah memiliki
Surat Izin Laik Operasi (SILO).
e. Memastikan bahwa operator alat berat memiliki Surat Izin Operator
(SIO).
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 8/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

f. Memeriksa kesesuaian penggunaan material/bahan produksi dalam


negeri dan barang impor sesuai dengan formulir Tingkat Komponen
Dalam Negeri (TKDN) dan daftar barang yang diimpor sebagaimana
tercantum dalam kontrak pekerjaan konstruksi.
g. Memastikan metode konstruksi dan hasil pekerjaan yang dihasilkan
Kontraktor sesuai dengan Dokumen Kontrak Pekerjaan Konstruksi.
h. Memberikan instruksi secara tertulis kepada Kontraktor, apabila metode
konstruksi dinilai tidak benar atau membahayakan dan dicatat dalam
buku harian (log book) serta segera melaporkannya kepada Team
Leader
i. Membuat justifikasi teknis terhadap usulan perubahan yang diajukan
oleh Kontraktor, Mencatat seluruh pelaksanaan pekerjaan serta
seluruh perubahan dan ketidak sesuaian pelaksanaan pekerjaan dari
perencanaan serta melaporkannya kepada Team Leader; dan
j. Memeriksa dan menyetujui laporan teknis yang dibuat oleh
Kontraktor.
k. Melakukan survei yang diperlukan untuk memeriksa pekerjaan dan
volume atau kuantitas pekerjaan sebelum dan saat pelaksanaan
pekerjaan.
l. Membuat catatan/laporan harian tentang kemajuan pekerjaan di
lapangan, serta selalu memberikan informasi tentang rincian pekerjaan
kepada Team Leader.
m. Menghitung kembali volume atau kuantitas pekerjaan yang
dilaksanakan sebagai dasar perhitungan prestasi pekerjaan.
n. Bekerjasama dengan Quality Engineer untuk menyesuaikan metode
pelaksanaan di lapangan dengan di laboratorium sehingga
perhitungan volume atau kuantitas pekerjaan dapat dilaksanakan.
o. Melakukan pengawasan di lapangan selama pekerjaan berlangsung dan
melaporkan segera kepada Team Leader jika terdapat volume atau
kuantitas pekerjaan yang tidak sesuai dengan Dokumen Kontrak
Pekerjaan Konstruksi.
p. Melakukan pengawasan, pemeriksaan, dan mencatat semua hasil
pengukuran, perhitungan volume atau kuantitas pekerjaan dan bukti
pembayaran terhadap Kontraktor sesuai dengan ketentuan dalam
Dokumen Kontrak Pekerjaan Konstruksi.
q. Membuat ringkasan dengan memperhatikan laporan Kontraktor tentang
pengadaan material, jumlah pekerjaan yang telah diselesaikan dan
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 9/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

pengukuran di lapangan untuk dilaporkan kepada Team Leader setiap


hari setelah selesai kerja.
r. Mengevaluasi prosedur perhitungan hasil pelaksanaan pekerjaan yang
diajukan oleh Kontraktor.
s. Melakukan inspeksi dan monitoring lapangan terkait keluaran hasil
pekerjaan serta melaporkannya secara tertulis kepada Team Leader;
dan
t. Membantu Team Leader dalam pengukuran akhir secara keseluruhan
dari bagian pekerjaan yang telah diselesaikan dan memenuhi
persyaratan mutu pekerjaan

3) Quality Engineer

Tugas Quality Engineer akan meliputi, namun tidak terbatas pada hal- hal
yang tersebut di bawah ini :
a. Memeriksa, mengawasi dan melakukan pengujian terhadap pekerjaan,
material dan peralatan yang ditempatkan di lapangan apakah sesuai
dengan gambar dan spesifikasi dan dokumen perubahannya.
b. Melakukan pengawasan atas pemasangan, pengaturan dan
penempatan alat ukur dan alat uji sebelum dan saat pelaksanaan
pekerjaan konstruksi.
c. Melaksanakan pengawasan atas semua pengujian yang dilaksanakan
oleh Kontraktor dalam rangka pengendalian mutu material serta hasil
pekerjaannya, dan segera melaporkan kepada Team Leader jika
terdapat ketidaksesuaian dan cacat mutu baik dalam prosedur
maupun hasil pengujiannya.
d. Menganalisa semua data hasil pengujian mutu pekerjaan dan
memberikan laporan secara tertulis kepada Team Leader atas
persetujuan dan penolakan penggunaan material dan hasil pekerjaan.
e. Mengawasi semua pelaksanaan pengujian di lapangan yang dilakukan
oleh Kontraktor sesuai dengan persyaratan dalam spesifikasi dan
dokumen perubahannya.
f. Menyerahkan laporan bulanan yang di antaranya berisikan laporan hasil
pengendalian mutu, data laboratorium serta pengujian dilapangan
beserta risalah/kesimpulan dari data yang ada kepada Team Leader
untuk selanjutnya dilaporkan kepada PPK.
g. Menyiapkan format laporan pengendalian mutu pekerjaan, pengujian
hasil pekerjaan dan kriteria penerimaan pekerjaan.
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 10/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

h. Menyampaikan laporan hasil uji data mutu material, jumlah benda uji
mutu dan mutu keluaran pekerjaan kepada Team Leader.
i. Membuat rekomendasi kepada Team Leader terhadap ketidaksesuaian
mutu pekerjaan dan tindak lanjut penanganannya, guna pencegahan
ketidak sesuaian; dan
j. Memberikan panduan di lapangan bagi personel Kontraktor mengenai
metodologi pengujian mutu bahan dan pekerjaan.

