Kegiatan : PENGADAAN DAN PEMASANGAN JARINGAN INTERNET DAN INTRANET PEMERINTAH KABUPATEN BUTON TENGAH
Pekerjaan : PENGADAAN MENARA ANTEN JARINGAN INTERNET KAB.BUTON TENGAH
Lokasi : KAB. BUTON TENGAH
Tahun Anggaran : 2018
A PEKERJAAN PENDAHULUAN
B PEKERJAAN TANAH
C PEKERJAAN STRUKTUR
1 Pemasangan tower Segi empat labrang (30 Meter/10 Stage) Stage 5.0 55,743,375.00 278,716,875
Total = ( A + B + C + D + E + F ) 1,086,519,014
Dibulatkan 1,086,519,000
LA OTA, S.Pd
NIP. 19720911 199802 1 002
B.1
Menggali 1 M 3 Tanah Keras Sedalam 1 M
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
( RUPIAH ) ( RUPIAH )
A TENAGA
1 Pekerja L.01 OH 1.0000 90,000 90,000
2 Mandor L.04 OH 0.0320 110,000 3,520
HARGA JUMLAH
NO URAIAN KODE SATUAN KOEFISIEN SATUAN HARGA
( RUPIAH ) ( RUPIAH )
A TENAGA
1 Pekerja L.01 OH 1.0000 90,000 90,000
2 Mandor L.04 OH 0.0320 110,000 3,520
HARGA JUMLAH
NO URAIAN KODE SAT UAN KOEFISIEN SAT UAN HARGA
( RUPIAH ) ( RUPIAH )
A TENAGA
1 Pekerja L.01 OH 0.6800 Rp 90,000.00 Rp 61,200.00
2 T ukang Batu L.02 OH 0.2900 Rp120,000.00 Rp 34,800.00
3 Kepala T ukang L.03 OH 0.0290 Rp125,000.00 Rp 3,625.00
4 Mandor L.04 OH 0.0290 Rp110,000.00 Rp 3,190.00
JUMLAH TENAGA KERJA Rp 102,815.00
B BAHAN
1 Batu Gunung M3 1.2000 Rp255,000.00 Rp 306,000.00
3
2 Pasir Urug M 0.5440 Rp225,000.00 Rp 122,400.00
JUMLAH HARGA BAHAN Rp 428,400.00
C PERALATAN
Rp -
JUMLAH HARGA ALAT Rp -
HARGA
JUMLAH HARGA
NO URAIAN KODE SATUAN KOEFISIEN SATUAN
( RUPIAH ) ( RUPIAH )
A TENAGA
1 Pekerja L.01 OH 3.4000 Rp 90,000.00 Rp 306,000.00
2 Tukang Batu L.02 OH 0.8500 Rp120,000.00 Rp 102,000.00
3 Kepala Tukang L.03 0.0850 Rp125,000.00 Rp 10,625.00
4 Mandor L.04 0.1700 Rp110,000.00 Rp 18,700.00
JUMLAH TENAGA KERJA Rp 437,325.00
B BAHAN
1 Batu Gunung / Kali M3 1.1000 Rp250,000.00 Rp 275,000.00
1 Semen Portland Kg 143.0000 Rp 1,500.00 Rp 214,500.00
3
2 Pasir Beton M 0.3120 Rp250,000.00 Rp 78,000.00
JUMLAH HARGA BAHAN Rp 292,500.00
C PERALATAN
A TENAGA
1 Pekerja L.01 OH 3.4000 Rp 90,000.00 Rp 306,000.00
2 Tukang Batu L.02 OH 0.8500 Rp 120,000.00 Rp 102,000.00
3 Kepala Tukang L.03 0.0850 Rp 125,000.00 Rp 10,625.00
4 Mandor L.04 0.1700 Rp 110,000.00 Rp 18,700.00
JUMLAH TENAGA KERJA Rp 437,325.00
B BAHAN
1 Semen Portland Kg 143.0000 Rp 1,500.00 Rp 214,500.00
2 Pasir Beton M3 0.3120 Rp 250,000.00 Rp 78,000.00
3 Kerikil M3 0.4680 Rp 300,000.00 Rp 140,400.00
4 Besi Beton Kg 140.0000 Rp 17,000.00 Rp 2,380,000.00
5 Kawat Beton Kg 2.0000 Rp 17,000.00 Rp 34,000.00
6 Besi Kanal U uk.5x10 cm Kg 21.0000 Rp 17,000.00 Rp 357,000.00
