KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT

DIREKTORAT JENDERAL BINA MARGA


BALAI PELAKSANAAN JALAN NASIONAL SULAWESI TENGGARA
SATUAN KERJA PELAKSANAAN JALAN NASIONAL WIL I SULTRA
PPK 1.3 PROV. SULAWESI TENGGARA

REKAPITULASI LAPORAN KEMAJUAN PEKERJAAN


NAMA PAKET : PRESERVASI JALAN POMALAA - WOLULU
RUAS : POMALAA - WOLULU
KONTRAKTOR : PT. LINCE ROMAULI RAYA - PT. AGUNG SARANA PERSADA (KSO)
NO. KONTRAK : HK 0201-Bb21.1.3/286, Tanggal 17 Mei 2022
KONSULTAN : PT.UMUM
KEMENTERIAN PEKERJAAN TRIBINA MATRA CARYA
DAN PERUMAHAN RAKYAT CIPTA KSO PT. WINSOLUSI KONSULTAN -
PT. ARISTA CIPTA
DIREKTORAT JENDERAL BINA MARGA
BALAI PELAKSANAAN JALAN NASIONAL SULAWESI TENGGARA
SATUAN KERJA PELAKSANAAN JALAN NASIONAL WIL I SULTRA
REALISASI
PPK 1.3 PROV. KEMAJUAN
PEKERJAAN MINGGU KE 62 (19 Agustus - 25 Agustus 2023)
SULAWESI TENGGARA
BOBOT (%)
NO. OUTPUT PEKERJAAN
RENCANA REALISASI DEVIASI
I KONTRAK INDUK GABUNGAN 72.682 67.116 -5.566

1. PELEBARAN JALAN 72.565 67.010 -5.555

2. PEMELIHARAAN JALAN 80.909 75.715 -5.194

3. PEMELIHARAAN JEMBATAN 76.329 64.529 -11.800

II KONTRAK TAHUN 2023 59.206 57.227 -1.979

1. PELEBARAN JALAN 59.122 59.236 0.115

2. PEMELIHARAAN JALAN 65.239 92.154 26.915

3. PEMELIHARAAN JEMBATAN 66.900 60.612 -6.288

Disetujui Diperiksa Disiapkan


Direksi PUPR Konsultan Supervisi Kontraktor
PPK 1.3 Provinsi Sulawesi Tenggara PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI PT. LINCE ROMAULI RAYA - PT.
KONSULTAN - PT. ARISTA CIPTA AGUNG SARANA PERSADA (KSO)

DOLLY HUMADA SIREGAR, ST Ir. MUHAMMAD IDRIS RAZAK RISKY KURNIAWAN, ST


NIP. : 19760106 201410 1 001 Supervision Engineer Manager Proyek
PROGRES BULAN AGUSTUS 2023
NAMA PAKET : PRESERVASI JALAN POMALAA - WOLULU 16
RUAS : POMALAA - WOLULU
KONTRAKTOR : PT. LINCE ROMAULI RAYA - PT. AGUNG SARANA PERSADA (KSO) MINGGU KE : 62
KONSULTAN : PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI KONSULTAN - PT. ARISTA CIPTA Periode : 19 Agustus - 25 Agustus 2023
NO. KONTRAK : HK 0201-Bb21.1.3/286, Tanggal 17 Mei 2022

PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-06 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
15S/D BULAN 15BULAN 16INI 15INI
I DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 500,000,000.00 500,000,000.00 0.4189 0.700 - 0.700 0.293 - 0.293 350,000,000.00
1.80 Manajemen dan Keselamatan Lalu Lintas Ls 1.00 100,000,000.00 100,000,000.00 0.0838 0.597 0.010 0.607 0.050 0.001 0.051 60,736,842.11
1.17 Pengamanan Lingkungan Hidup
1.17.(1a) Pengujian pH Buah 9.00 70,000.00 630,000.00 0.0005 6.000 - 6.000 0.000 - 0.000 420,000.00
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 9.00 100,000.00 900,000.00 0.0008 6.000 - 6.000 0.001 - 0.001 600,000.00
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 9.00 150,000.00 1,350,000.00 0.0011 6.000 - 6.000 0.001 - 0.001 900,000.00
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 9.00 100,000.00 900,000.00 0.0008 6.000 - 6.000 0.001 - 0.001 600,000.00
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 9.00 140,000.00 1,260,000.00 0.0011 6.000 - 6.000 0.001 - 0.001 840,000.00
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 9.00 140,000.00 1,260,000.00 0.0011 6.000 - 6.000 0.001 - 0.001 840,000.00
1.17.(2c) Pengujian Parameter Kebisingan dan/atau Getaran Lainnya ……… Buah 9.00 140,000.00 1,260,000.00 0.0011 6.000 - 6.000 0.001 - 0.001 840,000.00
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 9.00 200,000.00 1,800,000.00 0.0015 6.000 - 6.000 0.001 - 0.001 1,200,000.00
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 9.00 125,000.00 1,125,000.00 0.0009 6.000 - 6.000 0.001 - 0.001 750,000.00
1.19 Keselamatan dan Kesehatan Kerja
1.00 1. Penyiapan RKK Buah 1.00 3,000,000.00 3,000,000.00 0.0025 1.000 - 1.000 0.003 - 0.003 3,000,000.00
2.00 2. Sosialisasi dan Promosi Dan Pelatihan Buah 1.00 5,000,000.00 5,000,000.00 0.0042 - - - - - - -
3.00 3. Alat Pelindung Kerja (APK) dan Alat Pelindung Diri (APD) Buah 1.00 35,000,000.00 35,000,000.00 0.0293 0.525 0.007 0.532 0.015 0.000 0.016 18,616,096.76
4.00 4. Asuransi dan Perizinan Buah 1.00 20,000,000.00 20,000,000.00 0.0168 1.000 - 1.000 0.017 - 0.017 20,000,000.00
5.00 5. Personel K3 Konstruksi Buah 1.00 99,000,000.00 99,000,000.00 0.0829 0.506 0.007 0.513 0.042 0.001 0.043 50,795,027.90
6.00 6. Fasilitas sarana kesehatan Buah 1.00 15,000,000.00 15,000,000.00 0.0126 - - - - - - -
7.00 7. Rambu-rambu terdiri atas Buah 1.00 22,727,272.73 22,727,272.73 0.0190 0.537 0.006 0.544 0.010 0.000 0.010 12,359,323.59
8.00 8. Konsultasi dengan Ahli Terkait Keselamatan Konstruksi Buah 1.00 15,000,000.00 15,000,000.00 0.0126 - - - - - - -
9.00 9. Lain-lain terkait pengendalian risiko K3 Buah 1.00 5,000,000.00 5,000,000.00 0.0042 - - - - - - -
1.21 Manajemen Mutu Ls 1.00 200,000,000.00 200,000,000.00 0.1676 0.613 0.010 0.623 0.103 0.002 0.104 124,500,000.00
Sub Total ( 1 ) 1,030,212,272.73 0.8631 0.539 0.003 0.542 646,997,290.36
II DIVISI 2. DRAINASE 16,928.000 187.000 16,774.000
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 11,009.65 25,000.00 275,241,150.00 0.2306 8,990.154 101.354 9,091.508 0.188 0.002 0.190 227,287,700.00
2.2.(1) Pasangan Batu dengan Mortar M3 8,363.10 700,000.00 5,854,170,000.00 4.9047 6,092.734 85.459 6,178.193 3.573 0.050 3.623 4,324,735,107.00
2.3.(15) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 100 cm x 100 cm M1 134.40 4,275,906.49 574,681,832.26 0.4815 60.000 18.000 78.000 0.215 0.064 0.279 333,520,706.22
2.3.(18) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 150 cm x 150 cm M1 354.00 7,268,205.12 2,572,944,612.48 2.1556 319.200 12.000 331.200 1.944 0.073 2.017 2,407,229,535.74
2.3.(20) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 250 cm x 250 cm M1 13.20 42,718,794.10 563,888,082.12 0.4724 - 13.200 13.200 - 0.472 0.472 563,888,082.12
2.3.(22) Saluran berbentuk U Tipe DS 1 (precast) M1 5,575.00 1,250,000.00 6,968,750,000.00 5.8385 4,391.000 121.000 4,512.000 4.599 0.127 4.725 5,640,000,000.00
Sub Total ( 2 ) 16,809,675,676.86 14.0833 10.519 0.789 11.308 13,496,661,131.08
III DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3.1.(1a) Galian Biasa M3 94,032.95 16,000.00 1,504,527,200.00 1.2605 59,331.791 77.400 59,409.191 0.795 0.001 0.796 950,547,060.27
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 15,331.32 100,000.00 1,533,132,000.00 1.2845 12,947.429 - 12,947.429 1.085 - 1.085 1,294,742,935.90
3.3.(1) Penyiapan Badan Jalan M2 88,172.79 5,000.00 440,863,950.00 0.3694 59,823.470 209.189 60,032.660 0.251 0.001 0.251 300,163,297.52
3.4.(2) Pemotongan Pohon Pilihan diameter 15 – 30 cm Buah 147.00 39,983.05 5,877,508.35 0.0049 116.000 24.000 140.000 0.004 0.001 0.005 5,597,627.00
3.4.(3) Pemotongan Pohon Pilihan diameter > 30 – 50 cm Buah 218.00 61,536.34 13,414,922.12 0.0112 60.000 - 60.000 0.003 - 0.003 3,692,180.40
3.4.(4) Pemotongan Pohon Pilihan diameter > 50 – 75 cm Buah 390.00 112,032.53 43,692,686.70 0.0366 207.000 19.000 226.000 0.019 0.002 0.021 25,319,351.78
3.4.(5) Pemotongan Pohon Pilihan diameter > 75 cm Buah 78.00 233,248.73 18,193,400.94 0.0152 52.000 - 52.000 0.010 - 0.010 12,128,933.96
Sub Total ( 3 ) 3,559,701,668.11 2.9824 2.167 0.005 2.172 2,592,191,386.83

2 / 16
PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-06 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
V DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN #REF! #REF!
5.1.(1) Lapis Fondasi Agregat Kelas A M3 24,285.05 600,000.00 14,571,030,816.00 12.2078 20,499.700 280.800 20,780.500 10.305 0.141 10.446 12,468,300,000.00
5.1.(3a) Lapis Fondasi Agregat Kelas S M3 15,031.93 250,000.00 3,757,982,500.00 3.1485 5,050.785 140.625 5,191.410 1.058 0.029 1.087 1,297,852,500.00
Sub Total ( 5 ) 18,329,013,316.00 15.3562 11.363 0.171 11.533 13,766,152,500.00
VI DIVISI 6. PERKERASAN ASPAL
6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair Liter 65,866.87 15,000.00 988,003,079.40 0.8278 45,811.251 2,337.989 48,149.240 0.576 0.029 0.605 722,238,605.37
6.1 (2)(a) Lapis Perekat - Aspal Cair Liter 68,220.25 13,000.00 886,863,250.00 0.7430 45,448.930 949.223 46,398.153 0.495 0.010 0.505 603,175,987.77
6.3.(8) Bahan anti pengelupasan Kg 3,983.28 75,000.00 298,745,827.03 0.2503 2,125.448 52.147 2,177.594 0.134 0.003 0.137 163,319,584.89
6.5.(1b) Laston Lapis Aus Asbuton Butir (AC-WC Asb Butir) Ton 22,538.67 1,425,000.00 32,117,602,968.75 26.9085 17,975.170 310.396 18,285.566 21.460 0.371 21.831 26,056,931,550.00
6.5.(2b) Laston Lapis Antara Asbuton Butir (AC-BC Asb Butir) Ton 12,814.17 1,350,000.00 17,299,127,228.88 14.4934 9,785.780 468.270 10,254.050 11.068 0.530 11.598 13,842,967,500.00

