(BOQ)
NAMA PEKERJAAN : PENINGKATAN JALAN DAN SLOPE PROTECTION
NAMA KEGIATAN : PENGEMBANGAN DAN PENINGKATAN PERLUASAN KESEMPATAN KERJA
INFRASTRUKTUR PEDESAAN PADAT PEKERJA I
LOKASI PEKERJAAN : KELURAHAN MATTIRO DECENG KECAMATAN TIROANG KABUPATEN PINRANG
SKPD : DINAS TENAGA KERJA DAN TRANSMIGRASI KABUPATEN PINRANG
B. PEKERJAAN KONSTRUKSI
1 Batu Belah 96.53 M³ 157,500.00 15,202,687.50 18.03
2 Pasir Pasang 102.23 M 3
112,000.00 11,450,208.00 13.58
3 Portland Cement (Pc) 50 Kg 387.20 Zak 68,000.00 26,329,600.00 31.22
52,982,495.50 62.83
C PEMBELIAN PERALATAN
1 Cangkul 8.00 Bh 80,000.00 640,000.00 0.76
2 Sekop 4.00 Bh 90,000.00 360,000.00 0.43
3 Gerobak Dorong 4.00 Bh 600,000.00 2,400,000.00 2.85
4 Sendok Semen 5.00 Bh 30,000.00 150,000.00 0.18
5 Linggis 3.00 Bh 150,000.00 450,000.00 0.53
4,000,000.00 4.74
DELAPAN PULUH DELAPAN JUTA TIGA RATUS TIGA PULUH RIBU RUPIAH"
Nama Jelas
Jabatan
RENCANA ANGGARAN BIAYA
(RAB )
NAMA PEKERJAAN : PENINGKATAN JALAN DAN SLOPE PROTECTION
NAMA KEGIATAN : PENGEMBANGAN DAN PENINGKATAN PERLUASAN KESEMPATAN KERJA
INFRASTRUKTUR PEDESAAN PADAT PEKERJA I
LOKASI PEKERJAAN : KELURAHAN MATTIRO DECENG KECAMATAN TIROANG KABUPATEN PINRANG
SKPD : DINAS TENAGA KERJA DAN TRANSMIGRASI KABUPATEN PINRANG
B. PEKERJAAN KONSTRUKSI
1 Batu Belah 96.53 M³ 157,500.00 15,202,687.50 18.01
2 Pasir Pasang 102.23 M 3
112,000.00 11,450,208.00 13.56
3 Portland Cement (Pc) 50 Kg 387.20 Zak 68,250.00 26,426,400.00 31.30
53,079,295.50 62.87
C PEMBELIAN PERALATAN
1 Cangkul 8.00 Bh 80,000.00 640,000.00 0.76
2 Sekop 4.00 Bh 90,000.00 360,000.00 0.43
3 Gerobak Dorong 4.00 Bh 600,000.00 2,400,000.00 2.84
4 Sendok Semen 5.00 Bh 30,000.00 150,000.00 0.18
5 Linggis 3.00 Bh 150,000.00 450,000.00 0.53
4,000,000.00 4.74
DELAPAN PULUH DELAPAN JUTA EMPAT RATUS DUA PULUH ENAM RIBU RUPIAH"
HERWIN RIZMA, SE
Nip. 19790312 201001 1 016
RENCANA ANGGARAN BIAYA
(RAB )
NAMA PEKERJAAN : PENINGKATAN JALAN DAN SLOPE PROTECTION
NAMA KEGIATAN : PENGEMBANGAN DAN PENINGKATAN PERLUASAN KESEMPATAN KERJA
INFRASTRUKTUR PEDESAAN PADAT PEKERJA I
LOKASI PEKERJAAN : KELURAHAN MATTIRO DECENG KECAMATAN TIROANG KABUPATEN PINRANG
SKPD : DINAS TENAGA KERJA DAN TRANSMIGRASI KABUPATEN PINRANG
B. PEKERJAAN KONSTRUKSI
1 Batu Belah 96.53 M³ 157,500.00 15,202,687.50 18.00
2 Pasir Pasang 102.23 M 3
112,350.00 11,485,989.90 13.60
3 Portland Cement (Pc) 50 Kg 387.20 Zak 68,250.00 26,426,400.00 31.29
53,115,077.40 62.89
C PEMBELIAN PERALATAN
1 Cangkul 8.00 Bh 80,000.00 640,000.00 0.76
2 Sekop 4.00 Bh 90,000.00 360,000.00 0.43
3 Gerobak Dorong 4.00 Bh 600,000.00 2,400,000.00 2.84
4 Sendok Semen 5.00 Bh 30,000.00 150,000.00 0.18
5 Linggis 3.00 Bh 150,000.00 450,000.00 0.53
4,000,000.00 4.74
DELAPAN PULUH DELAPAN JUTA EMPAT RATUS ENAM PULUH DUA RIBU RUPIAH"
HARDIANSYAH, ST
DAFTAR
HARGA BAHAN / MATERIAL
NAMA PEKERJAAN : PENINGKATAN JALAN DAN SLOPE PROTECTION
NAMA KEGIATAN : PENGEMBANGAN DAN PENINGKATAN PERLUASAN KESEMPATAN KERJA
INFRASTRUKTUR PEDESAAN PADAT PEKERJA I
LOKASI PEKERJAAN : KELURAHAN MATTIRO DECENG KECAMATAN TIROANG KABUPATEN PINRANG
SKPD : DINAS TENAGA KERJA DAN TRANSMIGRASI KABUPATEN PINRANG
DAFTAR HARGA
UANG PERANGSANG KERJA
#NAME?
Rp -
MATTIRO DECENG
GALIAN PROTEKSI
Dikali = 1.00 Bh
Jumlah = 66.00 M3
PASANGAN BATU 1 PC : 4 PS
PROTEKSI
KOPERAN TEGAK
Dikali = 1.00 M3
Jumlah = 42.90 M3
PLASTERAN
PROTEKSI
Lebar = 0.25 M
Lebar = 0.40 M
0.65
Dikali = 4.00
Jumlah = 858.00 M2
REKAPITULASI VOLUME
1 VOLUME GALIAN
PASANGAN BATU
KOPERAN 39.60
PROTEKSI 42.90
82.50
PLASTERAN
PROTEKSI 858.00
1 82.50 Pasir
290.4 50
102.23 Pasir
387.20 Semen
LEMBAR PERHITUNGAN (CALCULATION
NAMA PEKERJAAN :
NAMA KEGIATAN :
LOKASI PEKERJAAN :
SKPD / T. A. :
88,462,000.0
-
CALCULATION VOLUME)