4) Health Safety Envinment (HSE) Engineer


Health Safety Environment Engineer merupakan pihak atau orang yang
bertugas memastikan bahwa aspek Keamanan, Kesehatan, Keselamatan,
dan lingkungan sudah tersedia dan diterapkan dalam pelaksanaan pekerjaan
konstruksi.
Tugas Health Safety Environment Engineer akan meliputi, namun tidak
terbatas pada hal- hal yang tersebut di bawah ini :
a. Melakukan pengawasan terhadap pemenuhan persyaratan aspek
keselamatan konstruksi dalam pelaksanaan pekerjaan konstruksi, untuk
mendukung terwujudnya tertib penyelenggaraan Jasa Konstruksi.
b. Melakukan pengawasan terhadap penerapan Dokumen SMKK.
c. Memeriksa dan membuat rekomendasi terhadap penyusunan dan
pemutakhiran dokumen penerapan Keselamatan Konstruksi.
d. Berkoordinasi dengan HSE Engineer Kontraktor dalam mengidentifikasi
dan memetakan potensi bahaya yang mungkin terjadi di lingkungan
kerja, termasuk membuat tingkatan dampak dari bahaya (impact) dan
kemungkinan terjadinya bahaya tersebut (probability).
e. Berkoordinasi dengan HSE Engineer Kontraktor dalam menyusun
rencana program keselamatan dan kesehatan kerja yang meliputi upaya
preventif dan upaya korektif, untuk mengurangi terjadinya
bahaya/kecelakaan dan menanggulangi kecelakaan yang terjadi di
lingkungan kerja.
f. Memonitoring implementasi pengelolaan dan pemantauan lingkungan
dengan berkoordinasi Bersama HSE Engineer Kontraktor dalam
memastikan dampak lingkungan akibat pembangunan proyek dapat
diminimalisir.
g. Berkoordinasi dengan HSE Engineer Kontraktor atau pejabat lain dalam
penyiapan pengendalian dan keselamatan lalu lintas yang terlibat di
area proyek atau proyek lain yang berkaitan.
h. Membuat dan memelihara dokumen terkait kesehatan dan
keselamatan kerja, termasuk merancang prosedur baku dan
memelihara borang atau catatan terkait kesehatan dan keselamatan
kerja; dan
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 11/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

i. Mengevaluasi insiden kecelakaan yang mungkin terjadi, serta


menganalisis akar masalah termasuk tindakan preventif dan korektif
yang diambil.
3. Sub Professional Staff

1) Inspektor
Inspektor bertugas
a. Setiap saat melakukan pengawas pada semua lokasi kegiatan
b. Mencatat dan memeriksa julmlah tenaga kerja, peralatan yang
digunakan
c. Melaporkan hasil kegiatan pada Supervision Engineer / Quantity
Engineer

2) Surveyor
Surveyor bertugas
a. Mengikuti semua pekerjaan Pengukuran yang dilakukan peneyedia jasa
konstruksi
b. Mencatat dan memeriksa hasil ukur
c. Melaporkan hasil pengukuran kepada Supervision Engineer / Quantity
Enginee

3) Material Teknisi
Material Teknisi bertugas
a. Melakukan pengawasan atas semua pengujian yang dilakukan
kontraktor
b. Mencatat dan memeriksa hasil pengujian yang dilakukan kontraktor
c. Mencatat dan memeriksa setiap material yang masuk ke lokasi kegiatan
d. Melaporkan semua hasil pengawas pengujian kepada Quality Engineer
4) Supporting
a) Operator Komputer
Tugas Operator Komputer :
- Membantu Team Leader dalam membuat laporan pelaksanaan
pekerjaan
- Menyusun administrasi pelaksanaan pekerjaan
b) Pesuruh Kantor
Tugas Pesuruh Kantor
- Memperbanyak dokumen dengan cara foto copy secara mandiri
- Turut serta dalam menjaga keamanan kantor proyek
- Menjaga kebersihan lingkungan proyek
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 12/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

BAB III
JADWAL PELAKSANAAN
RENCANA KEGIATAN KONSULTAN
SATUAN KERJA : PERENCANAAN DAN PENGAWASAN JALAN NASIONAL PROVINSI SULAWESI BARAT
PEKERJAAN : PAKET-10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO - MAMASA - BTS. PROV. SULSEL
LOKASI : MALABO - MAMASA - TABANG KAB.MAMASA
TAHUN ANGGARAN : 2023
NAMA PERUSAHAAN : PT. BINTANG INTI REKATAMA, KSO- PT.CELEBES PRATAMA KONSULTAN