Sub Total ( 6 ) 51,590,342,354.06 43.2229 33.733 0.943 34.676 41,388,633,228.03


VII DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 Mpa (Kubus 60 x 60 x 60) M3 438.48 3,557,765.22 1,560,008,893.67 1.3070 - - - - - - -
7.1 (6a) Beton struktur, fc’25 Mpa (untuk penutup saluran) M3 576.00 1,700,000.00 979,200,000.00 0.8204 - - - - - - -
7.1 (7a) Beton struktur, fc’20 MPa (untuk bahu diperkeras) M3 2,654.17 1,125,000.00 2,985,941,250.00 2.5017 - - - - - - -
7.1 (7d) Beton struktur, fc’20 Mpa (untuk pengaman pantai) M3 583.60 3,494,109.91 2,039,177,917.56 1.7084 - - - - - - -
7.1 (9) Beton Siklop, fc’15 Mpa (untuk pengaman pantai) M3 133.93 893,667.17 119,688,844.08 0.1003 - - - - - - -
7.1 (10) Beton, fc’10 Mpa M3 - 1,100,000.00 - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 82,775.89 19,000.00 1,572,741,910.00 1.3177 - - - - - - -
7.3 (3) Baja Tulangan Ulir-BjTS 420 A Kg 27,677.40 20,934.10 579,401,459.34 0.4854 - - - - - - -
7.9.(1) Pasangan Batu M3 14,773.75 650,000.00 9,602,935,415.14 8.0454 9,733.468 251.210 9,984.678 5.301 0.137 5.437 6,490,040,700.00
7.10.(3a) Bronjong dengan kawat yang dilapisi Galvanis M3 500.00 725,000.00 362,500,000.00 0.3037 - - - - - - -
7.15.(1) Pembongkaran Pasangan Batu M3 869.00 304,690.52 264,776,061.88 0.2218 697.430 11.760 709.190 0.178 0.003 0.181 216,083,469.88
7.15.(2) Pembongkaran Beton M3 94.73 316,550.08 29,986,789.08 0.0251 35.000 5.620 40.620 0.009 0.001 0.011 12,858,264.25
Sub Total ( 7 ) 20,096,358,540.74 16.8369 5.488 0.141 5.629 6,718,982,434.13

IX DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN


9.1 Pekerjaan Harian
9.1.(2) Pekerja Biasa Jam 84.00 18,750.00 1,575,000.00 0.0013 - - - - - - -
9.1.(4) a Dump Truck, kapasitas 3 - 4 m³ Jam 84.00 200,000.00 16,800,000.00 0.0141 - - - - - - -
9.1.(6) Truk Tangki 3000 - 4500 Liter Jam 84.00 200,000.00 16,800,000.00 0.0141 - - - - - - -
9.1.(8) Motor Grader min 100 PK Jam 126.00 200,000.00 25,200,000.00 0.0211 5.000 - 5.000 0.001 - 0.001 1,000,000.00
9.1.(9) Loader Roda Karet 1.0 - 1.6 M3 Jam 126.00 200,000.00 25,200,000.00 0.0211 - - - - - - -
9.1.(13) Penggilas Roda Besi 6 - 9 Ton Jam 84.00 200,000.00 16,800,000.00 0.0141 5.000 - 5.000 0.001 - 0.001 1,000,000.00
9.2 Pekerjaan Lain-Lain
9.2.(1) Marka Jalan Termoplastik M2 12,284.04 120,000.00 1,474,084,800.00 1.2350 1,211.320 - 1,211.320 0.122 - 0.122 145,358,400.00
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grad Buah 144.00 450,000.00 64,800,000.00 0.0543 - - - - - - -
9.2.(5) Patok Pengarah, material Poly Ethylene (PE) Plastik murni/elastis Buah 1,490.00 300,000.00 447,000,000.00 0.3745 - - - - - - -
9.2.(6a) Patok Kilometer Buah 32.00 350,000.00 11,200,000.00 0.0094 - - - - - - -
9.2.(7) Rel Pengaman M1 4,072.80 850,000.00 3,461,880,000.00 2.9004 - - - - - - -
9.2(10a) Kerb Pracetak Jenis 1 (Peninggi/Mountable) M1 2,000.00 115,000.00 230,000,000.00 0.1927 - - - - - - -
9.2.(12a) Perkerasan Blok Beton pada Trotoar dan Median M2 2,400.00 135,000.00 324,000,000.00 0.2715 - - - - - - -
Sub Total ( 9 ) 6,115,339,800.00 5.1235 0.123 - 0.123 147,358,400.00

3 / 16
PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-06 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
X DIVISI10. PEKERJAAN PEMELIHARAAN
10.1 Pemeliharaan Jalan
10.1.(3) Perbaikan Pasangan Batu dengan Mortar M3 280.76 1,270,455.74 356,687,180.87 0.2988 - - - - - - -
10.1.(4) Perbaikan Lapis Fondasi Agregat Kelas A M3 130.61 600,000.00 78,366,000.00 0.0657 131.400 - 131.400 0.066 - 0.066 78,840,000.00
10.1.(10a) Perbaikan Campuran Aspal Panas dengan Asbuton M3 201.26 2,900,000.00 583,654,000.00 0.4890 214.095 - 214.095 0.520 - 0.520 620,874,129.18
10.1.(10b) Perbaikan Campuran Aspal Panas dengan Asbuton M3 29.80 3,200,000.00 95,359,994.13 0.0799 22.000 - 22.000 0.059 - 0.059 70,400,000.00
10.1.(21) Pembersihan Drainase dan Saluran Samping M1 29,383.09 5,500.00 161,606,995.00 0.1354 28,033.700 - 28,033.700 0.129 - 0.129 154,185,350.00
10.1.(22) Pengendalian Tanaman M2 519,937.66 500.00 259,968,830.00 0.2178 476,836.800 - 476,836.800 0.200 - 0.200 238,418,400.00
10.2 Pemeliharaan Jembatan
10.2.(1) Pemeliharaan Jembatan S SOPURA BOX Bentang 7 m LS 1.00 5,000,000.00 5,000,000.00 0.0042 0.645 - 0.645 0.003 - 0.003 3,226,428.57
10.2.(2) Pemeliharaan Jembatan S.SOPURA Bentang 20.8 m LS 1.00 22,000,000.00 22,000,000.00 0.0184 0.645 - 0.645 0.012 - 0.012 14,196,285.71
10.2.(3) Pemeliharaan Jembatan S.OKO-OKO I Bentang 9.8 m LS 1.00 12,500,000.00 12,500,000.00 0.0105 0.645 - 0.645 0.007 - 0.007 8,066,071.43
10.2.(4) Pemeliharaan Jembatan S.Oko-Oko II Bentang 8.9 m LS 1.00 10,000,000.00 10,000,000.00 0.0084 0.645 - 0.645 0.005 - 0.005 6,452,857.14
10.2.(5) Pemeliharaan Jembatan S.Oko-Ok0 III Bentang 20.8 m LS 1.00 25,000,000.00 25,000,000.00 0.0209 0.645 - 0.645 0.014 - 0.014 16,132,142.86
10.2.(6) Pemeliharaan Jembatan S.Oko-Oko IV Bentang 9.8 m LS 1.00 10,000,000.00 10,000,000.00 0.0084 0.645 - 0.645 0.005 - 0.005 6,452,857.14
10.2.(7) Pemeliharaan Jembatan S.Oko-Oko V Bentang 9.7 m LS 1.00 12,000,000.00 12,000,000.00 0.0101 0.645 - 0.645 0.006 - 0.006 7,743,428.57
10.2.(8) Pemeliharaan Jembatan S.Oko-Oko VI Bentang 6.8 m LS 1.00 9,000,000.00 9,000,000.00 0.0075 0.645 - 0.645 0.005 - 0.005 5,807,571.43
10.2.(9) Pemeliharaan Jembatan S.Lamedai I Bentang 8.9 m LS 1.00 11,500,000.00 11,500,000.00 0.0096 0.645 - 0.645 0.006 - 0.006 7,420,785.71
10.2.(10) Pemeliharaan Jembatan S.Lamedai II Bentang 8.9 m LS 1.00 11,500,000.00 11,500,000.00 0.0096 0.645 - 0.645 0.006 - 0.006 7,420,785.71
10.2.(11) Pemeliharaan Jembatan S.Box Tanggetada Bentang 6.9 m LS 1.00 6,000,000.00 6,000,000.00 0.0050 0.645 - 0.645 0.003 - 0.003 3,871,714.29
10.2.(12) Pemeliharaan Jembatan S.Tangketada Bentang 8.8 m LS 1.00 10,000,000.00 10,000,000.00 0.0084 0.645 - 0.645 0.005 - 0.005 6,452,857.14
10.2.(13) Pemeliharaan Jembatan S.Anaiwoi I Bentang 8.9 m LS 1.00 10,000,000.00 10,000,000.00 0.0084 0.645 - 0.645 0.005 - 0.005 6,452,857.14
10.2.(14) Pemeliharaan Jembatan S.Anaiwoi II Bentang 15.8 m LS 1.00 12,000,000.00 12,000,000.00 0.0101 0.645 - 0.645 0.006 - 0.006 7,743,428.57
10.2.(15) Pemeliharaan Jembatan S.Oneha I Bentang 10.3 m LS 1.00 10,000,000.00 10,000,000.00 0.0084 0.645 - 0.645 0.005 - 0.005 6,452,857.14
10.2.(16) Pemeliharaan Jembatan S.Oneha II Bentang 9.2 m LS 1.00 10,000,000.00 10,000,000.00 0.0084 0.645 - 0.645 0.005 - 0.005 6,452,857.14
10.2.(17) Pemeliharaan Jembatan S.Oneha III Bentang 8.7 m LS 1.00 10,000,000.00 10,000,000.00 0.0084 0.645 - 0.645 0.005 - 0.005 6,452,857.14
10.2.(18) Pemeliharaan Jembatan S.Oneha IV Bentang 12.8 m LS 1.00 13,000,000.00 13,000,000.00 0.0109 0.645 - 0.645 0.007 - 0.007 8,388,714.29
10.2.(19) Pemeliharaan Jembatan S.Oneha V Bentang 10.9 m LS 1.00 13,000,000.00 13,000,000.00 0.0109 0.645 - 0.645 0.007 - 0.007 8,388,714.29
10.2.(20) Pemeliharaan Jembatan S.Toengge Bentang 31.2 m LS 1.00 30,000,000.00 30,000,000.00 0.0251 0.645 - 0.645 0.016 - 0.016 19,358,571.43
10.2.(21) Pemeliharaan Jembatan S.Polewali Bentang 11 m LS 1.00 10,000,000.00 10,000,000.00 0.0084 0.645 - 0.645 0.005 - 0.005 6,452,857.14
10.2.(22) Pemeliharaan Jembatan S.Wolulu Bentang 30.3 m LS 1.00 30,000,000.00 30,000,000.00 0.0251 0.645 - 0.645 0.016 - 0.016 19,358,571.43
Sub Total ( 10 ) 1,828,143,000.00 1.5316 1.132 - 1.132 1,351,463,950.61
TOTAL 119,358,786,628.49 100.000 PROGRESS REALISASI 65.064 2.052 67.116 80,108,440,321.04
Pajak Pertambahan Nilai (Ppn) 11% 13,129,466,529.13 PROGRESS RENCANA 70.961 1.720 72.682 8,811,928,435.31
TOTAL 132,488,253,157.63 DEVIASI (5.898) 0.332 (5.566) 88,920,368,756.35
DIBULATKAN 132,488,253,000.00 (0.332) 88,920,368,000.00

