Pembebanan
Balok sloof = 0,25.0,50.2400 = 108 kg/m'
Tembok = 1.250 = 250 kg/m'
q 358 kg/m'
Statika L = 3 m
Mtum = 1/8 x 358 x 3^2 = 402.75 kgm
bc = 450 = 1.8
250
Vu = 36.45 kN
Mu = 4.17 kNm
s tanah = 125.83 x 100 = 12583 kNm2
d = 300 - 30 = 270 mm
bo = 4 x (270 + 250) = 2080 mm
Statika
bc = 450 = 1.8
250
Vu = 36.45 kN
Mu = 4.17 kNm
s tanah = 125.83 x 100 = 12583 kNm2
d = 300 - 30 = 270 mm
bo = 4 x (270 + 250) = 2080 mm
Penulangan
Penulangan lapangan
Mu 398.45 kgm b 1000 mm
fc' (beton) 20.75 Mpa h 300 mm
fy' (baja) 420 Mpa d' 30 mm
Penulangan
mm2 mm
Lapangan X (tul atas) 900.00 D13 - 125 ( 1,062 mm2 ) M10
Tumpuan X (tul atas) 900.00 D13 - 125 ( 1,062 mm2 ) M10
Tumpuan X (tul bagi) 360.00 D8 - 150 ( 335 mm2 ) M5