HARGA JUMLAH Bobot WA K T U P E L A K S A A N


No. POSISI NAMA PERSONIL VOLUME JANUARI FEBRUARI MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER KET.
SATUAN HARGA (%)
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
I.1 PROFESIONAL STAFF
0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2 0 .4 8 2
1 Team Leader Ir.Baharuddin Mus. 1 Org 11.50 OB 28,526,000.00 328,049,000.00 22.188
0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1 0 .4 7 1
2 SE, Quantity Engineer Jasdar, ST 1 Org 9.50 OB 27,112,000.00 257,564,000.00 17.420
0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5 0 .4 3 5
3 Quality Engineer Ibnu Hamka, ST. 1 Org 10.00 OB 25,697,000.00 256,970,000.00 17.380
0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9 0 .3 9 9
4 HSE. Hardiansya, ST. 1 Org 4.40 OB 21,454,000.00 94,397,600.00 6.385
I.2 SUB PROFESIONAL STAF
0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7
1 Inspector 01 Afgani M Nur. ST. 1 Org 11.50 OB 7,500,000.00 86,250,000.00 5.834
0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7
2 Inspector 02 Andy Saputra, ST. 1 Org 8.00 OB 7,500,000.00 60,000,000.00 4.058
- 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111 0 .111
3 Surveyor Kurniawan, ST. 1 Org 7.00 OB 7,500,000.00 52,500,000.00 3.551
0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7 0 .12 7
4 Material Teknisi Muh. Helmi Jaya, ST. 1 Org 6.00 OB 7,500,000.00 45,000,000.00 3.044
I.3 SUPPORTING STAF
0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1 0 .0 5 1
1 Operator Komputer A. Hisyam Hamdan 1 Org 11.50 OB 3,000,000.00 34,500,000.00 2.333
0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5
2 Pesuruh Kantor Friharwan AR.M 1 Org 11.50 OB 1,500,000.00 17,250,000.00 1.167
TOTAL BIAYA LANGSUNG PERSONIL 1,232,480,600.00 83.36
II.1 MOBILISASI DAN DEMOBILISASI
0 .0 9 0
0 .0 9 0 0 .0 9 0
1 Biaya Mobilisasi dan Demobilisasi Personil 16.00 OT 250,000.00 4,000,000.00 0.271 0 .0 6 2
0 .0 6 2 0 .0 6 2
2 Perjalanan Darat 11.00 OT 250,000.00 2,750,000.00 0.186
0 .0 6 1 0 .0 6 1 0 .0 6 1 0 .0 6 1 0 .0 6 1 0 .0 6 1 0 .0 6 1 0 .0 6 1 0 .0 6 1 0 .0 6 1 0 .0 6 1
3 Biaya Sewa Penginapan 33.00 OT 300,000.00 9,900,000.00 0.670
16,650,000.00 1.126
II.2 FASILITAS KANTOR
0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8
1 Biaya ATK ( Office Consumables) 11.50 Bulan 500,000.00 5,750,000.00 0.389
0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8
2 Biaya Komputer & Printer Consumables 11.50 Bulan 500,000.00 5,750,000.00 0.389
0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8
Biaya Sewa Laptop 11.50 Bulan 500,000.00 5,750,000.00 0.389
0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8
4 Biaya Sewa Printer A-4 11.50 Bulan 500,000.00 5,750,000.00 0.389
0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8
5 Biaya Sewa Meja dan Kursi Rapat 11.50 Bulan 500,000.00 5,750,000.00 0.389
0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8 0 .0 0 8
6 Biaya Komunikasi 11.50 Bulan 500,000.00 5,750,000.00 0.389
0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3 0 .0 0 3
7 Perlengkapan Lapangan 1.00 Ls 2,230,000.00 2,230,000.00 0.151
36,730,000.00 2.484
II.3 AKOMODASI
1 Sewa Kendaraan :
0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9 0 .16 9
'- Sewa Kendaraan Roda Empat 1 Unit 11.50 Bulan 10,000,000.00 115,000,000.00 7.778
0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0 0 .0 5 0
'- Sewa Kendaraan Roda Dua 7 Unit 56.40 Bulan 600,000.00 33,840,000.00 2.289
148,840,000.00 10.067
2 Sewa Kantor / Mess :
0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5 0 .0 2 5
'- Sewa Kantor 1 Unit 11.50 Bulan 1,500,000.00 17,250,000.00 1.167
0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5 0 .0 0 5
'- Biaya Pemeliharaan Kantor M²/Bln 138.00 Bulan 25,000.00 3,450,000.00 0.233
0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17 0 .0 17
'- Biaya Sewa Rumah 1 Unit 11.50 Bulan 1,000,000.00 11,500,000.00 0.778
32,200,000.00 2.178
II.4 BIAYA LAIN - LAIN / PELAPORAN ( Harga Satuan Tetap )
1 Laporan Program Mutu 5.00 Buku 100,000.00 500,000.00 0.034 ###
###
2 Laporan RKK 5.00 Buku 75,000.00 375,000.00 0.025
###
3 Laporan Pendahuluan 5.00 Buku 75,000.00 375,000.00 0.025
### ### ### ### - ### ### - ### - ### ### - ### - ###
4 Laporan Bulanan 55.00 Buku 75,000.00 4,125,000.00 0.279
- - 0 .0 3
5 Laporan Akhir 5.00 Buku 100,000.00 500,000.00 0.034
0 .0 5
6 HDD (2 TB) 1.00 Buah 750,000.00 750,000.00 0.051
0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4
7 Alat Pelindung Diri (APD) 1.00 Ls 2,500,000.00 2,500,000.00 0.169
0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4 0 .0 0 4
8 Alat Pelindung Kerja (APK) 1.00 Ls 2,500,000.00 2,500,000.00 0.169
11,625,000.00 0.786
TOTAL BIAYA LANGSUNG PERSONIL 246,045,000.00 16.64
JUMLAH BIAYA 1,478,525,600.00 100.00 0 0 1.0 1.0 1.1 1.0 1.0 1.0 1.5 1.4 1.9 1.9 2 .0 1.9 1.9 1.9 2 .1 2 .0 2 .0 2 .2 2 .2 2 .2 2 .2 2 .2 2 .5 2 .3 2 .3 2 .3 2 .4 2 .3 2 .7 2 .7 2 .8 2 .7 2 .6 2 .6 2 .7 2 .6 2 .6 2 .6 2 .7 2 .6 2 .6 2 .6 2 .7 2 .6 2 .6 2 .9