Disetujui Diperiksa Disiapkan


Direksi PUPR Konsultan Supervisi Kontraktor
PPK 1.3 Provinsi Sulawesi Tenggara PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI PT. LINCE ROMAULI RAYA - PT.
KONSULTAN - PT. ARISTA CIPTA AGUNG SARANA PERSADA (KSO)

DOLLY HUMADA SIREGAR, ST Ir. MUHAMMAD IDRIS RAZAK RISKY KURNIAWAN, ST


NIP. : 19760106 201410 1 001 Supervision Engineer Manager Proyek

4 / 16
PROGRES BULAN AGUSTUS 2023
NAMA PAKET : PRESERVASI JALAN POMALAA - WOLULU 16
RUAS : POMALAA - WOLULU
KONTRAKTOR : PT. LINCE ROMAULI RAYA - PT. AGUNG SARANA PERSADA (KSO) MINGGU KE : 62
KONSULTAN : PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI KONSULTAN - PT. ARISTA CIPTA Periode : 19 Agustus - 25 Agustus 2023
NO. KONTRAK : HK 0201-Bb21.1.3/286, Tanggal 17 Mei 2022

PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-02 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
15S/D BULAN 15BULAN 16INI INI
I DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 500,000,000.00 500,000,000.00 0.4254 0.700 - 0.700 0.298 - 0.298 350,000,000.00
1.80 Manajemen dan Keselamatan Lalu Lintas Ls 1.00 100,000,000.00 100,000,000.00 0.0851 0.597 0.010 0.607 0.051 0.001 0.052 60,736,842.11
1.17 Pengamanan Lingkungan Hidup
1.17.(1a) Pengujian pH Buah 9.00 70,000.00 630,000.00 0.0005 6.000 - 6.000 0.000 - 0.000 420,000.00
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 9.00 100,000.00 900,000.00 0.0008 6.000 - 6.000 0.001 - 0.001 600,000.00
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 9.00 150,000.00 1,350,000.00 0.0011 6.000 - 6.000 0.001 - 0.001 900,000.00
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 9.00 100,000.00 900,000.00 0.0008 6.000 - 6.000 0.001 - 0.001 600,000.00
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 9.00 140,000.00 1,260,000.00 0.0011 6.000 - 6.000 0.001 - 0.001 840,000.00
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 9.00 140,000.00 1,260,000.00 0.0011 6.000 - 6.000 0.001 - 0.001 840,000.00
1.17.(2c) Pengujian Parameter Kebisingan dan/atau Getaran Lainnya ……… Buah 9.00 140,000.00 1,260,000.00 0.0011 6.000 - 6.000 0.001 - 0.001 840,000.00
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 9.00 200,000.00 1,800,000.00 0.0015 6.000 - 6.000 0.001 - 0.001 1,200,000.00
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 9.00 125,000.00 1,125,000.00 0.0010 6.000 - 6.000 0.001 - 0.001 750,000.00
1.19 Keselamatan dan Kesehatan Kerja
1.00 1. Penyiapan RKK Buah 1.00 3,000,000.00 3,000,000.00 0.0026 1.000 - 1.000 0.003 - 0.003 3,000,000.00
2.00 2. Sosialisasi dan Promosi Dan Pelatihan Buah 1.00 5,000,000.00 5,000,000.00 0.0043 - - - - - - -
3.00 3. Alat Pelindung Kerja (APK) dan Alat Pelindung Diri (APD) Buah 1.00 35,000,000.00 35,000,000.00 0.0298 0.525 0.007 0.532 0.016 0.000 0.016 18,616,096.76
4.00 4. Asuransi dan Perizinan Buah 1.00 20,000,000.00 20,000,000.00 0.0170 1.000 - 1.000 0.017 - 0.017 20,000,000.00
5.00 5. Personel K3 Konstruksi Buah 1.00 99,000,000.00 99,000,000.00 0.0842 0.506 0.007 0.513 0.043 0.001 0.043 50,795,027.90
6.00 6. Fasilitas sarana kesehatan Buah 1.00 15,000,000.00 15,000,000.00 0.0128 - - - - - - -
7.00 7. Rambu-rambu terdiri atas Buah 1.00 22,727,272.73 22,727,272.73 0.0193 0.537 0.006 0.544 0.010 0.000 0.011 12,359,323.59
8.00 8. Konsultasi dengan Ahli Terkait Keselamatan Konstruksi Buah 1.00 15,000,000.00 15,000,000.00 0.0128 - - - - - - -
9.00 9. Lain-lain terkait pengendalian risiko K3 Buah 1.00 5,000,000.00 5,000,000.00 0.0043 - - - - - - -
1.21 Manajemen Mutu Ls 1.00 200,000,000.00 200,000,000.00 0.1702 0.613 0.010 0.623 0.104 0.002 0.106 124,500,000.00

Sub Total ( 1 ) 1,030,212,272.73 0.8765 0.547 0.003 0.550 646,997,290.36


II DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 11,009.65 25,000.00 275,241,150.00 0.2342 8,990.154 101.354 9,091.508 0.191 0.002 0.193 227,287,700.00
2.2.(1) Pasangan Batu dengan Mortar M3 8,363.10 700,000.00 5,854,170,000.00 4.9810 6,092.734 85.459 6,178.193 3.629 0.051 3.680 4,324,735,107.00
2.3.(15) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 100 cm x 100 cm (precast M1 134.40 4,275,906.49 574,681,832.26 0.4890 60.000 18.000 78.000 0.218 0.065 0.284 333,520,706.22
2.3.(18) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 150 cm x 150 cm (precast M1 354.00 7,268,205.12 2,572,944,612.48 2.1892 319.200 12.000 331.200 1.974 0.074 2.048 2,407,229,535.74
2.3.(20) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 250 cm x 250 cm (precast M1 13.20 42,718,794.10 563,888,082.12 0.4798 - 13.200 13.200 - 0.480 0.480 563,888,082.12
2.3.(22) Saluran berbentuk U Tipe DS 1 (precast) M1 5,575.00 1,250,000.00 6,968,750,000.00 5.9293 4,391.000 121.000 4,512.000 4.670 0.129 4.799 5,640,000,000.00
Sub Total ( 2 ) 16,809,675,676.86 14.3024 10.682 0.801 11.484 13,496,661,131.08
III DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1a) Galian Biasa M3 94,032.95 16,000.00 1,504,527,200.00 1.2801 59,331.791 77.400 59,409.191 0.808 0.001 0.809 950,547,060.27
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 15,331.32 100,000.00 1,533,132,000.00 1.3045 12,947.429 - 12,947.429 1.102 - 1.102 1,294,742,935.90
3.3.(1) Penyiapan Badan Jalan M2 88,172.79 5,000.00 440,863,950.00 0.3751 59,823.470 209.189 60,032.660 0.255 0.001 0.255 300,163,297.52
3.4.(2) Pemotongan Pohon Pilihan diameter 15 – 30 cm Buah 147.00 39,983.05 5,877,508.35 0.0050 116.000 24.000 140.000 0.004 0.001 0.005 5,597,627.00
3.4.(3) Pemotongan Pohon Pilihan diameter > 30 – 50 cm Buah 218.00 61,536.34 13,414,922.12 0.0114 60.000 - 60.000 0.003 - 0.003 3,692,180.40
3.4.(4) Pemotongan Pohon Pilihan diameter > 50 – 75 cm Buah 390.00 112,032.53 43,692,686.70 0.0372 207.000 19.000 226.000 0.020 0.002 0.022 25,319,351.78
3.4.(5) Pemotongan Pohon Pilihan diameter > 75 cm Buah 78.00 233,248.73 18,193,400.94 0.0155 52.000 - 52.000 0.010 - 0.010 12,128,933.96
Sub Total ( 3 ) 3,559,701,668.11 3.0287 2.201 0.005 2.206 2,592,191,386.83

5 / 16
PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-02 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
V DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN 1,100.000 #REF!
5.1.(1) Lapis Fondasi Agregat Kelas A M3 24,285.05 600,000.00 14,571,030,816.00 12.3976 20,499.700 280.800 20,780.500 10.465 0.143 10.609 12,468,300,000.00
5.1.(3a) Lapis Fondasi Agregat Kelas S M3 15,031.93 250,000.00 3,757,982,500.00 3.1974 5,050.785 140.625 5,191.410 1.074 0.030 1.104 1,297,852,500.00
Sub Total ( 5 ) 18,329,013,316.00 15.5951 11.540 0.173 11.713 13,766,152,500.00
VI DIVISI 6. PERKERASAN ASPAL
6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair Liter 65,866.87 15,000.00 988,003,079.40 0.8406 45,811.251 2,337.989 48,149.240 0.585 0.030 0.615 722,238,605.37
6.1 (2)(a) Lapis Perekat - Aspal Cair Liter 68,220.25 13,000.00 886,863,250.00 0.7546 45,448.930 949.223 46,398.153 0.503 0.010 0.513 603,175,987.77
6.3.(8) Bahan anti pengelupasan Kg 3,983.28 75,000.00 298,745,827.03 0.2542 2,125.448 52.147 2,177.594 0.136 0.003 0.139 163,319,584.89
6.5.(1b) Laston Lapis Aus Asbuton Butir (AC-WC Asb Butir) Ton 22,538.67 1,425,000.00 32,117,602,968.75 27.3270 17,975.170 310.396 18,285.566 21.794 0.376 22.170 26,056,931,550.00
6.5.(2b) Laston Lapis Antara Asbuton Butir (AC-BC Asb Butir) Ton 12,814.17 1,350,000.00 17,299,127,228.88 14.7188 9,785.780 468.270 10,254.050 11.240 0.538 11.778 13,842,967,500.00
Sub Total ( 6 ) 51,590,342,354.06 43.8952 34.257 0.958 35.215 41,388,633,228.03
VII DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 Mpa (Kubus 60 x 60 x 60) M3 438.48 3,557,765.22 1,560,008,893.67 1.3273 - - - - - - -
7.1 (6a) Beton struktur, fc’25 Mpa (untuk penutup saluran) M3 576.00 1,700,000.00 979,200,000.00 0.8331 - - - - - - -
7.1 (7a) Beton struktur, fc’20 MPa (untuk bahu diperkeras) M3 2,654.17 1,125,000.00 2,985,941,250.00 2.5406 - - - - - - -
7.1 (7d) Beton struktur, fc’20 Mpa (untuk pengaman pantai) M3 583.60 3,494,109.91 2,039,177,917.56 1.7350 - - - - - - -
7.1 (9) Beton Siklop, fc’15 Mpa (untuk pengaman pantai) M3 133.93 893,667.17 119,688,844.08 0.1018 - - - - - - -
7.1 (10) Beton, fc’10 Mpa M3 - 1,100,000.00 - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 82,775.89 19,000.00 1,572,741,910.00 1.3382 - - - - - - -
7.3 (3) Baja Tulangan Ulir-BjTS 420 A Kg 27,677.40 20,934.10 579,401,459.34 0.4930 - - - - - - -
7.9.(1) Pasangan Batu M3 14,773.75 650,000.00 9,602,935,415.14 8.1706 9,733.468 251.210 9,984.678 5.383 0.139 5.522 6,490,040,700.00
7.10.(3a) Bronjong dengan kawat yang dilapisi Galvanis M3 500.00 725,000.00 362,500,000.00 0.3084 - - - - - - -
7.15.(1) Pembongkaran Pasangan Batu M3 869.00 304,690.52 264,776,061.88 0.2253 697.430 11.760 709.190 0.181 0.003 0.184 216,083,469.88
7.15.(2) Pembongkaran Beton M3 94.73 316,550.08 29,986,789.08 0.0255 35.000 5.620 40.620 0.009 0.002 0.011 12,858,264.25
Sub Total ( 7 ) 20,096,358,540.74 17.0988 5.573 0.143 5.717 6,718,982,434.13

