Book 9
Book 9
No : 255(B)/PEN/AJT/IX/2023 4-Sep-2023
Kepada Yth
PT. YAMAHA MOTOR ELECTRONICS INDONESIA
Kawasan Industrial MM2100
Cikarang barat bekasi
Up. : Bpk. Joko, Bpk. Akbar.
Cc. : Mr. Gekka Hiromichi
: Bpk. Kesuma
Hal. : Penawaran harga
Dengan Hormat ,
Berdasarkan permintaan dari PT. YAMAHA MOTOR ELECTRONICS INDONESIA maka kami ajukan penawaran harga
dengan perincian sebagai berikut:
A. MATERIAL
Partition gypsum 37.44 m2 214,500 8,030,880
Painting material (JOTUN) 74.88 m2 75,000 5,616,000
Supporting material 1 lot 2,400,000 2,400,000
Miscellaneous material 1 lot 1,600,000 1,600,000
SUB TOTAL MATERIAL (A.) 17,646,880
B. LABOUR FEE
Installation material 1 lot 11,250,000 11,250,000
Transportation 1 lot 1,800,000 1,800,000
Temporary Work 1 lot 600,000 600,000
Unloading 1 lot 400,000 400,000
SUB TOTAL LABOUR (B.) 14,050,000
SUNHAJI
Hp 081388965106