Pajak Pertambahan Nilai (PPN) 11% 162,637,816.00 0 0 1.0 2 .1 3 .2 4 .2 5 .2 6 .2 7 .8 9 .2 11.1 13 .0 15 .0 17 .0 18 .9 2 0 .8 2 2 .9 2 5 .0 2 7 .0 2 9 .2 3 1.5 3 3 .6 3 5 .8 3 7 .9 4 0 .4 4 2 .7 4 5 .0 4 7 .3 4 9 .7 5 1.9 5 4 .6 5 7 .3 6 0 .1 6 2 .8 6 5 .4 6 8 .0 7 0 .7 7 3 .4 7 6 .0 7 8 .6 8 1.4 8 4 .0 8 6 .6 8 9 .2 9 2 .0 9 4 .6 9 7 .2 10 0

Rencana
JUMLAH BIAYA TOTAL 1,641,163,416.00 Uang Muka 328,232,600.00 81,636,888.7 89,502,991.6 101,866,060.4 110,524,058.2 114,353,557.3 123,011,555.1 131,491,686.5 140,663,299.5 139,356,781.6 139,356,781.6 142,464,780.8
Cash Flow
Total
DIBULATKAN 1,641,163,000.00 328,232,600.00 409,869,488.70 499,372,480.27 601,238,540.71 711,762,598.96 826,116,156.23 949,127,711.31 1,080,619,397.84 1,221,282,697.39 1,360,639,479.00 1,499,996,260.62 1,642,461,041.44
Cash Flow
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 14/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

BAB IV
METHODE PELAKSANAAN
4.1 Bagan Alir

NO KEGIATAN PROSEDUR / INSTRUKSI KERJA KODE


1. Mobilisasi Check : P1
- Design Perencanaan
- Data MC-0
- Mobilisasi Peralatan
- Shop Drawing
- Kesiapan
Jika semua yang tsb diatas sebagain atau seluruhnya tidak
ada, maka diinstruksikan untuk melengkapi semua, jika sudah
ada maka dilanjukkan mengecheck/memeriksa :
- Mutu Material
- Kwalitas Peralatan Q1
- SDM Tenaga Kerja
- DMF dan JMF
2 Rekayasa Rekayasa lapangan dapat dilakukan setelah persyaratan P1 P2
Lapangan dan Q1 terpenuhi dengan mengecek :
- Mutu Material
- Kwalitas Peralatan
- SDM Tenaga Kerja
- DMF dan JMF
3. Pemeriksaan Pemeriksaan Rencana Kerja dapat dilanjutkan setelah P3,
Rencana Kerja persyaratan / kegiatan rekayasa lapangan terpenuhi sesuai P4,
ketentuan dengan kegiatan pengawasan : P5,
1. Pengawasan Lapangan P6
2. Pengawasan Material
3. Pengawasan Laboratorium

Dengan mengecheck :
- Komposisi Campuran
- Pemeriksaan Quantity dan Quality
- Uji Laboratorium
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 15/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

4. Opname Setelah semua persyaratan sebagaimana pada P3, P4, P5 dan


Lapangan P6 terpenuhi sesuai persyaratan, maka dapat dilanjutkan
dengan Opname Pekerjaan di lapangan dan kalau tidak sesuai
persyaratan baik dilaboratorium, material maupun
pelaksanaan lapangan maka akan dilakukan perbaikan sampai
memenuhi ketentuan yang dipersyaratkan
5. Sertifikasi Sertifikasi kontraktor (MC) dilakukan setelah semua
Kontraktor persyaratan memenuhi ketentuan baik itu mutu pelaksanaan,
uji laboratorium maupun mutu dan persyaratan administrasi
(Lap. Harian, lap. Mngguan, lap. Bulanan, back up data
quality dan Quantity dan dokumen lain yang terkait)
6. Laporan Akhir Pembuatan Laporan Akhir dapat dilakukan setelah semua P1
persyaratan memenuhi ketentuan termasuk Asbuid Drawing. Q1
Laporan Akhir dianggap selesai apabila memenuhi ketentuan
dengan mengechec persyaratan :
1. Design Perencanaan
2. Data MC-0
3. Mobilisasi Peralatan
4. Shop Drawing
Serta :
1. Dok. Final Quantity
2. Administrasi yang terkait
3. Asbuil Drawing (gambar terlaksana)
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 16/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