6 / 16
PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-02 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
IX DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.1 Pekerjaan Harian
9.1.(2) Pekerja Biasa Jam 84.00 18,750.00 1,575,000.00 0.0013 - - - - - - -
9.1.(4) a Dump Truck, kapasitas 3 - 4 m³ Jam 84.00 200,000.00 16,800,000.00 0.0143 - - - - - - -
9.1.(6) Truk Tangki 3000 - 4500 Liter Jam 84.00 200,000.00 16,800,000.00 0.0143 - - - - - - -
9.1.(8) Motor Grader min 100 PK Jam 126.00 200,000.00 25,200,000.00 0.0214 5.000 - 5.000 0.001 - 0.001 1,000,000.00
9.1.(9) Loader Roda Karet 1.0 - 1.6 M3 Jam 126.00 200,000.00 25,200,000.00 0.0214 - - - - - - -
9.1.(13) Penggilas Roda Besi 6 - 9 Ton Jam 84.00 200,000.00 16,800,000.00 0.0143 5.000 - 5.000 0.001 - 0.001 1,000,000.00
9.2 Pekerjaan Lain-Lain
9.2.(1) Marka Jalan Termoplastik M2 12,284.04 120,000.00 1,474,084,800.00 1.2542 1,211.320 - 1,211.320 0.124 - 0.124 145,358,400.00
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade Buah 144.00 450,000.00 64,800,000.00 0.0551 - - - - - - -
9.2.(5) Patok Pengarah, material Poly Ethylene (PE) Plastik murni/elastis Buah 1,490.00 300,000.00 447,000,000.00 0.3803 - - - - - - -
9.2.(6a) Patok Kilometer Buah 32.00 350,000.00 11,200,000.00 0.0095 - - - - - - -
9.2.(7) Rel Pengaman M1 4,072.80 850,000.00 3,461,880,000.00 2.9455 - - - - - - -
9.2(10a) Kerb Pracetak Jenis 1 (Peninggi/Mountable) M1 2,000.00 115,000.00 230,000,000.00 0.1957 - - - - - - -
9.2.(12a) Perkerasan Blok Beton pada Trotoar dan Median M2 2,400.00 135,000.00 324,000,000.00 0.2757 - - - - - - -
Sub Total ( 9 ) 6,115,339,800.00 5.2032 0.125 - 0.125 147,358,400.00
TOTAL 117,530,643,628.49 100.000 PROGRESS REALISASI 64.926 2.084 67.010 78,756,976,370.43
Pajak Pertambahan Nilai (Ppn) 11% 12,928,370,799.13 PROGRESS RENCANA 70.831 72.565 8,663,267,400.75
TOTAL 130,459,014,427.63 DEVIASI (5.906) 2.084 (5.555) 87,420,243,771.17
DIBULATKAN 130,459,014,000.00 (2.084) 87,420,243,000.00
Disetujui Diperiksa Disiapkan
Direksi PUPR Konsultan Supervisi Kontraktor
PPK 1.3 Provinsi Sulawesi Tenggara PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI PT. LINCE ROMAULI RAYA - PT. AGUNG
KONSULTAN - PT. ARISTA CIPTA SARANA PERSADA (KSO)

SUKARDJO Ir. MUHAMMAD IDRIS RAZAK RISKY KURNIAWAN, ST


NIP. : 19750226 200312 1 002 Supervision Engineer Manager Proyek

7 / 16
PROGRES BULAN AGUSTUS 2023
NAMA PAKET : PRESERVASI JALAN POMALAA - WOLULU 16
RUAS : POMALAA - WOLULU
KONTRAKTOR : PT. LINCE ROMAULI RAYA - PT. AGUNG SARANA PERSADA (KSO) MINGGU KE : 62
KONSULTAN : PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI KONSULTAN - PT. ARISTA CIPTA Periode : 19 Agustus - 25 Agustus 2023
NO. KONTRAK : HK 0201-Bb21.1.3/286, Tanggal 17 Mei 2022

PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-02 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
15S/D BULAN 15BULAN 16INI 15INI
X DIVISI10. PEKERJAAN PEMELIHARAAN
10.1 Pemeliharaan Jalan
10.1.(3) Perbaikan Pasangan Batu dengan Mortar M3 280.76 1,270,455.74 356,687,180.87 23.2272 - - - - - - -
10.1.(4) Perbaikan Lapis Fondasi Agregat Kelas A M3 130.61 600,000.00 78,366,000.00 5.1031 131.400 - 131.400 5.134 - 5.134 78,840,000.00
10.1.(10a) Perbaikan Campuran Aspal Panas dengan Asbuton M3 201.26 2,900,000.00 583,654,000.00 38.0071 214.095 - 214.095 40.431 - 40.431 620,874,129.18
10.1.(10b) Perbaikan Campuran Aspal Panas dengan Asbuton M3 29.80 3,200,000.00 95,359,994.13 6.2098 22.000 - 22.000 4.584 - 4.584 70,400,000.00
10.1.(21) Pembersihan Drainase dan Saluran Samping M1 29,383.09 5,500.00 161,606,995.00 10.5237 28,033.700 - 28,033.700 10.040 - 10.040 154,185,350.00
10.1.(22) Pengendalian Tanaman M2 519,937.66 500.00 259,968,830.00 16.9290 476,836.800 - 476,836.800 15.526 - 15.526 238,418,400.00
Sub Total ( 10 ) 1,535,643,000.00 100.0000 75.7154 - 75.7154 1,162,717,879.18
TOTAL 1,535,643,000.00 100.000 PROGRESS REALISASI 75.715 - 75.715 1,162,717,879.18
Pajak Pertambahan Nilai (Ppn) 11% 168,920,730.00 PROGRESS RENCANA 80.361 80.909 127,898,966.71
TOTAL 1,704,563,730.00 DEVIASI (4.646) - (5.194) 1,290,616,845.89
DIBULATKAN 1,704,563,000.00 - 1,290,616,000.00

Disetujui Diperiksa Disiapkan


Direksi PUPR Konsultan Supervisi Kontraktor
PPK 1.3 Provinsi Sulawesi Tenggara PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI PT. LINCE ROMAULI RAYA - PT.
KONSULTAN - PT. ARISTA CIPTA AGUNG SARANA PERSADA (KSO)

SUKARDJO Ir. MUHAMMAD IDRIS RAZAK RISKY KURNIAWAN, ST


NIP. : 19750226 200312 1 002 Supervision Engineer Manager Proyek

8 / 16
PROGRES BULAN AGUSTUS 2023
NAMA PAKET : PRESERVASI JALAN POMALAA - WOLULU 16
RUAS : POMALAA - WOLULU
KONTRAKTOR : PT. LINCE ROMAULI RAYA - PT. AGUNG SARANA PERSADA (KSO) MINGGU KE : 62
KONSULTAN : PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI KONSULTAN - PT. ARISTA CIPTA Periode : 19 Agustus - 25 Agustus 2023
NO. KONTRAK : HK 0201-Bb21.1.3/286, Tanggal 17 Mei 2022

PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-02 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
15S/D BULAN 15BULAN 16INI INI
10.2 Pemeliharaan Jembatan
10.2.(1) Pemeliharaan Jembatan S SOPURA BOX Bentang 7 m LS 1.00 5,000,000.00 5,000,000.00 1.7094 0.645 - 0.645 1.103 - 1.103 3,226,428.57
10.2.(2) Pemeliharaan Jembatan S.SOPURA Bentang 20.8 m LS 1.00 22,000,000.00 22,000,000.00 7.5214 0.645 - 0.645 4.853 - 4.853 14,196,285.71
10.2.(3) Pemeliharaan Jembatan S.OKO-OKO I Bentang 9.8 m LS 1.00 12,500,000.00 12,500,000.00 4.2735 0.645 - 0.645 2.758 - 2.758 8,066,071.43
10.2.(4) Pemeliharaan Jembatan S.Oko-Oko II Bentang 8.9 m LS 1.00 10,000,000.00 10,000,000.00 3.4188 0.645 - 0.645 2.206 - 2.206 6,452,857.14
10.2.(5) Pemeliharaan Jembatan S.Oko-Ok0 III Bentang 20.8 m LS 1.00 25,000,000.00 25,000,000.00 8.5470 0.645 - 0.645 5.515 - 5.515 16,132,142.86
10.2.(6) Pemeliharaan Jembatan S.Oko-Oko IV Bentang 9.8 m LS 1.00 10,000,000.00 10,000,000.00 3.4188 0.645 - 0.645 2.206 - 2.206 6,452,857.14
10.2.(7) Pemeliharaan Jembatan S.Oko-Oko V Bentang 9.7 m LS 1.00 12,000,000.00 12,000,000.00 4.1026 0.645 - 0.645 2.647 - 2.647 7,743,428.57
10.2.(8) Pemeliharaan Jembatan S.Oko-Oko VI Bentang 6.8 m LS 1.00 9,000,000.00 9,000,000.00 3.0769 0.645 - 0.645 1.985 - 1.985 5,807,571.43
10.2.(9) Pemeliharaan Jembatan S.Lamedai I Bentang 8.9 m LS 1.00 11,500,000.00 11,500,000.00 3.9316 0.645 - 0.645 2.537 - 2.537 7,420,785.71
10.2.(10) Pemeliharaan Jembatan S.Lamedai II Bentang 8.9 m LS 1.00 11,500,000.00 11,500,000.00 3.9316 0.645 - 0.645 2.537 - 2.537 7,420,785.71
10.2.(11) Pemeliharaan Jembatan S.Box Tanggetada Bentang 6.9 m LS 1.00 6,000,000.00 6,000,000.00 2.0513 0.645 - 0.645 1.324 - 1.324 3,871,714.29
10.2.(12) Pemeliharaan Jembatan S.Tangketada Bentang 8.8 m LS 1.00 10,000,000.00 10,000,000.00 3.4188 0.645 - 0.645 2.206 - 2.206 6,452,857.14
10.2.(13) Pemeliharaan Jembatan S.Anaiwoi I Bentang 8.9 m LS 1.00 10,000,000.00 10,000,000.00 3.4188 0.645 - 0.645 2.206 - 2.206 6,452,857.14
10.2.(14) Pemeliharaan Jembatan S.Anaiwoi II Bentang 15.8 m LS 1.00 12,000,000.00 12,000,000.00 4.1026 0.645 - 0.645 2.647 - 2.647 7,743,428.57
10.2.(15) Pemeliharaan Jembatan S.Oneha I Bentang 10.3 m LS 1.00 10,000,000.00 10,000,000.00 3.4188 0.645 - 0.645 2.206 - 2.206 6,452,857.14
10.2.(16) Pemeliharaan Jembatan S.Oneha II Bentang 9.2 m LS 1.00 10,000,000.00 10,000,000.00 3.4188 0.645 - 0.645 2.206 - 2.206 6,452,857.14
10.2.(17) Pemeliharaan Jembatan S.Oneha III Bentang 8.7 m LS 1.00 10,000,000.00 10,000,000.00 3.4188 0.645 - 0.645 2.206 - 2.206 6,452,857.14
10.2.(18) Pemeliharaan Jembatan S.Oneha IV Bentang 12.8 m LS 1.00 13,000,000.00 13,000,000.00 4.4444 0.645 - 0.645 2.868 - 2.868 8,388,714.29
10.2.(19) Pemeliharaan Jembatan S.Oneha V Bentang 10.9 m LS 1.00 13,000,000.00 13,000,000.00 4.4444 0.645 - 0.645 2.868 - 2.868 8,388,714.29
10.2.(20) Pemeliharaan Jembatan S.Toengge Bentang 31.2 m LS 1.00 30,000,000.00 30,000,000.00 10.2564 0.645 - 0.645 6.618 - 6.618 19,358,571.43
10.2.(21) Pemeliharaan Jembatan S.Polewali Bentang 11 m LS 1.00 10,000,000.00 10,000,000.00 3.4188 0.645 - 0.645 2.206 - 2.206 6,452,857.14
10.2.(22) Pemeliharaan Jembatan S.Wolulu Bentang 30.3 m LS 1.00 30,000,000.00 30,000,000.00 10.2564 0.645 - 0.645 6.618 - 6.618 19,358,571.43
TOTAL 292,500,000.00 100.000 PROGRESS REALISASI 64.529 - 64.529 188,746,071.43
Pajak Pertambahan Nilai (Ppn) 11% 32,175,000.00 PROGRESS RENCANA 73.830 76.329 20,762,067.86
TOTAL 324,675,000.00 DEVIASI (9.301) - (11.800) 209,508,139.29
DIBULATKAN 324,675,000.00 - 209,508,000.00

