RENCANA ANGGARAN BIAYA (RAB)

No ITEM URAIAN BAHAN Volume Harga Jumlah


1 PAPAN PAPAN MAL PONDASI 1 KUBIK 1,700,000 1,700,000
BESI PONDASI 010 16 BATANG 85,000 1,360,000
BESI PONDASI 08 22 BATANG 85,000 990,000
BESI TIANG 010 8 BATANG 45,000 680,000
BESI TIANG 08 2 BATANG 85,000 170,000
2 BESI
BESI RING BALOK 08 16 BATANG 45,000 720,000
BESI RING BALOK 06 15 BATANG 45,000 675,000
KAWAT IKAT 8 KG 18,000 144,000
PAKU 15 KG 270,000
125 SAK 67,000 8,375,000
3 SEMEN

TANAH TIMBUN 4 MOBIL 300,000 1,200,000


4 PASIR PASIR 7 TRUK 300,000 2,100,000
KRIKIL 3 TRUK 350,000 1,050,000
5 DINDING DINDING BATA MERAH 10.000 BUAH 500 5,000,000
JENDELA 10 LUBANG 250,000 2,500,000
6 KUZEN
PINTU 2 LUBANG 250,000 500,000
5X10 1,3 M 2,250,000
7 KAYU 5X7 1M 1,700,000
4X6 1M 1,700,000
8 LES PLANG 3X25 8 LEMBAR 65,000 520,000
9 ATAP ATAP 132 M 36,000 4,752,000
TRIPLEK 26 LEMBAR 75,000 1,820,000
10 PLAFON
PAKU TRIPLEK 1 KG 18,000 18,000
CAT DINDING 4 KALENG 25 KG 950,000 3,800,000
11 CAT
CAT KUZEN 5 KG 65,000 300,000
12 LANTAI KERAMIK 40X40 75 KOTAK 65,000 4,875,000
13

PINTU 2 BUAH 600,000 1,200,000


JENDELA 10 BUAH 250,000 2,500,000
KUNCI 2 SET 150,000 300,000
14 PINTU GERENDEL PINTU 4 SET 15,000 60,000
GERENDEL JENDELA 20 SET 10,000 200,000
KAIT ANGIN 20 BUAH 8,000 180,000

11 Tukang BIAYA 72 M 550,000 39,600,000


12 BIAYA TOTAL 93,209,000