Gambar 4.1 Bagan Alir Pelaksanaan Pekerjaan


PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 17/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

BAGAN ALIR PENGENDALIAN MUT U


( POLA 2 - 3 - 5 )

5 HA L 2 LINGKUP

BAHAN DASAR
(RAW MATERIAL)

- DIMENSI RAW MATERIAL


RUJUKAN 5 HAL - SIFAT FISIK MATERIAL INDIVIDU
- OBYEK
- METODE TEST
- FREKWENSI TEST
- ACUAN SPESIFIKASI
- TOLERANSI

- Alternatif Quarry T idak DIMENSI MUTU Tidak Alternatif Quarry


- Screen/saringan
Ya Ya
Q C R

BAHAN OLAHAN
(MIX MATERIAL)

3 TAHAP
RUJUKAN 5 HAL - DIMENSI MATERIAL
- OBYEK CAMPURAN
- METODE TEST - SIFAT MATERIAL
- FREKWENSI TEST
CAMPURAN
- ACUAN SPESIFIKASI
- TOLERANSI

T idak DIMENSI MUTU Tidak

Ya Ya
Q C R

BAHAN JADI
- DIMENSI KONSTRUKSI
RUJUKAN 5 HAL ( BARANG JADI )
- OBYEK - SIFAT/MUTU KONSTRUKSI
- METODE TEST TEST
- FREKWENSI
- ACUAN SPESIFIKASI
- TOLERANSI

T idak Tidak
DIMENSI MUTU

Ya Ya
Q C R

2 (dua) LINGKUP : - DIMENSI 5 (lima) HAL : - OBYEK QCR : Quality Control Report
- MUTU - METODE TES
- FREKWENSI
3 (tiga) LINGKUP : - BAHAN DASAR - ACUAN FREKWENSI
- BARANG OLAHAN - TOLERANSI
- BARANG JADI

Gambar 4.2 Bagan Alir Pelaksanaan Pekerjaan


PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 18/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

BAGAN ALIR PENGENDALIAN KUANTITAS


( Dilakukan setiap Request selesai dilaksanakan)

SHOP DRAWING
GA

Tidak
CHECKED I
2 Hari
CHECKED - Kesesuaian dengan desain
- Perhitungan teknik
- Kesesuaian lokasi

S ETUJU I

REQUES T

Tidak
CHECKED II
- Kesiapan bahan
CHECKED 2 Hari - Kesiapan alat
- Kesiapan tenaga
- Kesiapan lahan

S ETUJU II

Max. 4 Hari
PELAKS ANAAN

PRODUK AKHIR

2 Hari
PENGUKURA N
(OPNAME)
2 Hari
CHECKED III
- Quality Control
CHECKED - Data ukur
- S ampel
- Perhitungan volume
- Lembar hasil opname

LEMBAR
OPNAME

Copy Copy

DIREKS I KONTRAKTOR S UPERVIS I


Pengawas Pelaksana Inspector

Koord. Lapangan QUANTTY CONTROL Chief Inspector

KA. KEGIATAN G.S S .E

Tanggal 25
RAPAT BULANAN

- PROGRES FIS IK
- BERITA ACARA PEMERIKS AAN
PENYELES AIA N PEKERJAAN
Asli Copy
Copy

PPK KONTRAKTOR S UPERVIS I

- REPORT KE S ATKER PENYUS UNAN MC - REPORT KE P2JN


- PENYUS UNAN LAP.BUL. SE
- QUANTITY

Gambar 4.3 Bagan Alir Pelaksanaan Pekerjaan


PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 19/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

BAGAN ALIR PENGENDALIAN WAKT U

Time Schedule

Dikaji Oleh Konsultan

Tidak
Diterima ?

Ya

Disetujui Oleh PPK

Cek Kemajuan
Pekerjaan

ya
Dalam Batas

Tidak

Show Cause Meeting PHO

Membantu Penjadwalan
FHO
Kembali

Gambar 4.4 Bagan Alir Pelaksanaan Pekerjaan


PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 20/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :
BAGAN ALIR PEKERJAAN GALIAN SALURAN

Gambar Kerja
Situasi, Pot. Memanjang dan Melintang

Rencana Pelaksanaan Rencana Pelaksanaan


Pekerjaan Perkerasan Pekerjaan Salauran

Ganbar Kerja
Potongan Melintang

No Check Ketersediaan Rambu


Keselamatan

Yes

Pembersihan

Galian

Pembentukan
Saluran

No
Check
II

Yes

End

Gambar 4.5 Bagan Alir Pelaksanaan Pekerjaan


PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 21/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

Bagan Alir Pelaksanaan Pekerjaan Tanah ( Badan Jalan )