Disetujui Diperiksa Disiapkan


Direksi PUPR Konsultan Supervisi Kontraktor
PPK 1.3 Provinsi Sulawesi Tenggara PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI PT. LINCE ROMAULI RAYA - PT.
KONSULTAN - PT. ARISTA CIPTA AGUNG SARANA PERSADA (KSO)

SUKARDJO Ir. MUHAMMAD IDRIS RAZAK RISKY KURNIAWAN, ST


NIP. : 19750226 200312 1 002 Supervision Engineer Manager Proyek

9 / 16
PROGRES BULAN AGUSTUS 2023
NAMA PAKET : PRESERVASI JALAN POMALAA - WOLULU 16
RUAS : POMALAA - WOLULU
KONTRAKTOR : PT. LINCE ROMAULI RAYA - PT. AGUNG SARANA PERSADA (KSO) MINGGU KE 62 (KONTRAK TAHUN 2023)
KONSULTAN : PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI KONSULTAN - PT. ARISTA CIPTA Periode : 19 Agustus - 25 Agustus 2023
NO. KONTRAK : HK 0201-Bb21.1.3/286, Tanggal 17 Mei 2022

PRESTASI
VOLUME HARGA JUMLAH
No. BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT KONTRAK JUMLAH
Item SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
ANAK ADD-02
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
15S/D BULAN 15BULAN 16INI 62INI
I DIVISI 1. UMUM
1.2 Mobilisasi Ls 0.30 500,000,000.00 150,000,000.00 0.1658 - - - - - - -
1.80 Manajemen dan Keselamatan Lalu Lintas Ls 0.66 100,000,000.00 65,631,578.95 0.0725 0.254 0.010 0.264 0.028 0.001 0.029 26,368,421.05
1.17 Pengamanan Lingkungan Hidup
1.17.(1a) Pengujian pH Buah 6.00 70,000.00 420,000.00 0.0005 3.000 - 3.000 0.000 - 0.000 210,000.00
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 6.00 100,000.00 600,000.00 0.0007 3.000 - 3.000 0.000 - 0.000 300,000.00
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 6.00 150,000.00 900,000.00 0.0010 3.000 - 3.000 0.000 - 0.000 450,000.00
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 6.00 100,000.00 600,000.00 0.0007 3.000 - 3.000 0.000 - 0.000 300,000.00
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 6.00 140,000.00 840,000.00 0.0009 3.000 - 3.000 0.000 - 0.000 420,000.00
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 6.00 140,000.00 840,000.00 0.0009 3.000 - 3.000 0.000 - 0.000 420,000.00
1.17.(2c) Pengujian Parameter Kebisingan dan/atau Getaran Lainnya ……… Buah 6.00 140,000.00 840,000.00 0.0009 3.000 - 3.000 0.000 - 0.000 420,000.00
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 6.00 200,000.00 1,200,000.00 0.0013 3.000 - 3.000 0.001 - 0.001 600,000.00
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 6.00 125,000.00 750,000.00 0.0008 3.000 - 3.000 0.000 - 0.000 375,000.00
1.19 Keselamatan dan Kesehatan Kerja
1.00 1. Penyiapan RKK Buah 1.00 3,000,000.00 3,000,000.00 0.0033 - - - - - - -
2.00 2. Sosialisasi dan Promosi Dan Pelatihan Buah 1.00 5,000,000.00 5,000,000.00 0.0055 - - - - - - -
3.00 3. Alat Pelindung Kerja (APK) dan Alat Pelindung Diri (APD) Buah 0.64 35,000,000.00 22,449,291.24 0.0248 0.167 0.007 0.173 0.006 0.000 0.007 6,065,388.00
4.00 4. Asuransi dan Perizinan Buah 1.00 20,000,000.00 20,000,000.00 0.0221 - - - - - - -
5.00 5. Personel K3 Konstruksi Buah 0.67 99,000,000.00 66,050,649.96 0.0730 0.173 0.007 0.180 0.019 0.001 0.020 17,845,677.87
6.00 6. Fasilitas sarana kesehatan Buah 1.00 15,000,000.00 15,000,000.00 0.0166 - - - - - - -
7.00 7. Rambu-rambu terdiri atas Buah 0.63 22,727,272.73 14,206,206.32 0.0157 0.163 0.006 0.169 0.004 0.000 0.004 3,838,257.18
8.00 8. Konsultasi dengan Ahli Terkait Keselamatan Konstruksi Buah 1.00 15,000,000.00 15,000,000.00 0.0166 - - - - - - -
9.00 9. Lain-lain terkait pengendalian risiko K3 Buah 1.00 5,000,000.00 5,000,000.00 0.0055 - - - - - - -
1.21 Manajemen Mutu Ls 0.64 200,000,000.00 128,500,000.00 0.1420 0.255 0.010 0.265 0.056 0.002 0.059 53,000,000.00

Sub Total ( 1 ) 516,827,726.47 0.5713 0.118 0.004 0.122 110,612,744.10


II DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 6,099.13 25,000.00 152,478,150.00 0.1685 4,079.634 101.354 4,180.988 0.113 0.003 0.116 104,524,700.00
2.2.(1) Pasangan Batu dengan Mortar M3 5,710.20 700,000.00 3,997,143,493.00 4.4184 3,439.839 85.459 3,525.298 2.662 0.066 2.728 2,467,708,600.00
2.3.(15) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 100 cm x 100 cm (p M1 134.40 4,275,906.49 574,681,832.26 0.6353 60.000 18.000 78.000 0.284 0.085 0.369 333,520,706.22
2.3.(18) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 150 cm x 150 cm (p M1 296.40 7,268,205.12 2,154,295,997.57 2.3814 261.600 12.000 273.600 2.102 0.096 2.198 1,988,580,920.83
2.3.(20) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 250 cm x 250 cm (p M1 13.20 42,718,794.10 563,888,082.12 0.6233 - 13.200 13.200 - 0.623 0.623 563,888,082.12
2.3.(22) Saluran berbentuk U Tipe DS 1 (precast) M1 4,575.00 1,250,000.00 5,718,750,000.00 6.3215 3,391.000 121.000 3,512.000 4.686 0.167 4.853 4,390,000,000.00

Sub Total ( 2 ) 13,161,237,554.95 14.5484 9.845 1.041 10.886 9,848,223,009.17


III DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1a) Galian Biasa M3 67,613.34 16,000.00 1,081,813,390.40 1.1958 32,912.178 77.400 32,989.578 0.582 0.001 0.583 527,833,250.67
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 11,144.96 100,000.00 1,114,496,000.00 1.2320 8,761.069 - 8,761.069 0.968 - 0.968 876,106,935.90
3.3.(1) Penyiapan Badan Jalan M2 64,166.26 5,000.00 320,831,300.00 0.3546 35,816.940 209.189 36,026.130 0.198 0.001 0.199 180,130,647.52
3.4.(2) Pemotongan Pohon Pilihan diameter 15 – 30 cm Buah 29.00 39,983.05 1,159,508.45 0.0013 101.000 24.000 125.000 0.004 0.001 0.006 4,997,881.25
3.4.(3) Pemotongan Pohon Pilihan diameter > 30 – 50 cm Buah 182.00 61,536.34 11,199,613.88 0.0124 60.000 - 60.000 0.004 - 0.004 3,692,180.40
3.4.(4) Pemotongan Pohon Pilihan diameter > 50 – 75 cm Buah 207.00 112,032.53 23,190,733.71 0.0256 199.000 19.000 218.000 0.025 0.002 0.027 24,423,091.54
3.4.(5) Pemotongan Pohon Pilihan diameter > 75 cm Buah 1.00 233,248.73 233,248.73 0.0003 50.000 - 50.000 0.013 - 0.013 11,662,436.50

Sub Total ( 3 ) 2,552,923,795.17 2.82 1.795 0.006 1.801 1,628,846,423.78

10 / 16
PRESTASI
VOLUME HARGA JUMLAH
No. BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT KONTRAK JUMLAH
Item SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
ANAK ADD-02
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
V DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN 1,100.000 #REF!
5.1.(1) Lapis Fondasi Agregat Kelas A M3 14,486.66 600,000.00 8,691,994,416.00 9.6081 10,701.306 280.800 10,982.106 7.098 0.186 7.284 6,589,263,600.00
5.1.(3a) Lapis Fondasi Agregat Kelas S M3 15,031.93 250,000.00 3,757,982,500.00 4.1541 5,050.785 140.625 5,191.410 1.396 0.039 1.435 1,297,852,500.00
Sub Total ( 5 ) 12,449,976,916.00 13.7622 8.493 0.225 8.718 7,887,116,100.00
VI DIVISI 6. PERKERASAN ASPAL
6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair Liter 46,717.40 15,000.00 700,760,995.99 0.7746 26,661.779 2,337.989 28,999.768 0.442 0.039 0.481 434,996,521.97
6.1 (2)(a) Lapis Perekat - Aspal Cair Liter 48,419.05 13,000.00 629,447,646.02 0.6958 25,647.729 949.223 26,596.953 0.369 0.014 0.382 345,760,383.79
6.3.(8) Bahan anti pengelupasan Kg 3,891.90 75,000.00 291,892,571.00 0.3227 2,034.071 52.147 2,086.218 0.169 0.004 0.173 156,466,328.85
6.5.(1b) Laston Lapis Aus Asbuton Butir (AC-WC Asb Butir) Ton 16,063.68 1,425,000.00 22,890,738,656.25 25.3034 11,500.177 310.396 11,810.573 18.115 0.489 18.604 16,830,067,237.50
6.5.(2b) Laston Lapis Antara Asbuton Butir (AC-BC Asb Butir) Ton 8,976.25 1,350,000.00 12,117,934,751.65 13.3951 5,947.860 468.270 6,416.130 8.876 0.699 9.575 8,661,775,022.77