JUMLAH HARGA BAHAN Rp 3,203,900.00
C PERALATAN
Rp -
JUMLAH HARGA ALAT Rp -
A TENAGA
1 Jasa pemasangan Instalasi tower Stage 10.00 Rp 750,000.00 Rp 7,500,000.00
JUMLAH TENAGA KERJA Rp 7,500,000.00
B BAHAN
1 Tower besi Siku Uk.3 mm (fourangle) 40x40, 3m per stage Stage 10.00 Rp 1,550,000.00 Rp 15,500,000.00
2 Kipas Caping dan segel caping bh 4.00 Rp 150,000.00 Rp 600,000.00
3 Jarum keras N0. 12 (Turn Buckle) pcs 30.00 Rp 27,000.00 Rp 810,000.00
4 Kawat Slink Baja 6 mm set 1.50 Rp 14,200,000.00 Rp 21,300,000.00
5 Segel/ klam Slink 6mm (kuku Macan) pcs 205.00 Rp 7,500.00 Rp 1,537,500.00
6 Baut / nut uk.19 x 15 cm pcs 50.00 Rp 17,500.00 Rp 875,000.00
7 Ring Baut / nut uk.19 x 15 cm pcs 100.00 Rp 3,500.00 Rp 350,000.00
JUMLAH HARGA BAHAN Rp 40,972,500.00
C PERALATAN
Rp -
JUMLAH HARGA ALAT Rp -
A TENAGA
1 Jasa instalasi Penangkal Petir Stage 1.00 Rp 1,200,000.00 Rp 1,200,000.00
JUMLAH TENAGA KERJA Rp 1,200,000.00
B BAHAN
1 Kabel Grounding 6mm mtr 45.00 Rp 75,000.00 Rp 3,375,000.00
2 Tali grounding pembagi mtr 40.00 Rp 35,000.00 Rp 1,400,000.00
3 Pipa splitz penangkal petir pcs 1.00 Rp 150,000.00 Rp 150,000.00
4 Splitz penangkal petir pcs 1.00 Rp 100,000.00 Rp 100,000.00
5 Stick rood grounding 16mm Btg 4.00 Rp 1,200,000.00 Rp 4,800,000.00
6 Clamp pcs 10.00 Rp 40,000.00 Rp 400,000.00
7 Scound pcs 4.00 Rp 15,000.00 Rp 60,000.00
8 Isolator pcs 1.00 Rp 25,000.00 Rp 25,000.00
9 Box Kontrol (beton) unit 1.00 Rp 350,000.00 Rp 350,000.00
10 wisbar grounding pcs 2.00 Rp 256,000.00 Rp 512,000.00
JUMLAH HARGA BAHAN Rp 11,172,000.00
C PERALATAN
Rp -
JUMLAH HARGA ALAT Rp -
D.3
Pemasangan Solar Cell
A TENAGA
1 Jasa instalasi Solar Cell Paket 1.00 Rp 1,200,000.00 Rp 1,200,000.00
JUMLAH TENAGA KERJA Rp 1,200,000.00
B BAHAN
SOLAR CELL PAKET LISTRIK 400 WATT TENAGA SURYA, PAKET SOLAR
1 Paket 1.00 Rp 11,500,000.00 Rp 11,500,000.00
HOME SYSTEM 100 WP
A TENAGA
1 Jasa instalasi Jaringan Paket 1.00 Rp 5,000,000.00 Rp 5,000,000.00
JUMLAH TENAGA KERJA Rp 5,000,000.00
B BAHAN
1 L 2 SWITCH support L3 lengkap dgn SFP (L 2 SWITCH support L3= 20 Buah, SFP = 40 buah) Pcs 5.00 Rp 10,460,000.00 Rp 52,300,000.00
2 Radio AP outdoor 600 mv 2,4 gHz UBIQUITI LiteBeam Set 5.00 Rp 10,450,000.00 Rp 52,250,000.00
HOTSPOT UBIQUITI Nanostation M2 /UBNT NanostationM2 access point outdoor Ubiquiti
3 Set 5.00 Rp 2,540,000.00 Rp 12,700,000.00
Network
4 Bandwith 20 mbps astinet PT Teklom Indonesia bln 12.00 Rp 36,048,000.00 Rp 432,576,000.00
JUMLAH HARGA BAHAN Rp 549,826,000.00
C PERALATAN
Rp -
JUMLAH HARGA ALAT Rp -