Pekerjaan Tanah

Kelengkapan Gambar Kerja


Situasi, Profil Memanjang
dan Potongan Melintang

Tidak
Check

Ya

Pembersihan dan
Pembongkaran

Pemadatan Persetujuan Galian sesuai


Dasar Material elevasi rencana
Timbunan Timbunan

Tidak Check
Persiapan
Tanah Dasar
Ya

Penghamparan sesuai
elevasi dan pemadatan
Check Tidak

1. Kepadatan
Kepadatan 2. CBR
Tidak Check
3. Material yang Ya
tidak terpakai
End
Ya

Gambar 4.6 Bagan Alir Pelaksanaan Pekerjaan


PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 22/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

BAGAN ALIR PERKERASAN BERBUT IR

Kondisi Permukaan JMF yg telah disetujui


Sebelumnya

No Check I
check 1. Fungsi Saluran Samping
I 2. Kondisi Permukaan Lapisan Sebelumnya

Maksimalkan Yes
Fasilitas Lalulintas

No Check II
Check Ketersediaan Fasilitas Lalulintas
II

Stock Material yg
memenuhi syarat

No Check III
Check 1. Kondisi stock pile material
III 2. Gradasi

Yes

Pengangkutan dan
Penghamparan Material
Membuang material
yg tidak terpakai

No Check IV
Check 1. Over size dan material yg tidak memenuhi syarat
IV 2.Ketebalan Hamparan sesuai dgn hasil Trial
3. Segregasi
Yes

Penyesuaian Kadar Air,


Elevasi dan Pemedatan

No Check V
Check 1. Kepadatan
V 2. Elevasi Akhir
3. Ketebalan Akhir
Yes

End

Gambar 4.7 Bagan Alir Pelaksanaan Pekerjaan


PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 25/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :
BAGAN ALIR UNTUK PEMBUATAN JOB MIX FORMULA AC-BC / AC - WC

12. 13.
Testing Testing AMP Trial Paving Trial

Aggregate & Aggregate Sampling Placing


Filler Mixing Compacting
2. Properties T 27, T 11 Testing Testing

T27, T11, T96, T245, T209, T166, T 166


T104, T182 T164, T30, T170,
T84, T85, M17 T49, T51
8.
7. Cold Bin Hot Bin
Calibration Calibration
Materials
9. 11. 14.
Coarse Agg.
Fine Agg. 4. Preliminary 6. Job Mix Formula Mix Design Job Mix Formula Job Mix
1.
Filler Mix Design (Tentative) Review (Adjusted) Formula
Aiditif (Definitive)
Asphalt

Testing 11. Job Mix Formula ( Adjusted )


Testing
JMF yang disesuaikan, yang didapat berdasarkan
Testing 5. Mix Properties hasil dari Review dan test terhadap komposisi
10. Mix Properties
Agregat dan Filler serta Aspal panas.
Asphalt Properties T165, T166, T245, T209 T165, T166, T245, T209
3.
T179, T49 12. AMP Trial
T201, T53 Untuk mengkonfirmasikan atau memastikan
T228, M20 bahwa AMP dapat secara konsisten
M226
menghasilkan hotmix sesuai dengan JMF yang
telah disesuaikan, dengan mempertimbangkan
toleransi yang diijinkan oleh Spesifikasi.
Keterangan :

1. Test Untuk Sumber Penerimaan 4. Preliminary Mix Design 7. Cold Bin Calibration 13. Paving Trial
Diperlukan untuk memastikan bahwa Berdasarkan Properties sample Aggregate Diperlukan untuk menentukan bukaan pintu Untuk mengkonfirmasikan atau memastikan
sumber aspal dan kumpulan Material lain dari Stockpiles dan kebutuhan minimum Cold Bin, berdasarkan komposisi material bahwa hasil dari JMF yang disesuaikan dapat
yang diusulkan dapat memenuhi semua dari spesifikasi, sehingga dirumuskan suatu Aggregate dan Filler yang didapat berdasarkan dilaksanakan dilapangan. Dan untuk
kebutuhan spesifikasi. Resep Campuran Nominal. dari JMF Tentative ( sementara ). memastikan bahwa pemakaian peralatan yang
diperlukan, misalnya jenis, kapasitas dan jumlah
2. Test Untuk Aggregate dan Filler 5. Mix Properties 8. Hot Bin Calibration lintasan, dapat ditetapkan.
- Gradation Yang ditentukan berdasarkan percobaan Diperlukan untuk menentukan persentase
- Hardness laboratorium pada campuran dengan kebutuhan Material Aggregate dan filler,
- Soundness resep nominal, untuk proporsi campuran sehingga dapat memenuhi kebutuhan gradasi 14. Job Mix Formula ( Definitive )
- Coating and stripping aggregate dan Asphalt Content. pada spesifikasi. Setelah AMP Trial dan Paving Trial sukses
- SG and absorption berdasarkan JMF yang disesuaikan, maka
JMF yang disesuaikan tadi dapat
3. Test Untuk Asphalt 6. Job Mix Formula ( Tentative ) 9,10. Mix Design Review & Testing dipergunakan sebagai Acuan pelaksanaan
Properties sebelum dan sesudah Optimum Komposisi resep campuran, Tinjauan dan test Disain campuran yang pekerjaan Hot Mix. Sehingga JMF tersebut
pemanasan setelah mempertimbangkan Mix telah didapat berdasarkan komposisi adalah merupakan JMF yang Definitive,
- Penetration Properties. JMF ini berlaku hanya untuk campuran material Agregat dan Filler dari namun hanya berlaku untuk jenis material
- Softening point Cold Aggregate Blending. Hot Bin, yang dicampur dengan aspal panas. dan peralatan yang sama dengan yang
- Viscisity dipergunakan pada proses pembuatan
- S.G JMF ini.
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 26/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