Sub Total ( 6 ) 36,630,774,620.92 40.4915 27.970 1.244 29.215 26,429,065,494.88


VII DIVISI 7. STRUKTUR
7.1 (5a) Beton struktur, fc’30 Mpa (Kubus 60 x 60 x 60) M3 438.48 3,557,765.22 1,560,008,893.67 1.7244 - - - - - - -
7.1 (6a) Beton struktur, fc’25 Mpa (untuk penutup saluran) M3 576.00 1,700,000.00 979,200,000.00 1.0824 - - - - - - -
7.1 (7a) Beton struktur, fc’20 MPa (untuk bahu diperkeras) M3 2,654.17 1,125,000.00 2,985,941,250.00 3.3007 - - - - - - -
7.1 (7d) Beton struktur, fc’20 Mpa (untuk pengaman pantai) M3 583.60 3,494,109.91 2,039,177,917.56 2.2541 - - - - - - -
7.1 (9) Beton Siklop, fc’15 Mpa (untuk pengaman pantai) M3 133.93 893,667.17 119,688,844.08 0.1323 - - - - - - -
7.1 (10) Beton, fc’10 Mpa M3 - 1,100,000.00 - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 82,775.89 19,000.00 1,572,741,910.00 1.7385 - - - - - - -
7.3 (3) Baja Tulangan Ulir-BjTS 420 A Kg 25,549.07 20,934.10 534,846,777.78 0.5912 - - - - - - -
7.9.(1) Pasangan Batu M3 12,645.42 650,000.00 8,219,520,651.07 9.0858 7,605.138 251.210 7,856.348 5.464 0.180 5.645 5,106,625,935.94
7.10.(3a) Bronjong dengan kawat yang dilapisi Galvanis M3 500.00 725,000.00 362,500,000.00 0.4007 - - - - - - -
7.15.(1) Pembongkaran Pasangan Batu M3 529.49 304,690.52 161,330,583.43 0.1783 586.220 11.760 597.980 0.197 0.004 0.201 182,198,837.15
7.15.(2) Pembongkaran Beton M3 90.09 316,550.08 28,519,294.56 0.0315 30.364 5.620 35.984 0.011 0.002 0.013 11,390,769.73
Sub Total ( 7 ) 18,563,476,122.16 20.5200 5.6724 0.1864 5.8588 5,300,215,542.82

IX DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN


9.1 Pekerjaan Harian
9.1.(2) Pekerja Biasa Jam 84.00 18,750.00 1,575,000.00 0.0017 - - - - - - -
9.1.(4) a Dump Truck, kapasitas 3 - 4 m³ Jam 84.00 200,000.00 16,800,000.00 0.0186 - - - - - - -
9.1.(6) Truk Tangki 3000 - 4500 Liter Jam 84.00 200,000.00 16,800,000.00 0.0186 - - - - - - -
9.1.(8) Motor Grader min 100 PK Jam 121.00 200,000.00 24,200,000.00 0.0268 - - - - - - -
9.1.(9) Loader Roda Karet 1.0 - 1.6 M3 Jam 126.00 200,000.00 25,200,000.00 0.0279 - - - - - - -
9.1.(13) Penggilas Roda Besi 6 - 9 Ton Jam 79.00 200,000.00 15,800,000.00 0.0175 - - - - - - -
9.2 Pekerjaan Lain-Lain
9.2.(1) Marka Jalan Termoplastik M2 12,284.04 120,000.00 1,474,084,800.00 1.6294 1,211.320 - 1,211.320 0.161 - 0.161 145,358,400.00
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade Buah 144.00 450,000.00 64,800,000.00 0.0716 - - - - - - -
9.2.(5) Patok Pengarah, material Poly Ethylene (PE) Plastik murni/elastis Buah 1,490.00 300,000.00 447,000,000.00 0.4941 - - - - - - -
9.2.(6a) Patok Kilometer Buah 32.00 350,000.00 11,200,000.00 0.0124 - - - - - - -
9.2.(7) Rel Pengaman M1 4,072.80 850,000.00 3,461,880,000.00 3.8268 - - - - - - -
9.2(10a) Kerb Pracetak Jenis 1 (Peninggi/Mountable) M1 2,000.00 115,000.00 230,000,000.00 0.2542 - - - - - - -
9.2.(12a) Perkerasan Blok Beton pada Trotoar dan Median M2 2,400.00 135,000.00 324,000,000.00 0.3581 - - - - - - -
Sub Total ( 9 ) 6,113,339,800.00 6.7577 0.161 - 0.161 145,358,400.00

11 / 16
PRESTASI
VOLUME HARGA JUMLAH
No. BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT KONTRAK JUMLAH
Item SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
ANAK ADD-02
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
X DIVISI10. PEKERJAAN PEMELIHARAAN
10.1 Pemeliharaan Jalan
10.1.(3) Perbaikan Pasangan Batu dengan Mortar M3 280.76 1,270,455.74 356,687,180.87 0.3943 - - - - - - -
10.1.(4) Perbaikan Lapis Fondasi Agregat Kelas A M3 (0.79) 600,000.00 (474,000.00) (0.0005) 161.195 - 161.195 0.107 - 0.107 96,716,716.38
10.1.(10a) Perbaikan Campuran Aspal Panas dengan Asbuton M3 (12.83) 2,900,000.00 (37,220,129.18) (0.0411) 49.900 - 49.900 0.160 - 0.160 144,710,418.43
10.1.(10b) Perbaikan Campuran Aspal Panas dengan Asbuton M3 7.80 3,200,000.00 24,959,994.13 0.0276 - - - - - - -
10.1.(21) Pembersihan Drainase dan Saluran Samping M1 1,349.39 5,500.00 7,421,645.00 0.0082 10,617.600 - 10,617.600 0.065 - 0.065 58,396,800.00
10.1.(22) Pengendalian Tanaman M2 43,100.86 500.00 21,550,430.00 0.0238 117,600.100 - 117,600.100 0.065 - 0.065 58,800,050.00
10.2 Pemeliharaan Jembatan
10.2.(1) Pemeliharaan Jembatan S SOPURA BOX Bentang 7 m LS 0.35 5,000,000.00 1,773,571.43 0.0020 0.215 - 0.215 0.001 - 0.001 1,075,000.00
10.2.(2) Pemeliharaan Jembatan S.SOPURA Bentang 20.8 m LS 0.35 22,000,000.00 7,803,714.29 0.0086 0.215 - 0.215 0.005 - 0.005 4,730,000.00
10.2.(3) Pemeliharaan Jembatan S.OKO-OKO I Bentang 9.8 m LS 0.35 12,500,000.00 4,433,928.57 0.0049 0.215 - 0.215 0.003 - 0.003 2,687,500.00
10.2.(4) Pemeliharaan Jembatan S.Oko-Oko II Bentang 8.9 m LS 0.35 10,000,000.00 3,547,142.86 0.0039 0.215 - 0.215 0.002 - 0.002 2,150,000.00
10.2.(5) Pemeliharaan Jembatan S.Oko-Ok0 III Bentang 20.8 m LS 0.35 25,000,000.00 8,867,857.14 0.0098 0.215 - 0.215 0.006 - 0.006 5,375,000.00
10.2.(6) Pemeliharaan Jembatan S.Oko-Oko IV Bentang 9.8 m LS 0.35 10,000,000.00 3,547,142.86 0.0039 0.215 - 0.215 0.002 - 0.002 2,150,000.00
10.2.(7) Pemeliharaan Jembatan S.Oko-Oko V Bentang 9.7 m LS 0.35 12,000,000.00 4,256,571.43 0.0047 0.215 - 0.215 0.003 - 0.003 2,580,000.00
10.2.(8) Pemeliharaan Jembatan S.Oko-Oko VI Bentang 6.8 m LS 0.35 9,000,000.00 3,192,428.57 0.0035 0.215 - 0.215 0.002 - 0.002 1,935,000.00
10.2.(9) Pemeliharaan Jembatan S.Lamedai I Bentang 8.9 m LS 0.35 11,500,000.00 4,079,214.29 0.0045 0.215 - 0.215 0.003 - 0.003 2,472,500.00
10.2.(10) Pemeliharaan Jembatan S.Lamedai II Bentang 8.9 m LS 0.35 11,500,000.00 4,079,214.29 0.0045 0.215 - 0.215 0.003 - 0.003 2,472,500.00
10.2.(11) Pemeliharaan Jembatan S.Box Tanggetada Bentang 6.9 m LS 0.35 6,000,000.00 2,128,285.71 0.0024 0.215 - 0.215 0.001 - 0.001 1,290,000.00
10.2.(12) Pemeliharaan Jembatan S.Tanggetada Bentang 8.8 m LS 0.35 10,000,000.00 3,547,142.86 0.0039 0.215 - 0.215 0.002 - 0.002 2,150,000.00
10.2.(13) Pemeliharaan Jembatan S.Anaiwoi I Bentang 8.9 m LS 0.35 10,000,000.00 3,547,142.86 0.0039 0.215 - 0.215 0.002 - 0.002 2,150,000.00
10.2.(14) Pemeliharaan Jembatan S.Anaiwoi II Bentang 15.8 m LS 0.35 12,000,000.00 4,256,571.43 0.0047 0.215 - 0.215 0.003 - 0.003 2,580,000.00
10.2.(15) Pemeliharaan Jembatan S.Oneha I Bentang 10.3 m LS 0.35 10,000,000.00 3,547,142.86 0.0039 0.215 - 0.215 0.002 - 0.002 2,150,000.00
10.2.(16) Pemeliharaan Jembatan S.Oneha II Bentang 9.2 m LS 0.35 10,000,000.00 3,547,142.86 0.0039 0.215 - 0.215 0.002 - 0.002 2,150,000.00
10.2.(17) Pemeliharaan Jembatan S.Oneha III Bentang 8.7 m LS 0.35 10,000,000.00 3,547,142.86 0.0039 0.215 - 0.215 0.002 - 0.002 2,150,000.00
10.2.(18) Pemeliharaan Jembatan S.Oneha IV Bentang 12.8 m LS 0.35 13,000,000.00 4,611,285.71 0.0051 0.215 - 0.215 0.003 - 0.003 2,795,000.00
10.2.(19) Pemeliharaan Jembatan S.Oneha V Bentang 10.9 m LS 0.35 13,000,000.00 4,611,285.71 0.0051 0.215 - 0.215 0.003 - 0.003 2,795,000.00
10.2.(20) Pemeliharaan Jembatan S.Toengge Bentang 31.2 m LS 0.35 30,000,000.00 10,641,428.57 0.0118 0.215 - 0.215 0.007 - 0.007 6,450,000.00
10.2.(21) Pemeliharaan Jembatan S.Polewali Bentang 11 m LS 0.35 10,000,000.00 3,547,142.86 0.0039 0.215 - 0.215 0.002 - 0.002 2,150,000.00
10.2.(22) Pemeliharaan Jembatan S.Wolulu Bentang 30.3 m LS 0.35 30,000,000.00 10,641,428.57 0.0118 0.215 - 0.215 0.007 - 0.007 6,450,000.00
Sub Total ( 10 ) 476,679,049.39 0.5269 0.466 - 0.466 421,511,484.8097
TOTAL 90,465,235,585.05 100.000 PROGRESS REALISASI 54.520 2.707 57.227 51,770,949,199.57
Pajak Pertambahan Nilai (Ppn) 11% 9,951,175,914.36 PROGRESS RENCANA 56.641 2.565 59.206 5,694,804,411.95
TOTAL 100,416,411,499.40 DEVIASI (2.121) 0.142 (1.979) 57,465,753,611.52
DIBULATKAN 100,416,411,000.00 (0.142) 57,465,753,000.00

Disetujui Diperiksa Disiapkan


Direksi PUPR Konsultan Supervisi Kontraktor
PPK 1.3 Provinsi Sulawesi Tenggara PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI PT. LINCE ROMAULI RAYA - PT.
KONSULTAN - PT. ARISTA CIPTA AGUNG SARANA PERSADA (KSO)

SUKARDJO Ir. MUHAMMAD IDRIS RAZAK RISKY KURNIAWAN, ST


NIP. : 19750226 200312 1 002 Supervision Engineer Manager Proyek

12 / 16
PROGRES BULAN AGUSTUS 2023
NAMA PAKET : PRESERVASI JALAN POMALAA - WOLULU 16
RUAS : POMALAA - WOLULU
KONTRAKTOR : PT. LINCE ROMAULI RAYA - PT. AGUNG SARANA PERSADA (KSO) MINGGU KE 62 (KONTRAK TAHUN 2023)
KONSULTAN : PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI KONSULTAN - PT. ARISTA CIPTA Periode : 19 Agustus - 25 Agustus 2023
NO. KONTRAK : HK 0201-Bb21.1.3/286, Tanggal 17 Mei 2022

PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-06 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
15S/D BULAN 15BULAN 16INI INI
I DIVISI 1. UMUM
1.2 Mobilisasi Ls 0.30 500,000,000.00 150,000,000.00 0.1761 - - - - - - -
1.80 Manajemen dan Keselamatan Lalu Lintas Ls 0.66 100,000,000.00 65,631,578.95 0.0771 0.254 0.010 0.264 0.030 0.001 0.031 26,368,421.05
1.17 Pengamanan Lingkungan Hidup
1.17.(1a) Pengujian pH Buah 6.00 70,000.00 420,000.00 0.0005 3.000 - 3.000 0.000 - 0.000 210,000.00
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 6.00 100,000.00 600,000.00 0.0007 3.000 - 3.000 0.000 - 0.000 300,000.00
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 6.00 150,000.00 900,000.00 0.0011 3.000 - 3.000 0.001 - 0.001 450,000.00
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 6.00 100,000.00 600,000.00 0.0007 3.000 - 3.000 0.000 - 0.000 300,000.00
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 6.00 140,000.00 840,000.00 0.0010 3.000 - 3.000 0.000 - 0.000 420,000.00
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 6.00 140,000.00 840,000.00 0.0010 3.000 - 3.000 0.000 - 0.000 420,000.00
1.17.(2c) Pengujian Parameter Kebisingan dan/atau Getaran Lainnya ……… Buah 6.00 140,000.00 840,000.00 0.0010 3.000 - 3.000 0.000 - 0.000 420,000.00
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 6.00 200,000.00 1,200,000.00 0.0014 3.000 - 3.000 0.001 - 0.001 600,000.00
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 6.00 125,000.00 750,000.00 0.0009 3.000 - 3.000 0.000 - 0.000 375,000.00
1.19 Keselamatan dan Kesehatan Kerja
1.00 1. Penyiapan RKK Buah 1.00 3,000,000.00 3,000,000.00 0.0035 - - - - - - -
2.00 2. Sosialisasi dan Promosi Dan Pelatihan Buah 1.00 5,000,000.00 5,000,000.00 0.0059 - - - - - - -
3.00 3. Alat Pelindung Kerja (APK) dan Alat Pelindung Diri (APD) Buah 0.64 35,000,000.00 22,449,291.24 0.0264 0.167 0.007 0.173 0.007 0.000 0.007 6,065,388.00
4.00 4. Asuransi dan Perizinan Buah 1.00 20,000,000.00 20,000,000.00 0.0235 - - - - - - -
5.00 5. Personel K3 Konstruksi Buah 0.67 99,000,000.00 66,050,649.96 0.0776 0.173 0.007 0.180 0.020 0.001 0.021 17,845,677.87
6.00 6. Fasilitas sarana kesehatan Buah 1.00 15,000,000.00 15,000,000.00 0.0176 - - - - - - -
7.00 7. Rambu-rambu terdiri atas Buah 0.63 22,727,272.73 14,206,206.32 0.0167 0.163 0.006 0.169 0.004 0.000 0.005 3,838,257.18
8.00 8. Konsultasi dengan Ahli Terkait Keselamatan Konstruksi Buah 1.00 15,000,000.00 15,000,000.00 0.0176 - - - - - - -
9.00 9. Lain-lain terkait pengendalian risiko K3 Buah 1.00 5,000,000.00 5,000,000.00 0.0059 - - - - - - -
1.21 Manajemen Mutu Ls 0.64 200,000,000.00 128,500,000.00 0.1509 0.255 0.010 0.265 0.060 0.002 0.062 53,000,000.00
Sub Total ( 1 ) 516,827,726.47 0.6068 0.125 0.005 0.130 110,612,744.10
II DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 6,099.13 25,000.00 152,478,150.00 0.1790 4,079.634 101.354 4,180.988 0.120 0.003 0.123 104,524,700.00
2.2.(1) Pasangan Batu dengan Mortar M3 5,710.20 700,000.00 3,997,143,493.00 4.6931 3,439.839 85.459 3,525.298 2.827 0.070 2.897 2,467,708,600.00
2.3.(15) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 100 cm x 100 cm (precast M1 134.40 4,275,906.49 574,681,832.26 0.6747 60.000 18.000 78.000 - - - 333,520,706.22
2.3.(18) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 150 cm x 150 cm (precast M1 296.40 7,268,205.12 2,154,295,997.57 2.5294 261.600 12.000 273.600 2.232 0.102 2.335 1,988,580,920.83
2.3.(22) Saluran berbentuk U Tipe DS 1 (precast) M1 4,575.00 1,250,000.00 5,718,750,000.00 6.7144 3,391.000 121.000 3,512.000 4.977 0.178 5.154 4,390,000,000.00
Sub Total ( 2 ) 12,597,349,472.83 14.7907 10.156 0.353 10.509 9,284,334,927.05
III DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1a) Galian Biasa M3 67,613.34 16,000.00 1,081,813,390.40 1.2702 32,912.178 77.400 32,989.578 0.618 0.001 0.620 527,833,250.67
3.2.(2a) Timbunan Pilihan dari Sumber Galian M3 11,144.96 100,000.00 1,114,496,000.00 1.3085 8,761.069 - 8,761.069 1.029 - 1.029 876,106,935.90
3.3.(1) Penyiapan Badan Jalan M2 64,166.26 5,000.00 320,831,300.00 0.3767 35,816.940 209.189 36,026.130 0.210 0.001 0.211 180,130,647.52
3.4.(2) Pemotongan Pohon Pilihan diameter 15 – 30 cm Buah 29.00 39,983.05 1,159,508.45 0.0014 101.000 24.000 125.000 0.005 0.001 0.006 4,997,881.25
3.4.(3) Pemotongan Pohon Pilihan diameter > 30 – 50 cm Buah 182.00 61,536.34 11,199,613.88 0.0131 60.000 - 60.000 0.004 - 0.004 3,692,180.40
3.4.(4) Pemotongan Pohon Pilihan diameter > 50 – 75 cm Buah 207.00 112,032.53 23,190,733.71 0.0272 199.000 19.000 218.000 0.026 0.002 0.029 24,423,091.54
3.4.(5) Pemotongan Pohon Pilihan diameter > 75 cm Buah 1.00 233,248.73 233,248.73 0.0003 50.000 - 50.000 0.014 - 0.014 11,662,436.50
Sub Total ( 3 ) 2,552,923,795.17 2.9974 1.906 0.006 1.912 1,628,846,423.78

V DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN 1,100.000 #REF!


5.1.(1) Lapis Fondasi Agregat Kelas A M3 14,486.66 600,000.00 8,691,994,416.00 10.2054 10,701.306 280.800 10,982.106 7.539 0.198 7.737 6,589,263,600.00
5.1.(3a) Lapis Fondasi Agregat Kelas S M3 15,031.93 250,000.00 3,757,982,500.00 4.4123 5,050.785 140.625 5,191.410 1.483 0.041 1.524 1,297,852,500.00
Sub Total ( 5 ) 12,449,976,916.00 14.6176 9.021 0.239 9.260 7,887,116,100.00

13 / 16
PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-06 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
VI DIVISI 6. PERKERASAN ASPAL
6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair Liter 46,717.40 15,000.00 700,760,995.99 0.8228 26,661.779 2,337.989 28,999.768 0.470 0.041 0.511 434,996,521.97
6.1 (2)(a) Lapis Perekat - Aspal Cair Liter 48,419.05 13,000.00 629,447,646.02 0.7390 25,647.729 949.223 26,596.953 0.391 0.014 0.406 345,760,383.79
6.3.(8) Bahan anti pengelupasan Kg 3,891.90 75,000.00 291,892,571.00 0.3427 2,034.071 52.147 2,086.218 0.179 0.005 0.184 156,466,328.85
6.5.(1b) Laston Lapis Aus Asbuton Butir (AC-WC Asb Butir) Ton 16,063.68 1,425,000.00 22,890,738,656.25 26.8762 11,500.177 310.396 11,810.573 19.241 0.519 19.760 16,830,067,237.50
6.5.(2b) Laston Lapis Antara Asbuton Butir (AC-BC Asb Butir) Ton 8,976.25 1,350,000.00 12,117,934,751.65 14.2278 5,947.860 468.270 6,416.130 9.428 0.742 10.170 8,661,775,022.77
Sub Total ( 6 ) 36,630,774,620.92 43.0085 29.709 1.322 31.031 26,429,065,494.88
VII DIVISI 7. STRUKTUR
7.1 (6a) Beton struktur, fc’25 Mpa (untuk penutup saluran) M3 576.00 1,700,000.00 979,200,000.00 1.1497 - - - - - - -
7.1 (7a) Beton struktur, fc’20 MPa (untuk bahu diperkeras) M3 2,654.17 1,125,000.00 2,985,941,250.00 3.5058 - - - - - - -
7.1 (10) Beton, fc’10 Mpa M3 - 1,100,000.00 - - - - - - - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 82,775.89 19,000.00 1,572,741,910.00 1.8466 - - - - - - -
7.9.(1) Pasangan Batu M3 12,645.42 650,000.00 8,219,520,651.07 9.6506 7,605.138 251.210 7,856.348 5.804 0.192 5.996 5,106,625,935.94
7.10.(3a) Bronjong dengan kawat yang dilapisi Galvanis M3 500.00 725,000.00 362,500,000.00 0.4256 - - - - - - -
7.15.(1) Pembongkaran Pasangan Batu M3 529.49 304,690.52 161,330,583.43 0.1894 586.220 11.760 597.980 0.210 0.004 0.214 182,198,837.15
7.15.(2) Pembongkaran Beton M3 90.09 316,550.08 28,519,294.56 0.0335 30.364 5.620 35.984 0.011 0.002 0.013 11,390,769.73
Sub Total ( 7 ) 14,309,753,689.07 16.8012 6.025 0.198 6.223 5,300,215,542.82
IX DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.1 Pekerjaan Harian
9.1.(2) Pekerja Biasa Jam 84.00 18,750.00 1,575,000.00 0.0018 - - - - - - -
9.1.(4) a Dump Truck, kapasitas 3 - 4 m³ Jam 84.00 200,000.00 16,800,000.00 0.0197 - - - - - - -
9.1.(6) Truk Tangki 3000 - 4500 Liter Jam 84.00 200,000.00 16,800,000.00 0.0197 - - - - - - -
9.1.(8) Motor Grader min 100 PK Jam 121.00 200,000.00 24,200,000.00 0.0284 - - - - - - -
9.1.(9) Loader Roda Karet 1.0 - 1.6 M3 Jam 126.00 200,000.00 25,200,000.00 0.0296 - - - - - - -
9.1.(13) Penggilas Roda Besi 6 - 9 Ton Jam 79.00 200,000.00 15,800,000.00 0.0186 - - - - - - -
9.2 Pekerjaan Lain-Lain
9.2.(1) Marka Jalan Termoplastik M2 12,284.04 120,000.00 1,474,084,800.00 1.7307 1,211.320 - 1,211.320 0.171 - 0.171 145,358,400.00
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade Buah 144.00 450,000.00 64,800,000.00 0.0761 - - - - - - -
9.2.(5) Patok Pengarah, material Poly Ethylene (PE) Plastik murni/elastis Buah 1,490.00 300,000.00 447,000,000.00 0.5248 - - - - - - -
9.2.(6a) Patok Kilometer Buah 32.00 350,000.00 11,200,000.00 0.0132 - - - - - - -
9.2.(7) Rel Pengaman M1 4,072.80 850,000.00 3,461,880,000.00 4.0646 - - - - - - -
9.2(10a) Kerb Pracetak Jenis 1 (Peninggi/Mountable) M1 2,000.00 115,000.00 230,000,000.00 0.2700 - - - - - - -
9.2.(12a) Perkerasan Blok Beton pada Trotoar dan Median M2 2,400.00 135,000.00 324,000,000.00 0.3804 - - - - - - -
Sub Total ( 9 ) 6,113,339,800.00 7.1777 0.171 - 0.171 145,358,400.00
TOTAL 85,170,946,020.45 100.000 PROGRESS REALISASI 57.113 2.123 59.236 50,785,549,632.64
Pajak Pertambahan Nilai (Ppn) 11% 9,368,804,062.25 PROGRESS RENCANA 56.542 59.122 5,586,410,459.59
TOTAL 94,539,750,082.70 DEVIASI 0.571 2.123 0.115 56,371,960,092.23
DIBULATKAN 94,539,750,000.00 (2.123) 56,371,960,000.00
Disetujui Diperiksa Disiapkan
Direksi PUPR Konsultan Supervisi Kontraktor
PPK 1.3 Provinsi Sulawesi Tenggara PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI PT. LINCE ROMAULI RAYA - PT. AGUNG
KONSULTAN - PT. ARISTA CIPTA SARANA PERSADA (KSO)