BAGAN ALIR PROSEDUR PEKERJAAN ASPAL

Material yg memenuhi syarat


Perbaikan Permukaan
dan Job Mix Formula (JMF)
(Prime / Tack Coat)

1. Kondisi Permukaan 1. Material yg tidak meme-


No 2. Ketersediaan Rambu No nuhi syarat di cold bin
Check Keselamatan Check 2. Kadar Air Agregat
3. Cuaca I 3. Penyesuaian bukaan Cold
Bin berdasarkan kapasitas
I Yes
drier
Yes
4. Waktu Pencampuran
Finisher dipanaskan, Produksi Aspal di Asphalt
garis batas luar dan Mixing Plant
elevasi/kemiringan

1. Suhu
No
Check 2. Berat
3. Kadar Aspal
4. Sampel untuk uji mutu
Yes

Pengangkutan

Penghamparan dan
Perataan

No 1.Suhu
Check 2. Segregasi
IV

Yes 1. Segregasi
2.Waktu dan suhu pemadatan
Check 3.Kelurusan tepi aspal
Pemadatan
V
4. Kerataan sambungan

Core Drilling Yes

Check Engineer memutuskan


1. Ketebalan VI No
langka langka perbaikan
2. Bulk Density yg diperlukan
3. Toleransi permukaan
Yes

End

Gambar 4.9 Bagan Alir Pelaksanaan Pekerjaan


PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 27/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :
BAGAN ALIR PROSEDUR PEKERJAAN BOX CULVERT

Persetujuan Gambar Kerja Persetujuan Material dan JMF


untuk Pekerjaan Beton

No Check
I
Pembesian dan Pemesangan
bekisting samping dan atas
Yes

Pekerjaan Galian dan


Pemadatan
No Check
1. Pembesian
V
1. Elevasi 2. Bekisting
No 2.Pemadatan
Check
II 3. Persetujuan
material
Pengecoran beton untuk
dinding dan lantai atas

Lantai Kerja
No Check 1. Proposi
VI 2. Pencampuran
3. Pengambilan sampel dan pengujian
Penempatan deking beton
Yes

1. Baja Tulangan Pengujian Kuat Tekan


No Check 2. Bekisting
III 3. Pipa Drain

No Engineer memutuskan
Check
langkah langkah yang
VII
Pembesian dan Pengecoran dpperlukan
Lantai Bawah
Yes
Penimbunan kembali,
1. Proposi/takaran pemadatan dan pembersihan
No Check penampang basah
2.Pencampuran
IV
3. Pengambil Contoh
Pengujian
No 1. Proses penimbunan dan Pemadatan
Yes Check
VIII 2. Kepadatan
3. Kelancaran pengaliran
4. Pembersihan Penam pang Basah
Yes
End

Gambar 4.10 Bagan Alir Pelaksanaan Pekerjaan


PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 28/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

4.2 Rencana kerja


AKTIVITAS METHODE KERJA OUTPUT KERJA DURASI TEBAGA AHLI
KERJA YANG TERLIBAT
1 Mobilisasi Memobilisasi sesuai Penempatan Selama Team Leader
kebutuhan sesuai jumlah periode
dan kebutuhan mobilisasi
2 Rekayasa Pemeriksaan mutu Mutu material Maks 60 hari Site Engineer/
lapangan material, kualitas sesuai sejak tanggal Quantity Eng
peralatan, SDM. persyaratan, SPMK Inspector
JMD dan JMF peralatan laik Surveyor
operasi, SDM
yang handal
serta JMD dan
JMF sebagai
acual
pelaksanaan
kegiatan
3 Pemeriksaan Memeriksa rencana Memastikan Minimal 3 Quality Eng
Rencana kerja dari setiap bahwa setiap hari sebelum Inspection Eng /
Kerja item kegiatan kegiatan sesuai pelaksanaan Quantity Eng
prosedur pekerjan
pelaksanaan tersebut
kegiatan,
termasuk
prosedur
administrasi dan
pelaksanaan
pekerjaan
dilapangan
4 Pengawasan Pemeriksaan Terjaminnya Selama Quality Eng
laboratorium terhadap semuat semua mat. periode Mat. Technician
material yang Yang digunakan pelaksanaan
digunakan serta memenuhi pekerjaan
semua produk persyaratan
pelaksaan di serta hasil
lapangan kwalitas
pekerjaan
memenuhi
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 29/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