SUKARDJO Ir. MUHAMMAD IDRIS RAZAK RISKY KURNIAWAN, ST


NIP. : 19750226 200312 1 002 Supervision Engineer Manager Proyek

14 / 16
PROGRES BULAN AGUSTUS 2023
NAMA PAKET : PRESERVASI JALAN POMALAA - WOLULU 16
RUAS : POMALAA - WOLULU
KONTRAKTOR : PT. LINCE ROMAULI RAYA - PT. AGUNG SARANA PERSADA (KSO) MINGGU KE 62 (KONTRAK TAHUN 2023)
KONSULTAN : PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI KONSULTAN - PT. ARISTA CIPTA Periode : 19 Agustus - 25 Agustus 2023
NO. KONTRAK : HK 0201-Bb21.1.3/286, Tanggal 17 Mei 2022

PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-06 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
15S/D BULAN 15BULAN 16INI 15INI
X DIVISI10. PEKERJAAN PEMELIHARAAN
10.1 Pemeliharaan Jalan
10.1.(3) Perbaikan Pasangan Batu dengan Mortar M3 280.76 1,270,455.74 356,687,180.87 91.6558 - - - - - - -
10.1.(4) Perbaikan Lapis Fondasi Agregat Kelas A M3 1.00 600,000.00 600,000.00 0.1542 161.195 - 161.195 24.853 - 24.853 96,716,716.38
10.1.(10a) Perbaikan Campuran Aspal Panas dengan Asbuton M3 1.00 2,900,000.00 2,900,000.00 0.7452 49.900 - 49.900 37.185 - 37.185 144,710,418.43
10.1.(10b) Perbaikan Campuran Aspal Panas dengan Asbuton M3 - 3,200,000.00 - - - - - - - - -
10.1.(21) Pembersihan Drainase dan Saluran Samping M1 1,349.39 5,500.00 7,421,645.00 1.9071 10,617.600 - 10,617.600 15.006 - 15.006 58,396,800.00
10.1.(22) Pengendalian Tanaman M2 43,100.86 500.00 21,550,430.00 5.5377 117,600.100 - 117,600.100 15.110 - 15.110 58,800,050.00
TOTAL 389,159,255.87 100.000 PROGRESS REALISASI 92.154 - 92.154 358,623,984.81
Pajak Pertambahan Nilai (Ppn) 11% 42,807,518.15 PROGRESS RENCANA 64.241 65.239 39,448,638.33
TOTAL 431,966,774.02 DEVIASI 27.913 - 26.915 398,072,623.14
DIBULATKAN 431,966,000.00 - 398,072,000.00

Disetujui Diperiksa Disiapkan


Direksi PUPR Konsultan Supervisi Kontraktor
PPK 1.3 Provinsi Sulawesi Tenggara PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI PT. LINCE ROMAULI RAYA - PT.
KONSULTAN - PT. ARISTA CIPTA AGUNG SARANA PERSADA (KSO)

SUKARDJO Ir. MUHAMMAD IDRIS RAZAK RISKY KURNIAWAN, ST


NIP. : 19750226 200312 1 002 Supervision Engineer Manager Proyek

15 / 16
PROGRES BULAN AGUSTUS 2023
NAMA PAKET : PRESERVASI JALAN POMALAA - WOLULU 16
RUAS : POMALAA - WOLULU
KONTRAKTOR : PT. LINCE ROMAULI RAYA - PT. AGUNG SARANA PERSADA (KSO) MINGGU KE 62 (KONTRAK TAHUN 2023)
KONSULTAN : PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI KONSULTAN - PT. ARISTA CIPTA Periode : 19 Agustus - 25 Agustus 2023
NO. KONTRAK : HK 0201-Bb21.1.3/286, Tanggal 17 Mei 2022

PRESTASI
HARGA JUMLAH
No. VOLUME BOBOT KUANTITAS BOBOT ( % )
URAIAN SAT JUMLAH
Item ADD-02 SATUAN HARGA ( %) S/D MINGGU MINGGU S/D MINGGU S/D MINGGU MINGGU S/D MINGGU
(Rp.) (Rp.) LALU INI INI LALU INI INI (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14
15S/D BULAN 15BULAN 16INI INI
10.2 Pemeliharaan Jembatan
10.2.(1) Pemeliharaan Jembatan S SOPURA BOX Bentang 7 m LS 0.35 5,000,000.00 1,773,571.43 1.7094 0.215 - 0.215 1.036 - 1.036 1,075,000.00
10.2.(2) Pemeliharaan Jembatan S.SOPURA Bentang 20.8 m LS 0.35 22,000,000.00 7,803,714.29 7.5214 0.215 - 0.215 4.559 - 4.559 4,730,000.00
10.2.(3) Pemeliharaan Jembatan S.OKO-OKO I Bentang 9.8 m LS 0.35 12,500,000.00 4,433,928.57 4.2735 0.215 - 0.215 2.590 - 2.590 2,687,500.00
10.2.(4) Pemeliharaan Jembatan S.Oko-Oko II Bentang 8.9 m LS 0.35 10,000,000.00 3,547,142.86 3.4188 0.215 - 0.215 2.072 - 2.072 2,150,000.00
10.2.(5) Pemeliharaan Jembatan S.Oko-Ok0 III Bentang 20.8 m LS 0.35 25,000,000.00 8,867,857.14 8.5470 0.215 - 0.215 5.181 - 5.181 5,375,000.00
10.2.(6) Pemeliharaan Jembatan S.Oko-Oko IV Bentang 9.8 m LS 0.35 10,000,000.00 3,547,142.86 3.4188 0.215 - 0.215 2.072 - 2.072 2,150,000.00
10.2.(7) Pemeliharaan Jembatan S.Oko-Oko V Bentang 9.7 m LS 0.35 12,000,000.00 4,256,571.43 4.1026 0.215 - 0.215 2.487 - 2.487 2,580,000.00
10.2.(8) Pemeliharaan Jembatan S.Oko-Oko VI Bentang 6.8 m LS 0.35 9,000,000.00 3,192,428.57 3.0769 0.215 - 0.215 1.865 - 1.865 1,935,000.00
10.2.(9) Pemeliharaan Jembatan S.Lamedai I Bentang 8.9 m LS 0.35 11,500,000.00 4,079,214.29 3.9316 0.215 - 0.215 2.383 - 2.383 2,472,500.00
10.2.(10) Pemeliharaan Jembatan S.Lamedai II Bentang 8.9 m LS 0.35 11,500,000.00 4,079,214.29 3.9316 0.215 - 0.215 2.383 - 2.383 2,472,500.00
10.2.(11) Pemeliharaan Jembatan S.Box Tanggetada Bentang 6.9 m LS 0.35 6,000,000.00 2,128,285.71 2.0513 0.215 - 0.215 1.243 - 1.243 1,290,000.00
10.2.(12) Pemeliharaan Jembatan S.Tangketada Bentang 8.8 m LS 0.35 10,000,000.00 3,547,142.86 3.4188 0.215 - 0.215 2.072 - 2.072 2,150,000.00
10.2.(13) Pemeliharaan Jembatan S.Anaiwoi I Bentang 8.9 m LS 0.35 10,000,000.00 3,547,142.86 3.4188 0.215 - 0.215 2.072 - 2.072 2,150,000.00
10.2.(14) Pemeliharaan Jembatan S.Anaiwoi II Bentang 15.8 m LS 0.35 12,000,000.00 4,256,571.43 4.1026 0.215 - 0.215 2.487 - 2.487 2,580,000.00
10.2.(15) Pemeliharaan Jembatan S.Oneha I Bentang 10.3 m LS 0.35 10,000,000.00 3,547,142.86 3.4188 0.215 - 0.215 2.072 - 2.072 2,150,000.00
10.2.(16) Pemeliharaan Jembatan S.Oneha II Bentang 9.2 m LS 0.35 10,000,000.00 3,547,142.86 3.4188 0.215 - 0.215 2.072 - 2.072 2,150,000.00
10.2.(17) Pemeliharaan Jembatan S.Oneha III Bentang 8.7 m LS 0.35 10,000,000.00 3,547,142.86 3.4188 0.215 - 0.215 2.072 - 2.072 2,150,000.00
10.2.(18) Pemeliharaan Jembatan S.Oneha IV Bentang 12.8 m LS 0.35 13,000,000.00 4,611,285.71 4.4444 0.215 - 0.215 2.694 - 2.694 2,795,000.00
10.2.(19) Pemeliharaan Jembatan S.Oneha V Bentang 10.9 m LS 0.35 13,000,000.00 4,611,285.71 4.4444 0.215 - 0.215 2.694 - 2.694 2,795,000.00
10.2.(20) Pemeliharaan Jembatan S.Toengge Bentang 31.2 m LS 0.35 30,000,000.00 10,641,428.57 10.2564 0.215 - 0.215 6.217 - 6.217 6,450,000.00
10.2.(21) Pemeliharaan Jembatan S.Polewali Bentang 11 m LS 0.35 10,000,000.00 3,547,142.86 3.4188 0.215 - 0.215 2.072 - 2.072 2,150,000.00
10.2.(22) Pemeliharaan Jembatan S.Wolulu Bentang 30.3 m LS 0.35 30,000,000.00 10,641,428.57 10.2564 0.215 - 0.215 6.217 - 6.217 6,450,000.00
TOTAL 103,753,928.57 100.000 PROGRESS REALISASI 60.612 - 60.612 62,887,500.00
Pajak Pertambahan Nilai (Ppn) 11% 11,412,932.14 PROGRESS RENCANA 63.406 66.900 6,917,625.00
TOTAL 115,166,860.71 DEVIASI (2.793) - (6.288) 69,805,125.00
DIBULATKAN 115,166,000.00 - 69,805,000.00

Disetujui Diperiksa Disiapkan


Direksi PUPR Konsultan Supervisi Kontraktor
PPK 1.3 Provinsi Sulawesi Tenggara PT. TRIBINA MATRA CARYA CIPTA KSO PT. WINSOLUSI PT. LINCE ROMAULI RAYA - PT.
KONSULTAN - PT. ARISTA CIPTA AGUNG SARANA PERSADA (KSO)

SUKARDJO Ir. MUHAMMAD IDRIS RAZAK RISKY KURNIAWAN, ST


NIP. : 19750226 200312 1 002 Supervision Engineer Manager Proyek

16 / 16