syarat dalam
spesifikasi
6 Pengawasan Mengawasi setiap Setiap kegiatan Selama Inspection Eng /
lapangan item pekerjaan dilapangan periode Quantity Eng
dilapangan diawasi sesuai pelaksanaan Inspector
perosedur pekerjaan Quality Eng
pengawasan Mat. Technician
7 Opname Melakukan Setiap Pada setiap Inspection Eng /
Lapangan pengukuran secara pengukuran minggu dan Quantity
cermat pada setiap volume di setiap tgl 25 naanEng
pekerjaan lapangan bulan Inspector
dilakukan berjanan Surveyor
dengan
methode yang
disetujui dan
dapat
dipertanggung
jawabkan
8 Sertifikasi Memeriksa Memastikan Setiap akhir SE
Kontraktor Sertifikasi bahwa setiap tgl 25 bulan Quality Eng
kontraktor dengan pekerjaan yang berjalan Inspection Eng /
mencocokkan ada dalam Quantity Eng
progres dari setiap dokumen
pekerjaan sertifikasi sesuai
keadaan
lapangan dan
memenuhi
persyaratan
9 Laporan Pemeriksaan Semua dokumen Akhir kontrak Team Leader,
Akhir terhadap dokumen yang ada Site
final quantity, lengkap Eng/Quantity dan
administrasi yang Quality Eng
terkait, asbuild
drawing
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 30/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

BAB V
PENGENDALIAN LAPORAN
5.1 Daftar Komposisi Tim dan Penugasan

Tabel 5.1 Jadwal Personil Inti dan Pendukung


PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 31/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

5.2 Checklist Kegiatan Konsultan Pengawas

PENGAWASAN TEKNIS JALAN DAN JEMBATAN


MALABO - MAMASA – BTS. PROV. SULSEL

PT. BINTANG INTI REKATAMA

KETERANGAN
No LINGKUP KEGIATAN

ADA TIDAK
1. Masa Mobilisasi
a. Data dan dokumen kegiatan pekerjaan
b. Data dan Dokumen kontrak
c. Rencana Mutu Pekerjaan Konstruksi Kontraktor
d. Jadwal Pengiriman Peralatan Penyedia Jasa Konstruksi
e. Data Tenaga Kerja Konstruksi
f. Jadwal Pelaksanaan Pekerjaan konstruksi (time skedule)
g. Gambar Design
2. Masa Pelaksanaan
a. Pemeriksaan deposit dan kualitas dari quaary material
b. Pengawasan Pembuatan Job Mix Formula (JMF)
c. Pemeriksaan terhadap permohonan izin kerja oleh Kontraktor
(Request)
d. Pembagian tugas kepada Team Supervisi setelah persetujuan
izin kerja (quality control, quantity surveyor, inspector, material
technician)
e. Pemeriksaan hasil pengukuran volume
f. Pemeriksaan hasil test laboratorium
g. Pemeriksaan laporan harian, laporan mingguan, laporan
bulanan, Backup data quality dan quantity serta Monthly
Certificate (MC) kontraktor
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 32/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

BAB VI
PELAPORAN

Table 6-1 Penjelasan Laporan

JENIS RENCANA
NO RENCANA ISI LAPORAN
LAPORAN PENYERAHAN
1. Laporan 1. Laporan pendahuluan paling sedikit Tanggal 25 Maret
Pendahuluan memuat hal-hal sebagai berikut: 2023
a. Pemahaman terhadap lingkup
layanan konsultansi selama
masa kontrak;
b. Rencana kerja dan
pengoragnisasian pekerjaan;
c. Jadwal pelaskanaan dan
penugasan tenaga ahli; dan
d. Ringkasan kemajuan
pelaksanaan pengawasan (jika
sudah ada).

2. Laporan Bulanan, Laporan bulanan paling sedikit memuat hal- Tanggal 25 Maret
Quality & HSE hal sebagai berikut: 2023
1. Rencana kerja bulan berjalan
2. Kemajuan pekerjaan penyedia
pekerjaan konstruksi
3. Total kemajuan kegiatan dan
keterlambatan yang terjadi serta
sebab-sebanya
4. Rencana kerja untuk bulan
selanjutnya
5. Jadwal pelaksanaan dan jadwal
kerja Tenaga ahli

3. Laporan Triwulan 1. Rencana Kerja Tanggal 25 Mei


2. Kemajuan pelaksanaan sampai 2023
dengan periode tiga bulanan
terakhir
PROGRAM MUTU
PAKET – 10. PENGAWASAN TEKNIS JALAN DAN JEMBATAN MALABO – MAMASA – BTS. PROV. SULSEL
No. Dok. : 01/PM/BIMA-10/V/2023 Tgl. Diterbitkan : 29 Mei 2023 Hal : 33/24
No. Rev. : 00 Tgl. Kaji Ulang : Paraf :

3. Rencana kerja untuk triwulan


selanjutnya
4. Jadwal pelaksanaan dan
penggunaan Tenaga Ahli sampai
periode tiga bulan selanjutnya
5. Evaluasi sementara dan saran
kepada pengguna jasa.

3. Laporan Akhir 1. Rencana Kerja awal untuk selama Tanggal 25


periode layanan Desember 2023
2. Rencana kerja yang telah
disesuaikan
3. Realisasi pelaksanaan pengawasan
4. Jadwal pelaksanaan dan
penggunaan Tenaga Ahli.
5. Realisasi pelaksanaan dan
penggunaan tenaga Ahli.